2013-01-17 SCO Supplier Education Meeting

advertisement
SCO Supplier Education Meeting
Presented January 17, 2013 via webcast
1:15 PM EST – 4:00 PM EST
https://meetingplace1.nisource.com
Phone number: 888-481-1480
Phone number: 304-357-4000 (Outside USA)
Meeting ID Number for call and webcast: 4996
Introduction and Background
Meeting Agenda
•
Introduction and Background – Tom Brown
•
Modifications to Existing Program – Tom Heckathorn
•
SCO Auction Process – Tom Heckathorn
•
Delivery Obligation - Demand and Supply Curves – Mike Ripley
•
Capacity Portfolio and Required Assignment – Mike Ripley
•
Ohio Production / City Gate Supply – Mike Ripley
•
Annual Cash Out / Reconciliation – Tom Heckathorn
•
Statewide Btu Value – Tom Heckathorn
•
CHOICE / SCO Supplier Payments – Tom Heckathorn
•
CHOICE / SCO Customer Eligibility – Tom Heckathorn
•
CHOICE / SCO Customer Billing – Tom Heckathorn
•
CHOICE / SCO Reconciliation Rider – Tom Heckathorn
•
Billing Enhancements – Tom Heckathorn
•
Website information – Tom Heckathorn
•
Contact Information – Tom Heckathorn
•
Question and Answer Period
2
Introduction and Background
Columbia SSO/SCO Auctions
•
Current settlement extends through March 31, 2013
•
Included two SSO Auctions and one SCO Auction
•
First SSO Auction for April 1, 2010 through March 31, 2011
– Seven suppliers awarded a total of 17 tranches
– Retail Price Adjustment of $1.93 added to NYMEX final settlement price each month
•
Second SSO Auction for April 1, 2011 through March 31, 2012
– Seven suppliers awarded a total of 16 tranches
– Retail Price Adjustment of $1.88 added to NYMEX final settlement price each month
•
First SCO Auction for April 1, 2012 through March 31, 2013
– Five suppliers awarded a total of 16 tranches
– Retail Price Adjustment of $1.53 added to NYMEX final settlement price each month
3
Modifications to Existing Program
Stipulation
•
Filed with the Commission on October 4, 2012 and amended November 27, 2012
•
Provides for extension of existing program through March 31, 2018 with the
following modifications:
– Additional cash deposit by the SCO Suppliers of 6 cents per Mcf multiplied by the
initial estimated annual delivery requirements due on March 1, 2013
– Balancing fee modified to $0.27 per Mcf and charged directly to customers – After
4/1/13, no CHOICE Supplier may charge retail CHOICE Customers a rate that is
designed or intended to provide compensation for the balancing fee that
Columbia charged Suppliers prior to 4/1/13.
– Adjustment to assigned capacity levels. Suppliers assigned capacity (including
peaking) up to 100% of the design peak day requirements of their customers
– Peaking contract to be terminated and North Coast capacity reduced. Remaining
North Coast capacity will be retained by Columbia as part of its peaking service.
– Columbia Gulf capacity reduced to 75% of current level effective April 1, 2016.
– Columbia will provide weather forecasts in the afternoon for the current day in order to
provide additional information to the Suppliers for scheduling purposes
– Modifications to off system sales and capacity release sharing mechanism
4
Modifications to Existing Program
Stipulation
•
Modifications continued:
– Exit the merchant function provisions discussed later in the presentation – will not have an impact
on the 2013-2014 program year
– Billing enhancements for April 2013
• Suppliers may bill their Choice Customers a flat fee each month covering the Supplier’s gas
costs for the month
• Rate ready billing codes increase to 100 per Supplier
• Suppliers may bill a rate based upon monthly NYMEX prices, plus or minus a value
• Supplier may increase the size of its logo and have it placed in the top margin on the front
page of the bill. There is a competitively neutral fee to Suppliers for this service and the
revenue is credited to the CSRR.
• Rates can be submitted daily to be effective with the Choice Customer’s next billing cycle
• Contract portability for those Choice Customers changing their address. Not applicable to
Governmental Aggregation customers.
– Billing enhancements to be completed by April 2017 discussed later in the presentation
•
The current forecast of total SCO Customer demand (including DSS) is 87 Bcf / year for an average of
5.4 Bcf / year per tranche. Security requirement will be $2.4 million per tranche.
•
World Energy will conduct the auction on Tuesday, February 26, 2013 at 9:00 AM EST
•
Documents are available on the Website www.columbiasuppliers.com
5
Exit the Merchant Function Provisions
Columbia will exit the merchant function under certain conditions
•
Survey will be conducted to determine educational needs of CHOICE-Eligible C&I Customers
•
If C&I CHOICE participation meets or exceeds 70% for three consecutive months by August 1 of any year,
Columbia will exit the merchant function for C&I Customers effective the following April 1
•
Columbia may file an application to exit the merchant function for residential customers provided the following
has occurred:
– At least one month has passed where CHOICE participation for residential customers has met or
exceeded 70% for three consecutive months
– At least 22 months have passed since Columbia has exited the merchant function for C&I Customers
– The exit will become effective the following April provided approval of the application is received by
November 1
•
Upon exit for any class of Customers, CHOICE-Eligible Customers in that class who have not elected a
CHOICE Supplier will be assigned to participating MVR Suppliers. Method of allocation will be as described in
the PUCO order.
6
Comparison
2012-2013
2013-2014*
70,685
66,056
5,151,000
5,429,500
3.23%
2.91%
Local Gas Fixed Purchase Price Adder
$3.1420
$4.0720
Peaking Service as a Percent of Peak Day Demand
27.95%
28.63%
3.40%
1.05%
$4,852,245
$4,524,336
1.0290
TBD
Security required per tranche
$2,900,000
$2,400,000
Default Fee per Tranche due March 1, 2013
$2,575,500
$2,714,750
$0
$325,770
Estimate of Tranche Size
Daily Dth
Annual Mcf
Local Gas Adjustment as Percent of Demand Curve
Percent of Demand provided by Supplier Capacity
Annual Demand Cost of Capacity per Tranche
Annual BTU
Cash Deposit of $0.06 due March 1, 2013
*Subject to change
7
Modifications to Existing Program
These first few slides were intended to highlight the modifications
made to the existing CHOICE and SCO programs for the 2013-2014
Program Year. A more complete presentation begins with the next
slide. Those Suppliers already familiar with these programs may
choose to forego the remainder of the presentation.
We will stop the presentation for a few minutes to allow Suppliers
to raise any questions they may have and drop off the call if they
do not wish to continue with the full presentation.
8
SCO Auction Process
The Nature of the SCO Arrangement
•
Winning Standard CHOICE Offer (“SCO”) Suppliers will be allocated CHOICE eligible customers (not
already with a CHOICE Supplier) as well as a pro rata share of the total estimated Default Sales Service
(“DSS”) demand based on the number of tranches supplied by each SCO Supplier. DSS includes transition
customers, those customers not eligible to participate in the CHOICE program or a Governmental
Aggregation Program, and PIPP customers.
•
Columbia will use its best efforts to establish relatively equivalent tranches allocated based on revenue
class, annual demand, PSP and credit rating. Since the peak day quantities for each tranche by PSP will be
based on the assigned customer demand, the capacity allocation will vary to a certain extent.
•
Monthly allocation of newly eligible SCO customers to SCO Suppliers will be done by random assignment
by PSP, based on the number of tranches supplied by each SCO Supplier.
•
The purpose of the auction is to secure firm supply for those customers falling under the SCO
•
Columbia will release Firm Transportation and Firm Storage upstream pipeline capacity to SCO Suppliers
for their use
•
Firm gas supply will be delivered by SCO Suppliers every day to the Columbia city gates, and will be
nominated on Aviator, Columbia’s on-system scheduling website
9
SCO Auction Process
The Nature of the SCO Arrangement (Continued)
•
The daily delivery volumes will be determined via Demand and Supply Curves provided by
Columbia each month
•
SCO Suppliers will be credited with and pay for volumes received under the peaking service
that Columbia provides, using pipeline transportation and storage contracts that it retains, under
the annual true-up mechanism
•
Each month, Columbia will pay SCO Suppliers the SCO Price for gas consumed by SCO
Customers assigned to that Supplier as well as a pro rata share of the DSS consumption in that
billing cycle less costs for local gas purchase requirement, etc.
•
A true up mechanism is used to balance the volumes paid for by Columbia with the annual
volumes delivered by the SCO Suppliers including the local gas purchase requirement.
•
The SCO Supplier’s name and phone number will appear on the Customer’s invoice.
•
Suppliers must agree to sell and assign to Columbia the SCO accounts receivable and
all related security and collections with respect to the receivables and will grant to
Columbia a first priority security interest in all of SCO Supplier’s right, title and interest
in and to all SCO accounts receivable. This does not apply to the DSS volumes.
10
SCO Auction Process
Enrollment and Data Files
•
Upon completion of the allocation process, SCO Suppliers will be provided with specific
customer information including, but not limited to, customer name, account number,
billed usage, billed charges, enrollments and drops.
•
All SCO Suppliers must utilize Columbia’s internet-based website in order to receive
file transactions for customer billing and enrollment information.
11
SCO Auction Process
Timing of SCO Auction (Program Outline Section 8)
•
Please refer to the Timeline for the 2013 SCO Auction for important dates and
deadlines.
•
In mid-March, the capacity allocation process for April 2013 business will take place
•
SCO gas supply will begin flowing to Columbia’s city gates on April 1, 2013 and
continue for the twelve month period ending March 31, 2014
12
SCO Auction Process
SCO Auction Process (Program Outline Section 9)
•
For bidding purposes, Columbia’s SCO supply requirements will be divided into 16
“tranches” of demand
– At the outset, each tranche will contain comparable volumetric demand, released
capacity and delivery location requirements
– The current forecast of total SCO Customer demand (including DSS) is 87 Bcf /
year for an average of 5.4 Bcf / year per tranche. This is subject to change.
– A bidder may choose to bid on up to 4 tranches
– Bidders that are affiliated with each other or have part ownership in other bidders
will collectively be limited to bidding on 4 tranches in total
13
SCO Auction Process
SCO Auction Process (Continued)
•
World Energy will perform as the outside auctioneer for this SCO Auction
•
Bidding will occur over the internet using World Energy’s web based auction system
•
A “descending clock” or “descending price” approach will be used
– A pre-established price will be used for bidding in the initial round
– The price being bid represents the “Retail Price Adjustment” or “RPA”, which will
be added to the NYMEX final settlement price each month to determine the
monthly SCO Price
– During the bidding rounds, bidders will bid the number of tranches they would like
to serve at the price announced by the auctioneer
– A report period will follow each bid round
– Assuming that more than sixteen tranches in total are bid in round one, the
process will move on to round two, with a new, lower price announced by the
auctioneer
14
SCO Auction Process
SCO Auction Process (Continued)
– A bidder may reduce the number of tranches that they bid from one round to the
next, but are not allowed to increase the number of tranches bid from one round
to the next
– The process continues, with each round opening at a lower price until exactly 16
tranches are bid, in which case, the auction is over
– If less than 16 tranches are bid in a round
• The auction bid price will move back to the last price at which more than 16
tranches were bid less one cent
• Rounds will continue with only one cent decrements in the price in each
round, until exactly 16 tranches are bid
• If fewer than 16 tranches are bid in a round during this phase of the auction,
then the immediately prior round, with bids in excess of 16, will be considered
the final round
– Because there will be more than 16 tranches awarded in this case, the size of
each tranche will be reduced accordingly
15
SCO Auction Process
SCO Auction Process (Continued)
• Bidders will not see bids submitted by others
• Neither the number of bids or the number of tranches bid will be revealed
during the auction rounds
• All bids submitted throughout the process are binding
• Following the auction, the Staff of the Public Utilities Commission of Ohio
(PUCO) will submit the results of the Auction to the Commission for its
approval
• Names of successful bidders shall be kept confidential until authorized by the
PUCO to be made public
16
SCO Auction Process
SCO Gas Price (Program Outline Section 10)
•
The SCO Price will be the final NYMEX settlement price for each month plus the RPA resulting
from the auction
– For example,
• If the NYMEX final settlement price is $3.524 per Dth, and
• And the RPA is $1.88, then
• The SCO Price to be paid will be $5.404 per Mcf
• SCO Customers will receive a billing cycle invoice based on an SCO Price of $0.5404
per Ccf
– Note that part of the role of the RPA is to convert the NYMEX Dth price to an Mcf price and
ultimately, to a Ccf price on the SCO Customer bills. This includes the impact of
Columbia’s LAUF.
– An SCO Supplier’s payment from Columbia will be based on multiplying the SCO Price by
the consumption of the customers allocated to the SCO Supplier plus the SCO Supplier’s
pro rata share of the total volume consumed by the DSS Customers in that billing cycle
17
SCO Auction Process
SCO Supplier Qualifications (Program Outline Section 12)
•
Potential bidders must be certified by the PUCO in order to supply competitive retail natural gas service in the
State of Ohio. This can be a lengthy process. Please refer to the PUCO website for pertinent information.
•
Potential bidders must submit a completed Retail Natural Gas Suppliers Registration Application to Columbia by the
deadline set forth in the timeline, that includes
– Company and contact information
– Financial information for credit review and $50 credit evaluation fee
– Executed confidentiality agreement related to the Credit Process
•
Applicant must submit a completed Bidder Registration Form to Columbia by the deadline set forth in the timeline, that
includes
– Designation of the number of tranches on which the applicant wishes to be able to bid
– Required financial security
– Various certifications and acknowledgements as detailed in the Bidder Registration form
• Acknowledge receipt of auction rules and procedures and agree to abide by those rules
• Acknowledge receipt of forecasted supply requirement data
• Certify whether bidder has any affiliate companies also bidding
• Acknowledge that if determined to be one of the winning bidders, the applicant will sign the SCO Supplier
Agreement
• Applicant must be certified at this time and provide its certification number.
18
SCO Auction Process
SCO Supplier Information and Education (Program Outline Section 13)
•
Documents are available on website www.columbiasuppliers.com under Columbia Gas of Ohio
Auctions: April 2013 – March 2014 (SCO)
•
Additional documents will be posted as they become available
•
This presentation will also be posted on the website
•
On-line Auction Preview / Trial Auction with World Energy held on the date set forth in the timeline
19
SCO Auction Process
SCO Supplier Agreement (Program Outline Section 14)
•
The SCO Supplier Agreement has been posted on the website
•
The Agreement must be signed by a winning bidder and provided to Columbia within
one week of the approval of the RPA by the Commission
•
$250 set up fee required for each new supplier
•
The SCO Supplier agrees to sell and assign to Columbia the SCO accounts
receivable and all related security and collections with respect to the receivables and
will grant to Columbia a first priority security interest in all of SCO Supplier’s right, title
and interest in and to all SCO accounts receivable. This does not apply to the DSS
volumes.
•
The SCO Supplier must be CRNGS certified by the PUCO and maintain that
certification during the period in which the SCO Supplier serves in that capacity.
20
SCO Auction Process
SCO Supplier Security Requirements (Program Outline Section 15)
•
Through the Application process, potential bidders will provide financial data to Columbia for
purposes of determining if, and to what extent, Columbia will extend unsecured credit
•
Columbia will then notify the applicant of any unsecured credit being extended
•
In the Bidder Registration process, potential bidders will compare the initial financial security
requirement per tranche, times the number of tranches they select to bid on, with any
unsecured credit level communicated to them by Columbia, to determine the level, if any, of
financial security to provide to Columbia at that time
•
The initial security requirements per tranche shall include:
– the cost of three months of released capacity demand charges
– an amount representing an average month’s incremental gas cost exposure
– the sum of the exposures above multiplied by 150% to account for the additional volumes
that could be assigned to the SCO Supplier in the case of another supplier’s default
– Based on current tranche size and currently effective pipeline demand rates, that amount
will be $2.4 Million per tranche. This security requirement is subject to change.
21
SCO Auction Process
SCO Supplier Security Requirements (Continued)
•
Security must be pre-approved for form and content by Columbia and may include cash, letter
of credit, or parent guaranty from approved credit support providers
•
If a bidder becomes an SCO Supplier, ongoing credit evaluations may be conducted from time
to time by Columbia to determine if the level of security provided is appropriate
•
Letter of Credit and Deposit for SCO Suppliers
– In addition to any security required by the process described above, by March 1, 2013,
successful bidders will provide a letter of credit to Columbia in an amount equal to fifty
cents per Mcf times the forecasted annual supply requirements for those tranches won by
each bidder. In the event of default by a Supplier, any money Columbia is able to collect
under the letter of credit with the defaulting Supplier will be allocated to replacement
Suppliers on a pro rata basis.
– Suppliers shall also provide to Columbia by March 1, 2013 a cash deposit of six cents per
Mcf multiplied by the forecasted annual supply requirements for those tranches won by
each bidder. This will be used to meet supply default expenses incurred by Columbia and
unused funds will be transferred to the CSRR at the end of the respective program year.
22
SCO Auction Process
CHOICE/SCO Supplier Failure to Perform (Program Section 16)
•
In the event of an SCO or CHOICE Supplier default
– If not cured by defaulting Supplier within five days, Supplier will be terminated from further
activity within the CHOICE and SCO programs
– Columbia will recall the released capacity and insure continuity of service to customers in
the short term
•
Customer quantities that are not served due to a Supplier default will be allocated to remaining
SCO Suppliers, in concert with the monthly development of demand curves, in the next
available monthly cycle.
– Non-defaulting SCO Suppliers will receive their pro rata share of the SCO customers by
random assignment, by PSP, and a pro rata share of the estimated DSS demand, by PSP,
based on the number of tranches served by the non-defaulting SCO Supplier
– Such allocations to SCO Suppliers will be capped at 150% of each SCO Supplier’s initial
annual delivery requirement measured as of April 1, 2013
– Columbia will assume supply responsibility for any unallocated requirements that result
from implementation of the 150% limit
23
Terms and Definitions
Terms used herein
•
Pipeline Scheduling Point (PSP) – a single delivery point or set of delivery points grouped or
designated by an upstream pipeline for purposes of scheduling gas supplies for delivery by
such upstream pipeline
•
Demand Curve – an estimate of CHOICE or SCO customer demand provided monthly by
Columbia. Establishes the CHOICE/SCO Supplier’s supply delivery obligation to Columbia
by PSP
•
Supply Curve – establishes: a) the requirement for supplies at non-TCO PODs or b) supply
requirements of an upstream pipeline at an upstream POD with another pipeline
24
System Map
Sandusky PSP
Parma PSP
Maumee
New Castle
PSP
Toledo PSP
Alliance PSP
Dungannon
Lima PSP
Ohio Misc PSP
Ohio Valley
PSP
Columbus PSP
Dayton PSP
Mansfield PSP
Portsmouth PSP
25
Delivery Obligation – Demand and Supply Curves
1.
Demand Curves (Program Outline Section 27)
a.
b.
Specify the total delivery obligation for each PSP. Developed based on the most recent 12
months normalized demand of participating customers
•
CHOICE Demand Curves developed based on actual customers of the CHOICE Suppliers
•
SCO Demand Curves developed based on actual customers allocated to the SCO
Suppliers plus a pro rata share of the DSS customers, based on the number of awarded
tranches.
•
Each SCO Supplier will receive a Demand Curve for each PSP and each CHOICE Supplier
will receive a Demand Curve for each PSP in which they have customers.
•
Should a Supplier be both a CHOICE Supplier and an SCO Supplier, the demand curves
and supply curves will be combined into a single curve with nomination groups by PSP.
Define the total confirmed supply that a Supplier must deliver to Columbia each day by PSP
•
For the months of October through April, the delivery requirements change with
temperature. The confirmed deliveries must match the curve specified quantity at the actual
temperature posted on Aviator at the end of the day for each PSP. The forecasted
temperature may be used as a guideline.
•
For the months of May though September, the Demand Curves specify a constant volume
each day of the month. Thus, there is no matching to actual temperatures required.
26
Delivery Obligation – Demand and Supply Curves
Demand Curves (Continued)
c.
d.
e.
f.
Demand Curves are Updated Monthly
Demand Curve Adjustment for Balancing
• Daily delivery requirements for the months of October and November are reduced to
facilitate balancing of demand uncertainty
• Projected under delivered quantities for October and November are delivered to COH in the
months of May through August
Failure to deliver confirmed volumes equal to Demand Curve specified requirements will result in
the assessment of a Noncompliance Charge on the difference between the confirmed volume and
required deliveries
• Non OFO/OMO days = higher of $10/Dth or 150% of the TCO Daily Index
• OFO/OMO days = higher of $30/Dth or 150% of the TCO Daily Index
• Applicable pipeline penalties are additive
Beginning in April 2013, Columbia will provide weather forecasts in the afternoon for the current
day in order to provide additional information to the Suppliers for scheduling purposes.
27
Delivery Obligation – Demand Curve Example
28
Delivery Obligation – Demand and Supply Curves
2.
Supply Curves (Program Outline Section 27)
a.
b.
c.
d.
Establishes the delivery obligations/limitations at non-TCO PODs. Developed based
on the operational requirements and/or ability of non-TCO PODs to accept supplies.
Supply Curves will be provided for deliveries from PEPL to Columbia at Maumee and
from Tennessee to TCO at Dungannon and only apply to the PSPs in which the POD
is located. Suppliers will only receive a Supply Curve if they have a delivery obligation
in the PSP where the Supply Curve POD is located. Should a Supplier be both a
CHOICE Supplier and an SCO Supplier, the supply curves will be combined into a
single curve for each location.
Each SCO Supplier will receive a copy of each Supply Curve. Each CHOICE Supplier
will receive a Supply Curve for each PSP in which they have customers.
Supply Curve delivery requirements will be determined based on the Forecasted
Temperature for the PSP in which the Supply Curve POD is located
• The use of Forecasted Temperatures is necessary because Columbia does not
have no-notice capacity similar to TCO FSS/SST that can be assigned to
Suppliers
29
Delivery Obligation – Demand and Supply Curves
Supply Curves (Continued)
e.
Volumes scheduled into Columbia pursuant to a Supply Curve can be allocated to
CHOICE/SCO requirements, TS customers, sold to another supplier, or a combination
•
•
•
f.
g.
If a CHOICE/SCO Supplier is also a TS customer supplier, it may allocate Supply Curve
deliveries to a TS customer or pool
All daily Supply Curve volumes allocated to CHOICE/SCO will be part of the Supplier’s daily
Demand Curve Requirements for the PSP in which the Supply Curve is located
Supply Curve required deliveries cannot be assigned to another party except for those
situations when the CHOICE/SCO Supplier has named an alternate Supplier as its agent for
purposes of meeting the Supply Curve delivery requirements
Columbia may request intra-day changes to these nominations if it experiences
sufficient differences between forecasted and actual temperatures to risk operational
problems
Maumee Gate Supply Curve: delivery volume to Maumee must match the curve
•
•
•
•
Deliveries from PEPL to Columbia at the Maumee Gate are required operationally during
the winter months
Confirmed deliveries at the Maumee Gate are required to match the Supply Curve
requirements at the Forecasted Temperature
Assigned PEPL capacity in total will be equal to the maximum (plateau) delivery
requirement for the Maumee Gate
No Maumee Gate deliveries are allowed during the summer months
30
Delivery Obligation – Demand and Supply Curves
Supply Curves (Continued)
h.
Dungannon Supply Curves: minimum required volume
• Deliveries from Tennessee to TCO at Dungannon are required operationally at
colder temperatures for TCO to meet city gate obligations downstream of
Dungannon in the Alliance PSP. Deliveries at Dungannon are not applied
directly to any Demand Curve as they must be scheduled on TCO for delivery to
Columbia.
• Deliveries from Tennessee to TCO are required beginning at Forecasted
Temperatures of approximately 42°F
• There are limited secondary delivery rights on the Tennessee contract containing
Dungannon as the primary POD
i.
There are no longer Supply Curves associated with North Coast. Columbia will retain
this capacity to be used for operational/peaking services.
j.
Failure to deliver volumes as specified shall result in the assessment of the same
Noncompliance charges that apply to demand curves.
31
Capacity Portfolio and Required Assignment
Columbia Gas of Ohio, Inc.
Pipeline and Ohio Production Contracts
City Gate
Columbia Transmission
Panhandle Eastern
Rate
Schedule
FSS-MDQ
FSS-SCQ
SST
FTS
PSP
All
All
6&9
15
All but 15 and 4
4
FS-MDQ
FS-SCQ
EFT
EFT
EFT
1
N/A
All
Upstream
Columbia Gulf Transmission
FTS-1
Point of Delivery
TCO-Leach, KY
Tennessee Gas Pipeline
FT-A
Ohio Production
Trunkline
FT
1
1
1
Demand
Upstream
Rate*
Pipeline
Notes:
$ 1.5090
N/A
$ 0.0289
N/A
$ 5.9230
TCO FSS
$ 3.9630
Columbia Gulf
$ 6.0930 Tennessee (Broad Run)
$ 6.0930
Columbia Gulf
$ 6.0930 Tennessee (Dungannon)
$2.9700
$0.0354
$3.9000
$13.4300
$0.0879
N/A
N/A
PEPL FS
N/A
Trunkline
N/A
Retained by Columbia and used with Peaking Service
Receipt Point
Rayne, LA
$4.2917
TCO-Broad Run, KY $5.7798
TCO-Dungannon, OH $8.7610
PEPL-Bourbon, IN
Daily rate
500 Leg Pool
500 Leg Pool
$0.1320
Patterson-ANR
*All rates are subject to change
32
Agreement/amendment pending
Agreement/amendment pending
Daily rate
Capacity Portfolio and Required Assignment
Capacity Allocation Process (Program Outline Section 19)
1.
Capacity Allocated/Assigned on “Level Playing Field” Basis
– Equal percentage levels of storage and FTS assigned to each PSP and equal
percentage level of Columbia provided Peaking Service provided in each PSP
– Percentages are identical for CHOICE and SCO
2.
Capacity Assignment based on Columbia’s peak day demand
– The initial capacity assignment will be made effective April 1, 2013 and will be
refreshed monthly, i.e. capacity will be released for one month at a time
– Releases of TCO capacity will be made by contract with releases to multiple PSPs
performed in single release whenever possible
– Suppliers may re-release the capacity assigned by Columbia subject to recall by
Columbia. Releases of assigned PEPL capacity does not entitle any third party
access to Columbia’s distribution system unless such third party has specifically been
named as an agent for the releasing Supplier for purposes of meeting that Supplier’s
Supply Curve requirements
– A re-release of TGP capacity does not alter the Supplier’s responsibility to abide by
the delivery requirements of its Dungannon Supply Curve
– All costs associated with the released capacity will be paid directly to the pipelines by
the CHOICE/SSO Suppliers pursuant to applicable pipelines’ capacity release
payment procedures
33
Capacity Portfolio and Required Assignment
Capacity Allocation Process (Continued)
–
3.
4.
5.
Columbia holds certain discounted contracts on PEPL, TRK and Tennessee where
the utilization of unauthorized alternate points may cause Columbia to incur significant
additional costs. Any incremental costs incurred by Columbia as a result of a Supplier
or another party to which a Supplier has released the Columbia assigned capacity
utilizing an unauthorized alternate point shall be paid by the Supplier. See tariff for full
details.
Columbia will assign (including peaking services) up to 100% of the design peak day
requirements of the Supplier’s customers.
– Columbia will retain TCO FSS/SST to provide Standby Service to TS customers that
sign up for the service
– Columbia shall retain 11,500 Dth of TCO FTS capacity for release/assignment to TS
customers
If an SCO Supplier is also a CHOICE Supplier, the demand curves, supply curves and the
capacity release transactions will be combined where applicable.
The North Coast capacity will be reduced effective November 1, 2013 and be retained by
Columbia as part of the peaking service.
34
Capacity Portfolio and Required Assignment
Capacity Allocation Process (Continued)
6.
Allocation steps followed by Columbia in determining the amount of assets to be assigned by PSP are
as follows:
i.
Overall percentage of capacity Columbia shall assign including the peaking service will be up to
100% of Supplier’s peak day demand. For the 2013-2014 winter, Columbia assigned capacity will
equate to approximately 99% of the Supplier’s peak day demand. Supplier will be required to
deliver approximately 1% of its own capacity before peaking service is available.
ii. Columbia will retain capacity equivalent to approximately 22% of peak day demand to provide
Non-Temperature Balancing Services for CHOICE and SCO Suppliers
iii. Columbia will assign approximately 53% of the peak day demand as storage.
• For the PSP that includes the Maumee Gate the percentage of storage assignment shall
include PEPL FS and TCO FSS.
iv. Columbia will assign approximately 17% of the peak day demand as FTS
• PEPL FTS will be included in the FTS assigned to the Toledo PSP
• For the Alliance and Portsmouth PSPs, the TCO FTS assignment shall include Tennessee
FT-A as the upstream pipeline
• All other TCO FTS assigned shall also have Columbia Gulf FTS-1 assigned as the upstream
pipeline
v.
Capacity that is not able to be assigned under this methodology will be retained by Columbia as
Operationally Retained Capacity and be used in providing its Peaking Service
vi. Total capacity utilized by Columbia to provide peaking is approximately 29% of peak day demand
35
Capacity Allocation Example for One SCO Tranche
Tranche Example November through March
TCO FSS
MDQ
3045
1,445,102
53.04%
Used for
Allocation
22 PORTSMOUTH
23-1 TOLEDO
23-3 LIMA
23-4 ALLIANCE
23-5 COLUMBUS
23-6 DAYTON
23-8 MANSFIELD
23-9 OHIO MISC
23N-2 PARMA
23N-7 SANDUSKY
24-35 PITTSBURGH
24-39 NEWCASTLE
TOTAL
Monthly Demand Chrg
Monthly Demand
858
9,434
2,595
2,064
21,822
9,281
3,912
4,049
6,606
3,296
2,108
31
66,056
PEPL FS
MDQ
18601
26,667
22 PORTSMOUTH
23-1 TOLEDO
23-3 LIMA
23-4 ALLIANCE
23-5 COLUMBUS
23-6 DAYTON
23-8 MANSFIELD
23-9 OHIO MISC
23N-2 PARMA
23N-7 SANDUSKY
24-35 PITTSBURGH
24-39 NEWCASTLE
TOTAL
Monthly Demand Chrg
Monthly Demand
455
4,720
1,376
1,095
11,575
4,923
2,075
2,148
3,504
1,748
1,118
16
34,754
$1.5090
$52,444
PEPL FS
SCQ
18601
2,000,000
TCO FSS
SCQ
3045
80,441,913
25,334
262,746
76,622
60,943
644,331
274,037
115,508
119,554
195,053
97,320
62,242
915
1,934,605
$0.0289
$55,910
PEPL
EFT-Stor
Nov-Mar
18606
26,338
TCO SST
Oct-Mar
3044
1,445,102
455
4,720
1,376
1,095
11,575
4,923
2,075
2,148
3,504
1,748
1,118
16
34,754
$5.9230
$205,850
PEPL
EFT-Stor
Apr-Oct
18606
10,244
TCO SST
Apr-Sept
3044
722,551
CGT
FTS-1
80061
273,629
228
2,360
688
547
5,788
2,461
1,038
1,074
1,752
874
559
8
17,377
$0.0000
$0
0
490
450
0
3,788
1,611
679
703
1,147
572
366
5
9,811
$4.2917
$42,106
Trunkline
FT
Nov-Mar
18122
29,223
PEPL
EFT
18605
15,000
TCO
FTS
Percentage
0.00%
5.16%
17.27%
0.00%
17.27%
17.27%
17.27%
17.27%
17.27%
17.27%
17.27%
17.27%
0
487
448
0
3,769
291
676
88
1,141
569
364
5
7,838
$6.0930
$47,757
PEPL
EFT
Nov-Mar
18604
28,662
288
21,600
284
110
393
765
750
288
$2.9700
$855
21,600
$0.0354
$765
284
$3.9000
$1,108
110
$0.0000
$0
393
$13.4300
$5,278
765
$3.9600
$3,029
750
$2.6370
$1,978
36
TCO
FTS
80152
238,186
TCO
FTS
85154
45,538
17.27%
Tenn
FT-A
46986
40,000
TCO
FTS
82544
38,974
17.27%
152
Tenn
FT-A
63440
30,000
TCO
FTS
82545
29,231
17.27%
148
366
357
366
$8.7610
$3,207
357
$6.0930
$2,175
1,312
611
1,923
$3.9630
$7,621
152
$5.7798
$879
148
$6.0930
$902
Capacity Allocation Example for One SCO Tranche
Total
Demand
22 PORTSMOUTH
23-1 TOLEDO
23-3 LIMA
23-4 ALLIANCE
23-5 COLUMBUS
23-6 DAYTON
23-8 MANSFIELD
23-9 OHIO MISC
23N-2 PARMA
23N-7 SANDUSKY
24-35 PITTSBURGH
24-39 NEWCASTLE
TOTAL
858
9,434
2,595
2,064
21,822
9,281
3,912
4,049
6,606
3,296
2,108
31
66,056
Total
Storage
City Gate
455
5,004
1,376
1,095
11,575
4,923
2,075
2,148
3,504
1,748
1,118
16
35,038
53.04%
Total
Transport
City Gate
148
1,630
448
357
3,769
1,603
676
699
1,141
569
364
5
11,409
17.27%
Total
Released
Local
603
6,634
1,824
1,452
15,344
6,526
2,751
2,847
4,645
2,317
1,482
21
46,447
70.32%
14
150
41
33
347
148
62
64
105
52
34
0
1,050
1.59%
37
Retained
42
464
128
102
1074
457
193
199
325
162
104
2
3,252
4.92%
Peaking
190
2,087
574
457
4,827
2,053
865
896
1,461
729
466
7
14,612
22.12%
Local+Pk
by COH
246
2,701
743
592
6,248
2,658
1,120
1,159
1,891
943
604
9
18,914
28.63%
Total
COH
849
9,335
2,567
2,044
21,592
9,184
3,871
4,006
6,536
3,260
2,086
30
65,361
98.95%
Prov by
Supplier
9
99
28
20
230
97
41
43
70
36
22
1
695
1.05%
Capacity Portfolio and Required Assignment
System Balancing (Program Outline Section 23)
1.
Columbia shall retain approximately 22% of the peak day demand to provide System Balancing
– Majority of retained storage will be TCO FSS/SST to balance differences between deliveries by
Suppliers (Demand Curve requirements) with the actual demand of the CHOICE/SCO
customers
– Small portion of retained storage will be PEPL FS/EFT to balance the Maumee Gate
2.
Per the Stipulation, CHOICE/SCO Suppliers will no longer pay the $0.32 per Mcf Balancing Charge.
Rather, the customers will be charged a reduced Balancing Charge of $0.27 per Mcf.
– All costs incurred by Columbia to provide balancing, along with all balancing revenue received
by Columbia, will be charged/credited to the CHOICE/SCO Reconciliation Rider (CSRR)
– After 4/1/13, no CHOICE Supplier may charge retail CHOICE Customers a rate that is
designed or intended to provide compensation for the balancing fee that Columbia
charged Suppliers prior to 4/1/13.
3.
Columbia shall utilize the retained storage assets to provide CHOICE/SCO balancing and to provide
its non-firm Banking and Balancing Service for its TS Customers
– The daily balancing component of the non-firm Banking and Balancing Service will be reduced
or interrupted when the retained assets are required to provide CHOICE/SCO balancing and/or
peaking services
– All Banking and Balancing fees collected by Columbia will be credited to the CSRR
38
Capacity Portfolio and Required Assignment
Storage Management (Program Outline Section 26)
Any 2012 SCO Supplier not continuing, or continuing but with a fewer number of tranches,
as a Supplier for the 2013 SCO Period must offer for sale to the succeeding SCO
Supplier(s) (and the replacement SCO Supplier must purchase) an amount of storage
inventory equal to 2% of the SCQ initially assigned per tranche for the 2013 SSO Period.
The sale in April 2013 shall be completed using the same index based price formula as
was used for the April 1, 2012 sale.
39
Capacity Portfolio and Required Assignment
Storage Management (Program Outline Section 26)
a.
b.
c.
d.
Based on Columbia’s historical planning practices the following minimum storage inventory levels
are recommended:
Nov. 1
98%
Feb. 15
30%
Mar. 5
20%
Mar. 22
10%
Apr. 1
2%
Outside the SCO Supplier’s storage inventory purchase requirement stated earlier, all CHOICE
and SCO Suppliers have the sole responsibility to fill and manage the storage inventories of the
TCO FSS and PEPL FS capacity assigned to them on a monthly basis
For the months of October through April, CHOICE/SCO Suppliers shall manage natural gas
supply nominations and deliveries to Columbia to match deliveries as specified by their individual
Demand Curves at the actual temperatures posted by Columbia through utilization of TCO FSS
and SST capacity. Such utilization shall generally consist of adjustments to their FSS/SST
nomination at the end of the gas day such that all confirmed supplies delivered to Columbia
(including the FSS/SST nomination adjustment) in each PSP match the specified Demand Curve
volumes at the actual temperature as posted by Columbia.
Each CHOICE and SCO Supplier is solely responsible for ensuring that they have adequate
injection and/or withdrawal rights to match their Demand Curve obligations
40
Ohio Production / City Gate Supply
Ohio Production (Program Outline Section 25)
1.
Columbia purchases certain Ohio gas production in small quantities or to satisfy location-specific
customer supply requirements that cannot be served via other means
2.
By their nature and/or contractual limitations, these supplies do not lend themselves to assignment to
multiple Suppliers
3.
The peak day and seasonal supplies associated with Columbia’s purchases of Ohio Production will be
utilized to benefit all CHOICE and SSO Suppliers equally
a. Columbia will utilize these Ohio Production volumes as a component of its Peaking Service
b. Impact of seasonal/annual supplies discussed under Local Gas Purchase Adjustment
City Gate Supply
1.
Columbia serves the majority of its needs for the city of Brewster under a firm city gate supply
arrangement. The minimal size of this requirement does not lend itself to allocation to multiple
CHOICE/SSO Suppliers.
a. Columbia will utilize these purchases for Brewster as a component of its Peaking Service
b. Impact of seasonal/annual supplies discussed under Local Gas Purchase Adjustment
41
Ohio Production / City Gate Supply
Local Gas Purchase Adjustment (Program Outline Section 25)
1.
Columbia will manage the daily, seasonal and annual supplies provided by the Ohio Production
contracts, city gate service for Brewster, and the Operationally Retained capacity. These supplies
are sufficiently large to impact system operations.
2.
Columbia will manage this system impact by adjusting each Demand Curve equally by a
percentage known as the Local Gas Purchase Adjustment
3.
Columbia will estimate annually the level of supplies it will purchase under these contracts. This
estimate will be converted to a Local Gas Purchase Adjustment that will be used to modify the
daily delivery obligations of all Demand Curves equally, i.e. daily deliveries across PSP’s will be
reduced equally on a percentage basis
4.
Since (a) Columbia will be purchasing these volumes daily; (b) customers will be consuming
these volumes daily; (c) all Demand Curves will be adjusted to reflect these volumes; and (d)
each Supplier’s monthly payments will reflect the consumption of these supplies, each CHOICE
and SCO Supplier will be required to purchase from Columbia the amount of gas represented by
the Local Gas Purchase Adjustment each month
5.
The amount of gas to be purchased monthly from Columbia shall be known as the Local Gas
Purchase Requirement
42
Ohio Production / City Gate Supply
Local Gas Purchase Adjustment (Continued)
6.
The purchase price for the Local Gas Purchase Requirement shall be the TCO Monthly Index plus a
fixed dollar amount per Mcf (“Local Gas Purchase Price”)
7.
Columbia shall determine the prospective fixed dollar amount annually, at the same time the Local Gas
Adjustment Percentage is determined, by performing a historical analysis of actual purchases. These
purchases are normalized, with actual purchase prices applied to the normalized volumes. The
demand costs associated with these purchases are also included in the calculation. The resulting
costs are then compared to the TCO Monthly Index price weighted by the normalized purchases by
month to determine the fixed dollar amount.
8.
Actual costs incurred by Columbia for its Local Gas Purchase Requirement, including demand costs,
shall be charged to the CSRR. All revenue received from the CHOICE/SCO Suppliers from the Local
Gas Purchase Requirement shall be credited to the CSRR.
9.
All Local Gas Purchase Requirement purchases shall be included in the annual volume reconciliation
process for CHOICE/SCO Suppliers
43
Annual Cash-Out / Reconciliation (Program Outline Section 29)
1.
COH will cash out all CHOICE and SCO imbalances annually (April through March)
2.
Imbalances represent the difference between the volumes that each Supplier is paid for and the
volumes that they deliver.
– Imbalances are determined for each PSP
– Payment volumes are based on monthly cycle-billing
– Deliveries are calculated on calendar months
• Deliveries include all confirmed nominations from an upstream pipeline and the Local
Gas Purchase Requirement volumes
• Confirmed nominations from upstream pipelines will be converted to Mcf utilizing the
Statewide BTU conversion factor and adjusted by Columbia’s System-Wide Retention
Factor. The Statewide BTU conversion factor will be posted to the website by February
1st.
– CHOICE Suppliers will continue to be reconciled under the existing CHOICE reconciliation
process
• Columbia shall calculate and incorporate an unbilled adjustment into the CHOICE
Customer’s consumption determination
• Columbia shall continue to incorporate a like-in-kind adjustment for CHOICE Suppliers
44
Annual Cash-Out / Reconciliation (Continued)
3.
CHOICE and SCO Suppliers will have two annual cash-out options:
– Arithmetic Average Option – the arithmetic average of the monthly cash-out index price for
the annual April through March period shall be applied to the difference between the annual
payment volumes and the annual deliveries for the same April through March period
– Weighted Average Option – the monthly cash-out index price will be applied to the monthly
difference between payment volumes and delivered volumes and these monthly results
summed at the end of the annual April though March period to determine the annual cashout requirement. Please note that any under delivery that results in a payment due
Columbia under this option is subject to the Natural Gas Excise Tax. This tax
requirement will not be offset against payments due the Supplier resulting from
excess deliveries.
– Each CHOICE Supplier elects the option they wish to utilize via its Aggregation Service
Agreement. The election continues from year to year unless changed by executing a new
Aggregation Service Agreement. SCO Suppliers will elect the option they wish to utilize on
the SCO Supplier Agreement. If the SCO Supplier is an existing CHOICE Supplier, its
election under the SCO Supplier Agreement must be the same as its existing election under
the CHOICE Program.
4.
All annual reconciliation adjustments will be run through the CSRR
45
Statewide Btu Value (Program Outline Section 28)
1.
The Btu value for CHOICE and SCO processes will be fixed for each April through
March period and will apply equally to all PSPs. All Demand Curves and billing
statements shall reflect the same Btu value
2.
Columbia will provide all CHOICE and potential SCO Suppliers the Btu value to be
effective on April 1st of each year no later than February 1st of the same year
46
CHOICE / SCO Supplier Payments
CHOICE / SCO Supplier Payments (Program Outline Section 17)
•
Payments to Suppliers will be made on a net basis
•
Examples of offsets to CHOICE / SCO Supplier payments include the following:
– Local Gas Purchase Charges
– Demand Curve Non-Compliance Charges
– Credit Evaluation Fees
– Annual Reconciliation Charges/Credits
•
Net payments will be rendered each month, by the 25th day of the month, for the prior
month’s activity
•
Columbia will pay SCO Suppliers the amount billed to their allocated SCO Customers,
including sales tax, plus their pro-rata share of the DSS dollars billed each month, less
costs and charges owed Columbia
•
CHOICE Suppliers will be paid for the dollars billed to their CHOICE customers (if
Columbia performs dual billing)
47
CHOICE / SCO Supplier Payments
Example of CHOICE/SCO Supplier Monthly Payment Timeline
Month prior to flow of supplies
15th (1)
Monthly CHOICE file closed to new additions, removals or changes
th
th
16 - 20
Columbia allocates SCO customers and develops monthly demand curves
st
rd
21 - 23
Columbia provides demand curves to CHOICE and SCO Suppliers
st
(2)
21 - EOM
Columbia determines the assignment of capacity for CHOICE and SCO, and
notifies Suppliers of the capacity to be released and the associated offer
numbers. Suppliers are required to take the necessary steps to accept
the capacity being released by Columbia.
Month of Flow
1st
28th - 31st
First gas day of flow under new demand curve
Last gas day of flow under current demand curve
Month Following Flow of Supplies
5th - 23rd
Columbia gathers customer billing and flow information for billing purposes
25th (1)
Columbia provides payment to CHOICE and SCO Suppliers
(1) If this date falls on a w eekend or holiday, the date under this example shall be the immediately preceding business day
(2) End of Month (EOM) w hether the 28th, 29th, 30th or 31st
48
CHOICE / SCO Customer Eligibility
Customer Eligibility (Program Outline Section 30)
CHOICE/SCO Customer Eligibility
•
All customer accounts using less than 6,000 Mcf per year and all human needs customer accounts using
6,000 Mcf or more per year
Transportation Service Customer Eligibility
•
Non-residential customer accounts using less than 6,000 Mcf/yr that have subscribed to 100% Backup
Service.
•
Non-residential Human Needs customer accounts with operable alternative fuel capabilities that consume
6,000 Mcf or more annually.
•
Other non-residential customer accounts that consume 6,000 Mcf or more annually.
•
Asphalt plants and grain dryers with annual usage less than 6,000 Mcf
•
Public School Districts that were receiving Transportation Service as of October 7, 2009, including any new
or existing facility placed into service in any such Public School District prior to March 31, 2013.
•
A TS customer account that is currently grandfathered and not paying the PIPP or DSM rider as of June 3,
1994, will continue to be grandfathered and will not pay the PIPP or DSM rider after April 1, 2012 whether it
defaults to CHOICE or SCO service or elects to remain on Transportation Service.
49
CHOICE / SCO Customer Billing
CHOICE / SCO Customer Billing (Program Outline Section 34)
•
Billing month will be comprised of 21 billing units.
•
Customers will continue to be billed on a billing cycle basis. There will be no proration of bills to
compensate for the variance between calendar month deliveries and billing cycle usage
•
CHOICE customers will be billed at the monthly effective CHOICE Supplier rate, converted to
Ccf (if Columbia performs dual billing) plus sales tax
•
SCO and DSS Customers will be billed at the monthly effective SCO Price, converted to Ccf.
The SCO Customers will be billed sales tax while the DSS Customers will be billed gross
receipts tax on the gas supply costs.
•
CHOICE and SCO Customers are responsible for providing tax exemption certificates.
•
CHOICE and SCO customers will be subject to all applicable service charges, billing
adjustments and riders as set forth in Columbia’s tariff
•
CHOICE Supplier names will appear on their customers’ bills
•
For each SCO Customer, the name of the customer’s SCO Supplier will appear on each
customer’s bill in the same manner that a customer’s CHOICE Supplier name appears on a
CHOICE customer’s bill. SCO Supplier names will not appear on the DSS customer bills.
50
CHOICE / SCO Reconciliation Rider
CHOICE / SCO Reconciliation Rider (“CSRR”) (Program Outline Section 39)
•
CSRR is applicable to CHOICE and SCO customers (including DSS)
•
Billed monthly on all gas consumed per CHOICE/SCO/DSS customer account
•
Provides for recovery or pass back of:
– Imbalances in gas cost expense and recoveries
– Refunds and penalties
– Off-System Sales and Capacity Release (OSS/CR) Revenue sharing
– Billing Enhancement costs
– Six cent cash collateral not required for reimbursement to Columbia for Supplier default
costs
51
Billing Enhancements April 2013
Pursuant to the Stipulation, Columbia has agreed to the following Billing
Enhancements for April 2013
•
Suppliers may bill their Choice Customers a flat fee each month covering the Supplier’s gas
costs for the month
•
Rate ready billing codes increase to 100 per Supplier
•
Suppliers may bill a rate based upon monthly NYMEX prices, plus or minus a value
•
Supplier may increase the size of its logo and have it placed in the top margin on the front
page of the bill. There is a competitively neutral fee to Suppliers for this service and the
revenue is credited to the CSRR.
•
Rates can be submitted daily to be effective with the Choice Customer’s next billing cycle
•
Contract portability for those Choice Customers changing their address. Not applicable to
Governmental Aggregation customers.
52
Billing Enhancements April 2017
Pursuant to the Stipulation, Columbia has agreed to the following Billing
Enhancements by April 2017
•
Suppliers may bill commodity-related charges to Choice Customers via rate ready, bill ready,
or a combination of the two under Columbia’s consolidated billing option
•
Provide Customers with the ability to prepay the commodity portion of the bill
•
Provide Customers with the ability to enroll in the Choice Program at the time they request
service with Columbia
•
Columbia will process Choice enrollment and drop transactions each processing day. A
snapshot will be used to develop the demand and supply curves as well as the capacity
allocation
53
Website information
SCO and Certification information
SCO information: http://www.columbiasuppliers.com/ under Columbia Gas of Ohio
Auctions: April 2013 – March 2014 (SCO)
Certification:
http://www.puco.ohio.gov/puco/ and more specifically at
http://www.puco.ohio.gov/puco/index.cfm/puco-forms/competitive-retail-naturalgas-provider-forms/
54
Primary Contacts for SCO/CHOICE
Tom Heckathorn
614-460-4996
theckathorn@nisource.com
Mike Ripley
614-460-6219
jripley@nisource.com
Michele Caddell
614-460-6841
mcaddell@nisource.com
55
Question and Answer Period
56
Download