Tidal In-Stream Energy Overview Brian Polagye Research Assistant University of Washington Department of Mechanical Engineering September 11, 2006 LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 1 Agenda • Resource and Performance • TISEC Devices • Siting Arrays in Puget Sound • UW Research LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 2 Tidal power is different than other forms of renewable energy Tidal Power Resource and Performance - Comparison to Wind Wind Tidal Resource • Driven by uneven heating of earth’s surface by sun • Occurs throughout the world • Driven by gravitational pull of moon and sun • Highly localized - requiring specific tidal range and bathymetry Availability • Intermittent • Long-term predictions as good as a weather forecast • Intermittent • Predictable centuries in advance Proximity to Loads • Often distant from load centers • Often close to load centers • Mature technology • Developing technology Maturity LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 017,09-07-06,SNOPUD.ppt 3 There are two very different approaches to harnessing the energy of the tides Resource and Performance Tidal Power - Utilizing the Resource - Barrage • Dam constructed across estuary ― High cost ($ Bn) ― Long construction period (decade) • Power produced by closing dam at high tide and allowing water to run through turbines once ocean has returned to low tide ― Completely alters estuary circulation ― Power produced in twice-daily surge ― All attendant problems of hydroelectric dams • Low-cost power production at very large scale LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION In-stream Tidal • Turbines installed in estuary at constrictions in groups called arrays ― Moderate unit cost ($ MM) ― Short unit construction time (weeks) • Power produced directly from tidal currents ― More continuous (but still intermittent) power production ― Smart choice of turbines and layout of arrays should avoid significant environment impact • Moderate-cost power production at varying scales http://www.energy.washington.edu 016,09-07-06,SNOPUD.ppt 4 At a very basic level, tidal currents are generated by the rise and fall of the tides – water runs downhill Resource and Performance Tidal Currents Side View Top View Ocean Ocean Water level increasing Flood tide Slack water Tidal Basin Tidal Basin Ebb tide Water level decreasing Seabed • Slack water ― Constant water height ― No velocity • Flood Tide • Ebb Tide ― Water level higher outside estuary than in main basin ― Water flows into estuary LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION ― Water level higher in basin than ocean ― Water flows out of basin http://www.energy.washington.edu 015,09-07-06,SNOPUD.ppt 5 Tidal currents vary primarily on a fourteen day lunar cycle Resource and Performance Tidal Cycle Spring Tides (strongest) 3 Current Velocity (m/s) 2 1 0 -1 -2 -3 -4 1-Feb 6-Feb 11-Feb 16-Feb 21-Feb 26-Feb Date Neap Tides (weakest) LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 014,09-07-06,SNOPUD.ppt 6 Flow power has a cubic dependence on velocity – small velocity changes have a large effect on power Device Performance Resource and Performance - Resource Utilization - Device Performance Representative Day 9000 1400 Fluid Power Power (kW) 1000 1 x Density x Velocity 3 x Area 2 Electric Power 800 Rated Speed 600 400 Electric Power 7000 Power (kW) 1200 Fluid Power 8000 6000 5000 4000 3000 2000 200 1000 Cut-in Speed 0 0.0 1.0 2.0 0 3.0 4.0 5.0 Current Velocity (m/s) LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION 0:00 4:48 9:36 14:24 19:12 0:00 Time http://www.energy.washington.edu 018,09-07-06,SNOPUD.ppt 7 Power generation varies day-to-day, but is consistent on a monthly basis and shows no seasonal dependency Device Performance Resource and Performance - Variable Predictability - Daily Average Monthly Average 250 500 Average Power (kW) Average Power (kW) 450 400 350 300 250 200 150 100 200 150 100 50 Date LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION Dec Nov Oct Sep 10/28 12/17 Jul 9/8 Jun 7/20 May 5/31 Apr 4/11 Mar 2/20 Feb 1/1 Jan 0 0 Aug 50 Month http://www.energy.washington.edu 019,09-07-06,SNOPUD.ppt 8 Agenda • Resource and Performance • TISEC Devices • Siting Arrays in Puget Sound • UW Research LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 9 All turbines have a number of common components, but many variants TISEC Devices Turbine Overview Gearbox • Increase rotational speed of shaft from turbine • 80-95% efficient Powertrain or Drivetrain Rotor • Extracts power from flow • Turns at low RPM • Efficiency varies with flow velocity (45% max) LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION Generator and Power Conditioning • Generate electricity • Condition electricity for grid interconnection • Turns at high RPM • 95-98% efficient Foundation • Secure turbine to seabed • Resist drag on support structure and thrust on rotor http://www.energy.washington.edu 009,09-07-06,SNOPUD.ppt 10 Two basic types of rotors have been developed – horizontal axis and vertical axis TISEC Devices Rotor Variants Horizontal Axis Vertical Axis Gearbox and Generator Gearbox and Generator LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 013,09-07-06,SNOPUD.ppt 11 Ducted turbines have been proposed to augment power production Power Augmentation TISEC Devices • Enclosing turbine in diffuser duct boosts power • A number of questions remain unanswered regarding this approach • Is it economically justified? ―Ducts were never justified for wind turbines ―Different set of circumstances for tidal turbines • Is there an increased hazard to marine mammals and fish? ―Can a large fish or mammal become trapped in the duct? LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 012,09-07-06,SNOPUD.ppt 12 Foundation selection is usually driven by site water depth TISEC Devices Foundation Types Monopile Hollow steel pile driven or drilled into seabed Gravity Base Pros: • Deep water installation feasible Pros: • Small footprint • Established technology used in offshore wind (10-40m) Chain Anchors Cons: • Large footprint • Scour problems for some types of seabed • Decommissioning problems Cons: • High cost in deep water • Installation expensive for some types of seabed Chains anchored to seabed and turbine Pros: • Small footprint • Deep water installation feasible Cons: • Problematic in practice • Device must have high natural buoyancy LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION Heavy foundation of concrete and low cost aggregate placed on seabed Tension Leg Submerged platform held in place by anchored cables under high tension Pros: • Small footprint • Deep water installation feasible Cons: • Immature technology now being considered for offshore wind in deep water http://www.energy.washington.edu 010,09-07-06,SNOPUD.ppt 13 TISEC Devices Maintenance Options Divers Divers service turbine • Marine intervention extremely costly and must be minimized if TISEC devices can hope to compete economically Pros: • Divers widely available Cons: • Difficult to work underwater • Very high intervention cost • In deep water, dive time measured in minutes per day • All device developers pursuing lowmaintenance philosophies Device Retrieval Crane barge mobilized to retrieval entire turbine Pros: • Less costly than divers • Deep water feasible Cons: • High cost to mobilize heavy-lift crane barge LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION Integrated Lift Lifting mechanism integrated directly into turbine support structure Pros: • Maintenance without specialty craft • Deep water feasible Cons: • Cost of lifting mechanism • Support structure may be surface piercing (aesthetic and shipping concerns) http://www.energy.washington.edu 011,09-07-06,SNOPUD.ppt 14 Marine Current Turbines is furthest along in the development process Marine Current Turbines (MCT) Power train TISEC Devices Horizontal axis (2 bladed) Planetary gearbox Induction generator Rated from 1.2 – 2.5 MW Foundation Monopile drilled or driven into seabed Two turbines per pile Maintenance Lifting mechanism pulls turbine out of water for servicing Development Large Scale (18 m diameter) LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION 3 years of testing prototype in UK 1.5 MW demonstration planned for installation in 2006/2007 Conceptual fully submerged units http://www.energy.washington.edu 002,09-07-06,SNOPUD.ppt 15 Verdant is positioned to install the first array of TISEC devices in the world TISEC Devices Verdant Power train Small Scale (5 m diameter) Horizontal axis (3 bladed) Planetary gearbox Induction generator Rated at 34 kW Foundation Monopile drilled or driven into seabed Maintenance Retrieval of power train by crane barge Divers employed during installation Development LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION Installing 6 turbines off Roosevelt Island, NY City (Starting mid-Sept) First permitted test project in US http://www.energy.washington.edu 002,09-07-06,SNOPUD.ppt 16 Lunar Energy has adopted a different philosophy with an emphasis on a “bulletproof” design Lunar Energy Power train Foundation TISEC Devices Horizontal axis (ducted) Hydraulic gearbox Induction generator Rated at 2 MW Gravity foundation using concrete and aggregate Maintenance Heavy-lift crane barge recovers “cassette” with all moving parts Development Tank testing Nearing end of design for first large scale unit Large Scale (21 m diameter inlet) LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 001,09-07-06,SNOPUD.ppt 17 Agenda • Resource and Performance • TISEC Devices • Siting Arrays in Puget Sound • UW Research LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 18 Environmental issues are probably the biggest unknown for siting arrays of tidal in-stream turbines Case Siting Study Environmental Issues - Marine Life Considerations Environmental Issue Key Questions Answers (so far) Direct “impact” of turbine on marine life • Will a turbine make sushi in addition to electricity? • No. Maximum tip velocity limited by cavitation. (~10 RPM for large turbines) • Will the rotor injure or harass fish and marine mammals? • Unknown. Considerable cost and effort being expended by developers to prove technology is benign. No Altamont Passes. Indirect impacts • Will anti-fouling paints used on turbines and supports degrade environment? • Developers are testing inert, glass-based anti-fouling paints to minimize this impact. • Will oils and lubricants leak from the turbine? • Not in large quantities, but developers are working to minimize any leakage. • How much of the seafloor will be disturbed during installation? • Depends on type of foundation and construction techniques. Choices will be driven by site depth and local concerns. LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 007,09-07-06,SNOPUD.ppt 19 Case Siting Study Environmental Issues Environmental Issue Effect of energy extraction on the environment Key Questions • What is the effect of energy extraction? Answers (so far) • Altered circulation in estuary • Effects complicated and counterintuitive ― Velocity increases downstream of an array and water depth decreases ― Overall flow rates are reduced • How much energy can be extracted without substantially altering circulation? • Rough estimates. 15% of the kinetic energy in a channel used as placeholder in resource studies. ― Overly conservative in some cases, overly optimistic in others. ― Question needs to be addressed on a case-by-case basis LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 008,09-07-06,SNOPUD.ppt 20 In addition to environment, a number of factors need to be considered when siting turbine arrays. Most have not yet been addressed for sites in Puget Sound. Case Siting Study Array Siting Issues - General Issue Key Questions Status Resource Size and Quality • How large is the extractable resource? • How many turbines in an array? • Preliminary estimates using NOAA single-point current predictions • Next Step: Current measurements Electrical Infrastructure • Will new transmission lines need to be built? • What local loads exist? • Not yet determined – requires consultation with local utilities Bathymetry and Seabed Geology • What foundation types are suitable for water depth? • What foundations can seabed support? • Not yet determined – requires geologic survey Port Facilities • Are there local marine contractors capable of performing installation and maintenance of an array? • Not an issue in Puget Sound for most types of construction LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 005,09-07-06,SNOPUD.ppt 21 And the list goes on… Case Siting Study Array Siting Issues - General Issue Key Questions Status Shipping Traffic • What is the maximum draft of shipping traffic in channel? • Not yet determined – requires consultations with marine exchange and Coast Guard Large-scale Turbulence • Are there local geographic features that would give rise to large-scale eddies? • Not yet determined – requires consultations with oceanographic experts Multiple Use • How is the site currently used? • Does the site overlap with major recreation or fishing areas? • Not yet determined – requires consultations with regional stakeholders Economics • Will turbines produce costeffective power? • Tacoma Narrows study predicted a cost of energy of ~10 cents/kWh • Next step: Feasibility study LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 006,09-07-06,SNOPUD.ppt 22 There are a number of prospective tidal energy sites in Puget Sound Puget Sound Resource Study Siting - Overview - Spieden Channel Guemes Channel San Juan Channel Deception Pass Admiralty Inlet Agate Passage Rich Passage Site Power Density (kW/m2) Resource (MW) Depth (m) • Tacoma Narrows 1.7 106 40 • Admiralty Inlet ―Point Wilson ―Marrowstone ―Bush Point 0.6 0.6 0.4 167 195 132 60 71 75 • Deception Pass ―Deception Pass ―Yokeko Point 5.5 0.4 26 3 30 16 • Guemes Channel 1.5 35 14 1.5 0.9 3 9 6 15 0.6 0.6 45 56 63 69 • Bainbridge Island ―Agate Passage ―Rich Passage • San Juan Islands ―San Juan Channel ―Spieden Channel Tacoma Narrows estimated COE ~10 cents/kWh. Other sites? LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 020,09-07-06,SNOPUD.ppt 23 San Juan Channel represents a substantial resource, but the channel is quite deep San Juan Channel Siting - Overview Preliminary Turbine Layout Preliminary Array Layout 0.8 km (0.5 mi) Turbine + Lateral Spacing San Juan Channel Ref. 0.6 kW/m2 • 116 turbines (20 m diameter) • Average installation depth ~95m LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION Preliminary Array Performance • 5 MW average electric power • 16 MW rated electric power • 39,900 MWh annual generation http://www.energy.washington.edu 024,09-07-06,SNOPUD.ppt 24 Spieden Channel also represents a substantial resource, but is again a deep water channel Spieden Channel Siting - Overview Preliminary Turbine Layout Preliminary Array Layout 1 km (0.6 mi) Turbine + Lateral Spacing Limestone Point Ref. • 168 turbines (20 m diameter) • Average installation depth ~83m LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION 0.6 kW/m2 Preliminary Array Performance • 8 MW average electric power • 26 MW rated electric power • 62,700 MWh annual generation http://www.energy.washington.edu 025,09-07-06,SNOPUD.ppt 25 Agenda • Resource and Performance • TISEC Devices • Siting Arrays in Puget Sound • UW Research LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION http://www.energy.washington.edu 26 Question 1: How much tidal energy can be environmentally extracted? Extraction Limits - Balancing Resource Against Environmental Impact - ? Point Wilson UW Case Research Study • How much kinetic energy can be extracted by an array? Admiralty Head ― Current estimates are 15% of kinetic energy in a channel (little physical reasoning) ― Probably much more site specific and closely related to frictional losses in channel ? • Does the construction of one array preclude the construction of others? Marrowstone Point ― Can 20+ MW arrays be built at Pt. Wilson, Marrowstone and Bush Point? ― Can an array be built at Admiralty Inlet if one already operating in Tacoma Narrows? Indian Island Bush Point ? LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION • Building an understanding with 1-D models ― Very interesting preliminary results ― Will be expanding to 2-D and 3-D cases http://www.energy.washington.edu 003,09-07-06,SNOPUD.ppt 27 Question 2: How tightly can turbines in an array be packed? Array Packing - Most Economic Use of Resource - • Regions of high power flux may be relatively short and narrow Low Power Density San Juan Island Lopez Island High Power Density Low Power Density • Economic reasons to site as many turbines in high power density regions as possible LABORATORY FOR ENERGY AND ENVIRONMENTAL COMBUSTION UW Case Research Study • How close is too close? ― Since flow is bi-directional, wind turbine spacing rules are probably too conservative ― Downstream turbines must be beyond wake of upstream turbines ― Wakes degrade performance and accelerate metal fatigue • Approaching with a combination of analytical and computational tools ― Little or no physical data available (since no arrays operating) ― Plan to leverage results of CFD modeling to suggest “engineering rules” for array layouts http://www.energy.washington.edu 004,09-07-06,SNOPUD.ppt 28