2013/14 MWIG PROJECT IMPLEMENTATION PLAN Date: 13 September 2013 By: Executive Mayor Cllr MD Magabe 1 BACKGROUND • The presentation will outlines the budget allocation amount and the cash flow projections. • The municipality has appointed the “Term Contractors” to short circuit the procurement process. • The amount of R2.4 m was transferred to the municipality at the end of August 2013. 2 BACKGROUND Cont.… • The MWIG funds will be allocated to Municipalities for only three financial years, starting from 2013/14 • SDM has the MWIG allocation of R29.2m for 2013/14, which will be utilised to eradicated the O&M backlogs(Hotspot areas with challenges of functionality) • The allocation for outer years; R 86.5m and R 150.5m respectively will be focusing on the Hotspot areas with challenges of infrastructure and sources as well as extensions. 3 ELIAS MOTSOALEDI REGION VILLAGE ALLOCATED PROJECT DESCRIPTION FUNDS JULY 13 Walkraal A Kuilsrivier (Stompo) Dennilton S/Holdings Connecting ± 1400m line from Whalkraal (RDP) steel tank to cater Kgobokwane. Connecting rising main from new equipped borehole and electric connection. Apply for electric connection Repair of pump and motor at booster pump station next to Zondagsfontein the steel tank. A (Mpheleng) CASH FLOW PROJECTIONS SEPT OCT 13 NOV 13 DEC 13 JAN 14 AUG 13 13 R 100 000 100 000 R 700 000 100 000 250 000 200 000 100 000 R 60 000 60 000 R 357 000 357 000 4 ELIAS MOTSOALEDI REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTIONS JULY 13 AUG 13 Uitspanning B Repair of boreholes. Replace stolen transformer and submersible pump. Elandsdoorn B • • • Kwarrielaagte • • • Connection of electric connection and the repair of the rising main. Repair pump at Kwarrilaagte pump station. Investigating the possibility of connection pipe to Malaeneg reservoir. Placement of stolen transformer and repair of non-operational pump at Waterkloof pump station. Connecting rising main from new equipped borehole and electric connection. Replace the burned control box SEPT 13 OCT 13 R 70 000 70 000 R 620 000 120 000 R 400 000 NOV 13 250 000 DEC 13 JAN 14 250 000 400 000 5 ELIAS MOTSOALEDI REGION VILLAGE ALLOCATED PROJECT DESCRIPTION FUNDS CASH FLOW PROJECTION JUL 13 Monsterlus • Town (MONSTERLUS • TOWNSHIP) Nkosini • • • Repair of Meters and pipe leaks. Refurbishment of WTW Hlogotlou plant. Cleaning up the siltation in the raw water dam and repair of two raw water pumps. Repair pump in the pump stations. Connect one pump from the pump station to pump to Nkosini Distribution reservior, AUG 13 SEPT 13 R 1 280 000 OCT 13 280 000 R 690 000 Sehlakwane Tafelkop (TAFELKOP VILLAGE ) Equipping of newly drilled borehole and connect to existing infrastructure. • Release pumps from service provider and upgrading of transformer at Motetema and Tafelkop to cater two pumpstations. • Refurbishment of broken boreholes, 400 000 DEC 13 300 000 JAN 14 300 000 690 000 R 145 000 R 210 000 NOV 13 145 000 210 000 6 ELIAS MOTSOALEDI REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS • Complete RBWS project, • Verify infrastructure requirements, procure, design and construct extensions R 170 000 Lukau • Plan, design and R 75 000 construct extensions; • Water Resources Development R 4 251 000 Motetema Groblersdal/ Lukau Refurbishment of pump and stations Tafelkop Sterkfontein Rehabilitate or drill test R 150 000 and equip new borehole. CASH FLOW PROJECTIONS JUL AUG SEPT 13 OCT 13 NOV 13 DEC 13 JAN 14 13 13 JeLe 170 000 75 000 2 200 000 2 000 051 150 000 TOTAL AMOUNT R 9 278 000 2 410 000 3 025 051 2 592 000 750 000 400 000 7 FETAKGOMO REGION VILLAGE PROJECT DESCRIPTION ALLOCATE D FUNDS CASH FLOW PROJECTION JUL AUG 13 13 • Current project in progress, • Verify BWS infrastructure requirements and extension requirements, • Optimise Local water resources use, Ga-mmela • Implement WC and WDM, • install elevated storage. Ga-Maesela • Rehabilitate and equip borehole. • Replace two uPVC storage Tanks. Ga-Nkwana Remove and Replace pipes Mohlaletsi SEPT 13 OCT 13 NOV 13 DEC 13 JAN 14 R 71 000 71 000 R 100 000 100 000 R 20 000 20 000 R 50 000 50 000 8 FETAKGOMO REGION VILLAGE ALLOCATED PROJECT DESCRIPTION FUNDS CASH FLOW PROJECTION JUL 13 • • Tshibeng Tsibeng B • • Refurbish pump mains. Replace pumps. • Complete connection to Nkadimeng RWS, Procure and install electrical submersible pump complete with motor , two 10kl jojo tanks and control box. Electrify borehole. Replace booster pumps. • Mphanama Implement WC/ WDM. Community awareness campaign. Repair leaking pipes. Electrify borehole. • TOTAL AMOUNT AUG 13 SEPT 13 OCT 13 R 5 500 5 500 R 24 500 24 500 R 105 000 105 000 R 376 000 0 276 000 NOV 13 100 000 DEC 13 JAN 14 0 0 9 EPHRAIM MOGALE REGION ALLOCATED PROJECT DESCRIPTION FUNDS VILLAGE CASH FLOW PROJECTION JUL 13 Makhutso Investigate Challenges and repair pump station. Phetwane (Flag Implement WCDM Boshielo RWTW) AUG 13 SEPT 13 OCT 13 NOV 13 R 450 000 450 000 R 1 100 000 450 000 R 320 000 320 000 DEC 13 250 000 JAN 14 400 000 Frischgewaagd • Mathukhuthela Installation of the electric connection. ; • Investigate RWS connection, • Investigate challenges, design, procure and construct. Implement WCDM R 400 000 ELANDSKRAAL Sealing of the leaking Reservoir. Hinlopen Refurbishment and Extension (MORARELA ) of reticulation network infrastructure TOTAL AMOUNT 100 000 250 000 R 400 000 400 000 R 220 000 220 000 R 2 890 000 50 000 0 100 000 2 090 000 300 000 400 000 10 TUBATSE REGION VILLAGE ALLOCATED PROJECT DESCRIPTION FUNDS CASH FLOW PROJECTION JUL 13 • AUG 13 SEPT 13 OCT 13 NOV 13 Equip two boreholes and rehabilitation of booster pumps, Verify, procure, design and construct. R 500 000.00 250 0 00 250 000 Verify, procure, design and construct Install package plant. Equip borehole and connect to line. R 593 280.00 120 000 300 000 Ga-Masha Repair of burst bulk pipeline. R 15 000.00 15 000 Ga-Malekana Replace foot mounted motor Address refurbishment and O&M requirements, R 19 165.00 19 165 • Phiring • • • Leboeng Kalkfontein • • Mapodile Address refurbishment and O&M requirements, Procure, site, drill, test and equip borehole R 80 000.00 R 82 149.00 DEC 13 JAN 14 173 280 80 000 82 149 11 TUBATSE REGION VILLAGE ALLOCATED PROJECT DESCRIPTION FUNDS CASH FLOW PROJECTION JUL 13 AUG 13 SEPT 13 • Address refurbishment and O&M requirements, • Procure, design and construct extensions, • Implement WCDM and cost recovery, • Drill and equip new Ga-Phasha borehole R 90 000.00 50 000 • Equip of two boreholes and rehabilitation of Tokagomo ext booster pumps, Mampuru [MAMPURU(M OSHATE)] Replace of rising main R 60 000.00 GaReplace submersible Mamphahlane pump and motor. R 12 000.00 Verify, procure and replace Motlolo stolen diesel engine R 56 000.00 OCT 13 NOV 13 DEC 13 JAN 14 90 000 50 000 60 000 12 000 56 000 12 TUBATSE REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 Sekiti Swale Magakala Replace Stolen diesel engine Replace stolen submersible pump. AUG 13 SEPT 13 R 98 000.00 98 000 R 12 000.00 12 000 Replace diesel engine R 98 000.00 Replace generator with a Ga-Mashabela higher rating one. R 107 001.00 Ga-Mashishi 98 000 Replace diesel engine Seuwe Replacement of submersible pump. R 12 000.00 • Repair pump at Kwarrilaagte pump station. • Investigating the possibility of DITHABANEN connection pipe to G Malaeneg Reservoir R 50 000.00 Replace monostroom Moshira pump R 25 000.00 OCT 13 NOV 13 DEC 13 JAN 14 98 000 107 001 98 000 12 000 50 000 25 000 13 TUBATSE REGION ALLOCATE VILLAGE PROJECT DESCRIPTION D FUNDS CASH FLOW PROJECTION JUL AUG 13 13 SEPT 13 OCT 13 NOV 13 Botshabelo Replace diesel engine, Replace monostroom Shakung pump X2 R 80 000.00 80 000 R 50 000.00 50 000 Sekopung Replace burnt element Replace of Stolen diesel Ga-Podile engine GaReinstate electricity, Khowane • Verify extension and resources requirements, • Procure, design and Sehlaku construct. • Verify extension and resources requirements, Mashibish • Procure, design and ane construct. R 26 535.00 26 535 R 78 000.00 78 000 R 30 000.00 30 000 R 57 474.00 57 474 R 50 000.00 50 000 DEC 13 JAN 14 14 TUBATSE REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 AUG 13 SEPT 13 • Verify extension and resources requirements, • Procure, design and Thabaneng construct. Remove and replace fallen Pulaseng pipes • Verify extension and resources requirements, Matimatsats • Procure, design and i construct. One borehole to be tested, equiped and connected to the exisisting pipe line and the Alverton other one to be electrified OCT 13 NOV 13 R 50 000.00 50 000 R 45 000.00 45 000 R 216 000.00 216 000 R 370 000.00 370 000 Thusanang Replace Stolen diesel engine R 150 000.00 • Replace Stolen diesel engine Ga-Motodi • Borehole to be electrified. R 200 000.00 150 000 100 000 DEC 13 JAN 14 100 000 15 TUBATSE REGION VILLAGE PROJECT DESCRIPTION ALLOCAT ED FUNDS Overall of hydrostat pump and purchase of new R 230 Praktiseer standby pump. 805.00 • Drilling, testing and equipping of boreholes • installation of 200kl steel tank and extension of R 3 326 Makofane reticulation pipeline. 557.00 Verify infrastructure requirements, procure, R 204 Leolo design and construct. 990.00 Replace broken R 20 Taung Monostroom. 000.00 Verify infrastructure requirements, procure, R 164 Sehlabeng design and construct. 491.00 R 7 563 TOTAL AMOUNT 447.00 CASH FLOW PROJECTION DEC MAR JUL AUG SEPT OCT 13 NOV 13 13 JAN 14 FEB 13 13 13 13 13 230 805 526 557 800 000 300 000 300 000 900 000 700 000 204 990 20 000 164 491 31800 0 2068212 2433464 637771 300000 900000 700000 16 MAKHUDUTHAMAGA REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 Kotupu Repair broken bulk pipeline and installation of air valve. Riverside • Refurbishment of Vergelegen WTW and Complete and commission Nebo RWS augmentation, • Implement of WC/WDM Ga-Moloi • Verify extension needs, procure, plan, design and construct • Refurbishment of Vergelegen WTW and Complete and commission Nebo RWS augmentation, • Implement of WC/WDM Jane Furse • Verify extension needs, procure, plan, design and construct. • Refurbishment of Vergelegen WTW and Complete and commission Nebo RWS augmentation, • Implement of WC/WDM AUG 13 SEPT 13 OCT 13 NOV 13 DEC 13 JAN 14 R 200 000 200 000 R 890 000 200 000 500 000 190 00 R 200 000 200 000 R 140 000 140 000 17 MAKHUDUTHAMAGA REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 Madibaneng • • • Sebitsane • • • • Malegale • • • • • Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM AUG 13 SEPT 13 OCT 13 NOV 13 DEC 13 JAN 14 R 130 940 130 000 R 20 000 20 000 R 101 168 101 168 18 MAKHUDUTHAMAGA REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 Maseleseleng • • • • Tsatane Ext 1 • • • Tsatane • • • • Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM AUG 13 SEPT 13 OCT 13 NOV 13 R 33 254 33 254 R 82 939 82 939 R 81 290 R81 290 DEC 13 JAN 14 19 MAKHUDUTHAMAGA REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 Ga-Mokadi • • • Ramphelane • • • • Ga-Maila Mapitsane • • • • • Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM R 32 422 AUG 13 SEPT 13 OCT 13 NOV 13 32 422 R 207 084 R207 084 R 56 283 R56 283 DEC 13 JAN 14 20 MAKHUDUTHAMAGA REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 Marulaneng • • • Manganeng • • • • Modiketsi • • • • • Address refurbishment of BWS components, Address O&M backlog Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM R 93 704 AUG 13 SEPT 13 OCT 13 NOV 13 93 704 R 104 461 R104 461 R 193 824 R193 824 DEC 13 JAN 14 21 MAKHUDUTHAMAGA REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTION JUL 13 AUG 13 SEPT 13 Disesane Masite Molapong • Address refurbishment of BWS components, • Address O&M backlog, • Verify extension requirements, design and construct, • WCDM • Address refurbishment of BWS components, • Address O&M backlog, • Verify extension requirements, design and construct, • WCDM • Address refurbishment of BWS components, • Address O&M backlog, • Verify extension requirements, design and construct, • WCDM R 40 654 OCT 13 NOV 13 40 654 R 78 810 78 810 R 41 530 R41 530 DEC 13 JAN 14 22 MAKHUDUTHAMAGA REGION VILLAGE PROJECT DESCRIPTION ALLOCATED FUNDS CASH FLOW PROJECTIONS JUL 13 Ga-Magolego • • • Ga-Mohlala • • • • Sebetole • • • • • Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM Address refurbishment of BWS components, Address O&M backlog, Verify extension requirements, design and construct, WCDM R 33 239 AUG 13 SEPT 13 OCT 13 NOV 13 33 239 R 52 123 52 123 R 20 000 20 000 DEC 13 JAN 14 23 MAKHUDUTHAMAGA REGION VILLAGE Thoto Molebeledi Ga-Marishane Maseshegwane Ga-Mogashoa Manamane PROJECT DESCRIPTION Design, procure and construct 5km pipeline Drilling or rehabilitate, testing and equipping of new borehole Sealing of leaking concrete reservoir. Replace burnt element Procure and repair the broken pump. TOTAL AMOUNT ALLOCAT ED FUNDS CASH FLOW PROJECTION SE AU JUL G PT 13 13 13 OCT 13 NOV 13 DEC 13 JAN 14 FEB 14 MAR 14 1 666 552 1 100 000 R 5 666 552 500 000 1600 000 400 000 400 000 R 120 000 120 000 R 320 000 220 000 100 000 R 25 000 25 000 R 34 000 34 000 R 9 092 553 2007772 3134013 500000 400000 1666552 1100000 24 Thanks 25