CL-07-02 Crane Lift Study Checklist

advertisement
CRANE LIFT STUDY – CHECK LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Page 1 of 6
PROJECT TITLE
SITE MANAGER
DATE
PROPOSED WORK METHODOLOGY
WORK PARTY
LOCATION
DESCRIPTION
REVIEW OF PROPOSED PROCEDURES & EQUIPMENT
MANDATORY REQUIREMENTS
HAZARD
CONTROL MEASURE
CHECKED
Unidentified Job
Specific Hazards
JHA to be carried out by staff detailing on the day hazards that could
not be practically assessed prior to attending site in addition to this
“CHECK LIST”. All staff to sign on to JHA accepting this form and the on
the day hazards and controls. JHA has been completed and approved
by the relevant personnel in accordance with the JHA Procedure
Hydro Hazards-Lack
of awareness of
local asset and
other simultaneous
operations
Unlisted Specific Lift
Hazards
Works Manager to notify work party of ALL Hydro Tasmania Assets in
area (including Protection PLC, Mechanical, Electrical and Civil
Assets). Work party to inspect and make safe
No crane works are to take place until the lift study has been
completed in full
Riding load or hook is prohibited
Load never lifted over workers or plant
Unknown Crane
Type
Unknown Crane
Owner
Unknown Capacity
Unknown Crane
Driver / Operator
Unknown Rigger(s)
Ticket No
Unknown Designed
Lifting Points
Ensure design drawings and or Maintenance Manuals are available
that designate / specify correct and certified lifting points and their
designed lifting capacity
Ticket No(s)
DOCUMENT REFERENCE: CL – 07 – 02
REVISION: 4
HYDRO-285-68
DATE: 19/06/2012
CRANE LIFT STUDY – CHECK LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Page 2 of 6
PROJECT TITLE
SITE MANAGER
DATE
GENERAL REQUIREMENTS
HAZARD
CONTROL MEASURE
Unacceptable
lifting Equipment
and arrangement
Weight of Load to be lifted
(see page 4)
Weight of Lifting Equipment
(see page 4)
Total Weight
(see page 4)
Load Slinging Arrangement Agreed
Slinging Points Assessed as Suitable
The Need for Load Control Assessed
Review daily crane operational check list
Control and slinging / rigging by certified rigger /
dogman
Radius from Centre of Crane to Centre of Load
From Crane Chart - Capacity of Crane as per Radius
Location of crane confirmed
Crane Operating Correctly (Limits, Faults, Remotes,
Speed, Brakes etc)
Area Clear for Lift and no Obstructions in Lift Path
Landing Floor Clear & Prepared
Floor Loading Confirmed Acceptable
Ground condition checked and suitable
Incorrect
operation of
Crane
Unsuitable Crane
Position
Unsuitable Crane
Condition
Unsuitable
Landing Area
Soft or Unsuitable
Ground
N/A
CHECKED
Location of underground services checked and marked
Overhead Hazards
Faulty
Communications
Fences or
Buildings in Close
Proximity
High Winds,
Snow, Electrical
Storms Etc
Unsuitable Lifting
Gear Selection
Unauthorised
Access
Stable operating surface and levelling blocks
Area checked for powerlines and other obstructions
and adequate clearance available
Communication system checked and operational
Working Radius established and marked
Weather conditions checked and favourable
Lifting Gear adequate, inspected & tagged, certified
with SWL, suitable for task, checked and in good
condition. E.g. Shackles, Strops, Slings, Chains, Lifting /
Spreader Beams etc
Restrict Access to work area. Signs / barricades
Warning siren
DOCUMENT REFERENCE: CL – 07 – 02
REVISION: 4
HYDRO-285-68
DATE: 19/06/2012
CRANE LIFT STUDY – CHECK LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Page 3 of 6
PROJECT TITLE
SITE MANAGER
DATE
GENERAL REQUIREMENTS
HAZARD
Falls From Heights
Lack of Coordination
SLING PLANT ID
NUMBER
CONTROL MEASURE
N/A
CHECKED
Provision of fixed access scaffold
Elevated work platform or similar
Safety Harness and Lanyard
Works Manager to supervise or delegate responsibility
Works Manager to notify Production manager of date
and time of lifts
Works Manager to notify Generation Operations of
date and time of lifts
Contractor to have direct communication with Works
Manager
S.W.L
DOCUMENT REFERENCE: CL – 07 – 02
WITHIN CURRENT
CERTIFICATION
REVISION: 4
VISUALLY
INSPECTED
HYDRO-285-68
N/A
CHECKED
DATE: 19/06/2012
CRANE LIFT STUDY – CHECK LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Page 4 of 6
PROJECT TITLE
SITE MANAGER
DATE
DESCRIPTION
NO
YES
Does the task require the use of multiple cranes
Location on Site of Lift
Date of Lift
Person Supervising the Lift
Position
CRANE AND PERSONNEL DETAILS
CRANE 1
Crane Type
Crane Owner
Capacity(SWL)
Crane Driver
Rigger(s)
Ticket No(s)
Ticket No(s)
CRANE 2
Crane Type
Crane Owner
Capacity(SWL)
Crane Driver
Rigger(s)
Ticket No(s)
Ticket No(s)
CRANE 3
Crane Type
Crane Owner
Capacity(SWL)
Crane Driver
Rigger(s)
CRANE
NUMBER
CRANE 1
CRANE 2
CRANE 3
ESTIMATED SHARE
OF LOAD
(%)
Ticket No(s)
Ticket No(s)
RADIUS FROM
CRANE TO LOAD
(M)
CAPACITY OF CRANE
FROM CHARTS
(T)
ADJUSTED
CAPACITY
(SEE NOTE) (T)
ESTIMATE LOAD
FOR EACH CRANE
(T)
TOTAL CAPACITY
NOTE: For Multiple crane lifts, it is a statutory requirement that the capacity of each crane at
the require boom or jib length be as follows.

For Two Cranes: 20 percent in excess of calculated load share

For Three Cranes: 33 percent in excess of calculated load share
DOCUMENT REFERENCE: CL – 07 – 02
REVISION: 4
HYDRO-285-68
DATE: 19/06/2012
CRANE LIFT STUDY – CHECK LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Page 5 of 6
PROJECT TITLE
SITE MANAGER
DATE
SKETCH OF LIFT
DOCUMENT REFERENCE: CL – 07 – 02
REVISION: 4
HYDRO-285-68
DATE: 19/06/2012
CRANE LIFT STUDY – CHECK LIST
PROJECT NUMBER
WORKS MANAGER
DOCUMENT NUMBER
Page 6 of 6
PROJECT TITLE
SITE MANAGER
DATE
SITE REGISTRATION (Note: Applies to all Work Parties and personnel working on site)
REQUIREMENT
CHECKED
Permit To Work issued
Visitors register sheet or emergency board being used. Site Map issued (showing
emergency assembly areas and fire equipment)
Hydro Tasmania Level 2 O H & S Induction complete
Hydro Tasmania Level 3 Site induction complete
S
ADDITIONAL PERSONAL PROTECTIVE EQUIPMENT (COMPLIANT WITH AUSTRALIAN STANDARDS)
REQUIREMENT
CHECKED
REQUIREMENT
CHECKED
REQUIREMENT
CHECKED
CERTIFICATION
I have personally checked and verified all items on all pages of this check list
Works Manager Name
Signature
Date
I acknowledge and agree that all items are detailed on all pages of this check list. I agree to ensure that
all employees and sub-contractors engaged in this work will fully comply with all control measures
indicated
Manager of Work Party Name
Signature
Date
DAILY REVIEW
IF THERE IS A SIGNFICANT CHANGE IN WORK AND OR CONDITIONS A NEW CHECK LIST IS REQUIRED
DATE AND TIME
DOCUMENT REFERENCE: CL – 07 – 02
REVIEWED / COMMENT
REVISION: 4
NEW CHECK LIST REQUIRED
HYDRO-285-68
DATE: 19/06/2012
Download