5.2.5 Development Plans Mining The development plans for all three cases are presented in the following series of tables. Cases 1, 2 and 3 all assume the same mine development sequence and the delivery of 2.8 million tons per year (8000 tpd) to the concentrator. Table 5.2.5-1 illustrates the mine sequence. The rational for this sequence has been described previously in section 2.2.6 of this volume. Mine production will continue in the Tajo until 1998 when it will move to Chabuca Sur. Open Pit production will continue through 2000 at Chabuca Sur. Underground development for Chabuca Este and Coroccohuayco will begin in 1997 which will allow enough time for them to be in full production by year 2001. Mining at a rate of 1.4 million tonnes annually form each of these deposits can continue until 2008 based on current reserves. Coroccohuayco will have a few years ore still available after this. Mining from areas under and beside the current Tajo are not programmed into this schedule. Annual mine operating costs are shown in Table 5.2.5-2. They are based on the following unit costs: Surface Mining US$ 0.90 per tonne (increased to US$1.00 after 1996) Chabuca Este US$ 9.50 per tonne Coroccohuayco US$ 12.50 per tonne. Mine operating costs will climb from the US$ 18 million forecast for 1994 to over US$ 30 million by 2002. This cost is directly related to the movement from open pit to underground mining. It is compensated by higher grade ore grades. Significant expenditures will be necessary to develop the known mine reserves. Table 5.2.5-3 shows the equipment and infrastructure costs associated with each operation. Table 5.2.5-4 shows the mine development costs. Details have been provided previously in section 2.2 of this volume. The total anticipated equipment and infrastructure capital cost to allow mining to continue over the next 15 years is US$ 119 million. Mine development costs are forecast to be US$ 38 million over the same period. The combined total is US$ 157 million. The majority of this (US$ 137 million) will have to be spent between know and 2000 to insure sufficient mill feed. PAH has previously explained that optimization of mine planning and consideration of open pit mining at Chabuca Sur may have a significant positive impact on the amount and timing of capital expenditures. Further study is called for and PAH strongly recommends that this be considered. Case 1 Case 1 assumes a continuation of the current practice of custom smelting concentrates. The concentrator production schedule is shown in Table 5.2.5-5. Although mill feed is kept constant at 2.8 million tonnes annually, concentrate production climbs from 164,410 tonnes in 1994 to 220,770 tonnes by 2002. This is a direct function of the higher ore grades anticipated from Chabuca Este and Coroccohuayco. Concentrator operating and capital costs are shown in Table 5.2.5-6. Annual operating costs are based on a unit cost of US$ 6.00 per tonne ore processed. Capital costs are for sustaining capital and some plant modification with the exception of new tailings capacity. A new investment of US$ 7.5 million will be required by the year 2000 to insure adequate tailings capacity. General, Administrative and Marketing expenses are shown in Table 5.2.5-7. Annual G&A costs are fixed at US$3.5 million. Although these costs appear modest in comparison to many operations it should be pointed out that Tintaya accounting policy allocates certain G&A costs back to the mine and mill areas. This results in those areas being slightly higher than might be expected. PAH has continued with this policy in its cost estimation. Annual FSR costs are based on a unit cost of US$ 0.33 per pound copper payable. This includes all inland freight, ocean going freight, smelting and refining charges. Table 5.2.5-8 presents a breakdown of unit operating costs on a US$ per pound copper produced basis. Although there are minor variations the average operating cost is US$ 0.68 per pound for the life of the current reserves. This figures do not include capital amortization. Based on total anticipated capital expenditure of US$ 173 million and production of 1.9 billion lbs (1994-2008) this would add another US$0.09 to the cost. Case 2 The second alternative development plan, Case 2, maintains concentrate production as described but also includes recovery of copper form oxide resources. This development of these resources has been discussed in section 5..1.5 of this Volume. Table 5.2.5-9 presents anticipated oxide copper production as well as the forecast production and investment costs. Full scale production would begin in 1997 and continue through the life of the project. Initial production would come from the existing high grade stockpiles. However subsequent processing of lower grade materials would result in a drop of production. There are potential but unquantified higher grade resources that could be substituted for the low grade material in later years. Initial production is expected to be 17,000 tonnes annually. This will continue for six years before dropping off. Total capital expenditures, including the operation of a pilot plant for two year, is forecast to be approximately US$ 56 million. Annual operating costs of US$ 11.4 million is based on a unit cost of US$ 12.54 per tonne ore processed and US$ 0.43 per tonne material moved from the existing stockpiles. Cathode freight costs of US$ 60 per tonne are additional to the operating costs. Total unit costs per pound of copper produced would drop significantly in Case 2 (Table 5.2.5-10). Costs would drop to a low of US$ 0.55 per pound copper in the peak years of oxide production. Although the average cost will climb in later years this trend could be reversed by the identification of higher grade oxide resources. Case 3 The construction of an on-site submerged combustion smelter combined with sulfuric acid production and recovery of oxide copper is modeled for Case 3. Concentrates will be treated on-site to produce blister copper which will be shipped for refining. The smelter production schedule and costs are shown in Table 5.2.5-11. This scenario results in the same total copper production as Case 2. This case has the advantage of eliminating custom smelting charges and lowering freight costs due to shipment of higher value added products. Also sulfuric acid would be generated as a byproduct which can be used in the oxide recovery process. This would eliminate the US$ 80 per tonne acid cost included in Case 2. This advantages are partially offset by higher on-site operating cost (smelter costs). Annual smelter operating costs vary between US$ 13.5 and US$ 17.5 million. This is based on a unit cost of US$ 0.1231 per pond of copper in blister. Blister refining charges are US$ 0.11 per pound payable copper. Blister freight charges are estimated at US$ 60 per tonne. Based on a purity of 97.5 percent this translate into US$ 0.028 per pound copper. The total FSR charges under Case 3 are therefore US$ 0.26 per pound. This represents a reduction of US$ 0.07 from custom smelting. Annual savings are approximately US$ 7-8 million depending on the volume of copper produced. The production cost of oxide copper will also drop under this scenario as acid is generated as a by-product of smelting. This would eliminate the estimated US$ 80 per tonne cost for delivered acid. Copper oxide production costs would drop substantially from the US$ 12.54 per tonne ore treated (Case 2) to US$ 6.99 per tonne treated. This results in an annual saving of about US$ 5 million. The cost savings will not come without a price. The estimated investment expense is estimated to be US$ 64.4 million. PAH emphasizes that this Case is conceptual and substantial investigation will be required before its feasibility is proven. Table 5.2.5-12 shows the total unit operating costs per pound of copper. During best years this would be reduced to US$0.48/lb.