Quarterly Progress Report No. 17 2nd Quarter 2012 (April – June 2012) Table of Acronyms ADB Asian Development Bank ADR Arthur D Riley APM Acting Project Manager ATS Automatic Transfer Switch AusAID Australian Agency for International Development CDC Cabinet Development Committee CEO Chief Executive Officer CSO Community Service Obligation DSR Debt-service Ratio EA Executing Agency EARF Environmental Assessment and Review Framework EI Egis International EPC Electric Power Corporation ESU Environment and Social Unit GoS Government of Samoa IA Implementing Agency ICB International Competitive Bidding IEE Initial Environmental Examination IRR Internal Rate of Return JBIC Japan Bank for International Cooperation JICA Japan International Cooperation Agency km kilometre kV kilo Volt kVA kilo Volt-Ampere kW kilo Watt LARF Land Acquisition and Resettlement Framework LARSF Land Acquisition and Resettlement Screening Form MAN MAN Diesel Australia Ltd MCIL Ministry of Commerce, Industry and Labour MNRE Ministry of Natural Resource and Environment MOF Ministry of Finance MOU Memorandum of Understanding MV Medium Voltage MWCSD Ministry of Women Community and Social Development NCB National Competitive Bidding EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 2 of 55 NPV Net Present Value PEAR Preliminary Environmental Assessment Report PM Project Manager PMC Project Management Committee PMU Project Management Unit PPMS Project Performance Monitoring System PSEP Power Sector Expansion Project PSC Project Steering Committee PUMA Planning & Urban Management Agency REA Rapid Environmental Assessment SLC Samoa Land Corporation SMEC Snowy Mountain Engineering Consultant STEC Samoa Trust Estate Corporation SWA Samoa Water Authority TA Technical Assistance TER Tender Evaluation Report USD American Currency EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 3 of 55 Distribution List Hon. Manualesagalala Enokati Posala Minister of Works, Transport and Infrastructure Anthony Maxwell Team Leader Asian Development Bank Wen Zhand ADB South Pacific Infrastructure Specialist Heather Dixon 2nd Secretary Development Cooperation Australian High Commission Yoshifusa Shikama Resident Representative JICA Sachie Terasaki Pacific Division JICA Hon. Afoafouvale J. Moors Associate Minister, EPC Tologata G.L.T. Tuimalealiifano General Manager Electric Power Corporation (EPC BOARD MEMBER ex Official) Fa‟aolesa Katopau T. Ainu‟u EPC Board Member and Chairman Papalii Ryan EPC Board Member Fiu Peni Asi EPC Board Member Leiataua Daryl Clarke EPC Board Member Fanene Mark Betham EPC Board Member Ale Vena Ale EPC Board Member Fiu Taligi EPC Board Member Tupa‟imatuna Iulai Lavea Chief Executive Officer Ministry of Finance (EPC BOARD MEMBER & PSC CHAIRPERSON) Aumua Ming Lang Wai Attorney General (PSC MEMBER) Taulealea Malua Chief Executive Officer MNRE (PSC MEMBER) Tainau Taputoa Titimaea General Manager SWA (PSC MEMBER) Kuiniselani Toelupe Tago Chief Executive Officer MWCSD (PSC MEMBER) Vui Lance Lameko Manager, Corporate Services, EPC (PMC MEMBER) Peseta Saepate Acting Manager, Distribution Section, EPC (PMC MEMBER) Vagana Stephanie Lomitusi Manager, Savaii EPC (PMC MEMBER) Toleafoa Tony Atilua Manager, Generation, EPC (PMC MEMBER) Tagaloa Patricia Fruean HR Manager, EPC (PMC MEMBER) Amelia Fa‟asau Manager, Legal Department, EPC (PMC MEMBER) Faumui Iese Toimoana Manager, Utilization, EPC, (PMC MEMBER) Sam Kava Manager, ICT, EPC, (PMC MEMBER) Masoe Tautua Manager, Retail, EPC, (PMC MEMBER) Amituanai Faimanu Tausisi Internal Auditor, EPC, (PMC Member) EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 4 of 55 Table of Contents 1. EXECUTIVE SUMMARY...................................................................................................................... 6 2. INTRODUCTION ................................................................................................................................. 17 3. PROJECT IMPLEMENTATION............................................................................................................ 17 3.1 Project Management Unit Staff Movement.................................................................................. 17 3.2 PMU Actual Personnel Movement during 2nd Quarter and Plan for 3rd Quarter.......................... 19 3.3 Implementation Consultants Personnel Movement...................................................................... 21 3.4 Egis International Personnel Movement during this Quarter and Plan for next Quarter.............. 22 3.5 Implementation Progress .............................................................................................................. 23 SCADA .................................................................................................................................................. 27 NEW SUBPROJECTS........................................................................................................................... 27 4. RISKS AND ISSUES ............................................................................................................................ 28 A. PMU Organization Structure ............................................................................................................ 28 B. Staff Recruitment .............................................................................................................................. 28 C. Prepayment Meters............................................................................................................................ 28 D. Vending and Card System................................................................................................................. 29 E. Fiaga Power Plant Access Road, Pipeline and Fence ........................................................................ 29 F. Land transfer to EPC.......................................................................................................................... 29 G. Claims against EPC........................................................................................................................... 29 5. EPC PERFORMANCE MONITORING ............................................................................................... 30 7. LOAN EFFECTIVE MILESTONES (Electric Power Corporation) ..................................................... 37 8. RESETTLEMENT (updated quarterly) ................................................................................................. 37 9. ENVIRONMENT (updated quarterly)................................................................................................... 41 10. LOAN DRAW DOWN TO DATE (1 Jan - 31 March 2012) ................................................................ 44 11. LAST ADB REVIEW MISSION .......................................................................................................... 45 12 APPENDICES ....................................................................................................................................... 45 13. ATTACHMENTS .................................................................................................................................. 45 Appendix 1 – INVESTMENT PLAN Revised June 2012 ..................................................................... 46 Appendix 2 – DISBURSEMENT PLAN ............................................................................................... 49 Appendix 3 - Revised Project Schedule to end June 2012..................................................................... 50 Appendix 4 - Electricity Receivables..................................................................................................... 52 Appendix 5 – Prepayment Meter Installation Projection & Actuals...................................................... 52 Appendix 6 - System Average Interruption Duration Index (SAIDI) Monitoring................................. 53 Appendix 7 – System Average Interruption Frequency Index (SAIFI) ................................................. 54 Appendix 8: - PMU Current Organisational Structure........................................................................... 55 EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 5 of 55 1. EXECUTIVE SUMMARY This is the Quarterly Progress Report No. 17 and it covers the project activities and progress for the 2nd Quarter 2012 from April 1 to June 30, 2012. Here is a summary of the progress of each subproject at end of Quarter 2, 2012: 1.1 Core Subprojects Hospital Feeder Upgrade Stage 1 – Contractor was Bluebird Ah LAL JV Project is complete. Prepayment Meters – Contractor is A D Riley NZ Ltd Total number of Prepayment meters installed by ADR up to end of June 2012 is 19,616; 1,384 left to complete ADR‟s contract. Total number of PPM to be installed in ADR‟s contract is 21,000. Contract includes lowering of meters. Total of 3,845 meters have been lowered so far. There are 31,909 active meters at end of June; 22,932 Prepayment Meters and 8,977 still on induction meters. 71.87% of total active meters are on Prepayment; this leaves 3.13% to achieve project goal of having 75% of total number of active meters on Prepayment Meters. ADR repaired 1,064 defective meters with blank screen; 786 are contract meters and 278 EPC installed meters. They replaced a component in defective meters. It was thought this would solve the blank screen problem. But it didn‟t. EPC is very concern of the defect and have pressured ADR for a solution. Worse is that customers continued to receive power even if meters are blank screens. This is a loss to EPC of customers with this kind defective meters will continue to receive free power. Tests continued of an alternative prepayment meter from another supplier, Joy Electric Ltd Company. Test is if meter can work with tokens from existing vending system installed by A D Riley. If tests prove successful, this will give EPC another supplier of these meters. Consultancy Services Implementation Consultant, Egis International, is continuing to complete Feasibility Studies of 5 hydro schemes and tender documents of 3 of the 5 schemes. PMU still has 2 individual consultants hired. Replacement of 3 rd individual consultant who resigned was replaced with a local hired Distribution Engineer. PMU to submit to ADB proposal for additional consultants required to complete project. ADB approved to hire short term experts to assist with detailed commissioning of these subprojects; Fiaga power plant, SCADA, and Fuluasou Substation. ADB approved to fund as part of PSEP a short term individual consultant to conduct a Cost of Service and Tariff Study. Request for Proposal for solicitation will be issued soon. 1.2 Candidate Subprojects EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 6 of 55 Upolu Generation 1.2.1 Tanugamanono Plant Noise and Emission Controls No activity this Quarter. May not need to do this subproject because new Board of Directors approved to relocate all 4 base load generators from Tanugamanono power station to the new power station in Fiaga. New power station is built with only 3 generators to be relocated to Fiaga new power station. To also relocate 4th generator would require major redesign and construction work to accommodate the 4th generator. Main critical reason for keeping one generator in Tanugamanono is for backup to the main hospital and critical government facilities in middle of Apia, if transmission line from Fiaga power station to Fuluasou Substation and Tanugamanono is down on a fault. Main feeder which supplies power to main hospital and rest of critical facilities in Apia is connected to Tanugamanono power station. Refurbishment of Alaoa Hydro Plant Project is complete. Plant is back in operation. One change order from civil contractor is approved. Change is for extra length of stairway they built alongside penstock to use by maintenance crew. Fiaga Power Plant Lot A – Contractor is Blue Bird Ah LAL in association with Woods Pacific Ltd and Mitsubishi Heavy Industry (BBA/Woods/MHI) This project include; powerhouse, 4 new generators, drainage, ring road, single stack, water system, fire fighting system, wastewater system, workshops, electrical reticulation in power plant, fence, earth grid system, and water storage tanks. 70% of contract is completed. Commission of generator is scheduled at end of October this year. Installation of generators continued. 6 additional change orders were approved this quarter. This brings accumulated value of all change orders to 4.73% of original contract amount. There are still other change orders being considered. Fiaga Power Plant Electrical Lot B – Contractor is North Power NZ Ltd This contract involves design, manufacture, supply, installation and commissioning of 415 volts, 11kV, 22kV, and 33kV electrical switchgear, 6 power generators, 2 local supply transformers, and backup generators. Installation is 90% complete. Remaining work is dependent on completion of work by others. Pre-commission tests are successfully completed with no problems. Tender Board also approved Change Order No 2 and submitted to Cabinet for approval. Change Order No 2 covers 110VDC and battery bank system and SCADA interface equipment. Fuel Tanks – Contractor is Fuelquip NZ Ltd/GMA Construction Ltd JV Tank bunds are completed. All 6 tanks are completed, arrived and installed. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 7 of 55 Pipe work and pumps to connect tanks to power station is not part of contractor‟s contract. Variation for this is approved. Contractor preparing design and construction drawings Estimate completion is in October 2012. Fiaga Access Road/Pipe/Fence – Contractor is Silva Transport Ltd Contract is complete and being closed out. Change Order No 2 is approved. This is for additional fill materials used for construction of road. Punch list of defects is prepared for contractor to fix. Relocation of Generators 5A, 7A and 9A from Tanugamanono to Fiaga Power Plant Actual moving of the 3 generators has not started, but some of work associated with relocating the 3 generators to Fiaga has been done as part of Fiaga power plant. Bluebird Ah LAL JV, contractor for powerhouse, completed construction of foundation for the 3 generators. North Power NZ Ltd under Fiaga Power Plant Lot B contract supplied and installed 3 power transformers, cable racks and power cables. Also the 11kv switchgear circuit breakers for the 3 generators are included in 11kV switchgear for entire power plant. Work is done. PMU started preparation of tender for relocation of 3 existing generators. New Board of Director approved to relocate all 4 Mirrlees generators from Tanugamanono to Fiaga. Design and construction of Fiaga power station did not allow for the 4th generator to be relocated. Original decision to keep the 4th generator (Unit No. 12) was critical to provide backup for main hospital and Government critical office in Apia. Hospital Feeder Stage 2 – by Bluebird Ah LAL JV 70% of construction is complete; worked stopped awaiting arrival of certain materials. Vaults are installed and connectors inside vaults installed and cables terminated and connected to connectors. North Power NZ Ltd will install terminations of underground cables of feeders to connect to new 22kv switchgear in Tanugamanono power station. Improvements included in this subproject are: a) Upgrade voltage Hospital Feeder from 6.6kV to 22kV; b) replace eighteen (18) 6.6kV transformers with 22kV transformers; c) replace the main 500 kVA transformer which supply the National Hospital d) Install two padmount Automatic Transfer Switches (ATS) at the National Hospital‟s two electricity supply points. ATSs enable two distribution feeders to be connected to the hospital substations so that if the primary feeder is off, the ATS will automatic switch to 2nd feeder; e) Replace the 22kV overhead lines of Hospital Feeder with 22kV underground cables from Tanugamanono power station to Savalalo; f) Construct a dedicated underground transmission line to connect the Samasoni hydro plant direct to Tanugamanono power station; and EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 8 of 55 g) Connect dedicated transmission line for Alaoa and Fale ole Fee hydro plants direct to 22kv switchgear in Tanugamanono power station instead of feeding through East Coast distribution feeder. 33kV Transmission Line – Construction by EPC This 33kV transmission line connects the new Fiaga power plant to the new Fuluasou Substation and continues to Tanugamanono power station. This line becomes the 33kV backbone transmission line that links power stations to substation. There are two 33kV circuits connecting Fiaga Power Plant to Fuluasou Substation; one underground and one overhead. Reason is to improve reliability of transmission line during major cyclone or earthquake. Line continued underground from Fuluasou Substation to Tanugamanono power station. Construction of 33kv overhead line started. Construction is done by EPC and supervised by Distribution Engineer. EPC introduced use of pre-stressed concrete poles for this important transmission line. EPC used to use wooden poles. Underground 33kv cables will be run inside Golf Course to Substation. Samoa Land Corporation approved to run underground cables inside the Golf Course fence. Materials started to arrive. Cables are expected to arrive in September. Factory testing of cable is scheduled on September. Consultations with affected people and survey of powerline route are finished. Total length of trenching for underground cable from Fiaga power station to Fuluasou substation 15 kilometers. EPC will contract out excavation and EPC crew only lay and install cables. . 22kV Underground Cables from Fuluasou Substation to Apia – by EPC Rest of materials supplied as part of 33kv TL contract. Contract has been awarded to 2 suppliers. Design of interconnection of customers along Vaitele Road is complete. Construction has not started. All conduits and vaults for this underground feeder have been built and installed under another earlier contract. Fuluasou Substation – by North Power NZ Ltd Construction continued; about 50% of civil work and 50% of building and transformers bund are completed. Subcontractor is Fletcher Construction Ltd. All medium volt switchgear has arrived in Apia. Factory testing of all main transformers is done. There are tests that did not pass, manufacturer are resolving failed tests. Two PMU engineers attended FAT. EPC reduced scope and cost of this Contract. Replacing the Lalomauga hydro plant 22/33 kV substation for 33kV tie and interconnecting 33kV switchgear is taken out of contract. These changes are included in Change Order 1. CO1 is with ADB for their review and approval. NPL conducted computer modelling of EPC‟s electric network with addition of the Fiaga Power station 4 new generators. This will enable Mitsubishi to design protection system for the 4 new generators in Fiaga. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 9 of 55 Completed factory testing of transformers in Schneider‟s (supplier) factory Indonesia. EPC sent 3 engineers to witnessed tests. Transformers are now shipped due to arrive at end of August. Low Voltage System Improvements (Upolu) Feasibility Study is approved by ADB. About 70% of materials have arrived; rest is ordered with 33kv line materials. Construction is carried by EPC. 22kV Overhead line Reconductoring – Contractor is GMA Construction Ltd Construction continued. Work is 55% complete. Work slowed down due to shortage of materials. Additional materials are ordered 33kv materials contracts. Contracts for supply of materials have awarded to INTRACOR and SOUTH AUSTRAL. Contractor filed a SAT$1,126,076.84 claim loss of revenue due to stoppage of work due to lack of materials. Acting Project Manager disapproved this claim twice. Contractor is now requesting dispute to taken to Adjudicator. Refurbishment of Salelologa Power Station and construction of new power station in Vaiaata. Feasibility Study and Resettlement Plan have been submitted to ADB for review / approval. MOF approved Resettlement Plan. Evaluation report for consultant to conduct resistivity study is submitted to ADB for review/approval. ADB will not approve it until Feasibility Study is approved. EPC is considering to incorporate a bio-diesel plant (by others) in planning of power plant in Vaiaata. Bio diesel plant will be built and operated by somebody else, not EPC. EPC main involvement is buying bio fuel to use in power station. PMU decided to implement Salelologa Substation separately from Vaiaata Power Plant due to deteriorating conditions of electrical switchgear in Salelologa power plant and long implementation time of the Vaiaata power plant. PMU started to prepare bid for substation. Substation will be housed inside old power plant building. Puapua to Asau 22kV (Savaii) overhead line upgrade – Contractor is Tenix NZ Ltd Project is 100% complete. There is still a section of HV powerline (102 spans) that conductors need replacing. Materials for reconductoring of these additional spans are ordered with 33kV line materials. Work will be done by EPC crew. Stream Flow Gaging & Test Equipment Project is 100% complete. Stream gauging station in Tiavea is shutdown and equipment removed. Adequate data has been collected. Refurbishment of Generators 7A and 9A in Tanugamanono Power Station – Contractor is MAN Diesel Australia Ltd EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 10 of 55 Contract is complete with recent commissioning of generator 7A. A new crankshaft was installed in 7A as well as major overhaul. Unit 7A replaced Unit 5A in original contract to overhaul generators 9A and 7A. SCADA – Schneider Electric Ltd Contract is awarded to Schneider Electric Ltd. Contract agreement is signed. Design work starts. Schneider engineers visited on April 10 - 13 to start data collection and finalize contract agreement. Signing of contract is delayed due to a few legal and technical issues. PMU / Office of Attorney General continued to work on contract. Vending System for Prepayment Meters EPC and National Bank of Samoa launched a new system this year for customers to buy top up tokens by a texting system to NBS and payment of token is deducted direct from customer account in NBS. Cost of each transaction is 1 Tala, and is paid by customer. Money collected is automatically deposited in EPC account with NBS. Already 1000 new customers have signed up with NBS for this new service. A new prepayment meter from another supplier is being tested if can work in existing vending system. If it works, this will give EPC an option of another supplier. Taelefaga, Lalomauga, and Samasoni Hydro Plants and Tanugamanono Power Station 22kv Switchgear Refurbishment Contract is 100% complete. Plants are back in operation. Hydro Development Hydro development of schemes in Savaii and Upolu are combined under this subproject. Implementation Consultant (Egis International) continued with preparation of Feasibility Studies of 5 hydro schemes; which are: Faleseela, Fuluasou, Tiapapata, and Tafitoala on Upolu and Faleata-Palauli on Savaii. They are also preparing design built tenders of 3 schemes (Fuluasou, Faleseela, and Tiapapata). Summary of capital costs and annual electricity generated from each of the 3 selected schemes. There isn‟t enough funding in the present budget to build all 3 schemes. Additional funding is needed. Hydro Schemes Fuluasou Tiapapata Falese‟ela Total Installed Capacity MW 1.15 0.6 0.5 2.25 Annual Generation kWh million 4.061 3.478 1.776 11.315 Capital Costs US$million. $13.057 $6.177 $4.910 $24.144 Vaipu Pump Scheme Decision from ADB and EPC to start implementation of this project is still pending. ADB funded study under a Technical Assistance TA: 7121 SAM – Afulilo Environmental Enhancement Project Phase 1 Report by SMEC is complete. Report has been reviewed EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 11 of 55 and discussed by various Government agencies. EPC is presently planning to conduct consultation with 6 villages of Fagaloa District to present findings of the Study. Unpleasant smell of hydrogen sulphide odour generated at Afulilo Dam continues to be of major concern to the people of the village of Taelefaga where the discharge water from the hydro plant flow through. Kids affected by the smell ended up in hospital from vomiting and headache. EPC has decided to implement recommendations of Study Report to mitigate the smell. A new subproject outline to implement these recommendations will be submitted to EPC Board for approval. It is also brought to ADB for their review and approval. Plan is to: 1st install concrete pipes in the ocean to pipe the water from hydro plant to discharge in deep part of bay. 2nd is install pumps or air compressor to improve the circulating of deep water in dam up on surface to expose to oxygen. A USD$300,000 is left over from the TA used for SMEC study. ADB is requested to reprogram this money towards the budget for implementation of remedy to the odour problem. Taelefaga Hydro Plant Governor System Replacement Revised Evaluation Report was submitted to ADB for final consideration. ADB and Government granted approval to award contract to North Power NZ Ltd for total price of US$914,967.75 or SAT$2,091,354.86. Contract replaces existing control system of two hydro generators in the Taelefaga hydro station. Training This is subproject of its own, with a budget of US$0.235million. EPC Board approved outline of this subproject; budget is US$0.235 million. PMU is preparing Training Plan Plan will include setting up a computer based Asset Management Program (AMP) to plan, schedule and manage maintenance of all facilities. PMU reviewed an existing maintenance schedule that was used by EPC if suitable for AMP. PMU prepared bid for installation of Asset Management Program, bid has not been issued until evaluation of an existing program is done. It also include of EPC linemen, mechanics, SCADA technicians and engineers, and operators and power system controllers. PMU Staffing Project Manager‟s position is still vacant. Generation Engineer Consultant continued as acting project manager. EPC advised position locally and internationally. Interview has been done. All positions are now filled except for PM. PMU to submit proposal for additional consultancy services needed to see PSEP to completion. EPC hired Distribution Engineer for PMU. 30 EPC linemen are also assigned work under PMU for construction of power distribution subprojects. This include: 33kv underground transmission line from Fiaga power station to Fuluasou substation, 33kv overhead transmission line from Fiaga power station to Fuluasou substation, 33kv underground EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 12 of 55 transmission line from Fuluasou substation to Tanugamanono power station, 22kv overhead distribution line from Fiaga power station to Fuluasou substation, 22kv underground feeder from Fuluasou substation to Apia, connecting Samasoni hydro 22kv transmission line to Tanugamanono power plant, connecting Alaoa/Fale ole Fee hydro transmission line to Tanugamanono power station and other powerline work. ADB concurred to conduct EPC cost of service and tariff study and funded under PSEP loan. ADB also concurred to hire short term experts for commissioning of Fiaga power plant, SCADA and Fuluasou Substation. Investment Plan Revision Revised Investment Plan is submitted to ADB for approval. Same plan has been approved by Project Steering Committee, and Project Management Committee. Project original Plan had 19 subprojects. 11 new subprojects were added under the same budget. No subproject was dropped. Financial Report at end Quarter 2, 2012 Financial Report to end of 2nd Quarter 2012 No. 1 Details Amounts in USD Total Project Budget USD$100 million 2 Total Amount Obligated/Committed USD$79.156 million 3 Total Claimed (Withdrawal Application) US$54 million 4 Total Amount Already Disbursed (Loan+Grant) US$51.675 million 5 Total Amount Paid Out from: ADB Loan ADB Grant JICA Loan AusAid EPC (US$4.5m include interest payment during construction of SAT$2.8million, Principal repayment has not started until 2013 or 5 yrs from start of project in May 2008) US$15.3 million US$ 6.4 million US$22.9 million US$ 6.6 million US$ 4.5 million 6 Original Funding Sources: ADB Loan ADB Grant JICA Loan AusAid Grant EPC EPC PMU nd US$26.61 million US$15.39 million US$38.00 million US$8.00 million US$12.00 million 2 QUARTER 2012 PROGRESS REPORT Page 13 of 55 Notes: 1. ADB informed Govt. and EPC during their Mission in May of an increase of US$18 million of JICA‟s contribution to Project. EPC will provide a list of subprojects to use this fund on. 2. ADB Mission preferred to keep hydro development subprojects in PSEP under a different development package to seek funding from other sources. EPC Funded Projects These subprojects which are also managed and implemented by PMU are funded under EPC‟s local budget: Generator No. 5A major overhaul – TBA (pay to EPC) Overhaul was bided out. Evaluation report was approved by EPC Project Management Committee and Board. ADB and Government approved award of contract to MAN Diesel Ltd for price of AUD$274,114.23 or SAT$682,046.98. Salelologa No. 8 and 9 Major Overhaul EPC did not go ahead with major overhaul. EPC is consideration other options to improve generation in Salelologa before completion of new power station in Vaiaata. RENEWABLE ENERGY Solar Samoa Ltd Power Purchase Agreement between SSL and EPC has been signed. Project will be launched in July with first 1MW installation in Faleolo Airport. PPA has been approved by the Regulator. BIOGen3 There has been a long delay due to approval of Environmental Impact Assessment (EIA). Company had plans to import power millet to raise here for feed stock for gas manufacturing. MNRE/PUMA did not approve. Company proposed giant grass instead. Approval is being processed as part of EIA. As a starter, Company plans to import glycerine grade liquid fuel to run the generators first awaiting production of gas. Company is seeking land on Apia Wharf to build storage tanks for the imported glycerine. This has not been approved. Company said they secured a 10 acre block in Nuu for the plant. We have not received confirmation. JICA 400kw Solar Project This project is funded by a US$3.6M grant from Japanese Government to all Forum Countries. Main condition is that the (i) main contractor MUST be a Japanese incorporated company; (ii) all major components of the PV systems must be Japanese made and brand; and (iii) Major components are: solar panels, inverters, and power transformers and switchgear. Project involves installation of 400kw or more of total capacity solar systems to generate electricity and feed into EPC‟s grid. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 14 of 55 Bid for construction is advertised. Bid closes on 27 of August 2012. There are 3 EPC sites considered for installation. They are Vaitele Depot, Tanugamanono power plant, and Salelologa power plant sites. Prebid meeting is completed. There are a few bidders who took bid documents. ProCom Solar PV System Proposal Received proposal from ProCom for installation of a 3.5MW Independent Power Producer (IPP). Cabinet approved for National Energy Coordinating Committee (NECC) to investigate ProCom proposal whether it is needed by EPC. EPC main concern of too much solar generation is the impact on system stability. Total solar generation should not exceed 20% of EPC‟s noon peak. The 20% limit in solar generation capacity is already maxed out with Samoa Solar Ltd‟s 3-4MW proposal. So EPC cannot approval anymore solar PV system connected to EPC grid. ProCom original offered a feed in tariff of 57 sene/kWh; later they raised to 65 sene/kWh. EPC notified National Energy Committee that EPC cannot approve to connect any more Solar System to grid. 20% limit of system noon peak has maxed out with Samoa Solar Ltd installations. Renewable Energy Systems Interconnection to EPC system Draft Rules/ Regulations for interconnection agreement has been submitted to Power Regulator and Attorney General for their review and comments. Received Regulator comments. Same with interconnection agreement also submitted to Regulator and AG. Biodiesel NECC approved to ask developer to provide a formal proposal on setting up bio diesel plants in Samoa. Expressional of Interest (EOI) National Energy Coordinating Committee (NECC) of Government approved to issue EOI for investment for development of renewable energy. EOI is for (i) development of biodiesel, (ii) solar hybrid systems with storage batteries for generation of electricity, Withdrawal Applications Table 1 below provides a summary of Withdrawals Application and Disbursements at end of 2nd Quarter 2012: EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 15 of 55 WITHDRAWAL APPLICATIO N S A ND DI SBURSEMENTS AS AT 30TH JUNE 2012 ADI LOAN ·LOAN 2368 ADII GIIANT - ADII 0017 AUSM> GIIANT- AilS 0101 .1CA LOAN- L8232 I SAM-1'1 EPC TOTAL OIS8URSEO PROJECT/ CONTllACTS US$ Equivalent CONTllACT NO'S Value Date US$ Equivalent Value Dllte I US$ Equivalent Value Date US$ Equivalent Value Dllte FU NDS · LOANS+6RANT COUNTDIPAIIT TOTAL PAYMENT RNANONG PER PROJECT VARIANCES TOTAL BUDGET PER PROJECT VAR IANCES (S) (%) I TOTAL PROJECT FUNDS 26610 000 16390,000 PROJECT MANAGER 0 IMPLEMENTATION & INDIVIDUAL CONSULTANTS - L - SINGLE AND THREE PHASE PREPAYMENT METERS ,L 1,612,483 - - 0 88,000,000 12,000,000 - 100,000,000 100,000,000 52,937 323,441 376,378 750,000 373,6 22 50% OL - OL - 2,367,934 272,312 2,640,247 3,181,458 541,211 17% 769 557L - ,L 2,430,087 - 5,170,926 336,110 5,507,036 6,142,688 635,653 10% 2,367,934 L 358 799 L - 0 ' - - 1,318,100 85,676 1,403,776 1,893,637 489,86 1 26% 640,576 - 1,345,781 87,476 1,433,257 1,697,378 264,121 16% 30,293L - 133,775L - 304,244 95,837 400,080 503,029 102,949 20% 9,132 L - 19,568L - 62,199L - 131,314 8,535 139,850 170,497 30,647 18% 82o,4o1L - 1 185,172 · - 396,631L - 1,289,128L - 2,691,331 174,937 2,866,267 2,861,391 393,872L - 192, 413L - 87,o59L - 6o3,895L - 1,277,238 83,020 1,360,259 1,677,825 91,825 5,969 97,794 91,825 4,797,608 311,845 5,109,453 7,040,000 2,199,791 142,986 2,342,778 2,314,104 28,066,024 2,074,292 30,140,316 35,305,078 5,164,76 2 15% 1,069,381 569,510 1,638,891 5,690,000 4,051,109 7 1% - 2,167,150 140,865 2,167,150 3,680,000 1,512,850 41% 118,o62L - 250,218 16,264 250,218 250,218 23,028,079 51,134,652 4,588,210 55,706,598 6 1% 58% - 91:736 r--= 196,500 412,509 - 93,131 L - 199,566L - - 1 14,180 · - REFURBISHMENT OF ALAOA HYDRO POWER STATION - CIVIL WORKS - - 409,111 REFURBISHMENT OF ALAOA HYDRO POWER STATION - MECHANICAL ELECTRICAL MEASUREMENT EQUIPMENTS & POWER SYSTEM PLANN ING SOFTWARE 52,93)- 38,000000 620,752 HOPITAL FEEDER STAGE ONE,ALAOA AND PUAPUA FEEDER - 8000000 125,995 40,415 REFURBISHMENT OF SWITCHGEARS - TAELEFAGAILALOMAUGAISAMASONIIT/NONC (4,877) 0% REFURBISHMENT OF TINONO GENERATORS 9A AND 7A CASHPOWER - VENDING SYSTEM REIMBURSEMENT - ' 28 466L 6428 L - 13 774L ' HOSPITAL FEEDER STAGE 2 & 22Kv UPGRADING 1,556,140 22Kv UNDERGROUND CABLE - FULUA SOU SUBSTATION TO APIA WHARF AREA 687,279 FIAGA DIESEL POWER STATION 8,804,992 33Kv - FIAGA PS TO FULUASOU 55 TO TANUGAMANONO PS 334,418 FULUASOU 22KV SUBSTATION 664,432 - - - 344:766 r=:: 739,050 368,868 L - 112,656L - ·' 2,026,286 - 242 177 L - 01 470:858 r--= 0 - 43158L ' 1,030,988 - - 13,214,284L - - - 19% - 2,343,089 ,L 4,020, 462 317,56 6 498,08s' 1,031,860 - (5,969) 1,930,547 (28,674) -7% 27% -1% UPOLU LOW VOLTAGE n,3ooL - I TOTAL DISBURSEMENTS A S AT 30TH JUNE 2012 % OF FUNDS ALREADY DISBURSED REMAIN ING PROJECT FUNDS A S AT 30TH JUNE 2012 % OF REMAINING PROJECT FUNDS TOTAL FUNDS ALREADY COMMiffiD FOR AWARDED CONTRACTS % OF FUNDS ALREADY COMMITTED FOR AWARDED CONTRACTS 16,303,380 58% 1 11,306,620 % OF FUNDS AVAILABLE FOR NEW PROJECTS 37 4o2L 6,622,518 I 83% 1 42% 1 9,018,587 59% 1 1,377,482 17% 1 I I I 19,747,000 74% 1 9,240,000 60% 1 6,863,000 26% 1 I EPC PMU 6,371,413 I 41% 1 I REMAIN ING PROJECT FUNDS AVAILABLE FOR NEW PROJECTS 17,454 L - 7,969,000 I 6,160,000 100% 1 39% j 36,866,348 42% 7,411,790 62% 40% 1 I I 56% 44% 71,166,000 81% 8,000,000 67% 79,166,000 90% 16,844,000 4,000,000 20,844,0001 3,800,000 10% Page 16 of 55 19% 33% - 44,293,402 34,200,000 I 31,000 0% 1 2"d QUARTER 2012 PROGRESS REPORT 14,971,921 38% 0% 79%1 21% 1 - 2. INTRODUCTION This is the Quarterly Progress Report No. 17 and it covers the project activities and progress for the period from beginning of April to end of June 2012 (2nd Quarter 2012 Progress Report). This Report provides progress report of each subproject highlighting work completed to date, problems encountered and planned solutions. It also provides financial situation of Project, of total funds obligated, claims received, withdrawal application processed and submitted to ADB and amount of money paid to contractors. It also gives status of spending. 3. PROJECT IMPLEMENTATION 3.1 Project Management Unit Staff Movement PMU has a total of 22 staff; 20 EPC local staff and 2 ADB recruited Individual Consultant engineers (Civil and Generation Engineers). Total staff includes: 1 Project Manager (vacant since July 2011), 3 Engineers, 4 Graduate Engineers, 1 Mechanical Supervisor, 1 Project Accountant, 1 Attorney, 1 Social and Land Resettlement Staff, 1 Environmentalist, 1 Public Relation Staff, 1 Secretary, a driver, 1 linemen assistant, 1 Store-person and 3 store assisting staff, and 2 Renewable Energy staff. RE section is now incorporated as part of PMU. A JICA engineer was with PMU for 3 months assisting with SCADA project. . EPC hired a local Distribution Electrical Engineer to replace the International TD engineer who resigned after 4 months of work here. 30 EPC linemen were also assigned to work with PMU for construction 33kv transmission line from Fiaga power station to Fuluasou Substation and to Tanugamanono power station. They also completed other power distribution subprojects under Power Sector Expansion Project. The Project Manager position is still vacant. Newly hired Generation Engineer has been acting Project Engineer since beginning of this year. It is critically important the appointment should be made as soon as possible. PMU staff: Generation engineer/Acting Project Manager Generation Electrical Engineer, TD Electrical Engineer, locally hired and to join PMU in start of 3rd Quarter. System Planner Graduate Engineer, SCADA/Graduate Engineer, Civil Engineer Electrical Graduate Engineer, Civil Graduate Engineer, 1 Environmentalist 1 Land Resettlement Specialist, 1 Legal Advisor, 1 Public Relation Coordinator, 1 Project Accountant, 1 Secretary, 1 Administrative Assistant / Store Keeper, 1 Lineman, and 3 Store assistants, and 1 driver. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 17 of 55 3 Meter inspectors were transferred back to EPC‟s Utilization Section. Fifteen (15) subprojects were under construction this quarter. The status of construction of each subproject at end of 2nd Quarter 2012: 1. Access road and water pipeline to Fiaga new power plant – 100% complete. 2. Construction of security fence around Fiaga property – 100% complete. 3. Upgrading of the Hospital Feeder to 22kv and undergrounding medium voltage cable from Tanugamanono power plant to Apia – 80% complete. 4. Reconductoring of all 22kv overhead line feeders in Upolu – 60% complete. 5. Civil work of refurbishment of Alaoa hydro plant – 90% complete; work that can be done. 6. Reconductoring of Puapua to Asau 22kv Overhead line – 100% complete. 7. Fiaga power plant fuel and oil storage tanks and off loading facility – 60% complete 8. Construction of Alaoa and Fale ole Fee hydro plants dedicated 22kv transmission line from the hydro plants to Tanugamanono power station is in progress – 80% complete 9. Construction of Samasoni hydro plant dedicated transmission line to Tanugamanono power station is in progress – 80% complete. 10. Refurbishment of the 9A and 7A generators in Tanugamanono – 100% complete. 11. Fiaga New Power Plant and Generators Lot A – construction of power house is 90% completed, installation of generators 60% complete, civil work (road, drainage, fence, etc) 60% complete, water tanks, collection, and water distribution system 60% complete. 12. Fiaga Power Plant MV Electrical Switchgear Lot B – switchgear installation and precommissioning testing is 95% complete. 13. Construction of 33kv overhead transmission line from Fiaga power plant to Fuluasou substation started with training on handling and setting up of pre-stressed concrete poles. Underground 33kv line has not started, waiting on arrival of cables and materials. Work is done by EPC. 30 EPC linemen are assigned to this project and other power distribution projects. 33kv line continues to from Fuluasou to Tanugamanono. 14. 22kv underground cable from Fuluasou to Apia wharf – 70% of installation of electrical conduits is completed. This was done as part of the 4 lane road corridor project with Ott Transport as main contractor. Materials were ordered and started to arrive. Cable installation has not started – 0% complete. 15. Prepayment meters – 91.29% of meters under A D Riley‟s contract have been installed. Defective meters with blank screens continued to rise. Defective meters with blank screens are the biggest concern on this project. Worse, is customers with blank screen meters continue to receive electricity without paying top up. Contractors have been asked many times to fix problem. Factory of these meters have not come up with a technical solution. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 18 of 55 3.2 PMU Actual Personnel Movement during 2nd Quarter and Plan for 3rd Quarter 2nd QUARTER 2012 ACTUAL DESIGNATION START FINISH Acting Project Manager 1 April 2012 Jun 30, 2012 & Individual Consultant Generation Engineer Transmission& 1 April 2012 Jun 30, 2012 Distribution Engineer Generation Electrical 1 April 2012 Jun 30, 2012 Engineer Graduate Engineer 1 April 2012 Jun 30, 2012 Power System Planner Project Accountant 1 April 2012 Jun 30, 2012 3rd QUARTER 2012 PLAN START FINISH 1 July 2012 Sept 30, 2012 1 April 2012 Moetuasivi Asiono Legal Environment Advisor Land Acquisition DFC Specialist PRCS Iosefa Aiolupo NAME Fonoti Perelini Taulealea Aumalaga Tiotio Tupai Mau Simanu 1 July 2012 Sept 30, 2012 1 July 2012 Sept 30, 2012 1 July 2012 Sept 30, 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Environmental Specialist 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Raema S. Adam Graduate Engineer – SCADA 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Roberto Pamingtuan Sila Individual Consultant Civil Engineer Electrical Inspector 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Oikumene Apprentice 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Posi Moe Linesman 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Nuulopa Pereira Faalepo Solofa Mathew Lemisio Seukeva Asi Tuuau EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 19 of 55 COMMENTS Will be available for whole 3rd quarter Appointed as Deputy General Manager Operation and left PMU. Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Was away on maternity leave for most of 2nd quarter, but will return to work in 3rd quarter. Will be available for whole 3rd quarter Transferred to EPC Utilization Section in 2nd quarter. To transfer to EPC Utilization Section in 3rd Quarter. Will be available for whole 3rd quarter Elisapeta Collins Secretary 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Alfred Matatia Graduate Civil Engineer 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 John Rimoni 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Venisini Iese Graduate Electrical Engineer Project Assistant/Store keeper Storeman 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Iosefa Leota Storeman assistant 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Puleia Tuiloma Storeman assistant 1 April 2012 Jun 30, 2012 1 July 2012 Sept 30, 2012 Penelope Tupuola EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 20 of 55 Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter Will be available for whole 3rd quarter 3.3 Implementation Consultants Personnel Movement The Implementing Consultant (Egis International) remaining task under their contract is completion of feasibility studies of 5 hydro schemes and tender documents of 3 schemes. Only 3 experts are involved in this remaining task. Completing this task is late. There was little progress during this quarter in completing FS and tenders. Project Manager is putting pressure on IC to complete the FS and tenders. Table below provides number of days worked in each month and combined for 2nd Quarter 2012 for each of IC personnel and remaining man months. Team Members Hydro Expert Civil Engineer Environmentalist Social and Land Resettlement EPC PMU nd Contract Person-mnth person-mnths worked in Q2 Q4 2011 2012 0.526 0 0.89 0 (0.37) 0 (0.1) 0.37 2 QUARTER 2012 PROGRESS REPORT Remaining man- months 0.481 0.604 0 0 Page 21 of 55 3.4 Egis International Personnel Movement during this Quarter and Plan for next Quarter NAME Dominique Giraud Peri Perelini Sam Sesega Sam Sesega EPC PMU DESIGNATION Hydro Expert & Coordinator National Civil Engineer National Environmentalist National Resettlement Specialist nd 2nd QUARTER 2012 ACTUAL START FINISH 1 Apr 2012 31 Jun 2012 1 Apr 2012 31 Jun 2012 1 Apr 2012 31 Jun 2012 1 Apr 2012 31 Jun 2012 2 QUARTER 2012 PROGRESS REPORT PLAN for 3rd QUARTER 2012 START FINISH COMMENTS 1 Jul 2012 30 Sept 2012 Continued working to complete feasibility studies of 5 hydro schemes. 1 Jul 2012 30 Sept 2012 Continued working to complete tenders of 3 schemes. 1 Jul 2012 30 Sept 2012 Continued working to complete feasibility studies of 5 hydro schemes. 1 Jul 2012 30 Sept 2012 Continued working to complete feasibility studies of 5 hydro schemes. Page 22 of 55 3.5 Implementation Progress All implementation activities or tasks are reflected in measuring implementation progress against the subprojects implementation schedules and referred to as “project progress”. All pre-implementation activities or tasks are considered in calculating subproject implementation progress. These activities or tasks include preparation of the Subproject Outline, Feasibility Study, Rapid Environmental Assessment, Initial Environmental Examination, Screening for Land Acquisition and Resettlement, Tender documents, Evaluation of tenders and preparation of awards and contracts. Each task in the implementation schedule is weighted according to its overall contribution (using time as a reference) to progress of subproject implementation. These weights are used to calculate the percentage of subproject progress along the entire time span of the project. This is to provide a holistic view of the pace on implementation. Due to the magnitude of the Power Sector Expansion Project and the number of its subprojects, it is not practical to list all the tasks or activities. Therefore only milestones are listed for the purpose of simplicity of subprojects progress but more details can be obtained from the Project Schedule Gantt Chart of each respective subproject. Refer to Appendix 2 for Project Monitoring. A. Core Subprojects: 1. Hospital Feeder Upgrading Project Stage 1 Project is complete. 2. Single and Three-Phase Prepayment Metering (PPM) A total of 218 prepayment meters were installed during 2nd Quarter; 29 are new installations and 189 conversions from induction to prepayment meters. This brought the total number of meters installed under this contract at end of the 2nd Quarter is 19,722 or 93,91% of 21,000 meters to be converted under this Contract in AD Riley Contract. Total number of active meters at end of 2nd Quarter is 31,909; made up of 22,932 prepayment meters and 8,977 induction meters. This brings total percentage of customers with prepayment meters to 71.87% or 3.13% short of target is 75%. Remaining meters to be installed by A D Riley will bring total percentage to 75%. All new installations are installed with prepayment meters. Besides converting to PPMs, contractor also lowered the meters; 36 meters were lowered to 1.6 meters this 2nd Quarter bringing the total number of meters lowered to 3,715. Most CRITICAL issue with this Contract of installing Prepayment meters is: Blank screen defective meters is still unresolved. A D Riley has been replacing defective meters under warranty. But main concern is that customers with blank screen meters continue to receive power with topping up their meter with more credit resulting in loss of revenue. ADR have not found a solution on this defect. EPC has written strong letters to ADR related to issue. EPC will eventually claim from ADR its loss of revenue due to blank screen meters. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 23 of 55 A D Riley had two technicians here in May to carry out repairs to 786 contract meters and 278 meters installed by EPC. These meters had blank screens. An electronic component was replaced in all these defective meters. However, the repair didn‟t eliminate defect which caused blank screens. At end of this 2nd Quarter 2012, a total of 19,616 meters have installed by ADR under their contract, leaving 1,384 meters remained to be installed to complete their contract. Table below shows meters installed during the 1st and 2nd Quarter 2012: No. Subcontractors Total installed since start Meters installed in Jan 2012 Meters installed in Feb. 2012 Meters installed in Mar. 2012 Meters installed in Apr. 2012 Meters installed in May. 2012 Meters installed in Jun. 2012 1 All Electrical 5,201 0 0 0 0 0 0 2 McLean Electrical 9,278 113 152 60 51 106 69 3 Telecom. Tronics Ltd. 5,243 0 0 0 0 0 0 Total meters installed each month 19,722 113 152 60 51 106 69 Breakdown below are meter lowered during 1st Quarter of 2012 and 2nd Quarter of 2012: Categories Cable length Q1 – 2012 Quantity Q2 – 2012 Quantity 1 0-5 meters 57 68 2 5-10 meters 6 14 4 6 no cable needed 0 0 Lowered during maintenance 0 0 Total meters lowered 70 95 10 meters 3 4 Included in meter count above are meters that were lowered during maintenance. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 24 of 55 Only 3,715 meters have been lowered so far by ADR. This is 19.38% of total number of meters converted plus new ones ( or 19,171 at end of 4th Quarter) installed by A D Riley under its present contract. So there are still about 81% of the meters to be lowered. Beside ADR‟s subcontractor lowering meters as they convert them, EPC is lowering meters already converted on request by consumers. All new meters are installed at 1.6 meters. B. Candidate Subprojects: 1. Upolu a. Generation (i). Tanugamanono Power Station Noise & Emission Control No activity. (ii). Refurbishment of Alaoa Hydro Power Station Completed. (iii). Fiaga Diesel Power Station Powerhouse and Generators (Lot A) Bluebird Ah LAL JV/Woods/MHI continued with construction of powerhouse. About 90% of building is complete. Installation of generators and all associated equipment continued. 5 change orders were approved. This includes; water tanks, external water system, extra excavation, and strengthening of floor of switch room. There are additional change orders under review. Fiaga power station electrical switchgear (Lot B) North Power NZ Ltd completed 95% of construction and installation of all electrical switchgear, and transformers and testing. Final installation will be done when Bluebird Ah LAL JV completed electrical installation of generators. This includes power cables from generators to11kv switchgear. One change order was approved for upgrade of DC system and supply and installation of SCADA interface equipment. They filed two claims for cost for not accessing site during Easter weekend and extra storage cost due to delay in accessing the switchgear room to install generators. Project Manager disapproved both claims. Fiaga Access Road, Water Pipeline and Fence Project is complete. The only outstanding item is approval by ADB and Government of Change Order No 2 for supply of base course materials for construction of road. It is now approved and official closure of project is now being processed. Fiaga Pumped Water Source Tender is prepared to pump water from Samoa Water Authority‟s water system to Fiaga power plant. Bid is with ADB for approval. SWA system is 4 km away from the power plant and an elevation climb of about 250 meters. Because of the high elevation of the power plant at 520 meters, it requires 4 booster pumps to pump water to the power plant. Sites of 4 pumps are selected and a consultation with Samoa Land Corporation who owns the land and lessees is underway. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 25 of 55 (iv) Refurbishment of 9A and 7A Generators at Tanugamanono Power Plant Project is complete and both generators are back in operation. . (v) Taelefaga, Samasoni, and Lalomauga hydro plant and Tanugamanono power station new 22kv switchgear Project is complete. b. Transmission (i). Upgrade of Alaoa 6.6kV Transmission Line to 22kV Project is complete. (ii). 33 kV Underground Cable from Fiaga Power Station to Fuluasou Substation Materials for this project started to arrive. There are two suppliers; INTRACOR and South Austral. The 33kv transmission line has 2 circuits; underground and overhead. This will improve reliability of this critical line against cyclones and earthquakes. Construction of overhead line by EPC crew started. (iii). Hospital Feeder Upgrading Stage 2 This project is under construction; 80% of work is completed. Remaining work is energizing of cable and replacement of 18 x 6.6kv transformers with 22kv ones. Same subproject included; Samasoni hydro underground transmission line and connection to Tanugamanono power station of Alaoa/Fale O le Fee transmission line. Conduits and underground feed to main hospital 2nd substation. (iv) 22kV Fuluasou Substation This project is under construction. Construction by subcontractor, Fletcher Construction continued and is progressing well. Building and civil work (road, drainage, transformer bunds, etc) is 60% complete. Switchgear arrived and is being stored until moved into building. Shipping delayed some of materials for construction. One change order which reduces scope and adding some other items of contract has been approved by ADB and Government. We took off replacing of 33kv tie substation in Lalomauga hydro plant. PMU is preparing tender for construction of river bank protection rock rep rap; this is not part of North Power‟s contract. Construction will be scheduled during dry season next year. (v). Upolu Low Voltage Network Improvements Construction has not commenced. 50% of materials have been received. Remaining 50% is included with rebid materials. Construction will be done by EPC. (vi). Fuluasou Substation to Apia Wharf Area 22kV Underground Cable Installation of cable and equipment has not started. Cables and materials are arriving. Conduits and vaults for this project from Lepea bridge to Apia is already laid as part of the main Vaitele road. There is a 1.7km section from Fuluasou substation to Lepea bridge that has not been done. Excavation of this 1.7km is included as part of another contract which included the 33kv underground cable. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 26 of 55 (vii). 22kV Overhead Conductor Upgrading Program This project is under construction. Contractor, GMA Construction Ltd, continued with construction. About 60% of work is completed and invoiced. This contractor submit a claim of about SAT$1.1M for loss of revenue from September 2011 to February 2012 due to shortage of materials according to them. Acting Project Manager disapproved this claim twice. Dispute is now transferred to Adjudication Process. This is contractor who hired 17 linemen from EPC. Linemen returned to EPC in July 2011. This greatly affected its work production because they did not have qualified linemen and engineer to perform. 2. Savaii a. Generation (i) Hydropower Scheme Savaii hydropower scheme is included under „Hydro Developments‟. One Savaii hydro scheme is included. This is scheme in Faleata, Vailoa, Palauli. Sili Scheme is on hold. Only activity this quarter is completion of Feasibility Study by Egis International, Implementation Consultant. b. Distribution (i). Puapua-Asau 22kV Distribution Line Reconductoring Project is complete. No work on this subproject this Quarter. There are still some sections of distribution system (102 spans of 22kv lines) with conductors that needs replacing with larger ones. Poles and other items will be replaced at same time. Materials are included in rebid materials. EPC will do the work. (ii). Power Factor (PF) Completed. (iii). Low Voltage Network Improvement Program in Savaii Materials are ordered and received. Work has not started. 3. Measurement Equipment: (i). Steam Flow Gauging Equipment Completed. (ii). HV Testing Equipment Completed. SCADA Contract started; contractor is Schneider Electric (Australia) Ltd. Completed field survey and study of option of network. Continued with design. NEW SUBPROJECTS Listed as follows are approved new subprojects: EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 27 of 55 (i). Public Dissemination On going. (ii). Vending System Expansion System is in operation. Only activity is testing of a prepayment meters from Joy Electric Ltd supplier if they work on current vending system. Also getting ITRON manufactured meters to undergo same tests. If successful, this will give EPC other suppliers to buy meters from. (iii). Power System Planning Software On-going updating of system as changes are completed. (iv). Refurbishment of Salelologa Power Station New power plant is built in Vaiaata, not Salelologa. Only substation and mini control centre is located in Salelologa depot. ADB approved FS and Resettlement Plan. Due to deteriorating conditions of existing electrical switchgear in Salelologa and long delay in completing Vaiaata Power Plant, it was decided to separate bid for Salelologa new substation from Vaiaata Power Plant bid. Tender for Salelologa Substation was prepared and submitted to ADB for final review before issuing bid. Resistivity study is carried out in Vaiaata site. Similar geotechnical study will be carried out. (v). Refurbishment of Taelefaga and other power plants 22kV Switchgears Project is complete. (vi). Refurbishment of Tanugamanono Diesel Generators Involves Unit 9A and 7A. Refurbishments are completed. Contract is closed out. (vii). Vaipu Pumping Scheme No decision on this yet if to go ahead. $300,000 is left over from ADB Technical Assistant used for SMEC study on Afulilo. Request is with ADB to reallocate this fund for implementing of solution to odour problem from water from Afulilo Dam that discharges from Taelefaga hydro plant. There is a separate mitigation subproject to solve smell problem. Tender is prepared. . 4. RISKS AND ISSUES A. PMU Organization Structure No further action is needed. PMU continued with present organization structure. B. Staff Recruitment Project Manager‟s position is vacant since middle of 2011; position and is being advertised locally and internationally. A local TD engineer is hired. . C. Prepayment Meters Major issue is blank screen defective meters that is continuing to increase. Contractor is yet to find a solution even though they are replacing defective meters as part of guarantee. But EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 28 of 55 worse problem is customers with blank screen meters continuing to receive power without topping up their meter. D. Vending and Card System There are no issues. Tests of prepayment meters from other suppliers if working on vending system is on-going. Two new suppliers provide test samples. E. Fiaga Power Plant Access Road, Pipeline and Fence Only outstanding item was approval of final Change Order No 2, which was finally approved by ADB and Government. Contract Agreement addendum is in process. Project is complete and is being closed out. F. Land transfer to EPC Official transfer of 97 acres in Fiaga and 100 acres in Vaiaata for new power plants is still outstanding. A third piece of land (5,059 square meters) in Tuanaimato for the Fuluasou substation was approved by Minister of Environment to be used by EPC. Samoa Land Corporation also approved lease of four 20m x 20m lots of access road to Fiaga Power Plant to install booster water pumps. G. Claims against EPC There are two contractual claims against EPC. One is from GMA Construction Ltd with 22kV overhead line reconductoring. Claim is for lost of revenue when work slowed down due to shortage of materials. Total claims is SAT$1,126,076. Acting Project Manager disapproved claim twice. Case is now refereed to Adjudication. Our counter arguments are: GMA did not have qualified linemen since 17 EPC linemen returned to EPC; contract is for work completed; some qualified is excessive; contractor delayed work from beginning as they were finding some qualified linemen and engineer. Second claim is from North Power NZ Ltd for extra cost associated with their contract of Fiaga Power Plant Lot B. Extra cost is for additional storage charges due to delay in completion of switchgear room in Lot A contract for construction of powerhouse. Second part of this claim is extra cost for non accessing power plant during public holiday during Easter weekend. Again, Acting Project Manager disapproved claims on ground they supposed to coordinate work with power house contractor. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 29 of 55 5. EPC PERFORMANCE MONITORING Design Summary Impact Access to sustainable and reliable electricity services at affordable prices Outcome Improved quality, reliability, and costeffectiveness of power supply Performance Targets/Indicators Current Status Consumer satisfaction ratings of EPC‟s services Complaints to EPC‟s consumer service division Initial Consumer Confidence Survey (CCS) is scheduled for 2011 System Average Interruption Duration Index (SAIDI) Baseline established and verified on 4th Quarter of 2008 and reduced by 20% by 2015 Baseline SAIDI established on 3rd Quarter 2008: Annual SAIDI for Upolu: 1515 min EPC reactivated service order tracking system in Daffron System to track all customers requests.. Annual SAIDI for Savaii: 2622 min Quarterly SAIDI for Upolu: 379 min Quarterly SAIDI for Savaii: 656 min 2nd Quarter 2012 SAIDI: Total Annual SAIDI for Upolu: 380 Annual Unplanned SAIDI Upolu:104 Annual Planned SAIDI Upolu: 276 Total Annual SAIDI for Savaii: 340 Annual Unplanned SAIDI Savaii: 312 Annual Planned SAIDI Savaii: 28 Total Quarterly SAIDI for Upolu: 95 Quarterly Unplanned SAIDI Upolu: 26 Quarterly Planned SAIDI Upolu: 69 Total Quarterly SAIDI for Savaii: 85 Quarterly Unplanned SAIDI Savaii: 78 System Average Interruption Frequency Index (SAIFI) Baseline established and verified on 4th quarter 2008 and reduced by 20% by 2015 Quarterly Planned SAIDI Savaii: 7 Baseline SAIFI established on 3rd Quarter 2008 Annual SAIFI for Upolu: 26 Annual SAIFI for Savaii: 44 Quarterly SAIFI for Upolu: 6.5 Quarterly SAIFI for Savaii: 11 SAIFI on 2nd Quarter 2011 Annual SAIFI for Upolu: 5.2 Annual SAIFI for Savaii: 24 Quarterly SAIFI for Upolu: 1.3 EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 30 of 55 Design Summary Performance Targets/Indicators Current Status Quarterly SAIFI for Savaii: 6 Refer to Appendix 8 for SAIDI monitoring Refer to Appendix 9 for SAIFI monitoring Outputs 1. EPC‟s investment plan meets demand requirements 2. Operational efficiency of EPC improves Cost of generation established and published by 1st Quarter of FY 2009 Cost of Generation established and reported to Power system capacity for energy and power meets demand requirements on Savai‟i and Upolu Baselines for technical system losses are established and verified by 4th Quarter of 2008 and are to be reduced by 10% by 4th Quarter 2010 and 20% by 4th Quarter 2012 Project Implementation Plans meet estimated demand per survey. Planned expansion of power generation is based on N-2 criteria. Baseline for nontechnical system losses established and verified by 4th quarter 2008 and reduced by 10% by 2010. 3. The financial performance of EPC PMU Consistent application nd EPC Board as part of FY 2008 Budget process Baselines figures of Total System losses established on a 12 month moving average at September 2008 are: Upolu: 15.7% Savaii: 18.2% EPC : 15.9% Updated 12 month moving average of total system losses now reported monthly to the Board. End of December 2008 are: Upolu: 17.1% Savaii: 18.2% EPC : 17.2% Not possible to calculate Technical losses due to lack of metering and dedicated resources. Not possible to calculate non-technical losses - this can only be calculated as “total system loss – technical loss” Technical loss is established to be 13.5% from studies by the Japanese Volunteer and PMU in 4th Quarter 2008. Change in non technical loss can be monitored as technical loss level generally remains static Finance Department have begun diagnostic review of causes of non-technical loss as basis for implementation of reduction measures Procedures reviewed in August 2008 and revised procedures implemented. Refer to Customer aging 2 QUARTER 2012 PROGRESS REPORT Page 31 of 55 Design Summary EPC improves Performance Targets/Indicators Current Status of disconnection policy report below. Fuel audits conducted on all EPC‟s diesel power stations Fuel Audit‟s at both Upolu and Savaii Generation Stations introduced 1 May 2008 and now routinely conducted monthly. Results reported monthly to Board. Refer to Fuel Report below for Period of June 2011 to June 2012 Timeliness of tariff adjustments in response to cost Base Tariff decrease of 3.6% effective from 1 August 2012, and 2% discount for all prepayment meter customers top up purchases. This changes were incorporated in FY 2012/13 approved Budget which is already implemented. EPC planning to hire a consultant to conduct a cost of service and tariff review before end of 2012. EPC‟s collection performance improves such that accounts receivables are below 2 months of sales Customers‟ arrears on 2nd Quarter of 2012 were: Debtor days as = 45.4 days % Government Debt (of total debt) = 19.45% % Government Sales (of total sales) = 10.63% Government consumers‟ share of EPC‟s accounts receivables reduced from 55% in 2007 to less than their share of total sales by 31 December 2009 EPC PMU nd Debt/Sales Ratio:1.83 Reference Appendix 5 2 QUARTER 2012 PROGRESS REPORT Page 32 of 55 4. Effective regulation of the power sector is established Electricity Act Reform to govern the power sector was established by 31 December 2009 Not within Scope of this Project Amendments of the EPC Act consistent with the Electricity Act by 31 December 2009 Regulatory agency established by 31 December 2010. 5. Energy demand-side management Energy conservation and demand-side management public awareness campaign implemented Not within Scope of this Project 6. Development of clean energy Number of projects by energy subsector financed by the clean energy fund Not within Scope of this Project Number of projects by energy subsector eligible for clean development mechanism Electricity produced by clean energy resources (baseline of 45 EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 33 of 55 89.91% 62.399% 37.59S% 0.006% ElSTOCK RECONCILIATION ASAT 30JUNE 2012 Lilres I s SAYM Lilres 1 s TOTAL I liln!s 368,106 s 1.115,997 FuelCon!uqJtion(Urs) IElllll!dl!dFuel Slid end .......... EPC PMU 2"d QUARTER 2012 PROGRESS REPORT Page 34 of 55 GovemmatilldPrivateSa:taEla:trAicrrm MoothEIIII'g By Cnll!lerCa1egxy SEP am JJNE 2011 SXXl s:xxJ s:xxJ l.laith. 11 Milltrls I »3 state-Owned 8ltiies 23 317 C g) Street Lijltilg 1 015 HiS T!tal Gam1111nt 1,5al Prtfa1eSector Dill Note GraiiiT!ta l By ADe oc Prdi Cnnt 1 ·(lysarrears 31·60 Qlysarrmrs 61·90 (lysa rrmrs owril(lys arreall Dill Note Taal ARREARS lexd ClrrSJ II 12 moothtotalsaes KEY mro /ACEIJC.UOR c rtamarroo Tatr DEC 1 .R JN 2012 FEB 2012 12 [(X) KOO KOO 112 • y JJNE 2012 2012 SYIJ 160 1Qn 5 1.21' 3,008 1,29) 611 133 1,151 826 6,861 824 9,879 11,183 10,787 3, 1 1,214 $1 4,103 t190 4,616 1,280 4,4l! 1,221 553 680 m 483 m J11 3,198 5 3,2 833 826 824 9,879 5}16 $80 11,183 6,507 $80 10,787 6,355 llll ]lll 1]t 1:002 Z009 1!& 01) 1,\Q4 1 11.11 l063 1,111 1 1 014 m 11,002 9,49 1,11 4 11 294 \111 10,329 101 I 4,122 4pol a 1)83 1H21 1, 611 634 6JII .t6 491 tM ,214 2r445 23111 1,014 912 9.411 9:940 10,329 101 97 1 2 224 l411 311 l-601 oos 079 2$00 0$ l,f!h t 6.]33 6 1,551 su 833 9466 9,519 .6 t,lro 67l 9,519 5)642 $00,001 .000 94ffi 54ff •t J[I 563 $8). JWW I ' 1..Q2 66 su hm (JI OmJ 121 851 liAY 135 Ull 203 211 U11 15!BI 80 496 2,211 JLNVS SOOl II 31 169 20 .. .lln-12 465 3 1,133 11,002 7,034 .000 1)11 585 418 5I \903 2!11 \063 9A94 5,X() $80 - .,, 41& ,. 1 • $8l &lDAn 42 9,9«1 5.818 Jlmm J[UJI] 9.11 1211 ll9l !111 110 0111 42 .llll 5,826 $80.1»J Jllbrou J1I . - 4i.l rBJ I 1! GoP.nJMnt r&otas lR % l(l% . _ % GMrment r&ot % GMrments c rtamarroo TarQet EPC PMU I @.W% .% r&os 2"d QUARTER 2012 PROGRESS REPORT Page 35 of 55 6. COMPLIANCE WITH LOAN COVENANTS (Beneficiary) Covenant The Beneficiary shall carry out the project with due diligence and efficiency and in conforming with sound administrative, financial, engineering, environmental and public utilities practices In carrying out of the Project and operation of the project facilities the Beneficiary shall perform or cause to be performed, all obligations set forth in schedule 5 of the Financing Agreement Status Complied Comments PMU is carrying out project with due diligence Complied PMU new office at TTTE Bldg is being provided with all facilities Yes, Beneficiary committed personnel, funds, and other resources to support the project. The Beneficiary shall make available promptly, as needed, the funds, facilities, services, land and other resources which are required in addition to the proceeds of the ADB Loan and Grant, and the JBIC Loan and the Government of Australia Grant, for carrying out of the Project and for the operation and maintenance of the Project facilities. The Beneficiary shall enable ADB‟s representatives to inspect the Project, the goods financed out of the proceeds of the ADB Loan and the Grant and the JBIC Loan and the Government of Australia Grant, and any relevant records and documents. Complied Complied Yes, ADB Mission here on Sept 5 to 7. The Beneficiary shall take all action which shall be necessary on its part to enable EPC to perform it‟s obligations under the Project Agreement and shall take or permit any action which would interfere with the performance of such obligations. Complied Yes, EPC provided resources to support Project. The Beneficiary shall exercise its rights under the Subsidiary Financing Agreement in such a manner as to protect the interests of the Beneficiary and ADB and to accomplish the purpose of the Loan and Grant, and the JBIC Loan and the Government of Australia Grant. Complied Yes, regard claims against project and managing of contracts. No rights or obligations under the Subsidiary Financing Agreement shall be assigned, amended, or waived without the prior concurrence of ADB. Complied ALL changes to contracts are pre approved by ADB including less than 15% of contract amount changes. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 36 of 55 7. LOAN EFFECTIVE MILESTONES (Electric Power Corporation) Details Settlement of Government arrears as of 30 September 2007 Status Complied Subsidiary Financing Agreement with EPC Establishment of the Project Steering Committee (PSC) Establishment of the Project Management Committee (PMC) Establishment of Project Management Unit Complied Complied Complied Complied Hire of Implementation Consultant IC contract expired except completion of 5 hydros feasibility study Project Manager To be appointed Restructure of PMU Maintained old flat org. chart. It works. Project Accountant Generation Engineer Transmission & Distribution Engineer Power System Planner Public Relation & Community Liaison Specialist SCADA Engineer PMU Secretary Establishment of Environment and Social Unit Legal / Environment Advisor Environment Specialist Land & Acquisition Specialist Effectiveness of the JBIC Loan Agreement Commitment of the Government of Australia Grant Legal Opinion from the Attorney General‟s Office 8. Complied Complied Complied Complied Complied Complied Complied Complied Complied Complied Complied Complied Complied, Aussie Aid grant is used up Complied; all contracts need AGO clearances. RESETTLEMENT (updated quarterly) Official transfer or lease of Fiaga 97 acres, Vaiaata 100 acres and additional land in Tuanaimato for Fuluasou Substation is still pending; but not affecting progress of project. These will be addressed towards end of the Project. However, Cabinet had approved all 3 properties for EPC to use for power sector facilities. Samoa Land Corporation also approved lease of four 20m x 20m lots to install booster water pumps for Fiaga power plant water supply. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 37 of 55 Status of land acquisition and resettlement for subprojects at end of 2nd Quarter 2012: Subproject Temporary Land Acquisition Permanent Land Acquisition Percentage Obtained Commentary on Negotiations and Compensation paid % 1) Hospital Feeder Upgrading Stage 1 N/R N/R N/R N/R 2) Single & Three Phase PPM N/R N/R N/R N/R 3) Tanugamanono Power Station Noise & Emission Control N/R N/R N/R N/R 4) Refurbishment of Alaoa Hydropower Station N/R N/R N/R N/R 5) Fiaga Diesel Power Station NO YES 100% Official transfer or lease of land to EPC is outstanding 6) Upgrade of Alaoa 6.6 kV Transmission Line to 22kV N/R N/R N/R N/R 7) Fiaga Diesel Power Station to Fuluasou Substation 33KV Underground Cable N/R N/R N/R Cable route is inside road reserve but 30% of existing road is outside of legal road reserve. People planted crops inside legal road reserve. Held consultations with affected people and their crops will be compensated. 8) Hospital Feeder Upgrading Stage 2 N/R N/R N/R Cable is laid inside road legal reserve. Have sorted out all land issues. 100% cable is laid. 9) 22kV Fuluasou Substation NO YES 50% Use old EPC hydropower station land. Cabinet approved 500sq meters of extra land for substation. Land is registered. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 38 of 55 10) Low Voltage Network Improvement Program 11)Fuluasou Substation to Apia Wharf Area 22kV Underground Cable 12) Fuluasou Substation to Leulumoega via Vaigaga 22kV Underground Cable N/R N/R N/R N/R N/R N/R N/R Underground feeder will terminate at corner of Vaitele and Falealili Road N/R N/R N/R N/R 13) 22kV Overhead Conductor Upgrading Program N/R N/R N/R N/R 14) Hydro Schemes YES YES YES YES 15) Puapua-Asau Transmission Line 22kV Reconductoring N/R N/R N/R N/R 16) Power Factor Improvement Program N/R N/R N/R N/R 17) Low Voltage Network Improvement N/R N/R N/R N/R 18) Fiaga water booster pumps N/R YES 90% SLC approved 4 lots for pump sites EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 39 of 55 18)Stream Flow Gauging Equipment 19)HV/LV Testing Equipment N/R N/R N/R 20)Supply, Installation & Operation of SCADA System NO YES 50% 21)Public Dissemination N/R N/R N/R N/R 23)Power System Planning Software N/R N/R N/R N/R 24) Refurbishment of Salelologa Power Station N/R N/R N/R Old power plant will be replaced with a new power station at Vaiaata. Old plant will be converted to a substation and a Mini Control Center for Savaii system. 25) Refurbishment of Taelefaga Switchgears N/R N/R N/R N/R 26)Refurbishment of Samasoni Switchgears N/R N/R N/R N/R 27) Refurbishment of Tanugamanono Generators N/R N/R N/R N/R 28)Vaipu Pumping Scheme YES YES 0% Yes, would need approval of land for pump and pipeline N/R N/R N/R N/R NCC included in Fuluasou Substation at old Fuluasou hydro site. Mini NCC in Salelologa Depot. 22)Vending System Expansion 30) Refurbishment of Taelefaga hydro governor system EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT N/F Page 40 of 55 9. ENVIRONMENT (updated quarterly) PUMA approved development consents of all subprojects that are now under construction. PMU is monitoring construction in accordance the DC and reported to PUMA. Inspectors from PUMA also visited construction sites to carry out their own independent inspection of these projects. ADB approved feasibility study of Vaiaata power plant. Included in FS is Resettlement Plan and Initial Environmental Examination. Subproject Constraints Activities Action Taken Comments 1) Hospital Feeder Upgrading Stage 1 NIL NIL NIL Completed 2) Single & Three Phase PPM NIL NIL NIL 93.4% of meters have installed. This brings total number of consumers with PP to 71.87%. Target is 75%. 3) Tanugamanono Power Station Noise & Emission Control NIL NIL NIL Started Feasibility Study; not finished. Project is complete. 4) Refurbishment of Alaoa Hydropower Station NIL NIL NIL 5) Fiaga Diesel Power Station NIL YES YES 6) Upgrade of Alaoa 6.6kV Transmission Line to 22kV NIL NIL NIL Completed. Followed existing line a long side of road. 7) Fiaga New Diesel Power Station to Fuluasou Substation Underground Cable NIL NIL NIL Contracts are awarded for supply of materials. EPC will do construction. 33kv Transmission Line is changed to have one circuit overhead and other underground. 8)Hospital Feeder Upgrading Stage 2 NIL NIL NIL Construction continued; 100% of trenching and EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 41 of 55 installation of ducts is complete. Cables being pulled and installed terminations. 9) 22kV Fuluasou Substation YES NIL NIL Cabinet approved 500 sq meters of land for Substation. Land survey has been registered with MNRE. 10) Low Voltage Improvement Program NIL NIL NIL Received all materials 11) Fuluasou Substation to Apia Wharf Area 22kV Underground Cable NIL NIL NIL Contracts were awarded for supply of materials. Vehicles, tools, equipment and other material have arrived. 12) Fuluasou Substation to Leulumoega via Vaigaga 22kV Underground Cable NIL NIL NIL NIL 13) 22kV Overhead Conductor Upgrading Program NIL NIL NIL Construction continued. 40% is complete. New powerline along East Coast Road require easements and social resettlement of affected trees. No IEE required 14) Hydro Scheme 5 Feasibility Study reports are finalized. 15) Puapua-Asau Transmission Line 22kV Reconductoring NIL NIL NIL Project is complete. 16) Power Factor Improvement Program NIL NIL NIL Assessment completed. PF is good. No further work required. EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 42 of 55 17) Low Voltage Improvement program NIL NIL NIL 18) Stream Flow Gauging Equipment 19) HV/LV Testing Equipment NIL NIL NIL Rapid Environmental Assessment has been prepared and submitted to ADB. No IEE required Completed. NIL NIL NIL NIL 20) Supply, Installation & Operation of SCADA System 21) Public Dissemination 22) Vending System Expansion NL NIL NIL NIL NIL NIL NIL 23) Power System Planning Software NIL NIL NIL NIL 24) Refurbishment of Salelologa Power Station YES YES YES 25) Refurbishment of Taelefaga Switchgears 26) Refurbishment of Samasoni Switchgears NIL NIL NIL NIL NIL NIL NIL 27) Refurbishment of Tanugamanono Generators NIL NIL NIL NIL 28) Vaipu Pump Assisted Scheme NIL NIL NIL Need to complete IEE and prepare tender for construction. 29) Upolu hydro schemes EPC PMU Report of Tender submitted to ADB for approval. ADB approved Feasibility study & Resettlement Plan of Vaiaata power plant NIL Implementation Consultant revising Faleseela Feasibility study and continued with rest of FS for other 4 schemes and tender of 3 schemes. nd 2 QUARTER 2012 PROGRESS REPORT Page 43 of 55 10. 10 No. LOAN DRAW DOWN TO DATE (1 Jan- 31 March 2012) LOAN DRAW DOWN TO DATE (31December 2010) TITLE OF SUBPROJECTS ADB categ• Schedule Date Revised Actual Contract Price Contract Award Contract Budaet USD$M ADB Loan ADB Grant JICA Loan Ausaid Grant Contract Number Actual Date Contract Awarded Draw Down to date Balance 26.61 15.39 38.00 8.00 12.00 100.00 EPC CORE SUBPROJECTS 1Project Manager (0,37 + 0,38 unallocated) Pr oject r mplementatr on consultant: EBI(73 man. 2 m onths) 3 Hosprtal Feeder Upgradr ng Project- Stage 1 Smgle.and Thr ee-Phase Prepayment Metenng 4 Pro·ect 4 Q4 2007 0.75 0.37 CO N-0108 30th Oct 2 007 0.06 4 Q 1 2008 2.67 2.67 CON-05058 2 Ma y 2008 1.74 0.93 3 Q 1 2009 0.60 1.94 ·1.34 3 Q3 2008 5.67 4.90 0.77 3 Q4 2009 0.17 0.00 0.17 3 Q3 2009 1.34 SAM·PSEP -03 0.00 1.34 3 Q1 2010 22.27 35.88 SAM·PSEP -08 6.10 29.78 3 Q3 2009 1.14 SAM·PSEP -02 3 Q1 2010 3.12 3 Q4 2009 3.20 3 Q2 2010 2.93 2.93 3 Q2 2010 1.29 1.29 3 Q2 2012 0.00 0.00 3 Q2 2012 2.78 3 Q3 2009 6.03 16 Hydropower Scheme 3 Q3 2012 10.65 SAVAI'I Transmission Puapua-Asau Transmrssron Line 22 kV 17 Reconductonna Pr oect 18 Low- Voltage Network Expansion Progr am 3 Q3 2009 1.24 3 Q2 2010 0.56 19 Stream Flow Gaugrng Equrpment 3 Q3 2008 0.05 SAM·PSEP -04 23rd Oct 08 0.06 -0.01 20 Electrical Test Equipment Equr pment 3 Q3 2008 0.06 SAM·PSEP -05 23rd Oct 08 0.07 -0.01 21 SCADA 3 Q4 2009 3.48 16.12 53.88 0.10 0.15 SAM·PSEP·02 5.89 PP M1207 30 July 2008 0.69 CANDIDATE SUBPROJECTS UPOLU Generation T anugamanono Power StatJon Noise and Em1ss1on 5 Control Proaram 6 Refur brshment of Alaoa Hydropower Statron 7 Fraga New Dresel Power Station Project UPOLU Transmission Upgrade of the Aa l oa 6.6 kV Transmrssr on Line to 22 8 kV Pro·ect Upolu Diesel Power St ation to Fuluasou Substatron 9 Underaround Cable Pro·ect 10 Hosprt al Feeder Upgradr ng Project- Stage 2 11 22 kV Fuluasou Substatr on Project 12 Low- Voltage Network Expansion Program Fuluasou Subst ation to Apr a Wharf Area 22 kV 13 Underaround Cable Pro·ect Fuluasou Subst ation to Leulumoega via Vaigaga 22 14 kV Underaround Cable Proect 15 22 kV Overhead Conductor Upgradrng Program -0.80 3.12 SAM·PSEP -09 0.84 2.36 2.78 SAM·PSEP -09 0.41 5.62 SAVAII Generation 10.65 0.00 SAM-PSEP-02 1.24 0.56 Measurement Equipment CORE AND CANDIDATE SUBTOTAL 70.00 3.48 44.81 APPROVED NEW SUBPROJECTS 22 Vendrng System 3 Q 1 2009 0.25 23 Public Dr ssemr natron 24 Power System Plannrng Sof tware 3 Q 1 2009 0.10 3 Q3 2008 0.06 SAM·PSEP -06 25 Refurbrshment of Taalefaga and Samasonr SW1tchgea 3 Q2 2009 1.60 26 Refurbrshment of Salelologa Power Statr on 3 Q2 2009 27 Refurbrshment of Tanugamanono Two Generators l Hydro 28 Upou 3 Q3 2009 3 Q ! 20 10 3.51 29 Contrngency (Var pu Assrsted Pumprng Scheme) 3 Q 1 2010 0.50 NEW SUBPROJECTS SUBTOTAL GRAND TOTAL EPC PMU 0.10 23rd Oct 08 0.06 0.00 1.97 -0.37 5.90 SAM·PSEP -07 SAM-PSEP-10 0.75 SAM-PSEP-08 0.47 5.90 0.28 3.51 0.50 12.67 0.00 82.67 44.81 2"d QUARTER 2012 PROGRESS REPORT 2.60 18.7 Page 44 of 55 10.07 63.95 LIST OF WITHDRAWAL APPLICATIONS OUTSTANDING AT END OF Q2, 2012 No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 11. WA No WA 0269 WA 0270 WA 0271 WA 0272 WA 0273 WA 0274 WA 0275 WA 0276 WA 0277 WA 0278 WA 0279 WA 0280 WA 0281 WA 0282 Contractor A D Riley A D Riley BBA JV /Woods / MHI A D Riley A D Riley A D Riley A D Riley Northpower NZ Ltd Northpower NZ Ltd INTRACOR INTRACOR INTRACOR INTRACOR INTRACOR Contract No PPM 1207 PPM1207 12/03A PPM1207 PPM1207 PPM1207 PPM1207 14/01 14/01 13/02A 13/02A 13/02A 13/02A 13/02A Lot LOT 5 LOT 3 LOT 5 LOT 1 LOT 1 Claim No Claim 5 Claim 9 Claim 1 Claim 1 Claim 2 Claim 2 Claim 1 Currency SAT USD USD SAT USD SAT USD NZD NZD USD USD USD USD USD Amount $ $ $ $ $ $ $ $ $ $ $ $ $ $ 46,303.95 4,040.43 351,163.87 18,661.02 1,579.02 16,341.92 1,342.16 435,889.66 62,676.23 54,218.64 99,120.00 42,075.25 5,559.68 45,778.07 LAST ADB REVIEW MISSION No ADB Mission during this Quarter. Next Mission is schedule towards middle of year. 12 APPENDICES 13. ATTACHMENTS EPC PMU nd 2 QUARTER 2012 PROGRESS REPORT Page 45 of 55 Appendix 1 - INVESTMENT PLAN Revised June 2012 REVISED INVESTMENT PLAN (Revised): JUNE 2012, WITH ADDITIONAL SUBPROJECTS No Contractors I Consultants Contract Description Location Estimate Cost mi(USD) Subproject Number %Completed CORE PROJECTS 1 Upolu Hospital Feeder Upgrade Stage 1 Bluebird Ah LAL JV 0.700 SAM PSEP 02/01A 2 Upolu/Savaii Single & three phase Prepayment Metering AD Riley 6.143 SAM PSEP 1207 3 Upolu Project Manager TBA 0.750 4 Upolu Consultant Services (Note 1) Implementation consultant 2.67 Individual consultants 1.50 100% Installation is 91% complete; 73% of All active customers (31, 730) have Prepayment Meters Vacant Egis International & Individual CON 0508 Consultants, short term consultants, COS and Tariff Study Individual consultants, short term experts for commissioning, cost of servce & tariff review CANDIDATE SUBPROJECTS Upolu Generation 5 Upolu T'manono Power Station noise and em iss ion control program 6 Upolu Refurbishment of Alaoa Hydro Power Station: a Electrical- Mechanical 7 Upolu b Civil Works Fiaga Power Plant 0.170 0% 535,847.309 Tenix NZ Ltd Silva Transport Ltd 1.291 SAM PSEP 03 100% 0.536 SAM PSEP 03/01 90%, reduced scope 28.015 SAM PSEP 12/3A Bldg-70%; Equip. Supply-80%; Equip. insta11-70% SAM PSEP 12/38 a LOT A (Generators & Powerhouse) Bluebird/Woods/MHI b LOT B (Electrical SWitchgear) Northpower NZ Ltd 3.437 c Survey work Sepulona Surveyor 0.041 d Level power plant site PPG Construction 0.071 SAM PSEP 12/28 100% e Access Road/fence/water pipeline Silva Transport Ltd 1.420 SAM PSEP 12/2A f Fuel & Oil Tanks Fuelquip/GMA JV 1.200 SAM PSEP 12/04 100% Tank manuf-100%; Design-100%; g Water booster pumping system & tanks EPC 0.400 EPC 0.032 i Relocate Units SA, 7A, & 9A to Fiaga TBA 3.00 j Lube oil supply TBA 0.560 h Water well drilling EPC PMU TBA 2"d QUARTER 2012 PROGRESS REPORT Construction-100%; Equip Supply 90%; Equip. Install 95% 100% SAM PSEP 12/06 Construction-GO% Bid doc-100%;with ADB to review SAM PSEP 12/05 construction 30%, bid preparing 0% Page 46 of 55 Upolu Transmission 8 Upolu 9 Upolu Alaoa Feeder Upgrade 6.6 to 22kV 33kV Transmission Line from Fiaga to Fuluassou Substation Bluebird AhlAL JV 0.440 EPC SAM PSEP 02/02A a Survey services b Trench excavation contract Sepulona SS Ltd TBA 5.690 SAM PSEP 13/03 0.007 1.500 SAM PSEP 13/02 c Equipment rental EPC 0.043 Bluebird AhLAL JV 3.753 SAM PSEP 09/01A SAM PSEP 12/01 10 Upolu Hospital Feeder Upgrade- Stage 2 11 Upolu Fuluasou Substation a River bank riprap protection 100% 10% 100% biding continuing construction 100%, installation 70% Northpower NZ Ltd 3.103 TBA 0.652 construction 70%, installation 5% preparing bid materials supply 100%, construction 0% 12 Upolu Low Voltage System Improvements EPC 0.162 13 Upolu 22kV UG Fuluasou Substation to Apia Wharf EPC 1.430 SAM PSEP 10/01 14 Upolu 22kV Overhead conductor upgrading program GMA Construction Ltd 3.360 SAM PSEP 09/28 construction 60% SAM PSEP 02/028 100% construction 30%, installation 0% Savaii Transmission 15 Savaii Puapua- Asau 22 kV line reconductoring Tenix NZ Ltd 0.754 16 Savaii Low Voltage Network Improvements EPC 0.534 materials supply 100% construciton 9% 17 Savaii Reconductor remaining spans (102) EPC 0.096 0% 100% Measurement Equipme nt 18 Upolu/Savaii Measurement equipment: stream flow gauging EPC 0.062 19 Upolu/Savaii EPC 0.058 19 Upolu/Savaii Measurement equipment: electric HV/current SCADA System Schneider Electric Ltd 3.548 Contingency, 5% 100% SAM PSEP 12/05 0% 0.177 APPROVED NEW SUBPROJECTS 20 Savaii Vaiaata Power Station and Salelologa Substation TBA 7.683 Separate bids a Resistivity study Northpower NZ Ltd 0.010 start on 15/9/12 b Geotechnical study TBA 0.020 c Surveying d Prepare access rd and clear site Sepulona TBA 0.003 0.050 start on11/9/12 0% 21 Upolu/Savaii Vending System AD Riley 0.162 100% 22 Upolu/Savaii EPC 0.100 Continuing 23 Upolu Northpower NZ Ltd 2.731 24 Upolu Public dissemination Taelefaga/Lalomauga/SamasonifTanugamanono Power stations Switchgear Refurbishment Power System Planning Software Northpower NZ Ltd 0.051 MAN Diesel 1.678 25 Upolu Refurbishment of Generators 9A and 7A in Tanugamanono Power Station 26 Upolu Vaipu Pumping Scheme EPC PMU await EPC/ADB approval 2"d QUARTER 2012 PROGRESS REPORT SAM PSEP -07 100% 100% SAM PSEP -08 0.477 Page 47 of 55 100% FS-100%;EIA-80%; Bid-0% 27 ALL Training TBA 28 Upolu Taelefaga Power station Hydro Governor System Upgrade Northpower NZ Ltd Linemen & other trainings & 0.238 0.90 computerized maintenance program SAM PSEP 17/01 Contract awared Hydro Development 29 Upolu/Savaii Hydro Developments- Feasibility Study & tender doc. SUBTOTAL refer below 91.37 Packaged separately & refer NEW PROJECTS below investment costs CONTINGENCY (Physical) 3.42 contingencies LOAN INTERES T PAYMENT DURING CONSTRUCTION 5.21 loan interest during construction TOTAL 100.00 NEW SUBPROJECTS PENDING APPROVAL 30 31 32 33 34 35 Afulilo Dam Environmental hazard Mitigation 0.75 Design and tender Refurbish hydro m/c control system of 3 hydro plants (Samasoni, FOF, Lalomauga) 1.80 EPC Board to approve Refurb. Penstock, valves, etc. of 4 hydros- Taelefaga, Lalomauga, Samasoni & FOF. Refurbish Tanugamaono diesel generator Unit 12 2.40 0.40 EPC Board to approve EPC Board to approve 0.50 getting EPC Board approval Refurbish 3 Cummins generator in Salelologa Hydro developments TOTAL 13.15 I I 19.00 1 Include IC completion of hydro study, independent consultants, short term commission consultants, cost of service and tariff study 2 Total funds needed for 5 hydras is $48m, and $25m for 3 hydras (Fuluasou, Tiapapata, and Faleseela) tender being prepared now. 3 No decision yet on Vaipu Pump Scheme;assign USD300K from TA in SMEC contract to prepare design/tender. 4 TBA- To be announced 5 Proposed new subprojects for additional funds of US$19 million. EPC PMU 2"d QUARTER 2012 PROGRESS REPORT Page 48 of 55 Appendix 2 - DISBURSEMENT PLAN POWER SECTOR EXPANSION PROJECT DISBURSEMENT PLAN- AS OF 2ND QUARTER 2012 TITLE OF SUBPROJECTS AOB Amrd 'D"o'te' cottg• Re 21118 2009 2010 2011 2012 2013 2014 Budgol CORE SUBPROJECTS 1 PrCljectManagef (0,37 +0,38ooaloc ed) 4 04:m7 2 PrCljectifllllemert ion coosuftart EB (13 mal} rrontrn) 3 Hospttal Feeder Up!JadingProject stae 1 4 01 xoo 3 01 JDi:l 4 Sif)Jie- aOOThree-Pha>ePrepa'y!TlertMeterio;J Project 300ml ,. Tan ,. JamaooooPcwer st ionNClise nl Emissioo CClltrCli 3 Q4JD9 O.il RefiJtlishmenlr:t )l,laoaHydroptwef Station- CMiliiiOfo: 3 00 Jll9 1.31 3 01 Xl10 222? O JJ3 OJJ3 OJJ3 0 06 028 0.1U5 0 O.D&'S 0 0 OD625 O.D625 OD625 0!1625 O.HIS O.HIS 0.1145 O.HIS 0211'9 0111'9 0111'9 OlH<J 0.2m 0.271 0 .15 0.15 0 .15 0.15 0.3189 0.3189 0.3189 0.31 00 0.3100 0.31113 0.31&3 0.31 00 0.31 8 ODl% 0.02al O.Onl O.OW O.CWJ O.lll8 O.JJ1 0.1621 0.1621 0.1621 0.1621 0.1621 0.16 27 0.1627 3.3105 U831 1.1831 1.1831 1.1831 oro 018 0.00 0561 0.3189 0.15 261 oro 0.31 8 0 .31 8 CANDIDATE SUBPROJECTS "" "" "" "" '" UPOUJ Gt11ention 0 .11 "' RefiJtlishment r1 AtaoaHydropcwef Station- ElectrciMech. 9 UpctJOies eiPowefPia"lt- Geoerat XandPcwerhClUSe na gaPcwer Plani - EiectrK:al9111itctgeOJ" 10 na gaPPFuei&Ciitlar1\s 1.1831 1.1101 1.1101 1.1101 1.1101 1.1 831 1.1 831 1.1 831 1 .1831 1.183 1.183 1.183 01 Xl10 01 Xl12 11 FiagaPPao:essroad,pipeine& feoce Q2 Xl11 12 naa \lli te em 8oostef PlmJ:S 13 naalllbe cMis upply 03 Xl12 UPOUJ Transrrlssion Up17aOe the Naoa 6.6kV Tr smission Lioeto22 kVPrctect 3 00 Jll9 UpokJOiffi elf'owefSiaiOOilFLiJ: >ooSUtsloi:ionUndef!1CN.m:l 3 14 0., 01 Xl10 Olffi 16 HospHaiFeeOerUpgradirJ9Project-stage2 3 Q4JD9 3 02 Xl10 17 3V!22kVFUU:fl ou SUtsloi:ionPr ect 3 Q2 FUuasouSutGta1ontoApiaWhaI' Area22kVUnOer!1000d 3 02ffi oro oro 3 0.0 05U 2. Xl10 Q2 Xl12 3 02 21 3 00 Jll9 •ro 3 03 Xl12 10.65 Xl12 1H 05U 3.12 05 05U OJ325 0.1325 0.1325 0.13 0.16125 0.161 25 1)_16125 0.161 016ro 016i'll o.llro 32 0.161 0.161 1)_161 293 12'3 0.161 000 19 CablePrrliect 20 FUuasooSuffita1ontoLaloma allia TalliJ;lamanono 22 kV Ovefhe adCorJO.rctCli Upgr adin g Progra-n Olffi 3.12 15 33kVCablePI"Clject 1)_183 o.s l81 0.188 026ro 016ro 13.ll7 0.267 0 >31 02<J 02<J O .HJ ou 011 0 11 0 .3911 0.1111 0.391 02<J 0267 01670 132670 02670 O.ll?O 02£1 02£1 159H 1293£ 1293£ 1.29 1293 1293 603 SA VAll Generation 1293 1293 SA VAl, Transrrlssion Puapua----AsauTrarnmissbn lile 22kV Reom:lucXt i'lgProject 23 24 LcwVoftae Neb.o\l((k E>; anson ProJam 0.186 3 02 Xl10 300ml 0 3 00ml OIJl l7 SCADA 3 Q4Jil9 30 0.3513 I.H 3 02 Jll9 3 01 JD9 100 3{) Pl.biK: Oisse!Tina1oo 3 0 .100 31 3 02 JD9 01 ;mg 0.25 0008 0056 "'' 0"' 0056 0."' 0. "' 0. 005 005 OIJl 1.11 I.S l 1.61 Ul l.ll 0.9i'5 0.9i'5 0.00 0.00 0.31636 0.316 36 0.316 36 0.3163636 1.• "' Ul 0001 0001 APPROVED NEW SUBPROJECTS 2B Ref l..l'bishment r1 Sau-a l D iese l Power sta1oo 29 Ve!ldio;JSy.>tem 0056 O.llilti55 0.316ll 6361 l.l! 121 0.3513 0056 lUI CORE AND CAIIDIDATE SUBTOTAL 0.3513 0.., Meilsurarent ECJ.iiprrart 2s Stream FlcwG augingEquipmert 26 Electrica iTffii Eiflert EIJlipmert TaalefaiJ3, Samasooi,et:swtchQE!ars Ol195 0 .16 0008 0.00 0.00 t.ro 021 031 0.31636361 0.31636361 0.31 636361 0.31 636 1 0.31 6361 ur 0.31 3.16 l.ll l.ll 1.!6 l.ll 0.001 0.001 0.001 ooot '" '" '" 3.131 lHl U7i Ull 000< 000< 000< 0001 0001 0001 0001 0001 0001 03 03 03 0001 0001 0001 025 "'" 3 01 Xl10 05) 0. ro " ore APPROVED BY EPC & ADB,NEW SUBPROJECTS 3p32009 71.81 1B 051 0001 ore 32 PtwefS)stemPimio;ISoflware B V3ipUP\rfllli'lgScheme 34 Retlt812T anono0iesel Generaors "" 3 00 Jll9 0 .125 0.1125 01125 0 .125 01125 01125 0.811 0.87 0 .125 05 0.125 0.15 0.2 3sTrai 36 Retll*.tlimertofT{l(1efagah)tto!PIIerraccrtrol 37 AILJiiO m Ernlirc:m ffl!a hazard mitigation 3B Retlt8Nmert ofotfer 3 h\'df'05QO¥e!TXX' c::cctrOI 022012 oro 0. 1.00 NOT YET APPROVED EPCI ADB,NEW SUBPROJECTS 39 Retlt:81me1o!T<mgam<n:n:JN012Lrlit 0.0 40 Retttt.:hnB1of3Saleblcgageneratocs 41 Ret.rtmnffi h)tto pertod< pes 42 UpokJHyt:lroGeoeratioo 09l GRAND TOTAL EPC PMU 2< 3 01 2010 3.51 !U& I.H 1.3! 1.n 1.61 1.61 Ul '·" 2"d QUARTER 2012 PROGRESS REPORT 0.87 '·" 351 0.131 5.13 ur 2 JI Page 49 of 55 2JI U1 1.!6 ,. '" '" '" l.U 1.31 o Appendix 3- Revised Project Schedule to end June 2012 NO IStatus TITLE OF SUBPROJECTS 2008 1 2 2009 3 2 1 4 2010 3 CORE SUI Hospital Feeder Upgrading Project- Stage1 3 liP CON" 4 Project implementation consultant: EBI (73 man-months) CONT 2011 3 2 1 4 2012 3 2 1 4 2013 3 4 2 1 2014 3 4 2 1 2015 3 1 4 ... COM Single- and Three-Phase Prepayment Metering Project Project Manager (0,37 + 0,38 unallocated) 2 2 1 4 'Ill -.11 • SUBPROJECTS UPOLU Generation 5 6 7 8 9 ,""""""' '""" ...,.••••••' Noise and Emission Control Program t of Alaoa Hydropower Station FSIP Upolu DieselPower Station Project (LotA and Lot B) CIP Fiaga Access Road, Pipeline,and Fence CIP Fiaga Fuel and oH tanks C)p CIP 10 Fiaga; ·system 11 Relocate Gen SEts 5A, 7A & 9A to Fiaga Power Plant 12 Upgrade of the Alaoa6.6 kV · • PL .ine to 22 kV Project 1 line from Fiaga to Fuluasou Substation ... C)p CIP 33kv Iline from Fuluasou ss to· 15 18 HospitalI 1 Project- Stage 2 Samasonihydro ltrans line to Tanugamanono 22 kV Fuluasou Substation I •Network iml CIP CIP CIP PL 19 Fuluasou CIP >Apia Wharf Area22 kV ... COMP 14 16 · I• .... UPOLU 13 :"!.. '4 COM ICable 20 22 kV Overflead Conductor Upgrading Program CIP 21 Alaoa & FOF hydros · CIP i 1linetoT< I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I ... • '-4 ... ... -. ,... • SAVAll OH 22 SAVAI'I Transmission 1 Transmission Line 22 kV 23 24 1 Project Low-Voltage Network 1m1 ... CIP PL Measurement 25 26 27 l=n..inn..•nt Stream Flow Gauging Equipment COMP ElectricalTest Equipment COMP SCADA ,... .. '4.. ... CIP 'Ill NEW SUI 28 ·station PL 29 Sal,.oloaa Substation TP 31 Public Dissemination 32 Refurbish Taaletaga, & others 22kv switchgears COMP 33 Power System Planning Software COMP tof 34 35 Vaipu Pumping Scheme 36 Upolu hydro ONG • Generators 9A and 7A Refurbish Taeletaga hydro plant govemor control system CA TP I I I I EPC PMU 'Ill I I I NEW TP ; ;d = tocks, valves , etc ror 1ae1eraga, am as om, Lalom auga, 42 I I PL Refurbish No 12 gen in T'manono &3 gens in Salelologa Refurbish governor & generator controls of FOF, Lalom auga & Samasoni hydro stations : I I I FSIP Afulilo Dam Environmental Hazard Mitigation rraining 41 I PL ·Fuluasou, Tipapata, Faleseela, & Tafttoala 38 40 I CIP 37 39 ... NEW 2nd QUARTER 2012 PROGRESS REPORT Page 50 of 55 2 2016 3 4 1 2 3 4 NOTES & KEY 1 Completion date -actual & planned 2 Original subprojects & implementation schedules from RRP Report 3 8 9 New subprojects NOT in original RRP Report Completed Construction in Progress Planning Installation in Progress Feasibiilty Study in Progress On-Going 10 11 12 13 Contract Award On Hold Tender Preparation New, pending approval 4 5 6 7 EPC PMU 2"d QUARTER 2012 PROGRESS REPORT COMP CIP PL INP FSIP ONG AG OH TP NEW Page 51 of 55 Appendix 4 - Electricity Receivables Refer to Receivable Rport in Page 36. Appendix 5 – Prepayment Meter Installation Projection & Actuals Project Target is to get 75% of consumers on Cash Power Meters at end of project in 2016. 19,616 meters have converted by A D Riley under their contract. At end of 2nd Quarter of 2012, 71.87% of active consumers have been converted or installed with prepayment meters. There is 3.13% needed to meet target. About 1,384 meters are left to be installed under A D Riley‟s contract. 75% will be reached with these meters. EPC is still testing a new meter from another supplier, Joy Electric Ltd. Another supplier is sending test meters to be tested on A D Riley vending system. If successful, this will give EPC new suppliers beside A D Riley. There has not been any technical solution on blank screen defective meters. ADR is asked for a solution. They have gone back to factory of CP meters. No word from them. POWER SECTOR EXPANSION PROJECT Customers Converted to Prepayment Meters Month Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Total to date EPC PMU All Electrical 136 249 5 203 207 254 595 542 510 194 109 30 55 70 68 79 439 436 390 127 131 185 163 24 - 5,201 McLean Electrical 198 212 162 348 366 233 286 459 583 509 419 190 106 11 129 134 99 304 498 447 433 345 246 289 236 278 235 192 131 127 131 59 83 71 47 48 31 38 14 113 152 60 51 106 69 9,278 Tel ADR Total Installed Tronic this Month 130 464 335 796 5 172 200 751 215 788 233 322 862 495 1,549 473 1,598 370 1,389 223 836 149 448 125 261 218 284 156 355 197 399 209 387 351 1,094 328 1,262 486 1,323 186 746 60 536 431 3 455 7 267 278 235 192 131 127 131 59 83 71 47 48 31 38 14 113 152 60 51 106 69 5,243 19,722 nd No of customers on Cash Power 20,990 21,268 21,503 21,695 21,826 21,953 22,084 22,143 22,226 22,297 22,344 22,392 22,423 22,461 22,475 22,588 22,740 22,800 22,906 22,932 2 QUARTER 2012 PROGRESS REPORT Page 52 of 55 Appendix 6- System Average Interruption Duration Index (SAlOl) Monitoring WOOr--------------------------------------------------------------------------------UPOI.U ACTUAl TOTAL QUARTERLY & ANNUAUY SAlOl MONITORING 5000 AnnuliSAlO l buline OI.atttity SAlOl tw..m. - OutnerlySAIDI --+-- AMuat( SAIDI r----------------------------------------------------------------------------------, SAYAll ACTUAlTOTAl Q UARTERLY & ANNUAUY SAlOl MONITORING 3500 3000 2500 Ar.ru..&ISAIDIbu.tliM =Ouon'"Y SAlOl bmine 2000 - 0\wttltf SAlOl -+--ArinudySAIDI 1500 1000 500 • • SAlOl to be reduced by 20% by 2015 Plan interruption is included since 1st Quarter 2009. EPC PMU 2"d QUARTER 2012 PROGRESS REPORT Page 53 of 55 Appendix 7- System Average Interruption Frequency Index (SAIFI) lmU ACJIIAL TUIAL QUAJIIBII.Y I Alf«JALL.YSAIA c:::::ak.':::• S}Slt e CJil.'"!'"!."..)':E b!S!l"t .------------------------------------------------------------------------------, SAYAll ACTUAlTUIAL QUARlBlY IAitfUALI.Y SAIA c:::::l. !llb!set c::::::JQ:!"-':t"..Y itc"t ll.c-,y Afl .........\:a::::!ly.'i: • • SAIFI to be reduced by 20% by 2015 Plan interruption is included since 1st Quarter 2009. EPC PMU 2"d QUARTER 2012 PROGRESS REPORT Page 54 of 55 Appendix 8: PMU Current Organisational Structure EPC PROJECT MANAGEMENT UNIT Revised 14 Sept 2012 EPC Hoard of Directors General Tologata Tile Tuimalealiifano Manager Project Manager § -----+-----[! = Se c re ta rvi:]P!eta Collins & 1 driver Generation Engineer lndivid. Consultant Perelini Perelini Transmission & Distri buti on Engineer Generation Elec. Engineer Lafai ele. J. Pe eira Mau Simanu Telecom Engneer Civil Engineer Asolima Noted Perelini Perelini a nd Roberto P a mingtuan are 2 individua l consultants fonoti Perelini S. Perelini (Acting Project Manager) A red M tatia Grad. Elec. Engineer John Rimoni ESU Legal Advisor Mathew Lemisio Project Accountant faalepo Solofa Preinspection Overseer Underground Overseer Line Construction Overseer Line Construction Crewl Crew 2 Crew 3 Draftsman EPC PMU 2nd QUARTER 2012 PROGRESS REPORT ESU Social Resettlement Officer Asi Tuuau Page 55 of 55 Renewable Energy Manager Public Relation I Community Officer R pa Yo ng Moe Asi RE Assoc. Technician Bobby Williams