Moldova Electric Power Market Options Sector Study Donors Meeting Chisinau, June 4, 2015 Energy and Extractives Global Practice Belarus, Moldova and Ukraine Country Unit Europe and Central Asia Region Strictly Confidential © 2015 Strictly Confidential © 2015 Electric Power Sector Issues Electricity Sector Issues Extreme dependence on power imports and natural gas as fuel Domestic generation covers only 25% of demand, mostly by old and inefficient CHP plants Imports from MGRES now covers almost 75% of demand Ukraine import share now very minor in terms of volume Moldova system synchronously interconnected with IPS/UPS system via 110 kV and 400 kV lines Existing 400 kV line with Romania not used for imports due to complex operation and lack of maintenance Near-total dependence on one source/supplier of natural gas, both for domestic generation as well as imports Title of Presentation Strictly Confidential © 2015 2 Peak Load Demand and Supply Electricity Sector Issues Peak Load Demand and Supply, 2008 – 2013 (MW) Annual Peak Load Demand CHP-1 CHP-2 CHP-Nord HPP Costesti Deficit, covered by: – MGRES – Ukraine 2008 2009 2010 2011 2012 2013 792 780 805 820 831 833 40 210 20 5 517 30 196 20 9 525 30 201 20 9 545 517 524 545 13.7 173 20 6 607 420 187 25 202 20 0 584 399 185 27 162 20 0 624 438 186 Source: Moldelectrica Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 3 Power System Planning Demand Forecast Assumptions for electricity demand forecast Electricity demand has been and is linearly correlated with PPP GDP GDP growth rate of 3.26 %/year, which is equal to the average during 2001-2013 Assumptions for peak load forecast Annual peak load occurs in the winter season (but gap decreasing) Load factor will increase by 0.5 %/year due to increased use of air-conditioning, etc Demand forecast through 2033 Estimated average annual growth in electricity demand 2.1% and in peak demand 1.6% 2013 2014 2015 2016 2017 2018 2019 2020 2021 2025 2030 2033 12.27 12.67 13.08 13.51 13.95 14.41 14.88 15.36 15.86 18.03 21.17 23.31 Electricity Demand in mill. kWh 4,072 4,170 4,248 4,328 4,410 4,496 4,584 4,675 4,769 5,177 5,766 6,168 Peak Load Demand in MW 833 849 862 873 886 898 911 925 939 999 1,085 1,143 GDP in bill. US$ Source: Calculations based on Moldelectrica data and Energy Strategy until 2030 of the Republic of Moldova Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 4 Supply Capacity Assumptions Power System Planning Moldova Renewable Energy Sources (RES-E) 2% of 150 MW capacity to be installed considered base load equivalent (= 3 MW) Moldova Combined Heat and Power Plants 250 MW CHP-3 will be in operational in 2020 CHP-N in Balti will keep 20 MW capacity until 2033 CHP-1 and -2 will be retired in 2020 Imports from Ukraine Already prior to current problems forecasts showed UKR not to be able to satisfy its own peak demand starting in 2018, thus unable to cover Moldova’s power deficit through 2033 Imports from MGRES Significant investments needed to keep current capacity operating, so ability to fully cover Moldova’s power deficit beyond 2020 questionable Imports from Romania Able to export about 3,300 MW at any time during 2020 – 2033 (even excluding Romania’s 4,500 MW RES-E capacity) Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 5 Power System Planning Energy Balance Forecast Peak load capacity deficit of 870 MW expected by 2033 Year 2012 2013 2015 2019 2020 2025 2030 2033 Annual Peak Load Demand 831 833 862 911 925 999 1,085 1,143 Domestic Generation 247 209 222 222 273 273 273 273 CHP-1 25 27 0 0 0 0 0 0 CHP-2 202 162 202 202 0 0 0 0 CHP-3 0 0 0 0 250 250 250 250 20 20 20 20 20 20 20 20 0 0 0 0 3 3 3 3 TOTAL Deficit 584 624 640 689 652 726 812 870 Covered by: MGRES imports 399 438 550 Ukraine imports 185 186 90 400 Depending on the scenario 289 selected CHP-Nord RES-E Source: Forecasts based on ANRE data. Data for 2012 and 2013 are actuals. Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 6 Interconnection Scenarios Examined Power System Planning The study examined eight different scenarios: •Self-sufficiency 1 assumes the use of both natural gas and coal for new plants. Self-sufficiency 2 assumes only natural gas use. •Synchronous 1, 2 and 4 assume that Romania will cover the entire power deficit and all ancillary services of Moldova. Synchronous 3 assumes MGRES will be interconnected with ENTSO-E. •Asynchronous 1, 2 and 3 link two power systems with different frequency standards through Back-to-Back stations, enabling interconnection with ENTSO-E while remaining in IPS/UPS. Title of Presentation Strictly Confidential © 2015 7 Power System Planning Scenario Investment Costs and Tariff Levels The values for two out of seven criteria used in scenario ranking are shown below. Levelized tariffs are used only for ranking purposes. Actual end-user tariffs may show greater differences between scenarios Total Investments (US$ million) Scenarios Nominal 20-year levelized tariffs, (US$ cents/kWh) PV* SS-1 1,445 1,023 16.60 SS-2 1,005 700 16.31 S-1 410 285 15.01 S-2 383 266 14.96 S-3 348 242 14.94 S-4 463 322 15.07 A-1 709 491 15.45 A-2 715 495 15.43 A-3 728 504 15.48 Title of Presentation Strictly Confidential © 2015 8 Multi-Criteria Decision Analysis Power System Planning Multi-Criteria Decision Analysis used the following criteria: 1. Present value of investment costs 2. 20-year levelized tariff 3. Security of supply 4. Level of competition (number of supply sources) 5. Capacity to transit electricity between East and West 6. CO2 emissions 7. Operational difficulty (number of interconnection lines to be disconnected) Scenario Ranking 1. Values of criteria are calculated by the model based on quantified input data 2. Weighting for each criterion is calculated, by scenario 3. Total score for each scenario is the sum of calculated individual criterion scores Criteria can be changed but must be quantifiable Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 9 Power System Planning Asynchronous Scenarios Asynchronous -1 (A-1) Descri ption Asynchronous interconnection Suceava with Romania (ENTSO-E) through BtB (VSC & LCC) Major new lines Iasi 400kV Iasi – Straseni 330kV Straseni – Chisinau 400kV Chisinau - Vulcanesti 400kV Vulcanesti - Isaccea LCC=Line-Commutated Converter VSC=Voltage-Sourced Converter Asynchronous -2 (A-2) Balti Straseni Ribnita Chisinau Vulcanesti PV of investmen t cost Tariff Suceava Balti Straseni Ribnita Iasi Isaccea Chisinau Vulcanesti MGRES Isaccea Higher capability to stabilize power system Less expensive Mature technology Direct supply to demand center Less operational experiences 25% more expensive 0.5% higher losses (1.2% versus 0.7%) Additional equipment to stabilize voltage fluctuation may be needed (subject to additional study) Pros Cons MGRES Asynchronous interconnection with Romania (ENTSO-E) through BtB (LCCs) Major new lines 400kV Suceava – Balti 400kV Iasi – Straseni 330kV Straseni – Chisinau 400kV Chisinau - Vulcanesti US$ 491 million US$ 495 million 15.45 US$ cents/kWh 15.43 US$ cents/kWh Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 10 Power System Planning Asynchronous Scenarios Asynchronous -1 (A-1) Asynchronous interconnection with Romania (ENTSO-E) through BtB (VSC & LCC) Major new lines 400kV Suceava – Balti Descript ion 400kV Chisinau - Vulcanesti 400kV Vulcanesti – Isaccea 400kV and 330Kv line bays and 400/330kV transformers Suceava Balti Straseni Ribnita Iasi LCC=Line-Commutated Converter VSC=Voltage-Sourced Converter Chisinau Vulcanesti MGRES Isaccea Higher capability to stabilize power system Pros Cons PV of investment cost Tariff Less operational experiences 25% more expensive 0.5% higher losses (1.2% versus 0.7%) US$ 504 million 15.48 US$ cents/kWh Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 11 Recommended: Asynchronous interconnection Power System Planning The top ranked interconnection scenarios are three alternative asynchronous interconnection scenarios with Romania, each scenario having two interconnections. Although one of these scenarios, referred to in this study as Asynchronous-2, ranks under most assumptions higher than the other two, the three asynchronous scenarios are within one percent of each other in terms of ranking. For that reason we recommend that these three scenarios be studied at the same time at feasibility stage in order to ultimately select the most appropriate one for implementation. All three asynchronous scenarios: Can be implemented by 2020 Integrate Moldovan power system into EnC Enable supplies from both West and East Help put downward pressure on electricity prices Important investments necessary both in the BtB interconnections and in the domestic transmission system Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 12 Asynchronous vs Self-sufficiency and Synchronous Power System Planning Self-sufficiency: Very high cost: US$ 0.7-1.0 billion. Limited choice of fuel sources. Increases dependence on sole source and supplier of gas. Synchronous: Full synchronization may take 10-15 years or more. Until then Moldova energy security remains exposed. Synchronous interconnection scenarios imply disconnection from IPS/UPS (Ukraine and MGRES) thus reducing competition. Synchronous 3 assumes major role for MGRES as well, with most assets on Left Bank to be interconnected with ENTSO-E. However, not possible to political uncertainties. Asynchronous: 2 interconnections vs 1 or 3? 1 interconnection not sufficient to cover demand so Moldova remains exposed. 3 interconnections expensive. In future, if Moldova opts for synchronization, the cost of BtB disposal is even higher. Title of Presentation Strictly Confidential © 2015 13 Current Market Structure Power Market Design Limited number of players and no structural basis for competitive market 6 licensed electricity producers State-owned ENERGOCOM SA acting as single buyer of imports 3 suppliers at regulated tariffs: distribution companies RED Union Fenosa (71.1% market share), RED Nord (26.7%) and RED Nord-Vest (8.7%) and 7 suppliers at nonregulated tariffs (3.5%) Small market does not provide enough incentives for private sector investment in generation Regulation and trading framework are missing for competitive market Most TSO roles of Moldelectrica are missing from legislation Regulations on wholesale competition are missing Wholesale market is not competitive given fully regulated domestic generation and non-competitively procured supplies from MGRES and Ukraine Retail market was to be fully opened by 2015 Needed to achieve 100% retail market opening (currently at 10%) by 2015 to meet the EU Energy Directive 2009/72/EC Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 14 Competitive Wholesale Market Criteria Power Market Design To build a truly competitive wholesale market in Moldova means meeting the following criteria: • • • • Ensuring an appropriate market structure (i.e., having enough sellers and buyers to enable competition on both the supply and demand side) Adopting appropriate market rules for trading electricity as well as for procuring cross-border interconnector capacities over the various contractual time horizons Ensuring efficient balancing, i.e., provision of ancillary services by contracting reserves in a regulated and competitive manner and using such reserves through a reliable balancing mechanism Strengthening existing institutions and creating appropriate additional institutions, including capacity building where appropriate. A competitive legal framework alone may not provide enough investment in generation under the authorization procedure. Title of Presentation Strictly Confidential © 2015 15 Power Market Design Market Design Options Possible market design options associated with interconnection scenarios and conforming with EnC requirements: Market Design Option Interconnection Scenario 1. Standalone competitive wholesale market (Moldova separate bidding zone) SS-1, SS-2 Description Electricity subject to competition (in long-term) would be produced inside the country 2. Competitive wholesale market A-1, A-2, A-3 with appropriate rules for energy trading and cross-border capacity allocation (Moldova separate bidding zone) Suppliers able to purchase competitively priced electricity from East and West 3. Merging with an already competitive wholesale market (Moldova and Romania one bidding zone) Electricity would be produced in the common market among Romania/EnC and Moldova S-1, S-2, S-3, S-4 Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 16 Recommended Market Design Power Market Design Competitive wholesale market with appropriate rules for energy trading and cross-border capacity allocation (Option 2) Maximizes benefits in terms of : (i) Security of supply; (ii) Level of competition; (iii) Affordability; (iv) Compliance with regional integration objectives; and (v) Sustainability. Market structure Making competition rules in Moldovan wholesale market effective requires competition on sell side, requiring electricity injection from the West. This will benefit Moldovan retail market and improve conditions for market opening. Market rules Appropriate market rules can be adopted by supplementing domestic generators with foreign/domestic traders who import electricity from West or East. Ensuring sufficient interconnection capacity with ENTSO-E would be of paramount importance. Role of ENERGOCOM to be reviewed. Institutions A market operator should administer day-ahead and centralized forward markets. Suggest using services of OPCOM, either directly or through a subsidiary in Chisinau. Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 17 Overall Conclusion Conclusion Asynchronous interconnection scenarios are recommended Rank consistently highest in the multi-criteria decision analysis Would ensure greater energy security and better prices for Moldova as the electricity could be bought from East and/or West in a competitive manner The nominal incremental investments range from US$421-441 million in current dollars, depending on the asynchronous scenario ultimately selected following feasibility studies. Implementation would result in a 20-year levelized tariff of US$ 15.5 cents/kWh. Adopt a competitive wholesale market design, with appropriate rules for energy trading and cross-border capacity allocation Would help achieve desired increase in security of supply and possibly exert downward pressure on end-user prices due to competition in markets outside Moldova Most of the legislative, regulatory and institutional actions necessary to implement this market structure are already mandatory under the EnC Treaty. Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 18 Next Steps Conclusion Implementation of recommendations will require: Additional studies Comprehensive system planning study needed to determine required structure of domestic transmission system (necessary even without interconnection). Feasibility studies required for each major domestic system component. Design of a medium-term investment program and financing plan to secure adequate interconnection capacity, domestic transmission network reinforcements and CHP-3 replacement Legislative/regulatory changes to open up electricity market and to align legislation and regulations with EU Electricity Directive and Energy Acquis requirements Institutional capacity building/strengthening of MoE, Moldelectrica and ANRE. We assume market operator will be set up with OPCOM. Moldova Electricity Power Market Options Sector Study Strictly Confidential © 2015 19 Sandu Ghidirim Senior Operations Officer sghidirim@worldbank.org Moldova Country Office World Bank Group 20/1, Pushkin Street Worldbankgroup.org Strictly Confidential © 2015