10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS Introduction The preceding chapters in this Technical Digest have focused on design and construction issues associated with jointed plain concrete pavements. This chapter describes special considerations for the design and construction of reinforced concrete pavements, i.e., pavements with steel reinforcing (either welded wire fabric or deformed rebar) distributed throughout the slab. Characteristics of these pavement types (either jointed reinforced concrete pavements [JRCP] and continuously reinforced concrete pavements [CRCP]) are described in chapter 2. Many of the recommendations presented in the preceding chapters are applicable to reinforced concrete pavements. Several specific design issues and special design considerations for these pavements are highlighted in this chapter. Where previously presented recommendations are applicable to reinforced pavements, references to the appropriate chapters are made. Subgrade Characterization No special requirements are needed for the characterization of the subgrade for the design of reinforced concrete pavements. Thus, the recommendations provided in chapter 3 are applicable. Drainage and Base Type Considerations Drainage design elements and base type considerations, presented for JPCP designs in chapters 4 and 5, respectively, are also applicable to reinforced concrete pavements. However, at least one agency has reported that open-graded drainage layers constructed beneath new CRCP designs appeared to accelerate the development of transverse crack deterioration and punchouts (Heckel 1997). Thus, the use of open-graded bases beneath CRCP should be carefully considered in light of their potential to accelerate the development of distress. Strong, uniform support under CRCP is more critical than permeability. Slab Thickness Design As described in chapter 6, the predominant practice in concrete pavement thickness design is to not differentiate by concrete pavement type; that is, the JRCP or CRCP thickness required for a given design situation is presumed to be the same as the JPCP thickness required (assuming an adequate reinforcement design for JRCP or CRCP). Therefore, the slab thickness design approaches described in chapter 6 for JPCP are also applicable to reinforced concrete pavements. However, as noted in chapter 6, the designer should be aware that it is an extrapolation of the AASHTO model (AASHTO 1993; AASHTO 1998) to apply it to the prediction of performance of undoweled jointed pavements, jointed pavements with stabilized bases, jointed pavements with joint spacings other than those at the Road Test (4.6 m [15 ft] for JPCP and 12.2 m [40 ft] for JRCP), CRCP, or concrete pavements of any type in climates that may produce significantly different curling and warping stresses than those experienced by the Road Test sections. For the Concrete Pavement Design Details and Construction Practices 89 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS purpose of reinforced slab thickness design using the 1998 AASHTO procedure, a hypothetical joint spacing of 9 m (30 ft) should be used for JRCP and 4.6 m (15 ft) for CRCP (AASHTO 1998). Joint Design Table 9, presented in chapter 7, summarizes the types of joints commonly used in concrete pavement construction. These include transverse contraction joints, transverse construction joints, transverse expansion joints, longitudinal contraction joints, longitudinal construction joints, and terminal joints. While the information contained in chapter 7 on expansion joints and on longitudinal joint design is applicable to reinforced pavements, this section presents specific recommendations regarding the design of transverse contraction joints in JRCP and the design of terminal joints in CRCP. JRCP Transverse Contraction Joint Spacing Because JRCP designs contain steel reinforcement distributed throughout the slab, they typically incorporate longer joint spacings than JPCP designs. The slabs are expected to crack but the steel reinforcement is relied upon to hold transverse cracks tightly together and prevent them from deteriorating. However, the performance of many JRCP designs has been compromised by excessive joint spacings (which result in large joint and crack movements) and insufficient steel reinforcement contents (Smith et al. 1990; Smith et. al. 1998). Because of these problems, there has been a movement toward the use of shorter joint spacings for JRCP designs. Maximum joint spacing recommendations for JRCP range from 9.1 m (30 ft) (ACPA 1991; FHWA 1990a) to 13.7 m (45 ft) (Darter et al. 1997), but these recommendations should be tempered by local experience. Because JRCP joints are doweled, skewed joints and/or variable joint spacings are not considered necessary. JRCP Contraction Joint Load Transfer Because JRCP designs typically have longer joint spacings and larger joint openings, the use of dowel bars at transverse contraction joints is always recommended. The recommended dowel diameters, dowel lengths, dowel spacings, and dowel coatings are the same as those for JPCP designs, although dowel alignment tolerances are more critical in JRCP due to the longer joint spacings. JRCP Contraction Joint Sealing and Reservoir Design For JRCP designs, a properly designed joint-seal system is important because of the longer joint spacings and larger anticipated joint openings. The guidelines for the design of the joint-seal system, including the determination of the anticipated joint movements and the design reservoir width, are the same as for JPCP, described in chapter 7. CRCP Terminal Joints 90 Concrete Pavement Design Details and Construction Practices 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS Terminal joints are placed at locations where the continuity of a CRCP slab is interrupted at junctions with fixed structures or other pavements (McCullough 1993). These joints may consist of either a wide-flange beam expansion joint system that accommodates movement or a lug anchor system that restrains movement. Lug anchor systems have been most widely used, and these typically consist of a series of three lugs placed 1.2 m (4 ft) deep and 4.6 m (15 ft) apart (McCullough 1993). The use of lug anchors on soft or cohesionless soil should be avoided. Wide-flange beam expansion joint systems have recently come into greater use. These beams accommodate movement from the pavement while the steel flange protects the corners from spalling and aids in load transfer (McCullough 1993). A sleeper slab is commonly placed beneath the beam to provide additional support to the system. FHWA (1990b) and McCullough (1993) provide more detailed information on the design of CRCP terminal joints. Reinforcement Design Steel reinforcement distributed throughout JRCP and CRCP pavements consists of welded wire fabric (WWF, sometimes referred to as wire mesh and consisting of both transverse and longitudinal wires) or deformed bars that provide reinforcement in the longitudinal or transverse directions. Longitudinal steel reinforcement is the primary steel design element that significantly affects the performance of both JRCP and CRCP. In both designs, its function is to hold cracks tightly together and prevent them from deteriorating under traffic and environmental loadings; an additional requirement of longitudinal steel reinforcement in CRCP is to confine transverse cracking to acceptable widths and spacings. Transverse steel reinforcement may be placed in both of these pavement types to control any longitudinal cracking that may develop. Its use is more common on JRCP designs since these designs typically use welded wire fabric; most CRCP designs do not require transverse reinforcing (Darter et al. 1997). This section provides guidance on the design of longitudinal steel reinforcement for both JRCP and CRCP. The use of transverse steel reinforcement and its design are also described. JRCP Longitudinal Reinforcement Design Types of Reinforcement Steel reinforcement used in JRCP is generally smooth WWF, although a few agencies have used deformed WWF or deformed reinforcing bars. In laboratory studies simulating loading across transverse cracks, concrete slabs containing either deformed WWF or deformed bars were effective in delaying the deterioration of transverse cracks by holding the cracks more tightly than smooth reinforcement (Snyder 1994). Because of this, the use of deformed WWF or deformed bars is strongly recommended for JRCP (Yu et al. 1998). WWF requires a minimum spacing of 102 mm (4 in) between wires in order to facilitate concrete placement and vibration (Yu et al. 1998). Recommended maximum spacings are 305 mm (12 in) for longitudinal wires and 152 mm (6 in) for transverse wires (Yu et al. 1998). Concrete Pavement Design Details and Construction Practices 91 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS Steel Reinforcement Contents The 1993 AASHTO Design Guide’s procedure for determining required longitudinal steel contents in JRCP is not recommended. The procedure is based on the subgrade drag theory and has been shown to be an oversimplification of the actual forces at work, resulting in inadequate steel reinforcement contents (Heinrichs et al. 1989; Kunt and McCullough 1992; Snyder 1994, Vandenbossche 1995). Kunt and McCullough (1992) point out that the AASHTO procedure ignores critical temperature factors and material properties (thermal coefficient, drying shrinkage), and also fails to address critical performance parameters (for example, crack widths, joint opening, and steel stress). Both Snyder (1994) and Vandenbossche (1995) assert that the AASHTO procedure fails to account for the fatigue effects caused by repeated heavy traffic loadings. The selection of longitudinal steel reinforcement contents should be based on past performance and local experience. Longitudinal steel reinforcement contents for JRCP are generally about 0.15 to 0.25 percent of the cross-sectional area of the slab. Numerous field studies on JRCP performance (Darter et al. 1985; Smith et al. 1990; Smith et al. 1998; Khazanovich et al. 1998) have indicated that longitudinal steel contents greatly affect the performance of these pavements, and that higher steel contents lead to improvements in overall performance. Recommended minimum steel contents for various slab thicknesses are provided in table 13 (Darter et al. 1997). Table 13. Recommended minimum longitudinal steel contents for JRCP (Darter et al. 1997). JRCP Slab Thickness, in Minimum Percent Reinforcement 9.5 – 10.5 0.19 10.5 – 11.5 0.20 11.0 – 12.5 0.21 12.0 – 13.5 0.22 13.5 – 15.0 0.23 1 in = 25.4 mm Depth of Reinforcement Placement 92 Concrete Pavement Design Details and Construction Practices 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS It is recommended that the steel reinforcement be placed with a minimum cover of 64 mm (2.5 in) (Yu et al. 1998). However, the reinforcement should be placed well above the mid-depth of the slab in order to effectively hold the transverse cracks tightly together. Alternative JRCP Designs Several JRCP design variations have been employed that show very good performance. For example, Japan constructs a conventionally reinforced JRCP that contains three additional 13mm (0.5-in) diameter deformed bars placed along the outside longitudinal edge of the pavement (Iwama 1964; Nakamura and Iijama 1994). This additional bar effectively controls crack widths and, consequently, crack deterioration (Nakamura and Iijama 1994). Also, the Illinois Department of Transportation (IDOT) has constructed a “hinge joint” design that contains doweled contraction joints at 13.7-m (45-ft) intervals and two hinge joints at the third points of the 13.7-m (45-ft) slab (IDOT 1989; Yu et al. 1998). Deformed tie bars are placed across these hinge joints, thus clustering the steel at key stress points in the pavement and providing an effective longitudinal steel content of 0.26 to 0.29 percent (Yu et al. 1998). Laboratory study of the “hinge joint” design showed no failure after nearly 8 million load cycles (Snyder 1994). CRCP Longitudinal Reinforcement Design Types and Size of Reinforcement Only deformed steel bars should be used as reinforcement for CRCP. The bars should be Grade 60 steel and are generally 13-mm (0.5-in), 16-mm (0.62-mm), or 19-mm (0.75-in) in diameter. Recommended spacing of the longitudinal steel is not less than 102 mm (4 in) or 2½ times the maximum aggregate size (whichever is less), and not greater than 230 mm (9 in) (FHWA 1990b). The use of epoxy coated reinforcing steel is generally not recommended, with the possible exception of areas exposed to heavy applications of salt and deicing chemicals (FHWA 1990b). A recent evaluation of CRCP steel corrosion in Belgium showed that corrosion was light to minimal for twenty pavements ranging in age from 10 to 23 years and containing 0.67 to 0.85 percent longitudinal reinforcement and no epoxy coating (Verhoeven 1993). This suggests that a properly designed CRCP that maintains tight crack widths does not require epoxy coating of the steel. If epoxy coating is used, the FHWA (1990b) suggests increasing the bond area by 15 percent, which implies a concomitant increase in steel reinforcing content. Limited field data, however, indicate that CRCP incorporating epoxy-coated steel does not exhibit irregular crack patterns, suggesting that the increase in steel content may not be warranted (Tayabji et al. 1995). A unique steel reinforcement material for CRCP currently being tested in France is called Flexarm. Flexarm is manufactured as a flat ribbon (2 mm [0.08 in] thick by 40 mm [1.57 in] wide), has a high yield stress (690 MPa [100,000 psi]), and is heat galvanized to prevent corrosion. Early versions contained a regular pattern of alternating bumps and dimples imprinted in the steel to enhance bonding (Peshkin et al. 1993), but more recent version are using a pattern of small slots in the steel. The main advantages of Flexarm are that it reduces the length of the CRCP “construction train” (because the steel can be rolled and fed out right in front of the paver) Concrete Pavement Design Details and Construction Practices 93 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS and its flat shape provides the desired surface bond area with a lower steel content. Evaluation of the long-term performance of this material is ongoing. Steel Reinforcement Contents The 1993 AASHTO Design Guide provides a procedure for determining longitudinal steel contents for CRCP based on three criteria: Limiting crack spacing to between 0.9 and 2.4 m (3 and 8 ft) to prevent spalling and punchouts. Limiting crack widths to 1 mm (0.04 in) to prevent spalling and water penetration. Limiting steel stress to 75 percent of the ultimate steel tensile strength to prevent steel fracture. Steel contents based on each limiting criterion are developed and then the critical steel content of the three is selected as the design value. A procedure similar to AASHTO’s is available from the Concrete Steel Reinforcing Institute (CRSI) that is based on the same limiting criteria but uses slightly different design equations (McCullough 1993). However, when applying these procedures, consideration should be given to achieving smaller crack widths (0.6 mm [0.025 in] or less) to ensure good performance. These procedures can be used to estimate required steel contents in CRCP, but results should be compared with field performance data and local experience. Generally, longitudinal steel reinforcement contents in CRCP are between 0.6 to 0.8 percent of the cross-sectional area, with numerous field studies on CRCP performance (LaCoursiere et al. 1978; FHWA 1993; Tayabji et al. 1995) indicating that increased steel contents lead to an improvement in overall performance. As a general guide, table 14 may be used to indicate minimum longitudinal reinforcement contents for CRCP (adapted from Darter et al. 1997). It should also be noted that thickness control during paving is particularly important for CRCP because variations in the slab thickness produce variations in the steel content as a percentage of the slab’s cross-sectional area. Depth of Reinforcement Placement The longitudinal steel reinforcement should be placed above mid-depth of the slab because it will hold cracks more tightly together and reduce the occurrence of punchouts (Darter et al. 1997). Additionally, the steel should be placed with a minimum cover of 64 to 76 mm (2.5 to 3 in) to protect against corrosion due to the penetration of deicing chemicals (Yu et al. 1998). Table 14. Minimum longitudinal reinforcement contents for CRCP (adapted from Darter et al. 1997). Corresponding 94 Nonfreeze Climate Freeze Climate Concrete Pavement Design Details and Construction Practices 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS Design ESALs (millions) 3–6 6 – 12 12 – 18 18 – 30 30 – 54 54 – 90 90 – 150 Base Type CRCP Slab Thickness, in Percent Steel Bar Size Percent Steel Bar Size Aggregate 7.5 – 9.0 0.60 No. 4, 5, or 6 0.70 No. 5, 6, or 7 Treated 7.25 – 8.75 0.60 No. 4, 5, or 6 0.70 No. 5, 6, or 7 Aggregate 9.0 – 10.75 0.65 No. 5, 6, or 7 0.70 No. 6 or 7 Treated 8.75 – 10.25 0.65 No. 5, 6, or 7 0.70 No. 6 or 7 Aggregate 10.25 – 11.5 0.65 No. 6 or 7 0.70 No. 6 or 7 9.5 – 11.0 0.65 No. 6 or 7 0.70 No. 6 or 7 Aggregate 10.5 – 12.25 0.65 No. 6 or 7 0.70 No. 6 or 7 Treated 10.25 – 12.0 0.65 No. 6 or 7 0.75 No. 6 or 7 Aggregate 11.75 – 13.25 0.65 No. 6 or 7 0.70 No. 6 or 7 Treated 11.25 –13.0 0.65 No. 6 or 7 0.75 No. 6 or 7 Aggregate 12.75 – 14.5 0.65 No. 6 or 7 0.70 No. 6 or 7 Treated 12.25 – 14.25 0.65 No. 6 or 7 0.75 No. 6 or 7 Aggregate 13.75 – 15.75 0.65 No. 6 or 7 0.70 No. 6 or 7 Treated 13.25 – 15.25 0.65 No. 6 or 7 0.70 No. 6 or 7 Treated No. 4 bar = 0.5 in (13 mm) diameter No. 5 bar = 0.62 in (16 mm) diameter No. 6 bar = 0.75 in (19 mm) diameter No. 7 bar = 0.88 in (22 mm) diameter 1 in = 25.4 mm Transverse Reinforcement Design As described earlier, transverse reinforcement may be placed in either JRCP or CRCP for control of longitudinal cracking. It may also be used in CRCP to facilitate construction by supporting longitudinal steel at the required depth and spacing. Because WWF is commonly used for reinforcement in JRCP, transverse steel is generally included in JRCP designs. Although transverse reinforcement is not required for CRCP designs (FHWA 1990b; Darter et al. 1997), it is usually provided since CRCP is more commonly constructed with reinforcement placed on chairs. Local experience and past performance should be reviewed to determine the appropriateness of transverse reinforcement in CRCP. Although it has limitations, transverse steel reinforcement contents may be estimated with the procedure in the AASHTO design guide (AASHTO 1993). The modified design procedure developed by Kunt and McCullough (1992) may also be used. Shoulder Design Considerations The same concepts described in chapter 8 on the design of shoulders apply to reinforced pavements as well. In particular, however, it is generally recommended that transverse joints in a concrete shoulder match the transverse joints in the traffic lane slab to which it is tied. Jointed concrete shoulders (and jointed concrete ramps) can be problematic when tied to CRCP Concrete Pavement Design Details and Construction Practices 95 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS traffic lanes because opening of the joints in the shoulder may cause adjacent shrinkage cracks in the CRCP to open and deteriorate. States that construct CRCP try to avoid this problem by using CRCP or AC ramps, and AC shoulders, with CRCP traffic lanes. Also as described in chapter 8, the 1986/1993 AASHTO design procedure incorporates the benefit of a concrete shoulder in reducing slab stress through the selection of the J factor. An appropriate J factor must be selected from table 12 in chapter 8 for the specific pavement type and load transfer conditions. Construction Considerations In general, the construction considerations described in chapter 9 also apply to reinforced concrete pavements. Two additional areas of concern for reinforced pavements are given below. Transverse Construction Joints Transverse construction joints are placed at the end of each day and where interruptions in paving occur. Weather conditions should govern the length of delay which is considered sufficient to warrant placing a construction joint. In hot, dry conditions, 30 minutes is a reasonable limit on the allowable delay; in cooler, wetter conditions, up to an hour or more may be reasonable. Transverse construction joints are placed by staking a bulkhead and tiebars to terminate the fresh concrete slab. When constructing CRCP, the longitudinal reinforcement must pass through the transverse construction joint bulkhead so that it can be tied or welded to the steel in the concrete which is placed the following day. Additional consolidation may be required when placing new concrete adjacent to the previous day’s construction. If more than 5 days elapse between concrete pours, the adjacent pavement temperature should be stabilized by placing insulation material on it for a distance of 61 m (200 ft) from the free end at least 72 hours prior to placing new concrete (FHWA 1990b). This procedure should reduce potentially high tensile stresses in the longitudinal steel (FHWA 1990b). Steel Reinforcement Placement Steel reinforcement for JRCP is placed in welded wire fabric sheets or bar mats. The width of the fabric sheets or bar mats should be such that the extreme longitudinal members are not less than 50 mm (2 in) or more than 150 mm (6 in) from the edges of the slab (ACI 1991). When JRCP is to be paved in two lifts, the reinforcement can be placed directly on the first lift, and the second lift placed over the reinforcement. The time between placement of the first and second lifts must be strictly controlled to prevent debonding of the layers. If the full slab thickness is to be placed in a single lift, the reinforcement is placed on the freshly placed surface and vibrated or pressed down to the proper depth. Adjacent reinforcing sheets or bars must be lapped and tied (ACI 1991). Steel reinforcement for CRCP is generally placed on chairs at the specified height, ahead of the paver. Lap splices in CRCP longitudinal reinforcement must be carefully constructed to maintain steel continuity and to prevent cracking of the concrete. Furthermore, these laps should 96 Concrete Pavement Design Details and Construction Practices 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS be staggered across the pavement to reduce localized strain in the slab or nearby construction joint (CRSI 1983). Inadequate laps and poor consolidation near construction joints are the most common construction-related deficiencies for CRCP. References for Special Design Considerations for Reinforced Concrete Pavements American Concrete Institute (ACI). 1991. “Guide for Construction of Concrete Pavements and Concrete Bases.” Manual of Concrete Practice. ACI 325.9R-91. American Concrete Institute, Detroit, MI. American Concrete Pavement Association (ACPA). 1991. Design and Construction of Joints for Concrete Highways. TB–010.0 D. American Concrete Pavement Association, Arlington Heights, IL. American Association of State Highway and Transportation Officials (AASHTO). 1993. Guide for Design of Pavement Structures. American Association of State Highway Officials, Washington, DC. American Association of State Highway and Transportation Officials (AASHTO). 1998. Supplement to the Guide for Design of Pavement Structures. American Association of State Highway Officials, Washington, DC. Concrete Reinforcing Steel Institute (CRSI). 1983. Construction of Continuously Reinforced Concrete Pavements. Concrete Reinforcing Steel Institute, Schaumburg, IL. Darter, M. I., J. M. Becker, M. B. Snyder, and R. E. Smith. 1985. Portland Cement Concrete Pavement Evaluation System—COPES. NCHRP Report 277. Transportation Research Board, Washington, DC. Darter, M. I., H. Von Quintus, Y. J. Jiang, E. B. Owusu-Antwi, and B. M. Killingsworth. 1997. Catalog of Recommended Pavement Design Features. Final Report, NCHRP Project 1-32. Transportation Research Board, Washington, DC. Federal Highway Administration (FHWA). 1990a. Concrete Pavement Joints. FHWA Technical Advisory T 5040.30. Federal Highway Administration, Washington, DC. Federal Highway Administration (FHWA). 1990b. Continuously Reinforced Concrete Pavement. FHWA Technical Advisory T 5080.14. Federal Highway Administration, Washington, DC. Federal Highway Administration (FHWA). 1993. Report on the 1992 U.S. Tour of European Concrete Highways. FHWA-SA-93-012. Federal Highway Administration, Washington, DC. Heckel, L. 1997. “Open-Graded Drainage Layers: Performance Problems Under Continuously Reinforced Concrete Pavements.” Proceedings, Sixth International Purdue Conference on Concrete Pavement Design Details and Construction Practices 97 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS Concrete Pavement Design and Materials for High Performance. Purdue University, West Lafayette, IN. Heinrichs, K. W., M. J. Liu, M. I. Darter, S. H. Carpenter, and A. M. Ioannides. 1989. Rigid Pavement Analysis and Design. FHWA-RD-88-068. Federal Highway Administration, Washington, DC. Illinois Department of Transportation (IDOT). 1989. Mechanistic Pavement Design. Supplement to Section 7 of the Illinois Department of Transportation Design Manual. Illinois Department of Transportation, Springfield, IL. Iwama, S. 1964. Experimental Studies on the Structural Design of Concrete Pavement. Report of Public Works Research Institute, Volume 117. Ministry of Construction, Tokyo, Japan. Khazanovich, L., M. I. Darter, R. Bartlett, and T. McPeak. 1998. Common Characteristics of Good and Poorly Performing PCC Pavements. FHWA-RD-97-131. Federal Highway Administration, Washington, DC. Kunt, M. M., and B. F. McCullough. 1992. Improved Design and Construction Procedures for Concrete Pavements Based on Probabilistic Modeling Techniques. FHWA/TX-92+1169-5F. Texas Department of Transportation, Austin, TX. LaCoursiere, S. A., M. I. Darter, and S. A. Smiley. 1978. Performance of Continuously Reinforced Concrete Pavements in Illinois. FHWA-IL-UI-172. Illinois Department of Transportation, Springfield, IL. McCullough, B. F. 1993. Design of Continuously Reinforced Concrete Pavements for Highways. Concrete Reinforcing Steel Institute, Schaumburg, IL. Nakamura, T. and T. Iijama. 1994. “Evaluation of Performance and Structural Design Methods of Cement Concrete Pavements in Japan.” Proceedings, Seventh International Symposium on Concrete Roads. Vienna, Austria. Peshkin, D. G., M. I. Darter, and J. Aunis. 1993. “The Construction and Performance of Concrete Pavements Reinforced with Flexarm.” Proceedings, Fifth International Conference on Concrete Pavement Design and Rehabilitation. Purdue University, West Lafayette, IN. Smith, K. D., D. G. Peshkin, M. I. Darter, A. L. Mueller, and S. H. Carpenter. 1990. Performance of Jointed Concrete Pavements, Volume I—Evaluation of Concrete Pavement Performance and Design Features. FHWA-RD-89-136. Federal Highway Administration, Washington, DC. Smith, K. D., M. J. Wade, D. G. Peshkin, L. Khazanovich, H. T. Yu, and M. I. Darter. 1998. Performance of Concrete Pavements, Volume II—Evaluation of Inservice Concrete Pavements. FHWA-RD-95-110. Federal Highway Administration, Washington, DC. 98 Concrete Pavement Design Details and Construction Practices 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS Snyder, M. B. 1994. “Effects of Reinforcement Design and Foundation Stiffness on the Deterioration of Transverse Cracks in Jointed Reinforced Concrete Pavements.” Proceedings, Third International Workshop on the Design and Evaluation of Concrete Pavements. Krumbach, Austria. Tayabji, S. D., P. J. Stephanos, and D. G. Zollinger. 1995. “Nationwide Field Investigation of Continuously Reinforced Concrete Pavements.” Transportation Research Record 1482. Transportation Research Board, Washington, DC. Vandenbossche, J. M. 1995. An Analysis of the Longitudinal Reinforcement in a Jointed Reinforced Concrete Pavement. M.S. Dissertation. Michigan State University, East Lansing, MI. Verhoeven, K. 1993. “Cracking and Corrosion of Continuously Reinforced Concrete Pavements.” Proceedings, Fifth International Conference on Concrete Pavement Design and Rehabilitation. Purdue University, West Lafayette, IN. Yu, H. T., K. D. Smith, M. I. Darter, J. Jiang, and L. Khazanovich. 1998. Performance of Concrete Pavements, Volume III—Improving Concrete Pavement Performance. FHWA-RD-95111. Federal Highway Administration, Washington, DC. Concrete Pavement Design Details and Construction Practices 99 10. SPECIAL DESIGN CONSIDERATIONS FOR REINFORCED CONCRETE PAVEMENTS 100 Concrete Pavement Design Details and Construction Practices