-1BARTLEY HOUSE, HOOK Outline Specification for Refurbishment of Offices 1. Introduction Owens Galliver, architects were commissioned to prepare a specification for the refurbishment and alteration of the offices and retained to monitor the contractor. 2. Accommodation 2.1. Internally 2.1.1 Entrance, to disabled access standards, with space for name plaque, double doors, polished stainless steel ironmongery and letter plate. 2.1.2 Entrance foyer and reception area, with space for security desk and seating by Tenant 2.1.3 Double doors for furniture access to office areas; fully glazed fire resisting screens with views into office areas. 2.1.4 7 no. male wc cubicles 7 no. female wc cubicles 2 no. urinals 14 no. hand basins. Split between front and rear of building 1 no. unisex disabled w.c. with hand basin and grab rails. 2.1.5 1 no. male, 1 no. female shower cubicle on ground floor 2.1.6 Cleaners’ cupboard on each floor with sink. 2.1.7 8 person electric lift at each end of the building. 2.1.8 Office area with general nominal floor to ceiling height of approx. Ground floor: First floor: 2750mm. 2710mm 2.1.9 Ceiling zone to suit new air conditioning. 2.1.10 Fully accessible raised access floor system with minimum clear void of approx: Ground floor: First floor: 2.1.11 158mm 115mm Comms cupboard/gas intake/elec risers/BT intake -22.1.12 Fixed ladder access for personnel to plant room/lifting beam and pulley over 2.1.13 Roof level plant room. 2.1.14 Roof mounted air-con chiller and air handling unit 2.1.15 Entirely new air-conditioning, water and electrical services throughout. 2.2. Externally 2.2.1 New road pattern imprinted resin surface to ramp to car park. 2.2.2 Car parking spaces for 91 no. cars, with existing and additional “security” lighting on columns. 2.2.3 Upgraded tree, shrub and ground cover planting to perimeter and between parking bays. New planting bed in front of building. Existing gravel perimeters made good 2.2.4 All existing air-conditioning equipment and plinths removed. 2.2.5 New widened and re-orientated entrance steps, with existing retaining walls reduced in length and replaced with steel guards/fencing. 2.2.6 Dilapidated fences removed; security fence on ramp removed; manual sliding gate at foot of ramp. 2.2.7 Entrance area shrubbery cut back, dwarf wall removed, area re-landscaped. 3. Structure All new work to Structural Engineer’s design, and subject to soil surveys and Building Control. 3.1 Foundations Pile re-enforced pad footings to steel columns and brick piers/lift shaft. 3.2 Floors Existing in-situ concrete waffle and flat slab unaffected except for service holes. In-situ concrete with in-situ lift pit on compacted hardcore. 3.3 Walls Existing insulated cavity walls largely unaffected New external: generally non-load bearing cavity construction, brick and 100mm medium density block, 70mm insulated cavity. Internal walls 100mm medium dense block restrained at head (all new) New concrete wall at rear core, with existing concrete wall cut for opening with steel frame support all to Engineer’s design. -33.4 Frame Existing steel and concrete frame largely unaffected, columns at approx 8.0 m centres 3.5 Stairs Front: existing concrete stair removed. New steel stair with maple clad, folded steel treads and risers, ash rail, stainless steel balustrade with glass infill Rear existing concrete stair refurbished To Building Regulation requirements, clear width 1100 mm approx., min 250 nominal going, 190 rise approx. 3.6 Lift shaft New 215mm brick shaft. 3.7 Roof Existing steel rafters at grid lines, existing built up galvanised twin wall insulated metal decking on cold rolled steel purlins. Existing decking cleaned off, limited repairs where necessary, coated with Torseal to give guaranteed life. Existing roof light removed, and infilled with barrel vaulted steel, insulated. Existing U Value assumed: 0.6 W/sq.m.K. Existing air-con chiller slab asphalt tanked; new warm roof construction with paving slab protection, with new intake louvres within existing window frame. Plant removable by crane from open well. U Value target: 0.45 W/sq.m.K. Existing air handling slab asphalt tanked; new warm roof construction with paving slab protection. Plant removable by crane from open well. U Value target: 0.45 W/sq.m.K. 4. External Finishes 4.1 Facing brick All new work to match existing 4.2 Entrance Existing two storey aluminium curtain walling to be adapted to allow for new raised floor and recessed entrance, with thermally isolated curtain walling system, with sealed double glazed units, toughened where required. -44.3 Spandrel panels Front elevation enamelled glass/sheet metal spandrels within curtain walling and windows to be replaced with insulated double glazed “look-alike” panels 4.4 Rear access Existing entrance screen adapted to allow for new raised floor; new doors. 4.5 Windows Existing windows cleaned and waxed internally, prepared and resprayed externally All opening lights sealed shut with mastic and screws New solar film applied to windows on south east and south west of office spaces, to M&E requirements. New windows in existing blank walls to match existing in appearance. All perimeter external window mastic replaced. 4.6 Entrance and escape doors Concealed slimline overhead closers to entrance doors. 4.7 Car park Existing blockwork cleaned down, existing bays re-marked. Existing concrete apron removed and replaced with blockwork to match in 200mm x 100mm x 80mm concrete block. 450 x 450 Camas Moordale textured paving slabs to steps and entrance paths. 5. Internal Finishes (provisional) 5.1 Foyer Floor: Concrete block and screed make up to new levels. Perimeter band and feature circle in maple boarding, with polished s/s trim Maple strip heating duct grilles Walls: All to be plastered; paint finish (Crown Period Tudor Rose, provisional) Ceilings: Sandtex sprayed plaster board on MF grid with concealed access panels. Skirtings: Clear finished ash 100mm x 20mm approx. -55.2 Office areas Floors: Ground floor: New fully accessible raised access floor, 600mm x 600mm steel tray and top, sealed with chipboard core, on adjustable pedestals, all to PSA MOB light grade standards, e.g. Hewetson. Rockwool cavity barriers as required by B. Regs. First floor: Existing, largely as ground floor. Existing floor boxes removed and panels replaced and cleaned of significant carpet residue Rockwool cavity barriers as required by B. Regs. (all new) 500mm x 500mm loop pile heavy contract carpet tiles; allow £19 per sq.m. supply and lay. Walls: All existing perimeter services/casings to be removed, plaster made good Existing lightweight plaster, painted with emulsion, colour to be agreed New plaster to ground floor fair faced concrete columns, rwp cased in; Painted three coats emulsion, colour to be agreed Ceilings: (all new) 600 x 600 metal tiles, SAS System 150, hinged, with circular perforations, concealed grid with plasterboard infill on MF ceiling grid at perimeter and around column heads, linear diffusers on main longitudinal grid lines and long perimeters. Woven blanket cavity barriers as required by B. Regs. (all new) Skirtings: (all new) Clear finished ash 100mm x 20mm approx Cill boards: (all new) Ash veneered blockboard with solid ash lippings. 5.3 Core areas Floors: Insitu concrete, new floors power floated or concrete block and screed, and sealed for carpet Walls: Three coat emulsion paint on new two coat lightweight plaster colours to be agreed Ceiling: New sprayed sandtex plasterboard on MF ceiling grid -6Skirtings: 5.4 New clear finished ash 100mm x 20mm approx W.C.s Floors: New and existing solid concrete or new screed over blockwork make up. New glazed tiles 100 x 100mm, Langley Unit 1, white Walls: New tiles 100 x 100mm, on two coat sand/cement render. Full height block work wc cubicles also tiled Full width mirrors above counter tops Duct panel and system: (all new) Proprietary post formed panels, Armitage Venesta Azure, black flashgaps Ceilings: 5.5 New painted plasterboard suspended ceiling Generally Ironmongery: (all new) Polished stainless steel D handles with matching accessories, Allgood Modric, Dom, or equal. Closers to match to all doors required by Building Regulations Doors etc: (all new) 44mm solid core ash veneered, over solid lippings, Shadbolt or equal, factory lacquered. All lobby and stair doors ½ hr fire resisting, with Pyran glazed vision panels, in small panes, proprietary intumescent glazing gaskets. Core/office doors to be pairs. Matching duct panels to risers, lockable. Pair doors book matched. Architraves, frames etc: clear finished solid ash moulded. 6.0 Services (all new) All to M&E consultants outline design, and sub-contractors detail design. 6.1. M & E Services -7Please refer to M & E Services specification prepared by RHB Partnership. 6.2. Sanitary ware (all new) Columba Duraplus white porcelain cantilever w.c. and free standing hand basins in rear wc's and disabled wc. Armitage Shanks Contour white porcelain urinals Armitage Shanks white porcelain shower trays Heatrea Sadia electric showers Armitage Shanks white Corian under counter basins, with Corian counter tops Chromed w.c. flush handles. Chromed traps and wastes to free standing basin in disabled wc Concealed cisterns. White bezel recessed tundishes with vision panels. 6.3. Tenants’ kitchen Spur services and wastes to back of cores on each floor in positions to be agreed for connection by Tenant. 6.4. Waste All new internal foul drainage via upvc stacks to existing internal and new external manholes (direct to mains at front of building, via sump and pump at rear of building alarm in reception) Repairs and rodding as recommended by Engineers following survey. 6.5. Surface water Via existing rainwater goods to mains Repairs and rodding as recommended by Engineers following survey. 6.6. Supplies Mains water, electricity and gas from Station Road/sub-station New gas supply with external meter enclosure. All incoming supplies uprated where necessary for proposed uses. 6.7. Year 2000 All M&E installations to be fully Year 2000 compliant.