Electricity Supply Request
INFORMATION SHEET
Customer Projects
8 Beaconsfield Avenue
BEACONSFIELD VIC 3807
Tel: 1300 360 795 Fax: 03 9238 6447
e-mail: supplyrequest@ausnetservices.com.au
Thank you for your inquiry. Please follow the 4 steps as detailed below.
STEP 1 – applicant contact details
STEP 2 – type of electricity supply request
Please indicate: (A) whether you want a Preliminary Estimate or Firm Offer and
(B) the nature of the work required.
Preliminary Estimate – Office Based Design / Assessment. No Site Visit.
An indicative price only, for making electricity supply available. There is no charge for this option.
Firm Offer – Field Based Design / Assessment. Site Visit Required.
A fixed price for making electricity supply available to a property. This option has an up front Project Fee from $550.00. This
offer is valid for 60 days and the project fee is non refundable.
* Please make cheques payable to AusNet Asset Services Pty Ltd ABN 27 075 826 881.
STEP 3 – details of property requiring electricity
IMPORTANT - IS THIS A SUBDIVISION?
If property is being subdivided, you must provide a plan of subdivision with this application. Architectural or building site plans
are not acceptable. You must also provide the location of electricity supply arrangements of existing dwellings.
STEP 4 – amount of electricity required – parts A, B & C
IMPORTANT:
This information must be provided in full to avoid delays. Please consult your electrician.
C. Existing & Proposed Equipment - Estimate as accurately as possible the amount of electricity supply (in kilowatts or
horsepower) you plan to use. It is critical that we know if you are installing Floor Heating, Air Conditioning or any other high
load equipment. Our design is based upon your information and requirements.
Property Sketch - Please sketch your property to help us identify where you want your electricity supply. If it is a large rural
property, you must detail the exact location (measurements & pole numbers) and all other buildings and objects. Fences will
be assumed to be the property boundary unless otherwise indicated.
Please ensure you indicate the location of any obstructions or features such as:
 rows of trees  existing buildings  waterways  railway lines  highways  steep sloping ground
 rocky terrain  powerlines crossing property  Telstra or other utility’s assets.
SOP 11-4013A Issue 17
4/8/2014
1/2
Example of Property Sketch
T
RES
NEA
SS
CRO
D
ROA
dist
n
Bou
dar
y
e
ce
tan
dis
anc
ty
per
Pro
EET
STR
existing/proposed
buildings
E
NAM
ce
t an
d is
SHED
DAM
Neighbour Property No #
dist
e
anc
Pole# 123456
NORTH
* An aerial photograph of your property may be available at no cost on the internet or via your estate agent or local council.
Pole Numbers
Please provide the pole number and the distance of the power pole closest to your property. The pole number is generally on a
strip of plastic or aluminium attached to the pole at eye level and between 4 and 6 digits in length.
* Providing us with a clear photograph of the pole numbers will ensure accuracy and avoid delay.
How long does it take to get connected?
The time frame to connect power is determined by a number of factors including our works schedule and activities such as
surveying and obtaining necessary permits and approval from councils and other authorities. A more specific time frame will be
provided once contracts have been signed and payments received.
Please advise us if you think a new powerline may need to cross your neighbour’s property. If known please provide
neighbour’s contact details
Important Notice Concerning Your Privacy
Personal details are collected and used solely for the purpose of providing the requested services. This information will be
treated as confidential and only disclosed to our construction and engineering agents and your electricity retailer to enable the
delivery of the requested works. If you wish to gain access to this information please contact our Customer Contact Centre on
1300 360 795.
SOP 11-4013A Issue 17
4/8/2014
2/2
Electricity Supply Request
APPLICATION
Customer Projects
8 Beaconsfield Avenue
BEACONSFIELD VIC 3807
Tel: 1300 360 795 Fax: 03 9238 6447
e-mail: supplyrequest@ausnetservices.com.au
STEP 1
Applicant Contact Details
Our Ref:
Name:
Company Name:
ABN:
Postal Address:
Suburb:
Postcode:
Phone No:
Fax No:
Mobile No:
Email:
Your Registered Electrician:
STEP 2
Phone No:
Type of Electricity Supply Request
FIRM OFFER (please complete invoice details over page)
A
PRELIMINARY ESTIMATE
B
New Electricity Supply
Upgrade to Existing Supply
Underground Service Pit
Availability of Supply
Pole Relocation
Private Overhead Line
Availability of 3 phase
Other (provide details)
STEP 3
$550 payment included
Send invoice (credit card/EFT)
Details of Property Requiring Electricity
Property Owner:
Road Address:
(Lot & Street No)
Suburb:
Nearest Cross Rd:
Nearest Pole No:
Melway/Vic Roads ref:
Crown Allotment:
Parish:
Are you currently building:
Yes
If already on supply: (refer to your bill)
No
Estimated completion date:
Meter No:
NMI No:
If property is subdivided: Complete if property is subdivided or is in the process of being subdivided (attach plan)
Subdivision Name:
SOP 11-4013A Issue 17
Subdivision Plan No:
4/8/2014
1/2
STEP 4
A
Amount of Electricity Required
Premise Type:
Single Premise
B
Domestic
Commercial
Multiple Premises
Industrial
Number of Units:
Farm
Size:
(squares)
Nature of Business: (eg: dairy farming)
IMPORTANT: This information must be provided in full to avoid delays. Please consult your electrician
C
Supply Required:
1 Phase (230 volts)
(E) Existing or (P) Proposed Equipment
eg: Air Conditioning
General Power & Lights (covers general
household appliances and lights)
P
2 Phase (230/460 volts)
3 Phase (230/400 volts)
Number
of Units
Rating
(kW) or (hp) or (amps)
Number of
phases
Daily Hours of
Use
2
3.8 kW
1
7
P/E
2 kW
Air Conditioning
INPUT/OUTPUT
(Specify if INPUT or OUTPUT)
Electric Floor/Storage Heating
Electric Water Heating
Electric Oven/Hotplates
Pump
Other (please specify)
* Phase & rating details (kilowatts (kW) or horsepower (hp) or amps) should be noted on the appliance / machinery, within its manual or via the
manufacturer. Please provide the starting method used for any motor rated over 3.75 kW.
Invoice Details for Firm Offer
Company Name:
Name:
ABN:
Postal Address:
Suburb:
Postcode:
Phone No:
Fax No:
Mobile No:
Email:
Signature:
Date:
Please Read & Sign Below
I/we* understand that the subsequent preliminary advice provided by AusNet Services will be based upon the information provided in this Electricity Supply
Request, without detailed assessment. The preliminary estimate is not binding, although the amount is generally effective for up to 60 days. Any constraints
placed on AusNet Services by third parties may cause additional costs to you or your client. Construction of the electricity supply extension is programmed upon
acceptance of a contract and receipt of any payments required from the applicant. Negotiations need to be finalised about four months prior to electricity supply
being made available.
I/We* understand that electricity will not be connected until AusNet Services has received a prescribed “Certificate of Electrical Safety” (CES) according to
regulations as determined by Energy Safe Victoria.