Customer Information System Replacement Project Update Cornerstone Phase 4 Update for Stakeholders October 19, 2011 1 Phase 4 – Current Status Board Approval On Track TODAY Go Live 2012 2011 Q2 Apr May Q3 Jun Jul Blueprint (6 months) Aug Q4 Sep Oct Nov Q1 Dec Jan Feb Q2 Mar Apr May Realization (7 months) 2013 Q3 Jun Jul Aug Final Prep (5 Months) • The CIS project is nearing the end of the Blueprint phase. • The project schedule is “on track” to the baseline plan • Benefits confirmation is being completed as a part of blueprint • Forecast at completion remains at: $179.8M (including contingency) Q4 Sep Oct Nov Q1 Dec Jan Feb Mar Verification and Stabilization (4 months) 2 Phase 4 - Project Milestones Milestone Date Implementation Kickoff June 1, 2011 Blueprint phase October 31, 2011 Realization Description Context: Officially start the implementation phase. Status Complete Measure: 1. Project team structure has been assembled. 2. Project methodology has been documented and agreed to by all parties. 3. Project leadership team / sponsors assign accountability to the project team. April 30, 2012 Context: The CIS project design has been completed. Measure: 1. Hydro One has reviewed and accepted the design documents and solution. 2. Project governance has compared the design criteria against requirements, timeline, cost and benefits and confirmed that the exit criteria to the Realization phase has been met. In-Progress On track To complete Oct 31 Context: The CIS solution development has been completed and tested. Measure: 1. Development of solution is completed. 2. Systems integration testing has been completed. 3. Business processes changes have been completed. On track To start Nov 1 3 Phase 4 - Project Milestones Milestone Date Final Preparation October 9, 2012 Description Context: Testing, Training and Sustainment Readiness completed Measure: 1. 2. 3. 4. Go-Live October 9, 2012 February 15, 2013 User acceptance testing completed and signed off by LOB. System data conversion and migration activities have been tested / audited and confirmed ready for Go Live weekend. The Sustainment organization has signed off the Operational Readiness Tests and Commissioning final documents are completed. Training material has been developed and training is tracking to plan. On track To Start May 1, 2012 Context: Go-Live – cutover the CIS solution into production. Measure: 1. 2. 3. 4. Verification and Stabilization Status Conversion Activities are completed in accordance with the plan Transactional activity begins within new CIS and legacy systems are moved to read only. Users are able to function within the new system. Adequate support is available to aid users through the transition. On track To go Live Oct 9, 2012 Context: The transition to the sustainment organization for all aspects of support outlined in the services agreement with Inergi. Measure: 1. Hydro One has completed the CIS System Acceptance. 2. The user change management organization is in place and supporting impacted users. 3. Inergi Commissioning final documents are completed. On track To complete Feb 15, 2013 4 CIS Solution Overview By the Numbers 15 Current systems to be retired 40 Existing systems to be integrated with the new CIS Solution 68 Detailed Business Process Designs (BPDs) 2700 Business Requirements to be met 1500 Employees directly impacted by the transformation across Hydro One, Vertex & Inergi (11 lines of business, 27 5 CIS Business Functions Customer Service Customer Information and Contact Management Service Order and Work Management Service Order Management Metering Meter Device Management Meter Data Acquisition and Storage Billing and Payment Bill Calculation and Printing Complex Billing (Interval Metered) Retail and Wholesale Market Wholesale Market Settlements Retailer Enrollment and Billing Conservation and Demand Management Remittance Processing Credit and Collections CIS Systems Telephony IVR/ CTI Inbound Correspondence Fax Mail Reporting CRM Interaction Centre iCare Exception Management Application Work Mgmt PCAD ORMS Meter FMS MDUS & WEB Metering Business Warehouse Service Order and Work Management Email Business Objects Customer Service Web eCustomer / TOU Portal Autodialler HES Radix IESO MDMR Billing and Payment Device Mgmt Rates and Billing Collections & Financials AMI Integration EDM & Complex Billing ERP Formatting Retail and Wholesale Market Archiving Market Intercompany Data Exchange - IDE(X) EDM Data Marts Billing and Payment 80+ Interfaces to be built and tested Project Costs On Track Cost Items Cost ($Ms) % of Project Labour / Services HCL Axon Hydro One Inergi/Vertex Subtotal Hardware Software Commissioning and Other Support Implementation Subtotal Contingency (20%) Interest & Overhead Total Implementation Cost Discovery Total PROJECT TOTAL COST $49.1 $14.2 $19.7 $83.0 46% $10.0 $13.4 $21.3 $127.7 71% $25.5 $17.5 $170.7 95% $9.1 $179.8 9