Managing Projects Project Management Questions What activities are required to complete a project and in what sequence? When should each activity be scheduled to begin and end? Which activities are critical to completing the project on time? What is the probability of meeting the project completion due date? How should resources be allocated to activities? Tennis Tournament Activities ID Activity Description Network Node 1 Negotiate for Location A 2 Contact Seeded Players B 3 Plan Promotion C 4 Locate Officials D 5 Send RSVP Invitations E 6 Sign Player Contracts F 7 Purchase Balls and Trophies G 8 Negotiate Catering H 9 Prepare Location I 10 Tournament J Immediate Predecessor 1 3 3 2,3 4 5,6 5,7 8,9 Duration (days) 2 8 3 2 10 4 4 1 3 2 Notation for Critical Path Analysis Item Activity duration Symbol t Definition The expected duration of an activity Early start ES The earliest time an activity can begin if all previous activities are begun at their earliest times Early finish EF The earliest time an activity can be completed if it is started at its early start time Late start LS The latest time an activity can begin without delaying the completion of the project Late finish LF The latest time an activity can be completed if it is started at its latest start time Total slack TS The amount of time an activity can be delayed without delaying the completion of the project Scheduling Formulas ES = EFpredecessor (max) (1) EF = ES + t (2) LF = LSsuccessor or (min) (3) LS = LF - t (4) TS = LF - EF (5) TS = LS - ES (6) Tennis Tournament Activity on Node Diagram TS A2 C3 START B8 F4 D2 G4 E10 I3 H1 ES EF LS LF J2 Early Start Gantt Chart for Tennis Tournament ID A Activity Days 2 C Negotiate for Location Contact Seeded Players Plan Promotion D Locate Officials 2 E I Send RSVP 10 Invitations Sign Player 4 Contracts Purchase Balls 4 and Trophies Negotiate 1 Catering Prepare Location 3 J Tournament B F G H 2 3 4 5 6 2 2 2 2 2 3 3 8 3 2 Personnel Required Critical Path Activities Activities with Slack 1 Day of Project Schedule 7 8 9 10 11 12 13 14 15 16 17 18 19 20 3 3 3 3 2 1 1 1 2 1 1 1 1 Resource Leveled Schedule for Tennis Tournament ID A Activity Days 2 C Negotiate for Location Contact Seeded Players Plan Promotion D Locate Officials 2 E I Send RSVP 10 Invitations Sign Player 4 Contracts Purchase Balls 4 and Trophies Negotiate 1 Catering Prepare Location 3 J Tournament B F G H 2 3 4 5 6 Day of Project Schedule 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2 2 2 2 2 2 2 8 3 2 Personnel Required Critical Path Activities Activities with Slack 1 2 2 2 2 2 2 3 2 2 2 2 1 1 Incorporating Uncertainty in Activity times F(D) P(D<A) = .01 P(D>B) = .01 A optimistic M most likely D B pessimistic TIME Formulas for Beta Distribution of Activity Duration Expected Duration _ D A4M B 6 Variance B A V 6 2 Note: (B - A )= Range or 6 Activity Means and Variances for Tennis Tournament Activity A B C D E F G H I J A 1 5 2 1 6 2 1 1 2 2 M 2 8 3 2 9 4 3 1 2 2 B 3 11 4 3 18 6 11 1 8 2 D V Uncertainly Analysis Assumptions 1. Use of Beta Distribution and Formulas For D and V 2. Activities Statistically Independent 3. Central Limit Theorem Applies ( Use “student t” if less than 30 activities on CP) 4. Use of Critical Path Activities Leading Into Event Node Result Project Completion Time Distribution is Normal With: _ D For Critical Path Activities 2 V For Critical Path Activities Completion Time Distribution for Tennis Tournament Critical Path Activities A C E I J D 2 3 10 3 2 = 20 V 4/36 4/36 144/36 36/36 0 2 188/36 = 5.2 = Question What is the probability of an overrun if a 24 day completion time is promised? Z 52. 2 Z X 24 20 5.2 Z 175 . 24 P (Time > 24) = .5 - .4599 = .04 or 4% Days Costs for Hypothetical Project Total Cost Cost Indirect Cost Opportunity Cost Direct Cost (0,0) Duration of Project Schedule with Minimum Total Cost Activity Cost-time Tradeoff Cost C* Crash Slope is cost to expedite per day Normal C D* D Activity Duration (Days) Cost-Time Estimates for Tennis Tournament Activity A B C D E F G H I J Time Estimate Normal Crash 2 1 8 6 3 2 2 1 10 6 4 3 4 3 1 1 3 2 2 1 Total Direct Cost Normal Crash 5 15 22 30 10 13 11 17 20 40 8 15 9 10 10 10 8 10 12 20 115 Expedite Cost Slope Progressive Crashing Project Duration 20 19 18 17 16 15 14 13 12 Activity Crashed Normal Project Paths A-C-D-G-I-J A-C-E-I-J A-C-E-H-J A-C-F-H-J B-F-H-J Direct Cost 115 Normal Duration 16 20 18 12 15 Indirect Cost 45 41 37 33 29 25 21 17 13 Opportunity Cost 8 6 4 2 0 -2 -4 -6 -8 Duration After Crashing Activity Total Cost 168 Applying Theory of Constraints to Project Management Why does activity safety time exist and is subsequently lost? 1. Dependencies between activities cause delays to accumulate. 2. The “student syndrome” procrastination phenomena. 3. Multi-tasking muddles priorities. The “Critical Chain” is the longest sequence of dependent activities and common resources. Replacing safety time with buffers - Feeding buffer (FB) protects the critical chain from delays. - Project buffer (PB) is a safety time added to the end of the critical chain to protect the project completion date. - Resource buffer (RB) ensures that resources (e.g. rental equipment) are available to perform critical chain activities. Accounting for Resource Contention Using Feeding Buffer NOTE: E and G cannot be performed simultaneously (same person) A2 C3 START D2 FB=7 G4 E10 I3 J2 FB=5 B8 F4 H1 Set feeding buffer (FB) to allow one day total slack Project duration based on Critical Chain = 24 days Incorporating Project Buffer NOTE: Reduce by ½ all activity durations > 3 days to eliminate safety time A2 C3 START D2 E5 B4 F2 FB=2 G2 I3 H1 J2 PB=4 FB=3 Redefine Critical Chain = 17 days Reset feeding buffer (FB) values Project buffer (PB) = ½ (Original Critical Chain-Redefined Critical Chain)