Networking Project Milestones and Objectives

advertisement
Networking Project Milestones and Objectives
The ultimate goal of this project is to redesign the network in the 114 MRC data center to
improve security and scalability.
Milestone 1 – Documentation of Existing Network Infrastructure and Inventory
Complete
Target Completion Date – February 20th, 2009
Objective 1 – Gain Understanding of Network Infrastructure
Objective 2 – Take Inventory of Current Hardware
Objective 3 – Document Layout of Current Network (Ie. Switches, servers,
external drops, etc)
Deliverables:
 Word document documenting current layout.
 Excel spreadsheet with up to date hardware inventory of the data center, Room
114 MRC
Milestone 2 – Requirements Gathering Complete
Target Completion Date – February 23rd, 2009
Objective – Gather network requirements
Deliverables:
 A document detailing the current, 1 year, and 3 year projections for network
requirements.
Milestone 3: Needs Analysis Complete
Target Completion Date – February 25th, 2009
Objective – Determine number of Networks
Objective – Determine if Networks will be Separate
Objective – Examine External Drops with our Requirements
Objective – Determine IP Addressing
Deliverables:
 A document detailing the answers to the above questions.
Milestone 4 – Network Research and Design Complete
Target Completion Date – March 6th, 2009
Objective – Research Current Hardware and Capabilities
Objective – Determine Which Hardware will be Reused/Retired
Objective – Research New Hardware
Objective – Determine New Hardware
Objective – Determine Which Network to Which Switch
Objective – Determine the overall layout of the new network
Deliverables:
 A document detailing the recommended network design and that addresses all of
the above areas.
 Presentation to all other systems administrators in the group for peer review.
 Revise design if required based on peer review.
 List of hardware to be purchased.
Milestone 5 – Create Detailed Upgrade Plan.
Target Completion Date – March 13th, 2009
Objective – Create a detailed list of the procedure involved with the upgrade
(include necessary networks changes as well as server side changes such as modifications
to ip addresses).
Objective – Approximate the amount of preparation time required for the upgrade
Objective – Approximate the resources required for implementation, including the
number of man hours
Objective – Detail the impact on production systems and the expected outage
window required for the upgrade.
Deliverables:
 A comprehensive upgrade document.
 Peer review of plan and revisions as required.
Milestone 6 – Completion of Network Upgrade
Target Completion Date – March 27th, 2009
Objective – Schedule time for upgrade
Objective – Notify users of impact
Objective – Execute upgrade plan
Deliverables:
 Successful execution of the upgrade plan.