Thursday, Mar 1 - Chapter 6 - Project Time Management

advertisement
Chapter 6:
Project Time Management
Using Critical Chain Scheduling,
PERT, and MS Project 2003
Thursday, March 1
Information Technology Project Management,
Fourth Edition
Today’s Schedule

Complete Chapter 6 Time
Management
Critical Chain Scheduling
 PERT Analysis
 Using MS Project

Assignments #7 and #8 are posted
 Test #2 on Calendar

Information Technology Project
Management, Fourth Edition
2
Overview of Project Time
Management Processes

Activity definition: Identifying the specific
activities must be performed to produce the
project deliverables.
 Activity sequencing: Identifying and
relationships between project activities.
 Activity resource estimating: Estimating how
many resources should be used.
 Activity duration estimating: Estimating the
number of work periods needed to complete
individual activities.
Information Technology Project
Management, Fourth Edition
3
Overview of Project Time
Management Processes (cont’d)

Schedule development: Analyzing activity
sequences, activity resource estimates, and
activity duration estimates to create the project
schedule.
 Schedule control: Controlling and managing
changes to the project schedule.
Information Technology Project
Management, Fourth Edition
4
What do you say …

From your text, page 240,
Discussion Questions 1 through 5
Information Technology Project
Management, Fourth Edition
5
Gantt Chart for Software Launch
Information Technology Project
Management, Fourth Edition
6
SMART Criteria

Adding Milestones to Gantt Charts

Specific

Measurable

Assignable

Realistic

Time-framed
Information Technology Project
Management, Fourth Edition
7
Using Critical Path Analysis to
Make Schedule Trade-offs

Free slack or free float - time an activity can be
delayed without delaying the early start of any
immediately following activities.
 Total slack or total float - time an activity can be
delayed from its early start without delaying the
planned project finish date.
 A forward pass through the network diagram
determines the early start and finish dates.
 A backward pass determines the late start and
finish dates.
Information Technology Project
Management, Fourth Edition
8
Multitasking Example
Multitasking often adds time and
increases risk level of project
Information Technology Project
Management, Fourth Edition
9
Critical Chain Scheduling

Attempts to minimize multitasking, which
occurs when a resource works on more
than one task at a time.

Critical chain scheduling

considers limited resources when creating a
project schedule

includes buffers to protect the project
completion date.
Information Technology Project
Management, Fourth Edition
10
Buffers and Critical Chain

Parkinson’s Law states that work expands
to fill the time allowed.


People often add a buffer to each task and use
the additional time whether it’s needed or not.
Critical chain scheduling removes buffers
from individual tasks and instead creates:


A project buffer or additional time added before the
project’s due date.
Feeding buffers or additional time added before
tasks on the critical path.
Information Technology Project
Management, Fourth Edition
11
Example of Uncertainty in Model
Information Technology Project
Management, Fourth Edition
12
Program Evaluation and Review
Technique (PERT)

Estimate project duration when there is a
high degree of uncertainty about the
individual activity duration estimates.

PERT uses probabilistic time estimates:

Duration estimates based on using optimistic,
most likely, and pessimistic estimates of activity
durations, or a three-point estimate.
Information Technology Project
Management, Fourth Edition
13
PERT Formula and Example

PERT weighted average =
optimistic time + 4X most likely time + pessimistic time
6

Example:
PERT weighted average =
8 workdays + 4 X 10 workdays + 24 workdays = 12 days
6
optimistic time= 8 days
most likely time = 10 days
pessimistic time = 24 days
Therefore, you’d use 12 days on the network diagram instead of 10 when
using PERT for the above example.
Information Technology Project
Management, Fourth Edition
14
Perform reality checks on
schedules

Allow for contingencies.

Don’t plan for everyone to work at 100 percent
capacity all the time.

Hold progress meetings with stakeholders and
be clear and honest in communicating
schedule issues.

If you know the project completion date will slip,
negotiate with the project sponsor.
Information Technology Project
Management, Fourth Edition
15
Words of Caution on Using
Project Management Software

Many people misuse project management
software because they don’t understand important
concepts and have not had training.

You must enter dependencies to have dates
adjust automatically and to determine the critical
path.

You must enter actual schedule information to
compare planned and actual progress.
Information Technology Project
Management, Fourth Edition
16
You try it …
From your textbook
Chapter 6, page 241, #4
Look at the tasks and as a class,
we’ll develop Duration Estimates to use
for the homework
 Complete #3, Using MS Project, with a
partner

Information Technology Project
Management, Fourth Edition
17
For Tuesday, March 13
Complete Chapter 6
 Complete Assignment #7
 Begin Assignment #8

Information Technology Project
Management, Fourth Edition
18
Download