Portland State University SYSC-505 Power System Economic Dispatch Professors: Tim Anderson & Herman Migliore Student: Donald Ogilvie Date: Aug 17, 2010 Table of Contents Abstract Introduction Economic Dispatch Common Formulae 1.0 Cost of Generating Electrical Power 1.1 Monitoring System efficiency via Turbine Heat Rate (THR) Test 1.2 Typical Power Plant showing heat rate calculation 1.3 Analyzing the THR process 1.3.1 Heat Rate Verification & Validation Using Calculus 1.3.2 Matlab Software Code & Fuel Cost Curve 2.0 Power Flow and Economic Dispatch 2.1 Economic Dispatch System One generator Concept 2.2 Incremental Cost (IC) 2.2.1 System-2 (Two Generator Concept) 2.3 System-3 Three Generators Economic Dispatch Applications 2.3.1 Matlab Software Code for Three Generators Lambda (Cost) 2.3.3 Economic Dispatch with Generator Limits 3.0 System Modeling 3.1 Computer Modeling & Simulation 3.2 Computer simulation of a two bus 1-generator system 3.3 Two generator economic dispatch modeling 4.0 Conclusion Appendix References List of Figures & Tables Figure 1.0 Input/Output (I/O) Curve Figure 1.1 Calculating Heat Rate Figure 1.2 THR Test Figure 1.3 Applying THR Loading Figure 1.4 Heat Rate vs. Power Figure 1.5 Typical Operating Cost Curve Figure 2.1 Single Generator Concept Figure 2.2 Power Flow System Figure 2.3 Two Generator Concept Figure 2.4 Gauss Seidel Method Figure 2.5 Three Generator Economic Dispatch Application Figure 3.1 Modeling Two Bus System Figure 3.2 Bus Modeling Figure 3.3 Modeling 7-Bus System Figure 3.4 Modeling A Single Generator Figure 3.5 Modeling A Two Bus Power Flow System Table-1.1 Fuel Cost Table-1.2 Cost of Electricity Generation Table-2.1 Voltage Iteration Summary Table-2.2 Voltage Iteration 1 Page 2 2 3 4 7 11 12 13 14 17 18 24 24 32 36 38 41 45 47 48 50 52 55 Page 7 11 12 12 13 15 18 20 24 29 37 42 44 45 47 48 4 5 22 30 Abstract This paper describes several efficient and practical methods to formulate and analyze the economic dispatch of a power system, while taking into consideration the constraint of the transmission line and load. Some of the practical approaches used are Lagrange method, Matlab software code, Powerworld modeling software, and fuel cost curve sometimes referred to as the input and output curve (I/O). Iterative techniques for power flow are represented by Gauss-Seidel methods. Introduction In economic dispatch practices there are many choices for setting the operating points of generators. The main aim of the economic dispatch paper is to include variables that affect operational costs, such as the generator distance from the load, type of fuel, load capacity and transmission line losses. By including these variables one will be able to perform economic dispatch and inter-connect generators to minimize operating cost and functions. The generator cost is typically represented by four curves, namely: Input/Output (I/O), heat rate, fuel cost and incremental cost curve. Generator cost curves are not smooth, and they are generally represented by quadratic functions and piecewise linear functions. Each plant uses a quadratic cost function such as the Fuel Cost Curve: Ci ( PGi ) PGi PGi2 . Where i = generator i, one of the number of units Ci = operating cost of unit in $/h PGi = electrical power output of a generator i in per unit on a common power base Alpha, Beta & Gamma are in units of dollars ( $/h) This fuel cost curve allows us to look at a wide range of economic dispatch practice such as total operating cost of a system, incremental cost and minute by minute loading of a generator. Power flow concept is a major component of economic dispatch and this paper briefly covers the basic concepts that will help us to look at power and power losses from the view point of power dynamics. The power system modeling and economic dispatch used in this paper helps to drive home the fact that power grid system is fast becoming a computerized control system. For example, small incremental changes can be simulated on one input parameter at a time while looking at all the affected output parameters in the system. By taking this approach, we are aiming at a much higher operating precision and less human error which can be caused by countless pages of mathematical calculations done by hand. 2 Economic Dispatch Common Formulae Fuel Cost Curve: Ci ( PGi ) PGi PGi2 Power Flow Constraint: PGi PD Cost function: Ci ( PGi ) PGi PGi2 Compute Incremental cost: ICi Ci ( PGi ) PGi The final system operating points: Constraints: Ci ( PG1 ) C ( P ) C ( P ) * L1 i G 2 * L2 ......... i Gi * Li PG1 PG 2 PGi G PG PL 0 in1 PGi PL 0 Ignore losses: L C (in1 PGi P) If Lambda is the same for each generator: Ci 2i PGi i PGi i Ignoring losses: Ci i PGi2 PGi i = incremental cost per unit Lagrange is: L C (in1 PGi PL ) The Partial derivatives are: Incremental Cost: i Ci L C (1) 0 PGi PGi PGi i 1, 2,...., n Ci 2i PGi i PGi Lagrange can be formulated as: Pi i i or λ = dCi/dPi = βi + 2γiPi 2 i 3 1.0 Cost of Generating Electrical Power The three main sources that are used to determine the cost of electrical energy (MW) generation are facility construction, ownership cost and operating costs. Please note that energy sources, such as solar, wind, nuclear, and hydro are not included in the cost components. Since operating cost is the most significant of the three main sources, the focus will be on the economics of the operation. The operating cost is dominated by the fuel cost, although labour is also a key component. The goal of power system economic dispatch is to maximize system efficiency and minimize system losses that cannot be billed or pass on to customers. Table-1.1 and Table-1.2 below the average costs of fuel such as coal, petroleum and natural gas. The cost of uranium is around $0.65/MBTU or $0.65 per Million British Terminal Unit (MBTU). Table 1.1 – Fuel Cost Receipts, Average Cost, and Quality of Fossil Fuels for the Electric Power Industry, 1991 through 2002, obtained from All Fossil Fuels Average Average Avg. Avg. R Average Cost Receipts Average Cost Receipts Cost CostR Sulfur Sulfur Percent Percent (cents/ (cents/ (thousand (dollars/ (thousand (cents/ (cents/ by 106 (dollars/ton) by 106 barrels) barrel) Mcf) 106 Btu) 106 Btu) Weight WeightR Btu) Btu) 144.7 30.0 1.3 172,051 252.7 15.9 1.1 2,630,818 215.3 160.2 141.2 29.4 1.3 147,825 251.4 15.9 1.2 2,637,678 232.8 158.9 138.5 28.6 1.2 154,144 237.3 14.9 1.3 2,574,523 256 159.4 135.5 28.0 1.2 149,258 242.3 15.2 1.2 2,863,904 223 152.5 131.8 27.0 1.1 89,908 256.6 16.1 1.2 3,023,327 198.4 145.2 128.9 26.5 1.1 113,678 302.6 18.9 1.3 2,604,663 264.1 151.8 127.3 26.2 1.1 128,749 273 17.28 1.4 2,764,734 276 152 125.2 25.6 1.1 181,276 202.1 12.7 1.5 2,922,957 238.1 143.5 121.6 24.7 1.0 145,939 235.9 14.8 1.5 2,809,455 257.4 143.8 120.0 24.3 0.9 108,272 417.9 26.3 1.3 2,629,986 430.2 173.5 R R 123.2 24.7 0.9 124,618 369.3 23.2 1.4 2,152,366 448.7 173 125.5 25.5 0.9 120,851 334.3 20.8 1.6 5,607,737 356 151.5 Coal Period Receipts (thousand tons) 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 769,923 775,963 769,152 831,929 826,860 862,701 880,588 929,448 908,232 790,274 762,815 884,287 Petroleum Natural Gas Source: Energy Information Administration, Form EIA-423, “Monthly Cost and Quality of Fuel for Electric Plants Report,” 4 Aside: Cost of Electricity Generation Table- 1.2 Cost of Electricity Generation 1994 Compared to 2003 Technology 1 1994 Cost of Electricity (cents/KWh) Current Cost of Electricity (2003) data, cent/KWh Hydroelectric Nuclear Coal Natural Gas Solar Wind 0.31 to 4.4 2.5 1.9 to 2.3 2.5 to 11.7 16.4 to 30.5 7.6 0.25 to 2.7 1.4 to 1.9 1.8 to 20 5.2 to 15.9 13.5 to 15.9 4.6 Source: California Energy Commission: http://www.energy.ca.gov/electricity/comparative_costs_vl.html All values are in 2003 dollars. Nuclear costs do not include decommissioning cost, which is < 0.1 cents/KWh. Please see Appendix for more current energy cost. The data in Table-1.2 shows that a renewable energy source such as solar and wind are still very expensive in contrast to all the other traditional methods of generating electricity. In short, the cost of producing electricity by Solar or Wind Turbine system is not economically feasible to supply. Therefore, it is yet to be determined if the initial implementation cost will drop low enough to make it the source of choice for the future electricity market. Major Components in Economic Dispatch The three major components in economic dispatch are system efficiency, heat rate and power output in megawatts. Moreover, in order to understand the concept of economic dispatch, we should start with the cost of fuel. Table-1.1 and Table-1.2 show that the cost of fuel varies significantly with different types of fuel. 5 Economic dispatch allows us to look at the cost of the fuel, labour cost, power generation cost and transmission line losses. Therefore, the power generated will be PG = PL + PTL Where PL = total system load PTL = total system transmission losses per unit Knowing PL + PTL can allow us to predict the total PG required for an area demand and various bus and substation commitments. This information provides no insight in how the individual area generator will share information on a common grid to meet the regional grid demand at various hours such as peak and off-peak window. Furthermore, it is not economically feasible to run fossil fuel systems when there is very low demand for power. Therefore, the process of load scheduling becomes a major process in how a power system operates to stay economically feasible. In minimizing cost without compromising system reliability and market security, one must take into account one basic constraint of each generator which is Pmin ≤ PGi ≤ Pmax where the upper boundary Pmax is directly related to upper rating of the generator. On the other hand, the lower boundary Pmin is directly linked to thermal consideration that is required to maintain the boiler steam which drives the turbine. Power plants measure results in terms of efficiency, as seen in the equation below. sec watts *106 * hr MW BTU lb joules 12, 000 * 2000 *1054.85 * ytons lb ton BTU P * T * 3600 Some plants have an overall efficiency of 34% which is very good for this type of industry. Plant efficiency varies as a function of the generator power level. The efficiency level shown in the above equation is power output in megawatt hour (MWHR) divided by the energy input in British Thermal Unit (BTU). The graph of MWHR versus power output, as seen in Figure 1.4 on page 14, is used to monitor the health of the system. For example, if the heat rate is high then the system is running inefficiently because a high heat rate will produce a low efficiency. 6 1.1 Monitoring System efficiency via Turbine Heat Rate (THR) Test: The THR test was originally designed as a diagnostic type of test. This test provides a broad range of data on the thermal efficiency and operating costs of the turbine steam cycle, and consequently of the entire unit. Moreover, it is standard practice to run a THR test in order to determine the overall efficiency of the system (since efficiency is the reciprocal of heat rate). Figure 1.0 below shows the I/O curve for a 500 MW system after a major a boiler and turbine overhaul. The post overhaul test was done over the entire load range. A minimum of four test points are required to monitor the I/O curve for design compliance. This test is normally done at 25%, 50%, 75%, and 100% of the maximum capacity (MC) rate. In cases where it is not feasible or possible to run tests in the 25% range, the heat input from the latest I/O curve is added to the data points and used in curve fitting. Test readings are taken over periods ranging from 1 hour to 2 hours of steady run. I/O Equation (Post Overhaul) 5000 4500 Heat Input (GJ/h) 4000 3500 Y = 0.001793*x. 2 + 8.05279*x + 399.3 R2 = 1.0000 3000 2500 2000 1500 1000 100 150 200 250 300 Net Output MW 350 400 450 500 Figure 1.0 – Input. Output (I/O) Curve In the real world, pre and post overhaul turbine heat rate tests are performed to monitor the system efficiency at different levels of power output. In addition, heat rate tests are periodically run to look at the unit efficiency throughout the year. The system condenser cooling process can allow an additional 1.5% to 2% change in efficiency due to the change in temperature. Furthermore, 2% change in efficiency can be the deciding factor that will determine if the generating plant will make or lose money. 7 The Heat Rate (H) equation shown below shows that the efficiency is inversely proportional to the heat rate. A typical coal fired plant heat rate (HR) is about 10.5 * 10^6 BTU/MW.h. The operating cost of a generating plant or unit includes cost of fuel, labour, supplies, and maintenance is commonly known as Ci = Fi Pi Where Ci = operation cost of unit in $/h Fi = operation cost of unit in $/MBTU Pi = input unit power in MBTU/h H H 12, 000 1 * BTU lb 1BTU 2000 * ytons lb ton 106 BTU P *T 3600 3.41 1054.85 The cost of fuel can be highly volatile and since Fi depends on the type of fuel such as coal, oil, gas and nuclear – it is very hard to empirically determine a fixed price per MBTU. A rough average for Fi in the power industry is about $1.50 per MBTU. In the power industry, the fuel cost curve is the standard that is the most accurate to analyze cost as it relates to heat rate. The cost is given as a second order expression shown as: Fuel Cost Curve: Ci ( PGi ) PGi PGi2 Where i = generator i, one of the number of units Ci = operating cost of unit in $/h PGi = electrical power output of a generator i in per unit on a common power base Alpha, Beta & Gamma are in units of dollars ( $/h) The cost curve is commonly called the I/O curve. However, Fuel Cost Curve is the I/O Curve multiplied by the cost of fuel. For example, if the cost fuel is $1.90 per MBtu then (A + B*MWn + C* MWn2) * 1.90 would be the Fuel cost curve. The concept of I/O will be explained below, and coefficients A, B & C are given by design manufacture to determine the heat rate. 8 Input & Output tests and calculations were used to provide system performance data, in the form of input and output equation. I/O curves were primarily used in the calculation of the total incremental cost. The following two methods were used to establish the I/O curve for a given unit. (1) Direct I/O Method of Measurement: This is the most commonly used method because it only requires measurements of fuel flow, calorific value of fuel samples taken during tests of net unit output and reference operating conditions. The test is ideally suitable for gas and oil-fired units. However, this test is not ideal for coal-fired units. (2) Indirect I/O Method of Calculation: This method of calculating I/O curves are more complex than the direct method. However, it is much more accurate for coal fired unit. I/O results are derived from two sets of separate performance tests namely: Thermal Heat Rate Test (THR) and Steam Generator efficiency test. Both tests require at least four test points, ranging from 25% to 100% of the maximum capacity Rate (MCR) to calculate the heat inputs for given net outputs. Results are then “curve-fitted” to yield the desired format of I/O equations, where the required input is expressed as a function of the net load desired: I = A + B*MWn + C* MWn2 Where I Is Unit Heat Input (GJ/h) A, B, C Is the Coefficients of I/O Equation MWn Is Net Unit Output (MW) Frequency of Updating of I/O Curves: Currently, there is no set frequency for updating I/O curves applicable to all units. The main reason is the large variation in Capacity Factors of individual power plants and units. Instead, I/O curves are typically updated after major system overhauls, or when there are indications of measureable changes in thermal efficiency of individual turbines, or steam generators. Generally, I/O tests have been “free by-products” of diagnostic and optimization testing of turbines and boilers. 9 Calculating Thermal Heat Rate (THR) Thermal heat rate is required by a turbine-generator system to produce power at the generator terminal. Heat rate is measured in kilojoules per kilowatt (KJ/KWh). The lower the heat rate, the more efficient the turbine cycle, the more cost effective it is to operate, and the longer life cycle expectancy. The turbine efficiency is the reciprocal value of the THR, which is the cycle Eff. = 100 * (3600/THR) where 3600 KJ/h = 1KW. Figure 1.1 shows the operating points for the calculation. There are several different approaches to measure and analyze THR. However, the method used for coal, gas and nuclear plants is shown in the equation below. THR was calculated using the following equation: W1 (H1 – h1) + Wr ( Hr – hr) P + PB GJ/h KWH = Where: W1 = Steam to HP Turbine Stop Valve Kg/h Wr = Steam Flow to Re-heater Kg/h H1 = Enthalpy of Steam Supplied to the High Pressure Turbine Stop Valve (KW/Kg) hr = Enthalpy of Steam Supplied to the Intermediate Pressure (IP)Turbine before Interceptor Valve (KW/Kg) h1 = Enthalpy at the Feed-water at HP outlet (KW/Kg) hr = Enthalpy of Steam at HP Turbine Exhaust (KW/Kg) P = Net Generated Output (KW) PB = Equivalent Electrical Output from Boiler Feed Pump Turbine (KW) In addition, other methods are used to measure THR, such as the Input and Output (I/O) method and the condensate flow measurement test. The I/O method can be linked to a computerized software that is programmed to do live trend mathematical analysis of the THR through a non-linear equation such as: Input (GJ/h) = A + B * MWnet + C*MWnet^2. The result of I/O is generally analyzed in terms of the R-Square value. 10 1.2 Typical Power Plant showing the required data for heat rate calculation Figure-1.1 Calculating Heat Rate GJ/h KWH = W1 (H1 – h1) + Wr ( Hr – hr) P + PB 1250.446(2790.6 – 750.8) + 59.93(2790.6 -1135.0) * 3600) 935300 Thermal Heat-Rate = 10199 KJ/KWh This method of calculating heat rate is common to Group-1 (Coal Fire), Group-2 (Gas Fire, and Group-3 Nuclear. Flow diagrams are often used to navigate the decision process. See Figure 1.2 and Figure 1.3 below. 11 1.3 Analyzing the THR Process Figure 1.2 THR Test Method Figure 1.3 Applying THR Loading 12 1.3.1 Heat Rate Verification & Validation Using Calculus Minute by minute loading also known as Incremental Heat Rate (IHR) is used to analyze the station Operation Efficiency Factor from the ratio of Actual Net Unit Heat Rate (KJ/KWh) or MWHR/MBTU to the Reference Net Unit Heat Rate (KJ/KWh). The graph in Figure-1.4 shows the typical behaviour pattern for heat rate. Figure 1.4 Heat Rate Vs Power (MW) Actual Net Unit Heat Rate (KJ/KWh) This can be verified from the equation shown below: dI b 2CW 3dW 2 dW Substituting W for L IHR dI ( IHR) dL II 12 dI I 2 I1 ll12 ( IHR)dL The minute by minute loading allows us to observe and analyze the heat rate that is required between selected points shown below. By using calculus one can verify and validate the heat rate used between selected points with reference to the manufacturer design heat rate. A five point test will be used to check and analyze how much deviation is present after a major unit overhaul. For example, a generating unit rated at 610 MW could experience a planned maintenance system reliability test to 13 see if the heat rate is within the range of the manufacturer design specifications. See the 5-point test below. 5-Point calculated steps are: 2 610 450 [421.3 8.0l 0.00192l ]dl = 832756 BTU/hr 610 350 [421.3 8.0l 0.00192l 2 ]dl = 1.22577E6 BTU/hr 2 610 250 [421.3 8.0l 0.00192l ]dl = 1.52534E6 BTU/hr 610 100 [421.3 8.0l 0.00192l 2 ]dl = 1.80789E6 BTU/hr 0450 [421.3 8.0l 0.00192l 2 ]dl = 950683 BTU/hr The numbers shown in Table-1.1 reflect only the cost of fuel to operate the generator(s), and they do not reflect the actual cost of generating electricity because the actual outputs from the process of producing electrical energy is subjected to a substantial loss of about 66%. Therefore, any power plant that is running above 34% is considered to be very efficient. 1.3.2 Matlab Software Code & Fuel Cost Curve Matlab software is an indispensable tool that is often used to solve power system problems. By choosing four points in the system power output and the associated cost related to each points, the result is the input and output curve shown below in Figure-1.5. EDU>> p=[40 60 80 100]'; c=[650 850 930 1200]'; X=[ones(size(p)) p p.^2]; a = X\c T = (0:1:100)'; Y = [ones(size(T)) T T.^2]* a; plot(T,Y,'-',T,Y,'o'),grid on a= 494.5000 2.5250 0.0438 Where “a” = the quadratic equation that represent the cost curve shown in C1 below. 14 C1 = 494.50 + 2.5250P1 + 0.0438 P12 ($/MWhR) Typical operating cost curve 1200 1100 Operating cost in $/h 1000 900 800 700 600 500 400 0 10 20 30 40 50 60 Output Power (MW) 70 80 90 100 Figure 1.5 Typical Operating Cost Curve (Power MW) In addition, the code creates the Quadratic equation for the cost curve, this curve is critical to the lifecycle of the system, because all future curves will be taken with reference to the date and time when this curve was generated. Below is a practical example that will allow one to understand how to go from the fuel cost curve to the cost of generating power by including input and output parameters. The fuel cost per hour can also be shown as: Fuel Cost Curve: Ci ( PGi ) PGi PGi2 . For example, the cost curve at 100 MW is (494.50 +2.525PG + 0.0876P2G) = 494.50 + 2.525 * 100 + 0.0876 * 100^2) = $1623/hr 15 In addition, one can see how to implement the Incremental cost: ICi Ci ( PGi ) = PGi 2.525 + 0.1752 * 100 = 20.045/MW Another example, if a generating unit fuel input in millions of BTU/h is expressed as a function of the output PG in megawatts as 0.032P2G + 5.8PG + 100), then as a System Engineer your duty is to determine the following: (a) The incremental cost equation in dollars per megawatt hour as function of the generating power (PG) based on the fuel cost of $2.00 per million BTU (b) The cost of fuel per megawatt hour if the (PG) = 150 MW. (c) The additional fuel cost per hour to raise the output of the unit from 150 MW to 151 MW. Solution: (a) The fuel cost curve in dollars per MWh is FC = (0.032P2G + 5.8PG + 100) * 2 = 0.064 P2G + 11.6PG + 200$/MWh Ci ( PGi ) = 0.128 PG + 11.6 $/MWh PGi (b) The cost of fuel when PG = 150 MW is: Incremental cost: ICi (0.064(150)2 +11.6 PG (150) + 200)/150 = 22.6 $/MWh (c) The Approximate ICi that is required to raise the power by 1MW from 150 MW to 151 MW is = 0.128 (150) + 11.6 = $30.8 $/MWh Therefore, by using the Incremental Cost (CI) equation, one can formulate the equations into computer code to automate the process to minimize potential error when making hard and explicit decisions. 16 2.0 Power Flow and Economic Dispatch This section covers several mock-up scenarios, examples and concepts that deal with a single generator, two generator and three generator concepts and applications. In order to continue exploring economic dispatch, the basics of power flow will be covered since it is directly linked to the topic of economic dispatch. The study of power flow is an indispensable process in planning and designing the future expansion of power systems as well as determining the best operating system. The general information obtained from the study of power flow is the voltage magnitude and phase angle at each bus in conjunction with real and real and reactive power flowing in the line. There are three types of buses: load, voltage-controlled and slack. Each non-generator bus is called the load bus where both Pgi and qi are at zero and the real and reactive bus Pdi and Qdi are power and reactive bust respectively, their associated loads drawn are negatively input into the system. The voltage controlled bus is any bus in the system at which the voltage magnitude is kept constant and controlled. In short, the control is done with the generator excitation unit. Therefore, for each bus where there is a generator, the generator must meet the condition of the power flow network to maintain the credibility of the grid. This means that a generator must stay within a very tight window of variance such as 5% tolerance in term of voltage swing. At the slack bus, the voltage angle of the slack serves as reference for all the other buses, and mismatches are not defined. P and Q are not scheduled at the slack bus, and the power loss at each bus in the system is given as: N PLoss Pi i 1 i Re al power loss N Pgi i 1 N P i 1 Total Generation di Total load Maximum and minimum generated reactive power is ignored at the slack bus. Figure-2.1 shows a single generator system with a general concept of power flow that leads us into power system economic dispatch. The examples shown will also briefly overview the topic of perunit system and how it relates to power system. 17 2.1 Economic Dispatch System One Generator Concept Figure-2.1 (1) Single Generator Concept Assume the generator below voltage is set at 10% above its rate value, and the load connected to bus D is equal to 5 MW at a pf 0.9 lagging. Compute the per unit model for the system shown below. (2) Find the load voltage at Bus-D (3) Find the active and reactive power supplied by Bus-A (4) Find the active and reactive losses (5) Find the economic loss from the active power loss (6) Use NPV to determine if this project is viable for investment Solution: Per-Unit System In many engineering applications, it is useful to scale, or normalize quantities and dimensions. This practice is commonly used in the power system industry, and the standard used is called per-unit system. It is common for impedance value to convert from an old base to a new base, and in order to do so we must take into consideration the other components in the system such as Voltage (V), Current (I) and Power (W). The formulae below will give a brief overview of the concept. It is very common practice to express per-unit (pu) values as percentage such as 1pu =100%. 18 A typical conversion, is: Per-unit value = (percent value/100). (1) Solution Per unit value actual value in SI units base value identical SI units New pu value old pu value ( Per unit impedance old base value ) newbase value (actual im pedance, ) * (base KVA) (base voltage, KV ) 2 *1000 Per unit Z new per unit Z given ( Z base I base Vbase I base base KVgiven base KVnew )2 ( base KVAnew ) base KVAgiven V 2 base Sbase Sbase Vbase Transmission line in power system operates in units of kilovolt (KV), megawatts, kilovolt-amperes, megavolt-amperes and ohms. These quantities are often expressed as per-unit value with respect to a given base or reference base. For example, the base voltage is given as 120 KV in a system where other voltages such as 108 KV, 120 KV and 126 KV become 0.90, 1.00 and 1.05 respectively. On the other hand pu values can also be expressed as 90%, 100% and 1.05%. The pu value of any given quantity is defined as the ratio of value expressed as a decimal or percentage. Figure-2.2 below shows a typical generating system with the basic component that will allow one to understand the basic concept of power flow. Economic dispatch is an integral part of power flow, where one can look at economic dispatch without including the power flow components. 19 Figure-2.2 Power Flow System 20 Sb 10 MVA, chooseVb, A 132( Zb, BC 13.2 69 ) 13.2 KV ,Vb, D 132( ) 66 KV 132 138 1322 1742.4 10 Z 10 10 100i Z AB 0.10i( ) 0.2i, Z BC line 0.006 0.06i 5 Zb, BC 1742.4 X T 2 0.08( Sload 6910 ) 0.087i 6910 5 cos 1 0.9 5.5625.8 MVA 5 MW 2.42 MVar 0.9 Sload , pu 0.55625.8 (2) Z CD X T 2 0.087i Ztotal Z AB Z BC Z CD 0.2i 0.006 0.06i 0.087i 0.006 0.347i Y 1 Ztotal 2.8889 0.05 2.8796i 21 (3) Solution Below GAUSS SEIDEL METHOD: 0.05 2.87960i 0.05 2.87960i 0.05 2.87960i 0.05 2.87960i Y11 Y12 Y21 Y22 YBUS V2 (i 1) v2 S 1 [ 2 Y21V1 ] Y 22 V2 (i) 0.500 0.2419i [ ( 0.05 2.87960i) ] 1.1 ( 0.05 2.87960i) ( 1.0 0i) 1 v2 1.013 0.172i v2a 1 0.500 0.2419i [ ( 0.05 2.87960i) ] 1.1 ( 0.05 2.87960i) ( 1.013 0.172i) v2a 0.988 0.151i v2b 0.500 0.2419i [ ( 0.05 2.87960i) ] 1.1 0.988 0.157i 1 ( 0.05 2.87960i) ( 0.988 0.151i) v2c 1 0.500 0.2419i [ ( 0.05 2.87960i) ] 1.1 0.987 0.156i ( 0.05 2.87960i) ( 0.988 0.157i) Table 2.1 Voltage Iteration Summary Iteration # V2 0 1.013- 0.172i 0.988- 0.151i 1 0.988- 0.157i 2 0.987- 0.1562i 3 Where V2 converges at 0.987-0.156i 22 (4) Solution S1 = V1(Y11 *V1 * + Y12 *V2*) = 0.5017 + j0.3492 Active power P1 = 0.5017 x 10 = 5.017MW Reactive power Q1 = 0.3492 x 10 = 3.492MVar Active power Ploss = P1 - P2 = 0.5017 - 5 = 0.017MW Reactive loss Qloss = Q1 – Q2 = 3.492 – 2.42 = 1.072 MVar (5) Solution Economic loss based on active power Active power Ploss = P1 - P2 = 0.5017 - 5 = 0.017MW = 0.17 MW Assuming the cost of generating electricity is: $25 per MWh Therefore an annual economic loss would be: 0.017 MW * $25 *24hr * 365days = $3723 In addition, if the shareholder initial investment cost is $10 M and there was no power loss, then the $3723 would be cash flow. Now we can evaluate the economic dispatch process in terms of NPV 1 (1 rp ) n NPV [ ]R Investment Cost rp Where rP = % Return for the project R = Cash Flow N = Number of years ` NPV 1 ( 1.05) 5 3723 10 106 9.984 106 0.05 The NPV Decision Rule is: Accept a project if its NPV > 0 Reject a project if its NPV < 0 Indifferent where NPV = 0 23 2.2 Incremental Cost (IC) Incremental cost is the slope of the fuel cost curve, and the unit of IC is in dollars per megawatt hour (MWh). IC tells us how much it will cost to operate a generator to produce an additional 1MW of power. Let us assume a case where there is two generators no line losses, no generator limit and IC1 > IC2. This means that for an additional 1MW, generator-1 operating cost is more than generating-2 operating cost. If our objective is to minimize operation cost, which always the business case, then it is reasonable to reduce power output at generator-1 and, in return, increase the output of generator-2. Then the optimal condition would be that the operation cost from generator-1 and generator-2 should be the same. See example below in Figure-2.3. 2.2.1 System-2 Figure-2.3 Two Generator Concept Two Generator Concept 24 Two Generator fuel cost curve equations are used to set Generator-1 & Generator -2 economic dispatch optimum loading. Optimal Power Condition without line loss = Two generators with the following cost curve. C1 (PG1) = 500 + 45PG1 + 0.01P2G1 IC1 C1 PG1 PG1 C2 (PG2) =2000 + 43PG2 + 0.003 P2G2 45 0.02 PG1 IC 2 PG1 + PG2 = PG2 = 500 IC1 = IC2 = 45 + 0.02 PG1 = 43 + 0.006 (500 - PG1) PG1 = 38.4615 MW PG2 = 461.539 MW PG1 + PG2 = 38.4615 + 461.539 = 500 MW IC1 = 45 + 0.02 PG1 = 45 + 0.02 * 38.4615 = 45.769 IC2 = 43 0.006 PG 2 = 43 + 0.006 * 461.539 = 45.769 IC1 = C2 = $45.769/MWh 25 C2 PG 2 43 0.006 PG 2 PG 2 Penalty Factor and Power Loss On the other hand, if we have a scenario where the fuel cost curve is given as: C1(PG1) = 600 + 15 * PG1 + 0.05 * (PG1)2 C2(PG2) = 800 + 20 * PG2 + 0.03 * (PG2)2 Assume the penalty factor for the first generator (slack bus) is set to1, and the second generator (PG2) Plosses partial derivative of the losses is given as 0.05 . PG 2 The Systems Engineer is required to calculate the dispatch values of PG1 and PG2 for load + Losses of 1000 MW. Solution: Power Loss is Li 2C1 15 0.1P1 2 PG1 2C2 20 0.06 P2 2 PG 2 2C1 L1 2 PG1 L1 1 P 1 loss PGi 2C2 L2 2 PG 2 1 1 2 PLoss 1 0 1 2 PG1 15 0.01 PG1 L2 1 1 1.0526 2 PLoss 1 0.05 1 2 PG 2 15 0.1 (20 0.06 PG 2 )1.0526 PG 2 ( 1.0526 0.06 20) 15 0.1PG1 1.0526(20 0.06(1000 PG1 )) 14.25 0.095 PG1 20 0.06(1000 PG1 ) PG1 424.194 MW PG 2 575.806 MW 26 0.95 20 0.06 By using the same cost curve given in the first scenario shown above, one can analyze the system to show the potential cost saving that is possible without losses. See the tabulated results below. C1(PG1) = 600 + 15 * PG1 + 0.05 * (PG1)2 C2(PG2) = 800 + 20 * PG2 + 0.03 * (PG2)2 2C1 15 0.1P1 2PG1 2C2 20 0.06 P2 2PG 2 IC1 = IC2 = 15 + 0.1 PG1 = 20 + 0.06 (1000- PG1) PG1= 406.25 MW PG2 = (1000 - PG1) = 593.75 MW The cost associated with 1C1 & 1C2 are: 1C1 = 15 + 0.1 * 406.25 = $55.625/MW 1C2 = 20 + 0.06 * 593.75 = $55.625/MW In contrast, the cost associated power loss in scenario-1is shown below: 1C1 = 15 + 0.1 * 424.194 = $57.419/MWh 1C2 = 20 + 0.06 * 575.806 = $54.548/MWh 1C1 cost per megawatt shows an increase of $1.8 Per MWh when losses at generator-2 were set to 5%. Another Method used to set the incremental cost (IC) is the Lagrange Multiplier (2.2.3). This method uses the matrix approach that will result in a $-value for Lambda. With this $-value the aim is to get IC1 for generator one equal to IC2 for generator two even when the two generators may not be the same. This approach offers the most optimum cost benefit when (IC1 = IC2). 27 Two Generators Alternate Solution Using Lagrange Multiplier System PD = PG1 + PG2 = 1000MW And C1(Pg1) = 1500 + 20PG1 + 0.01P2g1 C2(Pg2) = 500 + 15Pg2 + 0.03P2g2 Using the Lagrange multiplier method, we know: dc1(Pg1) – λ = 20 + 0.02Pg1 – λ = 0 dc2(Pg2) – λ = 15 + 0.06Pg2 – λ = 0 1000 – PG1 – PG2 = 0 Solve three linear equations: 20 + 0.02Pg1 – λ = 0 15 + 0.06 Pg2 – λ = 0 1000 – Pg1 – Pg2 = 0 Solution to the Matrix yields: Pg1 = 687.5 MW Pg2 = 312.5 MW λ = $33.75/MWh Comparing the results with previous method used, yield similar results IC1 = IC2 = 20 + 0.02Pg1 = 15 + 0.06(1000- Pg1), Pg1 = 687.5 Pg2 = 1000- 687.5) = 312.5 Cost = 20 + 0.02 * 687.5 = 15 + 0.06 * 312.50 = $ 33.75 28 Two Generator (GEN) Power Flow & Economic Dispatch System Example The example shown in Figure 2-4 below covers the general concept of how we go from power flow to economic dispatch Figure-2.4 Gauss-Seidel-Method Bus 1 is slack bus: V =1@ 0° degree Schedule power at Bus 2 is 1.2 pu Schedule power at Bus 3 is 1.5 pu Calculate: 1. YBus model 2. Bus voltage using Gauss-Seidel Method 3. Power mismatch at Bus 2 & 3 4. Power supply by the swing bus 5. Power loss of transmission lines 6. Assume there was no loss, what would be the additional revenue for this system over a 5year period @ 5% and $20/MW Solution (1) Y 11 Y 12 Y 13 Y 22 Y 12 Y 23 Y 33 Y11 Y12 Y13 14 4 10 Y Y Y Y 4 9 5 BUS 21 22 23 Y31 Y32 Y33 10 5 15 29 Y 23 Y 13 (2) k 1 n 1 S k Vk (i 1) [ Y V ( i 1) YknVn (i)] kn n Ykk Vk (i) n 1 n k 1 V2 (i 1) S 1 [ 2 Y21V1 (i 1) Y23V3 (i)] Y 22 V2 (i ) S3 1 V3 (i 1) [ Y31V1 (i 1) Y32V2 (i 1)] Y 33 V3 (i) Table 2.2 Voltage Iteration Iteration 0 1 2 3 4 5 Voltage (V2) 1 1.1333 1.0621 1.0885 1.0784 1.0781 Voltage (V3) 1 0.9 0.9333 0.9224 0.9180 0.917 V2 = 1.078 p.u., V3 = 0.917 pu S2 = V2 (Y21 * V1* Y22 * V2 * + Y23 * V3 *) = 1.078(-4x1 + 9 x1.078-5.0917) = 1.2041 S3 = V3 (Y31 * V1* Y23 * V2 * + Y33 * V3 *) = 0.917(-10 x 1 - 5 x1.078 + 15 x.0917) = 1.4993 30 Power mismatch at Bus 2 ∆S2 = S2cal – S2sch = 1.2041 – 1.2 = 0.041 ∆P2 = P2cal – P2 = 1.2041 – 1.2 = 0.041 ∆Q2 = Q2cal – Q2sch = 0 – 0 = 0 Power mismatch at Bus 3 ∆S3 = S3cal – S3sch = 1.4993 – (-1.5) = 0.0007 ∆P3 = P3cal – P3 = 1.4993 – (-1.5) = 0.0007 ∆Q3 = Q3cal – Q3sch = 0 – 0 = 0 (4) Power supply by swing bus S1 = V1 (Y11* V1 * Y12 * V2 * +Y13 * V3 *) ∆P2 = 1 ∙ (14 ∙1-4 ∙ 1.078-10 ∙ 0.917) = 0.518 For a resistive power system, P1=S1=0.518, Q1=0. (5) Power loss of transmission lines: S loss = P loss = S1 + S2 + S3 = 0.518 + 1.2041 – 1.4993 = 0.223 (6) 1 (1 rp ) n NPV [ ]R Investment Cost rp Where rP = %Return for the project R = Cash Flow N = Number of years Given: 5% interest rate, $20/MW and a power loss of 0.233 pu (22.3 MW) Cash flow = 20 * 22.3 * 24 * 365 = 3,906,960 NPV 1 ( 1.05) 5 3906960 0 1.692 107 0.05 NPV = $16.92 M (If no power loss in the system) 31 2.3 System-3 Three Generators Economic Dispatch Applications In economic dispatch systems where there are more than 2-generating units, two pieces of data will be available for us to work with. They are total load and IC curves of each unit. By using the Lambda Iteration Method, we can find Lambda which is the cost that will produce optimum condition. This approach is carried out by using an iterative procedure that will allow us to: (1) pick an initial value for Lambda (2) find the corresponding output power each generating unit. (3) Check if output power is less required load In addition, if the total power is less than the load, then we would increase Lambda and go step two, Else, condition met (stop). Lambda Iteration Method & Example Pick L and H Such that m P i 1 Gi ( L ) PD 0 m P i 1 ( H ) PD 0 Gi While H L Do M ( H L ) 2 m If P i 1 Gi ( M ) PD 0 Then H M Else L M Assuming a three generator system with the following: IC1 (PG1) = 15 + 0.02PG1 = λ $/MWh IC2 (PG2) = 20 + 0.01PG1 = λ $/MWh IC3 (PG3) = 18 + 0.025PG1 = λ $/MWh and with a constraint PG1 + PG2 + PG3 = 1000 MW. Rearranging the equations as a function of λ, PGi (λ), to allow PG1 (λ) = 15 0.02 PG3 (λ) = 18 PG2 (λ) = 20 0.01 0.025 32 Now the task is to find what value of Lambda that will allow us to meet the system demand (1000 MW). Pick L so that m P Gi i 1 Pick H so that ( L ) 1000 0 and m P i 1 ( H ) 1000 0 Gi m Try L 18 Then P (18) 1000 i 1 15 0.02 20 0.01 Gi 18 0.025 1000 650 m Try H 32 Then P (32) 1000 i 1 15 0.02 20 0.01 Gi 18 0.025 1000 1610 Assume convergence tolerance 0.05$ / MWh The iterate since | L H | M L H 2 Then since m (25) 1000 280 set H 25 Gi |25-18| > 0.05 M m P i 1 0.05 18 32 25 2 P i 1 and L H 2 18 25 21.5 2 (21.5) 1000 385 set L 21.5 Gi Continue the iteration until | H L | 0.05 The convergence value of lambda ( ) is 23.53 $/MWh Upon knowing we can calculate the PGi 33 PG1 (23.5) (23.5) 23.53 15 426.5 MW 0.02 23.53 20 353 MW 0.01 PG 3 (23.5) 23.53 18 221.2 MW 0.025 PG1 PG 2 PG 3 1000 MW The results are within the constraint of PG1 PG 2 PG 3 1000 MW given at the out set. This method starts with a Lambda valve below and above the optimal value shown here. The main disadvantages of this approach in comparison to the direct method are: (a) more challenging (b) more time consuming. The main advantage in using this method is that it works for both linear and non linear application. While on the other hand, the direct method is only accurate for linear applications. Another method is to use the direct formula for Lambda which will yield similar results. This direct method works well if the incremental cost curves are linear and all the generators are below their limits. See formula below. ngen P Demand i1 ngen i1 i 2i 1 2 i For example, if generating station has a three generator system with the following, IC1 (PG1) = 15 + 0.02 PG1 = λ $/MWh IC2 (PG2) = 20 + 0.01 PG1 = λ $/MWh IC3 (PG3) = 18 + 0.025 PG1 = λ $/MWh With a constraint of: PG1 + PG2 + PG3 = 1000 MW 34 The solution using direct method is shown below ngen P Demand i 1 ngen 1000 i 2i 15 0.02 1 1 0.02 20 0.01 1 0.01 18 0.025 1 23.526 0.025 2 i i 1 P ( 23.53) G1 P ( 23.53) G2 PG1 = 426.5 MW, P PG2 = 253 MW, ( 23.53) G3 P 1 P 2 P 3 23.53 15 P 426.5 0.02 1 23.53 20 P 353 2 0.01 23.53 18 0.025 PG3 = 221.2 MW P 221.2 3 PG1 + PG2 + PG3 = 1000 MW In addition, we can use software option to solve for lambda. This will take into account the complete cost curve, and provide the option of setting the limit on each generator. For example, if you choose the PG1 = 426.5 MW, PG2 = 253 MW and PG3 = 221.2 MW with an operating cost of 1700, 1000, and 250 respectively, then Matlab code will allow you to find the best value for Lambda. Bear in mind that the Lambda will not be the same since the total operating cost is now factored in. See examples below. 35 2.3.1 Matlab Software Code for 3-Generator Lambda (Cost) Code and Results EDU>> % Example 3-Generator Station gendata = [1700, 15, 0.02; 1000, 20, 0.01; 250, 18, 0.025]; power = [426.5, 353, 221.2]; % find lambda0 n = length (gendata); lambda0 = 0; for i = 1:n lambda0 = lambda0 + gendata (i,2) + 2*gendata(i,3)*power(i); end lambda0 = lambda0 / 3 clear x0 x0 = power, x0(n+1) = lambda0 %calculate the gradient for k = 1 : 10 disp (k) clear gradient gradient = []; pgen = 0, cost = 0; for i = 1:n gradient(i) = gendata(i,2) + 2 * gendata (i,3) * x0(i)- x0(n+i); pgen = pgen + x0(i); cost = cost + gendata (i,1) + gendata (i,2) * x0(i) + gendata (i,3) * x0(i) * x0(i); end gradient(n+1) = Pload - Pgen; disp ([x0, Pgen, cost/1000]) x1 = x0 - gradient * alpha; x0 = x1; lambda0 = 29.3933 x0 = 426.5000 353.0000 221.2000 x0 = 426.5000 353.0000 221.2000 29.3933 36 Please see Matlab code examples for Lagrange Method and Kuhn-Tucker Conditions shown below. Figure-2.5 Three Generator Economic Dispatch Application Using Lagrange Method & Matlab Code EDU>> % Example 3-Generator Station gendata = [1700, 23.76, 0.004686; 1000, 23.55, 0.00582; 250, 23.70, 0.01446]; power = [400, 200, 400]; % find lambda0 n = length (gendata); lambda0 = 0; for i = 1: n lambda0 = lambda0 + gendata (i,2) + 2*gendata(i,3)*power(i); end lambda0 = lambda0 / 3 clear x0 x0 = power, x0(n+1) = lambda0 %calculate the gradient for k = 1 : 10 disp (k) clear gradient gradient = []; pgen = 0, cost = 0; for i = 1:n gradient(i) = gendata(i,2) + 2 * gendata (i,3) * x0(i)- x0(n+i); pgen = pgen + x0(i); cost = cost + gendata (i,1) + gendata (i,2) * x0(i) + gendata (i,3) * x0(i) * x0(i); 37 end gradient(n+1) = Pload - Pgen; Disp ([x0, Pgen, cost/1000]) x1 = x0 - gradient * alpha; x0 = x1; lambda0 = 29.5516 x0 = 400 200 400 x0 = 400.0000 200.0000 400.0000 29.5516 Therefore the cost of generating power is $29.55 per MW/hr 2.3.2 Economic Dispatch with Generator Limits The power output of any generator must not exceed its rating nor drop below a given value for stable boiler operation. The Aim is to find the real power generated for each plant to minimize cost, subject to: (1) Meeting load demand - equality constraints (2) Constrained by generator limits – inequality constraints. By using the Kuhn-Tucker Conditions we can formulate the equation that allows one work within such limits. See equation below: dCi/dPi = λ Pi(min) < Pi < Pi(max) dCi/dPi ≤ λ Pi = Pi(max) dCi/dPi ≥ λ Pi = Pi(min) In this example, if one ignores the system losses, the optimal dispatch and the total cost in $/hr for three generators can be found from the following equations: C1 = 1700 + 23.76 P1 + 0.00468P2 ($/MWhr) C2 = 1000 + 23.76 P2 + 0.00468P2 ($/MWhr) C3 = 250+ 23.76 P3 + 0.00468P2 ($/MWhr) 200 ≤ P1 ≤ 450 150 ≤ P2 ≤ 350 100 ≤ P3 ≤ 200 38 Total Demand = 1000 Total cost: C1 = (1700 + 23.76 * 450) + (0.00468 * 4502 ) = 13339.7 + C2 = 1000 + (23.55 * 350) + (0.0058 2* 3502) = 9955.45 + C3 = 250+ (23.70 * 200) + (0.00468 * 2002) = 5568.4 Total Cost = 28,863.6 $/hr Setting Limits to Generators In some applications the Systems Engineer will have to run the generators without limits and in other applications limits must be enforced. An example using three generators will be used to explore the concept of limits. If the generator cost function of three generators are given as: C1 = 472.8 + 7.47 P1 + 0.023 P12 ($/h/MW) 100≤ P1 ≤ 400 C2 = 432.9 + 7.87 P2 + 0.020 P22 ($/h/MW) 150≤ P2 ≤ 350 C3 = 463.9 + 7.56 P3 + 0.022 P32 ($/h/MW) 120≤ P3 ≤ 400 (a) Find the optimal dispatch of the three generators without any limits (b) What is the new dispatch if the generator limits are enforced? 39 Solution ngen P Demand i 1 ngen i 1 1800 i 2i 7.47 0.046 1 1 0.046 7.87 0.040 1 0.040 7.56 0.044 1 33.555 0.044 2 i P P ( 33.555) P ( 33.555) P G2 P 33.555 7.47 1 G1 P ( 33.555) 1 33.555 7.87 2 P 642.125 2 0.040 33.555 7.56 3 G3 P 567.065 0.046 P 590.795 0.044 3 Lower limits are enforced P G2 350 Meets lower limit ngen P Demand i 1 ngen i 1 P G1 350 i 2i G3 0.046 1 0.046 1 2 i 15.387 7.47 0.046 P 7.47 15.387 7.56 0.044 172.109 177.886 40 7.56 0.044 1 0.044 15.387 3.0 System Modeling This section explains how modeling is used in decision analysis as it relates to power system economic dispatch. Modeling is the cog that drives the concept of decision making. It can be defined as a process where the risk is measured and controlled by checks and balances such as planning, assessment, action taken to mitigate risks, monitor the situation and report the findings. Requisite decision modeling will be the focus as it is the answer to “what if” questions in decisionmaking. Modeling is also used for analyzing policy, alternative solution and strategy that helps in making the right decisions with a high degree of confidence. Requisite decision modeling requires a wide range of testing and no new intuitions emerge about the problem the model set out to solve. By using a wide range of testing, one can verify the sensitivity points or parameters that will affect the model. Therefore, by knowing the sensitivity limits on these parameters, one can make decisions with less risks and less uncertainty. In addition, a requisite model will provide the modeler or user with trade-off options between long-term returns and volatility. Modeling in this case is used to ultimately replicate the historical performance of similar projects. It is also very important that a model replicate the data for the right reasons while capturing the underlying structure of the project. In addition, modeling is used to promote inquiry, expose hidden assumptions, motivate the widest range of empirical tests, challenge preconceptions and support multiple viewpoints. Modeling the power system economic dispatch with power world software helps one to get reliable, useful and effective models to serve as virtual worlds to aid learning and policy design. Furthermore, simulation models are always necessary for learning about dynamically complex systems. Figure 3.1 shows a system with 250 MW load and shunt of 50 Mvar with a line condition of 25.92 MW, -8.64 Mvar and 27.32 MVA. By using incremental modeling techniques, one can achieve the condition that will minimize line loss and in return boost cash/NPV. 41 25.92 MW -8.64 Mvar 27.32 MVA 50.0 Mvar 250 MW 250 MW 30.0 Mvar 2 1 100 MW 60 Mvar slack 152 MW 43 Mvar Figure 3.1 Modeling Two Bus System By applying Computerized Simulation using power world software to show power system and power flow as it relates to economic dispatch, we obtain a wide range of power data. The above Figure-3.1 is used to generate the Ybus Sparse to give us the voltage magnitude and angle. The phase angles of different substation or bus cannot be economically measured, but the voltage magnitude is constantly monitored. 42 In order to effectively estimate the voltage magnitude and angle, one must choose a bus as reference, and that bus will now become the standard by which all other bus angles will be measured. The Matlab Software was used to generate voltage magnitude and angle from the above Figure-3.2. See Ybus data below. EDU>> j = sqrt (-1); Ybus = sparse (3); Ybus ( 1, 1) = 10.0000+ j*( -29.6750); Ybus( 1, 2) = -10.0000+ j*( 30.0000); Ybus( 2, 1) = -10.0000+ j*( 30.0000); Ybus( 2, 2) = 10.0000+ j*( -29.4750); Ybus( 3, 3) = 0.0000+ j*( 0.0000); V( 1) = 1.000000 + j*( 0.000000); V( 2) = 1.000000 + j*(-0.017278); V( 3) = 0.000000 + j*( 0.000000); EDU>> The voltage angle of the slack bus shown in Figure-3.2 at bus-1 is used as reference to all the other bus voltages. The angle of the slack bus is not important because the voltage angle difference is used to determine the power (Pi) and the imaginary (Qi) at the load. The slack bus also known as the swing bus is a fictitious concept that is created and defined in the problem formulations. This process allows us to address the I2R losses that are not known before the load flow calculation. 43 0.00 MW 0.00 Mvar 0.00 MVA 50.0 Mvar 250 MW 250 MW 30.0 Mvar 2 1 152 MW 42 Mvar slack 100 MW 60 Mvar Figure-3.2 Bus Modeling By changing line conditions, we were able to eliminate the line loss during the simulation process. Line loss is one of the key components of power system economic dispatch. For example, if we have a scenario where the loss between buses resulted in 50 MW and the cost of generating power is $50 per MWh, then there will be a loss of $50 for every hour which results in $438,000 per year. Therefore, by using modeling techniques, one can exponentially minimize the hours spent on various power flow data such as Ybus, voltage magnitude/angle mismatches and power loss. 44 3.1 Computer Modeling & Simulation By using simulation process to design the system in Figure-3.3, one can learn about the system and document the system behaviors from the view point of power flow and economic dispatch. The approach used is to design a basic system with two generators with the per-unit voltage of the system set 1.0 pu. A system of 1.0 pu is considered a perfect system. In power system design and planning this method is known as a flat start. After the flat start is achieved, the iteration technique is used to increment the system load while documenting the system. Moreover, this process allows us to check the sensitivity of the system to see when the system will collapse. The system collapses at bus 7 when the load of 220MW and 50 Mvar was applied. 1 2 99 MW 17 Mvar A A 300 MW slack Amps MVA 30 Mvar 220 MW 50 Mvar 30 Mvar A A MVA System Callaspses @ 0.95 PU on Bus 7 Amps 4 A 7 Amps A 99.45 MW A MVA 5 MVA 6 50 MW 0 Mvar 20 MW SYSE 505 Student: Ogilvie Donald Figure-3.3 7-Bus System 45 500 MW 100 Mvar The data shown below is from the simulation process in Figure-3.3 and it provides us with the Ybus record for each bus. In order to get the power system economic dispatch, one must deal with the following power flow conditions: (1) Ybus model (2) Bus voltage (3) Power mismatch at each bus (4) Power supplied by the swing bus (5) Power loss of transmission lines (6) Power system economic dispatch. Therefore, since our objective is power system economic dispatch, we must meet all the power flow conditions in order get to the system economics, and there is no better way than simulation modeling to eliminate the hundreds of hours in crunching numbers. Furthermore, when we factor in human fatigue, errors and the duplications, simulation modeling will no doubt be the future of all power system planning and economic dispatch YBus Records Number Name Bus 1 Bus 2 Bus 3 Bus 4 Bus 5 Bus 6 Bus 7 1 1 5.88 - j23.52 -2.94 + j11.76 2 2 -2.94 + j11.76 5.88 - j23.52 -2.94 + j11.76 3 3 -2.94 + j11.76 5.88 - j23.52 0.00 + j0.00 4 4 0.00 + j0.00 2.94 - j11.76 -2.94 + j11.76 5 5 -2.94 + j11.76 5.88 - j23.52 -2.94 + j11.76 6 6 -2.94 + j11.76 8.82 - j35.28 -2.94 + j11.76 7 7 -2.94 + j11.76 5.88 - j23.52 -2.94 + j11.76 -2.94 + j11.76 -2.94 + j11.76 46 -2.94 + j11.76 3.2 Computer simulation of a two bus 1-generator system The Ybus matrix, voltage magnitude and angle are shown below for Figure-3.4. The transmission line data that was used in simulation process came from Figure-2.2. Using Gauss Seidel method of iteration for the problem associated with Figure-2.2 resulted in V2 = 0.987-0.156i, while on the other hand computer simulation yields V2 = 0 979-0.173i for Figure 3.5 resulted in a difference of 0.008 pu. The acceptable tolerance is plus or minus 5% of 100% where 100% = 1.0 pu. j = sqrt(-1); Ybus = sparse(2); Ybus( 1, 1) = 0.0498+ j*( -2.5910); Ybus( 1, 2) = -0.0498+ j*( 2.8810); Ybus( 2, 1) = -0.0498+ j*( 2.8810); Ybus( 2, 2) = 0.0498+ j*( -2.5910); V( 1) = 1.000000 + j*( 0.000000); V( 2) = 0.979153 + j*(-0.173715); 50 MW -24 Mv ar 1 2 slack Figure 3.4 Modeling a Single Generator 47 3.3 Two generator economic dispatch system modeling Figure-3.5 shows a typical 3-bus scenario for modeling. By using computer based simulating we were able to capture all the key components needed to meet our economic dispatch requirements. For example, the bus record number, the bus sensitivity and the bus mismatches provided data such as sensitivity limits and upper and lower per-unit voltage limits. In addition, we can clearly see that under Gen Marginal Loss Sensitivities that there is no megawatt loss or system sensitivity issues. Under bus sensitivities, we can see the assigned limits for each bus for both MW & Mvar. YBus Records Number 1 2 3 Name 1 2 3 Bus 1 1.85 - j24.80 -0.31 + j12.49 -1.54 + j12.31 Bus 2 -0.31 + j12.49 0.87 - j29.14 -0.55 + j16.65 1 Bus 3 -1.54 + j12.31 -0.55 + j16.65 2.09 - j28.96 2 150 MW 0 Mv ar slack 51 MW 0 Mv ar Figure 3.5 100 MW 7 Mv ar 3 Modeling a two Bus Power Flow System 48 Bus Sensitivities Number Number 1 2 3 1 Area Name 1 2 1 1 3 1 1 1 Name 1 2 3 Name 1 2 3 Area Num Area Name 1 1 1 Monitor Yes Yes Yes P Sensitivity Q Sensitivity 0 0.63929194 0.36759728 0.01529269 Limit Group Default Default Default PU Volt 1 1 0.99507 Volt (kV) 138 138 137.319 Limit Low PU Volt 0.9 0.9 0.9 Limit High PU Volt 1.1 1.1 1.1 Ctg Limit Low PU Volt 0.9 0.9 0.9 Ctg Limit High PU Volt 1.1 1.1 1.1 Max MW 1000 1000 Gen Mvar 0.42 7.49 Bus Mismatches Number 1 2 3 Name 1 2 3 Area Name 1 1 1 Mismatch MW Mismatch Mvar 0 0 0 Mismatch MVA 0 0 0 0 0 0 Gen Marginal Loss Sensitivities Number 1 2 Name 1 2 ID 1 1 Status Closed Closed Loss MW Sens Penalty Factor 0 0 49 1 1 Gen MW 50.52 100 Min MW 0 0 4.0 Conclusion This paper has given me the opportunity to research and develop new techniques to simulate and model power systems. For example, Figure 3.3, the 7-Bus System, was designed and developed to meet the requirements of the North American power grid system. The simulated Y-bus data is shown on page 46. In addition, I was able to successfully set the per-unit voltage limits to trip the circuit breaker. If the per-unit voltage varies by +/- 5%, then this action will remove the system from the grid. The focus of this economic dispatch paper is to compare the different ways in which to analyze power systems to get the best economic benefit while minimizing cost. The process of analyzing began with the different fuel sources and their associated cost, and how to minimize cost by making the system more efficient, because power plant measures result in terms of efficiency. In addition, efficiency is output divided by input and in this case our input is heat rate (MWHR/MBTU) and our output in power is MW. By using the input and output concept one can conclude that the system of generating power will maximize profit when the heat is maintained as low as possible while maximizing your output requirements. In the power industry, fuel cost curve provides the best accuracy to effectively analyze heat rate. In fact, power system economic dispatch is driven by the fuel cost curve: Ci ( PGi ) PGi PGi2 and incremental cost which is a derivitive of the fuel cost. Heat rate is widely used in the power industry to troubleshoot the system when the system efficiency drops below optimum setting before or after major system repairs or overhaul. Furthermore after a major overhaul, it is standard practice in this industry to apply minute by minute loading of the system. This minute by minute loading process is shown here with the use of calculus as a source for verification and validation. Matlab Software code was used to generate the fuel cost curve equation, and graph the operational cost against the output power in MW. This paper also focused on 1-generator, 2-generator operation and a 3-generator operation to look at various methods used to determine the cost of power with and without power loss. Although the focus of the paper is on economic dispatch, areas such as per-unit system and power flow was briefly covered to allow one to complete the process from a typical scenarios such as transformers, generators and z-line conditions. Gauss Seidel method of iteration was used to show 50 the overall concept of obtaining the bus voltage from the Ybus matrix and thus the economic dispatch. Moreover, from the power loss conditions this paper was able to obtain the equivalent cash flow using NPV if the system was operating without power loss. Modeling and simulation process was also used to show the effectiveness of using software as a tool to make quick, clear, accurate and explicit decision when planning economic dispatch operation as a system engineer. By using Powerworld software in modeling power system and economic dispatch, this paper shows how to analyze the power loss and the per unit voltage limits to make the system economically viable. For example, Figure 3.5 shows a complete power flow analysis and the data required to perform economic dispatch. In addition, the analysis shows zero power loss and zero mismatches which would result in a perfect system. I would recommend modeling and simulation to be the first step in planning and assessing economic dispatch. It is also an indispensable source for performing verification and validation of power system economic dispatch. 51 Appendix Total Electricity System Power 2009 Total California In-State Power Generation Fuel Type Coal In-State Generation (GWh) Percent of California In-State Power Northwest Imports Southwest Imports Total System Power 3,735 1.8% N/A N/A N/A Large Hydro 25,094 12.2% N/A N/A N/A Natural Gas 116,716 56.7% N/A N/A N/A 31,509 15.3% N/A N/A N/A 67 0.0% N/A N/A N/A 7 0.0% N/A N/A N/A 28,567 13.9% N/A N/A N/A 5,685 2.8% N/A N/A N/A Geothermal 12,907 6.3% N/A N/A N/A Small Hydro 4,181 2.0% N/A N/A N/A Solar 846 0.4% N/A N/A N/A Wind 4,949 2.4% N/A N/A N/A Total 205,695 100.0% 19,929 71,201 296,827 Nuclear Oil Other Renewables Biomass Source: EIA, QFER, and SB 105 Reporting Requirements Note: Due to legislative changes required by Assembly Bill 162 (2009), the California Air Resources Board is currently undertaking the task of identifying the fuel sources associated with all imported power entering into California. 1. In-state generation: Reported generation from units 1 MW and larger. Previous years information (2008 Total System Power). 52 Total Electricity System Power 2008 Total System Power in Gigawatt Hours Fuel Type Coal* In-State Generation[1] Northwest Imports[2] Total System Power Southwest Imports[2] Percent of Total System Power 3,977 8,581 43,271 55,829 18.21% Large Hydro 21,040 9,334 3,359 33,733 11.00% Natural Gas 122,216 2,939 15,060 140,215 45.74% Nuclear 32,482 747 11,039 44,268 14.44% Renewables 28,804 2,344 1,384 32,532 10.61% Biomass 5,720 654 3 6,377 2.08% Geothermal 12,907 0 755 13,662 4.46% Small Hydro 3,729 674 13 4,416 1.44% Solar 724 0 22 746 0.24% Wind 5,724 1,016 591 7,331 2.39% 208,519 23,945 74,113 306,577 100.0% Total Source: 2008 Net System Power Report - Staff Report, Publication number CEC-200-2009-010, to be considered for adoption July 15, 2009. (PDF file, 26 pages, 650 kb) EIA, QFER, and SB 105 Reporting Requirements *Note: In earlier years the in-state coal number included coal-fired power plants owned by California utilities located out-of-state. 1. 2. In-state generation: Reported generation from units 1 MW and larger. Net electricity imports are based on metered power flows between California and out-of-state balancing authorities. The resource mix is based on utility power source disclosure claims, contract information, and calculated estimates on the remaining balance of net imports. Previous years information (2007 Total System Power). 53 Please see web links for energy source and cost information http://greenecon.net/understanding-the-cost-of-solar-energy/energy_economics.html http://greenecon.net/category/alternative-energy http://energyalmanac.ca.gov/electricity/index.html#table 54 References 1. Florida State University 2002 and 2004 EEL 6266 Power System Economics and Control with Matlab Software Code Lecture Notes 2. Tom Overbye, ECE 476, Power System Analysis Lecture 16 Economic Dispatch 3. Thomas J. Overbye, Powerworld Simulator Software 4. Ali. Keyhani, Power Flow Problem Tutorial and Course Notes and Matlab Software Codes 5. Robert T. Clement, Making Hard Decisions 6. Chanan Singh and Panida Jirutitijaroen Power System Control and Operation: Economic Dispatch 7. Form E1A-423 Monthly Cost of Fuels for Electric Plants Report 8. Grainger Stevenson, Power System Analysis 9. Charles A. Gross Power System Analysis 10. http://greenecon.net/understanding-the-cost-of-solar-energy/energy_economics.html 11. http://greenecon.net/category/alternative-energy 12. http://energyalmanac.ca.gov/electricity/index.html#table 55