Networking Project Milestones and Objectives The ultimate goal of this project is to redesign the network in the 114 MRC data center to improve security and scalability. Milestone 1 – Documentation of Existing Network Infrastructure and Inventory Complete Target Completion Date – February 20th, 2009 Objective 1 – Gain Understanding of Network Infrastructure Objective 2 – Take Inventory of Current Hardware Objective 3 – Document Layout of Current Network (Ie. Switches, servers, external drops, etc) Deliverables: Word document documenting current layout. Excel spreadsheet with up to date hardware inventory of the data center, Room 114 MRC Milestone 2 – Requirements Gathering Complete Target Completion Date – February 23rd, 2009 Objective – Gather network requirements Deliverables: A document detailing the current, 1 year, and 3 year projections for network requirements. Milestone 3: Needs Analysis Complete Target Completion Date – February 25th, 2009 Objective – Determine number of Networks Objective – Determine if Networks will be Separate Objective – Examine External Drops with our Requirements Objective – Determine IP Addressing Deliverables: A document detailing the answers to the above questions. Milestone 4 – Network Research and Design Complete Target Completion Date – March 6th, 2009 Objective – Research Current Hardware and Capabilities Objective – Determine Which Hardware will be Reused/Retired Objective – Research New Hardware Objective – Determine New Hardware Objective – Determine Which Network to Which Switch Objective – Determine the overall layout of the new network Deliverables: A document detailing the recommended network design and that addresses all of the above areas. Presentation to all other systems administrators in the group for peer review. Revise design if required based on peer review. List of hardware to be purchased. Milestone 5 – Create Detailed Upgrade Plan. Target Completion Date – March 13th, 2009 Objective – Create a detailed list of the procedure involved with the upgrade (include necessary networks changes as well as server side changes such as modifications to ip addresses). Objective – Approximate the amount of preparation time required for the upgrade Objective – Approximate the resources required for implementation, including the number of man hours Objective – Detail the impact on production systems and the expected outage window required for the upgrade. Deliverables: A comprehensive upgrade document. Peer review of plan and revisions as required. Milestone 6 – Completion of Network Upgrade Target Completion Date – March 27th, 2009 Objective – Schedule time for upgrade Objective – Notify users of impact Objective – Execute upgrade plan Deliverables: Successful execution of the upgrade plan.