Government Contracts Outline

advertisement
Government Contracts Outline – Professor Schwartz
Allison Geewax – Fall 2012
Table of Contents
BASIC CONSIDERATIONS FOR GOVERNMENT CONTRACTS .................................................................... 3
OVERVIEW ................................................................................................................................................................................ 3
THE POWER TO CONTRACT ................................................................................................................................................... 4
APPROPRIATIONS AND THE ANTI-DEFICIENCY ACT ......................................................................................................... 4
AUTHORITY OF AGENTS ......................................................................................................................................................... 6
ASPECTS AND CONSEQUENCES OF SOVEREIGNTY ............................................................................................................ 10
The Federal Government’s Authority to Change its Contracts ........................................................................ 10
State Disabilities Under the Contract Clause ........................................................................................................... 11
Choice of Law in the Field of Federal Procurement .............................................................................................. 12
The Government Contractor Defense .......................................................................................................................... 14
Qualified Immunity for Government Contractors - Richardson ...................................................................... 15
FEDERAL-STATE RELATIONS .............................................................................................................................................. 17
Federal Contractors’ Immunity from State and Local Taxation .................................................................... 17
Federal Contractors’ Immunity from State Regulation (Paul v. United States) ...................................... 18
THE FALSE CLAIMS ACT AND QUI TAM SUITS AGAINST CONTRACTORS..................................................................... 18
CRIMINAL PROSECUTION ..................................................................................................................................................... 19
FREE SPEECH RIGHTS OF GOVERNMENT CONTRACTORS............................................................................................... 20
PROTESTS, CLAIMS, AND DISPUTES ............................................................................................................. 21
CONTRACT AWARD CONTROVERSIES (BID PROTESTS) ................................................................................................. 21
The Bid Protest Jurisdiction of the General Accounting Office ........................................................................ 22
Award Controversies in the Court of Federal Claims Prior to 1996 and After 1996 ............................. 23
U.S. District Courts under the Administrative Procedure Act .......................................................................... 24
Board of Contract Appeals ............................................................................................................................................... 25
The Relationship Between Bid Protest Forums and Performance Dispute Forums .............................. 26
International and Comparative Law Notes Regarding Bid Protests ............................................................ 26
CONTRACT PERFORMANCE DISPUTES ............................................................................................................................... 28
Introduction to the Disputes Process........................................................................................................................... 29
The Role of the Contracting Officer .............................................................................................................................. 29
Choice of Forum and Procedures Under the Contract Disputes Act .............................................................. 29
FORMATION OF GOVERNMENT CONTRACTS ............................................................................................ 31
BASIC PRINCIPLES OF GOVERNMENT CONTRACT FORMATION ..................................................................................... 31
COMPETITION POLICIES ....................................................................................................................................................... 32
ALTERNATIVE PROCEDURES ............................................................................................................................................... 37
Sealed Bid Contracting....................................................................................................................................................... 37
Competitive Negotiation ................................................................................................................................................... 37
QUALIFICATION ..................................................................................................................................................................... 38
Debarment and Suspension ............................................................................................................................................. 38
Responsibility.......................................................................................................................................................................... 39
Pre-Qualification ................................................................................................................................................................... 40
TYPES OF CONTRACTS: ALLOCATION OF THE RISK OF UNCERTAINTY......................................................................... 41
AUDIT AUTHORITY................................................................................................................................................................ 42
COLLATERAL SOCIO-ECONOMIC POLICIES ............................................................ERROR! BOOKMARK NOT DEFINED.
GOVERNMENT CONTRACTS OUTLINE 1
INTERNATIONAL COMPETITIVE PROCEDURES .....................................................ERROR! BOOKMARK NOT DEFINED.
ADMINISTRATION OF GOVERNMENT CONTRACTS ................................................................................ 44
GENERAL APPROACH TO CONTRACT INTERPRETATION ....................................ERROR! BOOKMARK NOT DEFINED.
CONTRACTORS’ RIGHTS ....................................................................................................................................................... 44
Delay ........................................................................................................................................................................................... 44
Changes and Modifications .............................................................................................................................................. 45
GOVERNMENT PREROGATIVES ........................................................................................................................................... 47
Termination for Convenience of the Government.................................................................................................. 47
Inspection/Acceptance....................................................................................................................................................... 48
Default Termination............................................................................................................................................................ 49
APPENDIX I – ANSWERS TO CASE QUESTIONS ......................................................................................... 51
MOTOR COACH INDUSTRIES ................................................................................................................................................ 51
FORMAN .................................................................................................................................................................................. 54
TINGEY .................................................................................................................................................................................... 56
CORLISS................................................................................................................................................................................... 58
BOWSHER ............................................................................................................................................................................... 59
AMERON ................................................................................................................................................................................. 61
34 COMP. GEN. 239 (1954) (TIME ISSUE) ..................................................................................................................... 63
35 COMP. GEN. 319 (1955) .............................................................................................................................................. 64
42 COMP. GEN. 226 (1962) (PURPOSE ISSUE).............................................................................................................. 66
SOLAR...................................................................................................................................................................................... 67
GOODYEAR TIRE .................................................................................................................................................................... 69
C.H. LEAVELL......................................................................................................................................................................... 71
G.L. CHRISTIAN ..................................................................................................................................................................... 73
GORDON WOODROFFE ......................................................................................................................................................... 75
2 GOVERNMENT CONTRACTS OUTLINE
Basic Considerations for Government Contracts
Overview
-
-
-
-
-
-
There are two main areas in government contracts law:
o The performance of the contract
o The formation of the contract
There are two main types of government contracts:
o Military procurement (covered by ASPA and the FAR)
o All other procurements (covered by FPASA and the FAR)
ASPA
o Applies to procurement (acquiring); this means that selling and regulating
are not covered by the statute.
o The language “for its use or otherwise” was added to prevent agencies from
tying to evade the statute by buying for another agency.
FPASA
o This statute is broader than ASPA by using the language “purchases and
contracts” as opposed to “procurement.”
o It does not apply to the agencies listed in ASPA.
o It only applies to executive agencies, which leaves a gap for non-executive,
non-military agencies (i.e. judicial agencies).
Contract formation disputes:
o Also called bid protests.
o Brought by a disappointed bidder against the government agency and the
winning bidder.
o The losing bidder usually argues that the proper procedures were not
followed or that they had a lower bid yet were not chosen.
o Motor Coach: a government agency cannot attempt to create an “alter ego”
with public funds to try to circumvent procurement procedures.
o Bid protests are handled by the GAO and the Comptroller General.
 There is an automatic stay on the execution of the contract while an
investigation is done.
 The agency can override the stay.
 The Comptroller General issues a very convincing recommendation.
Contract performance disputes:
o Brought by the contractor usually against the government.
o When a contractor has a claim:
 It files it with the contracting officer,
 There is a choice between two forums to appeal the contracting
officer’s decision:
 The appropriate board of contract appeals (“BCA”),
 The Court of Federal Claims (“CoFC”)
 The appellate decision can then be appealed to the Federal Circuit,
which can then be appealed to the Supreme Court.
o The government cannot appeal if the contracting officer finds for the
contractor.
GOVERNMENT CONTRACTS OUTLINE 3
-
o Forman:
 Leases are covered under FPASA even though acquisition of real
property is excluded. It is unsure if this is the majority view.
 The purpose of the contract does not create a restrictive covenant
absent the required language, so the USPS was no in breach of the
agreement.
Doctrinal and Interpretive Approaches
o Congruence: When the government enters into a contract, its rights and
duties are governed generally by the law applicable to contracts between
private individuals.
o Exceptionalism: Because of its sovereign status, unique functions, and special
responsibilities, the government as a contracting party is not subject to all of
the legal obligations and liabilities of private contracting parties.
 This shields the government from liabilities that would apply to
private contracting parties and gives it power that private contracting
parties would lack.
 It arises mostly in performances issues (i.e. the government is allowed
to technically be in breach).
o Reverse Exceptionalism: The government as a contracting party bears duties
that private contractors do not bear.
 This arises mostly in contract formation disputes (i.e. the government
has certain mandatory procurement procedures that private
contracting parties do not have).
The Power to Contract
-
-
Tingey:
o The government has inherent constitutional authority, as well as implied
statutory authority, to enter into contracts.
o Specific government agencies can enter into contracts that are necessary and
proper to the functions and operations of the agency.
o The government cannot enter into a contract that is not consensual or
authorized by statute.
Corliss:
o The government and its agencies have inherent authority to suspend or
terminate contracts.
o They also have the power to enter into settlement agreements that are
binding on the government.
Appropriations and the Anti-Deficiency Act
-
The appropriations clause of the constitution states that no money can be drawn
from the treasury without appropriations from Congress.
This means that the government can enter into contracts before receiving
appropriations but cannot pay.
However, if the government enters into a contract but cannot pay, it is in breach and
must pay damages likely equal to the amount under the contract.
4 GOVERNMENT CONTRACTS OUTLINE
-
-
-
-
-
o To avoid this contradictory result, the Judgment Fund was created to pay
damages resulting from breach due to lack of appropriations.
o There is some question as to the constitutionality of the Judgment Fund, but
no one has standing to challenge it.
o The government also includes a “funds availability clause,” which says that
the government isn’t liable if it doesn’t get appropriations to pay for the
contract.
The Anti-Deficiency Act makes it a crime to contract for something before
appropriations have been made or to authorize an expenditure that exceeds the
amount appropriated.
o In practice, this is very difficult to abide by because appropriations are made
yearly whereas contracts often last several years.
o However, the threat is scary.
Bowsher: The GAO and Comptroller General are agents of Congress.
Ameron: The GAO and Comptroller General do not violate separation of powers by
executing powers given to them under CICA.
The general rule is that appropriations must be available on three levels:
o Time
o Purpose
o Amount
34 Comp. Gen 239: In order to be able to use the lapsed funds, you need:
o A valid binding contract executed during the funds’ appropriated fiscal year,
o Termination of the original contract due to the contractor’s default,
o A new contract to complete the work from the original contract, and
o The need continued to exist up to the time of the execution of the new
contract (and the need existed in the first place).
35 Comp. Gen 319:
o In order for the contractors bid to be an offer and the signature by the
contracting officer an acceptance, the following factors must be present
 Each bid must have been in writing,
 The acceptance of each bid must have been communicated to the
bidder in the same manner as the bid was made, and
 Each contract must have incorporated the terms and conditions of the
respective bid without qualification. Otherwise, it is a counteroffer.
o The general rule for legally obligating a fiscal year appropriation is that the
supplies or services are required to serve a bona fide need of the fiscal year
in which the need arises. Ordinarily where a contract is entered into during
one fiscal year and the services contracted for are not performed or required
until the following fiscal year, the appropriation current at the time the
services are rendered is properly chargeable to the cost.
42 Comp. Gen. 226: The general rule is that an express statutory provision is not
required for every item of expenditure, but an appropriation in general terms for a
particular purpose is available for expenditures necessary to accomplish that
purpose, except as to expenditures in contravention of statute or for which other
appropriations are more specifically available.
GOVERNMENT CONTRACTS OUTLINE 5
-
-
-
-
-
-
Solar: This was a requirements contract, not a multiyear contract, and there was no
termination for convenience. Because there was no termination for convenience, the
contractor was not entitled to an equitable adjustment.
Goodyear Tire:
o This case represents extreme exceptionalism.
o In order for a multi-year lease to be binding on the government, the
government has to affirmatively continue the lease for that year that an
available appropriation has been made (i.e. to make a new lease for the year
under the authority of such appropriation).
 This idea would probably be overruled today.
o The holdover doctrine (under Ohio law) is an implied in law contract.
Therefore, there is no right of action under the Tucker Act.
 This part is still good law.
C.H. Leavell:
o A funds available clause only insulates the government from liability for
breach, not from an equitable adjustment.
o The test for the availability of an equitable adjustment under this suspension
of work clause is:
 The suspension cannot be the fault (or due to the negligence) of the
contractor,
 The suspension must be for an unreasonable period of time,
 The suspension must be due to an act, or failure to act, of the
contracting officer, and
 The performance of the contractor must not have been prevented by
other causes, even without the suspension.
o The government cannot use the excuse that the contractor worked too fast,
causing the funds to be exhausted, because the contracting officer had
approved the schedule.
G.L. Christian: Where valid procurement regulations mandate inclusion of particular
standardized clauses in government contracts, those clauses are to be read into
contracts to which they are factually applicable where they have been omitted by
mistake.
Force and Effect Principle: When specified conditions are met, agency regulations
can be treated as the equivalent of a statute and are binding on private parties
affected by its terms.
Accardi Doctrine: Agencies must follow their own regulations; when they fail to do
so, the resulting agency action may be set aside under the Administrative Procedure
Act.
Authority of Agents
-
Types of Authority:
o Actual: Actual authority (either express or implied) gives the agent power to
bind the government.
 Express: delegated orally or in writing
6 GOVERNMENT CONTRACTS OUTLINE
Implied: delegated by conduct; one instance of conduct does not
necessarily delegate authority. Course of dealings evidence is of low
probative value on this issue.
o Apparent: The actions or statements of the principal cause a third party to
reasonably believe that authority has been conferred on the agent, whether
or not the principal actually intended to confer such authority.
 Apparent authority is a way to estop the defendant from arguing that
the contract is invalid because the agent did not have authority to
bind the defendant.
 Apparent authority cannot bind the government.
The doctrine of ratification: If someone without authority contracts on behalf of the
government, someone with authority to contract must ratify that decision in order
for it to be binding.
o Individual ratification: When an authorized contracting officer expresses a
definite opinion concerning the merits of a claim with knowledge of the
relevant facts, the contracting officer ratified the contract. (General Electric;
Note: Schwartz believes this rationale is false because the contractor didn’t
even know that the contracting officer “ratified” the contract, and the
contracting officer didn’t intent to ratify the contract.)
o Implied ratification: This occurs when the government seeks the benefits of
an otherwise unauthorized contract while the officials with ratifying
authority know of the promise. (Williams; Note: Schwartz thinks that this
case crosses the line and is probably incorrect, but it shows that courts are
always looking for ways to get around the inability to use apparent authority
against the government when it would be unfair to do so.)
The FAR
o FAR: Federal Acquisition Regulation.
o FAR System: the FAR itself, together with the agency-specific supplemental
regulations that implement the FAR, which are themselves authorized under
the terms of the FAR.
o The FAR requires publication in the Federal Register of an invitation to
submit comments on pending regulatory proposals, and consideration of
comments received.
o The procedural requirements have not been the subject of significant
litigation.
§ 1.601 of the FAR details contracting authority:
o Authority and responsibility to contract rests with the agency head.
o Contracts may be entered into and signed on behalf of the government only
by contracting officers. (Look for the proper name, i.e., not “contracting
specialist.”)
o In some agencies, a relatively small number of high level officials are
designated contracting officers solely by virtue of their positions.
Gordon Woodroffe: The doctrine of apparent authority is inapplicable in
government contracts disputes. This is a bit of an extension of the holding in Merrill
that the government cannot be estopped.

-
-
-
-
GOVERNMENT CONTRACTS OUTLINE 7
-
-
-
-
-
-
It is important to remember that the authority to contract is not just relevant in the
making of the contract, but also in the modification or termination of the contract. A
contracting officer is still the only one who can do that.
General Electric: When an authorized contracting officer expresses a definite
opinion concerning the merits of a claim with knowledge of the relevant facts, the
contracting officer ratified the contract.
Williams Equipment: The contracting officer knew about the paving work being
done and, by his inaction, ratified the contract. Therefore, despite the fact that the
agent did not have the authority to enter into a binding agreement, the government
is bound.
Equitable Estoppel and Its Application Against the Government:
o Equitable estoppel prohibits a party from disavowing a representation it has
made, where an opposing party has justifiably and foreseeably relied on that
statement, and where to allow the change of position would redound unfairly
to the detriment of the other party.
o The party is barred from raising an otherwise valid legal defense or claim or
asserting a truthful version of the facts because to do so would be unfair to
the other party in light of the first party’s earlier conduct or statements.
o The doctrine of apparent authority is arguable an application of the doctrine
of equitable estoppel.
o In transactions involving federal agencies, there is great potential for agents
to make representations that are inconsistent with applicable statutes or
regulations.
o The government is immune from equitable estoppel.
 Merrill: the government cannot be estopped.
 There is a duty of those who do business with the government to turn
square corners.
 Some cases, however, held open the possibility that estoppel might be
applied against the government in a case of what was described as
“affirmative misconduct.”
 The Supreme Court has deliberately neglected to close the door to
equitable estoppel.
Richmond: There are four different holdings in this case:
o The government cannot be estopped when the private party is seeking
payment that is prohibited by an appropriations statute. (Strongest
argument, narrowest holding)
o The government cannot be estopped when the private party is seeking
payment that is prohibited by a statute.
o The government cannot be estopped when the private party is seeking
payment that is prohibited by law (i.e. statutes and regulations).
o The government cannot be estopped when the private party is seeking
payment at all, regardless of whether or not payment is in violation of a
statute or regulation. (Weakest argument, broadest holding)
How to recognize an equitable estoppel case:
o There is either a factual or legal reason that the government should win, i.e.,
they are correct.
8 GOVERNMENT CONTRACTS OUTLINE
-
-
o The private party argues that it would be unfair for either the government to
profit or for the private party to suffer because of the government’s actions.
o Do not confuse an estoppel argument with a finality argument:
 A finality case is one in which the government clearly should not win
but rather just wants to undue a valid decision that it regrets.
 For example, in Broad Ave. Laundry, the government argued that it
should not be bound by its own adjustment to the contract that was
not required because the contracting officer (with contracting
authority) mistakenly believed that the adjustment was required by
law.
 The adjustment was not prohibited by regulation, so the government
cannot “undue” a valid contracting decision.
Proper analysis for an equitable estoppel question:
o Do we really have an equitable estoppel case? (Don’t believe labels.)
o Does an appropriations statute prohibit payment (Richmond)?
 If yes, there is no recovery.
 If no…
 Would payment be in violation of a statute? If yes, there is a
strong argument against payment.
 Would payment be in violation of a regulation? If yes, there is a
slightly strong argument against payment, but it is getting
weaker.
 Is the private party asking for money and payment is not in
violation of any law? If yes, there is a relatively weak argument
against payment.
o Was there “affirmative misconduct” on the part of the government?
 Note: This is very difficult to prove, as case law suggests that mere
negligence on the part of a government employee is not “affirmative
misconduct.” It would probably have to be some kind of purposeful
misconduct.
 If yes, there may be recovery.
 If not, there is no recovery.
o The government almost always wins estoppel cases.
Schwartz’s argument for when relief should be given:
o If the agency has any authority under the pertinent statutes and regulations
to waive the requirements that the agency is seeking to enforce,
o The claimant made a timely request for such a waiver to the government
agency involved, and
o The refusal of the waiver was an abuse of discretion that may be overturned
on judicial review under the Administrative Procedure Act.
GOVERNMENT CONTRACTS OUTLINE 9
Aspects and Consequences of Sovereignty
The Federal Government’s Authority to Change its Contracts
- The Sovereign Acts Doctrine (“SAD”): the government is not liable for breach of
contract when its “public and general” acts as a sovereign have the effect of violating
contracts that it has entered into with private parties.
o Ex: a regulatory rail embargo that prevents that government from
performing an undertaking to ship goods to a contracting partner.
o The rationale is that the government’s contracts do not include a warranty
that performance will not be obstructed or burdened by the regulatory and
other uniquely sovereign actions of the government.
o This is comparable to the impossibility doctrine in private contracts, but that
doctrine is not applicable when the impossibility is the fault of the party
invoking the doctrine.
o Similarly, the SAD does not apply whenever a significant consequence of the
governmental action is to free the government from its own contractual
undertakings. (Winstar)
- The Unmistakability Doctrine (“UMD”): Contracts to which a governmental entity is
a party should not be interpreted to immunize the government’s contracting partner
from subsequent exercises that authority against the contracting partner in
“unmistakable terms.”
- Winstar:
o Contract Interpretation
 Scalia, Kennedy, Thomas, Rehnquist, Ginsburg (5): The UMD cannot
be avoided by re-characterizing a contract that promises a particular
course of regulatory treatment as though it promised indemnification
in the event of a change in the law.
 Souter, Stevens, O’Connor, Breyer (4): A promise respecting
regulatory treatment (to insulate thrifts from changes in regulation)
should be understood as a promise to indemnify thrifts, not literally as
a promise of immunity from regulatory changes.
o Unmistakability Doctrine
 Scalia, Kennedy, Thomas, Rehnquist, Ginsburg (5): The UMD applies to
all government contracts.
 Scalia, Kennedy, Thomas (3): There is a common sense
presumption in the UMD – the government will rarely promise
to a contractor that it will be exempt from future changes in
the law, so courts should hesitate to read a government
contract to make that kind of promise. Such a promise should
be found only if the contract is clear. However, the contract
only need be reasonable clear in this respect. If the contract
explicitly promises a contractor that it will have the benefit of a
particular course of regulatory treatment, it need not contain a
second promise that the contractor will continue to receive the
promised regulatory treatment even if the law applicable to
other people changes.
10 GOVERNMENT CONTRACTS OUTLINE

-
Rehnquist, Ginsburg (2): The UMD creates a very strong
presumption against finding a promise to the contractor of
indemnification if there is a change in the law.
 Souter, Stevens, O’Connor, Breyer (4): The UMD is inapplicable in this
case. It applies most strongly to contracts directly about the exercise
of a sovereign power. This principle applies not at all to routine
supply contracts. (Note: Schwartz says this idea is irreconcilable with
Bowen v. Public Agencies.)
 Souter, Stevens, O’Connor (3): When the UMD does apply, it
creates a very strong presumption against finding such a
promise, as opposed to a common sense presumption.
 Breyer (1): Congruence should be used in interpreting and
enforcing government contracts. The government made a
promise to indemnify its contracting partners if the law was
changed to their detriment.
o Sovereign Acts Doctrine
 Souter, Stevens, Breyer (3): Only if releasing the government from its
own contractual obligations is an incidental effect of a much more
widely applicable change in the law can the new law be considered a
“public and general act.” If a “substantial effect” of the change in the
law is to allow the government to avoid its own contract obligations,
the change is not a public and general sovereign act, and the SAD is
not applicable.
 Scalia, Kennedy, Thomas (3): The SAD should add little to the effect of
the UMD.
 Rehnquist (1): The SAD and UMD should be integrated into a single,
consistent doctrine.
 O’Connor, Ginsburg (2): No comment on this issue.
Mobile Oil:
State Disabilities Under the Contract Clause
- Contract Clause: The Contract Clause of the Constitution prohibits the states from
enacting any law that retroactively impairs a contractual obligation.
- Reserved Power Doctrine: The Contract Clause does not require a State to adhere to
a contract that surrenders an essential attribute of its sovereignty. Such a contract is
void. Typically, courts find that purely financial contracts do not violate the
Reserved Powers Doctrine, although this could technically be considered a
surrender of spending power.
- U.S. Trust Company: The repeal of the covenant was in violation of the Contracts
Clause because the public problem (the increase in commuter traffic) was foreseen
and acknowledged at the time the legislature enacted the covenant, and the
legislature could have modified the covenant to achieve its goal.
- Proper analysis to determine if a state regulation is in violation of the Contracts
Clause:
GOVERNMENT CONTRACTS OUTLINE 11
o First, you must determine whether a state regulation has impaired a
contractual obligation. If not, there is no violation of the Contract Clause and
the analysis can end here.
 The Contracts Clause does not apply to the federal government (only
to states).
 This only applies to legislation, not to judicial decisions.
 Impairment does not necessarily mean damages (i.e. you can sue
before you suffer damages). The regulation mist significantly impair
the obligation.
o Second, you must determine whether the contract is void because of the
Reserved Powers Doctrine because it surrenders an essential attribute of
state sovereignty (such as state police power or eminent domain).
Essentially, the question is, Did the state have the ability to promise what it
promised? If the contract violates the Reserved Powers Doctrine, the analysis
can end here.
o Third, you must determine whether that impairment violates the Contract
Clause. In order for a state regulation that impairs a contractual obligation
not to be a violation of the Contract Clause:
 It must have a significant and legitimate public purpose behind it,
such as the remedying of a broad and general social or economic
problem; and
 The regulation must be:
 If the regulation modifies private contracts, reasonable and
appropriate for its intended purpose; or
 If the regulation modifies public contracts, reasonable and
necessary. This is a less deferential standard because the
government is modifying its own contracts.
o Necessary: Was there a less drastic alternative method
of remedying the public problem? If so, the regulation
was not likely necessary.
o Reasonable: Was the public problem anticipated or
foreseeable? If so, the regulation is probably not
reasonable in light of the circumstances.
o If the government loses at the second step (the Reserved Powers Doctrine), it
is likely that the government will lose at the third step as well because it is
easy to think, in hindsight, of less restrictive means of remedying the public
problem.
Choice of Law in the Field of Federal Procurement
- Relevant Statutes:
o 28 U.S.C. § 1345: The district courts have original jurisdiction of all actions
commenced by the United States.
o 28 U.S.C. § 1652 (Rules of Decision Act): State law can apply in federal courts
(i.e. Erie Doctrine).
- Sometimes federal law may consist of “borrowing” state law when there is no
applicable statute or when it is otherwise appropriate.
12 GOVERNMENT CONTRACTS OUTLINE
-
-
-
-
The basic strategy of the federal government is to leave no gaps that could be filled
by state law. The Christian Doctrine helps this strategy because government
contracts do not even have to incorporate all of the FAR’s provisions – they are read
in.
Clearfield Trust: Federal law applies to all government contracts cases.
Kimbell Foods: Federal courts must consider three factors when determining
whether to borrow from state law in government contracts cases in which there is
no applicable federal law: the need for uniformity in this type of case; the potential
frustration of federal program objectives; and the potential disruption of
commercial relationships predicated on state law.
American Pipe: When a dispute between a prime and sub contractor arises out of a
subcontract dealing with national security, federal law is applied due to the
overwhelming need for uniformity. (Note: Schwartz thinks that this case is
incorrect. It was a private contract between two private parties. The dispute arose
in no way out of the actions of the government. Therefore, state law, not federal law,
should have been applied.)
Federal law is not, in fact, uniformly applied to govern subcontracts, even when the
cases are heard in federal court; it would be hard to square doing so with Erie.
Sometimes, issues need to be decided under federal law even if the dispute is
between private parties (the definition of “adjustment”).
Even if state law is controlling, the state can borrow federal doctrine. (Linan-Faye
Construction Co,)
Proper analysis for what type of federal law should be applied in government
contracts cases:
o If this is a government contracts case, federal law must be applied. Be careful
when the case involves a dispute between two private parties (a general and
a subcontractor). There are two arms of analysis:
 The dispute is a private contracts dispute, so state law applies;
 The dispute is private but deals with issues so intertwined with
government contracts law that there is a need for uniformity and
federal law should be applied (i.e. in national security).
o That law must first come from the constitution or a statute.
o If there is a gap (unlikely because of how comprehensive the FAR is), the
courts can either borrow state law or apply federal common law. The most
common result is the applicable of federal common law. The following test
must be applied to determine which law should be used:
 Is there a strong need for uniformity in cases such as this? If so, state
law may not be used. However, there may be a case in which the state
law is uniform (for example, almost all states have adopted the UCC),
and therefore state law may be more appropriate.
 Will borrowing state law frustrate the specific objectives of the federal
programs? If so, state law may not be used. If the agency’s own
regulations incorporate state law in the administration of the program
at issue, this indicates that objectives will not be frustrated and that
state law may be used.
GOVERNMENT CONTRACTS OUTLINE 13


Will the use of a federal law disrupt commercial relationships
predicated on state law? If so, state law may be more appropriate.
Will the borrowing of state law result in discrimination against the
federal government? If so, state law is inappropriate.
The Government Contractor Defense
- The Federal Tort Claims Act (FTCA): Waiver of sovereign immunity for tort claims.
o The district courts have exclusive jurisdiction of civil actions on claims
against the United States.
o Exemptions in the FTCA:
 Discretionary Function Exception: There is no liability
 Based on an act or omission of an employee exercising due
care in the execution of a statute or regulation, or
 Based on the exercise or performance or failure to exercise or
perform a discretionary function or duty on the part of a
federal agency of an employee of the government, whether or
not the discretion is abused.
 Note: The government can only be sued under tort law for an
injury caused by the government’s failure to perform a
ministerial action.
 Combatant Activities Exception: The government is not liable for any
claim arising out of the combatant activities of the military during
time of war.
 Foreign Country Exception: The government is not liable for any claim
arising in a foreign country.
o Exceptions Created by the Court or Congress:
 The Feres doctrine: Service members cannot sue the government for
injuries suffered in the course of military service. This doctrine
creates a very strong incentive for injured service members to sue
government contractors.
 The Safety Act: A defense to tort liability for manufactures (who may
or may not be government contractors) of equipment certified as
“qualified antiterrorism technology.”
- Boyle: Allowing private litigants to hold government contractors liable for certain
torts would just result in the increase in price of government contracts, which would
frustrate the purpose of the discretionary function exception.
- The holding in Boyle does not apply to “off the shelf” products.
- It is unknown whether the Boyle holding applies to service contracts; however,
Schwartz believes that it should apply if the three factors are satisfied. It is possible,
but less likely.
- Boyle applies in both civil and military procurement cases.
- Bailey: It does not matter if a claim is labeled as a manufacturing defect or as a
design defect. If the three factors of Boyle are satisfied, the government contractor
defense applies.
- The proper analysis: Liability for design defects in military equipment cannot be
imposed on the supplier pursuant to state law when:
14 GOVERNMENT CONTRACTS OUTLINE
o The government approved reasonably precise specifications, whether the
specifications were created by the contractor or the government;
o The equipment conformed to those specifications; and
o The supplier warned the government about the dangers in the use of the
equipment that were known to the supplier but not to the government.
o Note: The requirements of reasonably precise specifications and conformity
with them refer to the particular feature of the product claimed to be
defective, not to the product as a whole (i.e. the feature in dispute).
Qualified Immunity for Government Contractors - Richardson
- Qualified Immunity: state or local employees subject to a constitutional tort claim
under 42 U.S.C. § 1983 (and federal employees subject to a Bivens claim) are
immune from liability unless their actions violate a constitutional right of the
plaintiff that was clearly established at the time of the action.
- In Richardson v. McKnight, the Supreme Court held that prison guards employed by
a private firm that had contracted with the state to manage a Tennessee prison are
not entitled to a qualified immunity defense against a constitutional tort claim
brought against them by prisoners under 42 U.S.C. § 1983.
- Majority Opinion:
o It doesn’t matter that the worker is performing a function that is identical to
that of state employees.
o There are significant differences between the incentives and pressure that
face contractors and their employees and those facing governmental
agencies and employees that suggest that qualified immunity for contractors’
employees is not warranted.
o Privatization permits the private firm to offset any increased employee
liability risk with higher pay or extra benefits.
o The analysis and holding of the case are specific to this situation: one in
which a private firm, systematically organized to assume a major length
administrative task (managing an institution) and with limited direct
supervision by the government, undertakes that task for profit and
potentially in competition with other firms.
o The court did not address the possibility of a “good faith” defense.
- The Dissent:
o Immunity is normally determined by function, not status.
o There are no real market pressures for private prisons. The choice is made
by politicians with taxpayer money. Therefore, the incentives faced by the
contractor and the government are the same.
o Cost is the predominate factor in the government’s selection of a contractor
for prisons, not quality. A contractor’s price depends on its costs. Lawsuits
increase costs.
o The more cautious the prison guards, the fewer the lawsuits, the higher the
profits.
o The majority is using the economic benefits of prison out-sourcing as a
justification for a legal rule that will make out-sourcing more expensive.
GOVERNMENT CONTRACTS OUTLINE 15
-
-
o The distinctions between private contractor employees and public
employees can be incredibly arbitrary.
o The only effect of this decision is that it will artificially raise the cost of
privatizing prisons.
It would not be surprising if contractors’ employees are ultimately held to have
some kind of qualified immunity in this situation.
The court might reach a different conclusion on the immunity issue as to
contractors’ employees carrying out a different public function.
This case does not address the availability of qualified immunity to employees of
contractors performing functions for the federal government.
o Qualified immunity of state and local government employees when they are
sued under 42 U.S.C. § 1982 has generally been defined in the same terms
and with the same limits as the immunity of federal employees sued in
Bivens actions.
o The result will likely be the same.
o However, there is a distinction between the liability of federal and state or
local contractors:
 Liability of state and local government officials and employees for
constitutional torts arises under 42 U.S.C. § 1983.
 Liability of federal government officials and employees for
constitutional torts arises under Bivens, which is a court-made
doctrine.
Correctional Services Corp. v. Malesko: a Bivens action may not be brought against
corporate federal contractors.
o This case does not address the question of whether a Bivens action may be
maintained against individual employees of a contractor that are alleged to
have violated an individuals constitutional rights.
o Suing the individual is less attractive than suing the corporation for
monetary reasons.
o However, even if individuals and corporations cannot be sued in a Bivens
action, they can certainly be sued for common law torts.
o However, when common law tort claims are brought against governmental
officials and employees, they enjoy the protection of another type of
immunity. It is not clear whether this immunity from common law claims
applies to government contractors.
 Barr v. Mateo: Federal officials are absolutely immune from suit for
common law torts allegedly committed while performing their official
responsibilities even while performing discretionary acts. Only
qualified immunity is available on claims of constitutional torts.
 Westfall v. Erwin: Only qualified immunity should be available with
respect to common law tort claims entailing nondiscretionary acts.
 FTCA Amendment in 1988: Federal employees acting within the scope
of their office or employment are absolutely immune from being sued
for common law torts. This most definitely does not extend to
government contractors.
16 GOVERNMENT CONTRACTS OUTLINE
-
o To determine whether this type of immunity would apply to government
contractors, the court will likely use an analysis similar to that employed in
Richardson (i.e. a policy analysis).
Proper Qualified Immunity Analysis:
o Is this a constitutional tort?
 Is the defendant a state contractor?
 The cause of action arises under 42 U.S.C. 1983.
 There is probably no qualified immunity defense, as in
Richardson.
 The analysis and holding of the case are specific to this
situation: one in which a private firm, systematically organized
to assume a major length administrative task (managing an
institution) and with limited direct supervision by the
government, undertakes that task for profit and potentially in
competition with other firms.
 There might be a “good faith” defense.
 There could be an argument to distinguish the case from
Richardson and, if the factors are met, to see if the Boyle test
would apply.
 Is the defendant a federal contractor?
 The cause of action arises under Bivens.
 According to Malesko, Bivens does not extend to federal
government contractors. So there is no cause of action.
 If Bivens did apply, and therefore if the contractor could be
sued, it is unclear if the qualified immunity defense would
extend to government contractors.
o Is this a common law tort?
 Is the defendant a state contractor?
 The claims and defenses are controlled by state law.
 Is the defendant a government contractor?
 Regardless of the type of contract or claim, the Boyle test
applies. If the factors are satisfied, then the government
contractor has a defense.
 If the Boyle test is not satisfied, there is a chance that the
contractor could try to use the defense for government
employees under Barr v. Mateo and Westfall v. Erwin.
However, the court has not addressed whether these extend to
government contractors, so it might be a long shot.
Federal-State Relations
Federal Contractors’ Immunity from State and Local Taxation
- The states may not tax the federal government. (McCulloch v. Maryland)
- Government contractors may have immunity from state taxation if they can show
that the tax levied on the government contractor is actually a tax levied on the
government.
GOVERNMENT CONTRACTS OUTLINE 17
-
Alabama v. King & Boozer:
o The mere fact that the increase in price to the contractor will be transferred
to the government via an increased cost is not enough to make the
government the “purchaser” on whom the tax is levied. This is a rejection of
the economic incidence test.
o In order to be immune from taxation under state law, the contractor must
have been an agent of the government, capable of binding the government to
purchases. This is a legal incidence test.
o To determine if the contractor was an agent of the government, the court
looks at the wording of the contract regarding the passing of title of the
purchases or any parts that discuss whether a contractor could have bound
the government by making a purchase.
 For example, the title of the lumber didn’t pass to the government
until after the lumber was inspected and accepted by the government
(not when the contractor purchased the lumber). The contractor
purchased the lumber and was reimbursed by the government after
the government determined that the lumber was satisfactory.
 The contract expressly stated that the government was not bound by
the purchases of the contractor until after the government accepted
the materials.
Federal Contractors’ Immunity from State Regulation (Paul v. United States)
- Federal government contractors are not invariably immune from regulation by state
agencies or state statutes.
- Federal government contractors are only immune from regulations if the particular
state regulation, if applied to federal contractors, would frustrate federal policies
about procurement.
- Minimum price regulation is one of the only forms of regulation that would be so
directly passed through to affect the federal government.
- If you regulate the minimum price that a contractor can charge, you are necessarily
regulating the price that the federal government will have to pay, and eliminating
the possibility of competition, which federal policy requires the federal government
to seek.
- In other words, if the effect of regulating the contractor is to regulate the federal
government, the contractor is immune from the regulation.
The False Claims Act and Qui Tam Suits Against Contractors
-
The False Claims Act (“FCA”), 31 U.S.C. § 3279, makes it illegal for a person to
knowingly present a false claim for payment to the United States, or to knowingly
present a false record in support of a claim for payment.
o The falsity may pertain either to the claim/work itself or to the supporting
material. (If you claim that you have tested a product but actually have not,
that is a violation even if the product is fine.)
o A government contractor may be liable for certifying that its subcontractor
did something that it actually didn’t.
18 GOVERNMENT CONTRACTS OUTLINE
-
o The penalties are: a penalty sum ($5,000-$10,000) and treble actual
damages.
o The FCA provides civil remedies for fraud against the government.
o An action may be filed by the Attorney General or by a private party with
knowledge of the facts that give rise to a violation (known as the “relator”).
o The relator may file an action in the name of the United States (“United States
ex rel. “Relator” v. “Defendant”). This is called a qui tam action.
 The government can take the suit over and then either dismiss it,
settle it, or litigate it.
 The government can choose not to do anything with the suit and just
let the private litigant litigate the suit. The government is then able to
intervene at a later time for good cause. The government can also ask
the court to limit the participation of the relator.
o A criminal conviction or a plea of nolo contender to a criminal charge
precludes the defendant from relitigating facts that were established by the
criminal conviction.
o If the government settles a qui tam action initially brought by a relator, the
relator can not litigate the claim.
o A person can be tried criminally and civilly without a double jeopardy issue,
after Harper was overruled.
U.S. ex rel. Kelly v. Boeing: affirmed the constitutionality of the qui tam provisions of
the FCA:
o Standing: The injury in fact test is satisfied because the injury is that of the
government, not of the qui tam plaintiff. The government only assigns its
claims to qui tam plaintiffs. The qui tam provisions operate as an enforceable
unilateral contract, accepted by the relator upon filing suit. (Note: This view
has been endorsed by the Supreme Court.)
o Separation of Powers: There is no absolute rule that only the executive
branch may prosecute. In addition, the FCA permits a degree of executive
control that satisfies the Morrison standard. If the government intervenes, it
takes over the case. If the government does not intervene, it can intervene at
a later time for good cause or ask the court to limit the participation of the
relator. The fact that the judiciary decides if the government has good cause
to intervene does not run afoul of separation of powers. (Note: So far, there is
no conflict among the Courts of Appeals on this issue.)
o Appointments Clause: The relator only has power over one claim, not over
multiple prosecutions, and thus doesn’t need to be appointed.
o Due Process Clause: It doesn’t matter that the relator has a financial incentive
to prosecute. The interest of the relator is the same as the interest of the
public.
Criminal Prosecution
-
18 U.S.C. § 287: Criminal provisions of the False Claims Act. Fines of up to one
million dollars may be imposed in Defense Department procurement false claims.
18 U.S.C. § 1001: False Statements Act. It is illegal to make a false statement or to
conceal a material fact in a statement in any matter within the jurisdiction of any
GOVERNMENT CONTRACTS OUTLINE 19
-
department or agency of the federal government (i.e. false certifications
accompanying claims, and false statements with regard to compliance with
specifications).
18 U.S.C. § 201(b): Bribery both of and by public officials.
18 U.S.C. § 371: Conspiracy to commit an offense or to defraud the United States.
18 U.S.C. § 641: Conversion and embezzlement of money or property of the United
States. (United States v. Matzkin)
18 U.S.C § 1341: Mail fraud.
18 U.S.C. § 1343: Wire fraud. These two statutes (§§ 1341, 1343) provide a device
for prosecution of government officials for fraud in procurement.
United States v. Matzkin: Bid information in sealed bidding is both property of the
government and a thing of value for the purposes of 18 U.S.C. § 641. The
government does not need to have a sole interest in the property or to have sole
knowledge of the information in order for there to be a violation of § 641.
Free Speech Rights of Government Contractors
-
-
-
General Rule: Government contractors can be terminated for a good reason or for no
reason, but not for a bad reason. (Umbehr)
Government contractors are protected by the First Amendment and the Pickering
balancing test applies.
The First Amendment rights of government employees and contractors depend on
the balance between the interests of the employee as a citizen in commenting on
matters of public concern and the interests of the government as an employer in
promoting efficiency of public services it performs through its employees.
o The contractor must show that the termination of his contract was motivated
by his speech on a matter of public concern.
o If he can make that showing, the government will have a valid defense if
 It can show, by a preponderance of the evidence, that, in light of their
knowledge, perceptions, and policies at the time of termination, the
government would have terminated the contract regardless of his
speech; or
 It can show that the government’s legitimate interests as contractor,
deferentially viewed, outweigh the free speech interests at stake.
o If the contractor prevails, evidence that the government members discovered
facts after termination that would have led to a later termination anyway,
and evidence of mitigation of his loss by means of subsequent contracts,
would be relevant in assessing what remedy is appropriate.
The dissent in Umbehr believes that:
o This application of the Pickering test will lead to an influx of litigation.
o There are already enough statutes and regulations in public procurement
that control this issue.
o Political favoritism often happens, and sometimes should happen.
o Employees deserve more protection that contractors because the contractors
are often rich corporations.
This is an issue that has not come up a lot in public procurement.
20 GOVERNMENT CONTRACTS OUTLINE
-
Recall that while in Umbehr, government contractors are given the same protections
as government employees, in Richardson v. McKnight, contractors are not given the
same immunities as government employees.
Protests, Claims, and Disputes
Contract Award Controversies (Bid Protests)
Summary of the current process for bid protests:
The losing bidder files a bid protest with:
The Agency (optional, and
sometimes not allowed by the agency)
Appeal to (two choices):
The GAO
(Either go directly to the GAO or appeal agency’s
decision)
GAO will dismiss if same case is filed at CoFC
Appeal to:
The CoFC
(Either go directly to the CoFC or appeal the GAO’s decision)
Appeal to:
The Fed. Cir.
Appeal to:
The U.S. Supreme Court
GOVERNMENT CONTRACTS OUTLINE 21
-
-
-
-
Bid protest forums currently available:
o The procuring agency itself,
o The GAO,
o The Court of Federal Claims,
o Possibly the district courts, but this is very unlikely.
The GSBCA was the only forum available for bid protests regarding the procurement
of computer equipment, but this jurisdiction was abolished. The GSBCA still exists,
but not for this purpose.
The district courts used to be another open forum, but due to the expiration of a
sunset provision, Congress expressly abolished this jurisdiction. However, there is
some controversy over whether this sunset provision had its intended effect
because the Administrative Procedure Act (“APA”) actually gave the district courts
this jurisdiction, and the APA and its relevant provisions are still in effect.
Terminology:
o IFB: Invitation for bids; used in a contracting process called “sealed bidding.”
This process used to be called “advertising.”
o RFP: Request for proposal; used in a contracting process called “competitive
negotiation.”
o COC: Certificate of competency; a determination that the SBA is authorized to
make that overrides a procuring agency’s determination that a particular
small business bidder is to be disqualified on grounds of nonresponsibility.
o Responsibility: the demonstrable capacity to perform the required work.
o Responsiveness: the requirement that an offer satisfy the specification
established in the IFB.
The Bid Protest Jurisdiction of the General Accounting Office
- The jurisdiction of the GAO over bid protests was given to it in CICA. This
jurisdiction is not exclusive.
- Standing in the GAO is outlined in CICA:
o Any “interested party” may bring a bid protest in the GAO. Interested party
means any actual or prospective bidder or offeror whose direct economic
interest would be affected by the award of the contract or by the failure to
award the contract.
o A contractor doesn’t have to show that he would have won the contract but
for the alleged violation. He only has to show that he had a reasonable
possibility of winning.
o There is no injury in fact requirement because this is not an Article III court.
o Recently, the GAO has shown an inclination towards limited standing by
requiring protestors to show that they had a reasonable possibility (i.e. a
more probable than not standard) of winning.
o Parties such as labor unions or municipalities do not have standing.
- The remedies available for a bid protest in the GAO are outlined in 31 U.S.C §
3554(b)(1):
o First, there is an automatic stay of the contract in dispute,
o The GAO then issues recommendations that range from termination of the
contract to the issuance of a new solicitation, but it cannot order that the
22 GOVERNMENT CONTRACTS OUTLINE
-
-
agency do anything. In practice, these recommendations are very persuasive
because if an agency does not follow the recommendation, it must explain
why in writing. The GAO is then required to send this information to
Congress yearly. Therefore, there is the fear that if an agency does not follow
the GAO’s recommendation, it will lose funding from Congress the next year.
o The GAO can also recommend that the agency pay the protestor’s reasonable
costs of bid preparation and litigation and attorney’s fees. There is no
recovery of anticipated lost profits.
The standard of review is supposed to be deferential.
The GAO has weak fact-finding ability. (Dyneteria)
The bid protest process in the GAO:
o A party files a protest with the GAO.
o The GAO notifies the agency of the protest within one day of receiving the
protest.
o The agency must submit a complete report on the protested procurement to
the GAO within 30 days, typically:
 Express, 20 days;
 Longer if needed.
o There is an automatic stay (the agency cannot award the contract after
receipt of the notice) while the protest is pending.
o The head of the agency can override the automatic stay upon a finding of
urgent and compelling circumstances and upon notifying the GAO of that
finding.
o The GAO must make a decision within 100 days, typically:
 Express, 65 days.
Most parties choose to go to the GAO as opposed to the CoFC because it is the fastest
and because it is not a court, so the rules of preclusion do not apply (second bite at
the apple). There is also an automatic stay that is not available in the CoFC. It is also
cheaper, and easier to navigate for pro se litigants.
Award Controversies in the Court of Federal Claims Prior to 1996 and After 1996
- Jurisdiction of the CoFC prior to 1996 was given by the Tucker Act:
o Statutory branch of the Tucker Act: A person can sue the United States for a
claim founded upon the Constitution or a statute or regulation, but only those
that mandate compensation in the event of a violation (e.g. the Just
Compensation Clause).
o Contracts branch of the Tucker Act: A person can sue the United States for
breach of an express or implied-in-fact contract. There can be no recovery for
breach of an implied-in-law contract. (Heyer Products)
o Heyer Products: A bid protester may not recover lost anticipated profits, but
he may recover the expense to which he was put in preparing his bid.
 The court stretches the rules to find jurisdiction over the claim by
finding an implied-in-fact contract between the government and the
bidder. The government agreed to consider all bids fairly; it did not do
so in this case.
GOVERNMENT CONTRACTS OUTLINE 23
To recover the cost of bid preparation, it must be shown that bids
were not invited in good faith, but rather as a pretense to conceal the
purpose to let the contract to some favored bidder, or to one of a
group of preferred bidders, and with the intent to willfully,
capriciously, and arbitrarily disregard the obligation to let the
contract to him whose bid was most advantageous to the government.
o Relief in the CoFC prior to 1996 was limited to monetary, not injunctive or
declaratory, relief.
The current status of bid protest jurisdiction in the CoFC can be summarized
as follows:
o Jurisdiction is granted by the amended Tucker Act – 18 U.S.C § 1491(b)(1).
There is jurisdiction over the protest regardless whether it is instituted
before or after the contract is awarded.
o Any “interested party” has standing.
 Standing in the CoFC should follow the GAO approach at least where
the GAO approach is more restrictive than the standing of district
courts once was with regard to bid protests (i.e. no labor unions or
municipalities). See below for standing of the district courts prior to
2001.
 However, there is an argument that standing in the CoFC should
follow the standing that was seen in the district courts. This is not the
current majority view.
 The CoFC was intended to take over the jurisdiction of the
district courts.
 It is unconstitutional because a person has a valid government
contract claim but has no Article III forum in which to litigate.
o The court can award any relief that it deems necessary including:
 Declaratory relief,
 Injunctive relief,
 Monetary relief, limited to bid preparation and proposal costs (i.e. no
attorney’s fees, no expectancy damages).
 Note: The Equal Access to Justice Act (“EAJA”) says that a successful
litigant against the United States can recover attorney’s fees but only
if the court determines that the government’s position was not
substantially justified. The litigant has to have below a certain net
worth, at different levels for individuals and corporations.
o The standard of review is deferential (“arbitrary, capricious, an abuse of
discretion”). This is the same standard of review as that of the APA in the
district courts. See below for an explanation. The amount of deference the
CoFC would give to the GAO is debateable.
o The fact-finding ability of the CoFC is that of a typical court.

-
U.S. District Courts under the Administrative Procedure Act
- Note: The jurisdiction of the district courts over bid protests was terminated when
Congress declined to extend it (Sunset Provision). This was the intent of Congress.
However, some argue that jurisdiction still exists.
24 GOVERNMENT CONTRACTS OUTLINE
-
-
-
-
-
Jurisdiction over bid protests in the district courts was given in the APA.
Section 701 of the APA creates a presumption that a final agency action is judicially
reviewable except where another statute precludes review. Awarding of a contract
is a final agency action (Scanwell).
Section 701 extends standing to all those who are aggrieved within the meaning of
the relevant statute (outside of the APA) that the plaintiff seeks to enforce.
o The injury in fact is that the bidder would have been better off with the
contract award and that he is now worse off by having expended the bid
preparation costs. The disappointed bidder is within the zone of interests
that Congress wanted to protect because government contracts laws are
intended to protect not just the public but also the bidders.
o The courts generally do not require the plaintiff to show that it had an inside
track or certainty of success in getting the contract if it prevailed in its
challenged to the existing award.
o If the plaintiff is not even eligible for the contract, or if ultimate benefit to the
plaintiff from a favorable result in the litigation is highly speculative, the
plaintiff may not have standing.
o There may be a trend toward more restrictive applications of standing in
procurement cases.
Relief does not include money damages. The plaintiff can get only injunctive or
declaratory relief. The only way that a plaintiff can get money is if the court orders
injunctive relief that requires the government to comply with the payment
provisions of a statute.
The standard of review in the district courts is deferential in findings of fact.
o If two agencies disagree, deference should be given to the agency to which
Congress has delegated primary enforcement responsibility of the statute in
issue. This suggests deference to the procuring agency, rather than to the
GAO, in the event the two disagree. Chevron would also support deference to
the procuring agency because the GAO is a legislative entity. However,
deference to the GAO might be preferable given its expertise and neutrality.
o The Chevron doctrine states that considerable weight should be accorded to
an executive department’s construction of a statutory scheme it is entrusted
to administer. Obviously, Chevron cannot mean that complete and total
deference should be given in government contracts disputes because that
would lead to the government winning every case.
The “Little Tucker Act” allowed the district court concurrent jurisdiction over claims
within the CoFC core jurisdiction provided that the amount of the claim did not
exceed $10,000.
Board of Contract Appeals
- Coastal Corp.: Boards of contract appeals do not have bid protest jurisdiction. The
reasoning employed in Heyer Products does not support the argument for an
exercise of jurisdiction because the implied contract in that case was not a contract
for procurement. Boards of contract appeals only have jurisdiction over
procurement contracts.
GOVERNMENT CONTRACTS OUTLINE 25
-
The Contract Disputes Act intended to give the boards of contract appeals
jurisdiction over performance disputes. This makes the boards an alternative forum
to the CoFC for performance disputes.
The Relationship Between Bid Protest Forums and Performance Dispute Forums
- Sometimes, there can be confusion between where the bid protest dispute ends and
where the performance dispute begins. This problem is worse when the protest is
litigating in the CoFC, which is also a performance dispute forum.
- It is not for the bid protest forum to decide what the financial arrangement should
be for the termination of a wrongfully awarded contract. (Amdahl)
- This problem occurs when there is a bid protest, but the contract has already been
awarded and performance has begun. If the protester wins, the bid protest forum
can recommend or order that the contract be terminated and grant a remedy for the
protester.
- However, the bid protest forum cannot order the remedy for the termination of the
contract.
- Upon finding that the award was improper, the decision goes back to the agency.
The contract then either becomes void or voidable.
o Void: The government doesn’t have to terminate the contract because it was
void. This gives the contractor less in recovery, as he only gets the “value
conferred.”
o Voidable: The government can terminate the contract for its own
convenience. This gives better compensation to the contractor (performance
costs plus a reasonable profit on what it had completed).
- First, the government must have a chance to decide what it thinks the terminated
contractor deserves after the contract is terminated for convenience (“TFC”).
- If the terminated contractor is unhappy with the government’s decision, it can bring
a performance dispute under the CDA.
International and Comparative Law Notes Regarding Bid Protests
- Treaties might be used to interpretatively broaden the standing, remedies, and
jurisdiction of the Court of Federal Claims in order for the U.S. to be in compliance
with international law.
- International law is an avoidance cannon of interpretation: you should avoid
interpreting domestic law such that it causes a treaty breach.
- WTO and the Government Procurement Agreement (GPA)
o Although WTO has over 100 member nations, only ~30 have signed the GPA
o GPA only applies to agencies listed in the Annexes
o Applies only to procurements over a financial threshold of 130K Special
Drawing Rights (SDRs) in the international monetary system.
o Requires national treatment – each member nation must treat suppliers from
other member nations no less favorably than their own domestic suppliers.
o Bid Protest Procedures Required by GPA
 “Non discriminatory, timely, transparent and effective procedures
enabling suppliers to challenge alleged breaches of the Agreement in
26 GOVERNMENT CONTRACTS OUTLINE
-
the context of procurements in which they have, or have had, an
interest”
 Same thing as “actual or prospective bidder”?
 Court or non-judicial tribunal subject to judicial review or a set of due
process requirements
 GAO or CoFC appears to meet these standards
 Foreign entities appear to be allowed to bring a claim of violation of
U.S. domestic procurement law in either the GAO or CoFC
 Nothing in Tucker Act or CICA suggests a limitation
disqualifying foreign bid protestors
 Required Remedies:
 “rapid interim measures . . . “
o GAO’s automatic stay provision?
 “correction of breach or compensation for loss . . which may be
limited to costs for tender preparation or protest”
o Arguably GAO’s authority, which is limited simply to
recommendations, does not meet this test. But b/c
protestors can go to CoFC instead, US is incompliance
w/ GPA
NAFTA – Similar procurement requirements, but unlike GPA, does not seek to
regulate the quality of bid protest tribunals made available by member nations.
European Union - Directive 2004/18/EC, consolidated the Public Supplies Directive,
Public Works Directive, and Services Directive. Did not address remedies for
violation of procurement rules.
o Review Directive 1989 – Addresses remedies and procedures for
enforcement
 Requires procedures for prompt and effective review for alleged
violations of European Community law
 No requirement that review extend to alleged violations of nat’l
procurement law, but if review rights are extended to domestic
suppliers, foreign suppliers must also have access.
 Standing: “any person having or having had an interest . . . how has
been or risks being harmed . . .”
 Tribunals must have authority to
 Take interim measures to prevent further damage to interests
 Either Set aside or ensure setting aside of unlawful decisions,
including removal of discriminatory specifications . . . or
 Award damages
 Not explicit, but most EU tribunals limit monetary damages to bid
preparation costs and deny expectancy damages.
 Does not mandate that initial review tribunal be independent of
procuring agency (unlike GPA)
GOVERNMENT CONTRACTS OUTLINE 27
Contract Performance Disputes
Summary of performance dispute process:
The contractor has 6 years to bring
a claim:
To the contracting officer.
If the CO rules against the government,
The government cannot appeal.
A losing contractor has two choices for appeal:
The appropriate BCA
90 statute of limitations
De novo review
120 days to appeal to Fed. Cir.
The CoFC
1 year statute of limitations
De novo review
60 days to appeal to Fed. Cir.
Government needs DoJ permission to appeal
The dispute can be appealed to the Fed. Cir.
Questions of Law: De novo review
Questions of Fact: Clearly erroneous standard
The dispute can then be appealed to
The US Supreme Court
28 GOVERNMENT CONTRACTS OUTLINE
Introduction to the Disputes Process
- Current contract dispute (all “sections” refer to the Contract Disputes Act):
o The protester brings his claim to the Contracting Officer for the procuring
agency. There is a six-year statute of limitations.
o If the Contracting Officer decides the matter adversely to the government, the
government cannot appeal. If the Contracting Officer decides the matter
adversely to the protester, the protester can appeal to either:
 The appropriate board of contract appeals (military – ASBCA, or
civilian – CBCA), or
 Ninety-day statute of limitations
 De novo review (Section 7103)
 The CoFC.
 One-year statute of limitations
 De novo review (Section 7104)
o The decision can be appealed, in either case, to the Federal Circuit. The
government can only appeal with permission of the Attorney General.
 If the appeal comes from the board of contract appeals, there is a 120day statute of limitations. The standard of review is deferential
(Section 7107(b)).
 If the appeal comes from the CoFC, there is a 60-day statute of
limitations. The standard of review is deferential (Fed. R. App. Pro.).
o The decision of the Federal Circuit can be appealed to the Supreme Court of
the United States.
The Role of the Contracting Officer
- Contracting officers have dual (incompatible) roles as both the government’s
representative and the primary unbiased adjudicator of disputes.
- The de novo standard of review of a contracting officer’s decision reflects that
courts are not confident that contracting officers can be entirely impartial.
- Keystone: The statute of limitations for appeal doesn’t begin to run if there is no
dispute. Where the contracting officer outright denied the contractor any input, but
rather merely demanded payment, there is no dispute.
- Penner: The findings of fact of a contracting officer, affirmed on appeal, are
conclusive unless the evidence shows he acted arbitrarily or capriciously or that his
decisions were so grossly erroneous as to show bad faith. But a contracting officer
must act impartially in settling disputes.
Choice of Forum and Procedures Under the Contract Disputes Act
- The Contract Disputes Act (CDA) gives a board of contract appeals jurisdiction over
a contracting officer’s final decision on a claim.
o The CDA does not define “claim.”
o The FAR fills the gap:
 Written demand or written assertions by one of the contacting parties
 Seeking, as a matter of right, the payment of money in a sum certain,
the adjustment or interpretation of contract terms, or other relief
arising under or relating to the contract.
GOVERNMENT CONTRACTS OUTLINE 29
A voucher invoice or other routine request for payment that is not in
dispute when submitted is not a claim.
 The submission may be converted to a claim by written notice to the
contracting officer if it is disputed to either as to liability or amount or
is not acted upon in a reasonable time.
o Requests for equitable adjustments are, by definition, claims.
o Those demands that are not routine do not also have to already be in dispute.
o Proper analysis:
 If it’s a non-routine submission, it must be a demand as a matter of
right to a sum certain.
 If it’s a routine submission, the contractor must dispute it and then
contract must request a final decision. There is no formal language
required to request a final decision from the contracting officer.
 Transamerica: Given all of the facts and the circumstances,
should the contracting officer have known there was a request
for a final decision?
 If the contractor is willing and prepared for a final decision,
even if he is also willing to bargain or negotiate, he has
submitted a claim.
 The contractor must say something that would reasonably
communicate to the contracting officer that they are willing
and prepared for a final decision
The CDA has a certification requirement for claims of more than $100,000.00 made
by a contractor.
o The certification must state that:
 The claim is made in good faith
 The supporting data are accurate and complete to the best of the
contractor’s knowledge and belief,
 The amount requested accurately reflects the contract adjustment for
which the contractor believes the government is liable,
 The certifier is authorized to certify the claim on behalf of the
contractor.
o The certification must be executed by an individual authorized to bind the
contractor with respect to the claim.
o Failure to certify of defective certification:
 A contracting officer is not obligated to render a final decision on a
claim of more than $100,000.00 that is not certified if, within 60 days
after receipt of the claim, the contracting officer notifies the
contractor in writing of the reasons why any attempted certification
was found to be defective.
 A defect in the certification of a claim does not deprive a court or an
agency board of jurisdiction over the claim.
 Prior to the entry of a final judgment by a court or a decision by an
agency board, the court or agency board shall require a defective
certification to be corrected.

-
30 GOVERNMENT CONTRACTS OUTLINE

It is unclear what would happen if there were no certification. I think
it would defeat jurisdiction because the contracting officer likely
won’t make a final decision on the issue. Without a final decision,
there is no jurisdiction. But this was not discussed much in class.
Formation of Government Contracts
Basic Principles of Government Contract Formation
-
-
-
-
-
In sealed bidding:
o Offer: when a company submits a bid
o Acceptance: when the government sends a black contract to the company
that wins the bid
In competitive negotiation:
o An RFP is just a request for offers
o Offer: when the winning bidder sends its signed contract back to the
government
o Acceptance: when the government signs the contract
Government contracts need consideration unless a statute or regulation says
otherwise. (Torncello)
o When contracts are ambiguous, they should be interpreted such that
consideration is preserved.
o Even though consideration is required, nominal consideration is almost
always allowed. There is no litigation on the adequacy of consideration.
o There is no requirement that option contracts have separate consideration
from the contract.
Types of contracts:
o Definite quantity contracts: have a minimum and a maximum
o Indefinite quantity contracts: have only a minimum (without a minimum,
there is no consideration)
o Requirements contracts: have neither a minimum or a maximum (the
consideration is the fact that the government promises to get all of its
specified needs from a single contractor, thus giving up its power to choose).
Implied contracts:
o Implied in law
 Created by the courts for equitable remedial purposes even though
there was in fact no agreement
 The government has only waived its sovereign immunity with regard
to contracts implied in fact, not contracts implied in law.
 Implied in law contracts are not actionable in government contracts.
o Implied in fact
 The court is finding that the parties actually had an agreement.
 It may not have been manifested, but it was bade on a meeting of the
minds.
GOVERNMENT CONTRACTS OUTLINE 31
As long as an objective observer can discern by the parties conduct
and words that an agreement existed, a contract implied in fact has
been formed.
 Requirements of an implied in fact contract:
 Mutual intent to contract
 Offer
 Acceptance
 Consideration
 Formation or ratification by a person with actual authority to
bind the government
 Remedies: Where a benefit has been conferred by the contractor on
the government in the form of goods or services, which it accepted, a
contractor may recover the value of the conforming goods or services
received by the government. (Amdahl)
 A contract implied in fact for the continued storage of government
furnished materials existed where there are numerous provisions
imposing obligations on the plaintiff to maintain, repair, and protect
government furnished materials so long as they were in his
possession, the government issued a form to the contractor
requesting information as to how much storage space he had for the
materials, which the contractor returned, and the government
accepted by its conduct by leaving the materials on site. (Algonac)
 There was no implied in fact contract to indemnify the contractor
against losses for third party claims where there Contracting Officer is
well aware of the statutory mechanisms under which he could have
provided indemnity, and the Anti-Deficiency Act, which would
prohibit an open-ended promise.
Statute of Frauds
o Government contracts must be in writing.
o This requirement is intended to protect both sides from the possibility of
fraud or misrepresentation.
o If only the private party had to have a written contract to enforce, there
would be consideration.
o The requirement that contracts be in writing to be enforced does not bar
enforcement of an implied in fact contract.

-
Competition Policies
-
Full and open competition is required unless one of the following is true:
o There is only one responsible source or only a limited number of responsible
sources for the property or services and no other type of property or services
will satisfy the government’s needs.
o The government’s need for the property or services is of such an unusual and
compelling urgency that the United States would be seriously injured unless
the agency is permitted to limited the number of sources from which it
solicits bids or proposals. The urgency may not have been created by the
government due to lack of planning. The head of the agency must request
32 GOVERNMENT CONTRACTS OUTLINE
-
offers from as many potential sources as is practicable under the
circumstances.
o It is necessary to award the contract to a particular source or sources in
order (any one of the following):
 To maintain a facility, producer, manufacturer, or other supplier
available for furnishing property or services in case of a national
emergency or to achieve industrial mobilization.
 To establish or maintain an essential engineering, research, or
development capability to be provided by an education or other
nonprofit institution or a federally funded research and development
center.
 To procure the services of an expert for use, in any litigation or
dispute (including any reasonably foreseeable litigation or dispute)
involving the federal government, in any legal dispute, or to procure
the services f an expert or neutral for use in any part of an ADR or
negotiated rule-making process, whether or not the witness is
expected to testify.
o The terms of an international agreement or treaty between the United States
and a foreign government or international organization, or the written
directions of a foreign government reimbursing the agency for the cost of the
procurement of the property or services for such government, have the effect
of requiring the use of procedures other than competitive procedures.
o A statute expressly authorizes or requires that the procurement be made
through another agency or from a specified source, or the agency’s need is
for a band-name commercial item authorized for resale (subject to
subsection K).
o The disclosure of the agency’s needs would compromise national security
unless the agency is permitted to limit the number of sources from which it
solicits bids or proposals. The head of the agency must request offers from as
many potential sources as is practicable under the circumstances.
o The head of the agency:
 Determines that it is necessary in the public interest to use
procedures other than competitive procedures in the particular
procurement concerned, and
 Notifies Congress in writing of such determination no less than 30
days before the award of the contract.
If full and open competition is required:
o Sealed bidding is required if all of the following are satisfied:
 Time permits the solicitation, submission, and evaluation of sealed
bids (lack of time cannot have been created by the agency due to lack
of planning),
 The award will be made on the basis of price and other price-related
factors,
 A non-price factor must be real and not just a way to avoid the
use of sealed bidding
GOVERNMENT CONTRACTS OUTLINE 33

-
-
Track record is an acceptable factor when it is used as a
weighted factor and not as a pass/fail element
 It is not necessary to conduct discussions with the responding sources
about their bids, and
 Essex: The GAO will not question the judgment of the agency
when it determines that certain specifications are sufficiently
important to warrant discussions and thus negotiated
procurement unless the determination is shown to be
unreasonable.
 Racal: The possibility that bidders will not fully understand the
request is not a good reason to have competitive negotiation
(that’s what a bidder’s conference is for.
 The possibility that bidders will not be able to produce is
supposed to be handled in the responsibility investigation.
 Possible changes in quantity, delivery schedules, opening
dates, etc. are supposed to be handled using cancellation of the
IFB and reissuing a new invitation for bids, even if it’s
inconvenient. Inconvenience is the price we pay for full and
open competition.
 There is a reasonable expectation of receiving more than one sealed
bid
o Otherwise, competitive negotiation can be used.
If full and open competition is not used:
o The contracting officer for the contract must justify the use of
noncompetitive procedures in writing and certify the accuracy and
completely of the justification,
o The justification must be approved by:
 The competitive advocate for the procuring agency (without further
delegation) for contracts between $500,000.00 and $10,000,000.00.
 By the head of the procuring agency (or the head’s delegate) for
contracts between $10,000,000.00 and $75,000,000.00.
Ways to circumvent full and open competition:
o Task order contracts (indefinite delivery/indefinite quantity contracts;
framework contracts)
 The government can call and ask for a certain delivery of a product at
a certain price in a certain amount of time.
 They are supposed to be used in emergency situations (i.e. what FEMA
should have done during Hurricane Katrina).
 They are frequently used under the GSA system, where one agency
can order through another agency’s task order contracts, and where
the hosting agency and the ordering agency are not the same. It is not
clear who is responsible for ensuring full and open competition.
o Government purchase cards:
 Competition is supposed to be ensured by the operation of the free
market.
34 GOVERNMENT CONTRACTS OUTLINE
However, nothing can stop an employee from going to a favored
retailer and buying at a higher price.
o Excessively narrow specifications:
 Memorex: Where the government has no reasonable basis for its
stated needs, and the requirements exceed the government’s
minimum needs, the scope of the procurement is excessive and
unwarranted.
 When a specification is framed merely as a factor for consideration as
opposed to a required element, it is less likely to be considered an
undue restriction on competition.
 The government can express specifications in terms of a commercial
product.
 However, when used a brand name or equivalent requirement in an
IFB, the government has to at least express the features of that brand
name product that it is interested in, so that bidders can evaluation
whether their product is equivalent.
o Improper bundling:
 Illegal bundling: putting too many items together in a contract to
make something true that wouldn’t otherwise be true (i.e. bundling so
many plane parts together that only one bidder can provide them).
 Administrative convenience is not a sufficient reason alone to justify
bundling that effectively limits competition.
 Where the agency anticipates that new sources for the good or service
will come into being during the contract, the contract should not be of
such length as to effectively limit competition.
 A “break out” clause that authorizes the agency to get parts currently
under a five year sole source contract from new contractors as they
come online effectively turns ensuring full and open competition into
a discretionary function.
o Other transaction authority (OTA):
 A proposed alternative to the government procurement system.
 An agency is given the authority to do some kind of alternate agencyspecific procurement.
Proper analysis:
o Is the procurement subject to full and open competition?
 The procurement must be for foods and/or services.
 Land procurement is not subject to full and open competition (See
Motor Coach).
 If the procurement falls within one of the seven statutory exceptions,
it is not subject to full and open competition (Section 2304(c)):
 Only available from one or a few sources, and no other product
will satisfy the need (1).
 Bona fide emergency (2).
 Necessary to award contract to a particular source or source in
order to:

-
GOVERNMENT CONTRACTS OUTLINE 35

-
-
-
Maintain facilities/supplies for national emergency or to
achieve industrial mobilization (3)(a).
 Establish and maintain research and development (3)(b).
 Hire an expert witness for the government in litigation (3)(c).
 International treaty or agreement requires noncompetitive
procedures (4).
 Statute requires it or need is for a brand name item for resale (5).
 National security exception (6)
 Catch-all exception: Head of agency determines that it is necessary
and in the public interest, and he notifies Congress at least 30 days
before awarding the contract (7).
If full and open competition is not required, did the government adequately justify
its use of an exception?
o Justification must be contemporaneous with the decision (no after-the-fact
rationalization).
o Justification must be written.
o Justification must be certified. How much money is involved will determine
who must certify the justification.
If full and open competition is required, which type of competitive procedure is the
procurement subject to?
o Sealed bidding must be used if:
 Time permits the solicitation, submission, and evaluation of sealed
bids (lack of time cannot have been created by the agency due to lack
of planning),
 The award will be made on the basis of price and other price-related
factors,
 It is not necessary to conduct discussions with the responding sources
about their bids, and
 There is a reasonable expectation of receiving more than one sealed
bid.
o Otherwise, use competitive negotiation.
Was the procedure done correctly?
o In sealed bidding:
 Was the winning bidder responsive, or did the contracting officer
waive a nonmaterial deviation from the IFB?
 A material deviation is one that affects price, quantity, or
quality of the final product.
 Was the winning bidder the lowest price?
 If so, the bidder should win after a responsibility determination.
o In competitive negotiation:
 Was the contract awarded to the contractor with the best value using
the weighted factors in the RFP?
 Was the contract awarded to a responsible contractor?
 Debarred and non-responsible bidders have standing to
challenge their own status.
36 GOVERNMENT CONTRACTS OUTLINE

No bidder has standing to challenge a failure to debar or deem
non-responsible a competing bidder.
Alternative Procedures
Sealed Bid Contracting
- A synopsis of the proposed procurement is published online.
- In response to the synopsis, people who want to bid can request an invitation.
- The agency then sends out an IFB to all who request one.
- The IFB contains all the terms of the contract and more details than the synopsis.
- Offerors submit their bids simply by filling in the price and schedule of performance.
- If a bid is submitted even one second late, the government is free to reject it.
- Bids are opened publically and evaluated without discussion with bidders
- A bidders’ conference is held before bids where bidders ask questions about the IFB
in front of everyone else and receive answers from the agency.
- Bids may be withdrawn on written or telegraphic request received from bidders
prior to the time fixed for opening.
o Negligence on the part of the bidder in preparing the bid confers no right for
the withdrawal of the bid after it has been opened.
o Exceptions:
 When the government should have known that there was a mistake in
the bid.
 When the government unreasonably delays in award a contract.
o If bidders were allowed to withdraw and correct bids after bids are opened,
contractors could cheat to increase profits while still maintaining the lowest
bidder status, or to achieve lowest bidder status.
- The government is always free to reject all the bids if such action is in the public
interest.
- The government must notify losing bidders within three days of the award.
Competitive Negotiation
- The government issues an RFP.
- The source selection plan says what the non-price related factors are and how they
are going to be weighted.
- The government must state whether it will hold discussions or whether it just
reserves the right to do so.
- The government must explicitly reserve the right to award immediately on the
initial round in order to do so.
- The government tends to reserve the right to award immediately on the initial
round of proposals, but the government is always free to talk to the parties or to do
a series of rounds winnowing the offers in which each surviving offeror in the
competitive range is requested to submit a new proposal.
- During negotiations, the Contracting Officer discusses the offeror’s proposal and
points out where the proposals are weak or what would make them better.
- The offers are not opened publically because the bids tend to include proprietary
information.
GOVERNMENT CONTRACTS OUTLINE 37
-
A losing bidder can request a debriefing as to why it lost. This request and
debriefing will form the basis of a bid protect.
Qualification
-
-
-
-
Qualification: a determination, based on past conduct, that a potential bidder should
be generally ineligible to receive government contracts. This determination cannot
be challenged in a bid protest jurisdiction because they are not tied to a particular
contract.
Prestex: A contract awarded to a nonresponsive bid is in effect one issued without
competitive bidding and is therefore invalid.
A remedy in the case of awarding the contract to a nonresponsive bidder is payment
for goods already delivered and received under an implied in fact contract.
Responsive: the bid meets all of the terms, conditions, and specifications of the
invitation for bids or the request for proposal.
In competitive negotiation, there is no bright line rule that a nonresponsive bid be
rejected, unlike in sealed bidding. In competitive negotiation, the government
should see whether a technically nonresponsive bid achieves the functional needs of
the government at the best value.
Nonresponsive bids cannot be cured after the bids have been opened. If we allowed
contractors to place illegal conditions on a bid and later cure them, they could use
this tactic to game the system.
When is a bid nonresponsive?
o Deviations from the specifications in the IFB may be waived by the
contracting officer provided they do not go to the substance of the bid or
work an injustice to other bidders.
o A substantial deviation is defined as one which affects either the price,
quantity, or quality of the article offers.
o A bid that could not be publically opened because it was marked as
confidential was determined to be nonresponsive.
Debarment and Suspension
- Debarment: a longer term of ineligibility
o Debarred contractors are not allowed to bid on any government contract.
o Each agency has its own special debarment official.
o The debarment process is not part of the contract award sequence. It can
happen at any time and is not supposed to be initiated by a bid.
o It usually results in executive-brand-wide debarment.
o The GSA maintains a central list of debarred contractors.
o Potential challenges to debarment:
 Procedures didn’t accord due process: likely to fail due to the
presence of regulations government debarment procedures.
 Decision was arbitrary and capricious: likely to fail due to the
deferential standard of review.
 The agency didn’t follow its own procedures.
 No one has standing to challenge the failure to debar a competitor.
38 GOVERNMENT CONTRACTS OUTLINE
o De facto debarment: Actions which have the practical effect of debarment
although the agency has not formally recognized them as methods of or
reasons for debarment (Old Dominion)
Responsibility
- Responsibility: a contractor’s present and future capability to perform a specific
contract.
- Responsibility determination is the last step in the process. First, the
competitiveness of bids must be definitely decided.
- However, technical capability and financial responsibility may be factors that go into
the type of contract that is selected.
- Responsibility can be challenged in a bid protest forum because it is tied to a
contract.
o A contractor can challenge its own determination of nonresponsibility.
o Losing bidders can challenge another’s determination of responsibility.
o Agencies are unlikely to wrongly affirm responsibility because that will
saddle them with an incompetent contractor.
o Therefore, it is easier to challenge you own determination of
nonresponsibility than it is to challenge someone else’s determination of
responsibility. (Keco)
- Responsibility includes:
o Adequate financial resources,
o Ability to comply with the proposed performance schedule.
o A satisfactory performance record.
o A record of integrity and business ethics.
o Organization, experience, accounting and operation controls, technical skills,
etc.
o Production, construction and technical equipment and facilities.
o Otherwise qualified and eligible.
- If a contractor hasn’t bought the equipment but promises it will, that isn’t good
enough for responsibility.
- Past behavior can be evidence of present and future capability to perform the
contract.
- Pre award surveys are used to ask bidders information about their responsibility.
- Non-Small Businesses:
o The GAO will generally not question a non-responsibility determination
unless the protestor can demonstrate bad faith by the agency or a lack of any
reasonable basis for the determination.
o The nature and extent of the information needed to assure a Contracting
Officer that a firm will meet its contractual obligation is for the Contracting
Officer’s judgment.
o The dollar value of the contract seems to be a factor in determining how
much the contracting officer has to investigate before deciding
nonresponsibility.
- Small Businesses:
GOVERNMENT CONTRACTS OUTLINE 39
-
o Small businesses have been protected by Congress against determinations of
nonresponsibility through the SBA.
o A decision of the SBA regarding the size status of a business is conclusive and
may not be ignored by the GAO.
o Small businesses get notice of determination of nonresponsibility and can
appeal to the SBA.
o The SBA can override a determination of nonresponsibility by issuing the
bidder a Certificate of Competency.
 Neither the agency nor the GAO can second guess the SBA’s decision
to issue a COC.
 If the COC isn’t issued within 15 business days (or whatever time was
agreed upon between the agency and the SBA), the contracting officer
is authorized to proceed with the acquisition and award the contract
to another offeror.
 Agencies might be able t get around this procedure by using
competitive negotiation instead of sealed bidding and making
responsibility-like factors as factors in source selection.
 It isn’t clear whether a prospective bidder would be successful in the
GAO claiming that the agency is doing this because the GAO is so
deferential.
Due Process
o Unless a bidder is a small business, no bidder requires notice or due process
measures prior to a determination of nonresponsibility.
o Exception: Old Dominion
 Bidders have a right grounded in the due process clause to some kind
of opportunity to be heard within whatever time is available when the
nonresponsibility determination is based on a recurrent and
stigmatizing claim, such as engaging in illegal or unethical behavior, as
opposed to simply not having the right equipment.
 This is not a hearing, just a right to be heard.
 It is unclear whether such a claim can be brought in district court
today.
 Would this be a bid protest challenge for which there is
arguable no more district court jurisdiction?
 Would this be a challenge to an agency action under the APA,
which has constitutional implications?
o When in doubt, courts tend to construe statutes such
they do not have constitutional problems, so a court
might say that even under the sunset provision, this
limited kind of claim could be brought in district court.
Pre-Qualification
- Pre-qualification determination: used to make a generic determination of the
responsibility and capability to perform a particular class of contract in advance, so
as to winnow the field of contractors to be considered when an actual solicitation is
made.
40 GOVERNMENT CONTRACTS OUTLINE
-
-
o Usually, this is not legal in the United States because it is anticompetitive.
o It can be done, but there has to be an extremely well-justified reason for
doing so.
o Mere administrative expediency and efficiency are not a good reason to be
able to do this.
If you must do prequalification:
o There must be a written justification.
o You cannot limit the bidding to those not on the list of qualified bidders. You
have to give room for contractors to try to show they are qualified.
o This effectively removes the incentive to do prequalification, on purpose.
Many U.S. procedures are effectively a form of pre-qualification, but not admittedly
so.
o Multiple Award Schedules: The pretense is that they represent the award of
an umbrella contract under which the government has the right to order or
not order at prices that the contractors have offered.
 There is a lack of consideration issue that no one seems to address.
 There is supposed to be competition to get on the list, but there isn’t
in reality.
 You can protest not getting on the list, but you cannot protect not
getting an order.
o The FAR defines the problem out of existence: “orders placed against a
[MAS], using the procedures [provided for the MAS] are considered to be full
and open competition.”
Types of Contracts: Allocation of the Risk of Uncertainty
-
-
-
Sealed bidding must result in one of the two types of fixed price contracts.
Competitive negotiation can result in any valid type of contract. The contracting
officer is given discretion in choosing the type of contract, although the FAR
indicates a preference for fixed price contracts.
Fixed price contracts:
o Firm fixed price:
 The price is X widgets for $X.
 Should be used when the risk involved is minimum or predictable.
o Fixed price with economic price adjustments
 The price is X widgets for $X. But if your widgets are made primarily
out of copper and the price of copper is volatile, then we can change it
by X amount under X circumstances.
 This encourages contractors not to increase their bid price to cover
the uncertainty.
 We’d rather get the lower price for the government at the outset and
have to adjust it later.
 This allocates some of the risk to the government and away from the
contractors.
Time and materials contracts:
o A hybrid between fixed price and cost-reimbursement contracts.
GOVERNMENT CONTRACTS OUTLINE 41
-
o (Fixed hourly rate) times (the number of hours the contractor personnel
worked) plus (the cost of materials).
o Criticism: creates no incentive for the contractor to control costs.
o The FAR requires a ceiling price above which the contractor cannot exceed
without securing an adjustment from the government.
o This may not be sued absent a written determination by the contracting
officer that, because it’s impossible to estimate the amount of labor required
or the costs, no other form of contract is suitable.
o Personal Services Contracts: a subspecies of time and materials contracts
where the contractors are hired to effectively just be regular employees. (No
materials, just time)
 Technically there is a prohibition on this, but it is often violated.
Cost reimbursement contracts:
o This type of contract is only in the government’s interest when the risk
attributable to the uncertainty about the cost of performance is so great that
either:
 There will not be a vigorous market of offerors under a fixed price
contract, or
 Bidders will bid in such a risk averse manner that the price will be
way too high.
o Cost plus percentage of cost contracts (CPPC): These are unlawful because
they create an incentive for the contractor to increase their costs.
o Cost plus incentive fee contracts:
 A formula makes it so the fee proportion goes up as the cost base goes
down. The more money the contractor saves in performance, the
larger incentive fee you get.
 The formula is the opposite of a CPPC contract.
o Cost plus award fee contracts: a panel decides how good of a job the
contractor did and then gives them an award.
Audit Authority
-
The GAO and the procuring agency have audit authority.
The GAO:
o The GAO can audit to identify government waste and investigate the
reasonableness of the prices the government is paying.
o The audit authority only extends to contracts formed from competitive
negotiation.
 It extends to both fixed-price and cost-reimbursement contracts
which were the product of competitive negotiation.
 The GAO cannot audit any contract created by sealed bidding.
o When auditing, the records used must directly pertain to the contract.
 Fixed Price Contracts (Merck)
 Under a fixed price contract, the comptroller general should be
permitted to access records of direct costs.
 He should be barred however from inspecting records of costs
incurred in areas of research and development, marketing and
42 GOVERNMENT CONTRACTS OUTLINE

promotion, distribution, and administration except to the
extent the contractor has allocated these costs as attributable
to the particular contract.
The procuring agency has two types of audit authority.
 Audit authority under the ordinary course of procurement:
o The agency can only audit cost-reimbursement
contracts.
o It cannot audit fixed price contracts. This means that it
can only audit contracts done under sealed bidding,
only competitive negotiation.
o The purpose of this audit authority is to make sure that
the contractor is being honest about which costs are
attributable to which contract, and that all costs are
legally eligible to be reimbursed.
 Audit authority under the Truth in Negotiations Act (TINA)
o This audit authority applies only to competitively
negotiated contracts above a certain price threshold,
currently set at $500,000.00.
o This applies to both fixed price contracts and cost
reimbursement contracts resulting from competitive
negotiation.
o Under TINA, the agency can request cost and pricing
data during contract formation, and if the agency does,
then there is audit authority to back that up.
 If the agency couldn’t (because TINA didn’t
apply) or didn’t (because it chose not to) request
the data, then there is no audit authority.
 TINA’s audit authority only exists where it was
used to demand cost and pricing data during
contract formation.
 The purpose of this isn’t to determine how much
should be reimbursed but to determine if the
original disclosure at the time of contracting was
honest and accurate.
 This covers all facts that a prudent buyer or
seller would expect to affect the price
significantly.
 Labor, capital, etc.
 Extremely intrusive
 Submissions must be certified as accurate. This
makes the certifier potentially liable under the
FCA.
o Exceptions to TINA Audit Authority.
 Contracts under $500,000.00 cannot be audited.
 Where there is adequate price competition:
GOVERNMENT CONTRACTS OUTLINE 43



TINA is not applicable to fixed price
contracts that result from competitive
negotiation.
 TINA is applied primarily to cost
reimbursement contracts created by
competitive negotiation
Where prices are fixed by law.
Commercial items (what is a commercial item?)
Administration of Government Contracts
Contractors’ Rights
Delay
- Excusable delay: the contractor should be excused from sanctions for later
performance, including termination for default, that would otherwise be applicable.
o Excusable delay in fixed price supply and service contracts:
o Except for the defaults of subcontractors, the contractor shall not be liable
for any excess costs if the failure to perform the contract arises from causes
beyond the control and without the fault or negligence of the contractor.
o Examples of such causes include (as long as the contractor is not at fault):
 Acts of God or of the public enemy,
 Acts of the government in either its sovereign or contractual capacity.
 Fires
 Floods
 Epidemics
 Quarantine restrictions,
 Strikes
 Freight embargoes, and
 Unusually severe weather.
o If the failure to perform is caused by the default of a subcontractor, and if the
cause of the default is beyond the control of both the contractor and the
subcontractor, and without the fault or negligence of either, the contractor
shall not be liable for any excess costs for failure to perform unless the
subcontracted supplies or services were obtainable from other sources in
sufficient time for the contractor to meet the required delivery schedule.
o When there is an excusable delay or express suspension order, the time
during which the contractor was on excusable standby gets added to the
available performance times when the work results.
o Thus, if the contracting officer terminates for default when the original
deadline passes, the termination for default is improper and should be
converted into a termination of convenience.
- Compensable delay: A contractor is entitled to an equitable adjustment to cover cost
of the delay where a Suspension of Work clause is applicable.
44 GOVERNMENT CONTRACTS OUTLINE
o All compensable delays are excusable, but not all excusable delays are
compensable.
o Two potential situations:
 Express suspensions by order of the contracting officer
 Constructive suspensions: Has the same effect and consequences of an
actual suspension, and relief should be granted as if an actual
suspension order had been issued.
o Substantive requirements for a compensable delay (Fruehauf):
 The contractor must be without fault in contributing to the ensuring
delay.
 The work was interrupted for the convenience of the government.
 Work interrupted by an incompetent other contractor whom
the government refuses to terminate for default or
convenience constitutes work interrupted for the convenience
of the government. (Fruehauf)
 Delay is either the governments fault or delay is so lengthy that it
would be unreasonable to expect the contractor to shoulder the added
expenses.
o Procedural requirements for a compensable delay:
 If the suspension order is express, there is no contemporaneous
notice requirement (because the government already knows the
contract is suspended).
 If the contractor believes that there has been a constructive
suspension, it must give a contemporaneous notice (within 30 days)
to the contracting officer that it is seeking an equitable adjustment.
 Failure to give a contemporaneous notice isn’t a jurisdictional
bar, but you lose the number of days worth of compensation
that you didn’t give notice.
 For both express and constructive delays, the contractor must submit
a claim to the contracting officer within the statute of limitations of six
years if the equitable adjustment is denied.
o Compensation available for compensable delay:
 Losses caused by the delay.
 Losses that flow from compacted lead and mobilization time.
 Losses that flow from subsequent acceleration of work.
 Expectancy damages are not available.
 Under constructive changes, however, the contractor is
entitled to reasonable profits on the additional work that has
to occur under the change.
 This causes some contractors to argue that it wasn’t just a
compensable delay but that the delay amounted to a
constructive change.
Changes and Modifications
- Changes must be within the general scope of the contract.
GOVERNMENT CONTRACTS OUTLINE 45
-
-
-
-
o General scope: anything that’s even vaguely related to contractor
performance.
o This limitation is not designed to protect the contractor.
o It is designed to protect full and open competition by preventing endless
modification of contracts so that the contracting officer doesn’t have to begin
a new bidding process.
o The test for whether the change is lawful (i.e. in the general scope of the
original contract): Given the change, would the contract have elicited a
different field of competitors for bidding?
o An argument that a change is illegal because it is outside of the general scope
should go to a bid protest forum.
Changes should be, but do not have to be, in writing.
o W.H. Armstrong: A change order doesn’t have to be written to constitute a
constructive change if the change was the result of an authorized contracting
officer’s oral change order.
o A mutual misunderstanding of an ambiguous contract where the contractor’s
interpretation is reasonable and the government’s interpretation requires a
more expensive performance that the contractor anticipated may result in a
constructive change because contracts shall be construed against the drafter.
Types of constructive changes:
o Additional work: The government misleads the contractor as to the nature or
extent of the performance that will be required.
o Acceleration
o Lack of appropriate government cooperation in facilitating performance:
This includes an overzealous inspection.
The contractor must give timely notice to the government that it is seeking an
equitable adjustment:
o 30 days from the receipt of a written change order.
 Failure to give contemporaneous notice isn’t a jurisdictional bar, but
you lose the number of days worth of compensation that you didn’t
give notice.
 Flexible timing when it comes to constructive change because of the
uncertainty as to when the change occurred.
o If the contractor is unsatisfied, it must submit a claim to the contracting
officer within the six year statute of limitations.
Equitable adjustment
o Cost of the extra labor and costs plus a reasonable profit thereon.
o If effect, the compensation for the extra work is a cost reimbursement
contract.
o Thus, sometimes changes can turn a fixed price contract into a cost
reimbursement contract.
46 GOVERNMENT CONTRACTS OUTLINE
Government Prerogatives
Termination for Convenience of the Government
- In order to terminate for convenience (“TFC”), the contracting officer must
determine that the termination is in the interest of the government.
o The court does not have to agree as to whether the termination was in the
interest of the government.
o The court must only find that the contracting officer determined that it was
in the best interest of the government.
o Terminations for default (“TFD”) held improper are turned into constructive
TFCs. (College Point Boat)
- Krygoski:
o No change in circumstance is required for a TFC.
o The test for when a TFC can be made is one of objective good faith.
o There are two possibilities:
 If the government entered into a contract in objective bad faith, not
intending to perform, unless something changes, the government is
still in bath faith, so it cannot use a TFC.
 However, a change circumstances can give the government
that reason it needs to TFC.
 If the government entered into a contract in objective good faith, no
changed circumstance is needed to terminate for the convenience of
the government.
- Proper analysis: Was the original contract entered into in good faith with the intent
to perform?
o If not, is there is changed circumstance which justified termination?
 If yes, the TFC is valid.
 If no, the TFC is not valid (Torncello).
o If yes, is the termination itself in bad faith (i.e. simply because they do not
like the contract they made)?
 If no, the TFC is valid (Krygoski).
 Amdahl: needing to re-solicit to preserve full and open
competition because the award has been made improperly is a
good faith reason to TFC.
 If yes, the TFC is not valid.
- Determining contractor compensation following a TFC
o The contracting officer issues a TFC.
o The contractor responds with a Termination Settlement Proposal (TSP).
 The TSP initiate’s the contracting officer’s obligation to determine the
amount of compensation due.
 If the contracting officer and the contractor agree on either the TSP or
a price that results from further negotiations, then no one has
standing to challenge the amount agreed upon.
 Negotiation factors:
 Contract price for work completed and accepted that hasn’t
been paid for.
GOVERNMENT CONTRACTS OUTLINE 47


Cost attributable to work partially performed or unavoidable
at the time the TFC notice was received. For example, the
contractor has a subcontract that needs to be terminated. The
cost of the subcontractor’s work in the interim should be
recoverable.
 A reasonable profit on work performed unless there would
have been a loss on the entire contract if it were completed.
The government doesn’t have to pay profit to the contractor
just to stop the bleeding.
 There is no right to recover anticipated profits for work not
performed. This would be expectancy damages, which is not
allowed.
If they can’t agree, it goes through the CDA process for performance
disputes.
Inspection/Acceptance
- Performance problems usually fall into two categories:
o Timeliness
o Quality of performance
- Contractors must come up with their own quality assurance program.
- The government can terminate for default just for failing to come up with a
program, even if there are no problems with performance.
- The government has its own right to inspection.
o The government’s right to inspect does not relieve the contractor of the duty
to inspect.
o The government had latitude with time, place, and frequency of inspection.
o However, excessive inspection ratified by an authorized contracting officer
can leave to a constructive change (either under W.H. Edwards or
acceleration).
- The government and the contractor rights depend on whether an error is caught
before or after final acceptance:
o Before final acceptance: the government has more rights than a private party
before it accepts.
 The government can reject the goods, even for a non-material breach
(Arrow Lacquer).
 The government can require correction.
 The government can order delivery of the good, which does not
constitute acceptance, and then institute an equitable price
adjustment downward.
 This is a change order.
 The amount of the adjustment can be disputed through the
CDA.
o After final acceptance: the government has fewer rights than a private party
would after it accepts.
 The government has given itself extremely weak warranties.
48 GOVERNMENT CONTRACTS OUTLINE


Exception: when off-the-shelf commercial items are purchased
under less-competitive procedures, UCC-type warranties
apply.
Latent defects, fraud on the part of the contractor, or gross mistake
amounting to fraud are all reasons for which final acceptance may be
revoked.
Default Termination
- Wegematic: The default rule is that unless the parties agree otherwise, the
contractor assumes the risk that it cannot accomplish that which it promised.
o Having promised the impossible is not a defense to default.
o This rule was created by borrowing from the UCC to create federal common
law.
- Contractors have a significant incentive to avoid received a TFD because past
performance can be used as a factor in future procurements. This also gives them an
incentive to contest a TFD, even if doing so doesn’t give them any more money.
- Timeliness problems:
o The ability to TFD applies to both failed interim deadlines and final
deadlines.
 There is no requirement for cure notice for failure to meet an interim
or final deadline.
 The right to terminate for this reason can be waived if the government
seems to continually not care about the deadlines. (DeVito)
 If the government is sitting idle and suddenly decides to care about
timelines, it needs to either send a cure notice or set a new deadline.
 Some sign must be sent to the contractor before termination. The new
deadline doesn’t necessarily need to be realistic.
o This applies where performance has closed so much that timely performance
is endangered.
 Cure notice is required where a deadline has not been missed but
where timely performance appears likely to not occur.
 The burden is on the government to show that the contractor is not
likely to be able to complete the performance on time.
- Quality problems:
o Strict compliance doctrine: the government can TFD for failure to achieve
specification even if the failure is not material.
o Substantial compliance doctrine:
 The contractor is entitled to a cure notice if:
 Nonconforming goods were delivered on time, and
 The contractor reasonably believed that the goods were
conforming.
o If the contractor does not cure, then the strict
compliance doctrine applies, no matter how
nonmaterial the nonconformance appears to be.
o In many cases, cure notice is a formality because it is
unlikely that the defect can be fixed within ten days.
GOVERNMENT CONTRACTS OUTLINE 49

-
To invoke this doctrine, the defects must be minor and readily
correctible, and the contractor must have reasonably bleiveed
that the goods were in fact conforming.
Determining contractor compensation following a TFD:
o The contractor is only entitled to the value of work already completed and
accepted.
o If the government chooses to have the contractor deliver half-completed
work or materials, it must pay for that.
o There is no entitlement to reasonable profit.
o The government is entitled to cover costs (the difference between the cost of
the re-procurement and the defaulting contractor’s bid.
o Any disputes then go to the proper performance dispute forum under the
CDA.
50 GOVERNMENT CONTRACTS OUTLINE
Appendix I – Answers to Case Questions
Motor Coach Industries
Date: August 29, 2012
1. This case is in the 4th Circuit. It was appealed from the district court. This procedural
posture is not possible today.
2. This is a bid protest.
3. This is probably in federal court because a government agency is a party. This could
also be federal question jurisdiction.
4. MCI is suing the FAA and Eagle for failure to follow appropriate procurement
procedures. Therefore, it is a procedural challenge.
5. The government concedes that it did not comply with the requirements. Instead, it
argues that it didn’t have to because the FAA didn’t seek bids – the Trust, a “private”
entity, did.
6.
a. The action is brought by MCI, a disappointed bidder who actively
participated in the procurement process that it is now saying is illegal. The
government’s standing objection is based on an unclean hands argument,
that MCI shouldn’t be allowed to protest a bid as illegal when it doesn’t have
clean hands. MCI probably responded by saying that it didn’t know the
process was illegal, or that but for the illegal process they would have won
the bid.
b. The defendants are the FAA, Eagle, and the Trust. Eagle is the winning bidder.
The Trust is paying for the contract as an alter ego of the FAA> They have
mostly the same interest – executing the contract.
7. MCI wants injunctive relief to prevent the execution of the contract. Eagle argues
that it acted in good faith and should not be punished for the FAA’s failure to comply
with procurement guidelines. It also argues that the district court didn’t have the
power to grant injunctive relief, only money damages. Injunctive relief can only be
ranted by the court of claims (now the Court of Federal Claims).
8. Eagle was an innocent player in the FAA’s attempt to bypass appropriation
guidelines, yet it now faces serious consequences. Granting injunctive relief would
allow bad actors to participate in illegal bidding and just sue when they lose.
However, this is not a typical case, and allowing the contract to go forward would
effectively endorse the creation of alter egos by government agencies for the
purpose of bypassing procurement requirements. If MCI had been awarded the
contract, Eagle would have sued on the same grounds. Eagle’s unclean hands
argument is inconsistent with its argument that it was an innocent player.
GOVERNMENT CONTRACTS OUTLINE 51
9. The court says that allowing the contract to go forward would undermine the
procurement process. I find this rationale persuasive. Additionally, if MCI were
allowed to seek money damages instead of injunctive relief, the court would
effectively be saying that the FAA would have to pay twice for the buses out of what
has been established as public funds.
10. There were a few arguments that FPASA didn’t apply:
a. The FAA argued that the money used to create the trust was private, not
public money. Therefore, the trust was a private entity, so federal
procurement provisions did not apply. The court rejected this argument,
saying that the FAA effectively lured the airlines into a deal that resulted in a
savings of millions of dollars and that diverted public funds into the trust.
This, along with the FAA’s control over the trust, made the trust an alter ego
of the FAA.
b. The FAA next argued that it was exempt from FPASA for the purpose of
buying buses. However, the FAA is only exempt from the public advertising
requirements of 41 U.S.C. § 5. Congress refused to extend this exemption to
all procurements. And there is nothing in FPASA to indicate that Congress
intended to treat the FAA any differently than other agencies that were
exempt from advertising requirements.
11. The court interprets the advertising exemption and the amendments to FPASA that
maintained that exemption. The court determined that if Congress had wanted to
extend the exemption for the FAA to all procurement practices, it would have done
so.
12.
a. To determine if a trust is an alter ego, the court must look at the totality of
the circumstances and, at a minimum, analyze the following facts:
i. The purposes for which the trust was established.
ii. The public or private character of the entity spearheading the trust’s
creation.
iii. The identity of the trust’s beneficiary and administrators.
iv. The degree of control exercised by the public agency over
disbursements and other details of administration.
v. The method by which the trust is funded.
b. The parties thought it would be easier, most likely.
c. The ruling will have a deterrent effect.
d. The test appears to be designed to discourage the creation of alter egos and
to force agencies to comply with procurement requirements.
13. Eagle argues that the court cannot grant injunctive relief. MCI must seek money
damages in the court of claims.
52 GOVERNMENT CONTRACTS OUTLINE
14. See answers for questions 10 and 11.
15. Eagle lastly argues that 1) MCI has unclean hands, and 2) that the award was
reasonable (i.e. harmless error). The court says that it can only review whether or
not the procedure was properly followed, not whether the award was reasonable. If
the harmless error standard were followed in judicial review of procurement
disputes, the government would never lose because the court must defer to the
government in this area.
16. –
17. –
GOVERNMENT CONTRACTS OUTLINE 53
Forman
Date: August 29, 2012
1. This case was decided in the Federal Circuit on appeal from the Postal Service Board
of Contract Appeals (“board”).
2. The winning contractor is suing the government for breach of contract. In Motor
Coach, there was no contract in dispute, just the bid and award.
3. The dispute is a contract performance dispute. Contract performance disputes are
between the government and the contractor.
4. The Formans entered into a contract with USPS to build a postal facility and to lease
it to the USPS in 1961. Since 1980, the USPS has sublet portions of the facility to
various businesses and has presumably made money off of these subleases.
5. The Formans argue that the sublets constitute breach of the lease. First, they
requested that the contracting officer either terminate the lease or give the profit
from the sublets to the Formans.
6. The contracting officer refused to grant either form of relief, so the Formans
appealed to the board.
7. The board concluded that:
a. It had jurisdiction.
b. Federal law applies.
c. The USPS was not in breach.
The Formans appealed.
8. The government contends that there is no jurisdiction because the Disputes Act
doesn’t apply to the procurement of real property in being.
9. The government argues that the Disputes Act specifically excludes contracts for real
property in being from Board jurisdiction. It is compared to the Policy Act, which
excludes contracts for the acquisition of leases from board jurisdiction.
10. First, the court says that this contract did not provide for the acquisition of a leave,
but rather for the creation of a new lease. Second, the court says that this was a
hybrid contract that also had a construction component, which is clearly within the
board’s jurisdiction.
11. This wasn’t an acquisition of a lease because the lease was not a lease in being at the
time of the contract. The contract created the lease. Had a lease already existed on
the land purchased by the government, the Disputes Act would not apply because it
was an acquisition of a lease.
12. Federal law controls because Federal Circuit precedent clearly states that federal
law applies to contracts in which the government is a party. Also, the contract was a
form contract constantly used by the Postal Service.
54 GOVERNMENT CONTRACTS OUTLINE
13. The court borrows state law because property and contract interpretation are
issues usually litigated in state court. There is no federal common law on point.
14. The important phrase in the lease is “for postal purposes.” The Formans say it is a
restrictive covenant. The government says that it is just a phrase that describes the
intended purpose of the premises.
15. The Formans say that the lease should be interpreted against the drafter. The
government says that any restrictions to a lease should be interpreted against the
landlord. These maxims do not necessarily depend on the fact that this is a
government contract. However, given the fact that the government is a repeat player
in litigation, any ambiguities in its own form lease should be construed against it.
16. The court concludes that the disputed phrase does not specifically state the proper
limiting language for a restrictive covenant. The lease only states the intended
purpose of the lease. In fact, evidence suggests that the language was necessary to
be in compliance with 39 U.S.C. § 2103(a).
GOVERNMENT CONTRACTS OUTLINE 55
Tingey
Date: September 4, 2012
1. –
2. The U.S. sued Tingey for debt on a bond. This case is different from previous ones
we have studied because the party being sued is not a party to the contract, but
rather is the surety of the contractor.
3. Tingey is Deblois’ surety. Deblois was a purser in the navy who was required to have
a performance bond in order to keep his position and benefits.
4. The purpose of a performance bond is to guarantee a contractor’s performance
under a contract. A surety is the person or corporation who guarantees the
contractor’s performance. If the assured performance does not occur as promised,
the surety is liable for monetary damages that result from the lack of performance
up to the amount of the bond, in this case, $10,000.00.
5. Tingey had a number of responses. One of which is that the bond is illegal because it
was extorted from Deblois and his sureties by the Secretary of the Navy.
6. “Issues were joined” just means that there are factual issues in dispute. A demurrer
is just the old equivalent of a 12(b)(6) motion.
7. The trial court ruled for Tingey on the demurrers. I do not know on what grounds.
8. The case was appealed form the Supreme Court from the D.C. Circuit Court. This
procedural posture would not happen today.
9. The main issue is whether the government can enter into contracts. The court says it
can. It can be implied from Congress’ legislation requiring such contracts, such as
the bond. However, the fallback argument is that the government has apparent
authority to enter into contracts.
10. This is not a procurement contract. This is a performance bond.
11. The bond is illegal because it was coerced and no voluntary. This, combined with the
fact that it exceeds statutory authority, makes the bond illegal.
a. Deblois was to be liable for all money and public property received, whether
officially as purser or otherwise.
b. Because there is no legal bond, the government cannot recover from the
surety.
12. The government argues that it shouldn’t matter that the bond exceeded statutory
requirements. They can contract just as a private party can. The court replies that if
the bond had been entered into voluntarily, it would have been legal.
56 GOVERNMENT CONTRACTS OUTLINE
GOVERNMENT CONTRACTS OUTLINE 57
Corliss
Date: September 4, 2012
1. This case comes from the Court of Claims.
2. –
3. Corliss sued the U.S. for the balance due on the contract. The Court of Claims is a
forum for claims of money damages against the government.
4. There were two contracts:
a. The contract between the Navy and Corliss for steam engines.
b. The settlement agreement.
5. The Navy suspended work under the contract.
6. Corliss wanted to get paid for work done. It gave the Navy two choices:
a. Corliss keeps the incomplete machines and the Navy pays $150,000.00
b. The Navy gets the incomplete machines and pays around $259,000.00.
7. Corliss’ second option was chosen. The Navy gave one condition: partial payment on
delivery with the certificate of balance due to be paid when Congress appropriates
funds. The Navy cannot disburse funds that have no been appropriated.
8. The government can argue that it doesn’t have to appropriate funds because it was
not a party to the settlement agreement. However, the Navy couldn’t disburse funds
that weren’t already appropriated. Using the government’s argument, government
departments could escape payment by promising appropriated funds with no
intention of following through.
9. The Navy likely argues that the Secretary of the Navy cannot bind the government
into a settlement agreement because it had no power to terminate the contract in
the first place.
10. The court finds that the Secretary of the Navy has the power to terminate contracts
that it enters into. Statute authorizes the Secretary to make procurement contracts.
Therefore, he must also be able to terminate those contracts and to agree upon
compensation for partial performance. To hold otherwise would be a serious
detriment to public service.
11. See answer to question 10.
12. The Navy could always give the machines back and pay only $150,000.00.
13. The government has the power to enter into settlement agreements and to
terminate agreements. The Secretary of the Navy has the power to bind the
government.
14. This case exhibits both exceptionalism and congruence. First, the government can
enter into settlement agreements. Second, the government can terminate for
convenience.
58 GOVERNMENT CONTRACTS OUTLINE
Bowsher
Date: September 5, 2012
1. The main question is whether executive functions had impermissibly been assigned
to the Comptroller General.
2.
a. The Comptroller General is nominated by the President from a list of three
individuals recommended by the Speaker of the House and the President pro
tempore of the Senate.
b. The Comptroller General can be removed by:
i. Impeachment, or
ii. A joint resolution of Congress at any time resting on any one of the
following bases:
1. Permanent disability,
2. Inefficiency,
3. Neglect of duty,
4. Malfeasance, or
5. A felony or conduct involving moral turpitude.
This could create a problem under Chadha because the President does not
have to sign it into law.
c. Congress supposedly must conform its reasoning for removal to the 5
options. However, they are so broad that Congress could sustain removal for
virtually any transgression, actual or perceived. The majority also states that
the removal may not be subject to judicial review, as that issue is contested.
3.
a. Yes. Congress can remove the Comptroller General even in the face of
Presidential opposition, with a 2/3 vote.
b. No. The President cannot remove the Comptroller General without support
from Congress.
4. This is different from executive brand officers, who are either removable by the
President at whim or for cause as prescribed in a statute. Congress can limit this
power slightly but cannot play a role in the removal of executive officials.
5. There are several provisions that govern the Comptroller General position that
make him a legislative official: removal power, AAA of 1950 (“as an agent of
Congress”), and other legislation. The removal power is a critical factor, but not
necessarily dispositive. Stevens says that the Comptroller General also has certain
duties and obligations with respect to the executive brand. He is not so clearly an
GOVERNMENT CONTRACTS OUTLINE 59
agent of Congress as the majority says. Stevens looks mostly at the Comptroller
General’s responsibilities to determine that he is an agent of Congress.
6. The Comptroller General’s responsibilities are repeatedly framed in terms of his
specific obligations to Congress:
a. Helps a congressional committee to develop a statement of legislative goals
upon request,
b. Makes annual reports on specified subjects to Congress,
c. Etc.
7. The GAO at its inception may have been intended primarily to provide an expert
accounting capacity to Congress that could be used to guide the development of
legislative policy and facilitate legislative oversight of government operations. Over
time, the GAO developed a stance more independent of Congress. While its formal
ties to Congress were never broken, the GAO drifted from a position clearly
subservient to Congress to a more independent role. In constitutional terms, it is
impermissible to assign a combination of executive functions and legislative control
found in the case of the Comptroller General and the GAO.
60 GOVERNMENT CONTRACTS OUTLINE
Ameron
Date: September 5, 2012
1. Ameron is a losing bidder who is suing the Army in a bid protest because it says it
had a lower bid than the winner.
2. Ameron had the lowest bid, but the Army claimed that the bid was nonresponsive
because its bid bond did not comply with the requirements.
3. Ameron filed a bid protest with the Comptroller General. The Comptroller General
issued a stay on the execution of the contract. The Army proceeded with the
execution because it believed the stay provisions to be unconstitutional. American
filed suit in District Court seeking injunction relief. The district court ruled for
Ameron. The Court of Appeals of the 3rd Circuit affirmed. The case was argued after
Bowsher.
4. See question 3.
5. The government is intentionally breaking the law because it wants to challenge the
constitutionality of the law. It uses unconstitutionality as a defense. It is never a
good idea to refuse to comply with a statute because you think it is unconstitutional.
The government should have asked for a declaratory judgment on this issue. The
government probably couldn’t have waited for someone else to challenge the law
because not many people have standing to do so.
6. The Army challenges CICA’s delegation of power to the Comptroller General. CICA
allows disappointed bidders to file a complaint to the Comptroller General. While a
protest is pending, there is a stay on the execution of the contract. The Comptroller
General then issues his recommendations to the agency. If the agency does not
accept the Comptroller General’s recommendation, the agency must explain its
reasoning to Congress.
7. Procedurally, the procurement process is suspended, barring exigent circumstances.
Substantively, while the agency does not have to follow the recommendation, it is
compelled to do so.
8. No. The agency is not legally required to abide by the GAO’s advice. However, it
could suffer if it doesn’t, mainly in funding from Congress.
9. Bowsher described the mission of the GAO as a way for Congress to have some
oversight into the procurement process while giving final control over decisions to
the executive branch.
10. Congress wanted to address the fact that agencies intentionally violate procurement
regulations (i.e. competitive bidding) and then try to finish the projects before the
bid protest is complete, rendering it moot. By having an automatic stay, the agency
must wait to execute the contract. Practically, agencies want contracts executed
quickly, so it isn’t worthwhile to intentionally violate procurement regulations.
11. First, the Army argues that CICA is unconstitutional because it authorizes the
Comptroller General to execute the laws (an executive function) in violation of
GOVERNMENT CONTRACTS OUTLINE 61
separation of powers. Second, the Army argues that CICA impermissibly gives the
Comptroller General control over the procurement process, again authorizing the
Comptroller General to execute the law. Third, the Army argues that CICA gives the
Comptroller General excessive influence over the procurement process and thereby
authorizes excessive legislative interference in a domain assigned to the executive
branch by the Constitution.
12. The court declines to focus on the manner in which the Comptroller General acts to
the exclusion of the power he wields. Instead, the court looks at whether the power
Congress gave the Comptroller General lies outside congressional authority, or is of
a kind that Article II of the Constitution grants exclusively to the President and his
subordinates. Therefore, the court looks more at the means as opposed to the ends,
and at direct as opposed to indirect consequences of the GAO’s exercise of authority.
13. The court determines that there is no usurpation of executive authority or
interference with executive functions on several theories.
a. First, it says that one can interpret the law without executing it; otherwise,
the judiciary would be unconstitutional (Marbury v. Madison).
b. Second, the court states that Congress may investigate executive conduct
when it does not act through legislation. It also has the power to seek to
influence executive action through the force of its opinions. CICA permits an
agent of the legislature to investigate potential government misconduct in
the execution of procurement laws and to influence the executive’s execution
of the laws through the power of public illumination and persuasion.
Congress has the authority to delay procurement activity in pursuit of these
goals.
c. Third, the court says that CICA’s stay provisions do not attempt to usurp the
President’s authority to execute the laws because CICA does not allow
Congress to wield powers that had been given to the executive.
d. Fourth, CICA does not authorize the Comptroller General to execute the
procurement laws because the executive can always override the stay and
because the Comptroller General can only issue recommendations.
e. Fifth, the Act does not intrude too much on the executive’s performance of its
procurement duties.
14. Boards of contract appeals are one of the forums available to hear disputes arising
out of the performance of a government contract. They do not have jurisdiction over
formation disputes, which are heard either by the GAO or the Court of Federal
Claims.
15. The system devised by Congress under which the GAO’s formal authority is limited
to the power to recommend to a procuring agency that it alter or redo the
procurement decision is clearly in part a response to the separation of powers issue.
Congress wanted a bid protest mechanism that is likely to be effective but which
does not violate constitutional norms.
62 GOVERNMENT CONTRACTS OUTLINE
34 Comp. Gen. 239 (1954) (Time issue)
Date: September 6, 2012
1. The Secretary of the Interior requested an opinion from the Comptroller General to
decide if it could use money appropriated for FY 1952 for a FY 1954 contract. There
is a private party with an interest – the new contractor. They are not present here
however. This way, the agencies don’t have to wait to get sued. They can ask for
approval in advance.
2. The obligation is for exploratory drilling in Utah. The agency wants to hire a new
contractor to finish the work left incomplete by the old contractor (under a FY 1952
contract).
3. The problem is that the funds were appropriated for use in FY 1952, but the agency
wants to use them for a FY 1954 contract.
4. The contract is dated June 23, 1952. The funds did not have to be expended entirely
in FY 1952, only under a contract executed in FY 1952.
5. If the funds aren’t spent in the fiscal year, they go back to the Treasury. Congress
may be willing to give the agency less money the next year as a result. Also, this way
the agency doesn’t need to use FY 1954 appropriations – i.e. this is essentially found
money. This creates an incentive to try to find a way to spend unused funds, even on
unneeded contracts.
6. The agency argues that the funds will be spent to finish the work still left on the FY
1952 contract. The Comptroller General accepts this theory.
7. In order to be able to use the lapsed funds, you need:
a. A valid binding contract executed during the funds’ appropriated fiscal year,
b. Termination of the original contract due to the contractor’s default,
c. A new contract to complete the work from the original contract, and
d. The need continued to exist up to the time of the execution of the new
contract (and the need existed in the first place).
8. Section 1311 of the Supplemental Appropriations Act of 1955 states that
appropriations for a given fiscal year can only be used if the contract was executed
before the expiration of the period of availability (i.e. before the end of the given
fiscal year). This technically means that 1952 funds can only be used on contracts
executed in 1952.
9. The Comptroller General says that there is no issue because the original contract
was executed prior to the expiration of the period of availability. The new contract is
just to finish what wasn’t done by the original contractor.
GOVERNMENT CONTRACTS OUTLINE 63
35 Comp. Gen. 319 (1955)
Date: September 6, 2012
1. The Assistant Secretary Controller requested reconsideration of four rejected
requests for appropriations. The Secretary of State recorded certain expenses as
obligations for FY 1954, but the Comptroller General doubted that they were for
that year.
2. The four contracts were executed on June 26 and June 30, 1954 but weren’t
forwarded to the contractors for signature until after July 1, 1954 (FY 1954 ends on
June 30, 1954. There was no evidence to show that the bids were accepted prior to
the close of FY 1954. Thus the contracts were not concluded.
3. The department contends that there were binding offers and signatures (signaling
acceptance) in FY 1954. The Comptroller General states that, even if that is true,
before it can be held that this was a binding agreement in each instance, the
following factors must be present:
a. Each bid must have been in writing,
b. The acceptance of each bid must have been communicated to the bidder in
the same manner as the bid was made in FY 1954, and
c. Each contract must have incorporated the terms and conditions of the
respective bid without qualification. Otherwise, it is a counteroffer.
The Comptroller General said it would examine the matter further. If all of the
factors are met, it will allow the obligation against FY 1954 funds.
4. The second item involved two maintenance service contracts for government
properties in Paris. The Comptroller General said that the services contracted for
did not appear to be intended to serve a bona fide need of FY 1954, current at the
time the contracts were executed. Maybe the agency was just trying to use unspent
FY 1954 funds for FY 1955 needs. This is a different problem than the one
illustrated by the first item. The first item presented an issue of when a binding
agreement was form. The second item is about whether a need even existed.
5. The general rule for legally obligating a fiscal year appropriation is that the supplies
or services are required to serve a bona fide need of the fiscal year in which the
need arises. Ordinarily where a contract is entered into during one fiscal year and
the services contracted for are not performed or required until the following fiscal
year, the appropriation current at the time the services are rendered is properly
chargeable to the cost. This prevents agencies from trying to spend unused FY 1954
funds on FY 1955 contracts just by contracting right before the end of FY 1954. Both
contracts were executed in June of 1954. This was a continuing service, not one job,
and no work started prior to September 1954. Therefore, this was not a bona fide
need for FY 1954.
6. The third item involves an unsubstantiated tax obligation of $2,000.00 to cover
anticipated municipal taxes on two buildings for which no billings had been
received during prior years. In July 1954, a tax bill was received on a third building
64 GOVERNMENT CONTRACTS OUTLINE
for which no billings had been received during prior years. On that basis, it was
considered that taxes might be assessed on the other two buildings. Tax authorities
have advised that a tax bill for $824.00 will be rendered b the municipality in which
the smaller building is located. However, at the time the obligation was recorded,
there was only conjecture. Therefore, only the $824.00 tax bill may be charged to FY
1954 funds, as long as the other requirements are met. To get money for another tax
bill to be charged to FY 1954 funds, the agency as to provide similar proof of the bill.
7. The fourth item concerns an obligation recorded on June 30, 1954 for the
government’s share of the cost of replacing an elevator. The issue is that there was
no binding agreement to replace the elevator in FY 1954. In fact, it was not definitely
known at the time that replacement would be necessary. A letter dated June 29,
1954 only confirms that the government would have to pay 10% of the cost of
replacement if the majority of co-proprietors agree that the replacement is
necessary. The commitment comes into being once a decision is made. In February
1955, still no such decision had been made.
GOVERNMENT CONTRACTS OUTLINE 65
42 Comp. Gen. 226 (1962) (Purpose issue)
Date: September 6, 2012
1. The expenditure in question is for the construction of a pneumatic tube delivery
system between the White House and the Department of State.
2. The Department of State wanted to charge the construction to appropriations in the
“no year” fund market for “extension and remodeling of the State Department
building.”
3. A pneumatic tube system was contemplated when making the appropriation, but
within the building, not between the Department of State and the White House. The
Department tries to justify this by arguing that the President’s counsel is required
on matters affecting the security of the country, so the secure communication to the
White House is an essential part of the communication system of the Department
and is an integral part of the Department’s operations and responsibility.
4. The Comptroller General says that it is important to look at the specific purpose of
the appropriations. The general rule is that an express statutory provision is not
required for every item of expenditure, but an appropriation in general terms for a
particular purpose is available for expenditures necessary to accomplish that
purpose, except as to expenditures in contravention of statute or for which other
appropriations are more specifically available.
5. The construction of a pneumatic tube system between the White House and the
Department is not necessary to accomplish the purpose for which the appropriation
involved was made (to extend and remodel the State Department building).
6. Had the appropriation had language in it that extended it to projects that would help
it to improve communication, the Department might have been able to charge the
expenditure to these funds.
7. The Comptroller General cites 31 U.S.C. 628, which says that appropriations can
only be sued for expenditures for which the appropriations are made. It also cites 41
U.S.C. 12, which forbids contracts that would bind the government to pay a larger
sum than the amount appropriated for the specific purpose.
8. If the State Department had already entered into the contract before an
appropriation for the tube system was made, it would be in violation of the AntiDeficiency Act. Had the Department also already paid for the contract, it would be in
violation of the Appropriations Clause. There would be no violation of either if the
appropriation had been made for the tube system.
9. Today, the statutory requirement that money be spent only for the statutorily
designated purpose of the appropriation is codified in 31 U.S.C. 1301(a).
66 GOVERNMENT CONTRACTS OUTLINE
Solar
Date: September 11, 2012
1. This case was appealed to the Court of Claims from the ASBCA. This would not
happen today.
2. Equitable adjustment is a remedy exclusive to government contracts that allows an
adjustment in compensation in the event the government needs to make a
constructive change to the contract. This eliminates the need to terminate contracts
and the go through the procurement process again.
3. Solar won a bid for requirements contracts for five years to supply power plans and
generators to the Air Force. The Air Force ended up purchasing less than its Best
Estimated Quantity (BEQ). Solar believes that the BEQ was a minimum and that it is
due the difference between what it earned and what it thought it was going to earn.
4. The government argues that it was only bound to purchase its requirements
exclusively from Solar at fixed prices, without regard to any particular dates or
minimum quantities, and that the quantities referred to in the contract were merely
the government’s best estimates of its potential requirements set forth for Solar’s
convenience.
5. Solar says that the government constructively changed the contract such that it is
entitled to an equitable adjustment.
6. Framing the claim as one for equitable adjustment, as opposed to breach, may affect:
a. The applicable procedure,
b. The standard to be applied in judging the claim, which may be more
generous to the claimant, and
c. The availability of certain government defenses, which may be disallowed.
7. Solar says that the government terminated part of the contract for convenience.
8. The government supposedly terminated for convenience by failing to order some of
the items in the contract.
9. Solar argues that contra proferentem requires any contract ambiguities to be
interpreted against the government. In order to prevail under the rule of contra
proferentem, Solar must establish that its interpretation of the disputed language
was within the “zone of reasonableness” and that it reasonably relied on that
interpretation in the course of bidding on performance.
10. The court looks at the five factors that Solar says reasonably led it to interpret the
BEQs to mean firm order that had to be placed within the program year specified:
the contract schedule, ASPR 1-322, the government’s response to an inquiry at the
1967 bidder’s conference, the glossary of terms, and practical considerations.
The first argument fails immediately because the contract clearly states that the
amounts given are anticipated and best estimates, not minimums. Also, orders could
be issued as needed, not just at the beginning of the year as Solar contends. Last, if
GOVERNMENT CONTRACTS OUTLINE 67
the contract were interpreted as Solar says, the cancellation clause limiting recovery
to 5% would be pointless.
11. ASPR 1-322 says that multi-year procurement is a method for competitive
contracting for known requirements for military supplies, in quantities and total
cost not in excess of planned requirements for 5 years. However, Solar could not
reasonably have believed that ASPR 1-322 was written into the contract because
that would require disregard of the express terms of the contract. It would also
require disregard of other regulations dealing with requirements contracts (ASPR 3409-2), which says, among other things, that the requirements contract will state an
estimated total quantity for the information of prospective contractors. Funds are
obligated by each order, not by the contract. In short, just because the contract
spans multiple years doesn’t mean it’s a multi-year contract that requires ASPR 1322, especially when that expressly contradicts both the express terms of the
contract and other regulations.
12. The government argues that Congress appropriates funds for only a single year’s
obligations, and the Anti-Deficiency Act prohibits anyone from obligating the
government in excess of dollars appropriated by Congress. Accordingly, ASPR 1322-5 requires all multi-year contracts to have a funds availability clause. This
clause does not appear, meaning this was not a multi-year contract.
13. This clause is not needed in a requirements contract because there is no obligation
to perform or buy until orders are placed. The government avoids liability by
compensating the contractor under the cancellation clause.
14. Had this been a multi-year contract, the government would want ASPR 1-322 and
the funds availability clause to be read into the contract. It would seem
contradictory for a government agency to be unable to pay for the contract,
constitutionally, but required to pay for breach.
68 GOVERNMENT CONTRACTS OUTLINE
Goodyear Tire
Date: September 11, 2012
1. The Tucker Act (28 U.S.C § 1491) waives the sovereign immunity of the government
with respect to contract claims among other things.
2. Goodyear sued under the Tucker Act to recover rent claimed under a lease to the
U.S.
3. The lease provided that if an appropriation was not made under which the rent for
any succeeding fiscal year might be paid, it should automatically terminate as of
June 30 of the year for which an appropriation was last available. The lease began in
October 1921 for a term ending June 30 1926.
4. The lease essentially said that if appropriations were made, the lease was renewed.
And if there was no appropriation, the lease was terminated.
5. This language is necessary because if no appropriation was made, the agency would
be in violation of the Anti-Deficiency Act by continuing the lease.
6. –
7. At the end of FY 1923, the agency was supposed to give up occupancy of the
premises as previously agreed despite the fact that appropriations were made for
FY 1924. However, the agency officials decided in June 1923 that they wanted to
stay for longer than agreed and would pay only for the period of occupancy as
opposed to for the entire year.
8. The landlord wants payment for rent for the entire FY 1924. The argument is that
under Ohio state law, a hold over tenant becomes obligated to pay rent for the entire
lease term as if the lease had been renewed. The government argued that the lease
was no binding for any year after FY 1922 because it had to affirmatively continue
the lease for the next year, which it did not do.
9. The court agreed with the government. Even though the language of the lease
indicates that the lease renews once an appropriation was made, the government is
not bound because it is contrary to the express provisions of the predecessor to the
Anti-Deficiency Act. The court acknowledges that the outcome may have been
different had this been a private contract decided using state law.
10. This decision is not necessary to prevent a statutory violation because in this case,
an appropriation was made. If this lease must be renewed every year, then it is
really a one-year lease, not a five-year lease. Thus, the promise to lease for five years
is illusory. This case basically stands for the idea that the government has the power
by use of sufficiently clear language to obligate itself to renew in subsequent years
of a contract if funds were in fact appropriated. Goodyear now serves to caution the
contractor that it must negotiate carefully over the contract language to make sure
that the government is obligated for additional years if the funds do become
available.
GOVERNMENT CONTRACTS OUTLINE 69
11. The final alternative basis for the court’s decision is that the holdover doctrine is an
implied in law contract. The Tucker Act waiver of sovereign immunity does not
extend to claims based on contracts implied in law.
12. This doctrine is well-settled and is still good law. Some jurisdictions, however,
believe that the holdover doctrine rests on an implied in fact contract, which would
mean that it would be a valid claim.
13. This case represents extreme exceptionalism.
14. This principle has not been applied to multiyear contracts for goods, as opposed to
services.
15. Federal, not state law, is controlling.
70 GOVERNMENT CONTRACTS OUTLINE
C.H. Leavell
Date: September 12, 2012
1. This was a long-term contract for construction of the Jonesville Lock and Dam. The
work was to be complete within three years. Monthly progress payments were to be
made on estimates approved by the contracting officer, less a 10% retention by the
government until completion and acceptance of the work.
2. The Corps included a funds availability clause, which only guaranteed funds in the
total amount of $75,000.00, unless the contractor is informed of additional
appropriations in writing. This is different than Goodyear because instead of being
obligated to continue the contract upon appropriations, the Corps has to receive
appropriations and notify the contractor in writing.
3. The funds availability clause prevents the government from have to pay for damages
under the entire contract when appropriations are not made.
4. The work was suspending in January 1969 and was resumed in June 1969 due to the
exhaustion of appropriated funds.
5. The contractor is seeking an equitable adjustment under the suspension of work
clause because the government’s failure to provide sufficient funds forced a
shutdown of Leavell’s operations.
6. The suspension of work clause provides a basis for relief.
7. The government argued that Leavell had elected to suspend operations during that
period, as it had the right to do under the funds availability clause, when
appropriated funds available for work under the contract were exhausted, and the
government relied upon that part of the clause providing that the government
would not be liable for damages on account of delay in payments due to lack of
available funds.
8. No. Leavell contends that while the funds availability clause may preclude any claim
for common law damages for breach of contract, it does not bar an equitable
adjustment under the suspension of work clause when work is suspended for an
unreasonable length of time due to lack of funds.
9. See answer to question 8.
10. The court says that the funds availability clause only insulates the government from
liability for breach, as opposed to equitable adjustment.
11. The basis for this distinction comes from legislative history. The funds available
clause originally came into effect to insulate the government from liability for
breach of contract when funds aren’t appropriated. Many years later, the suspension
of work clause became widely used along with the concept of equitable adjustment.
However, the funds availability clause remained unchanged when it was easy to
have changed it.
GOVERNMENT CONTRACTS OUTLINE 71
12. The language of the two clauses together implies that there can be no equitable
adjustment for suspension of work due to lack of funds. But this would result in the
contractor being completely at the mercy of the government.
13. This case reflects contra proferentem because the ambiguities in the contract are
interpreted against the government.
14. The suspension was unreasonable because the schedule was approved by the
contracting officer, who now wants to use the contractor’s efficiency as an excuse
for the delay.
15. The test for the availability of an equitable adjustment under this suspension of
work clause is:
a. The suspension cannot be the fault (or due to the negligence) of the
contractor,
b. The suspension must be for an unreasonable period of time,
c. The suspension must be due to an act, or failure to act, of the contracting
officer, and
d. The performance of the contractor must not have been prevented by other
causes, even without the suspension.
The court doesn’t seem to focus on the unreasonableness of the delay length,
even though the clause does so.
16. The court does not place any significance on the speed or efficiency of the contractor
because the contractor followed the schedule approved by the contracting officer.
The result might have been different had the contractor worker faster than the
approved schedule.
17. This appears to illustrate congruence.
72 GOVERNMENT CONTRACTS OUTLINE
G.L. Christian
Date: September 12, 2012
1. The contract was for the construction of housing units of Fort Polk for military
personnel.
2. The government terminated the contract.
3. The termination was due to the military base’s deactivation.
4. The government argues that the contractor is entitled to be made financially whole,
and most of the claims were settled. However, the contractors argue that they are
entitled to lost profits, which the government disputes.
5. The right to recover for anticipated profits arises only if the termination of the
contract by the government is wrongful and constitutes breach. If the government
has reserve the right to terminate a contract for its convenience and then does so,
there is no breach.
6. Although the Fort Polk housing contract did not contain a provision authorizing the
government to terminate for convenience, the government argues that the contract
should be read as if it did contain such a clause. This is because the clause is
mandatory by law.
7. See answer to question 6.
8. See answer to question 6.
9. The government’s argument is entirely inconsistent with the doctrine of contra
proferentem.
10. The statute is directed to contracting officers, not to contractors.
11. Because the statute is directed at contracting officers, not contractors, the provision
should not be read in as this unfairly punishes contractors. The regulation could
have been reworded to say that the government may always terminate a contract
for convenience.
12. The court agrees with the government and reads the provision in. Because the
government terminated for convenience pursuant to the provision, the contractor
cannot recover anticipated profits.
13. The argument is not very logical. The logical result would have been to construe the
omission against the government.
14. The court seems to focus on the importance of this particular provision historically
in military contracts. It does not explicitly hold that whenever a provision required
by regulations to be included in a government contract is omitted, the contract
should be read as though it were present.
15. Courts have interpreted this case to say that where valid procurement regulations
mandate inclusion of particular standardized clauses in government contracts, those
clauses are to be read into contracts to which they are factually applicable where
they have been omitted by mistake. This is known as the Christian doctrine.
GOVERNMENT CONTRACTS OUTLINE 73
16. This is an important holding for the government because it means that it will not be
held liable for mistakes made by contracting officers. This holding appears to be an
exception to the ability of agents to bind the government. Basically, every contract
requirement in the FAR is automatically in the contract unless the contracting
officer expressly excludes it.
17. In Solar, the government argued that there was no funds availability clause, so it was
intentionally left out. This might still be a sound argument as long as the clause was
expressly excluded because it was not necessary.
18. –
19. This is an exceptionalist approach. Had the contra proferentem argument worked, it
would have represented congruence.
74 GOVERNMENT CONTRACTS OUTLINE
Gordon Woodroffe
Date: September 13, 2012
1. This dispute arose from a contract for turbo alternator generators. Tientsin
Company owned the generator. Woodroffe Company secured an option to purchase
the generator. Woodroffe was in talks with Walsh (via Duke and McGhee) to buy the
generator from Woodroffe for $900,000.00, despite the fact that Woodroffe was
only going to pay $458,000.00. However, while these negotiations were going on,
Tientsin Company had sold the same generator to Athens Piraeus (the end user if
Walsh had purchased it) for $524,400.00. Walsh was a special assistant to the
Coordinator (McGhee) who purported to enter into a contract on behalf of the
government.
2. The contract terms were: the generator for $900,000.00 subject to inspection.
3. Walsh sent Woodroffe a telegram, with Deputy Wild’s signature, that said he was
accepting “this unit for and on behalf of the American Mission for Aid to Greece and
the Athens Piraeus Electricity Company.”
4. The court does not say what the theory of harm and remedy requested are.
However, I would guess Woodroffe wants the different between the actual and
anticipated profits under breach of contract theory.
5. The government argues that there was no contract because Walsh and Wilds did not
have the authority to bind the government.
6. The court looks at the statutes concerning contracting authority. The President
transmitted his authority to the Secretary of State. The Secretary of State then
delegated the authority to the Chief of the American Mission for Aid to Greece. The
court looks to see if any one of those people or organizations expressly gave Walsh
and Wild contracting authority through phone calls or telegrams.
7. The court determines that only the President, Secretary of State, and the
Coordinator had the authority to bind the government unless they expressly
delegated that authority.
8. Upon tracing the chain of authority, the court finds that it does not lead to Walsh or
Wild.
9. As the government is a repeat party in litigation, it would cost the government a lot
of money if it could be bound by the mistakes of all of its employees under the
doctrine of apparent authority.
10. Had the government wanted to enforce the contract and Woodroffe wanted it to be
declared void, it could have probably just had someone with authority ratify it or
expressly give Walsh or Wild contracting authority.
11. The dissent argues that Walsh indeed had authority given to him by the Secretary of
State, through the nature of Walsh’s office.
12. Actual authority is that which is intentionally conferred on the agent by a principal.
It can be either expressly conferred or implied from the surrounding circumstances.
GOVERNMENT CONTRACTS OUTLINE 75
However, in private transactions, an agent has apparent authority when the actions
or statements of the principal cause a third party to reasonably believe that
authority has been conferred on the agent, whether or not the principal actually
intended to confer such authority. The dissent suggests that Walsh has both kinds of
authority: implied actual authority and apparent authority.
13. Merrill held that the U.S. and its agents are not subject to the doctrine of equitable
estoppel. This doctrine, like apparent authority, is a doctrine that allows courts to
find contracts where there are none because it is fair to do so. By citing Merrill, the
majority appears to be acknowledging that the government sometimes should not
be subject to the same rules as private parties for policy reasons. Here, the majority
is holding that apparent authority does not apply to the government. Apparent
authority is a way to estop the government from using the defense that the apparent
agent did not have the authority to bind the government. In general, courts seem to
find that you cannot estop the government.
14. The dissent distinguishes this case from Merrill by point out that in Merrill, the
agent’s action was contrary to statute. In this case, Walsh was given authority to do
what he did by appointment. However, the majority would argue that Walsh was not
given any authority by statute to contract for the government.
15. This is once again an exceptionalist approach.
76 GOVERNMENT CONTRACTS OUTLINE
Download