Stakeholder Meeting #1 June 14, 2001 March 11, 1995 Opening Remarks and Agenda Overview June 14, 2001 Congressman Sam Farr’s Office — Alec Arago County of Monterey — Bill Phillips, Deputy County Administrator County of Santa Cruz — Susan Mauriello, County Administrator Agenda Overview — Tim Gilbert, MIG, Inc. Opening Remarks and Agenda Overview Today’s Meeting Purpose To provide stakeholders with an overview of the project and and planning process. Get input regarding project issues and opportunities. Today’s Agenda I. II. III. IV. V. VI. June 14, 2001 Welcome Project Background & Planning Process Structure Discussion of Visions, Goals, and Expectations Project Challenges and Opportunities Discussion of Issues, Opportunities and Constraints Summary and Next Steps Project Background The Problem— Insufficient Flood Protection June 14, 2001 Project Background The Problem - Long History of Floods and Planning Efforts June 14, 2001 Project Background The Problem - Long History of Floods and Planning Efforts 1936 Federal Flood Control Act authorizes flood control . 1949 Levee System Construction is completed along Pajaro River and Salsipuedes Creek 1955 First major flood event to breach levees 1966 Federal Flood Control Act authorizes new project 1974-5 Local community declines to support any identified project alternative 1982/6 Flooding occurs along Salsipuedes/Corralitos Creeks 1995 Major flood event breaches Pajaro River levees; flows exceed design capacity 1997 Flooding occurs along Corralitos Creek 1999 Pajaro River mainstem is combined with Salsipuedes/ Corralitos Creek project 2000 Corps of Engineers agree to Community Planning Process June 14, 2001 Project Goal Desired outcome of the Community Planning Process: June 14, 2001 Achieve agreement on a community-based concept plan for Pajaro River flood protection. Project Goal The Phase I Challenge… Develop a Community Concept Plan for Detailed Study No Build June 14, 2001 Community Concept Plan 1974 & 1996 Corps Plans Planning Process and Structure Phase I Concept Plan — November 2001 Phase II 2002 Final Design & Environmental Certification — Phase III 2003 Federal Funding & Authorization — Phase IV Initiate Construction — 2004 Phase V Project Completion — 2008 June 14, 2001 Planning Process and Structure Project Sponsors: Monterey and Santa Cruz Counties U.S. Army Corps of Engineers Stakeholders: June 14, 2001 31 Pajaro Valley organizations, constituency representatives, and regulatory agency stakeholders to work together to achieve a consensus Concept Plan, convened by Congressman Sam Farr Planning Process and Structure Stakeholders: City of Watsonville Dave Tavarez-Town of Pajaro Joseph Rosa-Town of Pajaro Vince Carrillo-Town of Pajaro John Martinelli-Santa Cruz Richard Uyematsu-Santa Cruz Karen Miller-Monterey Patricia Sakata-Monterey Jim Rider-Farm Bureau June 14, 2001 CA Coastal Commission-Tami Grove CA Fish & Game-Patricia Anderson CA Coastal Conservancy-Patsy Heasly US Fish & Wildlife-Amelia Orton-Palmer National Marine Fisheries –Joyce Ambrosius Monterey Bay Marine Sanctuary- Holly Price Wetlands Watch-Chris Johnson-Lyons Sierra Club-JoAnn Baumgartner Elkhorn Slough -Mark Silberstein Melanie Mayer Gideon Residents in Floodplain Bill Mancovich-Santa Cruz Ed Kelly-Santa Cruz Diane Young-Monterey Karen Sambraillo-Pajaro Local Environmental Organizations Regulatory Agencies Business Representatives Farm Representatives in Floodplain Carlos Palacios-City Manager Town of Pajaro Vergie Neighbors-Santa Cruz Dan Hernandez-Santa Cruz Diane Cooley-Monterey John Kasunich-Monterey Community Organizations Casa de la Cultura-Sister Rosa Delores Action Pajaro Valley-Lisa Dobbins Com. Alliance Family Farmers-Sam Earnshaw Planning Process and Structure How we are organized to accomplish Phase I … 2001 MAY JUNE Project Primer Stakeholder Issues Stakeholder Meeting #1 JULY AUGUST SEPTEMBER OCTOBER Design Options Design Options Urban Areas Rural Areas Draft Concept Stakeholder Meeting #3 Stakeholder Meeting #4 Stakeholder Meeting #2 NOVEMBER Final Concept Stakeholder Meeting #5 Community Focus Groups, Stakeholder Interviews, Bi-lingual Outreach Working Group June 14, 2001 Working Group Working Group Working Group Working Group Working Group Working Group Planning Process and Structure The Stakeholder Process is supported by a Working Group: Working Group Role… • Listen to Stakeholders • Provide technical answers to Stakeholders • Hydraulics • Environmental • Finance • Initiate project design options for Stakeholder discussion and debate. June 14, 2001 Planning Process and Structure Working Group…Resource to Stakeholders City of Watsonville Army Corps of Engineers David Koch—Public Works Director Steve Palmisano—Environmental Proj. Manager Santa Cruz County Susan Mauriello—County Administrator Tom Bolich — Public Works Director Peter Cota-Robles — Zone 7 Project Manager Ken Hart-Environmental Coordinator Consultants Arijis Rakstins — Project Management Erich Bluhm —Project Manager Jim Howells — Project Manager Dave Dickson—MIG, Inc. Tim Gilbert—MIG, Inc. Ed Wallace — NW Hydraulics Inc. Ken Myers — HDR Engineering Inc. Rick Swift-CH2M Hill Engineering Inc. Monterey County Bill Phillips — Deputy CAO Curtis Weeks — MCWRA General Manager Joe Madruga — Zone 1 Project Manager Scott Hennessey—Planning Director Project Oversight Observer June 14, 2001 Alec Arago—U.S. Congress Member Sam Farr Patsy Heasly, CA Coastal Conservancy Planning Process and Structure The role of consultant team in the process… • Facilitate consensus-based process • MIG, Inc. • Conduct outreach to diverse constituency groups; • 6 Focus Group Meetings-coordinated through the Stakeholders- MIG, Inc. • Provide the necessary technical data and research: • Northwest Hydraulic Consultants (NHC) Inc. • CH2MHill Engineering Inc. June 14, 2001 Planning Process and Structure Concurrent Army Corps of Engineers Milestones… 2001 JUNE JULY Begin EIS/EIR Scoping AUGUST SEPTEMBER OCTOBER Develop and Examine Environmental Baseline Conditions June 21 NOVEMBER Select Alternatives for Detailed EIR/EIS Final Community Concept Stakeholder Meeting #1 June 14, 2001 Stakeholder Meeting #2 Stakeholder Meeting #3 Stakeholder Meeting #4 Stakeholder Meeting #5 Planning Process and Structure The role of general government elected officials in the process… • Congress Member Sam Farr, 17th District • Senator Bruce McPherson, 15th District • Assembly Member, Speaker Pro Tem Fred Keeley, 27th District • Assembly Member Simon Salinas, 28th District • Supervisor Tony Campos - Santa Cruz County, 4th District • Supervisor Ellen Pirie - Santa Cruz County, 2nd District • Supervisor Lou Calcagno - Monterey County, 3rd District • Mayor Chuck Carter - City of Watsonville, 3rd District • Council Member Betty Bobeda - City of Watsonville, 7th District June 14, 2001 Project Approvals-Who Decides? Environmental Impact Report (NEPA) Environmental Impact Statement 401 Water Quality Permit Project Cooperation Local Finance Plan Corps of EngineersDC APPROVAL Monterey & Santa Cruz Boards of Supervisors APPROVAL Central Coast Regional Water Quality Control Board APPROVAL City of Watsonville REG AUTHORITY USFWS NMFS EPA REG AUTHORITY June 14, 2001 CA Coastal Commission CA Fish & Game REG AUTHORITY State Water Quality Control Board Santa Cruz & Monterey Zone Boards County Boards of Supervisors Landowners Voters: (2/3 for special tax) Corps of Engineers Construction Start & Appropriation Agreement (CEQA) APPROVAL Congressional APPROVAL Monterey & Santa Cruz Boards of Supervisors Corps of Engineers APPROVAL Local Congressional Congress Planning Process and Structure 23 flood protection alternatives studied since 1966 June 14, 2001 Planning Process and Structure 23 flood protection alternatives studied since 1966 June 14, 2001 Consensus Process 23 flood protection alternatives studied since 1966 • No project • Set-back levees and increase in levee height Community Concept Plan • Retention to upper basin reservoirs June 14, 2001 • Bypass Channels • Rebuild/increa se height of levees in place • Floodwalls built on top of existing levees Planning Process and Structure Framework for evaluation of plan alternatives: HYROLOGY & HYDRAULICS Level of Protection Water Surface Elevations Geomorphic Stability ENVIRONMENTAL SOCIO-ECONOMIC FINANCIAL & REGULATORY CONSIDERATIONS FEASIBILITY Endangered and Threatened Species Project Approvals Water Quality Regulations Future Environmental Regulations Agricultural Land Impacts Business Impacts Residential Impacts Economic Development Federal/Local Cost Sharing Local Share of Cost State Funding Visual Impacts Recreation Federal Authorization June 14, 2001 Flood Protection Who pays for local share of cost? Financing Options Consensus Process Key Elements to Success • Emerging Mission - Crisis/ Mandate • Common knowledge Shared meaning • Relationships among traditional adversaries Creative problem solving • Community of place • No better deals elsewhere • Primary parties participate in good faith • Multiple issues for trade off Community Benefits • Constituencies open to a deal • Adequate resources June 14, 2001 Multiple Ground Rules • All Stakeholder meetings will be open to the public. • All meetings will have agendas with meeting objectives clearly identified. • Meetings will be documented in summary reports. • Stakeholder Group members are expected to attend all meetings. Stakeholders will notify the Stakeholder Support Staff if they expect to be absent: Justine - 454-3484 • Stakeholder Group members will utilize active listening skills and refrain from interrupting June 14, 2001 Ground Rules • Issues or concerns about process must be brought to the Stakeholder Group as a whole for discussion. • Stakeholder Group members will share relevant information and facts to facilitate progress. • An attempt will be made to reach all decisions and recommendations by consensus. • Stakeholder Group members and the Working Group will complete all assignments in a timely fashion. • Stakeholder Group members will show courtesy and respect for each other when giving or receiving positive or negative feedback and contrary opinions. June 14, 2001 Consensus Process Three possible planning processes… OUTCOME Possible Outcome I Complete Consensus All members of the Stakeholder group are in agreement with everything. RESULT Flood Project Likely Classic Consensus Possible Outcome II A. I agree with most of the recommendations and I am willing to support all of them. B. I agree with many of the recommendations and I will not oppose them. C. I do not agree with the recommendations but I will not actively oppose them. Minority & Minority Reports Possible Outcome III June 14, 2001 A. Number of members who agree. B. Number of members who do not agree. C. Number of members who abstain. Flood Project is Possible High Risk of No Action Project Goal Desired outcome of the Community Planning Process: June 14, 2001 Achieve agreement on a community-based concept plan for Pajaro River flood protection. Open Discussion: Vision, Issues, Expectations Flood Project Challenges and Opportunities Hydrology and Hydraulics Primer— General Project Alternatives— Ed Wallace/ Loren Murray , NHC Inc. Environmental and Regulatory Considerations— Ken Hart, Santa Cruz County Planning Dept. Socio-Economic Considerations— David Koch, City of Watsonville Public Works Dept. Financial Feasibility— David Dickson, MIG Inc. June 14, 2001 Flood Project Challenges and Opportunities Hydrology and Hydraulics Primer— Ed Wallace / Loren Murray Northwest Hydraulic Consultants (NHC) Inc. June 14, 2001 Hydrology and Hydraulics Framework for evaluating plan alternatives: June 14, 2001 Level of Protection Water Surface Elevations Geomorphic Stability Hydrology and Hydraulics Level of Flood Protection: Current Protection: Pajaro River: 25 year storm protection (32,000 cfs) Salsipuedes Creek: 7 year storm protection (5,000 cfs) 100 Year Storm Flows: June 14, 2001 Pajaro River: 49,000 Cubic Feet Per Second (cfs) Salsipuedes Creek (@ Pajaro River): 8,500 cfs Corralitos Creek (@ Freedom): 7,400 cfs Hydrology and Hydraulics Level of Flood Protection: Current Capacity Pajaro 28,000 cfs 100 Year 50 Year 28,500 cfs 15- Year 1995/199 8 Flood 49,000 cfs 39,600 cfs 25- Year Salsipuedes 2,400 cfs 6- Year 8,450 cfs 6,750 cfs Corralitos 3,100 cfs 9- Year 7,350 cfs 6,100 cfs June 14, 2001 Hydrology and Hydraulics June 14, 2001 Hydrology and Hydraulics Insufficient Flood Protection: June 14, 2001 1995 Floodplain Hydrology: A Primer Watershed Area Total Watershed Area: 1,310 sq. miles Santa Cruz County Monterey 1.5% Santa Clara County Santa 7% Cruz Santa 25.5% Clara San Benito County Monterey County San Benito 66% June 14, 2001 Hydraulics: A Primer Capacity Comparison: Existing protection vs 100 year flows Hydraulics: A Primer Hydraulics: A Primer Example Flow Velocity Conditions Vel. ~ 3 fps June 14, 2001 Vel. ~ 4-5 fps Hydraulics: A Primer Example Flow Velocity Conditions (cont’d) Vel. ~ 5+ fps June 14, 2001 Hydraulics: A Primer Example Flow Velocity Conditions (cont’d) Vel. ~ 10 fps Vel. ~ 15 fps June 14, 2001 Hydraulics: A Primer Example Pajaro River Channel Conditions Flood Project Challenges and Opportunities Project Alternatives— Peter Cota-Robles County of Santa Cruz Dept. Public Works June 14, 2001 Project Alternatives 23 flood protection alternatives studied since 1966 June 14, 2001 Project Alternatives 23 flood protection alternatives studied since 1966 June 14, 2001 Project Alternatives General Project Alternatives: (combinations of following elements) • • • • • • • • • • June 14, 2001 Elevating Structures Early Warning System Dredging & Channel Excavation Ring Levee for Watsonville & Pajaro Bypass Channels Diversion of flood flows to Elkhorn Slough Retention to upper basin reservoirs Rebuild/increase height of levees in place Floodwalls built on top of existing levees Set-back levees Consensus Process 23 flood protection alternatives studied since 1966… • No project • Set-back levees and increase in levee height Community Concept Plan • Retention to upper basin reservoirs June 14, 2001 • Bypass Channels • Rebuild/increa se height of levees in place • Floodwalls built on top of existing levees Flood Project Challenges and Opportunities Environmental and Regulatory Considerations— Ken Hart County of Santa Cruz Planning Dept. June 14, 2001 Environmental and Regulatory Goals: • Identify botanical and wildlife species that will need to be addressed under the final plan. • Identify potential project related impacts on protected species. • Create an opportunity to allow for a proactive approach to project design relative to biological concerns. June 14, 2001 Environmental and Regulatory Final project and operation can result in: Negative Impacts Beneficial Impacts Neutral Impacts (No Effect) Environmental and Regulatory Federal and/or State “special status” species known to occur within the Birds Pajaro River corridor and• lagoon: Northern harrier hawk • • • • • • Yellow warbler Yellow-breasted chat White-tailed kite Saltmarsh common yellowthroat Willow flycatcher Great blue heron • • • • • Snowy plover Double-crested cormorant, Brown pelican California least tern Elegant tern Fish • • Steelhead trout Tidewater goby Amphibians and Reptiles • • • June 14, 2001 California red-legged frogs Western pond turtle Legless lizard Yellow Warbler Environmental and Regulatory Project Design and Operation Potential Effects On Protected Species June 14, 2001 Environmental and Regulatory The distance between the levees can effect the areas of the river that seasonally contain still water Potential Impact to: • California red-legged frog • Western pond turtle June 14, 2001 Environmental and Regulatory Structures may pose barriers to dispersal of amphibian and reptile species Potential Impact to: • Western pond turtle June 14, 2001 • Calfornia red-legged frog Environmental and Regulatory Vegetation removal along the river may impact nesting and foraging areas for birds Potential Impacts to: June 14, 2001 Yellow warbler Yellow-breasted chat White-tailed kite Great Blue Saltmarsh common yellowthroat Heron Willow flycatcher Northern harrier hawk Northern Harrier Haw Environmental and Regulatory Vegetation removal and grading activities could potentially affect burrowing animals Potential Impacts to: California red-legged frog Western pond turtle Legless lizard June 14, 2001 Environmental and Regulatory Changes to water velocity may affect steelhead trout Changes to in-stream flow velocities can affect migration. Changes to in-stream flow velocities can affect channel configuration and therefore migration, spawning, and rearing habitats. Channel maintenance, vegetation removal, and sedimentation from erosion may cause changes to spawning and rearing habitat (currently above Murphy’s crossing between river miles 15 to 17.5). June 14, 2001 Environmental and Regulatory Changes to water velocity or increased delivery of peak flows can impact the lagoon environment LAGOON SPECIES Steelhead trout Tidewater goby DUNE AND BEACH SPECIES • Legless lizard NESTING SPECIES • Western snowy plover NON-NESTING SPECIES (ONLY KNOWN TO ROOST OR FORAGE WITHIN THE PAJARO LAGOON) • Double-crested cormorant • Brown pelican • Great blue heron • California least tern • Elegant tern June 14, 2001 Environmental and Regulatory Potential project plan and alternatives must consider: Endangered and Threatened Species & Habitat June 14, 2001 Environmental and Regulatory Informal Consultation with key environmental agency representatives is an essential element of this process… Monterey and Santa Cruz Counties California Fish & Game Coastal Commission Regional Water Quality Control Board US Fish & Wildlife Service National Marine Fisheries Service Monterey Bay National Marine Sanctuary Individuals From The Above Are Invited To: Association of Monterey Bay Area Governments 1. 2. June 14, 2001 COE Scoping Process (begins June 21) Focus Group w/ MIG Flood Project Challenges and Opportunities Socio-Economic Considerations— David Koch City of Watsonville, Dept. Public Works June 14, 2001 Socio-economic Considerations Framework for evaluation of plan alternatives: Flood Protection Agricultural Land Impacts Business Impacts Residential Impacts Visual Impacts Recreation Economic Development Socio-Economic Considerations June 14, 2001 Agricultural acres Residential acres Commercial acres Socio-Economic Considerations Costs of Damages associated with flooding: Total Cost of 1995 Flood Damage – $95 Million Total Value of Existing Land in Floodplain – $1 Billion Source: US Army Corps of Engineers June 14, 2001 Socio-Economic Considerations Agricultural Land Implications Business Implications Residential Implications Visual Impacts Recreation Economic Development Public Safety June 14, 2001 Socio-Economic Considerations Agricultural Land Implications Business Implications Residential Implications Visual Impacts Recreation Economic Development Public Safety June 14, 2001 Socio-Economic Considerations Agricultural Land Implications Business Implications Residential Implications Visual Impacts Recreation Economic Development Public Safety June 14, 2001 Socio-Economic Considerations Agricultural Land Implications Business Implications Residential Implications Visual Impacts Recreation Economic Development Public Safety June 14, 2001 Socio-Economic Considerations Agricultural Land Implications Business Implications Residential Implications Visual Impacts Recreation Economic Development Public Safety June 14, 2001 Socio-Economic Considerations Agricultural Land Implications Business Implications Residential Implications Visual Impacts Recreation Economic Development Public Safety June 14, 2001 Socio-Economic Considerations Agricultural Land Implications Business Implications Residential Implications Visual Impacts Recreation Economic Development Public Safety June 14, 2001 Flood Project Challenges and Opportunities Financial Feasibility— David Dickson, MIG, Inc. June 14, 2001 Financial Feasibility June 14, 2001 Federal Authorization Federal/Local Cost Sharing Local Share of Cost Who pays for local share of cost ? Sources of Local Share-external Project Maintenance Financial Feasibility Federal Authorization: Flood Control Act of 1966 WRDA of 1986 Favorable Cost Sharing Federal Cost Share: 75% down to 50% •Local cost share: 25% minimum but cannot exceed 50% • Additional Authority Needed for June 14, 2001 Financial Feasibility Cost Sharing for Hypothetical $100 Channel Work Intensive million Project Local Cost Land Bridges/Utilities 5 % Cash TOTAL LOCAL $10 $15 $5 $30 million* Federal Cost Levees/Walls Channel Work Railroad Bridges Fish & Wildlife Planning Subtotal 5% Cash from Locals TOTAL FEDERAL $40 $15 $5 $10 $5 $75 million { 5} $70 *State Subventions reimburses up to 70% June 14, 2001 “Betterments”-100% Local Financial Feasibility Cost Sharing for a Hypothetical $100 Land and Bridgemillion Intensive Project Local Cost Land Bridges/Utilities 5% Cash Fed Reimbursement TOTAL LOCAL Federal Cost Levees/Walls Channel Work Railroad Bridges Fish & Wildlife Planning Subtotal Reimburse Locals TOTAL FEDERAL $30 $25 $ 5 {$10} $50 million* $15 $5 $5 $10 $5 $40 million $10 $50 million *State Subventions reimburses up to 70% June 14, 2001 Financial Feasibility Sources of Local Share Santa Cruz County Zone 7 Flood District Annual revenue - $1,200,000 year Existing assessment rates: $ 53 per year for homes $ 7.35 per acre for farm land $ 353.38 per acre for industrial/ commercial All revenues committed to June 14, 2001 Financial Feasibility Sources of Local Share MONTEREY COUNTY WATER RESOURCES AGENCY PAJARO LEVEE ZONES 1 & 1A June 14, 2001 Financial Feasibility Sources of Local Share Monterey County Water Resources Agency ZONES 1 & 1A June 14, 2001 • Annual revenue - $300,000 • Existing assessment rates: • $ 61 per acre for farm land and homes • $244 per acre for industrial, commercial and institutional land • Increasing assessments will be a challenge Financial Feasibility Sources of Local Share Prop 218: How Benefit Assessments may be levied: • Requires 50 % vote of landowners being assessed (weighted vote) or 2/3 of Electorate in area to be assessed, and • Requires nexus between amount paid and direct benefit received Special Tax: Sales Tax, Ad Valorum, etc = 2/3 of Voters June 14, 2001 Financial Feasibility Sources of Local Share Outside Sources: • CALTRANS HBRR • Land already owned • Prop 13 Water Bond-various programs • Wildlife Conservation Board • California Coastal Conservancy • State Lands Commission • Private Foundations • EPA Water Quality Programs June 14, 2001 Consensus Process Three possible planning processes… OUTCOME Possible Outcome I Complete Consensus All members of the Stakeholder group are in agreement with everything. RESULT Flood Project Likely Classic Consensus Possible Outcome II A. I agree with most of the recommendations and I am willing to support all of them. B. I agree with many of the recommendations and I will not oppose them. C. I do not agree with the recommendations but I will not actively oppose them. Minority & Minority Reports Possible Outcome III June 14, 2001 A. Number of members who agree. B. Number of members who do not agree. C. Number of members who abstain. Flood Project is Possible High Risk of No Action Stakeholder Meeting #1 June 14, 2001 Hydrology and Hydraulics What’s the difference? Hydrolog y Hydraulic s General definition… The study of the hydrosphere. The study of fluid motion. In flood damage reduction planning and design…. Computatio The estimation of flood flow rates under various watershed and precipitation conditions. The estimation of water surface elevations, flow depths, and velocities in the stream channel based on channel shape, size, and Computer modeling hydraulic roughness. and comparison to observed floods. n methods…. June 14, 2001 Statistical analysis of gage records and computer modeling. Hydrology: A Primer Hydrologic Investigations Statistical analysis of gage records and computer models are frequently used to estimate runoff rates, volumes, and timing. Typical Results: Source Data: • Streamflow gage data • Rainfall gage data • Watershed Characteristics • Land Use Practices • Soil Characteristics • Etc… June 14, 2001 • Statistical Analysis and/or Modeling • • Estimate of peak rate of runoff, in cubic feet per second (cfs). Estimate of volume of runoff, in acre-feet (af) Estimate of timing of runoff, including how runoff from various sub-areas and streams combine (shown as a hydrograph) Hydrology: A Primer Example Hydrologic for Pajaro River 1998 Pajaro River Historical Flood Flows 1998 Pajaro River Historical Flood Flows Flowrate in “cfs” 30,000 Area under curve is the volume of runoff from the storm Flow Hydrograph 20,000 15,000 10,000 5,000 Duration (by Date) Pajaro R. @ Chittenden Gage 8 -M ar -9 -M ar Time to runoff or “duration” 26 16 -9 8 8 6- M ar -9 8 -F eb -9 24 14 -F eb -9 8 8 Fe b9 4- -J an -9 8 0 25 Flowrate (cfs) 25,000 Hydraulics: A Primer Hydraulic Investigations A computer model is frequently used to estimate flow depths and velocities, and to determine floodplains. The model can then be used to study a variety of alternatives, including different channel configurations and level of vegetation or roughness Source Data: • Peak flow rate, cfs • Channel geometry (shape and size) • Roughness (usually depicts inchannel vegetation, surface treatment, sediment buildup, etc.) • Flood control features (levees; gates or weirs; etc.) June 14, 2001 Typical Results: Hydraulic Model • Estimate of flow velocity, in fps. • Estimate of flow depth, in feet (usually presented as a water surface profile and/or floodplain map). • Estimate of flood conveyance capacity, in cfs) Hydraulics: A Primer Example Hydraulic Study Results for Pajaro River