Item 6 - Estates, capital projects and facilities update

advertisement

Item 6

Estates and Capital projects six monthly report

Produced by:

Chris Harding – Director of Estates & Facilities

Presented by:

Rob Elek – Director of Strategy & Business Development

Board of Directors Meeting

20 th November 2014

Action for Board :

For information 

For consideration

For decision

Estates & Facilities biannual report – October 2014

1.

Executive Summary

2.

Backlog Maintenance

3.

Capital works at City Road

4.

Satellite Sites

5.

Estates & Facilities directorate report a) Development of 5 Year Estates and Facilities Strategy b) Estates Compliance c) Estates Services d) Clinical Technical Services (CTS) e) Security f) Sustainability g) Telecoms h) Portering i) Interpreting Services j) Transport Services k) Domestic Services l) Catering & Hospitality m) Waste Management n) Water dispensers

17

17

18

18

13

14

15

15

10

12

7

7

5

6

2

4

19

20

20

P a g e 1

Estates & Facilities biannual report – October 2014

1. Executive Summary

This report includes an update on the Estates and Facilities directorate for the six months from

April 2014 to October 2014, and includes progress reports for:

The backlog maintenance programme and major capital projects;

Developments which do not entail direct capital expenditure, but are estates related in that they involve contractual issues relating to our occupancy at host hospitals; and

Estates & Facilities work streams and projects which fall below the threshold for board approvals, as these illustrate the scale of planned developments, and demonstrate the delivery of the estates and facilities strategy as an enabler to Our Vision of Excellence.

The executive sum mary provides a précis of the important issues for the board; the following sections include a further level of granularity if required.

The backlog maintenance programme has been successfully tendered for 2014/15 and good progress is being made on all components of the programme.

Capital works have delivered major improvements to the patient experience, service capacity and organisational resilience across a range of projects; these include:

Expansion of paediatric ocular prosthetics;

The creation of a new laser suite (to be completed in early 2015);

Significant enhancements to the main entrance corridor at City Road;

Moorfields at Ealing expansion; and

 Moorfields at St Ann’s femto-phako laser suite (due for completion in late 2014.

The Moorfields at St George’s project initially envisaged the provision of a stand-alone building that reprovided and expanded all our current accommodation. The board is aware of the issues surrounding the recent change in direction, and discussions with the host hospital are on-going with respect to both the new interim and longer-term solutions. This represents the key strategic estates risk at present.

The estates & facilities directorate section includes detailed reports for each area, the following are the key issues for the board to note:

Compliance: A compliance manager has been introduced to the directorate, whose role is to review compliance relating to Estates and Facilities across all our sites in addition to supporting the property management function.

Security: The NHS Protect Self Review Tool (SRT) work plan section 2014-15, has been completed and agreed with the Security Management Director (SMD). This has been forwarded to NHS Protect. The full SRT document will be completed in full and forwarded to

NHS Protect by November 30th 2014 in accordance with NHS Protect guidance and advice.

Catering: The Costa outlet has been successfully running for almost 12 months and a great deal of positive feedback has been received. The outlet is generating revenues for reinvestment in patient services.

P a g e 2

Estates & Facilities biannual report – October 2014

Telecoms: the new call management system (Netcall 59R) has been successfully implemented at City Road, leading to a significant improvement in switchboard performance and to the accessibility of detailed information relating to call handling at sub-speciality level – this will assist in targeting areas for improvement over the coming period.

The board requested information relating to call handling at our other locations and the following is a summary of the current position:

 None of our other sites currently have the equivalent capability of Netcall 59R;

 We are unable to interrogate host hospital’s call handling systems; and

 There is a great deal of variability in how telephone communications are handled by our services in other locations; i.e. some have direct lines whilst some are only accessible through a switchboard.

In response to these issues, we have started negotiations with Netcall and have been advised that Netcall59R can be implemented on external lines going direct to sites, and on any lines going out over our N3 links.

We are currently drafting a review to fully understand these issues and to develop plans to improve our ability to control communications at all our sites.

A potential solution could entail diverting existing phone numbers to route all incoming calls for any Moorfields site into the City Road Netcall system, which would then transfer the call to the relevant phone (including mobiles), thereby giving us full functionality across the network.

The board is asked to consider the progress made in the delivery of the backlog maintenance programme and capital projects, and the overall performance of the Estates & Facilities directorate.

P a g e 3

Estates & Facilities biannual report – October 2014

2. Backlog Maintenance

The backlog maintenance programme is refreshed on an annual basis, and continues to deliver real improvements to our estate as well as ensuring we maintain appropriate standards for patient and staff safety.

The end of year estates report will include full details of the workstreams, alongside the programme for the following year.

The main backlog works undertaken in the last six months are summarised below.

1. Fire alarm upgrade.

Works to install the new sounders and sensors commenced on 9 th December 2013 and completed in May 2014. Software system upgrading and snagging / training continues, with completion planned within Q4.

2. External façade and roofs.

Works to repair all roofs, rectify façade defects and install fall arrest systems commenced on site on 3 rd February and completed on 19 th May 2014.

3. Fire doors and compartmentation upgrade to upper floors.

The initial high priority works were completed in earlier phases of the backlog programme, lower priority works commenced in October 2014 and will complete in February 2015. All fire related backlog works are fully coordinated with the Fire Brigade, and our revised

4. Emergency lighting and Disability Discrimination Act (DDA) works package.

A full DDA audit was completed in 2013 and final designs were approved earlier this year, works are programmed to commence and complete in Q4.

5. Lift upgrade works.

Following the refurbishment of the main patient lifts a programme to upgrade all City Road lifts started in late 2013. Despite problems with the initial contractor, lift 1 (by the old main entrance) and lift 3 (by outpatients) have been completely refurbished. Works to lift 6 (the goods lift) will be undertaken as part of the 2014/15 programme.

The overall programme and scope of all backlog works is adjusted to ensure that expenditure remains within the approved affordability envelope allocated by the Capital Planning & Oversight

Group (CPOG).

The Estates department has also been addressing significant numbers of the smaller, discrete backlog maintenance issues through its minor works programme.

P a g e 4

Estates & Facilities biannual report – October 2014

3. Capital works at City Road

1. Medical Gases

This project has successfully delivered a new Liquid Oxygen Compound in the goods yard.

Previously the hospital’s oxygen supply was provided from bottled gas, this facility now operates as a standby unit. This project has mitigated a significant health & safety risk as the oxygen bottles required frequent changing by porters, and a business continuity risk as the hospital did not have resilience in supply.

2. Expansion of paediatric ocular prosthetics

The expansion to the paediatric ocular prosthetics department was completed in June 2014. This was a complex project entailing a crane-lift for the modular build and intricate phasing to minimise the impact of works on the goods yard. The expansion includes striking artwork that has been a big hit with the children, and adults, visiting the department.

3. Private patient laser suite

A new laser suite will be created on the 4th floor. This project has just started on site and will complete in early 2015.

4. Friends of Moorfields information desk

The main entrance corridor to the outpatient area represented a somewhat confusing environment for patients, and was in some need of updating. Accordingly, the Friends of

Moorfields base has been moved to a more logical location by the main entrance and the porter’s desk has been removed. The new information desk has been widely welcomed as a much needed improvement to how we support and guide patients into the hospital, as well as greatly enhancing the appearance of the hospital.

5. Health Information Hub

The purpose of this completed project is to provide patients with an area to access general patient information via leaflets or to browse our information screens, in a calm and welcoming environment. The hub was funded by the Friends of Moorfields, who also support patients seeking information in the hub; though the Director of Nursing & Allied Health Professionals is reviewing the PALS / ECLO services with a view to potentially having full-time staff based in the hub.

6. Piano

The changes in the main entrance corridor have also enabled us to divide the former Friends

‘hutch’ into an office for the outpatient matron and to create a much needed space for a grand piano. The board will recall that our grand piano, previously housed in the City Road boardroom, has been in storage for some time. We have been fortunate in that a grateful supporter of the hospital has donated a better piano, and this new addition is now installed in the main entrance corridor.

P a g e 5

Estates & Facilities biannual report – October 2014

4. Satellite Sites

Estates maintenance strategy for satellite sites

The responsibility for estates maintenance for satellite sites, and the quantum of services, varies from one location to another - ranging from the landlord (host hospital) providing all or no maintenance, and the City Road estates department directly supporting a number of sites. This inconsistent approach is confusing for operational staff, and is not an efficient or effective means of providing such a key service. As the board is aware, we piloted an improved service model at St

Ann’s and Northwick Park and following the success of the pilot, we undertook a formal tender process for the supply of the planned maintenance services and the contract was awarded to

Lorne Stewart on 1 st May; this contract also includes the flexibility to add our other satellite sites.

Some aspects of maintenance at our satellite sites that are the responsibility of our landlords have created some concern about quality. The Director of Estates & Facilities has now appointed a

Compliance Manager to follow through with all relevant landlord estates departments a list of statutory works for confirmation by the landlord that these issues have been properly addressed

(as required under the landlord and tenants act), and to ensure that Moorfields has complied with its duty of care to our staff and patients. Where this is believed to fall below the required statutory standard, or if information is not forthcoming, internal audit tests have been carried out by

Moorfields estates and results shared with the landlord to action. These are then monitored to compliance completion.

Moorfields @ Northwick Park

Medical gas systems were removed from the original Northwick Park expansion project prior to construction. These systems are required to expand the scope of surgical procedures undertaken in the theatre – a key objective to enable the “repatriation” of further work from City Road and the development of new local services.

Negotiations with the host hospital have been in progress for some considerable time as our preferred solution, to connect into the existing site medical gas system, did not appear to be achievable and the landlord appeared reluctant to give permission for Moorfields to deliver a standalone local system.

The host hospital has very recently agreed that we can connect into the existing system and the project has been re scoped and submitted for approval by CPOG of a business case and proposed installation early 2015.

Moorfields @ St George’s Hospital (SGH)

The board approved the St George’s business case in October 2013 and positive discussions have continued with SGH around the key clinical requirements (access to main theatre space etc.) and the finalisation of the development agreement and lease documentation.

These discussions have flagged up a number of clinical issues and operational constraints, around anaesthetic support to a free-standing building, the increasingly complex case-mix of our activity at this site, and the impact of SGH’s designation as a regional trauma centre. The consequence of these issues is that SGH have stated that the planned development cannot proceed in its current form. SGH have proposed an alternate, interim, solution for the vacation of Duke Elder ward that includes outpatient expansion space, and have invited Moorfields to comment on this revised

P a g e 6

Estates & Facilities biannual report – October 2014 proposal. Meetings are being progressed with the key clinical and estates representatives to progress this proposal; however suitable commercial agreements will also need to follow.

At present, it is not possible to state with any certainly what the longer term solutions may entail, though SGH have revised their position and there is an expectation that a complete Moorfields unit will be provided within SGH clinical accommodation.

Moorfields @ Ealing Expansion

The long awaited expansion to the Moorfields @ Ealing service was successfully completed in

August, with occupation by services in September 2014. This £660k project included lease arrangements for the modular build’s location.

Ealing and North West London Hospitals have now merged to create London North West

Healthcare NHS Trust; this will enable us to reopen discussions around the occupancy provisions for the main Ealing accommodation.

Moorfields @ St A nn’s – femto-phako laser suite

The estates works to create an appropriate facility to house a new femtophako laser at St Ann’s are underway with completion planned by the end of the calendar year.

5. Estates & Facilities directorate report

a) Development of 5 Year Estates and Facilities Strategy

Over the next reporting period, we will be developing a 5 Year Estates & Facilities Strategy. As part of this development we will create:

5 year forward Estates & Facilities vision and documented strategy for the period April 2015-

March 2020

Key strategic objectives framed into a Balanced Scorecard

Business planning SMART measures

The development of a Moorfields Estates & Facilities Strategy will take into account NHS initiatives such as Payment by Results, Patient Choice and especially the Privacy and Dignity agenda. As such it is essential for the Estate to meet patient expectations by providing a quality environment for treatment and healthcare service delivery, at all our sites.

The overall purpose of the Estate & Facilities Strategy will be to show how the estate is being used and how this resource can be used in the future to support the Trust in delivering its key objectives.

The Estate & Facilities Strategy will need to flow from the Trust’s Service Strategy and Business

Plans, which in turn reflect Government and local initiatives for the delivery of healthcare services.

It will also demonstrate the priority given to achieving compliance with Standards for Better Health and statutory health and safety legislation as part of the drive to improve quality.

P a g e 7

Estates & Facilities biannual report – October 2014

Overall the completed Estate Strategy aims and objectives will include:

Maximise use of the built resources available

Enable development of high quality, fit for purpose and well placed buildings

Ensure that all capital investment is linked to the Trust strategic direction

Create standard approaches to project management and business case development

Coordinate the environmental response to the needs of all

Act as an information resource across the Trust

Develop shared learning

Approach:

The approach to undertaking the strategy development will be a based on the following three stages:

1

Where are we now? Baseline Assessment (Gathering Evidence)

•Conduct full Maturity survey across Key Estates & Facilities functions to establish a Baseline

2

Where are we going? Develop Strategic Objectives

•Planning with Leadership team to establish a concept vision, mission and strategic objectives for the

Estates that are fully aligned with the Moorfields Hospital corporate strategy

3

How will we get there? Engagement and Business Planning

•Translating strategic objectives into SMART measures linked to a Balanced Scorecard

This approach is aligned to the proven methodology already used for the development of our

Corporate Strategy as detailed below.

Stage 1 – Baseline (Gathering Evidence and Analysis):

P a g e 8

8)

9)

10)

11)

4)

5)

6)

7)

Estates & Facilities biannual report – October 2014

Initially we will establish a robust baseline from which future objectives can be measured against.

This baseline will provide a reality check into whether aspirational strategic objectives can actually be achieved and at what cost to the organisation.

An “In-Depth” assessment of the 14 Elements of our Estate & Facilities Management function will focus on the strategic, operational and tactical aspects of each component of the service.

The baseline elements are detailed on the Maturity Matrix as below:

1) Strategy, Leadership and Organisational Design

2)

3)

Asset and Maintenance Management

Risk Management

Compliance and Statutory Maintenance

Safety Management

Supplier Relationship Management

Service Delivery

Customer Service

Cost and Financial Management

Help Desk and Processes

Sustainability

12)

13)

Estates & Facilities People Management

Client (Stakeholder) Management

14) Innovation and Change Management

The Gap Analysis will be referenced against Best Practice and will be supported through a detailed

SWOT and PESTLE analysis.

Stage 2 Strategic Objectives (Synthesis):

The Estates & Facilities Strategy will be aligned to the Moorfields core business strategy. Using the Moorfields “ Our Vision of Excellence” document as a guiding template, we will undertake strategic planning workshops with key Team members.

These workshops will be used to:

 Present the “ Our Vis ion of Excellence” document and establish how this impacts and links into a future Estates & Facilities strategy

Review findings from the Maturity Matrix baseline

Review detailed SWOT and Pestle Analysis

Establish a realistic and draft Estates & Facilities vision and mission

Establish strategic objectives around a Balanced scorecard

Stage 3 Engagement (Business Planning):

P a g e 9

Estates & Facilities biannual report – October 2014

A vital part of any strategic development is the engagement of key stakeholders and planning. Key stakeholders and their broad needs will include:

Moorfields executive and board who will need to approve the Estates & Facilities Strategy and particularly the proposed strategic objectives

Estates team members who will need to translate the Strategic Objectives into quantified

SMART measures

Client stakeholders who will need to gain an understanding of the strategic objectives and

SMART measures and how they will enhance service provision, reduce or mitigate risk, and be aligned with associated cost drivers

In order to achieve the above, we propose a further three workshops with key Estates team members to transform the key Balanced Scorecard Strategic Objectives into SMART annual objectives.

Project Planning:

The following key milestones will be used to monitor progress.

14 th October Workshop

– Develop SWOT and PESTLE Analysis

– Commence Maturity Matrix Data Gathering

11 th November Workshop

– Develop Balanced Scorecard Strategic Objectives (Circa 4-8)

9 th December Workshop

– Develop SMART Measures for each Strategic Objective

13 th January Workshop

– Present Final Strategy

– Propose Change and Transformation Plan b) Estates Compliance

An Estates and Facilities Compliance Manager has been introduced to the directorate, whose role is to review compliance relating to Estates and Facilities across all our sites in addition to supporting the property management function.

The Head of Estates and Maintenance and E&F Compliance Manager have started to strengthen relationships with our host sites, resolving issues that had not been concluded and supporting representation at each site from City Road.

The host trust of each of our satellite site locations have been requested to provide information to support the validation of statutory compliance of occupied areas within their site. All reports are now stored on EMIS, the bespoke Estates Management Information System which is now to be utilised to its fullest potential.

P a g e 10

Estates & Facilities biannual report – October 2014

Lease management: The Director of Estates and Facilities and E&F Compliance Manager are currently in negotiation with Croydon University Hospital re service charge and Barnet Enfield and

Haringey Mental Health NHS Trust (St Ann ’s Hospital) in relation to lease renewal.

Theatre validation: Below shows the sites whereby the Trust occupies one or more surgical facilities on a sole use or shared basis and the outcome of the validation. Remedial works have been identified in the supporting reports and are directed to the host trust for completion and rebalancing.

Satellite site Validation

2013/2014

Pass/Fail Validation

2014/2015

Pass/Fail

Bedford

City Road

Croydon

Darent Valley

27/08/2014 Fail

07/06/2014

27/05/2014

14/04/2014

Pass

Fail

Validation due

Pass

Ealing

Mile End 23/05/2014

Northwick Park 24/08/2013

Potters Bar

Queen Mary’s

Pass

Pass

Not received

19/08/2014

18/10/2014

22/04/2014

Scheduled

Scheduled

Pass

04-05/06/2014 Air flows requested

St Ann’s

St Georges

Legionella Control: For those sites that do not form part of the Trust’s water monitoring assurance program, including Barking, Bedford, Croydon, Homerton, Loxford, Queen Mary’s,

Stratford and Watford, information has been requested in relation to their regimes to test for legionella. Not all sites have responded to the initial request to obtain this information, but this will be covered in the meeting program which will be set up with each host site as part of our ongoing compliance validation.

Fire Risk Assessment: The annual fire risk assessments have been completed in the majority of our satellite sites. The newer sites including Croydon, Darent Valley, Purley and Stratford have not yet been visited. City Road is scheduled to be undertaken. Recommendations have been forwarded to the relevant host trust for review and action. The mandatory Fire Safety Working

Group has been reinstated and met for the initial meeting on 1 st August 2014.

Policies: The following policies have been taken to the next Risk and Safety Committee for approval:

Fire Safety (including Theatre Evacuation Plan) – Revised and updated

Management of Contractors – New policy

14/10/2013 Pass 15-19/09/2014 Scheduled

06/05/2014 Fail

P a g e 11

Estates & Facilities biannual report – October 2014 c) Estates Services

The 2014 statutory insurance inspections are up to date.

The Estates department, previously located outside the main hospital, has now been centralised and is located in the lower ground floor of the main hospital building, this now also includes

Estates, Facilities, CTS and Capital Projects. To accommodate the increased number of clinical services provided, representation from the Estates department is on-site seven days a week.

An Estates Manager has been recruited, replacing the former Maintenance Manager and is operationally responsible for the estate and supporting our satellite site functions on matters concerning Mechanical and Electrical services.

Two members of the team have been awarded Employee of the Month – Kate Kosa, Catering

Administrator and Garry Auger, Head of Estates and Maintenance.

Approved persons: The Trust now has responsible persons in place, as outlined below:

Appointed persons for medical gases

Appointed person (limited authority

Appointed persons for LV

Garry Auger, Head of Estates and Maintenance

Paul Ashton, Senior Maintenance Manager

Andrew Taylor, Maintenance Supervisor

Andrew Taylor, Maintenance Supervisor

Dean Carter, Electrical Craftsperson

Garry Auger, Head of Estates and Maintenance Responsible person for water quality

Nominated fire manager Garry Auger, Head of Estates and Maintenance

Completed projects:

Conversion of Central Stores into a new Health Records office, housing 33 people.

Conversion of the maintenance workshop into the Estates and Facilities office.

Conversion of the boiler house into a new workshop for the maintenance team.

Refurbished ASU, 205-207 City Road (2 nd and 3 rd floors), John Saunders Suite and HR offices

The CHP plant is now exporting electricity and credit is now being received from the electricity board for this.

Energy saving projects as detailed in the annual sustainability report

Automated and computer controlled taps for legionella control and water quality.

Installation of new hand hygiene work stations that have received positive feedback.

Trialled new digital taps in Mackellar, Day Care and Sedgwick wards.

Updated medical gas and medical air alarms

.

Current schemes:

Refurbishment of eight theatres at City Road to be compliant under HTM 03-01.

Refurbishment and reallocation of the Estates Helpdesk.

New chiller plant being installed that will provide sufficient capacity for 24 hour cooling across the building.

E-Permits; All contractors requiring a Permit to Work will be required to submit a request with supporting documentation prior the commencement of works.

Asset tracking and management o Physical assets o Patient safety and throughput o Staff safety and work flow optimisation

A new module of EMIS named Agility is being rolled out, a new computerised maintenance management system recording all assets and their location.

P a g e 12

Estates & Facilities biannual report – October 2014 d) Clinical Technical Services (CTS)

CTS have made huge progress in understanding and verifying the management of specialist ophthalmic medical equipment enabling compliance in maintenance, repairs and procurement. The year to date has seen a material increase in the completeness of inventory records leading to stronger internal controls, greater accountability and fact based future capital spending.

During this reporting period the following are the key actions underway or completed.

We procured, commissioned and installed medical equipment at three new sites, Croydon,

Purley and Darent Valley; and commissioned and installed new medical equipment purchased by host site at Sir Ludwig Guttman Health & Wellbeing Centre in Stratford, all in a timely manner to ensure service delivery.

Ghana Korle bu Hospital medical equipment commissioning project delayed.

61% increase of registered medical devices input into our medical equipment database eQuip since March 2012 (1960 devices). Current recorded inventory is 3211 devices.

We procured, commissioned and installed new equipment for the Ealing expansion development in a timely manner to ensure service delivery.

We procured, decommissioned, installed and commissioned 18 Carl Zeiss HFAs and 11 upgrades funded through Moorfields Eye Charity in compliance with Personal Confidential Data

(PCD) procedure.

 All devices at City Road, St Georges, Mile End, St Ann’s, Barking, Loxford and Purley have been digitally photographed and uploaded to the CTS e-drive.

Progress has been made in relation to managing devices requested by our Medical

Consultants for evaluation and trial. In total we have supported and managed 11 medical equipment trails including lasers, OCT, IOLs, Phacoemulsifier, Vitrectomy and non-mydriatic cameras.

17 training sessions for medical equipment were organized by CTS with good attendance for all clinical staff and recorded on My Learning Centre.

57 medical devices were decommissioned following the process for decommissioning and information governance systems procedures ensuring Personal Confidential Data (PCD) compliance.

102 medical devices were procured, commissioned and installed during this period. We have added a new task to our commissioning procedure which includes “Smart Water Forensically

Coded” watermarking of devices as a deterrent to theft of Trust equipment.

Jobs logged per month by Estates Helpdesk have tripled since January 2012 demonstrating that our internal processes are working. We continue to encourage staff to complete and submit the Medical Equipment Job Form located on the Trust intranet homepage with good effect. Consultant Ophthalmologists and Nurse Managers have responded positively to this change enabling increase data input, accuracy of the data providing evidence to support decision making.

Employment of 3 Clinical Engineers into substantive posts has significantly increased our ability to repair in-house enabling quick turnaround of working equipment back into service.

We now average 45 repairs a month compared to 4 per month during the same period in 2012.

We achieved 100% score in our recent internal audit of our maintenance and repair procedures demonstrating high level of compliance.

Planned preventative maintenance (PPM) for medical equipment is on target.

Internal Audit NHSLA 6 monthly (January to June 2014) CTS report (excluding theatre data) submitted to Medical Devices Committee August 2014.

P a g e 13

Estates & Facilities biannual report – October 2014 e) Security

Below are the summary of key points relating to the security service

The NHS Protect Self Review Tool (SRT) work plan section 2014-15, has been completed and agreed with the Security Management Director (SMD). This has been forwarded to NHS

Protect. The full SRT document will be completed in full and forwarded to NHS Protect by

November 30 2014 in accordance with NHS Protect guidance and advice.

The NHS Protect Organisational Crime Profile 2014-15 has been completed and forwarded to

NHS Protect.

The 2013-14 Security Manager & LSMS Action Plan was reviewed by the SMD and LSMS, updated to take into account the work that had been completed during this period and the work to be completed during 2014-15. This revised action plan was agreed with the Trust SMD

The NHS Protect Organisational Crime Profile has been completed and forwarded to NHS

Protect.

Satellite visits have been carried out in accordance with the Security Manager & LSMS action plan and where security weaknesses are identified reports produced and forwarded to the general manager with actions recommendations for their consideration.

 Security visits to “new satellite sites” prior to becoming operational have been carried out at

MEH Ludwig Guttmann, MEH Purley, MEH Croydon and MEH Dartford.

Security risk review carried out at Upper Wimpole Street after burglary reported at the building.

A review of CCTV system at City Road has been completed, and a business plan agreed. A budget for the new CCTV system has been agreed. The expectation is that this will be installed and operational by the end of 2014

Meeting with senior staff Moorfields Pharmaceuticals regarding security issues, policies and procedures. Agreement to “oversee” security risk review

Policies

CCTV policy has been agreed at the Risk & Safety committee and approved by Man Ex.

Violence and Aggression policy agreed at the Risk and Safety Committee, approve by Man

Ex.

Draft Lockdown policy under review for presentation at Risk and Safety Committee

The Head of Security LSMS is fully engaged with:

Full engagement with NHS Protect processes and procedures, attendance at NHS Protect quarterly meetings. All NHS Protect requirements at this time have been met and relevant information and documents sent. SRT Work plan, Organisational Crime Profile 2014-15,

Violence Against Staff figures (VAS)

Attendance at Risk and Safety Committee meetings.

Attended all corporate induction sessions, presenting on security related matters. Two

Hundred and Twenty Three (223) attendees 2013-14. Attendees during this period one hundred and eighty seven (187)

Liaison and partnership working with the police to provide evidence and statements.

Working with EPL and local police to arrange Project ARGUS event.

P a g e 14

Estates & Facilities biannual report – October 2014 f) Sustainability

As per the previous report a revised Sustainable Development Strategy for the Health and

Care System 2014 – 2020 was released in January 2014. A review of the process has been completed and we are now in a position to start engaging key stakeholders within the organisation to improve our sustainability credentials.

To support these requirements a revised Sustainable Development Management Plan (SDMP) has been developed and is currently in draft format for review. This document, once reviewed, will be launched and the implementation phase started.

Within the SDMP it is the intention to use the NHS Good Corporate Citizen Model to ensure that each aspect of sustainability is embedded within Moorfields Eye Hospital’s operations and activities. A maturity matrix has been created to gauge current progress, set milestones and track progress over the coming years.

The Good Corporate Citizen Model covers 11 key activity areas:

Transport;

Procurement;

Facilities Management;

Workforce;

Community Engagement;

Partnership and Planning;

Buildings;

Climate Change Adaptation;

Resource use, scarcity and continuity;

Social and community impacts;

Models of care.

In order to discuss these requirements in detail, a communication to all key stakeholders has been sent and a meeting will take place at the start of October. Following this, the Sustainability Steering

Group will be reinstated to lead this process. Progress will be reported in the six-monthly/annual

Board Reports and Boards Sustainability Papers. g) Telecoms

Following the implementation of the new system (Netcall 59R), switchboard performance has improved against the two key measures (KPI 1 - 80% calls to be answered within 15 seconds, KPI

2 - 100% of calls to be answered within 60 seconds)

Implementation of 59R and additional staff member

P a g e 15

Estates & Facilities biannual report – October 2014

We were previously asked to provide 2 additional staff members to support this activity however, to achieve this we would have to spend around £16k upgrading the operators console system. With this in mind we trialled one additional member of staff, restructured current staff and with the implementation of Netcall 59R we have seen an increase in monthly performance for KPI 1 from

48% to 74% and KPI 2 from 70% to approximately 94%. These measures have been consistent month-on-month and we do occasionally hit the required service levels. If we want to exceed this on a regular basis then an additional person will need to be brought into this area - this would increase the output on this KPI to about 85-90% of calls being answered within 15 seconds.

Abandoned calls

On average the switchboard are receiving approximately 20,000 calls per calendar month; of these approximately 1200 calls (5.6%) of calls are abandoned. Please note this was approximately 10% of calls prior to the implementation of 59R.

Following a detailed review into these 1200 abandoned calls, it would appear that approximately

1000 of these calls are abandoned within 60 second - which suggests that patients are using the automated service effectively but that calls are not being answered in the departments and bounced back to the switchboard at which point the caller hangs up directly. Below gives a summary of the abandoned call detail:

A report was completed for August:

Seconds Abandoned Abandoned Percentage

0-60

60-120

934

91

85.4%

8.3%

120 + 68 6.2%

Total abandoned calls 1093

We are currently working on the additional 12 call centres that went live mid-September. The departments effected by the change are:

Booking centre

Outpatients (9 different mini-call centres)

Medical enquiry line; and

Optometry

It is important that consideration is now given to recruiting of a telecoms supervisor / manager to support the current new call centres, future call centres and help support the telecoms strategy that needs to be developed this coming year. (Unify (previously Siemens) will not be supporting the current phone systems we have at City Road, Provost and Ebenezer St from 2016).

P a g e 16

Estates & Facilities biannual report – October 2014 h) Portering

The former porters desk was removed as part of the reconfiguration in the main entrance corridor area; this was enabled by the planned implementation of a portering software system – Portertrac; this is used in over 100 NHS and enables the rapid entry and allocation of jobs, provides an ‘at a glance’ view of the operational status of portering activities to enable management to focus on the most urgent requirements.

Additional wheelchairs have also been purchased to support patient transfer from front of house to clinics.

Postage spend is on an upward trend. We are looking at the operational impact of processing mail in a different way to provide more information on postage used by department. Consideration is being given to tightening processes around 1 st and 2 nd class mail, and alternate forms of communication.

90 000

80 000

70 000

60 000

50 000

40 000

30 000

20 000

10 000

0

Postage spend - per month i) Interpreting Services

The outsourced interpreting and translation framework agreement continues to provide a high quality communication support to our patients with no KPI failures reported, across all sites. It is noted that the interpreting budget is held by Facilities but controlled by clinical users

We are currently reviewing the Interpreting services at Moorfields. A savings proposal has been submitted by 'thebigword' and is currently being reviewed by the Head of Facilities. The Facilities department will focus on:

Telephone interpreting

Capping visits to 3 hours

Language days

The Director of Nursing and Allied Health Professionals is leading the strategic review of interpreting services.

P a g e 17

Estates & Facilities biannual report – October 2014 j) Transport Services

The transport contract continues to deliver higher volumes that anticipated.

Feb-14 Mar-14 Apr-14 May-14 Jun-14

Inbound

Total Inward Journeys

Indicative number of journeys

Over activity number

Over activity percentage

1495

1414

81

5.4%

1769

1414

355

20.1%

1631

1414

217

13.3%

1577

1414

163

10.3%

1687

1414

273

16.2%

Late failures Nos

Late failures %

Outbound

Total Outbound Journeys

Indicative number of journeys

Over activity number

Over activity percentage

69

4.6%

64

3.6%

1357

1414

-57

1584

1414

170

-4.20% 10.73%

68

4.2%

1513

1414

99

6.54%

39

2.5%

1445

1414

31

2.15%

57

3.4%

1566

1414

152

9.71%

Jul-14

1760

1414

346

19.7%

66

3.8%

1627

1414

213

13.09%

Late failures Nos 36 50 82 80 55 68

Late failures % 2.7% 3.2% 5.4% 5.5% 3.5% 4.2%

Facilities have adopted a supplier relationship management process (SRM) whereby contract meetings and performance reviews are managed effectively. Whilst there is some flexibility with

Medical Services within the SLA’s and KPI’s the failures are being reviewed with close scrutiny to support improving late failures. Trend analysis forms part of the contract review meetings and over the next few months we will be implementing a continuous improvement programme (CIP) and will be expecting Medical Services to deliver performance improvements over the coming months. k) Domestic Services

The domestic service continues to be of a satisfactory standard. We are currently discussing the use of an external auditor to review the cleaning standards at City Road and possibly satellite sites.

This proposal will be developed over the next six months.

The annual Patient-Led Assessment Care Environment took place on Monday 24th March 2014.

The assessment covered four key areas as outlined below, which shows the national average score in line with the Trust score

2014 - Score

National

Average

2014 - Score

Moorfields

Eye Hospital

2013

– Score

Moorfields

Eye Hospital

Cleanliness 97.25% 99.62% 93.69%

Food and Hydration

Privacy Dignity and Wellbeing

88.79%

87.73%

Condition Appearance and Maintenance 91.97%

100%

88.31%

99.10%

100%

89.33%

89%

Due to Moorfields being an ambulatory care hospital, the score for food and hydration, although internally recognised as receiving a percentage score, will not be published to a wider audience.

P a g e 18

Estates & Facilities biannual report – October 2014 l) Catering & Hospitality

Below is summary of the key points within catering over the reporting period.

The full supply chain within catering has now been added to the eProcurement system, ensuring that we get the best price from suppliers. The reporting dashboard is shown below for information.

A food hygiene inspection, undertaken by an external body has recently been completed. This audit included a physical inspection of the main kitchen, restaurant, ward areas and children’s café.

This also included an audit of the Hazard Analysis and Critical Control Point (HACCP) Food Safety

Management Programme and documentation systems.

The key messages from this inspection are that all standards, systems and process are of a good standard, and have significantly improved in all areas over the past 12 months. A plan of action was put in place to resolve areas identified as needing attention. All outstanding actions have been completed. This will be an ongoing process to ensure full compliance within the trust.

The Costa outlet has been running successfully for almost 12 months and all complaints / comments for this area have been resolved. The outlet has provided over £40k in turnover share in the first 6 months of the calendar year, over and above the base rent, for reinvestment in patient services.

P a g e 19

Estates & Facilities biannual report – October 2014 m) Waste Management

The retendering of the general and clinical waste has now been completed and the new contracts are now in place. General waste is now managed by Bywaters and clinical waste was renewed with SRCL. These will deliver combined savings of approximately £54,500 per annum based on historic waste volumes. The new compactor will deliver vastly improved hygienic storage of waste pending collection.

The chart below details the waste volumes and segregation percentages as from April 2014 to date. n) Water dispensers

The Estates and Facilities department has now taken over the management of the water machines at Moorfields. This will mean that clinical staff will no longer have to raise purchase requests on an annual basis. There are currently 70 water machines which would require 70 purchase requests to be raised, and processing of numerous invoices. This has now been consolidated to one invoice per annum and two service visits.

Chris Harding

Director Estates and Facilities

P a g e 20

Download