contract Safety requirements are updated to integrate 5

advertisement

1

SEC Distribution Field Force Overview

Distribution Contractors Day with Saudi Electricity Company

October 28 th , 2015

2

The contracting phase consists of two main elements: tendering process and contracting process

Prequalification Contracting Operation

1.1 Ceiling distribution & coverage assurance

1.2 Bidding mechanism

2.1 General terms & conditions

2.2 Performance management

1.3 Pricing mechanism 2.3 Others

A number of key recommendations are implemented in Phase 1

3

1 Prequalification 2 Tendering 3 Contracting

1. Prequalification model: new prequalification process and criteria to assess contractors

2. Coverage model:

Kingdom model will be used on office level to help match supply to demand in all offices across the

3. Tendering strategy: will include the number of required contractors in each electricity department and how their ceilings will be defined

1. Pricing mechanism: reference prices along with an improved pricing mechanism are expected to yield more accurate prices

1. Guarantees: Bid bonds are required from contractors. These are refundable unless contractor confirms intent to sign contract.

Bank guarantees are 5% of contract ceiling.

2. Contract ceiling: contract ceiling is distributed based on contractors’ work capacities, prequalification scores and bids

2. Contract duration: new UR contract term is reduced to 2 years with 1 optional year

3. Awarding strategy: will determine who gets awarded a contract, and what their ceiling will be. If contractor refuses to sign, his ceiling is given to the next in line contractor (cascading)

3. Payment terms: 50% payment upon completion of work is incorporated to allow better liquidity

4. KPIs: KPIs are integrated in the contract to objectively measure contractor's performance, and linked to SEC’s evaluation sheet

5. Incentives & penalties system: the building blocks for a future incentive & penalty system are put in place

4

12+ operational tools are developed to facilitate the operationalization of the new process

PREQUALIFICATION TOOLS CONTRACTING & TENDERING TOOLS

CONTRACTING

GUIDE

UPDATED

CONTRACT

CLAUSES

KPI

EVALUATION

WORK ORDER

ALLOCATION

TOOL

COVERAGE

ANALYSIS

MODEL

PRICE

UNIFORMIZATION

VALUE

ALLOCATION &

COMMITMENT

INSTRUCTIONS

FOR BIDDERS

Initiation includes developing historic reference prices to gauge contractor bids

Prequal Tendering Contracting

Bids from last tendering process are entered into model

Model applies appropriate inflation factor

New price uniformization methodology is applied to bids

Final historic reference prices are generated

5

Historic bids entered to be compared against new contract bids

An inflation factor based on a detailed contractor cost model is applied to historical bids

New contract bids are uniformized on a line item level using a standard deviation methodology

Bids are compared to historic reference prices and final prices are calculated

Contractors ’ bids and prequal scores will be used in determining the contract ceilings

SEC WILL DETERMINE TOTAL COVERAGE

REQUIRED IN EVERY OFFICE

Prequal Tendering Contracting

…AND DISTRIBUTE IT ACCORDINGLY

TO CONTRACTORS x

150%

Demand

6

Note: This data pertains to the Madinah office only

Source: SEC data

~ x

40%

Supply

EXAMPLE OF MADINAH OFFICE

7

5 star safety system is now a mandatory system that all contactors must abide by

Prequal Tendering Contracting

CONTRACT SAFETY REQUIREMENTS ARE

UPDATED TO INTEGRATE 5-STAR SYSTEM

CONTRACT SAFETY REQUIREMENTS ARE

UPDATED TO INTEGRATE 5-STAR SYSTEM

Safety KPIs are incorporate in contractor performance measurement:

-

Number of Type 1 (First Aid) Incidents per 1 M work

-

Number of Type 2,3,4 (Injury, Handicap, Death) Incidents per 1

M work

-

Percentage of times that work site complied with SEC safety standards

12% of the points in the prequalification scoring pertains to safety record & HSE systems

Safety performance averaged over the last three months will be reflected in work allocation through KPIs

Contract addendum enforces the 5-star safety system in performance

Safety systems will be checked in post-signing stage.

Contract is subject to termination if standards are not met

Non-compliance on safety requirements for trenches subject contractors to a penalty of 200 SAR

~10 KPIs were developed based on current situation & best practices

Prequal Tendering Contracting

8

CATEGORY

Timely Work

Performance

Safety

Performance

Collaboration &

Responsiveness

KPI DESCRIPTION

1. Percentage of WOs completed within time (count)

2. Percentage of WOs completed within time (value)

5. Average delay on delayed

WOs (count)

7. Density of contractor work

Total work orders completed on time compared to total number of WOs completed

Value of all work orders completed on time compared to all work value performed under URC

The average number of delayed days for all work orders that have delays

Average work value for a given contractor's work orders

Number of type 1 incidents that happen with a given contractor compared to his value of work

9. Number of Type 1 (First Aid)

Incidents per 1M SAR work

10. Number of Type 2,3,4 (Injury,

Handicap, Death) Incidents per

1M SAR work

12. Percentage of times that work site complied with SEC safety standards

18. Average number of days to accept work order

20. Number of emergency and maintenance rejected WOs*

21. Number of construction rejected WOs

Number of type 2, 3, 4 incidents that happen with a given contractor compared to his value of work

Number of contractor site visits that complied with SEC safety standards compared to total number of site visits

Response time of contractor when a work order is issued

Number of emergency and maintenance rejected work orders in a given month

Number of construction rejected work orders in a given month

9

We have developed a new dashboard for KPIs linked to the

Prequal Tendering standard evaluation form

KPI DASHBOARD TO BE GENERATED

MONTHLY …

… AND AUTOMATICALLY LINKED TO

EVALUATION USING WEIGHTS

Contracting

New evaluation system will the building block for a future incentive & penalty scheme

Download