PRODUCTION AND OPERATIONS MANAGEMENT Ch. 15: Material Requirements Planning (MRP) POM - J. Galván 1 Learning Objectives Distinguish dependent from independent demand inventory Define material requirements planning Explain the benefits of MRP Identify the requirements of MRP, DRP, and ERP Explain the inputs & outputs of MRP Compute order releases POM - J. Galván 2 Dependent versus Independent Demand Item Materials With Independent Demand Demand Source Company Customers Materials With Dependent Demand Parent Items Material Type Method of Estimating Finished Goods Forecast & Booked WIP & Raw Materials Calculated Customer Orders Demand Planning Method EOQ & ROP MRP POM - J. Galván 3 Inputs to the Production Plan Marketing Customer Demand Production Capacity Inventory Procurement Supplier Performance Production Plan Management Return on Investment Capital Finance Cash Flow Human Resources Manpower Planning Engineering Design Completion POM - J. Galván 4 Requirements for Effective Use of Dependent Demand Inventory Models Effective use of dependent demand inventory models requires that the operations manager know the: • • • • • master production schedule specifications or bills-of-material inventory availability purchase orders outstanding lead times POM - J. Galván 5 The Planning Process Master Production Schedule Production Plan Material Requirements Plan Capacity Requirements Plan No Realistic?? Yes Execute Capacity Plans Execute Material Plans POM - J. Galván 6 Typical Level for the Master Schedule A customer order in a job shop (process focused/make to order) company Modules in a repetitive (assemble-tostock) company An end item in a continuous (product focused/make to stock) company POM - J. Galván 7 Bill-of-Material List of components & quantities needed to make product Provides product structure (tree) • • Parents: Items above given level Children: Items below given level Shows low-level coding • • Lowest level in structure item occurs Top level is 0; next level is 1 etc. POM - J. Galván 8 Bill-of-Material Product Structure Tree Bicycle(1) P/N 1000 Handle Bars (1) P/N 1001 Frame Assy (1) P/N 1002 Wheels (2) P/N 1003 Frame (1) P/N 1004 POM - J. Galván 9 Time-Phased Product Structure Must have D and E completed here so production can begin on B Start production of D 1 week D 2 weeks to produce B 2 weeks E A 1 week 2 weeks 2 weeks 1 2 1 week G 1 week E 3 weeks C F D 3 4 5 POM - J. Galván 6 7 8 10 Material Requirements Planning (MRP) Manufacturing computer information system Determines quantity & timing of dependent demand items 1 2 G ro s sR e q u ire m e n ts 2 2 0 S c h e d u le dR e c e ip ts 5 A v a ila b le 3 4 5 2 5 1 5 3 0 2 5 2 3 3 3 3 3 8 N e tR e q u ire m e n ts 7 P la n n e dO rd e rR e c e ip ts 7 P la n n e dO rd e rR e le a s e s 7 POM - J. Galván 11 MRP Requirements Computer system Mainly discrete products Accurate bill-of-material Accurate inventory status • 99% inventory accuracy Stable lead times POM - J. Galván 12 MRP PURPOSE • Coordination of Production and Inventory in large, multi-stage production systems • Capacity planning, scheduling, supplier coordination • Timely dissemination of information • Synchronized production and procurement • Central engineering and logistic database (Central element of the ERP system) MRP PROBLEMS • Deterministic model • Large data requirements and GIGO (Garbage in garbage out) • Self-fulfilling lead-times, so then what happens if fulfilment is not accomplished? • Difficulty and cost of installation and maintenance • Centralized command and control mindset MRP Benefits Increased customer satisfaction due to meeting delivery schedules Faster response to market changes Improved labor & equipment utilization Better inventory planning & scheduling Reduced inventory levels without reduced customer service POM - J. Galván 15 Variables in MRP o Master Schedule -WHEN o Bills of Material -WHAT o Stocks & Work in Progress (WIP) – HOW MUCH o Lead-times – WHEN TO HAVE AVAILABLE o Work orders / schedules – WHAT TO DO o Purchase orders / schedules –WHEN TO ORDER o Yields – WHAT IS LOST o Working days / times - CALENDAR Structure of the MRP System BOM (Bill-of-Material) Master Production Schedule MRP by period report Lead Times (Item Master File) MRP by date report MRP Programs Planned orders report Inventory Data Purchase requirements Purchasing data Exception reports POM - J. Galván 17 MRP and The Production Planning Process Forecast & Firm Orders Aggregate Production Planning Material Requirements Planning Master Production Scheduling Capacity Requirements No Planning Realistic? POM - J. Galván modify CRP, MRP, or MPS Resource Availability Yes Shop Floor Schedules 18 Master Production Schedule Shows items to be produced • End item, customer order, module Derived from aggregate plan POM - J. Galván 20 Master Production Schedule Shows items to be produced • End item, customer order, module Derived from aggregate plan Example Item/Week Oct 3 Oct 10 Oct 17 Oct 24 Drills 300 200 310 300 Saws 300 450 310 330 POM - J. Galván 21 MRP Dynamics Supports “replanning” • Problem with system “nervousness” “Time fence” - allows a segment of the master schedule to be designated as “not to be rescheduled” “Pegging” - tracing upward in the bill-ofmaterials from the component to the parent item Manager can react to changes, doesn’t mean he/she should POM - J. Galván 22 MRP and JIT MRP - a planning and scheduling technique with fixed lead times JIT - a way to move material expeditiously Integrating the two: • Small bucket approach and back flushing • balanced flow approach POM - J. Galván 23 Extensions of MRP Closed loop MRP Capacity planning - load reports MRP II - Material Resource Planning Enterprise Resource Planning POM - J. Galván 24 Extensions of MRP Closed Loop MRP Production Plan No Priority Planning Capacity Planning Desired Master Production Schedule Realistic? Resource Planning Material Requirements (detailed) Capacity Requirements (detailed) Priority Control Capacity Control Dispatch List Input/Output Is specific capacity adequate? First Cut Capacity No No Is average capacity adequate? Yes Yes POM - J. Galván 25 Extensions of MRP Capacity Planning Tactics for smoothing the load and minimizing the impact of changed lead time include: • Overlapping - reduces the lead time, entails sending pieces to the second operation before the entire lot has completed the first operation • Operations splitting - sends the lot to two different machines for the same operation • Lot splitting - breaking up the order and running part of it ahead of the schedule POM - J. Galván 26 Extensions to MRP Enterprise Resource Planning MRP II with ties to customers and suppliers POM - J. Galván 27 MRP in Services Can be used when demand for service or service items is directly related to or derived from demand for other services • restaurant - rolls required for each meal • hospitals - implements for surgery • etc. POM - J. Galván 28 Distribution Resource Planning DRP requires: • Gross requirements, which are the same as expected demand or sales forecasts • Minimum levels of inventory to meet customer service levels • Accurate lead times • Definition of the distribution structure POM - J. Galván 29