10 MW Biomass Based Power Plant ABEIL G1. INTRODUCTION Amrit Bio Energy and Industries Ltd (henceforth abbreviated as ABEIL) has been incorporated as a Public Limited Company on 29th January,2004 . This company was promoted by Shri. K.C.Dujari, Chairman & Managing Director and Smt. Sudha Dujari, Director. ABEIL is planning to set up an 11 MW independent biomass based power plant at Jagi Road in Mayong Circle of Marigaon district in Assam. This will be the first Independent Biomass Based Power Plant at Assam. 1.1 BACKGROUND AND INTRODUCTION Biomass is known to be an important energy source for developing countries like India. Its importance is now being reaffirmed even by developed countries in view of its renewable and environment friendly character. In our country also, optimum utilization of biomass resources could not only lead to savings in conventional energy but also result in many indirect benefits. In view of this, the Ministry of Non Conventional Energy Sources has been promoting electricity generation from biomass as a means of full exploitation of its inherent energy value. Among the technologies being promoted for this purpose is the megawatt scale power generation through combustion using boiler and turbine and gasification, using Gasifier and producer gas engines. Combustion route is used for independent biomass power plants and also in cogeneration mode. These projects are covered under the Biomass Power/Cogeneration Programme of Ministry of Non Conventional energy Sources, Govt. of India. The Ministry initiated the programme for promotion of these routes of biomass utilization almost a decade back and significant achievements have been made in this period towards their commercialization and establishment as a viable and environment friendly electricity generation option. 1.2 POTENTIAL The annual generation of biomass materials covering residues from agriculture, forestry, and plantation operations, is estimated at more than 550 million tons. Biomass is classified into three categories. Crop residues like Cotton stalks, mustard stalks, etc, agro industry residues like rice husk, bagasse, etc and from waste lands and forest. Biomass is also categorized into two functional categories like, suitable for fodder and suitable for power generation. Biomass suitable for fodder is not considered for power generation, eventhough the biomass is surplus. It has been estimated that about 70-80% of these wastes are used as fodder, as fuel for 10 MW Biomass Based Power Plant ABEIL domestic cooking and for other economic purposes leaving behind 120-150 millions tons of usable agro residues per year which could be made available for power generation. By using these surplus agro residues and the wastes from forestry and plantations, it has been estimated that more than 16,000 MW of grid quality power can be generated. In addition, around 3,500 MW of power can be produced, if the sugar mills in the country switch over to modern techniques of optimum co-generation. The States having the maximum potential for bagasse based cogeneration include Maharashtra, Uttar Pradesh, Tamil Nadu, Karnataka and Andhra Pradesh, while the States having greater potential for biomass based power generation include Andhra Pradesh. Tamil Nadu, Karnataka, Chhattisgarh, Bihar, Punjab etc. 1.3 ACHIEVEMENTS To tap this large potential, the Ministry has been implementing biomass power & bagasse cogeneration programme for the last 10 years. Over these years, 120 projects aggregating to 805 MW have been installed in the country for feeding power to the grid. In addition, it is estimated that another 91 projects aggregating to 822.43 MW of electricity are under various stages of implementation. The installed capacity includes 60 projects of bagasse based cogeneration aggregating to 437 MW and the capacity under implementation includes 42 projects aggregating to 435.43 MW of bagasse cogenerated electricity. 60 Biomass based power plants are already in operation with installed capacity of 342.5 MW and 49 projects are under various stages of completion. With the commissioning of pipeline projects, Biomass Based Power plants will contribute 730 MW, and bagasse based cogeneration projects – 898 MW. This capacity is in addition to the Biomass Gasifier systems, aggregating more than 62 MW. The States which have taken a leadership position in implementation of cogeneration projects include Andhra Pradesh, Tamil Nadu, Karnataka and Uttar Pradesh, while for biomass power projects, the leading States are Andhra Pradesh, Karnataka and Tamil Nadu. Government of India, had announced the power policy, where captive power plants are not needing any approval. With this policy, number of industries are opting for captive biomass based power plants. 1.4 MNES POLICY Ministry of Non Conventional Energy Sources (MNES) Govt. of India is promoting the power generation from renewable energy sources in general and the Power Group of Ministry is 10 MW Biomass Based Power Plant ABEIL specially promoting the Biomass Based Power Plants and Cogeneration power plants. MNES is giving fiscal and financial benefits to the project developers. Ministry had announced the fiscal incentives common for all renewable energy projects and announced category wise financial incentives. These financial incentives are also modified/revised from time to time. Fiscal Incentives are: 1. Accelerated depreciation –100% in first year of investment 2. Income tax exemption for 10 Years 3. Sales Tax exemption for plant and machinery a. Some states had given sales tax exemption for the equipment used in the renewable energy project. Some states had given additional price per unit is given from the sales tax revenue to the extent of project cost. And some states have allowed to off set the Sales tax payment with other products of industry 4. Excise duty or custom duty exemption a. Excise duty and custom duty is exempted on the plant and machinery of the project. Ministry has also extended the Capital subsidy for Biomass Based Power plants and Bagasse based cogeneration power plants. At present, Government of India had announced that rapid depreciation will be upto 80% of the project cost estimates in the first year, instead of 100% as announced earlier. Even though notification was generally exempting the excise duty for renewable energy projects, excise department had not given this concession to biomass based power plants and bagasse based cogeneration systems, as the boiler and turbine can be used for conventional systems also. Ministry of Finance, Govt. of India had issued notification no: 33/2005 dated 8.9.2005, clearly indicating that, plant and machinery needed to set up the biomass based power plants are exempted for excise and custom duty. Copy of the notification is given below: TO BE PUBLISHED IN PART II, SECTION 3, SUB-SECTION (i) OF THE GAZETTE OF INDIA, EXTRAORDINARY, DATED THE 8TH SEPTEMBER, 2005 17 BHADRAPADA, 1927 (SAKA) 10 MW Biomass Based Power Plant ABEIL GOVERNMENT OF INDIA MINISTRY OF FINANCE (DEPARTMENT OF REVENUE) *** New Delhi, dated the 8th September, 2005 17 Bhadrapada , 1927 (Saka) NOTIFICATION No. 33/ 2005-Central Excise G.S.R. (E).- In exercise of the powers conferred by sub-section (1) of section 5A of the Central Excise Act, 1944 (1 of 1944), the Central Government being satisfied that it is necessary in the public interest so to do, hereby exempts all items of machinery, including prime movers, instruments, apparatus and appliances, control gear and transmission equipment and auxiliary equipment (including those required for testing and quality control) and components, required for initial setting up of a project for the generation of power using non-conventional materials, namely, agricultural, forestry, agro-industrial, industrial, municipal and urban waste, bio waste or poultry litter, falling under any Chapter of the First Schedule to the Central Excise Tariff Act, 1985(5 of 1986), from the whole of the duty of excise leviable thereon which is specified in the said First Schedule, subject to the following conditions,(i) before the clearance of the goods from the factory, the manufacturer produces to the Deputy Commissioner of Central Excise or the Assistant Commissioner of Central Excise, as the case may be, a certificate, from an officer not below the rank of a Deputy Secretary to the Government of India in the Ministry of Non-Conventional Energy Sources recommending the grant of this exemption and the said officer certifies that the goods are required for initial setting up of a project for the generation of power using non-conventional materials, namely, agricultural, forestry, agro-industrial, industrial, municipal and urban waste, bio waste or poultry litter; and (ii) the manufacturer proves to the satisfaction of the Deputy Commissioner of Central Excise or the Assistant Commissioner of Central Excise, as the case may be, that there is a valid power purchase agreement between the importer and the purchaser, for the sale and purchase of electricity generated using non-conventional materials, for a period of not less than ten years from the date of commissioning of the project. [F.No. 460 / 44 /2005-Cus.V] (Ajay) Under Secretary to the Government of India The indications are that, MNES is planning to give capital subsidy instead of interest subsidy. This amount is paid to the financial institution through IREDA after commissioning of the power project. 10 MW Biomass Based Power Plant 1.5 ABEIL STATUS OF BIOMASS BASED POWER PLANTS Biomass Based power plants are in operation since 1992 in India, whereas these plants are in operation in the world since mid eighties. In California, biomass based power plants of 50 MW capacity are also in operation. Status of Projects Commissioned and under Implementation as on 30.9.2005 PROJECTS BIOMASS POWER MW Commissioned Nos. CO-GENERATION MW Nos. TOTAL MW Nos 342.5 60 462.53 60 805.03 120 Under Implementation 387.04 49 435.43 42 822.43 91 Total 729.54 109 897.96 102 1627.46 211 State-Wise status of Commissioned & Under Implementation Biomass Power / CoGeneration Projects as on 28/2/2005 S.N. State Commissioned No. of Projects 1 Andhra Pradesh 2 Under Implementation Capacity (in MW) No. of Projects Capacity (in MW) 48 257.25 19 135.96 Chhattisgarh 2 11 5 51 3 Gujarat 1 0.50 0 0 4 Haryana 2 6 0 0 5 Karnataka 15 151.98 20 155.66 6 Madhya Pradesh 1 1.00 0 0 7 Maharashtra 9 36.00 8 75.80 8 Punjab 3 22 1 6 9 Rajasthan 1 7.8 4 29.10 10 Tamil Nadu 19 173 9 77.00 11 Uttar Pradesh 10 73.00 8 64.30 Total Status of Assam 111 739.53 74 594.82 1.5.1 Assam Energy Development Agency is the nodal agency to give the approvals for setting up Biomass Based Power Plants in the state of Assam. Government of Assam is not yet 10 MW Biomass Based Power Plant ABEIL announced the policy of power purchase from Renewable Energy Projects. This project will be the first independent biomass based power project of Assam. Assam State Electricity Regulatory Commission while issuing the tariff order for the financial year 2005-06, had given special emphasis to promote renewable energy projects in the state. Relevant portion of the order is reproduced below: 11.28 Under section 86 (e) of the Act, the Commission to: “(e) promote co-generation and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity to any person, and also specify, for purchase of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licence;” 11.29 The Commission has considered this requirement and decided that it is too early to prescribe any purchase requirements on the Discom who have only been established late last year. 11.30 The Commission is interested in encouraging renewable energy for stand alone power systems or for remote villages not connected to the grid where a renewable energy source may be a more cost effective option to improve the reliability of supply instead augmenting the existing network. 11.31 ASEB had prepared a policy for small hydro power development up to 25 MW in the State of Assam and sent the draft policy to Assam Electricity Regulatory Commission for comment. AERC suggested a number of modifications in the policy. 11.32 To encourage generation of power from renewable sources, the Commission may consider fixing appropriate tariff for such generation if such a generation system is connected to grid. Wheeling charges for wheeling the generated energy will also be determined by the Commission. 11.33 The Commission is also decided in this tariff order to create an incentive for consumers to switch to solar hot water systems. In Assam, during winter months very high consumption of 10 MW Biomass Based Power Plant ABEIL electricity is observed during the morning hours resulting in peaking of demand in morning in addition to normal peak hours. One of the reason for Assam Electricity Regulatory Commission Tariff Order FY 2005-06 this peaking of demand in the morning during winter matters is use of water heating appliances like geysers, immersion rods etc. These heating appliances consume high amounts of electricity. 11.34 For proper grid management it is essential that consumers should be encouraged to opt for alternative methods to meet their water heating requirements. Solar water heaters offer an excellent alternative to electrical water heating system and can help in a big way in reducing the demand during the morning hours. It also results in substantial reduction in the consumers’energy bills. So use of solar heating is, thus, a win-win situation for consumers as well as utilities. 11.35 In order to encourage consumers to switch over to solar water heating system, the Commission proposes to introduce a monthly rebate of Rs.30 for all consumers who have installed such solar water heating systems for meeting their hot water requirements and these are actually used. To avail this rebate, the consumer will be required to give the licensee an affidavit to the effect that such a system has been installed on his premises and is being used to meet his water heating requirements. The declaration can be verified by the licensee’s meter readers / representative, if required. In case, any such declaration is found to be false, the licensee apart from taking appropriate legal action against such consumer would be entitled to recover the entire rebate allowed to such consumers with 100% penalty. As per the estimates of 2006-07 the power requirement of ASEB is more than the availability during the months of April, June and September-February.The deficit of 221MU for the year of 2006-07(after considering an export of 140 MU during the surplus months) has to be made up by purchasing power from traders at an estimated average cost of Rs.3.57 per unit.To this the indirect benefits of renewable energy needs to be added before fixing the tariff for biomass based power. . 1.6 ROLE OF FINANCIAL INSTITUTIONS The leading financial institution extending the financial assistance is IREDA. Indian Renewable Energy Development Agency (IREDA) the financial arm of Ministry also extends the financial assistance for setting up these power plants. The other financial institutions like IDFC, IDBI, 10 MW Biomass Based Power Plant ABEIL ICICI, HUDCO and nationalized banks like State Bank of India, Andhra Bank etc are also extending the financial assistance. IREDA is having the fixed rate of interest, irrespective of the promoter, but it is having different rate of interest depending upon the capacity of the power plant and the boiler pressure. Whereas, the other financial institutions interest rate is depending upon the credit rating of promoter, i.e. PLR rate of financial institution and some points. As per IREDA’s guidelines, the promoter has to bring minimum of 30% of project cost as their equity. The interest rate for the biomass power projects is 10.5%. Repayment of loan is for the period of 10 years after commissioning. This period is inclusive 3 years of moratorium followed by loan repayment. Special concession is given for North Eastern states Concessions given to North Eastern States are given below: Grid Connected Power Projects: 1. Rebate of 1.0% pa in interest rates 2. Exemption from Payment of a. Registration Fees b. Inspection Charges c. Legal Charges (other than incurred for Recovery) d. Expenditure Incurred on Nominee Directors e. Front End Fee 3. Concession of 5% in Promoters contribution 4. Cost of DPR preparation for Grid Connected projects by BDAS Security norms of IREDA are given below: 1. Equitable mortgage (Mortgage by deposit of title deeds) of all immovable properties; 2. Hypothecation of movable assets, both existing and future subject to prior charge of Banks on specified current assets 3. Guarantees by promoters/promoter Directors and promoter companies 4. Deposit of post dated cheques in accordance with repayment schedule of principal loan amount and interest. HUDCO: HUDCO also gives the term loan to the extent of 70% of the project cost. Conditions of HUDCO are given below: 10 MW Biomass Based Power Plant ABEIL For Bagasse/Bio-Mass Based Co-generation Schemes: Availability of bagasse and other secondary fuel (minimum 125%) of requirement for the proposed capacity of co-generation scheme Scheme may have provision for use of alternate fossil fuel such as coal as per MNES norms. Design parameter should be for 65 Kg per Sq. cm. pressure / 485 degree C temperature or higher steam parameters. The minimum capacity of the sugar unit should be 2500 TCD. Minimum annual DSCR of 1.2 and Average DSCR of 1.5. The minimum IRR of the project should be at least 15% or 3% more than HUDCO’s Rate of Interest whichever is higher. Track record of two successful crushing seasons of sugarcane with no outstanding dues in cane procurement and other goods in case of bagasse based co-generation project. The agency should not have been in loss during the last three financial years. However, in case of newly formed borrowing agencies, the proposal can be considered on the financial strength of the project/parent company with additional risk mitigation measures, such as, reduced debt exposure or increased margin of security for loan. In such cases, the balance sheet of the parent company should be examined. Mortgage/hypothecation of all project properties (land, building and plant & machinery and equipment) for private agencies. The total security cover should be minimum 150% (likely to be increased to 175%)of the loan amount which shall include 125% (likely to be increased to 150%)cover towards prime security and minimum 25% in the form of collateral security (for private sector schemes only): The 25% collateral security cover can be through any or combination of the items indicated below: a. Cash deposits (minimum of 15% of loan amount) b. First charge (pledge of equity shares of any other listed Company / hypothecation / mortgage) on personal properties of promoters. c. First charge (pledge / hypothecation/ mortgage) on other unencumbered properties of the company (other than project assets) or other un-encumbered properties of any other person / company. d. Pari-passu charge (hypothecation of movable properties and/or mortgage of immovable properties not financed by HUDCO) with other lenders. In addition to the above, agency shall furnish the following: Personal guarantee of Promoters. Corporate Guarantee (if promoter is a Company) A letter of Undertaking from the Agency to credit into the TRA all the Govt. subsidies (including MNES subsidies) This TRA account will be under the control of HUDCO. Assignment of contractual rights, title, interest, benefit, claims under various project documents, agreements and all licenses, permits, approvals and consents in respect of the project. 10 MW Biomass Based Power Plant ABEIL Power of Attorney to sell the project assets. Assignment of all insurance policies relating to the project up to the satisfaction of HUDCO. Pledging of 51% of equity shares (if available) to HUDCO. Opening of Trust and Retention Account/Escrow Account as per HUDCO norms with first charge on all receivables in HUDCO’s favour. Corporate guarantee acceptable to HUDCO. The valuation of the properties should be done by a valuer recognized by the Income Tax Department / Nationalised Banks/ Government approved valuer for the purpose of mortgage of the properties. Post dated cheques of the closely held Companies/Firms/Association of persons. 1.7 ASSAM GOVT POLICIES Ministry of Non Conventional Energy Sources, Govt. of India, had given the guidelines on power purchase by state electricity boards. Assam Government is yet to announce the policy based on the guidelines of MNES. Based on the projected deficit of 221MU for 2006-07 for which power is being purchased at an average rate of Rs.3.57 per unit,the cap ratef for the sale of renewable power to the grid can be fixed at Rs.3.50 per unit for a quantum of 200MU per annum. 1.8 ADVANTAGES OF BIOMASS BASED POWER PLANTS Biomass based project situated in rural areas will contribute the following: 1.8.1 * Employment Generation * Social Consideration * Impact on National Power Employment Generation Biomass based power plant purely depends on the biomass collection. Biomass is obtained as crop residue and agro industrial residue. As the biomass is having low bulk density and needs a scientific approach for collection unemployed youths can form a NGO to collect the biomass and sell the same to project. In nutshell biomass bank will be created. Biomass preparation system followed by transportation will help the locals to be employed. Even power plant needs the operating persons. This plant will keep the skilled manpower hence the local youth are exposed to the skilled jobs. There is an indirect employment generation, as more industries will come up in the area, due to less problems of power in that location. Hence there will be requirement of additional manpower. 10 MW Biomass Based Power Plant 1.8.2 ABEIL Social Considerations The setting up of the proposed plant will have a very positive impact on the purchasing capacity of individuals as they will be able to get money for the crop residue, which at present is either, burnt or too much under utilized. 1.8.3 Impact on National Power Today most of the states are having distribution losses of more than 20%. As the power is available at local point, this power will be equivalent to 120% of the conventional power plant generation. This will save the transmission losses and also assures the reliability in power supply. The power generation from biomass plays an important role in supplementing the power requirement in rural areas. This power generation leads to decentralized power generation and improves the general condition of rural masses. At present biomass is being used to generate steam and power in agro industries like Sugar Plants and rice mills. The biomass is also used as fodder, domestic fuel and left out is burnt in the open areas. Biomass is produced as crop residue, agro industry residue and waste from barren and uncultivable land and forests. Even though cattle also generate biomass as dung, the quantity is consumed as domestic fuel in combination with wood. Biomass consumption is taken for domestic fuel, cattle feed, manure, thatching etc. Biomass is consumed in industry, to generate steam. Today the surplus biomass is burnt in the open fields due to non-availability of attractive proposal. Biomass Based Power Plants will get the benefit of CDM. 1.9 Climatic Change Problem and Response 1.9.1 The United Nations Framework Convention on Climate Change, UNFCCC In June 1992, the “United Nations Framework Convention on Climate Change” (UNFCCC) was signed in Rio de Janeiro by over 150 nations. The climate convention is the base or international co-operation within the climate change area. In the convention the climate problem’s seriousness is stressed. There is a concern that human activities are enhancing the natural greenhouse effect, which can have serious consequences on human settlements and ecosystems. The convention’s overall objective is the stabilization of greenhouse gas conncentrations in the atmosphere at a level that would prevent dangerous anthropogenic 10 MW Biomass Based Power Plant ABEIL interference with the climate system.” The principle commitment applying to parties of the convention is the adoption of policies and measures on the mitigation of climate change, by limiting anthropogenic emissions Global Environmental Concerns greenhouse gases and protecting and enhancing greenhouse gas sinks and reservoirs. The commitment includes the preparation and communication of national inventories of greenhouse gases. The Climate convention does not have any quantitative targets or timetables for individual nations. However, the overall objective can be interpreted as stabilization of emissions of greenhouse gases by year 2000 at 1990 levels. The deciding body of the climate convention is the Conference of Parties (COP). At the COP meetings, obligations made by the parties are examined and the objectives and implementation of the climate convention are further defined and developed. The first COP was held in Berlin, Germany in 1995 and the latest (COP 10) was held in December 2004,Buenos Aires, Argentina. 1.9.2 The Kyoto Protocol There is a scientific consensus that human activities are causing global warming that could result in significant impacts such as sea level rise, changes in weather patterns and adverse health effects. As it became apparent that major nations such as the United States and Japan would not meet the voluntary stabilization target by 2000, Parties to the Convention decided in 1995 to enter into negotiations on a protocol to establish legally binding limitations or reductions in greenhouse gas emissions. It was decided by the Parties that this round of negotiations would establish limitations only for the developed countries, including the former Communist countries (called annex A countries). Negotiations on the Kyoto Protocol to the United Nations Framework Convention on Climate Change (UNFCCC) were completed December 11, 1997, committing the industrialized nations to specify, legally binding reductions in emissions of six greenhouse gases. The 6 major greenhouse gases covered by the protocol are carbon dioxide (CO2), methane (CH4), nitrous oxide (N2O), hydro fluorocarbons (HFCs), per fluorocarbons (PFCs), and sulfur hxafluoride (SF 6). Emissions Reductions The United States would be obligated under the Protocol to a cumulative reduction in its greenhouse gas emissions of 7% below 1990 levels for three greenhouse gases (including carbon dioxide), and below 1995 levels for the three man-made gases, averaged over the commitment period 2008 to 2012. 10 MW Biomass Based Power Plant ABEIL The Protocol states that developed countries are committed, individually or jointly, to ensuring that their aggregate anthropogenic carbon dioxide equivalent emissions of greenhouse gases do not exceed amounts assigned to each country with a view to reducing their overall emissions of such gases by at least 5% below 1990 levels in the commitment period 2008 to 2012. The amounts for each country are listed as percentages of the base year, 1990 and range from 92% (a reduction of 8%) for most European countries--to 110% (an increase of 10%) for Iceland. Developing Country Responsibilities Another problematic area is that the treaty is ambiguous regarding the extent to which developing nations will participate in the effort to limit global emissions. The original 1992 climate treaty made it clears that, while the developed nations most responsible for the current buildup of greenhouse gases in the atmosphere should take the lead in combating climate change; developing nations also have a role to play in protecting the global climate. Developing countries, including India and China, do not have to commit to reductions in this first time period because their per-capita emissions are much lower than those of developed countries, and their economies are less able to absorb the initial costs of changing to cleaner fuels. They have not contributed significantly to today’s levels of pollution that has been the product of the developed world’s Industrial Revolution. The idea is that developing countries will be brought more actively into the agreement as new energy technologies develops and as they industrialize further. Annex I and Annex II Parties Annex I parties are countries which have commitments according to the Kyoto protocol. The entire Annex I parties are listed in the Table 9.1 below. Further Annex I parties shown in bold are also called Annex II parties. These Annex II parties have a special obligation to provide “new and additional financial sources” to developing countries (non Annex I) to help them tackle climate change, as well as to facilitate the transfer of climate friendly technologies to both developing countries and to economies in transition. Commitments are presented as percentage of base year emission levels to be achieved during between 2008 – 2012. Actions required from developed and developing Nations The Kyoto Protocol does call on all Parties (developed and developing) to take a number of steps to formulate national and regional programs to improve "local emission factors,” activity data, models, and national inventories of greenhouse gas emissions and sinks that remove these gases from the atmosphere. All Parties are also committed to formulate, publish, and 10 MW Biomass Based Power Plant ABEIL update climate change mitigation and adaptation measures, and to cooperate in promotion and transfer of environmentally sound technologies and in scientific and technical research on the climate system. Who is bound by the Kyoto Protocol? The Kyoto Protocol has to be signed and ratified by 55 countries (including those responsible for at least 55% of the developed world's 1990 carbon dioxide emissions) before it can enter into force. Now that Russia has ratified, this been achieved and the Protocol will enter into force on 16 February 2005. 1.9.3 India’s Greenhouse Gas Emissions India has experienced a dramatic growth in fossil fuel CO2 emissions, and the data compiled by various agencies shows an increase of nearly 5.9 % since 1950. At present India is rated as the 6th largest contributor of CO2 emissions behind China, the 2nd largest contributor. However, our per capita CO2 of 0.93 tons per annum is well below the world average of 3.87 tons per annum. Fossil fuel emissions in India continue to result largely from coal burning. India is highly vulnerable to climate change as its economy is heavily reliant on climate sensitive sectors like agriculture and forestry. The vast low-lying and densely populated coastline is susceptible to rise in sea level. The energy sector is the largest contributor of carbon dioxide emissions in India. The national inventory of greenhouse gases indicates that 55% of the total national emissions come from energy sector. These include emissions from road transport; burning of traditional bio-mass fuels, coal mining, and fugitive emissions from oil and natural gas. Agriculture sector constitutes the next major contributor, accounting for nearly 34%. The emissions under this sector include those from enteric fermentation in domestic animals, manure management, rice cultivation, and burning of agriculture residues. Emissions from Industrial sector mainly came from cement production. Indian Response to Climatic Change Under the UNFCCC, developing countries such as India do not have binding GHG mitigation commitments in recognition of their small contribution to the greenhouse problem as well as low financial and technical capacities. The Ministry of Environment and Forests is the nodal agency for climate change issues in India. It has constituted Working Groups on the UNFCCC and Kyoto Protocol. Work is currently in progress on India's initial National Communication (NATCOM) to the UNFCCC. India ratified the Kyoto Protocol in 2002. 10 MW Biomass Based Power Plant 1.9.4 ABEIL The Conference of the Parties (COP) The Conference of the Parties is the supreme body of the Climate Change Convention. The vast majority of the world’s countries are members (185 as of July 2001). The Convention enters into force for a country 90 days after that country ratifies it. The COP held its first session in 1995 and will continue to meet annually unless decided otherwise. However, various subsidiary bodies that advise and support the COP meet more frequently. The Convention states that the COP must periodically examine the obligations of the Parties and the institutional arrangements under the Convention. It should do this in light of the Convention’s objective, the experience gained in its implementation, and the current state of scientific knowledge. Exchange of Information The COP assesses information about policies and emissions that the Parties share with each other through their national communications. It also promotes and guides the development and periodic refinement of comparable methodologies, which are needed for quantifying net greenhouse gas emissions and evaluating the effectiveness of measures to limit them. Based on the information available, the COP assesses the Parties efforts to meet their treaty commitments and adopts and publishes regular reports on the Convention’s implementation. Support for Developing countries Developing countries need support so that they can submit their national communications, adapt to the adverse effects of climate change, and obtain environmentally sound technologies. The COP therefore oversees the provision of new and additional resources by developed countries. The third session of the Conference of the Parties adopted the Kyoto Protocol. 1.9.5 The Flexible Mechanisms The Kyoto protocol gives the Annex I countries the option to fulfill a part of their commitments through three “flexible mechanisms”. Through these mechanisms, a country can fulfill a part of their emissions reductions in another country or buy emission allowances from another country. There are three flexible mechanisms: 10 MW Biomass Based Power Plant ABEIL i. Emissions trading ii. Joint implementation iii. Clean development mechanism i) Emissions trading Article 17 of the Kyoto protocol opens up for emissions trading between countries that have made commitments to reduce greenhouse gas emissions. The countries have the option to delegate this right of emissions trading to companies or other organisations.In a system for emissions trading, the total amount of emissions permitted is pre-defined. The corresponding emissions allowances are then issued to the emitting installations through auction or issued freely. Through trading, installations with low costs for reductions are stimulated to make reductions and sell their surplus of emissions allowances to organizations where reductions are more expensive. Both the selling and buying company wins on this flexibility that trade offers with positive effects on economy, resource efficiency and climate. The environmental advantage is that one knows, in advance, the amount of greenhouse gases that will be emitted. The economical advantage is that the reductions are done where the reduction costs are the lowest. The system allows for a cost effective way to reach a predefined target and stimulates environmental technology development. i) Joint Implementation, JI Under article 6 of the Kyoto protocol an Annex I country that has made a commitment for reducing greenhouse gases, can offer to, or obtain from another Annex I country greenhouse gas emissions reductions. These emissions reductions shall come from projects with the objectives to reduce anthropogenic emissions from sources or increase the anthropogenic uptake in sinks. In order to be accepted as JI-projects, the projects have to be accepted by both parties in advance. It also has to be proven that the projects will lead to emissions reductions that are higher than what otherwise would have been obtained. JI-projects are an instrument for one industrial country to invest in another industrial country and in return obtain emissions reductions. These reductions can be used to help fulfill their own reduction commitments at a lower cost than if they had to do the reductions in their own country. 10 MW Biomass Based Power Plant ABEIL Clean Development Mechanism (CDM) Article 12 of the Kyoto protocol defines the Clean Development Mechanism, CDM. The purpose of CDM is to: a) Contribute to sustainable development in developing countries; b) Help Annex I-countries under the Kyoto Protocol to meet their target. With the help of CDM, countries which have set themselves an emission reduction target under the Kyoto Protocol (Annex I countries) can contribute to the financing of projects in developing countries (non-Annex I countries), which do not have a reduction target. These projects should reduce the emission of greenhouse gases while contributing to the sustainable development of the host country involved. The achieved emission reductions can be purchased by the Annex I country in order to meet its reduction target. In order to be accepted as CDM-projects, the projects have to be accepted by both parties in advance. It also has to be proven that the projects will lead to emissions reductions that are higher than what otherwise would have been obtained. The difference between JI-projects and CDM-projects is that JI-projects are done between countries that both have commitments, while the CDM-projects is between one country that has commitments and another country that does not have commitments. Emissions reductions that have been done through CDMprojects during the period 2000 to 2007 can be used for fulfilling commitments in Annex I countries for the period 2008-2012. How CDM works? An investor from a developed country, can invest in, or provide finance for a project in a developing country that reduces greenhouse gas emissions so that they are lower than they would have been without the extra investment – i.e. compared to what would have happened without the CDM under a business as usual outcome. The investor then gets credits – carbon credits - for the reductions and can use those credits to meet their Kyoto target. If the CDM works perfectly it will not result in more or less emission reductions being achieved than were agreed under the Kyoto Protocol, it will simply change the location in which some of the reductions will happen. For example, a French company needs to reduce its emissions as part of its contribution to meeting France’s emission reduction target under the Kyoto Protocol. Instead of reducing emissions from its own activities in France, the company provides funding for the construction of a new biomass plant in India that would not have been able to go ahead without this investment. This, they argue, prevents the construction of new fossil-fueled plants 10 MW Biomass Based Power Plant ABEIL in India, or displaces consumption of electricity from existing ones, leading to Global Environmental Concerns reduction in greenhouse gas emissions in India. The French investor gets credit for those reductions and can use them to help meet their reduction target in France. 1.9.6 Requirements for Participating in CDM Project Cycle for CDM Global Environmental Concerns While investors profit from CDM projects by obtaining reductions at costs lower than in their own countries, the gains to the developing country host parties are in the form of finance, technology, and sustainable development benefits. Projects starting in the year 2000 are eligible to earn Certified Emission Reductions (CERs) if they lead to "real, measurable, and long-term" GHG reductions, which are additional to any that would occur in the absence of the CDM project. This includes afforestation and reforestation projects, which lead to the sequestration of carbon dioxide. At COP-7, it was decided that the following types of projects would qualify for fast-track approval procedures: - Renewable energy projects with output capacity up to 15 MW - Energy efficiency improvement projects, which reduce energy consumption on the supply and/or demand side by up to 15 GWh annually - Other project activities that both reduce emissions by sources and directly emit less than 15 kilotons CO2 equivalent annually. The CDM will be supervised by an executive board, and a share of the proceeds from project activities will be used to assist developing countries in meeting the costs of adaptation to climate change. Indian Initiatives on CDM Government of India has been willing to fulfill its responsibility under the CDM. It has developed an interim criterion for approval of CDM project activities, which is now available to stakeholders. It has undertaken various capacity building activities like holding of workshops, initiation of various studies, and briefing meeting with the stakeholders. India has been actively participating in the CDM regime and has already approved projects for further development. Under CDM, projects such as energy efficient hydrocarbon refrigerators, modernization of 10 MW Biomass Based Power Plant ABEIL small scale foundry units and renovation, modernization of thermal power stations etc. are being taken up. 1.9.7 Prototype Carbon Fund (PCF) Recognizing that global warming will have the most impact on its borrowing client countries, the World Bank approved the establishment of the Prototype Carbon Fund (PCF). The PCF is intended to invest in projects that will produce high quality greenhouse gas emission educations that could be registered with the United Nations Framework Convention on Climate Change UNFCCC) for the purposes of the Kyoto Protocol. To increase the likelihood that the ductions will be recognized by the Parties to the UNFCCC, independent experts will follow validation, verification and certification procedures that respond to UNFCCC rules as they develop. The PCF will pilot production of emission reductions within the framework of Joint Implementation (JI) and the Clean Development Mechanism (CDM). The PCF will invest contributions made by companies and governments in projects designed to produce emission reductions fully consistent with the Kyoto Protocol and the emerging framework for JI and the CDM. Contributors, or "Participants" in the PCF, will receive a pro rata share of the emission reductions, verified and certified in accordance with agreements reached with the respective countries "hosting" the projects. 1.9.8 Size of Market for Emissions Reductions • All estimates of market volume are speculative at this early stage in the market’s development. • One way of looking at the potential size of the market is to assume that about one billion tonnes of carbon emissions must be reduced per year during the commitment period of 20082012 in order for the industrialized countries to meet their obligations of a 5% reduction in their 1990 levels of emissions. Under Prototype carbon fund programme of the World Bank. Government of India has approved a municipal solid waste energy project for implementation in Chennai, which proposes to use the state of art technology for extracting energy from any solid waste irrespective of the energy content. Many industrial organizations in the private sector have also sought assistance under this fund. 10 MW Biomass Based Power Plant SIGNIFICANCE OF CDM Achieve sustainable development Reduce impact on environment Additional stream of income through sale of emission reductions Contributes for rural development Reduce pollution levels Technology improvement Improves economics of project Helps developed countries to achieve their emission reduction commitments ABEIL 10 MW Biomass Based Power Plant ABEIL 2. DEMAND ANALYSIS AND JUSTIFICATION OF THE PROJECT 2.0 INTRODUCTION It is a well-known fact that electricity is the most essential input for growth and development of any state. Assam is planning to grow rapidly in both the industrial and agricultural sectors and consequently the demand for power is on the rise. However, the growth in installed power generating capacity has not kept pace with the projected demand. 2.1 POWER SECTOR REFORMS IN ASSAM Govt. of Assam decided to reforms its Power Sector with the objective of creating conditions for sustainable development of the Power Sector and improving efficiency and quality of service to the consumers by allowing private participation in the State Power Sector. The Govt. of Assam established Assam Electricity Regulatory Commission (AERC). to regulate the functioning of the Power Sector on sound commercial principles, to safeguard the interests of the Consumers in respect of quality, reliability and fair price for electricity and to set cost and efficiency based tariff to ensure credit worthiness and viability of the Power Sector so as to progressively eliminate tariff distortions and subsidies. The Commission is fully functional and regulating the State Power Sector utilities. Assam state with Dispur as its capital has an area of 78,438 sq. Km and a population of 22.4 million. Administratively it is divided into 23 districts comprising of 87 towns and 28,590 villages (as per 1991 census). The state is predominantly agrarian with 89 percent of the population being rural. About 63% of its population is engaged in agriculture and allied activities, of which tea plantation is the most important. Assam is endowed with rich mineral resources. It has reserves of coal, limestone, petroleum and natural gas. 2.2 Growth of Power Sector Significant growth in Power Sector in the State with the establishment of the State Electricity Board took place. Apart from building up installed capacity of 554 MW as on 31st March 1997 as against 132 MW in 1975, electricity is extended to 19,019 out of 24,685 villages (habitated) covering 77% of villages in the State as on 31st March 1997 as against 10 MW Biomass Based Power Plant ABEIL 190 in 1975. ASEB is serving 9,11,514 consumers as on 30th June, 2001 - up from 7,12,714 consumers as on 31st March 1997 and 1,08,613 in 1975. The per capita consumption in the State over the last two decades is summarized briefly in the table below: Particulars 1975 1996-97 Installed Capacity (MW) 132 554 Energy Available (MU) 556 2,609 Length of HT Lines (ckt km) 5,456 42,615 Length of LT Lines* (ckt km) 8,763 41,872 Substations (33kv & above) (MVA) 678 2,518 Distribution Transformers (MVA) 391 1,657 Towns & Villages electrified (Nos.) 190 21,887 1,08,613 7,12,714 31 104 1975 1996-97 Installed Capacity (MW) 132 554 Energy Available (MU) 556 2,609 5,456 42,615 Number of consumers served Per capita consumption (kWh/person) Particulars Length of HT Lines (ckt km) 2.4 Energy Resources Assam has rich reserves of coal, petroleum and natural gas. The North-eastern region is endowed with about 37% of all India hydroelectric resources. The estimated hydroelectric potential of the region is about 31,857 MW at 60% load factor, out of which 315 MW have already been exploited and 305 MW are under development. Assam being an integral part of the North-Eastern region, it would be the beneficiary of development of hydro potential in the region. 2.4.1 Industry Structure Assam State Electricity Board (ASEB) constituted under the Electricity Act 1948 is responsible for generation, transmission and distribution of electricity in the State. An Electricity Board was constituted in 1958 in the composite state of Assam. The existing Board covers only part of the old State which was trifurcated into Assam, Meghalaya and Mizoram in 1972. 10 MW Biomass Based Power Plant ABEIL North Eastern Electric Power Corporation (NEEPCO), a Government of India Corporation, was established in 1976 for establishing and operating hydro and thermal power plants with transmission network in the North-eastern region supplementing the efforts of the States in power development in the region. Power Grid Corporation of India (PGCIL), a Government of India Corporation, was established in 1989 for planning, construction and operation of central transmission system in the country had taken over the transmission network of NEEPCO in the region. PGCIL has been made responsible for major works in the future in transmission sector. Independent Power Producers (IPP) such as DLF has also started operating since 1997 in the southern part of the State with a total installed capacity of 24.5 MW. LIST OF CAPTIVE POWER PLANTS IN ASSAM. S.No. Company Industry Fuel Capacity Location 1. Hindustan Paper Corp., Jagiroad Paper Coal 2x15 MW Jagiroad, DistNagaon 2. Hindustan Paper Corp., Panchgram Paper Coal 2x15 MW Panchgram, DistCachar 3. Bongaigaon Refinery & Petro Chemicals Ltd. Oil Oil/Gas 3x16 MW Dhaligaon, DistBongaigaon 4. Oil India Ltd. Duliajan Oil Gas 2x15 MW Duliajan, DistTinsukia Moran, DistSibsagar. 2x3 MW 5. Hindustan Fertilizer Corp. Namrup Fertilizer Gas 1x20 MW 1x7 MW 2x1 MW Namrup, DistDibrugarh 6. Indian Oil Corp. Ltd. Guwahati Refinery Oil Oil(RCO) 2x8 MW Noonmati Guwahati. 7. Indian Oil Corp. Ltd. Digboi Refinery Oil Gas/Oil 3x8.5 MW 8. ONGC Ltd. Rudrasagar Oil & Natural Gas Gas 2x3 MW Rudrasagar, DistSibsagar 9. ONGC Ltd. Geleky Oil & Natural Gas Gas 3x3 MW Geleky, DistSibsagar. Digboi, DistTinsukia 10 MW Biomass Based Power Plant ABEIL 10. ONGC Ltd. Lakwa Oil & Natural Gas Gas 3x3 MW Lakwa, DistSibsagar 11. Assam Industrial Dev. Corp. Sack craft Project Paper Coal 1x5 MW (closed) Dhing, Dist, Nagaon 12. M/s. Prag Bosimi Synthetics Ltd. Sipajhar Polyester Fibre Diesel 2x1.6 MW 4x2.7 MW Sipajhar, DistDarrang 13. Ashok Paper Mills, Jogighopa, Paper Diesel 1x8.3 MW not under operation Jogighopa, DistBongaigaon 14. CCI, Bokajan Cement Diesel 1x4 MW 15. Numaligarh Refinery Ltd. Golaghat Oil Gas Diesel 2x34 MW 1x1.17 MVA Numaligarh, DistJorhat. 16. Gas Authority of India Ltd. Lakwa Gas Gas Diesel 2x3.125 MW 2x0.2 MW Lakwa, DistSibsagar 17. IOC (AOD) Digboi Oil Gas 1x20 MW Bokajan, DistKarbi Anglong Digboi 2.5 The Current Power Scenario in Assam 2.5.1 Installed Capacity The installed capacity in the State as on 31st March 2002 is 574.4 MW. In addition to its own installed capacity, the State has a share of 288 MW from Central Sector Generating Stations owned by NEEPCO and NHPC. Besides this, the State has also 24.5 MW of private power (IPP) generation. The total capacity thus available for the State is 886.9 MW. The details of installed capacity are given below: Type of Generation Hydro Coal Capacity in MW 2.0 240.0 Oil 60.0 Gas 274.4 State's Installed Capacity: 574.4 Private Sector 24.5 Import from Other Sectors 288.0 Total Availability: 886.9 10 MW Biomass Based Power Plant ABEIL In addition, the State has captive generating capacity of 451 MW of which 207 MW with refineries, Oil India, ONGCL and paper mills etc. and 244 MW with tea gardens and other industries. The station wise details of ASEB's installed capacity are given below: Sl No. Station Capacity (MW) 1 Bongaigaon Thermal (coal fired) 240.0 2 Chandrapur Thermal (oil fired) 3 Lakwa Thermal (gas fired) 120.0 4 Namrup Thermal (gas fired) 133.5 5 Mobile (gas fired) 6 Hydro 60.0 18.9 2.0 2.5.2 Generation, Purchase and Sales ASEB has generated 868.54 MU (excluding auxiliary consumption) during 2000-2001 and purchased 2292.77 MU from Central Sector, Meghalaya, IPP and Eastern region. This includes 135.33 MU free power from NEEPCO hydro generation. The total energy thus available for sale was 3161.31 MU. 2.5.3 Power supply position in the State The peak demand and energy requirement met during 2000-2001 is 580.0 MW and 8.0 MU (per day) respectively. But at this level of supply both peak and energy was short of the real demand. The unrestricted peak demand and energy requirement are assessed at 600 MW and 9.0 MU (per day) respectively. The unrestricted peak demand and energy requirement have to be studied further. 2.5.4 Consumer Profile and Energy Sales. ASEB serves 9.11 Lakh consumers as on 2001-2002 with toal connected load of 1,650 MW. The rural domestic and commercial consumers numbering 1.5 Lakh (16.5% of total number of consumers) are not metered. However, all the services released from 1992 are metered. The State has about 2009 irrigation pumpsets. The Irrigation Deptt. operates most of these pumpsets and the consumption is metered. 10 MW Biomass Based Power Plant ABEIL GENERATION Assam State Electricty Board has four major Thermal Generating Stations. Installed Capacity STATION BTPS CTPS LTPS NTPS MOBILE CAPACITY 240.0 60.0 120.0 133.5 18.9 HYDRO 2.0 Unit-wise details are: BTPS: 4 x 60 MW Coal fired Steam Turbine. CTPS: 2 x 30 MW Oil fired Steam Turbine. LTPS: 4 x 15 MW + 3 x 20 MW Gas Turbine. NTPS: 3 x 23 MW + 1 x 12.5 MW Gas Turbine + 1 x 30 MW Gas fired Steam Turbine + 1 x 22 MW Waste Heat Recovery Unit. Mobile: 3 x 2.7 + 4 x 2.7 MW Hydro: 2.0 MW Total generating capacity: 574.4 MW Type of Installed Capacity Type of Generation Hydro Coal MW 2.0 240.0 Oil 60.0 Gas 274.4 State's Installed Capacity: 574.4 2.6 Rural Electrification ASEB had started the Rural Electrification (RE) programme in 1966-67 with a Cell headed by an Executive Engineer under Chief Engineer (Electrical). To cope up with tempo of RE works, the Cell was upgraded at various stages, to the Circle, Zone & Wing level being headed by Superintending Engineer, Additional Chief Engineer & Chief Engineer respectively. However, during slack period the Wing was put under ACE on a few occasions. At present RE Wing is headed by Chief Engineer and entrusted with preparation of schemes, monitoring progress of RE works which are being carried out by respective O&M Divisions under Chief Engineer (Distribution). 10 MW Biomass Based Power Plant ABEIL 2.6.1 Status of Electrification: ASEB has electrified 19,019 villages under various RE schemes, 5,666 nos of villages are yet to be electrified (List of unelectrified villages). Most of the schemes were financed by REC Ltd. on long term loan amounting to Rs. 329.84 Crore. A few schemes were also taken under State Plan. District-wise status of electrified villages are given as below: District-wise number of Electrified Census villages as per 1991 census Sl No Name of District Total populated village No of villages electrified up to 31.03.01 No of villages to be electrified 745 706 39 1,284 1,057 227 1 Goalpara 2 Dhubri 3 Kokrajhar 923 839 84 4 Bongaigaon 858 816 42 5 Darang 1,328 1,218 110 6 Sonitpur 1,691 1,426 265 7 Barpeta 1,046 948 98 8 Nalbari 803 800 3 9 Kamrup 1,300 1,234 66 10 Nagaon 1,379 1,249 126 11 Marigaon 569 432 137 12 Sibsagar 873 817 56 13 Golaghat 1,059 658 481 14 Jorhat 798 614 184 15 Lakhimpur 1,140 854 286 16 Dhemaji 1,110 342 768 17 Cachar 1,024 923 101 18 Hailakandi 327 290 37 19 Karimganj 893 535 358 20 Dibrugarh 1,306 1,136 170 21 Tinsukia 1,136 825 311 22 Karbi Anglong 2,520 1,039 1,481 23 N. C. Hills 577 261 316 -- Total 24,685 19,019 5,666 10 MW Biomass Based Power Plant ABEIL Government of India has also envisages the use of Non-Conventional sources of energy for electrification of remote villages where Grid power cannot be extended economically. In the first phase about 300 remote villages in Assam have been proposed to be electrified with NonConventional sources of energy viz. Photo Voltaic Cell, Micro Hydro and BioMass. 2.7 Brief Note on Tariff Petitions for FY 06-07 Assam State Electricity Board (ASEB) and its five successor entities submitted petition for Annual Revenue Requirements (ARR) for FY2006-2007 along with tariff revision proposals to meet the additional revenue requirements before the Hon’ble Assam Electricity Regulatory Commission (AERC) as per provisions of The Electricity act 2003. As per the provisions of Assam Electricity Reform First Transfer Scheme 2004, notified by the State Government as per the provision of The Electricity Act, the ASEB is now carrying out the function of bulk purchaser and bulk supplier. Accordingly ASEB has filed petition before the Commission for Bulk Supply Tariff applicable for distribution companies. ASEB had projected an expenditure ofRs.717.27 crores in its ARR filings for 2006-07 for the purchase of 3809.48 MU to meet the requirements of DISCOM sales of 2354.98 MU and trading sales of 140 MU.Against this, the Commission has approved a quantum o 4098.36MU to meet the requirement of DISCOM sales of 2417.63 MU and trading sales.The DISCOM sales of 2417.63MU exclude the distribution losses amounting to 910.38 MU which averages to 27.36%. It has been estimated that in 2006-07 there will be a deficit of 221 MU even after the purchases of ASEB(cited above) for which power has to be purchased from Traders at an average rate of Rs.3.57 per unit.A schedule of this deficit is given below in tabular form. 10 MW Biomass Based Power Plant ABEIL Schedule of Energy Deficit in ASEB during the year 2006-07 (All figures in million units) Availability of supply with ASEB ASEB requirement Excess Energy available for Export Energy Deficit for which import is reqd. 2.8 April May June July Aug Sept Oct Nov Dec Jan Feb Mar 252 291 296 377 398 300 315 255 281 279 263 281 3588 275 285 310 6 23 13 326 323 51 75 348 333 325 316 284 273 273 3670 8 47 18 70 36 5 10 NEED FOR THE PROJECT The deficit in the installed capacity as well as in the energy availability as discussed in the previous paragraphs is likely to increase in future unless corrective measures are planned right now. This provides ample justification for the installation of 11 MW power plant at Jagi Road in Mayong Circle of Marigaon district in Assam. After considering around one MW for internal consumption(auxiliaries etc), a net quantum of 10 MW will be injected to the ASEB grid. This power plant is environmental friendly and can be claimed for carbon credit. 140 221 10 MW Biomass Based Power Plant ABEIL 3. BIOMASS POTENTIAL 3.0 INTRODUCTION Amrit Bio Energy and Industries Limited has planned to set up a 11 MW independent biomass based power plant with rice husk as fuel at Jagi Road in Mayong circle of Morigaon district in Assam. This power plant is consisting of one traveling grate boiler of 50 TPH capacity operating at 67 bar and 4850C, one extraction cum condensing turbine of 11 MW capacity. Biomass assessment was carried out in full Kamrup and Morigaon district. For study, blocks falling in Kamrup and Morigaon district are considered. It is planned to have a Plant capacity utilization of 90% from the first year itself. This Plant Load Factor will include the annual maintenance and any unscheduled stoppages due to machine breakdown or non availability of fuel . The plant will thus be operating for 328.5 days. Rice husk requirement for this plant on the basis of above will be 108405 MT.The internal consumption of the plant (auxiliaries etc) is expected to be around 1 MW and the balance 10 MW of power will be sold to ASEB. 3.1 BLOCKS IN KAMRUP & MORIGAON DISTRICT Kamrup District Morigaon District Sualkuchi Mayong Hajo Moriabari Goroimari Laharighat Chhaygaon Bhurbandha Chandrapur Kapili Dimoria Chayani Barduar Boko Bongaon Chamaria Rani Rampur Bezera 10 MW Biomass Based Power Plant Kamrup District ABEIL Morigaon District Kamalpur Rangia Goreswar Bihdia Jajikona 3.1 DISTRICT PROFILE KAMRUP DISTRICT Kamrup District is the Capital District of Assam. It is situated between 25.43° and 26.51° North Latitude and between 90.36° and 92.12° East Longitude. The greater part of the district consists of wide plains, through the lower portion of which the mighty river Brahmaputra makes its way, flowing a steady course from east to west. MORIGAON DISTRICT Morigaon is basically an agrarian district. The District is situated in the Brahmaputra Valley Zone of the Assam. It lies between 26.15° to 26.5° North latitude and 92° to 95.5° east longitude. Morigaon district is the second smallest district of Assam 3.1.1 Soils The main soils in the district are Alluvial soil. The soils in general are fertile in nature. The District is richly endowed with natural and human resources and offer excellent scope for development of agriculture and allied industries. 3.1.2 Climate and Rainfall The average temperature is moderate, about 84 degrees F (29 degrees C) in the hottest month of August. The average valley temperature in January is 61 degrees F (16 degrees C). In this season, heavy fogs and a little rain mark the climate of the valley. Assam does not have the normal Indian hot, dry season. Some rain occurs from March onwards, but the real force of the monsoon winds is faced from June onward. Rainfall in Assam ranks among the highest in the world; its annual rainfall varies from 70 inches in the west to 120 inches per year in the east. Large concentrated during the months from June to 10 MW Biomass Based Power Plant ABEIL September; it often results in widespread destructive floods. Much of the state is covered with dense tropical forests of bamboo and, at higher elevations, evergreens. Common animals of Assam include the elephant, tiger, leopard, rhinoceros, and bear. KAMRUP DISTRICT This district generally experiences Sub tropical with semi -dry summer & cold in winter extreme conditions. The maximum and minimum temperature in the district is around 38.5° C and 7° C. The annual rainfall in the district ranges between 1500 mm to 2600 mm. MORIGAON DISTRICT The average annual rainfall is 1597.48 mm. The maximum temperature is felt during JuneJuly while the minimum during January. 3.1.3 Demographic Particulars KAMRUP DISTRICT As per 2001 census, there are 1342 inhabited villages in the district. This district has a total population of 2522324 as of 2001 Census. The literacy percentage of the district is 74.16 %. This district is having urban population of 908217 & rural population of 1614107 respectively. The total Male population is 1326981 and female population is 1195343. This district is having population density of 581 sq. kms, with sex ratio of 901 for 1000 males. MORIGAON DISTRICT As per 2001 census, there are 592 inhabited villages in the district. This district has a total population of 776256 as of 2001 Census. The literacy percentage of the district is 58.53 %. This district is having urban population of 37988 & rural population of 738268 respectively. The total Male population is 398926 and female population is 377330. This district is having population density of 456 sq. kms, with sex ratio of 946 for 1000 males. 3.1.4 Agriculture 10 MW Biomass Based Power Plant ABEIL 3.1.4.1 Land Classification The classification of geographical area under different categories of land utilised is stated in the table below: 3.2 Land Classification (Area in Hectares) Particulars Kamrup Morigaon TOTAL Geographical Area 446402 158765 605167 Forest 116694 17626 134320 Land put to non- agricultural uses 77246 20198 97444 Barren and unculturable land 20296 5120 25416 Permanent Pastures & other grazing land 21236 8331 29567 Land under misc. tress groves 25409 4489 29898 Culturable waste land 4573 690 5263 Fallow & current fallow 12428 939 13367 Net sown area 92680 101372 194052 (Source: Statistical book of Assam) It can be observed from the table above, a relatively large area (97444 ha) is not available for agriculture, while area (134320 ha) is designated as forest in the district. Only about 84881ha land is classified as barren and uncultivable land, permanent pastures and other misc. trees. 3.1.4.3 Cropping Pattern: The main crops grown in the district are Wheat, Paddy, Jute, Mustard etc. 3.3 Cropping pattern (Area in Ha) Season 2004-05 2003-04 2002-03 2001-02 2000-01 Kamrup District Kharif 110047 105798 105339 105011 104119 Rabi 105071 102754 101706 102600 101323 Total 215118 208552 207045 207611 205442 Morigaon District Kharif 35202 34585 34013 34530 33826 Rabi 66611 66083 65419 65623 65923 Total 101813 100668 99432 100153 99749 Grand Total 316931 309220 306477 307764 305191 10 MW Biomass Based Power Plant ABEIL 3.4 Cropped Area Kharif & Rabi Seasons (Area in Ha) Crop Name 2004-05 2003-04 2002-03 2001-02 2000-01 KAMRUP DISTRICT Kharif Sualkuchi Paddy 4498 4424 4449 4432 4426 Maize 13 10 20 11 30 Arhar 13 13 16 14 16 Sugarcane 91 90 100 64 100 576 518 522 524 466 Castor 5 6 4 6 4 Ground Nut 7 6 4 4 6 515 524 465 518 418 Paddy 14264 13864 13850 13871 13876 Maize 30 26 18 28 24 Arhar 20 24 20 20 18 Sugarcane 42 43 28 44 28 700 614 612 612 614 Castor 4 0 0 0 0 Ground Nut 0 0 0 0 0 877 866 818 814 820 Paddy 2865 2880 2880 2887 2866 Maize 30 23 16 26 10 Arhar 80 84 88 88 66 Sugarcane 43 42 44 24 42 220 224 218 218 224 Castor 0 0 0 0 0 Ground Nut 0 0 0 0 0 Other Pulses 38 44 66 43 64 2850 2726 2706 2733 2720 Jute Other Pulses Hajo Jute Other Pulses Goroimari Jute Chhaygaon Paddy 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Maize 110 110 98 115 101 Arhar 10 10 4 6 0 Sugarcane 35 36 60 38 36 Jute 75 78 66 79 60 Castor 0 0 0 0 0 Ground Nut 5 5 0 0 0 165 174 132 124 144 Paddy 1188 1165 1121 1170 1102 Maize 0 6 4 4 6 Arhar 0 4 6 6 4 Sugarcane 2 6 4 4 4 Jute 2 14 24 19 25 Castor 0 0 0 0 0 Ground Nut 0 0 2 6 0 Other Pulses 30 24 22 25 30 Paddy 4300 4303 4308 4308 4246 Maize 5 18 24 20 28 Arhar 50 50 53 48 52 Sugarcane 20 25 20 24 54 100 96 100 94 100 2 2 0 4 0 Ground Nut 27 14 10 14 0 Other Pulses 200 184 164 188 124 Paddy 1732 1602 1542 1610 1542 Maize 9 24 24 25 28 Arhar 10 10 24 10 18 Sugarcane 92 94 68 84 72 679 681 694 618 624 Castor 0 0 0 0 0 Ground Nut 0 0 0 0 0 Other Pulses Chandrapur Dimoria Jute Castor Chayani Barduar Jute 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 213 216 210 212 218 Paddy 4604 4536 4549 4557 4536 Maize 225 184 178 188 166 Arhar 55 56 84 52 52 Sugarcane 450 418 416 398 244 Jute 330 318 368 324 366 Castor 550 485 418 386 618 Ground Nut 170 136 0 144 0 Other Pulses 635 624 624 618 618 Paddy 2738 2676 2694 2692 2690 Maize 45 36 24 38 29 Arhar 35 24 20 18 18 Sugarcane 50 54 52 64 52 Jute 360 324 320 318 318 Castor 112 110 100 114 66 0 0 128 0 100 114 115 109 96 110 Paddy 15646 12846 12878 12856 12850 Maize 2 4 6 4 6 Arhar 578 518 521 524 518 79 64 54 84 84 1753 1724 1718 1801 1724 Castor 2 2 4 4 0 Ground Nut 2 0 0 0 0 638 624 610 618 624 Paddy 4200 4276 4242 4282 4290 Maize 0 16 18 18 16 Arhar 240 216 276 6 281 Sugarcane 360 316 300 384 278 Other Pulses Boko Bongaon Ground Nut Other Pulses Chamaria Sugarcane Jute Other Pulses Rani 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Jute 500 561 518 484 529 Castor 140 121 118 111 168 Ground Nut 410 384 274 285 124 Other Pulses 200 196 124 184 110 Paddy 2006 2086 2078 2087 2061 Maize 10 24 28 26 24 Arhar 10 24 18 20 6 Sugarcane 111 98 66 121 110 Jute 239 134 146 125 145 Castor 1 2 6 4 6 Ground Nut 0 0 0 19 0 226 218 210 224 188 Paddy 3216 3161 3208 3106 3135 Maize 6 4 4 4 4 Arhar 12 14 14 16 10 Sugarcane 21 20 78 22 38 Jute 25 16 28 34 24 4 2 0 0 0 Ground Nut 50 48 50 42 41 Other Pulses 250 264 288 216 262 Paddy 1330 1359 1284 1358 1327 Maize 2 2 4 0 0 Arhar 2 0 6 0 4 Sugarcane 9 0 20 12 18 Jute 5 5 6 0 6 Castor 0 0 0 0 0 Ground Nut 12 16 6 6 4 Other Pulses 211 178 194 178 176 13540 13574 13549 13406 13336 Rampur Other Pulses Bezera Castor Kamalpur Rangia Paddy 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Maize 303 222 324 284 218 Arhar 14 0 10 12 19 Sugarcane 68 66 16 63 64 Jute 29 24 34 24 33 Castor 0 0 0 0 0 Ground Nut 0 0 0 28 20 338 324 324 316 324 Paddy 11265 11229 11333 11306 11238 Maize 24 18 16 18 6 Arhar 29 34 24 18 25 Sugarcane 161 144 121 138 24 Jute 547 524 484 366 318 0 0 0 0 0 Ground Nut 29 34 24 18 20 Other Pulses 103 112 111 98 112 Paddy 2789 2858 2810 2870 2808 Maize 7 6 6 6 6 Arhar 18 6 6 4 16 Sugarcane 98 100 96 100 94 126 133 122 111 96 6 1 0 0 0 Ground Nut 25 24 18 6 0 Other Pulses 705 724 696 711 712 Kharif Total 110047 105798 105339 105011 104119 Paddy 4206 4316 4424 4324 4428 Wheat 679 684 618 685 624 Gram 14 18 24 21 20 Seasumum 54 62 64 56 66 Linseed 48 44 48 68 66 Other Pulses Goreswar Castor Bihdia Jajikona Jute Castor Rabi Sualkuchi 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 503 524 516 505 418 5 6 4 6 6 742 718 721 724 718 Paddy 5526 5418 5424 5420 5426 Wheat 670 618 624 621 628 Gram 22 20 18 22 10 177 170 138 179 166 Linseed 81 88 66 78 88 Mustard 721 524 710 718 716 0 0 2 6 2 405 444 418 414 424 Paddy 4370 4416 4524 4420 4518 Wheat 355 324 316 327 316 Gram 15 16 16 18 10 Seasumum 30 34 30 40 28 Linseed 81 24 22 40 24 Mustard 127 120 118 124 124 0 0 0 0 0 290 224 216 228 216 Paddy 4197 4124 4135 4125 4128 Wheat 210 210 208 214 210 Gram 10 10 10 13 10 6 2 6 6 6 Linseed 55 56 28 56 52 Mustard 90 94 98 98 68 Other Oilseeds 75 78 66 84 73 450 418 481 424 478 Paddy 1100 1124 1126 1128 1196 Wheat 30 36 24 38 34 Mustard Other Oilseeds Vegetables Hajo Seasumum Other Oilseeds Vegetables Goroimari Other Oilseeds Vegetables Chhaygaon Seasumum Vegetables Chandrapur 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Gram 0 6 4 6 2 Seasumum 0 0 0 0 6 Linseed 10 6 4 15 10 Mustard 30 32 18 24 24 2 4 4 6 4 200 200 184 202 180 Paddy 4667 4614 4630 4624 4587 Wheat 122 118 120 120 118 Gram 50 44 24 42 22 Seasumum 50 44 42 52 54 Linseed 5 5 0 6 6 Mustard 105 113 110 115 110 25 26 20 28 26 1200 1200 1212 1211 1210 Paddy 4823 4618 4624 4620 4416 Wheat 181 196 184 199 186 Gram 19 20 20 18 18 Seasumum 32 34 30 24 24 Linseed 0 2 0 6 2 Mustard 179 184 188 188 168 49 52 64 56 10 200 224 218 218 210 Paddy 5369 5218 5220 5220 5210 Wheat 198 118 108 120 100 Gram 75 72 84 64 84 Seasumum 250 218 216 265 188 Linseed 215 198 116 187 214 Mustard 475 418 420 416 418 Other Oilseeds 252 216 218 284 184 Vegetables 542 518 521 524 510 Other Oilseeds Vegetables Dimoria Other Oilseeds Vegetables Chayani Barduar Other Oilseeds Vegetables Boko 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Paddy 3594 3524 3225 3520 3445 Wheat 145 144 118 145 111 Gram 41 40 20 38 18 Seasumum 33 36 24 35 64 Linseed 15 6 4 18 10 Mustard 395 384 385 324 324 2 4 6 6 6 285 216 210 216 208 Paddy 3851 3864 3818 3865 3824 Wheat 1301 1286 1210 1288 1224 40 40 18 36 18 Seasumum 228 218 210 218 216 Linseed 135 198 112 135 124 Mustard 1149 418 1160 1155 1155 61 216 67 73 46 205 212 210 212 416 Paddy 3799 3618 3624 3624 3624 Wheat 510 466 416 467 415 0 0 6 6 6 Seasumum 100 94 68 100 64 Linseed 390 384 318 224 309 Mustard 570 524 548 534 524 Other Oilseeds 498 418 410 484 365 Vegetables 485 466 418 418 416 Paddy 3389 3465 3218 3466 3228 Wheat 160 145 125 147 125 Gram 11 12 24 10 16 Seasumum 34 28 18 24 24 0 6 6 6 6 Bongaon Other Oilseeds Vegetables Chamaria Gram Other Oilseeds Vegetables Rani Gram Rampur Linseed 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 164 162 160 168 162 41 24 20 31 24 243 218 231 224 224 Paddy 4418 4424 4424 4416 4400 Wheat 193 148 128 144 132 4 6 6 4 6 150 132 122 146 138 Linseed 8 6 0 6 6 Mustard 76 64 66 84 78 Other Oilseeds 23 24 28 24 18 219 200 224 218 202 Paddy 4331 4418 4421 4516 4321 Wheat 64 64 77 64 62 Gram 24 18 14 24 25 Seasumum 24 20 18 22 18 Linseed 40 36 24 36 24 Mustard 77 65 36 32 24 Other Oilseeds 10 10 10 12 24 206 200 200 194 182 Paddy 7750 7721 7624 7318 7724 Wheat 502 518 514 534 524 Gram 121 118 96 88 66 38 44 44 36 40 Linseed 0 0 0 6 6 Mustard 771 716 684 664 597 0 0 6 6 6 1339 1324 1224 1284 1214 Paddy 5691 5684 5518 5425 5324 Wheat 175 164 184 186 184 Mustard Other Oilseeds Vegetables Bezera Gram Seasumum Vegetables Kamalpur Vegetables Rangia Seasumum Other Oilseeds Vegetables Goreswar 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Gram 20 16 18 24 25 Seasumum 67 66 34 62 38 Linseed 122 110 96 112 96 Mustard 1095 1066 906 1044 1018 30 24 33 24 18 265 248 218 224 216 Paddy 9795 9729 9618 9624 9618 Wheat 79 66 88 80 78 Gram 5 6 8 6 4 Seasumum 68 68 66 54 24 Linseed 75 62 64 64 88 Mustard 308 311 288 224 184 56 46 24 46 34 Vegetables 289 294 300 216 198 Rabi Total 105071 102754 101706 102600 101323 Kamrup Total 215118 208552 207045 207611 205442 Other Oilseeds Vegetables Bihdia Jajikona Other Oilseeds MORIGAON DISTRICT Kharif Mayong Paddy 11689 11647 11582 11674 11526 Maize 55 50 50 28 38 Arhar 5 6 0 6 4 Sugarcane 115 96 98 100 96 Jute 520 544 518 518 464 10 4 0 0 0 Ground Nut 0 0 4 6 4 Other Pulses 13 18 18 14 24 Paddy 1478 1512 1497 1442 1472 Maize 0 0 0 0 0 Arhar 5 0 0 5 0 685 485 618 598 514 Castor Moriabari Sugarcane 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 434 444 388 316 325 0 0 0 0 0 Ground Nut 15 64 48 13 6 Other Pulses 50 24 16 64 78 Paddy 8822 8724 8614 8818 8650 Maize 0 0 0 0 0 Arhar 0 0 2 4 0 194 200 200 196 145 3000 2818 2624 2896 2946 0 0 0 0 0 Ground Nut 160 85 6 132 124 Other Pulses 102 98 96 98 64 Paddy 2412 2502 2294 2399 2404 Maize 0 0 0 0 0 Arhar 10 4 0 5 0 Sugarcane 200 200 184 184 155 Jute 847 844 818 864 818 Castor 0 0 0 0 0 Ground Nut 0 0 6 4 6 Other Pulses 62 64 96 66 65 Paddy 1564 1558 1700 1542 1534 Maize 0 0 0 0 0 Arhar 0 0 0 0 0 46 66 18 38 26 2385 2214 2224 2216 2114 Castor 0 0 0 0 0 Ground Nut 0 0 6 0 0 Other Pulses 324 314 288 284 224 Kharif Total 35202 34585 34013 34530 33826 Jute Castor Laharighat Sugarcane Jute Castor Bhurbandha Kapili Sugarcane Jute Rabi 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Paddy 19405 19412 19212 19345 19228 Wheat 375 384 285 301 288 Gram 14 18 24 19 24 Seasumum 245 188 214 194 218 Linseed 110 96 96 64 96 Mustard 746 718 718 668 718 Other Oilseeds 430 287 218 221 384 Vegetables 880 864 824 756 886 Paddy 9830 9824 9624 9824 9818 Wheat 382 288 265 214 196 0 0 0 5 6 Seasumum 78 66 68 76 64 Linseed 75 64 78 64 78 Mustard 261 212 244 255 244 0 6 4 6 4 94 98 96 64 95 Paddy 13002 13024 13125 13000 13096 Wheat 351 364 384 324 318 Gram 100 85 86 88 74 Seasumum 180 196 144 132 198 Linseed 72 72 74 78 74 Mustard 331 324 324 318 324 46 46 84 18 64 300 218 210 288 304 Paddy 13822 13816 13616 13814 13800 Wheat 194 165 200 144 164 0 0 0 0 0 379 410 318 404 384 95 94 98 78 92 Mayong Moriabari Gram Other Oilseeds Vegetables Laharighat Other Oilseeds Vegetables Bhurbandha Gram Seasumum Linseed 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 578 516 566 578 518 0 0 0 0 0 95 84 86 100 65 Paddy 3037 3024 3038 3024 3014 Wheat 104 98 78 105 96 0 0 0 2 12 38 24 64 88 44 Linseed 0 6 16 18 4 Mustard 817 864 812 810 796 0 0 0 0 0 Vegetables 145 128 126 136 135 Rabi Total 66611 66083 65419 65623 65923 Morigaon Total 101813 100668 99432 100153 99749 Grand Total 316931 309220 306477 307764 305191 Mustard Other Oilseeds Vegetables Kapili Gram Seasumum Other Oilseeds 3.1.5 Livestock Population The livestock population of Kamrup and Morigaon districts is given in table below: 3.5 Livestock Population details Particulars Cattle Kamrup Morigaon 610748 146951 13167 4729 Goats 241659 63952 Pigs 164919 8544 Poultry 1465574 357188 Total 2496067 581364 Buffaloes (Source: Statistics deptt, Assamand Animal Husbandry Department,) 3.1.6 Industries 3.1.6.1 Rice Mills: 10 MW Biomass Based Power Plant ABEIL There are around 5 Rice mills in the Kamrup district and 3 rice mills in Morigaon district as per rice mill association, but as per survey it is revealed that there are more no. of small capacity hullers in Kamrup and Morigaon district. The rice mills are milling the paddy coming from the district and nearby area. The rice mills are generating rice husk and rice bran. S.N. Name of Rice Mill Kamrup 1 Sharma Rice Mill 2 Sri Laxmi Rice Mill 3 Sagar Rice Mill 4 Surana Industries 5 Dhaemashwari Rice Mill Morigaon 1 Anand Rice Mill 2 Manhat Rice Mill 3 Sunil Rice Mill 3.1.6.2 Saw Mills: There are around 47 Sawmills in the Kamrup district and 13 sawmills in Morigaon district. These sawmills are getting wood from the near by villages. The main species are Babool, seasum, khejedi etc. The saw mills are generating wood chips and saw dust. 3.2 BIOMASS POWER PLANT LOCATION DETAILS Biomass assessment was carried out in full Kamrup and Morigaon district. For study, blocks falling in Kamrup and Morigaon districts are considered. 3.2.1 Demographic Features Circle wise population, households for Kamrup and Morigaon districts are given below. 3.6 Demographic Features Circle Name Household Kamrup District Population 10 MW Biomass Based Power Plant Circle Name ABEIL Household Population Goreswar 30770 172576 Rangia 32205 180976 Kamalpur 26900 152720 Hajo 38796 224381 Chhaygaon 36463 209740 Chamaria 16147 99919 Nagarbera 10743 61514 Boko 18628 99935 Palasbari 49963 266926 Guwahati 184454 809895 12417 65813 3067 16140 23049 124043 7138 37746 North Guwahati Dispur Sonapur Chandrapur Morigaon District Mayong 34752 203641 Bhuragaon 16556 106140 Laharighat 29742 183420 Marigaon 30762 164835 Mikirbheta 21646 118220 Mayong 34752 203641 Bhuragaon 16556 106140 Chandgad 34907 180781 (Source: As per 2001 census) 10 MW Biomass Based Power Plant 3.2.2 ABEIL Cropping Pattern: The season wise & crop wise cropping pattern for five years for the blocks covered within the Kamrup and Morigaon district are given below. 3.2.3 Block wise Cropping pattern in hectares The main crops grown in the districts are Wheat, Paddy, Jute, Mustard etc. 3.7 Cropping pattern (Area in Ha) Season 2004-05 2003-04 2002-03 2001-02 2000-01 Kamrup District Kharif 110047 105798 105339 105011 104119 Rabi 105071 102754 101706 102600 101323 Total 215118 208552 207045 207611 205442 Morigaon District Kharif 35202 34585 34013 34530 33826 Rabi 66611 66083 65419 65623 65923 Total 101813 100668 99432 100153 99749 Grand Total 316931 309220 306477 307764 305191 3.8 Cropped Area Kharif & Rabi Seasons (Area in Ha) Crop Name 2004-05 2003-04 2002-03 2001-02 2000-01 Kamrup District Kharif Sualkuchi Paddy 4498 4424 4449 4432 4426 Maize 13 10 20 11 30 Arhar 13 13 16 14 16 Sugarcane 91 90 100 64 100 576 518 522 524 466 Castor 5 6 4 6 4 Ground Nut 7 6 4 4 6 515 524 465 518 418 Jute Other Pulses 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Paddy 14264 13864 13850 13871 13876 Maize 30 26 18 28 24 Arhar 20 24 20 20 18 Sugarcane 42 43 28 44 28 700 614 612 612 614 Castor 4 0 0 0 0 Ground Nut 0 0 0 0 0 877 866 818 814 820 Paddy 2865 2880 2880 2887 2866 Maize 30 23 16 26 10 Arhar 80 84 88 88 66 Sugarcane 43 42 44 24 42 220 224 218 218 224 Castor 0 0 0 0 0 Ground Nut 0 0 0 0 0 Other Pulses 38 44 66 43 64 Paddy 2850 2726 2706 2733 2720 Maize 110 110 98 115 101 Arhar 10 10 4 6 0 Sugarcane 35 36 60 38 36 Jute 75 78 66 79 60 Castor 0 0 0 0 0 Ground Nut 5 5 0 0 0 165 174 132 124 144 Paddy 1188 1165 1121 1170 1102 Maize 0 6 4 4 6 Arhar 0 4 6 6 4 Sugarcane 2 6 4 4 4 Jute 2 14 24 19 25 Hajo Jute Other Pulses Goroimari Jute Chhaygaon Other Pulses Chandrapur 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Castor 0 0 0 0 0 Ground Nut 0 0 2 6 0 Other Pulses 30 24 22 25 30 Paddy 4300 4303 4308 4308 4246 Maize 5 18 24 20 28 Arhar 50 50 53 48 52 Sugarcane 20 25 20 24 54 100 96 100 94 100 2 2 0 4 0 Ground Nut 27 14 10 14 0 Other Pulses 200 184 164 188 124 Paddy 1732 1602 1542 1610 1542 Maize 9 24 24 25 28 Arhar 10 10 24 10 18 Sugarcane 92 94 68 84 72 679 681 694 618 624 Castor 0 0 0 0 0 Ground Nut 0 0 0 0 0 213 216 210 212 218 Paddy 4604 4536 4549 4557 4536 Maize 225 184 178 188 166 Arhar 55 56 84 52 52 Sugarcane 450 418 416 398 244 Jute 330 318 368 324 366 Castor 550 485 418 386 618 Ground Nut 170 136 0 144 0 Other Pulses 635 624 624 618 618 Paddy 2738 2676 2694 2692 2690 Maize 45 36 24 38 29 Dimoria Jute Castor Chayani Barduar Jute Other Pulses Boko Bongaon 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Arhar 35 24 20 18 18 Sugarcane 50 54 52 64 52 Jute 360 324 320 318 318 Castor 112 110 100 114 66 0 0 128 0 100 114 115 109 96 110 Paddy 15646 12846 12878 12856 12850 Maize 2 4 6 4 6 Arhar 578 518 521 524 518 79 64 54 84 84 1753 1724 1718 1801 1724 Castor 2 2 4 4 0 Ground Nut 2 0 0 0 0 638 624 610 618 624 Paddy 4200 4276 4242 4282 4290 Maize 0 16 18 18 16 Arhar 240 216 276 6 281 Sugarcane 360 316 300 384 278 Jute 500 561 518 484 529 Castor 140 121 118 111 168 Ground Nut 410 384 274 285 124 Other Pulses 200 196 124 184 110 Paddy 2006 2086 2078 2087 2061 Maize 10 24 28 26 24 Arhar 10 24 18 20 6 Sugarcane 111 98 66 121 110 Jute 239 134 146 125 145 Castor 1 2 6 4 6 Ground Nut 0 0 0 19 0 226 218 210 224 188 Ground Nut Other Pulses Chamaria Sugarcane Jute Other Pulses Rani Rampur Other Pulses 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Paddy 3216 3161 3208 3106 3135 Maize 6 4 4 4 4 Arhar 12 14 14 16 10 Sugarcane 21 20 78 22 38 Jute 25 16 28 34 24 4 2 0 0 0 Ground Nut 50 48 50 42 41 Other Pulses 250 264 288 216 262 Paddy 1330 1359 1284 1358 1327 Maize 2 2 4 0 0 Arhar 2 0 6 0 4 Sugarcane 9 0 20 12 18 Jute 5 5 6 0 6 Castor 0 0 0 0 0 Ground Nut 12 16 6 6 4 Other Pulses 211 178 194 178 176 Paddy 13540 13574 13549 13406 13336 Maize 303 222 324 284 218 Arhar 14 0 10 12 19 Sugarcane 68 66 16 63 64 Jute 29 24 34 24 33 Castor 0 0 0 0 0 Ground Nut 0 0 0 28 20 338 324 324 316 324 Paddy 11265 11229 11333 11306 11238 Maize 24 18 16 18 6 Arhar 29 34 24 18 25 Sugarcane 161 144 121 138 24 Jute 547 524 484 366 318 Bezera Castor Kamalpur Rangia Other Pulses Goreswar 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 0 0 0 0 0 Ground Nut 29 34 24 18 20 Other Pulses 103 112 111 98 112 Paddy 2789 2858 2810 2870 2808 Maize 7 6 6 6 6 Arhar 18 6 6 4 16 Sugarcane 98 100 96 100 94 126 133 122 111 96 6 1 0 0 0 Ground Nut 25 24 18 6 0 Other Pulses 705 724 696 711 712 Kharif Total 110047 105798 105339 105011 104119 Paddy 4206 4316 4424 4324 4428 Wheat 679 684 618 685 624 Gram 14 18 24 21 20 Seasumum 54 62 64 56 66 Linseed 48 44 48 68 66 Mustard 503 524 516 505 418 5 6 4 6 6 742 718 721 724 718 Paddy 5526 5418 5424 5420 5426 Wheat 670 618 624 621 628 Gram 22 20 18 22 10 177 170 138 179 166 Linseed 81 88 66 78 88 Mustard 721 524 710 718 716 0 0 2 6 2 405 444 418 414 424 Castor Bihdia Jajikona Jute Castor Rabi Sualkuchi Other Oilseeds Vegetables Hajo Seasumum Other Oilseeds Vegetables Goroimari 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Paddy 4370 4416 4524 4420 4518 Wheat 355 324 316 327 316 Gram 15 16 16 18 10 Seasumum 30 34 30 40 28 Linseed 81 24 22 40 24 Mustard 127 120 118 124 124 0 0 0 0 0 290 224 216 228 216 Paddy 4197 4124 4135 4125 4128 Wheat 210 210 208 214 210 Gram 10 10 10 13 10 6 2 6 6 6 Linseed 55 56 28 56 52 Mustard 90 94 98 98 68 Other Oilseeds 75 78 66 84 73 450 418 481 424 478 Paddy 1100 1124 1126 1128 1196 Wheat 30 36 24 38 34 Gram 0 6 4 6 2 Seasumum 0 0 0 0 6 Linseed 10 6 4 15 10 Mustard 30 32 18 24 24 2 4 4 6 4 200 200 184 202 180 Paddy 4667 4614 4630 4624 4587 Wheat 122 118 120 120 118 Gram 50 44 24 42 22 Seasumum 50 44 42 52 54 Linseed 5 5 0 6 6 Mustard 105 113 110 115 110 Other Oilseeds Vegetables Chhaygaon Seasumum Vegetables Chandrapur Other Oilseeds Vegetables Dimoria 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 25 26 20 28 26 1200 1200 1212 1211 1210 Paddy 4823 4618 4624 4620 4416 Wheat 181 196 184 199 186 Gram 19 20 20 18 18 Seasumum 32 34 30 24 24 Linseed 0 2 0 6 2 Mustard 179 184 188 188 168 49 52 64 56 10 200 224 218 218 210 Paddy 5369 5218 5220 5220 5210 Wheat 198 118 108 120 100 Gram 75 72 84 64 84 Seasumum 250 218 216 265 188 Linseed 215 198 116 187 214 Mustard 475 418 420 416 418 Other Oilseeds 252 216 218 284 184 Vegetables 542 518 521 524 510 Paddy 3594 3524 3225 3520 3445 Wheat 145 144 118 145 111 Gram 41 40 20 38 18 Seasumum 33 36 24 35 64 Linseed 15 6 4 18 10 Mustard 395 384 385 324 324 2 4 6 6 6 285 216 210 216 208 Paddy 3851 3864 3818 3865 3824 Wheat 1301 1286 1210 1288 1224 40 40 18 36 18 Other Oilseeds Vegetables Chayani Barduar Other Oilseeds Vegetables Boko Bongaon Other Oilseeds Vegetables Chamaria Gram 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Seasumum 228 218 210 218 216 Linseed 135 198 112 135 124 Mustard 1149 418 1160 1155 1155 61 216 67 73 46 205 212 210 212 416 Paddy 3799 3618 3624 3624 3624 Wheat 510 466 416 467 415 0 0 6 6 6 Seasumum 100 94 68 100 64 Linseed 390 384 318 224 309 Mustard 570 524 548 534 524 Other Oilseeds 498 418 410 484 365 Vegetables 485 466 418 418 416 Paddy 3389 3465 3218 3466 3228 Wheat 160 145 125 147 125 Gram 11 12 24 10 16 Seasumum 34 28 18 24 24 Linseed 0 6 6 6 6 Mustard 164 162 160 168 162 41 24 20 31 24 243 218 231 224 224 Paddy 4418 4424 4424 4416 4400 Wheat 193 148 128 144 132 4 6 6 4 6 150 132 122 146 138 Linseed 8 6 0 6 6 Mustard 76 64 66 84 78 Other Oilseeds 23 24 28 24 18 219 200 224 218 202 Other Oilseeds Vegetables Rani Gram Rampur Other Oilseeds Vegetables Bezera Gram Seasumum Vegetables Kamalpur 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Paddy 4331 4418 4421 4516 4321 Wheat 64 64 77 64 62 Gram 24 18 14 24 25 Seasumum 24 20 18 22 18 Linseed 40 36 24 36 24 Mustard 77 65 36 32 24 Other Oilseeds 10 10 10 12 24 206 200 200 194 182 Paddy 7750 7721 7624 7318 7724 Wheat 502 518 514 534 524 Gram 121 118 96 88 66 38 44 44 36 40 Linseed 0 0 0 6 6 Mustard 771 716 684 664 597 0 0 6 6 6 1339 1324 1224 1284 1214 Paddy 5691 5684 5518 5425 5324 Wheat 175 164 184 186 184 Gram 20 16 18 24 25 Seasumum 67 66 34 62 38 Linseed 122 110 96 112 96 Mustard 1095 1066 906 1044 1018 30 24 33 24 18 265 248 218 224 216 Paddy 9795 9729 9618 9624 9618 Wheat 79 66 88 80 78 Gram 5 6 8 6 4 Seasumum 68 68 66 54 24 Linseed 75 62 64 64 88 Mustard 308 311 288 224 184 Vegetables Rangia Seasumum Other Oilseeds Vegetables Goreswar Other Oilseeds Vegetables Bihdia Jajikona 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 56 46 24 46 34 Vegetables 289 294 300 216 198 Rabi Total 105071 102754 101706 102600 101323 Kamrup Total 215118 208552 207045 207611 205442 Other Oilseeds Morigaon District Kharif Mayong Paddy 11689 11647 11582 11674 11526 Maize 55 50 50 28 38 Arhar 5 6 0 6 4 Sugarcane 115 96 98 100 96 Jute 520 544 518 518 464 10 4 0 0 0 Ground Nut 0 0 4 6 4 Other Pulses 13 18 18 14 24 Paddy 1478 1512 1497 1442 1472 Maize 0 0 0 0 0 Arhar 5 0 0 5 0 Sugarcane 685 485 618 598 514 Jute 434 444 388 316 325 0 0 0 0 0 Ground Nut 15 64 48 13 6 Other Pulses 50 24 16 64 78 Paddy 8822 8724 8614 8818 8650 Maize 0 0 0 0 0 Arhar 0 0 2 4 0 194 200 200 196 145 3000 2818 2624 2896 2946 0 0 0 0 0 Ground Nut 160 85 6 132 124 Other Pulses 102 98 96 98 64 Castor Moriabari Castor Laharighat Sugarcane Jute Castor 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Paddy 2412 2502 2294 2399 2404 Maize 0 0 0 0 0 Arhar 10 4 0 5 0 Sugarcane 200 200 184 184 155 Jute 847 844 818 864 818 Castor 0 0 0 0 0 Ground Nut 0 0 6 4 6 Other Pulses 62 64 96 66 65 Paddy 1564 1558 1700 1542 1534 Maize 0 0 0 0 0 Arhar 0 0 0 0 0 46 66 18 38 26 2385 2214 2224 2216 2114 Castor 0 0 0 0 0 Ground Nut 0 0 6 0 0 Other Pulses 324 314 288 284 224 Kharif Total 35202 34585 34013 34530 33826 Paddy 19405 19412 19212 19345 19228 Wheat 375 384 285 301 288 Gram 14 18 24 19 24 Seasumum 245 188 214 194 218 Linseed 110 96 96 64 96 Mustard 746 718 718 668 718 Other Oilseeds 430 287 218 221 384 Vegetables 880 864 824 756 886 Paddy 9830 9824 9624 9824 9818 Wheat 382 288 265 214 196 0 0 0 5 6 Bhurbandha Kapili Sugarcane Jute Rabi Mayong Moriabari Gram 10 MW Biomass Based Power Plant Crop Name ABEIL 2004-05 2003-04 2002-03 2001-02 2000-01 Seasumum 78 66 68 76 64 Linseed 75 64 78 64 78 Mustard 261 212 244 255 244 0 6 4 6 4 94 98 96 64 95 Paddy 13002 13024 13125 13000 13096 Wheat 351 364 384 324 318 Gram 100 85 86 88 74 Seasumum 180 196 144 132 198 Linseed 72 72 74 78 74 Mustard 331 324 324 318 324 46 46 84 18 64 300 218 210 288 304 Paddy 13822 13816 13616 13814 13800 Wheat 194 165 200 144 164 0 0 0 0 0 379 410 318 404 384 Linseed 95 94 98 78 92 Mustard 578 516 566 578 518 0 0 0 0 0 95 84 86 100 65 Paddy 3037 3024 3038 3024 3014 Wheat 104 98 78 105 96 0 0 0 2 12 38 24 64 88 44 Linseed 0 6 16 18 4 Mustard 817 864 812 810 796 0 0 0 0 0 Vegetables 145 128 126 136 135 Rabi Total 66611 66083 65419 65623 65923 Other Oilseeds Vegetables Laharighat Other Oilseeds Vegetables Bhurbandha Gram Seasumum Other Oilseeds Vegetables Kapili Gram Seasumum Other Oilseeds 10 MW Biomass Based Power Plant ABEIL Crop Name 2004-05 2003-04 2002-03 2001-02 2000-01 Morigaon Total 101813 100668 99432 100153 99749 Grand Total 316931 309220 306477 307764 305191 3.2.4 Livestock Population The livestock population of Kamrup and Morigaon districts is given in table below: 3.9 Livestock Population details Particulars Cattle Kamrup Morigaon 610748 146951 13167 4729 Goats 241659 63952 Pigs 164919 8544 Poultry 1465574 357188 Total 2496067 581364 Buffaloes (Source: Statistics deptt, Assamand Animal Husbandry Department,) 3.2.5 Industries 3.2.5.1 Rice Mills: There are around 5 Rice mills in the Kamrup district and 3 rice mills in Morigaon district as per rice mill association, but as per survey it is revealed that there are more no. of small capacity hullers in Kamrup and Morigaon district. The rice mills are milling the paddy coming from the district and nearby area. The rice mills are generating rice husk and rice bran. S.N. Name of Rice Mill Kamrup District 1 Sharma Rice Mill 2 Sri Laxmi Rice Mill 3 Sagar Rice Mill 4 Surana Industries 5 Dhaemashwari Rice Mill Morigaon District 10 MW Biomass Based Power Plant ABEIL S.N. Name of Rice Mill 1 Anand Rice Mill 2 Manhat Rice Mill 3 Sunil Rice Mill 3.2.5.2 Saw Mills: There are around 47 Sawmills in the Kamrup district and 13 sawmills in Morigaon district. These sawmills are getting wood from the near by villages. The main species are Babool, seasum, khejedi etc. The saw mills are generating wood chips and saw dust. 3.3 FINDING FROM HOUSEHOLD SURVEY To arrive consumption around 60 households in each blocks from the surrounding villages of the power plant site for survey. The survey finding is given in the table below. 3.10 Findings from Household survey Category Min Size of the Family Agriculture Land Owned (ha) Max Avg. % HH 2 13 6 0.4 42 9 46.16 Cooking/Heating Devices Used (Hours/Day) Chulha 1 9 4 79.10 Mud Stove 2 2 2 11.79 Kerosene Stove 1 3 2 17.69 Gas Stove 1 6 3 78.97 Electrical Stove 3 4 4 5.90 Kerosene Lamp 1 4 2 26.52 Gas Lamp 1 4 3 9.79 Electric Lamp 3 18 11 97.55 Other Lamps 1 2 1 23.14 2 8 2.6 68.88 Lighting Devices Used (Hours/Day) Type Of Fuel (Kg/Day) Fuel Wood 10 MW Biomass Based Power Plant Category Crop Residue ABEIL Min Max Avg. % HH 0.5 3 1 21.03 Dung Cake 3 20 11 23.24 Kerosene (Lit/Month) 2 6 4 38.97 LPG (Cylinders/Month) 0.5 1.5 0.9 72.63 Electricity (kWh/Two Month) 152 175 162 95.00 Paddy Straw 1.17 1.96 1.86 Wheat Straw 1.27 1.93 1.79 Maize Stalk 2.16 2.86 2.35 Crop Yield (Tons/Hectare) 3.4 Biomass Generation The major sources of biomass generation are from Crop residues, wastelands and forestry, and Agro industry residues. Biomass is categorized into suitable for fodder and also not suitable for fodder. Enough care has been taken to not to use the fodder material for power plant. 3.5 Crop Residues Extensive survey was carried out to establish the yields and crop residue ratios. This information is gathered from the village heads, and literature. Estimates were made based on the field data and agriculture department data. The biomass generated is classified into the biomass suitable for fodder and also for burning. Biomass generated was estimated on the average values of yields and crop residue ratios. Block wise biomass Generation for season wise is given in the following table. 10 MW Biomass Based Power Plant ABEIL 3.11 Block wise Crop residue generation Crop Name Area (ha) Yield (T/ha) Production (Tons) Residue Type CRR Generation (Tons) KAMRUP DISTRICT Sualkuchi Kharif Paddy 4498 1.69 7601.62 Straw 1.33 10110.15 Maize 13 0.73 9.49 Stalks 1.86 17.65 Cobs 0.3 2.85 Stalks 1.03 7.90 Tops & Leaves 0.06 209.83 Trash 0.04 139.89 Arhar 13 0.59 7.67 Sugarcane 91 38.43 3497.13 Jute 576 1.87 1077.12 Stalks 1.83 1971.13 Castor 5 0.89 4.45 Stalks 1.23 5.47 Ground Nut 7 1.03 7.21 Stalks 1.78 12.83 515 0.53 272.95 Stalks 1.01 275.68 Paddy 4206 1.63 6855.78 Straw 1.31 8981.07 Wheat 679 1.03 699.37 Straw 1.36 951.14 Gram 14 0.56 7.84 Stalks 1.02 8.00 Seasumum 54 0.59 31.86 Stalks 1.51 48.11 Linseed 48 0.48 23.04 Stalks 1.43 32.95 Mustard 503 1.01 508.03 Stalks 1.61 817.93 5 0.53 2.65 Stalks 1.42 3.76 742 1.46 1083.32 Straw 1 1083.32 Other Pulses Rabi Other Oilseeds Vegetables TOTAL 21689.53 24679.66 Hajo Kharif Paddy 14264 1.69 24106.16 Straw 1.33 32061.19 Maize 30 0.73 21.90 Stalks 1.86 40.73 Cobs 0.3 6.57 Stalks 1.03 12.15 Tops & Leaves 0.06 96.84 Trash 0.04 64.56 Arhar 20 0.59 11.80 Sugarcane 42 38.43 1614.06 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Production (Tons) Residue Type CRR Generation (Tons) 700 1.87 1309.00 Stalks 1.83 2395.47 Castor 4 0.89 3.56 Stalks 1.23 4.38 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 877 0.53 464.81 Stalks 1.01 469.46 Paddy 5526 1.63 9007.38 Straw 1.31 11799.67 Wheat 670 1.03 690.10 Straw 1.36 938.54 Gram 22 0.56 12.32 Stalks 1.02 12.57 177 0.59 104.43 Stalks 1.51 157.69 Linseed 81 0.48 38.88 Stalks 1.43 55.60 Mustard 721 1.01 728.21 Stalks 1.61 1172.42 0 0.53 0.00 Stalks 1.42 0.00 405 1.46 591.30 Straw 1 591.30 Jute Other Pulses Rabi Seasumum Other Oilseeds Vegetables TOTAL 38703.91 49879.14 Goroimari Kharif Paddy 2865 1.69 4841.85 Straw 1.33 6439.66 Maize 30 0.73 21.90 Stalks 1.86 40.73 Cobs 0.3 6.57 Stalks 1.03 48.62 Tops & Leaves 0.06 99.15 Trash 0.04 66.10 Arhar 80 0.59 47.20 Sugarcane 43 38.43 1652.49 Jute 220 1.87 411.40 Stalks 1.83 752.86 Castor 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 Other Pulses 38 0.53 20.14 Stalks 1.01 20.34 Paddy 4370 1.63 7123.10 Straw 1.31 9331.26 Wheat 355 1.03 365.65 Straw 1.36 497.28 Gram 15 0.56 8.40 Stalks 1.02 8.57 Seasumum 30 0.59 17.70 Stalks 1.51 26.73 Linseed 81 0.48 38.88 Stalks 1.43 55.60 Rabi 10 MW Biomass Based Power Plant Crop Name Mustard Other Oilseeds Vegetables ABEIL Area (ha) Yield (T/ha) 127 1.01 0 290 Residue Type CRR 128.27 Stalks 1.61 206.51 0.53 0.00 Stalks 1.42 0.00 1.46 423.40 Straw 1 423.40 TOTAL Production (Tons) 15100.38 Generation (Tons) 18023.39 Chhaygaon Kharif Paddy 2850 1.69 4816.50 Straw 1.33 6405.95 Maize 110 0.73 80.30 Stalks 1.86 149.36 Cobs 0.3 24.09 Stalks 1.03 6.08 Tops & Leaves 0.06 80.70 Trash 0.04 53.80 Arhar 10 0.59 5.90 Sugarcane 35 38.43 1345.05 Jute 75 1.87 140.25 Stalks 1.83 256.66 Castor 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 5 1.03 5.15 Stalks 1.78 9.17 165 0.53 87.45 Stalks 1.01 88.32 Paddy 4197 1.63 6841.11 Straw 1.31 8961.85 Wheat 210 1.03 216.30 Straw 1.36 294.17 Gram 10 0.56 5.60 Stalks 1.02 5.71 6 0.59 3.54 Stalks 1.51 5.35 Linseed 55 0.48 26.40 Stalks 1.43 37.75 Mustard 90 1.01 90.90 Stalks 1.61 146.35 Other Oilseeds 75 0.53 39.75 Stalks 1.42 56.45 450 1.46 657.00 Straw 1 657.00 Other Pulses Rabi Seasumum Vegetables TOTAL 14361.20 17238.75 Chandrapur Kharif Paddy 1188 1.69 2007.72 Straw 1.33 2670.27 Maize 0 0.73 0.00 Stalks 1.86 0.00 Cobs 0.3 0.00 Stalks 1.03 0.00 Arhar 0 0.59 0.00 10 MW Biomass Based Power Plant Crop Name Sugarcane ABEIL Area (ha) Yield (T/ha) 2 38.43 Production (Tons) 76.86 Residue Type CRR Generation (Tons) Tops & Leaves 0.06 4.61 Trash 0.04 3.07 Jute 2 1.87 3.74 Stalks 1.83 6.84 Castor 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 Other Pulses 30 0.53 15.90 Stalks 1.01 16.06 Paddy 1100 1.63 1793.00 Straw 1.31 2348.83 Wheat 30 1.03 30.90 Straw 1.36 42.02 Gram 0 0.56 0.00 Stalks 1.02 0.00 Seasumum 0 0.59 0.00 Stalks 1.51 0.00 Linseed 10 0.48 4.80 Stalks 1.43 6.86 Mustard 30 1.01 30.30 Stalks 1.61 48.78 2 0.53 1.06 Stalks 1.42 1.51 200 1.46 292.00 Straw 1 292.00 Rabi Other Oilseeds Vegetables TOTAL 4256.28 5440.86 Dimoria Kharif Paddy 4300 1.69 7267.00 Straw 1.33 9665.11 Maize 5 0.73 3.65 Stalks 1.86 6.79 Cobs 0.3 1.10 Stalks 1.03 30.39 Tops & Leaves 0.06 46.12 Trash 0.04 30.74 Arhar 50 0.59 29.50 Sugarcane 20 38.43 768.60 Jute 100 1.87 187.00 Stalks 1.83 342.21 2 0.89 1.78 Stalks 1.23 2.19 Ground Nut 27 1.03 27.81 Stalks 1.78 49.50 Other Pulses 200 0.53 106.00 Stalks 1.01 107.06 Paddy 4667 1.63 7607.21 Straw 1.31 9965.45 Wheat 122 1.03 125.66 Straw 1.36 170.90 Gram 50 0.56 28.00 Stalks 1.02 28.56 Castor Rabi 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) 50 0.59 Linseed 5 Mustard Seasumum Other Oilseeds Vegetables Residue Type CRR 29.50 Stalks 1.51 44.55 0.48 2.40 Stalks 1.43 3.43 105 1.01 106.05 Stalks 1.61 170.74 25 0.53 13.25 Stalks 1.42 18.82 1200 1.46 1752.00 Straw 1 1752.00 TOTAL Production (Tons) 18055.41 Generation (Tons) 22435.64 Chayani Barduar Kharif Paddy 1732 1.69 2927.08 Straw 1.33 3893.02 Maize 9 0.73 6.57 Stalks 1.86 12.22 Cobs 0.3 1.97 Stalks 1.03 6.08 Tops & Leaves 0.06 212.13 Trash 0.04 141.42 Arhar 10 0.59 5.90 Sugarcane 92 38.43 3535.56 Jute 679 1.87 1269.73 Stalks 1.83 2323.61 Castor 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 213 0.53 112.89 Stalks 1.01 114.02 Paddy 4823 1.63 7861.49 Straw 1.31 10298.55 Wheat 181 1.03 186.43 Straw 1.36 253.54 Gram 19 0.56 10.64 Stalks 1.02 10.85 Seasumum 32 0.59 18.88 Stalks 1.51 28.51 Linseed 0 0.48 0.00 Stalks 1.43 0.00 Mustard 179 1.01 180.79 Stalks 1.61 291.07 49 0.53 25.97 Stalks 1.42 36.88 200 1.46 292.00 Straw 1 292.00 Other Pulses Rabi Other Oilseeds Vegetables TOTAL 16433.93 17915.87 Boko Kharif Paddy 4604 1.69 7780.76 Straw 1.33 10348.41 Maize 225 0.73 164.25 Stalks 1.86 305.51 10 MW Biomass Based Power Plant Crop Name Arhar Sugarcane Area (ha) ABEIL Yield (T/ha) Production (Tons) 55 0.59 32.45 450 38.43 17293.50 Residue Type CRR Generation (Tons) Cobs 0.3 49.28 Stalks 1.03 33.42 Tops & Leaves 0.06 1037.61 Trash 0.04 691.74 Jute 330 1.87 617.10 Stalks 1.83 1129.29 Castor 550 0.89 489.50 Stalks 1.23 602.09 Ground Nut 170 1.03 175.10 Stalks 1.78 311.68 Other Pulses 635 0.53 336.55 Stalks 1.01 339.92 Paddy 5369 1.63 8751.47 Straw 1.31 11464.43 Wheat 198 1.03 203.94 Straw 1.36 277.36 Gram 75 0.56 42.00 Stalks 1.02 42.84 Seasumum 250 0.59 147.50 Stalks 1.51 222.73 Linseed 215 0.48 103.20 Stalks 1.43 147.58 Mustard 475 1.01 479.75 Stalks 1.61 772.40 Other Oilseeds 252 0.53 133.56 Stalks 1.42 189.66 Vegetables 542 1.46 791.32 Straw 1 791.32 Rabi TOTAL 37541.95 28757.23 Bongaon Kharif Paddy 2738 1.69 4627.22 Straw 1.33 6154.20 Maize 45 0.73 32.85 Stalks 1.86 61.10 Cobs 0.3 9.86 Stalks 1.03 21.27 Tops & Leaves 0.06 115.29 Trash 0.04 76.86 Arhar 35 0.59 20.65 Sugarcane 50 38.43 1921.50 Jute 360 1.87 673.20 Stalks 1.83 1231.96 Castor 112 0.89 99.68 Stalks 1.23 122.61 0 1.03 0.00 Stalks 1.78 0.00 114 0.53 60.42 Stalks 1.01 61.02 3594 1.63 5858.22 Straw 1.31 7674.27 Ground Nut Other Pulses Rabi Paddy 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Wheat 145 1.03 Gram 41 Seasumum Residue Type CRR 149.35 Straw 1.36 203.12 0.56 22.96 Stalks 1.02 23.42 33 0.59 19.47 Stalks 1.51 29.40 Linseed 15 0.48 7.20 Stalks 1.43 10.30 Mustard 395 1.01 398.95 Stalks 1.61 642.31 2 0.53 1.06 Stalks 1.42 1.51 285 1.46 416.10 Straw 1 416.10 Other Oilseeds Vegetables TOTAL Production (Tons) 14308.83 Generation (Tons) 16854.58 Chamaria Kharif Paddy 15646 1.69 26441.74 Straw 1.33 35167.51 Maize 2 0.73 1.46 Stalks 1.86 2.72 Cobs 0.3 0.44 Stalks 1.03 351.25 Tops & Leaves 0.06 182.16 Trash 0.04 121.44 Arhar Sugarcane Jute 578 0.59 341.02 79 38.43 3035.97 1753 1.87 3278.11 Stalks 1.83 5998.94 Castor 2 0.89 1.78 Stalks 1.23 2.19 Ground Nut 2 1.03 2.06 Stalks 1.78 3.67 638 0.53 338.14 Stalks 1.01 341.52 Paddy 3851 1.63 6277.13 Straw 1.31 8223.04 Wheat 1301 1.03 1340.03 Straw 1.36 1822.44 40 0.56 22.40 Stalks 1.02 22.85 Seasumum 228 0.59 134.52 Stalks 1.51 203.13 Linseed 135 0.48 64.80 Stalks 1.43 92.66 Mustard 1149 1.01 1160.49 Stalks 1.61 1868.39 61 0.53 32.33 Stalks 1.42 45.91 205 1.46 299.30 Straw 1 299.30 Other Pulses Rabi Gram Other Oilseeds Vegetables TOTAL Rani Kharif 42771.28 54749.55 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Production (Tons) Residue Type CRR Generation (Tons) Paddy 4200 1.69 7098.00 Straw 1.33 9440.34 Maize 0 0.73 0.00 Stalks 1.86 0.00 Cobs 0.3 0.00 Stalks 1.03 145.85 Tops & Leaves 0.06 830.09 Trash 0.04 553.39 Arhar 240 0.59 141.60 Sugarcane 360 38.43 13834.80 Jute 500 1.87 935.00 Stalks 1.83 1711.05 Castor 140 0.89 124.60 Stalks 1.23 153.26 Ground Nut 410 1.03 422.30 Stalks 1.78 751.69 Other Pulses 200 0.53 106.00 Stalks 1.01 107.06 Paddy 3799 1.63 6192.37 Straw 1.31 8112.00 Wheat 510 1.03 525.30 Straw 1.36 714.41 0 0.56 0.00 Stalks 1.02 0.00 Seasumum 100 0.59 59.00 Stalks 1.51 89.09 Linseed 390 0.48 187.20 Stalks 1.43 267.70 Mustard 570 1.01 575.70 Stalks 1.61 926.88 Other Oilseeds 498 0.53 263.94 Stalks 1.42 374.79 Vegetables 485 1.46 708.10 Straw 1 708.10 Rabi Gram TOTAL 31173.91 24885.70 Rampur Kharif Paddy 2006 1.69 3390.14 Straw 1.33 4508.89 Maize 10 0.73 7.30 Stalks 1.86 13.58 Cobs 0.3 2.19 Stalks 1.03 6.08 Tops & Leaves 0.06 255.94 Trash 0.04 170.63 Arhar Sugarcane Jute 10 0.59 5.90 111 38.43 4265.73 239 1.87 446.93 Stalks 1.83 817.88 Castor 1 0.89 0.89 Stalks 1.23 1.09 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 226 0.53 119.78 Stalks 1.01 120.98 Other Pulses 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Production (Tons) Residue Type CRR Generation (Tons) Paddy 3389 1.63 5524.07 Straw 1.31 7236.53 Wheat 160 1.03 164.80 Straw 1.36 224.13 Gram 11 0.56 6.16 Stalks 1.02 6.28 Seasumum 34 0.59 20.06 Stalks 1.51 30.29 Linseed 0 0.48 0.00 Stalks 1.43 0.00 Mustard 164 1.01 165.64 Stalks 1.61 266.68 41 0.53 21.73 Stalks 1.42 30.86 243 1.46 354.78 Straw 1 354.78 Rabi Other Oilseeds Vegetables TOTAL 14493.91 14046.81 Bezera Kharif Paddy 3216 1.69 5435.04 Straw 1.33 7228.60 Maize 6 0.73 4.38 Stalks 1.86 8.15 Cobs 0.3 1.31 Stalks 1.03 7.29 Tops & Leaves 0.06 48.42 Trash 0.04 32.28 Arhar 12 0.59 7.08 Sugarcane 21 38.43 807.03 Jute 25 1.87 46.75 Stalks 1.83 85.55 4 0.89 3.56 Stalks 1.23 4.38 Ground Nut 50 1.03 51.50 Stalks 1.78 91.67 Other Pulses 250 0.53 132.50 Stalks 1.01 133.83 Paddy 4418 1.63 7201.34 Straw 1.31 9433.76 Wheat 193 1.03 198.79 Straw 1.36 270.35 4 0.56 2.24 Stalks 1.02 2.28 150 0.59 88.50 Stalks 1.51 133.64 Linseed 8 0.48 3.84 Stalks 1.43 5.49 Mustard 76 1.01 76.76 Stalks 1.61 123.58 Other Oilseeds 23 0.53 12.19 Stalks 1.42 17.31 219 1.46 319.74 Straw 1 319.74 Castor Rabi Gram Seasumum Vegetables TOTAL 14391.24 17947.64 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Production (Tons) Residue Type CRR Generation (Tons) Paddy 1330 1.69 2247.70 Straw 1.33 2989.44 Maize 2 0.73 1.46 Stalks 1.86 2.72 Cobs 0.3 0.44 Stalks 1.03 1.22 Tops & Leaves 0.06 20.75 Trash 0.04 13.83 Kamalpur Kharif Arhar 2 0.59 1.18 Sugarcane 9 38.43 345.87 Jute 5 1.87 9.35 Stalks 1.83 17.11 Castor 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 12 1.03 12.36 Stalks 1.78 22.00 Other Pulses 211 0.53 111.83 Stalks 1.01 112.95 Paddy 4331 1.63 7059.53 Straw 1.31 9247.98 Wheat 64 1.03 65.92 Straw 1.36 89.65 Gram 24 0.56 13.44 Stalks 1.02 13.71 Seasumum 24 0.59 14.16 Stalks 1.51 21.38 Linseed 40 0.48 19.20 Stalks 1.43 27.46 Mustard 77 1.01 77.77 Stalks 1.61 125.21 Other Oilseeds 10 0.53 5.30 Stalks 1.42 7.53 206 1.46 300.76 Straw 1 300.76 Rabi Vegetables TOTAL 10285.83 13014.13 Rangia Kharif Paddy 13540 1.69 22882.60 Straw 1.33 30433.86 Maize 303 0.73 221.19 Stalks 1.86 411.41 Cobs 0.3 66.36 Stalks 1.03 8.51 Tops & Leaves 0.06 156.79 Trash 0.04 104.53 Arhar 14 0.59 8.26 Sugarcane 68 38.43 2613.24 Jute Castor 29 1.87 54.23 Stalks 1.83 99.24 0 0.89 0.00 Stalks 1.23 0.00 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Residue Type CRR 0 1.03 0.00 Stalks 1.78 0.00 338 0.53 179.14 Stalks 1.01 180.93 Paddy 7750 1.63 12632.50 Straw 1.31 16548.58 Wheat 502 1.03 517.06 Straw 1.36 703.20 Gram 121 0.56 67.76 Stalks 1.02 69.12 38 0.59 22.42 Stalks 1.51 33.85 Linseed 0 0.48 0.00 Stalks 1.43 0.00 Mustard 771 1.01 778.71 Stalks 1.61 1253.72 0 0.53 0.00 Stalks 1.42 0.00 1339 1.46 1954.94 Straw 1 1954.94 Ground Nut Other Pulses Production (Tons) Generation (Tons) Rabi Seasumum Other Oilseeds Vegetables TOTAL 41932.05 52025.04 Goreswar Kharif Paddy 11265 1.69 19037.85 Straw 1.33 25320.34 Maize 24 0.73 17.52 Stalks 1.86 32.59 Cobs 0.3 5.26 Stalks 1.03 17.62 Tops & Leaves 0.06 371.23 Trash 0.04 247.49 Arhar Sugarcane Jute 29 0.59 17.11 161 38.43 6187.23 547 1.87 1022.89 Stalks 1.83 1871.89 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 29 1.03 29.87 Stalks 1.78 53.17 Other Pulses 103 0.53 54.59 Stalks 1.01 55.14 Paddy 5691 1.63 9276.33 Straw 1.31 12151.99 Wheat 175 1.03 180.25 Straw 1.36 245.14 Gram 20 0.56 11.20 Stalks 1.02 11.42 Seasumum 67 0.59 39.53 Stalks 1.51 59.69 Linseed 122 0.48 58.56 Stalks 1.43 83.74 Mustard 1095 1.01 1105.95 Stalks 1.61 1780.58 30 0.53 15.90 Stalks 1.42 22.58 Castor Rabi Other Oilseeds 10 MW Biomass Based Power Plant Crop Name Vegetables ABEIL Area (ha) Yield (T/ha) 265 1.46 TOTAL Production (Tons) 386.90 Residue Type Straw CRR 1 37441.68 Generation (Tons) 386.90 42716.77 Bihdia Jajikona Kharif Paddy 2789 1.69 4713.41 Straw 1.33 6268.84 Maize 7 0.73 5.11 Stalks 1.86 9.50 Cobs 0.3 1.53 Stalks 1.03 10.94 Tops & Leaves 0.06 225.97 Trash 0.04 150.65 Arhar 18 0.59 10.62 Sugarcane 98 38.43 3766.14 Jute 126 1.87 235.62 Stalks 1.83 431.18 6 0.89 5.34 Stalks 1.23 6.57 Ground Nut 25 1.03 25.75 Stalks 1.78 45.84 Other Pulses 705 0.53 373.65 Stalks 1.01 377.39 Paddy 9795 1.63 15965.85 Straw 1.31 20915.26 Wheat 79 1.03 81.37 Straw 1.36 110.66 Gram 5 0.56 2.80 Stalks 1.02 2.86 Seasumum 68 0.59 40.12 Stalks 1.51 60.58 Linseed 75 0.48 36.00 Stalks 1.43 51.48 Mustard 308 1.01 311.08 Stalks 1.61 500.84 56 0.53 29.68 Stalks 1.42 42.15 289 1.46 421.94 Straw 1 421.94 Castor Rabi Other Oilseeds Vegetables TOTAL 26024.48 29634.17 MORIGAON DISTRICT Mayong Kharif Paddy 11689 1.69 19754.41 Straw 1.33 26273.37 Maize 55 0.73 40.15 Stalks 1.86 74.68 Cobs 0.3 12.05 Stalks 1.03 3.04 Tops & Leaves 0.06 265.17 Arhar Sugarcane 5 0.59 2.95 115 38.43 4419.45 10 MW Biomass Based Power Plant Crop Name Jute Area (ha) ABEIL Yield (T/ha) Production (Tons) Residue Type CRR Generation (Tons) Trash 0.04 176.78 520 1.87 972.40 Stalks 1.83 1779.49 10 0.89 8.90 Stalks 1.23 10.95 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 Other Pulses 13 0.53 6.89 Stalks 1.01 6.96 Paddy 19405 1.63 31630.15 Straw 1.31 41435.50 Wheat 375 1.03 386.25 Straw 1.36 525.30 Gram 14 0.56 7.84 Stalks 1.02 8.00 Seasumum 245 0.59 144.55 Stalks 1.51 218.27 Linseed 110 0.48 52.80 Stalks 1.43 75.50 Mustard 746 1.01 753.46 Stalks 1.61 1213.07 Other Oilseeds 430 0.53 227.90 Stalks 1.42 323.62 Vegetables 880 1.46 1284.80 Straw 1 1284.80 Castor Rabi TOTAL 59692.90 73686.53 Moriabari Kharif Paddy 1478 1.69 2497.82 Straw 1.33 3322.10 Maize 0 0.73 0.00 Stalks 1.86 0.00 Cobs 0.3 0.00 Stalks 1.03 3.04 Tops & Leaves 0.06 1579.47 Trash 0.04 1052.98 Arhar Sugarcane Jute 5 0.59 2.95 685 38.43 26324.55 434 1.87 811.58 Stalks 1.83 1485.19 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 15 1.03 15.45 Stalks 1.78 27.50 Other Pulses 50 0.53 26.50 Stalks 1.01 26.77 Paddy 9830 1.63 16022.90 Straw 1.31 20990.00 Wheat 382 1.03 393.46 Straw 1.36 535.11 0 0.56 0.00 Stalks 1.02 0.00 78 0.59 46.02 Stalks 1.51 69.49 Castor Rabi Gram Seasumum 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Linseed 75 0.48 Mustard 261 Other Oilseeds Vegetables Residue Type CRR 36.00 Stalks 1.43 51.48 1.01 263.61 Stalks 1.61 424.41 0 0.53 0.00 Stalks 1.42 0.00 94 1.46 137.24 Straw 1 137.24 TOTAL Production (Tons) 46578.08 Generation (Tons) 29704.78 Laharighat Kharif Paddy 8822 1.69 14909.18 Straw 1.33 19829.21 Maize 0 0.73 0.00 Stalks 1.86 0.00 Cobs 0.3 0.00 Stalks 1.03 0.00 Tops & Leaves 0.06 447.33 Trash 0.04 298.22 Arhar Sugarcane Jute 0 0.59 0.00 194 38.43 7455.42 3000 1.87 5610.00 Stalks 1.83 10266.30 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 160 1.03 164.80 Stalks 1.78 293.34 Other Pulses 102 0.53 54.06 Stalks 1.01 54.60 Paddy 13002 1.63 21193.26 Straw 1.31 27763.17 Wheat 351 1.03 361.53 Straw 1.36 491.68 Gram 100 0.56 56.00 Stalks 1.02 57.12 Seasumum 180 0.59 106.20 Stalks 1.51 160.36 Linseed 72 0.48 34.56 Stalks 1.43 49.42 Mustard 331 1.01 334.31 Stalks 1.61 538.24 46 0.53 24.38 Stalks 1.42 34.62 300 1.46 438.00 Straw 1 438.00 Castor Rabi Other Oilseeds Vegetables TOTAL 50741.70 60721.61 Bhurbandha Kharif Paddy 2412 1.69 4076.28 Straw 1.33 5421.45 Maize 0 0.73 0.00 Stalks 1.86 0.00 Cobs 0.3 0.00 10 MW Biomass Based Power Plant Crop Name Arhar Sugarcane Jute ABEIL Area (ha) Yield (T/ha) Production (Tons) 10 0.59 5.90 200 38.43 7686.00 Residue Type CRR Generation (Tons) Stalks 1.03 6.08 Tops & Leaves 0.06 461.16 Trash 0.04 307.44 847 1.87 1583.89 Stalks 1.83 2898.52 Castor 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 Other Pulses 62 0.53 32.86 Stalks 1.01 33.19 Paddy 13822 1.63 22529.86 Straw 1.31 29514.12 Wheat 194 1.03 199.82 Straw 1.36 271.76 0 0.56 0.00 Stalks 1.02 0.00 379 0.59 223.61 Stalks 1.51 337.65 Linseed 95 0.48 45.60 Stalks 1.43 65.21 Mustard 578 1.01 583.78 Stalks 1.61 939.89 0 0.53 0.00 Stalks 1.42 0.00 95 1.46 138.70 Straw 1 138.70 Rabi Gram Seasumum Other Oilseeds Vegetables TOTAL 37106.30 40395.15 Kapili Kharif Paddy 1564 1.69 2643.16 Straw 1.33 3515.40 Maize 0 0.73 0.00 Stalks 1.86 0.00 Cobs 0.3 0.00 Stalks 1.03 0.00 Tops & Leaves 0.06 106.07 Trash 0.04 70.71 Arhar Sugarcane Jute 0 0.59 0.00 46 38.43 1767.78 2385 1.87 4459.95 Stalks 1.83 8161.71 Castor 0 0.89 0.00 Stalks 1.23 0.00 Ground Nut 0 1.03 0.00 Stalks 1.78 0.00 324 0.53 171.72 Stalks 1.01 173.44 Paddy 3037 1.63 4950.31 Straw 1.31 6484.91 Wheat 104 1.03 107.12 Straw 1.36 145.68 Other Pulses Rabi 10 MW Biomass Based Power Plant Crop Name ABEIL Area (ha) Yield (T/ha) Residue Type CRR 0 0.56 0.00 Stalks 1.02 0.00 38 0.59 22.42 Stalks 1.51 33.85 Linseed 0 0.48 0.00 Stalks 1.43 0.00 Mustard 817 1.01 825.17 Stalks 1.61 1328.52 0 0.53 0.00 Stalks 1.42 0.00 145 1.46 211.70 Straw 1 211.70 Gram Seasumum Other Oilseeds Vegetables Production (Tons) TOTAL 15159.33 Generation (Tons) 20231.99 3.12 Summary of District wise Crop residue generation in tons District Rabi Total Kamrup 244391.05 205853.89 450244.93 Morigaon 88443.68 136296.38 224740.06 332834.73 342150.27 674984.99 Grand total 3.4.2 Kharif Biomass from Forest and Other Waste Lands Besides the State forest there are other areas, which include waste lands in the district. Interaction with the farmers, during the survey revealed that the annual sustainable productivity of the forest land in the district is 1.5 MT/year and wastelands, which includes barren uncultivatable, permanent pasture and grazing land are 0.8 MT/year. Biomass from wastelands is calculated through multiplying the total area under barren uncultivable, permanent pasture and grazing land by the average annual sustainable productivity of wastelands. The following table indicates the area and biomass generated from forest and other lands in the district. 3.13 Biomass generation from forest & other land sources in tons District Forest land Other Waste lands Total Kamrup 175041 57211 232252 Morigaon 26439 14904 41343 201480 72115 273595 Grand Total 10 MW Biomass Based Power Plant 3.4.3 ABEIL Agro Industry Residues Major Agro industrial residues available within district are rice husk, rice bran, wood chips, saw dust etc. 3.14 District wise biomass generation from Industries in tons Particulars Kamrup Morigaon TOTAL Rice Mills Husk 63591 30846 94437 Bran 14453 7010 21463 2115 585 2700 423 117 540 Saw Mills Wood chips Saw dust 3.4.4 Summary of Biomass Generation from all Sources Biomass from crop residues, agro industries mainly from rice mills, and forest and wastelands is estimated and given below: 3.15 District wise biomass generation from all sources in tons Districts Crop Residue Forest & other lands AgroIndustry Total Kamrup 450244.93 232252 80582 763079 Morigaon 224740.06 41343 38558 304641 Grand total 674984.99 273595 119140 1067720 Total biomass generation in the both districts is 674984.99 tons of crop residue, 273595 tons of wood and 119140 tons of agro industrial residue which includes bagasse, rice husk, wood chips etc. The total biomass generation from all sources is 1067720. 3.5 Biomass Consumption The major areas of biomass consumption are for domestic fuel, fodder and small hotels etc. As per the survey, the average consumption of woody biomass consumed per household per annum is around 50-70 kgs in the both districts. 10 MW Biomass Based Power Plant 3.5.1 ABEIL Domestic Fuel Consumption This area is developed one and the purchasing capacity is much higher. Slowly domestic fuel is being shifted from the wood, dung cakes to LPG. The wood and crop residue consumption is considered on an average basis as 50-70 Kgs and 26-44 kgs per annum per person in Kamrup and Morigaon district respectively. This figure is arrived based on the household survey carried out in 60 households in selected village of each blocks. In every block one or two village was selected for household survey, for domestic and fodder consumptions and other miscellaneous purposes. Domestic fuel requirement in the district given below: 3.16 District wise Domestic fuel consumption in tons Districts Domestic Fuel (Tons) Wood Total Kamrup 112987 41958.80 154945.80 Morigaon 33222 32680.10 65902.10 146209.00 74638.90 220847.90 Total 3.5.2 Crop Residue Fodder Consumption In this area cattle also sent for grazing. On an average, the consumption of fodder is around 4-6 kg/day per cattle. 3.17 District wise Fodder consumption in tons Districts Fodder Consumption Rice Bran Total Kamrup 403488.80 14453 417941.80 Morigaon 189989.67 7010 196999.67 Grand total 593478.47 21463 614941.47 10 MW Biomass Based Power Plant 3.5.3 ABEIL Industrial Fuel Consumption The following table gives the details of consumption of biomass in industrial sector within Kamrup and Morigaon districts. 3.18 District wise Industrial Biomass consumption in tons District Saw mill Brick Kilns, Poultry farms, Hotels Wood Rice Husk Wood chips Saw dust Kamrup 8460 33067 2115 423 44065 Morigaon 2340 16040 585 117 19082 10800 49107 2700 540 63147 Grand total 3.5.4 Total Summary of Biomass Consumption The following table gives the summary of biomass consumption in different sectors within the district. 3.19 Summary of Biomass consumption in tons District Domestic Fodder Kamrup 154945.80 417941.80 44065 616952.60 Morigaon 65902.10 196999.67 19082 281983.77 220847.90 614941.47 63147 898936.37 Grand total 3.6 Industry Total Biomass Surplus After estimating the biomass generation from the possible sources, and estimating the consumption of biomass as fodder and also for domestic fuel, which contributes the major consumption, the other consumptions namely for saw mills etc can be accounted in the wood, portion, the net biomass surplus available from each block of district are given below: 3.6.1 Block wise Crop Residue Balance The following table gives the details of surplus biomass from different sources within the district. 10 MW Biomass Based Power Plant ABEIL 3.20 Block wise crop residue balance in tons Crop Name Residue Type Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus KAMRUP DISTRICT Sualkuchi Kharif Paddy Straw 10110.15 9806.85 303.30 0.00 0.00 Maize Stalks 17.65 17.65 0.00 0.00 0.00 Cobs 2.85 0.00 0.00 2.85 0.00 Arhar Stalks 7.90 0.00 0.00 7.90 0.00 Sugarcane Tops & Leaves 209.83 209.83 0.00 0.00 0.00 Trash 139.89 0.00 0.00 139.89 0.00 Jute Stalks 1971.13 0.00 0.00 1971.13 0.00 Castor Stalks 5.47 5.47 0.00 0.00 0.00 Ground Nut Stalks 12.83 12.83 0.00 0.00 0.00 Other Pulses Stalks 275.68 0.00 0.00 275.68 0.00 Paddy Straw 8981.07 8981.07 0.00 0.00 0.00 Wheat Straw 951.14 951.14 0.00 0.00 0.00 Gram Stalks 8.00 8.00 0.00 0.00 0.00 Seasumum Stalks 48.11 0.00 0.00 48.11 0.00 Linseed Stalks 32.95 0.00 0.00 32.95 0.00 Mustard Stalks 817.93 0.00 0.00 817.93 0.00 Other Oilseeds Stalks 3.76 0.00 0.00 3.76 0.00 Vegetables Straw 1083.32 1083.32 0.00 0.00 0.00 24679.66 21076.17 303.30 3300.19 0.00 Rabi TOTAL Hajo Kharif Paddy Straw 32061.19 31740.58 320.61 0.00 0.00 Maize Stalks 40.73 40.73 0.00 0.00 0.00 Cobs 6.57 0.00 0.00 6.57 0.00 Stalks 12.15 0.00 0.00 12.15 0.00 Arhar 10 MW Biomass Based Power Plant Crop Name Sugarcane Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Tops & Leaves 96.84 96.84 0.00 0.00 0.00 Trash 64.56 0.00 0.00 64.56 0.00 Jute Stalks 2395.47 0.00 0.00 2395.47 0.00 Castor Stalks 4.38 4.38 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 469.46 0.00 0.00 469.46 0.00 Paddy Straw 11799.67 11799.67 0.00 0.00 0.00 Wheat Straw 938.54 938.54 0.00 0.00 0.00 Gram Stalks 12.57 12.57 0.00 0.00 0.00 Seasumum Stalks 157.69 0.00 0.00 157.69 0.00 Linseed Stalks 55.60 0.00 0.00 55.60 0.00 Mustard Stalks 1172.42 0.00 0.00 1172.42 0.00 Other Oilseeds Stalks 0.00 0.00 0.00 0.00 0.00 Vegetables Straw 591.30 591.30 0.00 0.00 0.00 49879.14 45224.61 320.61 4333.92 0.00 Rabi TOTAL Goroimari Kharif Paddy Straw 6439.66 6117.68 321.98 0.00 0.00 Maize Stalks 40.73 40.73 0.00 0.00 0.00 Cobs 6.57 0.00 0.00 6.57 0.00 Arhar Stalks 48.62 0.00 0.00 48.62 0.00 Sugarcane Tops & Leaves 99.15 99.15 0.00 0.00 0.00 Trash 66.10 0.00 0.00 66.10 0.00 Jute Stalks 752.86 0.00 0.00 752.86 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 20.34 0.00 0.00 20.34 0.00 Paddy Straw 9331.26 9331.26 0.00 0.00 0.00 Wheat Straw 497.28 497.28 0.00 0.00 0.00 Rabi 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Gram Stalks 8.57 8.57 0.00 0.00 0.00 Seasumum Stalks 26.73 0.00 0.00 26.73 0.00 Linseed Stalks 55.60 0.00 0.00 55.60 0.00 Mustard Stalks 206.51 0.00 0.00 206.51 0.00 Other Oilseeds Stalks 0.00 0.00 0.00 0.00 0.00 Vegetables Straw 423.40 423.40 0.00 0.00 0.00 18023.39 16518.07 321.98 1183.33 0.00 TOTAL Chhaygaon Kharif Paddy Straw 6405.95 6085.65 320.30 0.00 0.00 Maize Stalks 149.36 149.36 0.00 0.00 0.00 Cobs 24.09 0.00 0.00 24.09 0.00 Arhar Stalks 6.08 0.00 0.00 6.08 0.00 Sugarcane Tops & Leaves 80.70 80.70 0.00 0.00 0.00 Trash 53.80 0.00 0.00 53.80 0.00 Jute Stalks 256.66 0.00 0.00 256.66 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 9.17 9.17 0.00 0.00 0.00 Other Pulses Stalks 88.32 0.00 0.00 88.32 0.00 Paddy Straw 8961.85 8961.85 0.00 0.00 0.00 Wheat Straw 294.17 294.17 0.00 0.00 0.00 Gram Stalks 5.71 5.71 0.00 0.00 0.00 Seasumum Stalks 5.35 0.00 0.00 5.35 0.00 Linseed Stalks 37.75 0.00 0.00 37.75 0.00 Mustard Stalks 146.35 0.00 0.00 146.35 0.00 Other Oilseeds Stalks 56.45 0.00 0.00 56.45 0.00 Vegetables Straw 657.00 657.00 0.00 0.00 0.00 17238.75 16243.61 320.30 674.84 0.00 Rabi TOTAL Chandrapur Kharif 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Paddy Straw 2670.27 2483.35 186.92 0.00 0.00 Maize Stalks 0.00 0.00 0.00 0.00 0.00 Cobs 0.00 0.00 0.00 0.00 0.00 Arhar Stalks 0.00 0.00 0.00 0.00 0.00 Sugarcane Tops & Leaves 4.61 4.61 0.00 0.00 0.00 Trash 3.07 0.00 0.00 3.07 0.00 Jute Stalks 6.84 0.00 0.00 6.84 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 16.06 0.00 0.00 16.06 0.00 Paddy Straw 2348.83 2348.83 0.00 0.00 0.00 Wheat Straw 42.02 42.02 0.00 0.00 0.00 Gram Stalks 0.00 0.00 0.00 0.00 0.00 Seasumum Stalks 0.00 0.00 0.00 0.00 0.00 Linseed Stalks 6.86 0.00 0.00 6.86 0.00 Mustard Stalks 48.78 0.00 0.00 48.78 0.00 Other Oilseeds Stalks 1.51 0.00 0.00 1.51 0.00 Vegetables Straw 292.00 292.00 0.00 0.00 0.00 5440.86 5170.81 186.92 83.13 0.00 Rabi TOTAL Dimoria Kharif Paddy Straw 9665.11 9375.16 289.95 0.00 0.00 Maize Stalks 6.79 6.79 0.00 0.00 0.00 Cobs 1.10 0.00 0.00 1.10 0.00 Arhar Stalks 30.39 0.00 0.00 30.39 0.00 Sugarcane Tops & Leaves 46.12 46.12 0.00 0.00 0.00 Trash 30.74 0.00 0.00 30.74 0.00 Jute Stalks 342.21 0.00 0.00 342.21 0.00 Castor Stalks 2.19 2.19 0.00 0.00 0.00 Ground Nut Stalks 49.50 49.50 0.00 0.00 0.00 10 MW Biomass Based Power Plant Crop Name Other Pulses Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Stalks 107.06 0.00 0.00 107.06 0.00 Paddy Straw 9965.45 9965.45 0.00 0.00 0.00 Wheat Straw 170.90 170.90 0.00 0.00 0.00 Gram Stalks 28.56 28.56 0.00 0.00 0.00 Seasumum Stalks 44.55 0.00 0.00 44.55 0.00 Linseed Stalks 3.43 0.00 0.00 3.43 0.00 Mustard Stalks 170.74 0.00 0.00 170.74 0.00 Other Oilseeds Stalks 18.82 0.00 0.00 18.82 0.00 Vegetables Straw 1752.00 1752.00 0.00 0.00 0.00 22435.64 21396.66 289.95 749.03 0.00 Rabi TOTAL Chayani Barduar Kharif Paddy Straw 3893.02 3659.44 233.58 0.00 0.00 Maize Stalks 12.22 12.22 0.00 0.00 0.00 Cobs 1.97 0.00 0.00 1.97 0.00 Arhar Stalks 6.08 0.00 0.00 6.08 0.00 Sugarcane Tops & Leaves 212.13 212.13 0.00 0.00 0.00 Trash 141.42 0.00 0.00 141.42 0.00 Jute Stalks 2323.61 0.00 0.00 2323.61 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 114.02 0.00 0.00 114.02 0.00 Paddy Straw 10298.55 10298.55 0.00 0.00 0.00 Wheat Straw 253.54 253.54 0.00 0.00 0.00 Gram Stalks 10.85 10.85 0.00 0.00 0.00 Seasumum Stalks 28.51 0.00 0.00 28.51 0.00 Linseed Stalks 0.00 0.00 0.00 0.00 0.00 Mustard Stalks 291.07 0.00 0.00 291.07 0.00 Other Oilseeds Stalks 36.88 0.00 0.00 36.88 0.00 Rabi 10 MW Biomass Based Power Plant Crop Name Vegetables Residue Type Straw TOTAL ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus 292.00 292.00 0.00 0.00 0.00 17915.87 14738.74 233.58 2943.55 0.00 Boko Kharif Paddy Straw 10348.41 10037.96 310.45 0.00 0.00 Maize Stalks 305.51 305.51 0.00 0.00 0.00 Cobs 49.28 0.00 0.00 49.28 0.00 Arhar Stalks 33.42 0.00 0.00 33.42 0.00 Sugarcane Tops & Leaves 1037.61 1037.61 0.00 0.00 0.00 Trash 691.74 0.00 0.00 691.74 0.00 Jute Stalks 1129.29 0.00 0.00 1129.29 0.00 Castor Stalks 602.09 602.09 0.00 0.00 0.00 Ground Nut Stalks 311.68 311.68 0.00 0.00 0.00 Other Pulses Stalks 339.92 0.00 0.00 339.92 0.00 Paddy Straw 11464.43 11464.43 0.00 0.00 0.00 Wheat Straw 277.36 277.36 0.00 0.00 0.00 Gram Stalks 42.84 42.84 0.00 0.00 0.00 Seasumum Stalks 222.73 0.00 0.00 222.73 0.00 Linseed Stalks 147.58 0.00 0.00 147.58 0.00 Mustard Stalks 772.40 0.00 0.00 772.40 0.00 Other Oilseeds Stalks 189.66 0.00 0.00 189.66 0.00 Vegetables Straw 791.32 791.32 0.00 0.00 0.00 28757.23 24870.78 310.45 3576.00 0.00 Rabi TOTAL Bongaon Kharif Paddy Straw 6154.20 5846.49 307.71 0.00 0.00 Maize Stalks 61.10 61.10 0.00 0.00 0.00 Cobs 9.86 0.00 0.00 9.86 0.00 Arhar Stalks 21.27 0.00 0.00 21.27 0.00 Sugarcane Tops & Leaves 115.29 115.29 0.00 0.00 0.00 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Trash 76.86 0.00 0.00 76.86 0.00 Jute Stalks 1231.96 0.00 0.00 1231.96 0.00 Castor Stalks 122.61 122.61 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 61.02 0.00 0.00 61.02 0.00 Paddy Straw 7674.27 7674.27 0.00 0.00 0.00 Wheat Straw 203.12 203.12 0.00 0.00 0.00 Gram Stalks 23.42 23.42 0.00 0.00 0.00 Seasumum Stalks 29.40 0.00 0.00 29.40 0.00 Linseed Stalks 10.30 0.00 0.00 10.30 0.00 Mustard Stalks 642.31 0.00 0.00 642.31 0.00 Other Oilseeds Stalks 1.51 0.00 0.00 1.51 0.00 Vegetables Straw 416.10 416.10 0.00 0.00 0.00 16854.58 14462.39 307.71 2084.48 0.00 Rabi TOTAL Chamaria Kharif Paddy Straw 35167.51 34815.84 351.68 0.00 0.00 Maize Stalks 2.72 2.72 0.00 0.00 0.00 Cobs 0.44 0.00 0.00 0.44 0.00 Arhar Stalks 351.25 0.00 0.00 351.25 0.00 Sugarcane Tops & Leaves 182.16 182.16 0.00 0.00 0.00 Trash 121.44 0.00 0.00 121.44 0.00 Jute Stalks 5998.94 0.00 0.00 5998.94 0.00 Castor Stalks 2.19 2.19 0.00 0.00 0.00 Ground Nut Stalks 3.67 3.67 0.00 0.00 0.00 Other Pulses Stalks 341.52 0.00 0.00 341.52 0.00 Paddy Straw 8223.04 8223.04 0.00 0.00 0.00 Wheat Straw 1822.44 1822.44 0.00 0.00 0.00 Gram Stalks 22.85 22.85 0.00 0.00 0.00 Rabi 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Seasumum Stalks 203.13 0.00 0.00 203.13 0.00 Linseed Stalks 92.66 0.00 0.00 92.66 0.00 Mustard Stalks 1868.39 0.00 0.00 1868.39 0.00 Other Oilseeds Stalks 45.91 0.00 0.00 45.91 0.00 Vegetables Straw 299.30 299.30 0.00 0.00 0.00 54749.55 45374.20 351.68 9023.68 0.00 TOTAL Rani Kharif Paddy Straw 9440.34 9157.13 283.21 0.00 0.00 Maize Stalks 0.00 0.00 0.00 0.00 0.00 Cobs 0.00 0.00 0.00 0.00 0.00 Arhar Stalks 145.85 0.00 0.00 145.85 0.00 Sugarcane Tops & Leaves 830.09 830.09 0.00 0.00 0.00 Trash 553.39 0.00 0.00 553.39 0.00 Jute Stalks 1711.05 0.00 0.00 1711.05 0.00 Castor Stalks 153.26 153.26 0.00 0.00 0.00 Ground Nut Stalks 751.69 751.69 0.00 0.00 0.00 Other Pulses Stalks 107.06 0.00 0.00 107.06 0.00 Paddy Straw 8112.00 8112.00 0.00 0.00 0.00 Wheat Straw 714.41 714.41 0.00 0.00 0.00 Gram Stalks 0.00 0.00 0.00 0.00 0.00 Seasumum Stalks 89.09 0.00 0.00 89.09 0.00 Linseed Stalks 267.70 0.00 0.00 267.70 0.00 Mustard Stalks 926.88 0.00 0.00 926.88 0.00 Other Oilseeds Stalks 374.79 0.00 0.00 374.79 0.00 Vegetables Straw 708.10 708.10 0.00 0.00 0.00 24885.70 20426.68 283.21 4175.81 0.00 Rabi TOTAL Rampur Kharif 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Paddy Straw 4508.89 4238.35 270.53 0.00 0.00 Maize Stalks 13.58 13.58 0.00 0.00 0.00 Cobs 2.19 0.00 0.00 2.19 0.00 Arhar Stalks 6.08 0.00 0.00 6.08 0.00 Sugarcane Tops & Leaves 255.94 255.94 0.00 0.00 0.00 Trash 170.63 0.00 0.00 170.63 0.00 Jute Stalks 817.88 0.00 0.00 817.88 0.00 Castor Stalks 1.09 1.09 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 120.98 0.00 0.00 120.98 0.00 Paddy Straw 7236.53 7236.53 0.00 0.00 0.00 Wheat Straw 224.13 224.13 0.00 0.00 0.00 Gram Stalks 6.28 6.28 0.00 0.00 0.00 Seasumum Stalks 30.29 0.00 0.00 30.29 0.00 Linseed Stalks 0.00 0.00 0.00 0.00 0.00 Mustard Stalks 266.68 0.00 0.00 266.68 0.00 Other Oilseeds Stalks 30.86 0.00 0.00 30.86 0.00 Vegetables Straw 354.78 354.78 0.00 0.00 0.00 14046.81 12330.69 270.53 1445.58 0.00 Rabi TOTAL Bezera Kharif Paddy Straw 7228.60 7011.75 216.86 0.00 0.00 Maize Stalks 8.15 8.15 0.00 0.00 0.00 Cobs 1.31 0.00 0.00 1.31 0.00 Arhar Stalks 7.29 0.00 0.00 7.29 0.00 Sugarcane Tops & Leaves 48.42 48.42 0.00 0.00 0.00 Trash 32.28 0.00 0.00 32.28 0.00 Jute Stalks 85.55 0.00 0.00 85.55 0.00 Castor Stalks 4.38 4.38 0.00 0.00 0.00 Ground Nut Stalks 91.67 91.67 0.00 0.00 0.00 10 MW Biomass Based Power Plant Crop Name Other Pulses Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Stalks 133.83 0.00 0.00 133.83 0.00 Paddy Straw 9433.76 9433.76 0.00 0.00 0.00 Wheat Straw 270.35 270.35 0.00 0.00 0.00 Gram Stalks 2.28 2.28 0.00 0.00 0.00 Seasumum Stalks 133.64 0.00 0.00 133.64 0.00 Linseed Stalks 5.49 0.00 0.00 5.49 0.00 Mustard Stalks 123.58 0.00 0.00 123.58 0.00 Other Oilseeds Stalks 17.31 0.00 0.00 17.31 0.00 Vegetables Straw 319.74 319.74 0.00 0.00 0.00 17947.64 17190.50 216.86 540.28 0.00 Rabi TOTAL Kamalpur Kharif Paddy Straw 2989.44 2780.18 209.26 0.00 0.00 Maize Stalks 2.72 2.72 0.00 0.00 0.00 Cobs 0.44 0.00 0.00 0.44 0.00 Arhar Stalks 1.22 0.00 0.00 1.22 0.00 Sugarcane Tops & Leaves 20.75 20.75 0.00 0.00 0.00 Trash 13.83 0.00 0.00 13.83 0.00 Jute Stalks 17.11 0.00 0.00 17.11 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 22.00 22.00 0.00 0.00 0.00 Other Pulses Stalks 112.95 0.00 0.00 112.95 0.00 Paddy Straw 9247.98 9247.98 0.00 0.00 0.00 Wheat Straw 89.65 89.65 0.00 0.00 0.00 Gram Stalks 13.71 13.71 0.00 0.00 0.00 Seasumum Stalks 21.38 0.00 0.00 21.38 0.00 Linseed Stalks 27.46 0.00 0.00 27.46 0.00 Mustard Stalks 125.21 0.00 0.00 125.21 0.00 Other Oilseeds Stalks 7.53 0.00 0.00 7.53 0.00 Rabi 10 MW Biomass Based Power Plant Crop Name Vegetables Residue Type Straw TOTAL ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus 300.76 300.76 0.00 0.00 0.00 13014.13 12477.75 209.26 327.12 0.00 Rangia Kharif Paddy Straw 30433.86 30129.52 304.34 0.00 0.00 Maize Stalks 411.41 411.41 0.00 0.00 0.00 Cobs 66.36 0.00 0.00 66.36 0.00 Arhar Stalks 8.51 0.00 0.00 8.51 0.00 Sugarcane Tops & Leaves 156.79 156.79 0.00 0.00 0.00 Trash 104.53 0.00 0.00 104.53 0.00 Jute Stalks 99.24 0.00 0.00 99.24 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 180.93 0.00 0.00 180.93 0.00 Paddy Straw 16548.58 16548.58 0.00 0.00 0.00 Wheat Straw 703.20 703.20 0.00 0.00 0.00 Gram Stalks 69.12 69.12 0.00 0.00 0.00 Seasumum Stalks 33.85 0.00 0.00 33.85 0.00 Linseed Stalks 0.00 0.00 0.00 0.00 0.00 Mustard Stalks 1253.72 0.00 0.00 1253.72 0.00 Other Oilseeds Stalks 0.00 0.00 0.00 0.00 0.00 Vegetables Straw 1954.94 1954.94 0.00 0.00 0.00 52025.04 49973.56 304.34 1747.14 0.00 Rabi TOTAL Goreswar Kharif Paddy Straw 25320.34 25067.14 253.20 0.00 0.00 Maize Stalks 32.59 32.59 0.00 0.00 0.00 Cobs 5.26 0.00 0.00 5.26 0.00 Arhar Stalks 17.62 0.00 0.00 17.62 0.00 Sugarcane Tops & Leaves 371.23 371.23 0.00 0.00 0.00 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Trash 247.49 0.00 0.00 247.49 0.00 Jute Stalks 1871.89 0.00 0.00 1871.89 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 53.17 53.17 0.00 0.00 0.00 Other Pulses Stalks 55.14 0.00 0.00 55.14 0.00 Paddy Straw 12151.99 12151.99 0.00 0.00 0.00 Wheat Straw 245.14 245.14 0.00 0.00 0.00 Gram Stalks 11.42 11.42 0.00 0.00 0.00 Seasumum Stalks 59.69 0.00 0.00 59.69 0.00 Linseed Stalks 83.74 0.00 0.00 83.74 0.00 Mustard Stalks 1780.58 0.00 0.00 1780.58 0.00 Other Oilseeds Stalks 22.58 0.00 0.00 22.58 0.00 Vegetables Straw 386.90 386.90 0.00 0.00 0.00 42716.77 38319.58 253.20 4143.98 0.00 Rabi TOTAL Bihdia Jajikona Kharif Paddy Straw 6268.84 5955.39 313.44 0.00 0.00 Maize Stalks 9.50 9.50 0.00 0.00 0.00 Cobs 1.53 0.00 0.00 1.53 0.00 Arhar Stalks 10.94 0.00 0.00 10.94 0.00 Sugarcane Tops & Leaves 225.97 225.97 0.00 0.00 0.00 Trash 150.65 0.00 0.00 150.65 0.00 Jute Stalks 431.18 0.00 0.00 431.18 0.00 Castor Stalks 6.57 6.57 0.00 0.00 0.00 Ground Nut Stalks 45.84 45.84 0.00 0.00 0.00 Other Pulses Stalks 377.39 0.00 0.00 377.39 0.00 Paddy Straw 20915.26 20915.26 0.00 0.00 0.00 Wheat Straw 110.66 110.66 0.00 0.00 0.00 Gram Stalks 2.86 2.86 0.00 0.00 0.00 Rabi 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Seasumum Stalks 60.58 0.00 0.00 60.58 0.00 Linseed Stalks 51.48 0.00 0.00 51.48 0.00 Mustard Stalks 500.84 0.00 0.00 500.84 0.00 Other Oilseeds Stalks 42.15 0.00 0.00 42.15 0.00 Vegetables Straw 421.94 421.94 0.00 0.00 0.00 29634.17 27693.99 313.44 1626.73 0.00 TOTAL MORIGAON DISTRICT Mayong Kharif Paddy Straw 26273.37 25747.90 525.47 0.00 0.00 Maize Stalks 74.68 74.68 0.00 0.00 0.00 Cobs 12.05 0.00 0.00 12.05 0.00 Arhar Stalks 3.04 0.00 0.00 3.04 0.00 Sugarcane Tops & Leaves 265.17 265.17 0.00 0.00 0.00 Trash 176.78 0.00 0.00 176.78 0.00 Jute Stalks 1779.49 0.00 0.00 1779.49 0.00 Castor Stalks 10.95 10.95 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 6.96 0.00 0.00 6.96 0.00 Paddy Straw 41435.50 41435.50 0.00 0.00 0.00 Wheat Straw 525.30 525.30 0.00 0.00 0.00 Gram Stalks 8.00 8.00 0.00 0.00 0.00 Seasumum Stalks 218.27 0.00 0.00 218.27 0.00 Linseed Stalks 75.50 0.00 0.00 75.50 0.00 Mustard Stalks 1213.07 0.00 0.00 1213.07 0.00 Other Oilseeds Stalks 323.62 0.00 0.00 323.62 0.00 Vegetables Straw 1284.80 1284.80 0.00 0.00 0.00 73686.53 69352.28 525.47 3808.78 0.00 Rabi TOTAL Moriabari Kharif 10 MW Biomass Based Power Plant Crop Name Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Paddy Straw 3322.10 3023.11 298.99 0.00 0.00 Maize Stalks 0.00 0.00 0.00 0.00 0.00 Cobs 0.00 0.00 0.00 0.00 0.00 Arhar Stalks 3.04 0.00 0.00 3.04 0.00 Sugarcane Tops & Leaves 1579.47 1579.47 0.00 0.00 0.00 Trash 1052.98 0.00 0.00 1052.98 0.00 Jute Stalks 1485.19 0.00 0.00 1485.19 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 27.50 27.50 0.00 0.00 0.00 Other Pulses Stalks 26.77 0.00 0.00 26.77 0.00 Paddy Straw 20990.00 20990.00 0.00 0.00 0.00 Wheat Straw 535.11 535.11 0.00 0.00 0.00 Gram Stalks 0.00 0.00 0.00 0.00 0.00 Seasumum Stalks 69.49 0.00 0.00 69.49 0.00 Linseed Stalks 51.48 0.00 0.00 51.48 0.00 Mustard Stalks 424.41 0.00 0.00 424.41 0.00 Other Oilseeds Stalks 0.00 0.00 0.00 0.00 0.00 Vegetables Straw 137.24 137.24 0.00 0.00 0.00 29704.78 26292.43 298.99 3113.36 0.00 Rabi TOTAL Laharighat Kharif Paddy Straw 19829.21 19333.48 495.73 0.00 0.00 Maize Stalks 0.00 0.00 0.00 0.00 0.00 Cobs 0.00 0.00 0.00 0.00 0.00 Arhar Stalks 0.00 0.00 0.00 0.00 0.00 Sugarcane Tops & Leaves 447.33 447.33 0.00 0.00 0.00 Trash 298.22 0.00 0.00 298.22 0.00 Jute Stalks 10266.30 0.00 0.00 10266.30 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 293.34 293.34 0.00 0.00 0.00 10 MW Biomass Based Power Plant Crop Name Other Pulses Residue Type ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus Stalks 54.60 0.00 0.00 54.60 0.00 Paddy Straw 27763.17 27763.17 0.00 0.00 0.00 Wheat Straw 491.68 491.68 0.00 0.00 0.00 Gram Stalks 57.12 57.12 0.00 0.00 0.00 Seasumum Stalks 160.36 0.00 0.00 160.36 0.00 Linseed Stalks 49.42 0.00 0.00 49.42 0.00 Mustard Stalks 538.24 0.00 0.00 538.24 0.00 Other Oilseeds Stalks 34.62 0.00 0.00 34.62 0.00 Vegetables Straw 438.00 438.00 0.00 0.00 0.00 60721.61 48824.12 495.73 11401.76 0.00 Rabi TOTAL Bhurbandha Kharif Paddy Straw 5421.45 4987.74 433.72 0.00 0.00 Maize Stalks 0.00 0.00 0.00 0.00 0.00 Cobs 0.00 0.00 0.00 0.00 0.00 Arhar Stalks 6.08 0.00 0.00 6.08 0.00 Sugarcane Tops & Leaves 461.16 461.16 0.00 0.00 0.00 Trash 307.44 0.00 0.00 307.44 0.00 Jute Stalks 2898.52 0.00 0.00 2898.52 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 33.19 0.00 0.00 33.19 0.00 Paddy Straw 29514.12 29514.12 0.00 0.00 0.00 Wheat Straw 271.76 271.76 0.00 0.00 0.00 Gram Stalks 0.00 0.00 0.00 0.00 0.00 Seasumum Stalks 337.65 0.00 0.00 337.65 0.00 Linseed Stalks 65.21 0.00 0.00 65.21 0.00 Mustard Stalks 939.89 0.00 0.00 939.89 0.00 Other Oilseeds Stalks 0.00 0.00 0.00 0.00 0.00 Rabi 10 MW Biomass Based Power Plant Crop Name Vegetables Residue Type Straw TOTAL ABEIL Biomass Generation Biomass Consumption Fodder Thatching Domestic fuel Collectable Surplus 138.70 138.70 0.00 0.00 0.00 40395.15 35373.47 433.72 4587.97 0.00 Kapili Kharif Paddy Straw 3515.40 3199.02 316.39 0.00 0.00 Maize Stalks 0.00 0.00 0.00 0.00 0.00 Cobs 0.00 0.00 0.00 0.00 0.00 Arhar Stalks 0.00 0.00 0.00 0.00 0.00 Sugarcane Tops & Leaves 106.07 106.07 0.00 0.00 0.00 Trash 70.71 0.00 0.00 70.71 0.00 Jute Stalks 8161.71 0.00 0.00 8161.71 0.00 Castor Stalks 0.00 0.00 0.00 0.00 0.00 Ground Nut Stalks 0.00 0.00 0.00 0.00 0.00 Other Pulses Stalks 173.44 0.00 0.00 173.44 0.00 Paddy Straw 6484.91 6484.91 0.00 0.00 0.00 Wheat Straw 145.68 145.68 0.00 0.00 0.00 Gram Stalks 0.00 0.00 0.00 0.00 0.00 Seasumum Stalks 33.85 0.00 0.00 33.85 0.00 Linseed Stalks 0.00 0.00 0.00 0.00 0.00 Mustard Stalks 1328.52 0.00 0.00 1328.52 0.00 Other Oilseeds Stalks 0.00 0.00 0.00 0.00 0.00 Vegetables Straw 211.70 211.70 0.00 0.00 0.00 20231.99 10147.37 316.39 9768.23 0.00 Rabi TOTAL 3.6.2 Biomass Surplus from Agro-industries The only biomass available in surplus from agro industries is rice husk. Other biomass generated from agro industries is fully consumed in industrial and other sectors. The district wise surplus biomass available is given in the table below. 10 MW Biomass Based Power Plant ABEIL 3.21 District wise Biomass Surplus from Agro-industries in Tons District 3.6.3 Rice Husk Total Kamrup 30524 30524 Morigaon 14806 14806 Grand total 45330 45330 Biomass Surplus from Forest and other land The following table gives the details regarding the biomass available from the forest and other wasteland within districts is given below. 3.22 District wise Biomass Surplus from Forest and other land in Tons District Surplus Wood Kamrup 110805 110805 5781 5781 116586 116586 Morigaon Grand total 3.6.4 Total Summary of Surplus Biomass Availability The following table gives the summary of surplus biomass from different sources within the district. 3.23 Summary of surplus biomass in Tons Districts 3.7 Crop residue Forest and other land Agroindustry Total Kamrup 0.00 110805 30524 141329 Morigaon 0.00 5781 14806 20587 Grand total 0.00 116586 45330 161916 POWER GENERATION POTENTIAL The surplus available for the power generation purpose is 161916 tons/year, which mainly consists of the wood from the forestlands and rice husk. 10 MW Biomass Based Power Plant ABEIL The power potential available with the surplus wood is about 11.66 MW, and with the Agroindustries residues i.e rice husk is about 4.53 MW. The total power potential available in Kamrup and Morigaon districts is 16.19 MW. 3.8 BIOMASS CHARACTERISTICS, AVAILABILITY AND COST 3.8.1 Biomass Characteristics Biomass is a renewable source of energy that can be made use of effectively for thermal as well as electrical energy generation. All the processes in which biomass is used as fuel have a definite bearing on the properties of the biomass material. Thus the characterization of biomass material is essential. The characterization of biomass involves the Proximate and Ultimate Analysis. 3.8.1.1 Proximate Analysis The proximate analysis gives the proxy information of biomass constituents such as moisture, volatiles, fixed carbon and ash content. The carbon content determined through this method is not actual carbon content in the biomass but only the non-volatile part of carbon content, some of the carbon present in the biomass escapes along with volatiles. The proximate analysis of some biomass is given in the table. Calorific Value (kcal/kg) Ash (%) Paddy straw 3730 15.50 68.30 16.20 Wheat straw 4146 7.70 80.60 11.70 Maize Stalks 3200 to 3800 1 to 20 60 to 85 10 to 20 Mustard stalk 4178 4.90 78.00 17.10 Cane trash 4120 10.90 70.40 18.70 3700 to 4200 1 to 3 70 to 85 15 to 20 3200 19.20 66.20 14.60 Biomass Wood Rice husk Volatile Fixed matter (%) Carbon (%) 3.8.1.2 Ultimate Analysis The ultimate analysis involves the determination of the elemental composition of the fuel i.e. carbon, nitrogen, oxygen, hydrogen, sulphur etc. The determination of the total carbon and 10 MW Biomass Based Power Plant ABEIL hydrogen and their (C/H) ratio gives an indication of the type of volatiles present in the biomass i.e. saturated or unsaturated hydrocarbons which governs the tar formation. The ultimate analysis of some biomass is given in the table. Biomass Oxygen (%) Ash (%) Paddy straw 35.97 5.28 0.17 43.08 15.50 Mustard Stalks 40.89 5.92 6.37 39.12 7.70 Maize Stalk 35 to 40 6 to 8 0.5 to 1 50 to 55 1 to 20 Cane trash 39.75 5.55 0.17 46.82 7.71 5 to 7 0.5 to 0.9 40 to 48 1 to 3 35.88 22.20 Wood Rice husk 3.8.2 Carbon Hydrogen Nitrogen (%) (%) (%) 45 to 50 36.42 4.91 0.59 Biomass Collection, handling, and preparation: As mentioned earlier, biomass is generated from crop residues, agro industry, barren and forest lands. The biomass obtained as crop residue and agro industry residue will have low bulk density. The type of crop residue generated depends on the crop and also harvesting methods. For example, if combines are used for harvesting of paddy crop, almost 5% of straw is left in the field. The harvested straw is in the form of powder with low bulk density. This straw needs to densified using briquetting technique. The straw left in the field, needs manual harvesting. Manual harvested straw can be densified using bailing. If the paddy crop can be harvested manual, total straw can be collected and can be efficiently used. Wheat straw is also being harvested similarly. Residue from oil seeds and pulses are brittle woody type. This type of material needs mechanism to break into pieces of 2 to 6 inches. Usually choppers are used for this purpose. Biomass obtained from energy plantation or wood from forest and barren land needs special attention of preparation. This material is heavy and transportation problems are less compared with low bulk residues. Depending on the size and quality of material, shredders, cutters, choppers and chippers can be used. 10 MW Biomass Based Power Plant 3.8.3 ABEIL Seasonal Biomass Availability and Cost The major crops in this area are paddy, maize wheat, sugarcane and barley. The residues from these crops like from these crops like paddy straw, wheat straw, maize stalks are used as fodder. Maize cobs, cane trash, Til and Mustard stalks are used as domestic fuel. Rice husk and Wood are the major biomass available this area which is used for industrial purpose and domestic. After the consumption of different biomasses in various sectors cane trash, Mustard and Til stalks, Maize cobs, wood and rice husk are available in surplus quantity, which can be used for power generation. As the power plant start working, biomass prices may increase to tune to 5 to 10 % in the offseason. 3.8.4 Transportation Modes Tractor trolleys and bullock carts are the most important means of transport available with farmers. The farmers are having adequate means for the transportation of the biomass. Different modes of transport like head load, hand carts, bullock carts, tractors, trucks etc. are used for the wood transportation. Wood in large quantity is transported either by means of tractor or trucks. While for transporting small quantity handcarts or bullock carts are used. 3.8.4.1 Bullock Carts In rural areas, bullock cart has been the most common mode of transport. Although tractor trolleys have also been adopted but still bullock cart is quite common particularly with the small and medium farms even now. Farmers usually do not charge for hiring of bullock carts. 3.8.4.2 Tractor Trolleys All the tractor owners do not own a trolley. As such special four-wheel wagons can be developed which may carry large quantity of crop residue stalks and wood. One such wagon, having capacity of 3-5 tones of crop residue stalks and 5-7 tones of wood. This capacity is less than that of a truck. The initial cost of a wagon and trolley is Rs. 25000 and Rs. 20000 respectively. 3.8.4.3 Trucks 10 MW Biomass Based Power Plant ABEIL Trucks are not at all common in rural areas for transport of agricultural wastes. However, for handling large volumes of arhar stalks, the use of trucks may become necessary because of time factor. These are fast moving vehicles. The capacity of a truck as mentioned above is about 5-7 tonnes for crop residue stalks and about 8-10 tonnes for Wood. 3.8.5 Storage Approximate biomass balance for year replicates the biomass is available in surplus in large quantity only in the month of harvesting. This large surplus biomass quantity has to be stored and should be used for rest of the year. Hence this biomass has to be procured in these months and stored. The following points may be taken into account while planning storage facilities: A well-drained site may be chosen. Leave at least 40 cms. Space between each stack to ensure proper drainage and ventilation. Plan different storage sites as a safety precaution against the fire. Ample fireguards and precautions may be taken at each of the site. There should be adequate natural ventilation arrangements and no natural shade of any kind should be near the stacks. On storage, the ash content increase, volatile matter decrease, fixed carbon increases and no appreciable change on tone of material. The loss of VM is to be corrected with loss of weight. 3.9 BIOMASS REQUIREMENT: Biomass Power plant will be operating at a PLF of 90% anf the rice husk requirement will be 108405 MT per annum. 3.10 CATEGORY WISE BIOMASS AVAILABLE: The category wise biomass available from different sources is shown in the table below 3.25 Category wise availability of Biomass 10 MW Biomass Based Power Plant Biomass Type ABEIL Residue Biomass Available Agro Residue Rice Husk Husk 45330 Wood 116586 Forest & other lands Wood Grand Total 3.10 161916 AVERAGE COST OF BIOMASS: The average cost of the biomass is taken as Rs.1500 per ton,as per current rates with annual escalation of 5%. . 10 MW Biomass Based Power Plant ABEIL 4. PLANT AND EQUIPMENT DESIGN CRITERIA 4.0 GENERAL This power plant will be using the combustion technology. The basic steps involve, biomass handling, boiler, turbo generator and evacuation system. Power generation is having direct bearing on the pressure and superheated temperature of steam. Normally 67 bar and 490 Deg C, is used for biomass based power plants. Clearly, the technological improvements can allow us to recover and put to use the energy, which would otherwise be wasted. In that process, the need for new energy projects can be reduced, resources can be preserved, and energy costs and environmental damage can be minimized, and these benefits can be the greatest when abundant renewable biomass is the power generation fuel. High pressure and high temperature cycles are crucial for increasing the operating efficiency and the power output from the Biomass Power Plants. The choice of the level of the pressure and temperature for the cycle depends on the level of confidence in the plant operators, quality of the feed water and the water treatment systems available and the cost of the high pressure/ temperature boiler and Turbo generator systems and the financial benefits realizable from the power plant by way of the sale of the exportable power. Thermodynamically, energy recovery from the Rankine Cycle is more dependent on the steam inlet temperature than the pressure and the higher the inlet steam temperature, higher the cycle efficiency. However, the practically attainable limits of temperatures are influenced by the metallurgy of the boiler tubing, piping and the turbine components and the complexity of the Creep fatigue interaction for the materials at higher temperatures. Temperatures upto 400 0C require the use of ordinary carbon steel and beyond 400 0C low alloy steels are employed. Above 500 0C, the requirements become stringent and expensive and above 550 0C, the requirements are very stringent and prohibitively expensive. It is extremely important that the selection of the temperature is done keeping in mind the nature of the industry. Considerations such as cost, maintainability, provision of adequate safety margins, the experience of the industry so far and the level of the operating personnel available in the industry, force us to a selection of around 485 0C as the practical limit for the steam temperatures. It is also important to keep in mind that the superheated steam temperature response is a little erratic, even with a good steam temperature control system, 10 MW Biomass Based Power Plant ABEIL mainly because of the nature of the fuel and the difficulty to ensure a correctly metered quantity of fuel flow to the boiler. From this point of view also 485 0C is a safe selection. Looking from purely the Cycle Efficiency point of view, with the selection of 485 0C as the steam temperature, the Thermodynamics laws, typical construction of the turbine blading and the practical extent of steam expansion possible in the turbines, dictate the limits of cycle pressure. Keeping the above temperature, there is a little thermodynamic efficiency advantage to be gained by pressures exceeding 67 ata. The cycle parameters are decided as 64 Ata and 480 0C at the turbine throttle valve inlet. Correspondingly the boiler outlet parameters shall be 67 Ata and 485 0C, accounting for the pressure and temperature losses in the piping. As the proposed power plant will be operating with the boiler outlet steam parameters of 67 Ata and 485 5 0C, a feed water management program will be implemented whereby the complete feed water requirements of the boiler will be met essentially by the condensate. The steam Condensate will be available at 450C and will be directly used in the feed water circuit, although with certain monitoring for certain circuits. The make up for the plant operation will be demineralized water and a Demineralized water treatment plant of adequate capacity will be provided. The boiler being proposed for the biomass power plant, will be with the steam parameters of 67 Ata and 485 5 0C at the boiler outlet. The boiler will be designed with a travelling grate with electric drive to burn the biomass. The steam to biomass percentage will be achieved with a minimum efficiency of 80 % with the dried biomass. The power generation turbine will be a condensing machine. The turbine steam inlet parameters will be 64 ata and 480 0C. The power plant will be operating for nearly 330 days. The boiler will be operating on 100 % of each biomass and also in combination of various biomasses. The power generation cycle will be provided with a deaerator serving the dual purpose of deaerating the feed water as well as heating the feed water with the extraction steam. The deaerator will be operating at 2.7 ata pressure, with the deaerated feed water temperature at 105 0C. The power generation in the turbo generator will be at 11 kV level. The turbo 10 MW Biomass Based Power Plant ABEIL generator will be operating in parallel with the ASEB Grid. The entire power requirements of the plant and the power requirements of the auxiliaries amounting to 1 MW(approx) of the power plant will be met by the power generated in the new turbogenerator. The balance of the power generated i.e.10 MW in the plant will be exported to the grid. The exportable power will be stepped up to 132 kV and will be connected to Jagi Road substation 132/11 kV of ASEB located at 1-2 kms distance. Adequate space and transformer capacities are available at the sub-station, for receiving the exportable quantum of power from the power plant. All the plant and systems shall be designed to achieve the best possible efficiency under the specified operating conditions. The power plant cycle shall be designed with one Deaerator for feed water heating. The steam requirements of the deaerator shall be met with the extraction from the turbine & low load PRDS. The complete plant instrumentation and control system shall be based on Distributed Control System (DCS) philosophy, covering the total functioning requirements of measuring, monitoring, alarming and controlling, logging, sequence interlocks and equipment protection etc. The ash collection points are, Grate ash from the furnace bottom and fly ash from the Air Heaters and Electro Static Precipitator hoppers. Ash handling system will have a combination of submerged scrapper conveyor or pneumatic conveyors. All the ash shall be taken and stored in bins and disposed off in trucks to be used as landfill or to be used as nutrients to the fields, or to be disposed of to Brick Kiln Owners. The optimum arrangement of the equipment shall be determined by the consideration of functional requirements, economy of equipment supports, installation and maintenance access requirements. This section of the report gives the basic criteria for design of the power plant. The design parameters like the size, layout, ratings, quantities, materials of construction, type of equipment etc., described in this report are approximate. Necessary changes could occur as the detailed engineering of the plant progresses, and such changes are permitted as long as the detailed engineering of the plant achieves the intent of this scheme. 10 MW Biomass Based Power Plant 4.1 AMBIENT CONDITIONS Plant Elevation above Mean Sea Level (MSL) 4.1.1 : As per IS: 875 Seismic Coefficient Design 4.2 : 1500 -2600 mm Wind Design and velocity 4.1.5 : 85.0 % : 45.0 % : 60.0 % Precipitation Total Annual Rainfall 4.1.4 : 37 °C : 7 °C : 30 °C : 35 °C : 27 °C : 45 °C Relative Humidity Maximum Minimum Plant design relative humidity 4.1.3 : 262 meters Temperatures Maximum day temperature Minimum day temperature Average day temperature Plant design temperature (dry bulb) Plant design wet bulb temperature Plant design temperature for electrical equipment 4.1.2 ABEIL : As per IS: 893 DESIGN AND GUARANTEE FUEL The design and guarantee fuel for the power plant is rice husk and wood. Detailed availability is given in Chapter 3. 4.3 RAW WATER The raw water supply will be from canal / bore wells. The distance of canal from power plant is 2 Kms. This raw water is used as a makeup of the losses in the boiler blow down, cooling tower blow down, service water etc. The raw water requirement for power plant is 1980 KL per day. Borewells are to be dug. The raw water will be analyzed. 10 MW Biomass Based Power Plant 4.4 MAIN PLANT AND EQUIPMENT 4.4.1 Steam Generator & Auxiliaries ABEIL The steam generating system for the power plant will use biomass collected from the fields, sugar industry, and rice mills. Boiler will be designed to fire the biomass like cotton stalks, and mustard stalks from crops, with a Maximum Continuous Rating (MCR) of 50 tph, with the outlet steam parameters at 67 Ata and 485°C. The variation on the superheater outlet temperature shall be ± 5 °C. The combustion system of the boiler shall be travelling grate with spreader stoker. The boiler efficiency, firing 100% mustard stalks, shall be a minimum of 80.0 % on the GCV basis. The dust concentration in the flue gases leaving the boiler shall be a maximum of 115 mg/Nm³. The design of the boiler shall be of bi-drum, natural circulation; radiant furnace with water cooled membrane walls, two-stage superheater with interstage desuperheater and balanced draft. The boiler shall be top supported and shall be semi-outdoor type. The boiler shall be capable of a peak generation of 110% of the MCR generation for a period of one (1) hour in a shift. The operating excess air percentage at the outlet of the boiler shall be less than 30%. 1) Boiler Feed Water The boiler shall be capable of operating with the following feed water quality requirements pH : 8.8-9.2 Oxygen : 0.005 ppm Hardness :0 Total Iron : 0.01 ppm Total Copper : 0.01 ppm Total Silica : 0.02 ppm Hydrazine : 0.01-0.02 ppm Specific electrical conductivity : 0.5 micro ohms / cm At 25 °C measured after cation exchanger in the H + form and after CO2 removal (max) 2) Steam Purity The boiler shall be capable of supplying uninterrupted steam at the MCR rating with following steam purity levels. * Total dissolved solids * Silica (max) : : 0.1 ppm (max) 0.02 ppm 10 MW Biomass Based Power Plant 3) ABEIL Performance Guarantee Tests Boiler efficiency at MCR on GCV basis while firing mustard stalks. Boiler efficiency at MCR on GCV basis while firing cotton stalks. Auxiliary power consumption under MCR operating conditions. Steam purity for all operating loads. Dust concentration in the flue gases leaving the ESP, while firing rice husk. The boiler will be of multifuel type, with provision to burn individual biomass with 100%. The Stack shall be of RCC construction, 50 mtr high with total internal refractory brick lining. 4.4.2 Turbo generator & Auxiliaries The turbo generator shall be a bleed cum condensing machine. The bleed shall be at 2.5 Ata. The following shall be the salient design parameters. The speed of the turbine shall be approx. 8000 rpm. Steam flow at the turbine stop valve at turbine MCR (kg/hr) Steam pressure at the turbine stop valve (Ata) Steam temperature at the turbine stop valve (°C) Condenser operating pressure (Ata) Condenser cooling water inlet temperature (°C) Power Factor (lagging) Generation voltage (kV) Ambient temperature for electrical equipment design (°C) Parallel operation with grid Grid voltage Duty requirements Condenser sizing System frequency Atmospheric Conditions Maximum noise pressure levels at 1.0 mtr distance for any Equipment from the Equipment surface shall be equal to or Less than db (A) 4.4.3 : 50,000 : 64 : 480 : 0.1 : 32.0 : 0.8 : 11.0 + 10% : 45.0 : Required with ASEB grid. : 132 kV : Continuous 8000 hrs. : 30 tph : 50 ± 5% Hz : Dusty : 85 dB(A) Performance Guarantee Tests The performance test shall be conducted for the following parameters as per ASME PTC 6 and DIN 1943. Power output at generator terminals with the inlet steam parameters of 64 Ata and 480°C specified power factor and cooling water inlet temperature of 32°C. Both the extractions shall be at the indicated Normal flow conditions. Uncontrolled extraction pressure and temperature with the inlet steam parameters of 64 Ata and 480 °C. Auxiliary power consumption under guaranteed conditions. 10 MW Biomass Based Power Plant ABEIL Cooling water consumption under guaranteed conditions. Maximum temperature rise in the generator windings. Heat rate under guaranteed conditions. 4.5 AUXILIARY PLANT AND EQUIPMENT 4.5.1 Biomass Handling The fuel for the power plant is a rice husk and wood. There will be one separate bunker for husk and wood. The fuel from the storage is conveyed to the boiler by a combination of belt conveyors. The system shall have provision for returning the excess fuel to the storage yard from the boiler. The fuel handling system shall be designed for a capacity of 16 TPH. Allowable inclination for the belt conveyors is 18°. The belt speed shall be approximately 1.0 m/sec. 4.5.2 Ash Handling The ash handling system envisaged for the power plant is of two types: Gravity system for fly ash Pneumatic System. The ash handling system shall be designed to take care of 100% biomass burning. The total ash quantity generated in the boiler, by the burning of husk is approximately 1875 kg/hr. This ash content is maximum, as wood will generate only 280 kgs/hr of ash. Ash removed from the grate is approximately 750 kg/hr and the fly ash quantity is approximately 1125 kg/hr. The ash density is 120 kg/m³. The ash received in the grate discharge hoppers will be around 500°C, with ash lumps of size 200 mm maximum. The ash from ash ridding hopper will be dry and powdery in nature and occasionally with hot solids. The temperature of the ash will be around 200°C maximum. The fly ash from Electrostatic Precipitator Hoppers will be dry and powdery in nature and occasionally with hot solids. The temperature of ash will be around 200°C maximum. The fly ash from the Air Heater Hopper will be dry and powdery in nature and occasionally with hot solids. The temperature of the ash will be around 250°C maximum. 10 MW Biomass Based Power Plant 4.5.2 ABEIL Cooling Tower The cooling tower shall be RCC counter flow induced draft cooling tower of capacity of 1800 m³/hr capacity having two (2) cells. The cooling tower shall be designed for a cooling range of 8°C, and an approach of 5 °C while operating under the atmospheric wet bulb temperature of about 27°C. The cooling tower shall be of RCC construction. The RCC frame of the tower shall be integral with the basin. The structure shall be designed for wind and other load as per IS: 875 and earthquake resistance as per IS: 1893. The cooling tower shall be carefully sited such that there is no re-entertainment of the vapors in to the cooling tower. 4.5.3 Pumps The head/flow characteristic of pumps will be such that the head continuously rises with decreasing capacity until a maximum head is reached at zero flow. Maximum runout flow should at least be 130% of duty point flow. The shut off head should be at least 1.1 times the duty point head and should not be more than 1.2 times the duty point head. The power curve should be non-overloading type with the maximum power occurring at or near duty point or towards maximum runout flow. NPSHR curve should be a continuously rising one in the range of operation, from the minimum flow in the range to the maximum flow in the range. Required NPSH values shall not exceed available values over the entire range from minimum to rated flow. The efficiency curve should be fairly flat in the range of +1% of the BEP flow. The duty point of the equipment should preferably lie in this flat region, but not at a flow higher than the BEP flow. 4.5.4 Condensate System The condensate from the surface condenser and the condensate from the process plant will be used to meet the complete feed water requirements of the high-pressure boiler. Under the normal circumstances the make up water for the cycle will be Demineralized water. 10 MW Biomass Based Power Plant 4.5.5 ABEIL DM Plant The DM plant shall be designed to have single stream with a capacity of 8 TPH. The DM plant shall be designed based on the raw water analysis furnished elsewhere in this section of this report. D.M.Tank capacity shall be 36 m3. The demineralized water quality at the outlet of the DM plant shall be as follows: Hardness (ppm) : pH @ 25 °C : Conductivity @ 25°C (microsiemens/cm) : Oxygen (max) (ppm) : Total iron (max) (ppm) : Total copper (max) (ppm) : Total silica (max) (ppm) : Residual Hydrazine (ppm) : 0 8.8-9.2 0.05 0.005 0.01 0.01 0.02 0.01-0.02 The raw water at the inlet of the DM plant will be delivered at a pressure of 3.0kg/cm². The treated water at the outlet of the DM plant will be delivered at a pressure of 3.0 kg/cm². All vessels shall be designed with adequate free boards. Only seamless pipe shall be used wherever rubber lining is done. All fabricated vessels shall be designed according to IS 2825.The regenerants like Hydrochloric acid and Caustic Soda shall be stored in bulk in the DM plant premises, and pumped to the DM plant for regeneration. Manual handling of the regenerants shall be avoided to the maximum extent. Adequately sized neutralizing pit shall be provided near the DM plant for collecting the discharges from the DM plant and effectively neutralizing the same before pumping the waste to the plant’s effluent treatment system. 4.5.6 Vessels & Heat Exchangers The design shall be as per ASME Sec. VIII, HEI & TEMA. All heat exchangers and vessels for steam application shall be designed for full vacuum conditions. The heat exchangers shall be provided with startup vent connections. The design shall have provision for complete drainage on both shell and tube sides. The heat exchangers shall be provided with emergency drains, Tube & Shell side safety valves, and individual bypasses with manual valves. 10 MW Biomass Based Power Plant ABEIL A minimum corrosion allowance of 1.6 mm shall be provided. The tube bundle shall be of removable type. The tube material shall be stainless steel, unless otherwise specified in the specifications. 4.5.7 Tanks The power plant tanks will have storage capacities as required by design of the systems. Tanks will be of the closed top type. Tanks will be fabricated in accordance with guidelines established by API or AWWA as determined by the service. A corrosion allowance of 1.5 mm shall be provided. Overflow connections and lines shall be provided where required and will be atleast one pipe size larger than the largest input line or combination of inputs that can discharge simultaneously. Maintenance drain connections shall be provided of an adequate size to facilitate drainage of tanks within a reasonable time. Manholes where provided on tanks and pressure vessels shall be of size 450 NB size. Ladders and cleanout doors shall be provided on large tanks. DM water tank shall be internally lined with natural rubber or painted with three coats of Epoxy Coating. 4.5.8 Piping All piping system shall be designed as per ASME B 31.1. In addition statutory requirements of Indian Boiler Regulations (IBR) shall be complied with for those lines under the purview of IBR. Stress analysis shall be carried out for all possible operating modes and shall be as per ASME B 31.1 requirements. Supports, guides, Directional Restraints and Anchors shall be selected to satisfy all the operating conditions. 1) Pipe Sizing All piping shall be sized considering the allowable velocity and allowable pressure drop in the system. The suggested flow velocities of various mediums are Superheated Saturated steam Boiler feed water Pump suction Pump discharge Water Pump suction : : : : 40 to 55 m/sec 15 to 30 m/sec < 1 m/sec 2.5 to 4 m/sec : < 1 m/sec 10 MW Biomass Based Power Plant 2) Pump discharge Condensate Pump suction Pump discharge Compressed air Lube oil Pump suction Pump discharge ABEIL : 2.5 m/sec : : : 0.6 to 0.7 m/sec 2.5 m/sec 12 to 18 m/sec : : 0.3 to 0.4 m/sec 1.0 m/sec Piping Materials The piping material selection shall be based on the following recommendations. 4.5.9 For temperature above 510 °C, SA 335 Gr. P22 shall be used. For temperature 400 °C to 510 °C, SA 335 Gr. P11/P12/P22 shall be used. For temperature 399 °C and below, SA 106 Gr. B/C or ASTM A-53 seamless steel shall be used. All pipe fittings other than those mentioned shall conform to ASTM A 234 standard and dimensions as per ANSI B 16.9 / B 16.28 / B 16.11 For cooling water, raw water, service water, safety / relief valve exhaust IS: 1239 / IS: 3589 ERW/EFW pipes shall be used. For service air applications the piping shall be IS: 1239 Black Medium Class. For instrument air applications: Galvanized pipe (Iron Pipe) to IS: 1239 Part I shall be used. The fittings for ERW applications shall be as per IS : 1239 Part II. Insulation All exposed portion of the plant which operate at temperature of 60°C and above during normal operation shall be thermally insulated so that the temperature on the outer surface of the cladding shall not exceed 20°C above ambient, based on an ambient temperature indicated in site data. The specified insulation thickness shall not include the thickness of wire netting, finishing cement or any other finishing or weatherproofing application. Insulation shall not fill the contours of the expansion bellows. Piping and equipment that are not insulated but having a surface temperature exceeding 50°C shall be insulated for personnel protection. In refractory walls suitable expansion gaps shall be provided at regular intervals. 4.6 Civil & Structural The reinforced concrete structures shall be designed in accordance with the latest version of IS: 456, “Code of practice for plain and reinforced concrete”. The structural steel design shall be as per IS: 800. The design wind speed and seismicity shall be in accordance with IS: 875 and IS: 1893 respectively. 10 MW Biomass Based Power Plant ABEIL The structures shall be designed to withstand the calculated dead loads, live loads, along with the wind and seismic loads in appropriate combinations recommended by the Codes. The minimum dead and live loads for the design of the platforms and walkways shall be 500 kg/m². Structural steel shapes, plates and other structural materials shall conform to IS: 800, with a minimum yield strength of 25 kg/mm² the connection bolts shall conform to IS: 1367. Welding electrodes shall be as per AWS. HYSD reinforcement steel bars shall conform to IS: 1786. All structural steel (IS 2062) and MS members will be painted with two coats of red oxide zinc chromate paint and two coats of synthetic enamel paint. All foundations shall be of the spread footing or mat type. Soil bearing capacity shall be 18 t/m² at 2 to 2.5 meter depth and settlement shall be 25 mm at a depth of 2.0 m below ground level. The above soil bearing capacity shall be verified by soil investigation before final design. The site is assumed to be relatively flat, requiring minimal grading and leveling (leveling and grading upto ± 0.5 m). No major grading / leveling work is envisaged. All excavation work shall be done by conventional manual methods or by mechanical equipment method (wherever required). For substructures and superstructures ordinary Portland cement (grade 43) will be used. Grade of concrete for steam turbogenerator foundations shall be M-25 and all other foundations / pedestals / buildings etc. shall be of M20. 4.7 Electrical System All equipment for the power plant shall be designed for satisfactory operation for a lifetime of minimum 30 years under specified site conditions. All equipments shall be suitable for rated voltage of ± 10% and frequency of 50 Hz with ± 5% variation and 10% (absolute sum) combined voltage and frequency variation. The generator shall be of synchronous type with brushless excitation system and shall be designed for rated voltage and frequency of 11 kV and 50 Hz, with corresponding variations of ± 10% and ± 5% respectively. The generator shall have closed circuit air-cooled system with external water circuit (CACW cooling) and the windings shall have class ‘F’ insulation, with temperature rise limited to class ‘B’ insulation limits, under specified cooling water and ambient air temperatures. 10 MW Biomass Based Power Plant ABEIL Auxiliaries of the power plant shall be connected to the 415 V level, by providing one (1) number 1.25 MVA, 11 / 0.433 kV distribution transformer. The surplus power from the power plant, after feeding the in-house loads(10MW), shall be exported to the ASEB grid by stepping up the power to 132 kV, through one number 12.5 MVA. 11/132 kV generator transformer. Transmission system for 132 kV with necessary tariff metering and other terminal equipment shall be arranged between the plant and the ASEB’s substation at Jagi Road. It is envisaged to start up the power plant unit by installing 2x500 kVA DG sets. Once the power plant is ready to take-up the loads, the TG set will be momentarily synchronized with the DG set to avoid interruption of supply to the power plant auxiliary loads and then the TG will be synchronized with the grid through 12.5 MVA 132 / 11 kV transformer. The nominal voltage of main DC system for protection and control systems, turbine emergency oil pumps and emergency lighting shall be 110 V. UPS system with rated voltage of 220 V AC shall be envisaged, for meeting UPS power requirements of the plant DCS and other instrumentation / control loads, emergency lube oil pump. All equipment shall comply with the applicable provisions of relevant IS/IEC/IEEE standards, as listed elsewhere in this document. 1. Breakers for various systems shall be as below: 132 kV breaker 11 kV breaker 415 V breakers : : : SF6 circuit breaker VCB / SF6 CB Air break circuit breaker All connections at 11 kV (between 11 kV switchgear and generator / generator transformer / distribution transformer) shall be carried out through 11 kV, UE grade, armored, XLPE insulated cables. Connection between secondary of the distribution transformer and the PCC / Panels shall be through non-segregated phase bus-duct, with electrolytic grade aluminum bus-bars and aluminum alloy enclosure. All other LT connections (power as well as control) shall be with PVC insulated, armored, aluminum / copper cables. 10 MW Biomass Based Power Plant 2. ABEIL Sizing of cables shall be as follows: Cables shall be selected to limit the maximum voltage drop at equipment terminals, during normal operation and starting conditions, to be well within permissible values. Cables in circuits controlled by circuit breakers shall be capable of withstanding the maximum system fault currents till that breaker open by main protection. Fuse protected cables shall withstand maximum let through fault current for fuse operating time. 11 kV grade cables shall be suitable for carrying maximum earth fault current of the 11 kV system for 3 sec. Current rating of the cables shall be assigned considering continuous conductor temperature of not more than 70°C for PVC and 90°C for XLPE. Cables should also be sized to carry system fault current for the duration specified in above without exceeding the temperature limit of 160°C for PVC and 250 °C for XLPE. For 415 V system, ACBs shall be provided for rating 800A and above, and fuse switch / switch fuse unit shall be provided for lesser ratings. Motor feeders shall have fuse switch / switch fuse units, over load relays and air-break contactors. Motor of rating above 37 kW shall be provided with star-delta starters, depending on application, and shall be provided with static motor protection relays. Motor for auxiliaries shall be of three-phase induction squirrel cage type except for fan motors, which can be of slip-ring type for ratings above 90 kW. All motors shall have class ‘F’ insulation, with temperature rise limited to class ‘B’ limits under specified ambient and voltage frequency conditions. 4.7.1 Fault Level All equipment shall be designed to withstand the maximum fault, under voltage variation of ± 10%, 25 kA for 3 sec in 33 kV & 11kV systems and 50 kA for 1 sec in 415 V system. Distribution transformer and all accessories shall be capable of withstanding for two seconds without damage during any external short circuit at the terminal. All switchgears, MCC & Distribution Boards shall be capable of withstanding the maximum fault currents that may arise, duly considering the maximum fault levels on high voltage system, negative tolerance on transformer impedance and maximum possible motor 10 MW Biomass Based Power Plant ABEIL contribution for maximum possible fault clearing time on ultimate backup protection but not lower than one second in any case. 4.7.2 4.7.3 Degree of Protection 11 kV Switchgear LT Switchgear Switchgear located outdoors LT busduct enclosure : : : : Control panel : Push button stations : Synchronous generator Induction motors : : IP42 IP52 IP52 IP52 (in the indoor portion) IP55 (in the outdoor portion) IP42 (in air-conditioned area) IP52 (in other area) IP54 (indoor) IP55 (outdoor) IP54 IP54 (indoor) IP55 (outdoors) Neutral Grounding 11 kV system neutral earthling shall be low resistance earthed type to limit the earth fault current to 70 A, which shall be earthed by providing neutral grounding resistor of the neutral of the generator. All 415 V transformer neutrals and 132 kV transformer neutral shall be solidly earthed through bolted links. The system shall be compatible for accepting / sending signals from / to DCS. Winding, bearing and cooling circuit (where applicable) RTDs shall be hooked up to DCS for signal processing and necessary trippings shall be arranged from DCS, for tripping of the corresponding motor. Signals from all transformers for winding temperatures, oil temperatures, oil level gauges, buchholz relay outputs for alarm and trippings shall be brought to DCS. Status (ON/OFF/TRIP) of all breakers, LT breakers in PCCs and all motor feeders shall be brought to DCS, for plant monitoring. Control of motor feeders, as per system requirement, shall also be arranged for control from the DCS system. 4.8 INSTRUMENTATION & CONTROL SYSTEM The plant’s Instrumentation and Control system, based on Distributed Control System philosophy, will be designed to provide monitoring and control capabilities to ensure safe and 10 MW Biomass Based Power Plant ABEIL reliable operation, minimize operator manual actions and alert operators to any conditions or situations requiring manual intervention in a timely manner. The control functions shall be backed-up by interlocks and safety systems, which cause pre-planned actions in case where unsafe conditions develop faster than controls or the operator can be, expected to respond. All I& C equipment will be of proven design and will be selected to achieve highest level of plant availability and facilitate equipment maintenance. All field control elements for modulating controls will have actuators of pneumatic type. Signals from various process parameters are electrical signals generated by field mounted electronic transmitters. The above signals are processed in the DCS cabinets to produce electrical signal output of 4-20 mA, DC, which will be converted to control pneumatic signal of 0.2-1.0 kg/cm²(g), through E/P converters to operate the pneumatic actuators. All computation and signal conditioning and control function generation will be configured in the DCS. 10 MW Biomass Based Power Plant ABEIL 5. DESCRIPTION OF THE MECHANICAL SYSTEMS IN THE POWER PLANT 5.0 GENERAL DESCRIPTION The proposed power system will consist of 1 no. High-pressure boiler of capacity,50 TPH, 67 ata 4850 C and 1 no. Bleed cum condensing steam turbine of nominal capacity 11 MW. The steam pressure at the inlet of the turbine will be 64 ata and temperature 480 0C. Apart from the boiler and turbogenerator, the power plant will consist of fuel handling system, boiler feed water system, cooling water system, electrical system, power evacuation system, control system, utilities like compressed air system, ash handling system, fire protection system etc., 5.1 BOILER SYSTEM 5.1.1 Boiler The boiler will be designed for firing biomass like rice husk, and wood. The super heater outlet steam will have a pressure of 67 ata and a temperature of 485 0C. The boiler will be designed for outdoor installation. The boiler will have sub systems like pressure parts, feeding system, firing system, draft system, feed water system, ESP and chimney. 5.1.2 Pressure parts The boiler pressure part consists of a water-cooled furnace, boiler bank, steam and water drums, primary and secondary superheaters, economizer, risers and down comers. Basically the boiler will be a radiant furnace, Bi-Drum, natural circulation, semi outdoor type with two-stage superheater. The boiler shall be designed with water cooled membrane / fin welded walls and the refractory work shall be kept to the barest minimum possible. No header shall be placed in the flue gas path. All headers in the boiler will have flat end covers. A minimum of two hand holes for the purpose of cleaning and inspection shall be provided, for each of the headers, either on the end covers or on the body of the headers. The boiler will preferably be top supported with adequate provisions for the thermal expansion of the boiler in all directions. 10 MW Biomass Based Power Plant ABEIL The boiler will be provided with one steam and one water drum and drums will be of fusion welded type. Both the drums will be provided with Semi-Ellipsoidal dished ends fitted with 320 x 420 mm elliptical manways at either end. The manway doors will be arranged to open inwards. The drum shell, dished ends and the manway doors will conform to SA 515 Gr. 70 or equivalent material specification. The steam drum will be liberally sized to assure low steam space loading, with adequate space to accommodate the internals. The drum design pressure will have a minimum margin of 6% over drum operating pressure. The steam drum shall be provided with internals of proven design, shall be bolted type, and of size that will enable removal through the manways. The system of internals consisting of the primary and secondary separators will ensure steam of highest purity with dissolved silica carry over limited to a maximum of 0.02 ppm, at all loads of the boiler. All the components of the internals, except the dryer screens, shall be carbon steel and the dryer shall be of 304 stainless steel. The necessary nozzle connections for the following, but not limited to, steam outlets, safety valves, feed water inlets, continuous blow down, level indicators, chemical feeding, vents and drains, sampling connections, down comers will be provided on the drums as applicable. All nozzle connections on the drums will be of welded type and the feed water inlet will be provided with a suitably designed thermal sleeve. The necessary drum suspension / support arrangements shall be provided. 1) Furnace – Water wall System The Furnace envelope will be constructed of fully water-cooled membrane / fin welded walls and adequately supported. The construction will be fully gas pressure tight, and the furnace will be strengthened by providing buckstay and tie-bar system. Necessary provisions will be made in the furnace for admitting the required quantity of overfire air at various levels. Adequate number of inlet and outlet headers, with the necessary stubs, commensurate with the arrangement of the furnace will be provided. The down-comers supply pipes and relief tube sizing will be based on the circulation calculations. 10 MW Biomass Based Power Plant 2) ABEIL Bank Tubes The bank design will be of inline arrangement and the tube spacing will enable easy removal of the tubes in case of any failure. The bank tubes will be expanded into both the top and the bottom drums, and the tubes after expansion will be bell mouthed. There will be adequate approach space to the tubes of the bank for maintenance. Adequate number of soot blowers will be provided to cover the maximum surface area of the bank. The flue gas velocity in the bank area will be restricted to a maximum of 15 meter/sec. 3) Superheater System The super heater (SH) system will be of Two (2) stage design with interstage desuperheating to achieve the rated steam temperature over 60 to 100% load range. The superheater will be of convection or a combination of convection and radiation type arranged to give the minimum metal temperature. The superheater pressure drop, the inlet and outlet header sizing, arrangement and sizing of their respective inlet and take off connections will be so as to give minimum unbalance and the tube element material selection will be based on the actual metal temperature calculations. 4) Attemperator System The spray type attemperator system to control the temperature of the final superheater outlet steam temperature within the specified value will be provided in between the two stages of the superheaters. The desuperheating system will be complete with all required control valve, bypass, piping and supports, etc. 5) Economizer The Economizer will be located immediately downstream of the boiler bank. The design will be of bare tube construction with inline, counter flow, and drainable arrangement. The economizer will be designed for an inlet feed water temperature of 105°C. The coil arrangement will take care of proper calculated end gaps to avert gas bypassing and the consequent erosion of the element tubes. Tubes will be of seamless type. 10 MW Biomass Based Power Plant 5.1.3 ABEIL Air Heater The Air heater will be arranged as the last heat recovery section downstream of the economizer. The Air heater will be recuperative type with flue gas flowing inside the tubes and the combustion air flowing over the tubes. The air heater will be arranged with the tubes in the vertical direction. The tubes except those required for staying purposes would be expanded into the tube sheets on both ends. The air heater arrangement will provide for adequate access for replacing the tubes. Considering the high moisture in the flue gases, suitable precautions should be taken to prevent the tube corrosion at the air inlet side of the air heater. If the air heater is designed with more than a single pass in the airside suitable guide vanes will be incorporated in the connecting ducting to prevent stratification. The Low Temperature bank of the Air-preheater will be designed to prevent corrosion and the cold end material of the air heater tubes will be Corten Steel. 5.1.4 Soot Blowing System The boiler will be provided with a complete system of soot blowers to effectively dislodge deposits from the heat transfer areas. The soot blowers will be motor operated with steam, taken from the outlet of Superheater First stage, as the cleaning medium. 5.1.5 Fuel Firing System The boiler will be designed for firing 100 % biomass. The layout of the fuel feeding systems will be such that each system is accessible and maintainable. All feeders and distributors will have independent drive arrangement. 1) Fuel Feeding System This power plant will be having a separate fuel handling system. The fuel feeding system includes rack and pinion isolation gates, fuel storage silos with a capacity of atleast for 60 minutes of MCR requirements. The excess fuel in the slat conveyor will be returned to the storage yard through the return conveyor. The fuel input to the boiler will be regulated by the feeding system. 10 MW Biomass Based Power Plant ABEIL The fuel feeding system in addition to the storage silo will consist of inlet chutes, feeders, feed chutes and the distributor. The fuel distributor will be pneumatic with provision to distribute the fuel uniformly across the furnace. The distributor will have provision for onload adjustment of the throw of the fuel. The distributor parts facing the radiation from the furnace will be of AISI 310 type stainless steel. The number of feeder and distributor will be decided based on the distributor capacity and the width of the furnace. 2) Firing System The firing system will consist of a spreader stoker with continuous ash discharge travelling grate with variable speed drive. The drive system will have overload protection. 5.1.6 Draft System The draft system for the boiler will be suitable for producing a balanced draft with subatmospheric pressure conditions in the furnace. The boiler will have one (1) x 100% capacity Induced Draft Fans, One (1) x 100% capacity Forced Draft Fans and one (1) x 100% capacity Hot Secondary Air Fans making up the complete draft system for the boiler. 1) Forced Draft Fan The forced draft fan will be a constant speed, horizontal, radial, backward curved blades, drive motor with suitable starter. The fan flow control will be with inlet guide vanes through servomechanism incorporating suitable linkages and power cylinder housed suitably to prevent settlement of dust on links. 2) Induced Draft Fan The Induced draft fan will be horizontal, radial, with backward curved blades. The fan flow control will be with inlet guide vanes / inlet damper through servomechanism incorporating suitable linkages and power cylinder. IGV/damper operating links/drives should be housed suitably to avoid settlement of dust or links. The fan will be driven by a motor drive with a suitable starter. The fan speed will not exceed 1000 RPM. The 10 MW Biomass Based Power Plant ABEIL fan will be supplied complete with motor, common base plate for motor and fan, coupling, etc. The fan shaft will be of simply supported design and the minimum thickness of the plates used in the construction of the fan will be 8 mm. The impeller will be hard faced to avoid erosion of the impeller blades. The fan design temperature will be 200°C. 3) Secondary Air Fan The Secondary air fan will be constant speed, horizontal, radial, backward curved and electric motor driven. The fan flow control will be with inlet guide vanes with pneumatic cylinder for operation from control room. The fan will be direct driven, with speed not exceeding 1440 RPM and will be complete with motor, common base plate for fan and motor, coupling, etc. The fan shaft will be of simply supported design and the minimum thickness of plate used in the fan will be 6 mm. This fan will handle hot air and will take suction from the air heater outlet duct. 5.1.7 Ducting System All ducts will be rectangular in cross section and will be of welded construction, properly stiffened. All the air ducts will be fabricated from steel plates of minimum 5 mm thick, and all flue ducts will be of minimum 6 mm thick. The duct plate material will conform to IS 2062. Carbon steel plates will not be used for ducting system if the operating temperature of flue gas exceeds 425°C. The duct corners will be stitch welded internally and full welded on the outside. All ducts will be suitably stiffened and reinforced on the outside and designed to withstand the pressures encountered. Ducts will be sized considering a maximum velocity of 18 m/sec for hot air and flue gases and 12 m/sec for cold air. The duct design consideration will include the operating internal pressure, medium temperature, dead loads, ash loads, live loads, seismic loads, expansion joint reaction etc. Dampers, in the ducting system, will be provided as required, for the proper operation of the boiler. All dampers will be of the `louver’ or butterfly type with the necessary frames, shafts, blades, bearings, linkages, seals etc. All fans will be provided with isolation dampers at the discharge ends for online maintenance. 10 MW Biomass Based Power Plant 5.1.8 ABEIL Chemical Dosing System The boiler will be provided with a tri-sodium phosphate based high pressure (HP) dosing system and a hydrazine and ammonia based Low Pressure (LP) dosing system. The HP dosing system will continuously add the chemicals to the boiler water and to maintain the phosphate reserve and to increase the boiler water pH. The LP dosing is done to the feed water preferably in the deaerator storage tank to scavenge the traces of oxygen and to increase the feed water pH. 5.1.9 Electro Static Precipitator The boiler will be equipped with an Electro Static Precipitator, which will remove the dust and ash particles from the flue gas, before the ID fan could handle it. The efficiency of the precipitator will be 98% and the dust concentration at the outlet of the ESP will be 115 mg/Nm3. 5.1.10 Chimney The reinforced concrete chimney will be constructed to exhaust the flue gas to the atmosphere. The size and height of the chimney will be to suit the gas flow and the local pollution control norms. 5.1.11 Fuel Handling System Fuel from the yard will be reclaimed through dozers / front end loaders and will be fed on to the ground conveyor (BC1). The conveyor BC1 will discharge the fuel on to the conveyor BC2 that subsequently will deliver the fuel on to the slat conveyor SC1. From SC1, the fuel will be fed to the boiler. The excess fuel will fall on to the conveyor BC3 and taken to the yard. 5.1.12 Ash Handling System The ash handling system is provided for the ash collected from the following region: * * * * Travelling grate hopper Plenum chamber Air heater hopper ESP hoppers 10 MW Biomass Based Power Plant ABEIL The ash collected in the plenum chamber is extracted by rotary valves and conveyed to a silo by pneumatic conveyor system. The ash collected from the air heater and ESP hoppers will be transported to Ash Silo by rotary valves and pneumatic conveyor. 5.2 TURBO-GENERATOR SYSTEM 5.2.1 Steam Turbine The proposed power plant will be with one 11 MW turbogenerator. The turbine will be a bleed cum condensing type and running at a high speed. The generator speed will be 1500 rpm. Hence, the turbine will be coupled with the generator through a reduction gear unit. Steam is admitted into the turbine through an emergency stop valve actuated by hydraulic cylinders. The turbine speed is controlled by an electronic governing system. The turbine exhaust pressure will be 0.1 ata. The turbine will be preferably single cylinder, single exhaust, bleed condensing type. All casing will be horizontally split and the design will be such as to permit examination of the blading without disturbing shaft alignment or causing damage to the blades. The design of the casing and the supports will be such as to permit free thermal expansion in all directions. The blading will be designed to withstand all vibrations, thermal shocks, and other loading that may be experienced during service and system disturbances. The blades will be machined from forged bars or die forged and the materials used will be chromium steels consistent with proven experience and standards. The glands will preferably of labyrinth type and sealed with it. A vacuum system required by the design will be provided. All piping and components of shaft seal and vacuum system will be sized for 300 percent of the calculated leakage. Steam leaving the glands will be condensed in seal steam condenser. It will be possible to inspect and replace the end seals without opening the casing and without damaging the thermal insulation. 1) Bearings The Turbine will be provided with liberally rated hydrodynamic radial and thrust bearings. The radial bearings will be split for ease of assembly, and of the sleeve or 10 MW Biomass Based Power Plant ABEIL pad type, with steel shell backed, babbitted replaceable pads. These bearings will be equipped with anti-rotation pins and will be positively secured in the axial direction. The thrust bearings will be of the steel backed babbitted multiple segment type, designed for equal thrust capacity in both directions. A liberal flow of lube oil under pressure will be supplied to all the bearings for lubrication and cooling. 2) Lubrication and control oil system A pressure lubrication and control oil system will be furnished for the turbo generator unit to supply oil at the required pressure to the steam turbine, gearbox, generator and governing system. Oil in the reservoir will be maintained at an appropriate temperature when the TG set is idle by providing suitable electric heaters and temperature controls. The oil system will include the following: 3) Main oil pump preferably driven by the turbine shaft. A 100% capacity AC motor driven auxiliary oil pump arranged to cut in automatically if the oil pressure falls to a preset value. This pump will also meet the requirements during the start up and shutdown. A D.C. motor driven emergency oil pump of sufficient capacity to provide adequate lubrication in the event of a failure of the unit AC motor driven pump. This pump also will cut in automatically at a pre set value of the oil pressure. Two 100% duty oil filters arranged in such a way by means of transfer valves that it is possible to clean one oil filter while the other is in service with continuous flow. Duplex 100% capacity oil coolers with changeover valves. An accumulator to maintain sufficient oil pressure, during servo control transients and while standby pump accelerates from idling to full speed. Oil storage and settling tank with adequate reservoir capacity, duplicate strainers, level indicators with float switches and alarm contacts, vent and oil mist eliminators. Flow and temperature indication for outlet oil from bearings and bearing metal temperature indication for all bearings. Centrifugal oil purifier. Oil coolers The oil coolers will be water-cooled with a duplicate arrangement and changeover valves. The coolers will be of shell and tube type. 10 MW Biomass Based Power Plant ABEIL The coolers will be constructed in accordance with TEMA class C. The provided surface area will be adequate to cool the oil with Inlet cooling water temperature at 35 °C even with 20% of the tubes plugged. 4) Filters Full flow oil filters will be used downstream of the coolers and will be piped in a parallel arrangement with a continuous flow transfer valve. Filtration will be 10 microns nominal. Filter cartridges will be designed for minimum pressure drop and suitable for maximum discharge pressure of the oil pumps. 5) Oil reservoir The interior of oil reservoirs will be descaled and rust proofed with a permanent coating. Reservoirs with top mounted equipment will have sufficient rigidity. All openings for piping will be made dust and waterproof. 6) Oil purifier A centrifugal type oil purifier will be provided for the removal of water, sediments and other oxidation products. The purifier will be a separate complete package. 7) Steam Turbine Governing System The turbine governing system will be electro-hydraulic or electronic designed for high accuracy, speedy and sensitive response. The electrical/electronic and hydraulic component of the control system will be selected on the basis of reliability over a wide range of operating conditions. All components used will be well proven to assure overall system reliability and will be designed for easy and quick replacement when necessary. The governor will ensure controlled acceleration of the turbo generator and will prevent overspeed without tripping the unit under any operating conditions including the event of maximum load rejection. The governor will also ensure that the unit does not trip in the event of sudden frequency fluctuation in the grid and also sudden grid failure / load through off. 10 MW Biomass Based Power Plant ABEIL The governor will have linear droop characteristics with a suitable range for stable operation and will have provision for adjusting the droop in fine steps. The governing system will have the following important functions: 8) Speed control Overspeed control Load control and speeder gear. Steam pressure control Master trip for Low Steam Pressure, Low Vacuum, High Vibration, eccentricity, over speed, Differential Expansion etc. Condenser The condenser will be of non-contact surface type condenser designed as per the requirements of Heat Exchange Institute Standards for Steam Surface Condensers and ASME Section VIII division 1. Condenser shell shall be cylindrical made of steel plate and tubes shall be 19 mm O.D. and 18 BWG admiralty brass. Heat transfer surface shall have 10% margin for tube plugging over and above fouling factor. The condenser will be sized to condense the maximum quantity of exhaust steam (i.e. when the extraction is minimum) with the inlet cooling water temperature at 32°C upto a maximum of 40°C. (with part load operation). The condenser design and supply will be complete with the neck, expansion joint, condensing chamber and tubes, tube sheets, hot well, water boxes, water side, valve, air removal system and accessories, rupture disc, Teflon padded sliding support, bolted and hinged water box cover at front and back. The condenser neck will be suitably designed to reduce the inlet steam velocity to ensure low-pressure drop and to protect the tubes from impingement of steam. The condenser will be adequately designed for the external pressure; stiffeners and bracing wherever required would be provided. The tubes will be provided with supports to eliminate any serious tube vibration problems and sagging. The tubes will be expanded into the tube sheets at both the ends and flared. 10 MW Biomass Based Power Plant ABEIL The condenser neck will be connected to the turbine exhaust hood with a properly designed stainless steel expansion bellow which allows free expansion of the condenser unit without exerting undue thrust on the turbine exhaust hood and facilitate independent supporting of the condenser on the foundations without resorting to springs. Manholes will be provided for facilitating inspection of tubes both at steam and watersides. The hot well at the condenser bottom will have a minimum capacity of 2 minutes storage while handling maximum quantity of exhaust steam. The hot well will be provided with level gauges and connections for condensate extraction and drain. A suitably designed level control system will be provided, with provision for alarm tripping etc. The condenser will be of divided water box design, and the water boxes will provide easy accessibility to the tubes. It will be possible to clean one section of the tubes with the condenser load suitably reduced. The circulating water inlet and outlet connections will be of adequate size to reduce the waterside pressure drop to the minimum. The water boxes will be coated with epoxy resin, internally to prevent corrosion from the cooling water and will be provided with sacrificial anodes. 9) Condenser Air Removal Equipment One steam operated hogging ejector of single stage will be furnished for the initial pulling of the vacuum in the system. The capacity will be so as to reach 80 – 90 % vacuum in 20 minutes time. Hogging Ejector will be, without any condenser, discharging to the atmosphere through a suitably designed silencer. 2 x 100% steam operated main ejectors of two-stage twin element type with inter and after condensers will be provided. 10 MW Biomass Based Power Plant 10) ABEIL Condensate Extraction Pumps Two numbers 100% capacity condensate extraction pumps to pump the condensate from the condenser hot well will be provided. Both the pumps will be driven by electric motors and the flow will be controlled by discharge throttling. The pumps will be of centrifugal, horizontal, single stage type and will be supplied complete with all valves, inlet and discharge piping with manifolds. 11) Gear Box The reduction gearbox, if required, between the turbine and the generator will be of proven design preferably of double helical arrangement with service factor of 1.2 It will be capable of transmitting the maximum rating of the set and be able to withstand 20% over speed over a period of minimum five minutes. The gearbox will also be designed for the short circuit condition of the generator. All bearings of the gearbox will be readily renewable and it will be possible to inspect the bearings and the gears readily without disturbing the shaft alignment. Illuminated sight glasses will be provided to inspect the lube oil drain from each individual bearing. The gearbox design will be as per the requirements of AGMA. 5.3 COOLING WATER SYSTEM The cooling water is used in the surface condenser for condensing the steam, turbine auxiliaries for cooling, boiler auxiliaries like feed pump, ID fan etc., for bearing and gland cooling. The cooling water after cooling the equipment will be cooled, so that the same water can be reused again. For this purpose, a wet cooling tower of induced draft type will be used. The cooling medium in the condenser will be raw water. The cooling water temperature rise in the systems will be limited to 10 Deg C. The hot return water will be distributed uniformly over the cells of the cooling tower. 10 MW Biomass Based Power Plant ABEIL The raw water from the Canal/ Borewells will be pumped to the cooling towers after suitable treatment, which will cool the cooling water. For this purpose, two nos (2 x 100%) pumps of 100% capacity each will be provided. The raw water will be stored in a raw water reservoir. The water will be pumped to the cooling tower fore bay. The water from the fore bay will then flow to the suction of the cooling water pumps. The cooling water pumps will have the head to meet the pressure drop in the entire circuit. The cooling water will also be taken to the turbogenerator, boiler area etc., through pipes of adequate size. Isolation valves of type gate / butterfly will be provided at different locations, for easy maintenance. Similarly suitable expansion joints will be provided in the piping, to facilitate dismantling and also to take care of the misalignments / thermal expansion of the pipes. The water in the cooling tower basin is prone for algae growth. If algae grow in the cooling tower water, it will affect the equipment, which are cooled by the cooling water. To prevent the growth of algae chlorine will be dosed in the water at appropriate quantity. To maintain the salt concentration in cooling water to acceptable limits, blow down will be given periodically. 5.4 CHLORINATION SYSTEM The Chlorination system will have two vacuum feed chlorinators, with one as standby. Each chlorinator will be connected independently to individual evaporators, which in turn be connected to two chlorine containers. The water for the Chlorination system will be supplied from the auxiliary cooling tower pump discharge header. The capacity of chlorinators will be base on a maximum dosing rate of five ppm on the total rate of main and auxiliary cooling water systems. 5.5 CONDENSATE WATER SYSTEM The condensate from the surface condenser will be collected in the hotwell. The condensate will be pumped to a condensate tank by two condensate extraction pumps (CEP). One of the pumps will be working and other serving as stand by. The dissolved gases like oxygen etc., present in the condensate, when heated to the saturation temperature, will dissociate from the condensate and will be vented out. Traces of oxygen will be removed by dosing hydrazine solution. The make up water for the system will 10 MW Biomass Based Power Plant ABEIL be DM water. The deaerator will have a storage tank with capacity equivalent to 20 minutes MCR requirements of the boilers. The feed water from the deaerator storage tank will be pumped to the economizer by one feed water pump with one 100% stand by, each of capacity 40 m3/hr. 5.6 Pressure reducing and Desuperheating stations: One No. PRDS with manual by pass will be provided for supply of low-pressure steam-tosteam Jet Air Ejector and Turbine glands. One No. Separate PRDS with manual by pass will be provided for supply of start up steam and pegging steam to deaerator. Pegging steam will be automatically cut in when pressure of extraction steam from turbine drops below required pressure. 5.7 DM WATER PLANT The DM water, which will be used as the make up water, will be produced in the DM Plant. The capacity of the plant proposed is 8 m3/hr. The DM plant will consist of sand filters, activated carbon filters, anion and cation exchangers, degasser and mixed bed exchangers. Two raw water pumps will pump the raw water. The regeneration of the DM plant will be 8 hrs/day. The DM water from this plant will be stored in a Storage tank of adequate capacity. The acids and alkali required for the regeneration will be sufficiently provided in the plant. The effluent from the DM plant will be neutralized in a neutralization pit. The outlet water from the neutralization pit will have a pH of 7.0. 5.8 SERVICE WATER AND POTABLE WATER The service water is required for general wash, gardening, toilets etc., and the potable water required for the power plant will be taken from the outlet of the activated carbon filter in the DM plant. 5.9 CRANES AND HOISTS Cranes, hoists and monorails will be provided in the following areas of power plant for maintenance purposes. Hand operated overhead travelling crane in the turbo-alternator building. Monorails with hoists for handling boiler feed water pumps located under the deaerator structure, Monorails with 10 MW Biomass Based Power Plant ABEIL hoists for handling impellers and motors of ID fans. Monorails with hoists for handling impellers and motors of FD/SA fans. Monorails with hoists for handling condenser components. The TG building would be provided with a hand operated overhead travelling crane of 15 / 5 tones capacity and about 16mts span for maintenance of all equipment in the TG building. The capacity would be adequate to handle all equipment / component in the TG building including the generator stator which is the heaviest equipment to be handled. The auxiliary hook would handle the smaller components in the TG building such as lube oil coolers, ejectors, gland steam condenser and ejector condenser. This crane will be hand operated. 5.10 COMPRESSED AIR SYSTEM Instrument air is required for various pneumatically operated control valves in the boiler and TG systems. The air is required to be supplied at a pressure of 5 to 6 Kg/cm2 (g) at the various consumption points. Instrument air from the air compressors will be dried by heatless air drier making use of the hot air from compressor for regeneration of the drier medium (desiccant). Service air is required for cleaning of various areas of the plant. Accordingly, the service air connections are proposed to be provided in the Boiler area, TG building, workshop, DM Plant etc. Considering the quantity of air required for the power plant, two (2) air compressors will be required. These compressors will supply the instrument air and the required service air. Compressors will be of non-lubricated type. 5.11 AIR-CONDITIONING AND VENTILATION SYSTEM The following areas in the power plant will be air-conditioned. - The main control room housing the control panels of boiler and TG, switchyard control panels and auxiliary panel room housing the associated system cabinets. Instrument maintenance room The above areas will be air-conditioned using window type/spilt type air conditioners. The capacity of the air conditioning units will be decided based on the area of the room and heat load dissipated in the room. 10 MW Biomass Based Power Plant ABEIL The following mechanical ventilation systems are proposed to be provided for various buildings/rooms in the power plant. 5.12 Two (2) axial type power roof ventilation of adequate capacity each for the TG building. Two (2) centrifugal type supply air fans of adequate capacity for the switch gear room, battery room etc., Suitable number of propeller type exhaust fans in the water pump house, DM Plant, filtration plant, workshop and stores. FIRE PROTECTION SYSTEM The following systems of fire protection are proposed to be provided for the power plant: - Hydrant system for the entire plant. High velocity water spray (HVWS) system for transformers and lube oil tanks. Carbon dioxide flooding system for the generator of the steam turbine. Portable fire extinguishers. The fire protection will basically comply with the Tariff Advisory Committee (TAC) requirements, enabling rebate in the insurance premium rate. 5.12.1 Reserve Storage Reserve storage of 350 m3 will be provided in the raw water storage tank with a suitable partition to cater to the water requirements of the fire protection system. In view of the above, pump house elevation will also be suitably lowered at the location of the fire water pumps as compared to the floor elevation at the location of the raw water pumps. 5.12.2 Hydrant System The hydrant system will comprise the following: - One motor driven and one diesel engine driven firewater pump. These pumps will take the suction from the water storage tank. As per TAC regulations, the above hydrant pump capacity will be adequate to cater to the total number of Hydrants provided in the plant. - Two motor driven jockey pumps (one working and one stand by) each of 10 cum./hr capacity will be provided to keep both the hydrant and HVWS system mains pressurized. These pumps will also take suction from the raw water tank. - External fire hydrants in all areas of the power plant including boilers, TG, DM Plant, control building, switch yard, canteen, stores, and workshop and administration buildings. 10 MW Biomass Based Power Plant - ABEIL Internal fire hydrants in all storied buildings and structures such as Boiler platforms, TG building, canteen and administration building. 5.12.3 High Velocity Water Spray System The HVWS system is proposed to be provided for the transformers and the steam turbine lube oil tank. Water supply to the HVWS system will be provided by one motor driven pump. Since the parameters for the HVWS system will be identical to that of the hydrant system, the diesel engine driven pump described in the hydrant system, can serve as a common standby for both HVWS system and hydrant system. The HVWS system will consist of a number of high velocity water projectors mounted on a pipe network around each transformer and steam turbine lube oil tank. Water supply to each pipe network from the HVWS system mains will be through a deluge valve. The HVWS system for the transformers will be of automatic type. In case of fire, quartzoid bulb sensors mounted around the transformers will automatically actuate the deluge valve on the spray water line. The HVWS system for the turbine lube oil tank will be manually actuated. Smoke and heat detectors will be used strategically. 5.12.4 Portable Fire Extinguishers It is proposed to provide an adequate number of wall/column mounted type portable fire extinguishers in various areas of the plant including the control room, administration building, canteen, stores, workshop, pump house, etc., These portable fire extinguishers would basically be of carbon dioxide and dry power type. 5.12 TECHNICAL DATA FOR MAJOR MECHANICAL EQUIPMENT 5.12.1 Boiler Number of boilers MCR capacity tph Peak generation tph Steam pressure at SH outlet Kg/ cm2 (g) 0C Steam temp. at SH outlet 0C Feed water inlet temp. Boiler efficiency on mustard or cotton stalks GCV% Gas temperature at the outlet of AH 0C : : : : : : : : One (1) 50 50 67 485 +/- 5 105 78.5 150 10 MW Biomass Based Power Plant ABEIL 5.12.2 Turbogenerator 1) Steam Turbine Power rated Inlet steam pressure Inlet steam temperature Exhaust steam pressure Bleed steam pressure Alternator speed 2) kW Kg/ cm2 (g) 0C ata Kg/ cm2 (g) rpm : : : : : : Surface, divided Water box 30.5 0.1 2100 32 40 : : : : : Centrifugal 35 0.1 6.0 2 : : : : : : : : : Induced draft One (1) 2200 32 42 0.5 2.5 Two (2) 27 : : : : : Two (2) 40 1000 Multistage Centrifugal Electric motor Condensate Extraction Pump Type Capacity Suction pressure Discharge pressure Number of pumps 4) 11000 64 480 0.1 2.5 1500 Surface Condenser Type Steam flow tph Steam pressure ata Cooling water flow tph 0C Tube material Outlet cooling water temperature 0C 3) : : : : : : m3/hr ata Kg/cm2 (g) Cooling Water System Cooling Tower: Type Number of cooling towers Capacity Cooling water supply temperature Cooling water return temperature Cooling water return pressure Evaporation loss and blow down % No. of cells Design wet bulb temperature 0C 5) m3/hr 0C 0C Kg/ cm2 Boiler Feed Pumps Number of pumps Capacity Head Type Drive m3/hr MLC 10 MW Biomass Based Power Plant 6) Deaerator Type Capacity Outlet water temperature Operating pressure Design pressure Steam inlet pressure Oxygen content in the outlet water 7) tph 0C Kg/cm2 (g) Kg/cm2 (g) Kg/cm2 (g) ppm : : : : : : : Spray cum tray 40 105 1.0 3.0 1.5 0.007 m3/hr hrs/day : : 8 8 DM Water Plant Capacity Regeneration 8) ABEIL DM Water Specification Hardness : Nil Chloride : Nil Silica as SiO2, max. ppm : <0.02 Iron as Fe, max. ppm : <0.01 Conductivity at 20 Deg.C max, : 0.5 microsiemens/cm pH : 9.0 to 9.4 DM water plant will be complete with activated carbon filter, anion, cation exchangers degassers, pumps, mixed bed exchangers, acid/alkali tank and pumps, raw water pumps etc., 10 MW Biomass Based Power Plant ABEIL 6 DESCRIPTION OF ELECTRICAL AND I & C SYSTEMS 6.0 GENERATOR The generator will be rated 11 MW, 11 kV, 50 Hz, 3 pH, and 0.8 pf. The rated speed will be 1500 rpm. The generator winding will have class F insulation. The winding will be star connected. The star point will be earthed through a resistor to limit the fault current to full load current. The generator will be air-cooled with an air -water heat exchanger. The generators will have brushless excitation system. All the six terminals of the turbo generator winding will be brought out for external connections. These connections will be taken to the Lightning Arrestor (LA) VT by suitably rated bus bars. The LAVT will house necessary current transformers, voltage transformers, lightning arrestor generator neutral grounding resistor, etc. Further connections to the generator circuit breaker in the 11 kV switchgear will be by means of suitably rated 11 kV cables. All six terminals of the steam turbine-generator will be brought out of the turbine pedestal wall, through seal-off bushings. The connections between generator terminals and seal-off bushing will be by open busbars. Outside the TG pedestal a short run of segregated phase busduct will be provided on the phase side of the generator to house the current transformers and give tap-off connections to LA & PT cubicle. This phase side bus duct will be terminated with a cable termination box for further connection by 11 kV cables upto the 11 kV switchgear. Similarly, a short run of segregated phase bus duct will be provided on the neutral side to house the current transformers. The neutral formation and the disconnecting link will be provided in an adaptor box after the current transformers. A short single-phase bus duct will be provided between the adapter box and the NGR cubicle. The generator shall be of closed circuit air-cooled type housed in an IP55 (CACW) enclosure and driven by steam turbine through a speed reducer. The necessary coupling and coupling bolts shall also form part of the supply. 1) Stator The stator frame shall be a single piece consisting of a cylindrical casing of welded plate construction, reinforced internally in the radial and axial direction by stationary web plates 10 MW Biomass Based Power Plant ABEIL making the entire frame perfectly rigid. The stator winding shall be of the double layer lap type with Class ‘F’ insulation. 2) 3) Rotor a) The generator rotor shall be forged from a single piece ingot of special alloy steel carefully heat treated to obtain excellent mechanical and magnetic properties and a comprehensive series of ultrasonic examinations on the rotor body shall be done to ensure that absolutely no inadmissible internal defects are present and that the material meets the quality standards. b) The design and construction of the rotor shall be in accordance with the best modern practice and shall be fully described in the offer. c) The insulation between turns of field winding shall be consistent class F insulation. d) The field poles shall be provided with adequate damper windings to ensure stability under fault conditions and to meet {(I2°C) 2*t} value of 20. Earth Terminal Two Nos. or more Earth terminals shall be provided. The earth terminals shall be designed to terminate Galvanized iron conductors. The size shall be as specified in IEC 34-1. 4) Speed Regulation The moment of inertia of the alternator together with that of the turbine shall be sufficient to ensure stability and the speed regulation specified in the section- covering turbine for full load. 5) Shaft a) The generator shaft shall be made of best quality forged alloy steel, properly treated. The shaft shall be of ample size to operate at all speeds, including maximum over speed without vibration or distortion and shall be able to withstand short circuit and other stresses without damage. To prevent the flow of harmful shaft currents damaging the bearings, suitable shaft earthling shall be provided. b) A complete set of test reports covering metallurgical strength, crystallographic and ultrasonic and boroscopic tests performed in each shaft during various stages of its manufacturing shall be furnished as also the complete specifications of the shaft forging material and its design parameters such as stresses and critical speed. 10 MW Biomass Based Power Plant ABEIL c) The generator shaft shall have a suitably shaped flange for coupling to the turbine/gearbox shaft. The coupling shall be forged integral with the shaft and the shaft coupling shall comply with the requirements of IEC for shaft coupling. All coupling bolts, nut and nut guards for coupling shall be furnished by the vendor. The alignment limit for the shaft shall be as per the latest NEMA/DIN standards. 6) Space Heaters Suitably rated heaters shall be installed within the enclosure of the generator. Location and the maximum temperature of the heaters shall be such that no damage can be caused to any insulation. Heaters shall be suitable for operation on a single-phase 230 V AC supplies. A suitable thermostat controlled switch shall be mounted on or adjacent to the stator frame for the switching off the heaters. 7) Excitation System a) A brushless exciter shall be used and it shall be mounted on the out board end of the generator frame. A static voltage regulator shall be included to control the voltage of the synchronous generator by varying the current supplied to the field. Details of the equipment shall be furnished along with the bid. b) A self-excited static excitation system shall be provided. A high speed, fully tropicalised, printed circuit, drawout type, automatic digital/analog voltage regulator shall be provided. It should be complete with necessary sensing PT’s, cable entries, cast resin type current transformer, adjusting rheostats, auto/manual and on/off selector switches. The following meters of class one accuracy of size not less than 144 x 144 mm shall be provided in the excitation cubicle and also in the unit control panel. Exciter Field Current Generator Field Current Generator Field Voltage Generator Terminal Voltage c) The excitation system shall be provided with the following features: Generator voltage control Excitation current control Excitation buildup during startup and fields suppression shutdown. 10 MW Biomass Based Power Plant ABEIL Limiter for the under excited range and delayed limiter for overexcited range. Feature for parallel operation of the generator with the grid system incorporating power factor control mode and feature for islanding operation during sudden grid failure. d) The system offered shall have the following facilities: Manual mode of operation Auto mode of operation Follow on mode to have smooth transfer from one mode of operation to the other. Auto/Manual changeover facility shall be provided. For manual mode voltage lower/raise pistol grip type / spring return type switch shall be provided. Following minimum alarms shall be transmitted to the unit control desk. The excitation system shall have diode protection relays to detect failure of the Rotating Diodes. 8) AVR fault AVR automatic changeover to manual Diode failure Accessory Equipment a) Terminal boxes shall be provided to enclose the leads and current transformer. The terminal boxes shall be adequately designed to accommodate termination of Bus duct/single core 11 kV XLPE cable per phase and its termination kits. The generator shall be provided with various RTD’s (temperature sensors) installed various in the stator winding with leads, brought out to a separate terminal box. These RTD’s shall be hooked upto the temperature scanner in the control panel. Necessary vibration transducer, displacement transducers with transmitters shall be provided which shall be hooked up to the control panel in the control room. b) Adequately rated neutral grounding resistor / neutral grounding transformer shall be supplied, the resistor shall be stainless steel edge wound type mounted in shielded safe enclosure. A current transformer shall be provided for ground fault current measurements for protection. The rating of the resistor shall be furnished. c) Necessary surge capacitors and lightning arrestors shall be provided for generator protection. The surge capacitors shall conform to the latest IS 2834 and shall be rated 10 MW Biomass Based Power Plant ABEIL 0.25 Micro Farad. The capacitors shall be suitable for indoor mounting and shall be provided with built-in discharge resistor. 6.1 SURGE PROTECTION EQUIPMENT The surge protection equipment would comprise lightning arrestors with suitable discharge characteristics to suit the generator insulation level in parallel with suitably rated capacitor for smoothening the rate of rise of impulse voltage. The lightning arrestors will be located as close as possible to the generator terminals. 6.2 POWER EVACUATION The power generated from the proposed power plant will be evacuated at 132 kV through 1 No. 100% capacity transformer. The generator is earthed through a resistor to limit the earth fault current to acceptable limits so that generator core is not damaged. Hence this system will be of non-effectively earthed type. 6.3 11 KV SWITCHGEAR The power generated from the generator will be fed to an indoor metal clad 11 kV switchgear through suitably rated cables. The 11 kV switcher will comprise of draw out type circuit breakers housed in indoor, metal clad cubicles. The calculated fault level of the 11 kV generator bus is 500 MVA. The circuit breaker proposed is 750 MVA/40 kA for the generator bus. The breakers will be of either SF6 or vacuum type. 6.4 POWER TRANSFORMERS Based on a maximum estimated load of about 12.5 MVA to be evacuated at 132 kV, one No. 12.5 MVA, 11 kV/132 kV, Ynd11, Z = 8% transformers will be provided for interconnection with the grid. The transformer will be ONAN cooled. It will be provided with OLTC on the HV side having ± 10% range in steps of 1.25%. The HV neutral will be solidly earthed. The HV side will be provided with bushings and LV side with cable box. 10 MW Biomass Based Power Plant 6.5 ABEIL 132 kV SWITCHYARD The 132 kV switchyard shall consist of single busbar arrangement, with one incomer from transformer and one outgoing feeder for connecting the 132 kV line from ASEB. The fault level at the 132 kV bus works out to 750 MVA. However, as the minimum available circuit breaker rating at 132kV is 630 A, SF6 circuit breakers suitable for 26.3 kA breaking capacity will be provided. The isolators will be horizontal center break type with motor operated closing mechanism. The current and potential transformers will be of oil filled type. The switchyard will be of outdoor type with galvanized steel lattice structures. The station auxiliary switchgear will feed the following switchgear / MCCs / Distribution boards: Boiler MCC Cooling Tower MCC TG MCC Ash handling system DB DM Plant DB Switchyard DB Lighting DB Crane DB Administrator Building / Guest House Fuel Handling System. Loads of the power plant auxiliaries and other station loads will be fed directly from the station auxiliary switchgear. The main one-line diagram for the power plant, enclosed indicates the auxiliary power distribution. The various auxiliaries of the power plant would be supplied at the following nominal voltages depending upon their ratings and functions: 6.6 415 V, 3 phase, 3 wire effectively grounded AC supply for motors. 240 V, 1 phase, AC supply for lighting, space heating of motors and panels, single phase motors, etc. 230 V, 1 phase grounded AC supply for AC control circuits. 110 V, ungrounded DC supply for control and indication. 415 V SYSTEM The 415V 3 phase, 3 wire power for the 415 V auxiliaries would be obtained from the auxiliary transformer. The 415 V switchgear would be of metal enclosed design with symmetrical short circuit rating of 50 kA. 10 MW Biomass Based Power Plant ABEIL All the power and motor control centers would be compartmentalized and would be of double front execution and fully draw-out design with all the circuit components mounted on a withdrawal sheet metal chassis. The circuit breakers would be air break type. Motor starting would be direct on-line. Motors rated above 125 kW will be controlled by air break, electromagnetic type contactors provided with ambient temperature compensated, time lagged, hand reset type thermal overload relays, having adjustable settings and backed up by HRC fuses for protection against short circuits. The switchgear would be located in the control building. 6.7 STATION AUXILIARY TRANSFORMER The auxiliary transformer would be 1 no. 1.5 MVA 11 / 0.433 kV Dyn11 common for all units. It will supply power to the 415 V auxiliaries of the power plant STG, CW/ACW system, water treatment plant, lighting, battery chargers, etc. The neutral of the transformer would be solidly earthed. The auxiliary transformer would be ONAN type and would be provided with ± 5% off circuit taps in steps of 2.5% on the HV side. 6.8 CONTROL & PROTECTION SYSTEM 6.8.1 Generator The following protections are proposed to be provided for the generators: 6.8.2 Differential protection Stator earth fault protection Loss of field protection Negative phase sequence current protection Impedance or voltage restrained overcorrect back-up protection Rotor earth fault protection Reverse power protection Over voltage protection Low forward power protection (for steam turbine generation only) Under voltage protection Overload alarm Capacity 11 kV / 415 V Station Auxiliary Transformer The following protections are proposed for the station auxiliary transformer: 3-pole high set overcorrect protection on H.T. side. D-pole I.D.M.T overcorrect back-up protection on H.T. side Single pole instantaneous overcorrect earth fault protection 10 MW Biomass Based Power Plant 6.8.3 ABEIL 12.5 MVA, 11 / 132 kV Transformer The following protections are proposed for the above transformer: 6.8.4 Differential protection Directional back-up phase overcorrect protection on HV and LV side REF protection Overfluxing protection Buchholz, oil and winding temperature protection 132 kV Lines Distance protection would be provided at the generating station side. 6.8.5 132 kV Busbars High impedance, circulating current type relay scheme with main and check features would be provided for the 132 kV busbars. 6.9 EMERGENCY POWER SYSTEM Two Nos. diesel generator sets, 500 kva each, 415 V, 50 Hz will be provided to make available emergency power supply to the station in case of black-out. The diesel generator set will be connected to the 415 V switchgear as shown in SLD. 6.10 DIRECT CURRENT SUPPLY SYSTEM The Direct Current System (DC) is the most reliable source of supply in the power station and will be used for the control and protection of the power plant equipment. The DC system will be used for the following: Electrical control of equipment and indications on the control panel. Power supply to the essential auxiliaries of the power plant and turbines in case of AC power failure. Power supply to the following services in case of total AC power failure. Communication system DC lighting of strategic areas for safe personnel movement. The battery sizing will be done to cater to the following type of loads: Momentary load for 1 minute Emergency load for 2 hours Continuous load for 10 hours 10 MW Biomass Based Power Plant ABEIL Under normal conditions, the battery will be on float charger. The float charger is connected to a distribution board and meets the requirements of DC load. In case of additional demand of load or AC supply failure; the battery will meet the requirements of DC loads. The boost charger will be designed to charger the fully discharged battery in 12 hours before putting it back on float charge. A set of two 110V battery blanks (100% standby) of suitable capacity with two float and boost chargers and a direct current switch board will meet the DC load of power plant. The batteries would be of stationary lead acid type, complete with racks, porcelain insulators, intercell and interior connectors. The chargers would be of silicon rectifier type with automatic voltage control and load limiting features. 6.11 UNINTERRUPTED POWER SUPPLY (UPS) SYSTEM One battery bank of suitable capacity with associated two 100% float and boost chargers and invertors would be provided to derive uninterrupted 230 V AC power supply through suitably rated invertors. The batteries will be sized to cater to the loads for 30 minutes. This power supply will be used to feed essential services such as control, instrumentation, and annunciation etc. requiring UPS power. The type of batteries and chargers for the UPS system would be similar to that described above for the DC system. 6.12 LIGHTING The power station lighting system would comprise the following: 1) Normal 240 V AC Lighting System The lighting circuit in the normal 240 V AC lighting system would be fed through 415/433 volts, 3 phase, 4 2wire lighting transformers connected to a 415 V distribution system. Lighting transformers in each area in the power station would be fed from a convenient 415 V switchgear/MCC located nearby. About 20% of the lighting fixtures will be connected to receive emergency AC supply. During failure of normal AC supply, these fixtures will be fed from emergency AC supply derived from the DG set. 10 MW Biomass Based Power Plant 2) ABEIL Direct Current Emergency Lighting Direct current emergency lights would be provided at strategic points in the power station, viz., near entrances, staircases, the main control room, etc. These would be fed from the station 110 V DC systems and would be off when the normal AC power supply is available. These would be automatically switched on when the normal AC supply fails. The proposed illumination levels for various areas are given below: Area Control room Switchgear / MCC rooms Power house Outlying areas Transformer yard & switchyard Boiler Area Air/Gas compressors house, DM plant Workshop Canteen Stores Parking area and cycle stand Battery room Cable vaults Administration building and office rooms Roads 6.13 illumination Level 500 lux. 200 – 250 lux 200 lux. 50 lux. 10 – 20 lux. 50 lux 200 lux 300 lux 150 lux. 100 – 150 lux. 70 lux. 150 lux. 100 lux. 350 lux. 10 lux. CABLING All cables would be selected to carry the load current under site conditions, with permissible voltage drop. In addition, high voltage cables would be sized to withstand the short circuit current. The following type of cables would be used: For 11 kV generator system: 11 kV unearthed grade, single / multi-core, stranded aluminum conductor, cross linked polyethylene insulated, screened, Aluminum wire / galvanized steel wire armored and overall PVC sheathed cables conforming to IS 7098 Part II. For medium voltage and low voltage power cables: 660 / 1100 V grade, stranded aluminum conductor, HR PVC/PVC insulated, color coded. PVC sheathed and Aluminum wire/galvanized steel wire armored overall PVC sheathed cables conforming to IS-1554. 10 MW Biomass Based Power Plant ABEIL Control, protection, signaling and supervisory cables would be of 650/1100 V grade, annealed high conductivity stranded copper conductor, PVC / elastomer insulated and overall PVC/elastomer sheathed. Signaling and supervisory cables would be twisted pairs and screened wherever required. The inner and outer sheaths of all the above cables would have fire retardant capabilities. Cables would be laid in steel ladder type cable trays, suitably supported in the control building, STG building, other auxiliary buildings. In outdoor areas, cables would be laid in racks/built-up trenches or would be buried directly underground depending on the environment. 6.14 LIGHTNING PROTECTION SYSTEM A lightning protection system would be provided as per IS 2309 and Indian Electricity Rules. The protections would consist of roof conductors, air terminals and downcomers and would be provided for tall structures such as the STG building. 6.15 FIRE ALARM SYSTEM A fire alarm system would be installed to provide visual and audible alarm in the power station for fire detection at the incipient stage. This system would comprise manual call points located at strategic locations in areas which are normally manned, and automatic smoke and heat detectors located at important points such as the cable vault, the control room, switchgear room etc., to detect fire at an early stage, and provide visual and audible alarm. 6.16 FIRE CONTAINMENT Strategic areas in the plant would be separated by adequately rated firewalls. All openings for switchgears and cable entry would be sealed by fireproof seals to prevent spread of fire from one area to another. 6.17 COMMUNICATION SYSTEM In view of the high noise level in power plants, public address system is not recommended. For effective communication in the plant, automatic dial type telephones would be set up, having the following features: 10 MW Biomass Based Power Plant ABEIL 6.17.1 Inter-communication Telephones This system would comprise a telephone exchange and an adequate number of dial type hand set stations located in soundproof cabins with suitable flashing indication on top of it to indicate incoming call. The handsets in the control room would be provided with priority service facility to enable them to have immediate access to any of the handsets even if the handsets are already engaged. A private automatic exchange for communication with outside parties would also be provided. 6.17.2 Walkie-talkie Sets Walkie-talkie sets would be provided for key personnel. This would, however require special permission from the statutory authorities. 6.18 SAFETY EARTHING SYSTEM A Safety earthling system consisting of a buried mild steel conductor earthling grid would be provided for the power plant transformer yard, switchyard and other outlying areas. These would be connected to the earth grids in various buildings. The buried earthling grid would be further connected to earthling grid would be further connected to earthling electrodes buried under ground and located at representative points. The earth electrodes will be 40 mm diameter and 3000 mm long G.I rods and the main earth conductors will be 75 mm x 12 mm flats. The earth conductors when buried will be of mild steel and galvanized wherever exposed to atmosphere. 6.19 INSTRUMENTATION AND CONTROL 6.19.1 General The instrumentation & control (I&C) system proposed to be provided for the power plant would facilitate centralized automated and safe control of the power plant comprising of the Boilers, TG and their auxiliaries, condensate system and the cooling water equipment. The I&C system would be designed to ensure maximum efficiency, reliability, safety and availability so that optimum plant control could be achieved with minimum staff. The I&C system basically comprise of the following: 10 MW Biomass Based Power Plant ABEIL Functionally distributed microprocessor based I&C system Hard wired annunciation system Analytical Instruments Control desks, panels and system cabinets Power supply systems Local instruments 6.19.2 Distributed Instrumentation & Control System (DCS) The functionally distributed microprocessor based I&C system will have a hierarchically distributed structure and will integrate the various plant functions/systems such as measurements system, closed loop control system, open loop control system, sequence of events record, data base system, fault monitoring diagnosis, man machine interface etc., The above I & C system will have complete redundancy at processor level and communication level. At the sensor level, triple redundancy will be provided for all critical closed and open loops and single sensors will be provided for all other open and closed loops. For critical analog controls, Freudian selection from three measurements will be adopted while for critical open loops triple sensors with two out of three logic will be provided. Considering the high reliability of presently available processors, no further redundancy by way of hard-wired back up systems is proposed for open loops. 1) The DCS shall include the following main subsystem a) Control and Data Acquisition Subsystem for monitoring and control of process parameters like flow, temperature, pressure, level, power, current, voltage, analytical and status. The system shall also platform the plant supervisory functions like performance calculations, utility display, operator guidance message displays, logs, historical storage and retrieval etc., as specified in the subsequent chapters. b) Sequence & interlock, safety sub-system for monitoring and executing sequence operation, plant shutdown, interlocks and plant start-up. c) Operator / Engineer interface sub-system for operator guidance message displays and remote control, for tuning, configuring, programming and maintaining the system. d) Redundant Communication sub-system for interconnecting all the sub-system. e) The closed loop sub-system for continuous action on valves or other mechanical devices which alter the plant operating condition to bring the plant parameters to stable condition. 10 MW Biomass Based Power Plant f) ABEIL The open loop sub-system for operation on various inter related drives of plant safely, automatically and sequentially with the interlock and protection functions being available all the time under all conditions of operation to avoid mal-operation and to increase the plant availability. The system shall communicate with the temperature scanners, other system using PLC in serial communication mode using MODBUS protocol mode for monitoring/interlocking purpose. Functionality of these subsystems described in the corresponding chapters of the specification. Programmable Logic Controllers (PLC) or other special control devices shall be incorporated in the subsystems. These controllers shall be full informationally compatible with the DCS and shall allow an information exchange through a mutual DCS/PLC Data Highway and corresponding gateways. The list of alarms shall be sufficient for providing safe plant operation. 2) DCS General Characteristics a) Process Controller Fire Characteristics: The word “process controller file” refer to any combination of microprocessor associated memory, data acquisition and output devices which can be configured to perform a set of control and/or logic function, data acquisition, calculation and complex analog & discrete strategies. Means shall be provided to ensure the loss of power supply of any controller file does not result in loss of memory requiring manual reconfiguration, without error, during a power outage. b) The minimum design features shall include but not limited to the following: Redundancy shall be provided to the processing controller unit, power supply, I/Os for critical signals and communication modules. Redundancy shall also be provided for the data highway connections and serial interfaces. 10 MW Biomass Based Power Plant ABEIL Power supply used for interrogation with field devices shall also be redundant. All input and output modules shall be short circuit proof. The system shall be arranged so that the failure of any monitoring device or control components or spurious intermediate grounding in the signal path shall not open the signal loop nor cause the loss or malfunction of signal to other devices using the same signal and unrelated control loops. Necessary grounding facilities shall be available with the system; to take care of the earthling related problems. The design of the control system and the related equipment shall adhere to the principle of fail-safe operation at all system levels. Fail-safe operation signifies that the loss of signal, loss of excitation or failure of any component shall not cause a hazardous condition and at the same time occurrence of false trips. Upon restoration of power, the system will initialize itself to the established configuration and operation. The contractor shall provide detailed explanation on system features provided for power failure recovery. If a transmitter fails for an analog input value exceeding preset limits, means shall be provided to create an alarm and initiate appropriate protection action, such as transfer to manual or any other protective action. It shall be possible to assign high or low limits to each analog input; should a transmitter exceed either limit it shall be possible, through configuration, to transfer the affected protections of the system to manual. The system shall be able to withstand the electrical noise and surge as encountered in actual service conditions. Detailed marshalling cabinets shall be provided on as required basis for termination of all analog and digital inputs to the system and all analog and digital outputs from the system. A minimum of 20% spare terminals and a minimum of 20% additional modules shall provided in excess of the total requirement of the system design. 10 MW Biomass Based Power Plant ABEIL The system shall include self-surveillance and monitoring facilities, diagnostic features, tools etc., so that a failure / malfunction shall be diagnosed automatically, and giving the details to the operator stations. - Closed loop control execution shall be done within 250 msec. Sequence control/interlocks scan time shall be within 100 msec. All the open loop shall be scanned at the rate of less than 1 sec. DCS and PLC sampling time shall be adjusted after selection of the DCS and PLC types. Provision shall be included to produce a clear text, hard copy record of the detailed configuration of each file. 6.19.3 Annunciation System All abnormal operating conditions leading to unit shutdown will be simultaneously annunciated on the distributed microprocessor based control system as well as on the conventional alarm fascia units mounted on the control panel. Additionally, group control function (i.e. related to the sub-system as a whole or the main equipment) and individual equipment failure will be annunciated on the alarm fascia in the control panel. All individual or subsidiary control function failure will be annunciated on the DCS. For safety and protection logic's, contacts will be taken only from primary sensing devices, wherever feasible. Alarm contacts will be derived from the measurement signal using limit value monitors. 6.19.4 Control desk and panel The main control room in the control building will house the necessary control desks and panels. The various I&C system cabinets will be housed in the auxiliary control room adjacent to the main control room. The programmers console, computer cabinets, disc cabinets, printer's etc., will be located in the computer room. The control desks will incorporate CRTs with associated keyboard, illuminated push button for pumps, dampers, valves, TG control devices etc., auto manual stations, control switches, push buttons and synchronizing equipment for the boiler and TG. The control panels will be of simplex free standing type and will house indicators / recorders for all controlled parameters 10 MW Biomass Based Power Plant ABEIL and certain important non-controlled parameters, annunciation windows for all trip conditions and critical process conditions and ammeters for all large capacity motors. 1) Operator Stations The operator main interface to the control system shall be through operator stations consisting of color CRT’s mouse/trackball and keyboards. In addition certain softwareassigned and hard-wired recorders shall be installed if required. The operator station shall be suitable for Industrial Duty. Non-disk based Man-machine interface is preferred. 2) Capabilities Capabilities of a minimum 100 process graphic displays will be provided. This figure does not include detail display, group display, trend display, alarm list and maintenance displays. 3) DCS Highway Communication Requirements A redundant network communication link (data highway) shall be provided. The data highway shall provide the means by which process I/O, management information and control information is accessible to the operator interface and to all other control files and other highway devices. In the event of failure on one link, communication shall continue without disturbance to on-going operation. 6.19.5 Power Supply The complete I&C system would basically be designed to operate on 110 V AC supply which would be provided from the uninterrupted power supply (UPS) system incorporating necessary batteries, chargers, inverters etc., Certain other voltages required for the system, e.g. 24 V DC power supply required for contact interrogation, 48 V DC required for certain electronics cards, etc., will be derived from the 110V AC power supply made available from UPS system. 6.19.6 Local Instruments In addition to the above, all necessary local instruments such as pressure, temperature and level gauges, pressure, temperature, level and flow switches etc., will be provided in the power plant to enable the local operator to supervise and monitor the equipment operation. 10 MW Biomass Based Power Plant 1) ABEIL Temperature Instruments All temperature elements shall be provided with thermowells fabricated out of bar stock of minimum SS 304 material. Any pipe lines less than 4” nominal bore shall be increased locally to 4” size to install thermo wells. Local temperature gauge shall be generally mercury in steel filled type, weatherproof, with 150 mm dia dial gauge size, with shatterproof glass. Filled type with capillary tubing shall be minimum of SS 304 with stainless steel flexible armoring. The gauges shall have accuracy of ± 1 % FSD. Duplex type thermocouples or RTD shall be used wherever required. Adequate design care has to be taken to ensure thermal conductivity between thermowell and temperature measuring element. Thermocouples shall be as per ANSI MC 96.1 and shall be of 14 AWG magnesium oxide insulated grounded type. For temperature above 800 dec. the sheath shall made of Inconel 600. For temperatures above 800 dec. the sheath shall be made of SS 316. The thermocouples shall be selected as follows: a) b) c) Copper – Constantan (ISA-TYPE T) for ranges : - 200 to 200°C Chromel – Constantan (ISA-TYPE E) for ranges : - 200 to 600°C Chromel – Alumel (ISA – TYPE K) for ranges :- 600 to 1200°C RTD shall be three wire type with platinum element with 100 ohms resistance at 0 dec. calibrated as per DIN 43760. Twin element sensors, if used, shall have two separate conduit entries. 2) Pressure Instruments Pressure gauges shall have an accuracy of ± 1% of FSD. These shall be weather proof with dial size of minimum 150 mm and shall have features like screwed bezels, externally adjustable zero, over range protection and blowout discs. Pressure gauge sensing element shall be minimum of SS 316 and moving parts of SS 304. For important applications, 250 mm dial size shall be used. The glass shall be 10 MW Biomass Based Power Plant ABEIL shatter proof. Bidder shall provide snubber / siphon along with the pressure gauges wherever required. Pressure transmitters – smart type with a minimum turndown ratio of 1:30 with local indicator shall be electronic capacitance type or piezoelectric resistance type with minimum of SS 316 element material and with a over range protection of minimum 130% of range. Direct mounted pressure switch shall have element diaphragm or below of minimum of SS 316 material with ½” NPTF connection. 3) Level Instruments All gauge glasses shall be steel armored reflex or transparent type with body and cover materials of carbon steel as a minimum and tempered imported borosilicate glass. Differential pressure transmitter shall be used for level measurement. Level switches shall generally be external ball float type with flanged head. For remote level indication of drum, a separate level transmitter shall be employed which will be connected to a digital indicator with LED and barograph display. 4) Flow Instruments Flow measurement shall be with flow nozzles for Main steam flow and thin plate square edge concentric orifice plate mounted between a pair of weld neck flanges of minimum 300 pounds ANSI rating with flange taps for other measurements. The material of the orifice plates shall be SS 316. Meter runs shall have sufficient straight line as per BS-1042. DP type flow transmitter shall normally be electronic capacitance / piezo – resistive type and smart type with a turndown ratio of minimum 1:30 10 MW Biomass Based Power Plant 5) ABEIL Control Valves - Control valves shall normally be Globe type. Other types like butterfly valves, ball valves, angle valves, 3 way valves, etc., shall be selected as per service. - Minimum body and flange rating of control valves shall be as per piping class. - Body material, as a minimum, shall be as per piping specifications. - Valve seat leakage shall be as per ANSI B 15.104. - Leakage of shut down valves shall be Class VI, as a minimum and leakage for control valves shall be Class IV. - Valve positioners wherever used shall be side mounted force balance pneumatic type. - For electronic instrumentation, I/P converter shall be used along with pneumatic positioners. - Self actuating regulators for flow, pressure and temperature shall be used where loads are constant and shall be of precision controls. The power cylinders shall be double acting piston modulating type, trunnion mounted, with linear cam characteristics and provision for reversal action. The piston rod shall be hard chrome plated high strength steel. The driving equipment shall be in “STAY PUT” mode on air failure. The power cylinders shall be supplied with positioners, limit switches and position transmitters. 10 MW Biomass Based Power Plant 7 ABEIL ENVIRONMENTAL IMPACT AND POLLUTION CONTROL The type of pollution, which affects the environment, emanating from the power plant can be classified as follows: 7.1 Air pollution Water pollution Thermal pollution Noise pollution THE POLLUTANTS GENERATED FROM THE POWER PLANT ARE * * * * * Dust and particulate matter in the flue gas Fly ash from the hoppers Furnace bottom ash Effluent from water treatment plant Sewage from the plant CONTROL METHODS FOR AIR POLLUTION 7.2.1 Dust and particulate matters The pollution control norms stipulates a maximum dust concentration of 115mg//N.cu.mt. The proposed power plant will have an Electrostatic Precipitator (ESP), which will separate the dust from the flue gas and has an efficiency of 98%. The dust concentration is the flue gas leaving the ESP will be maximum 115 mg/Nm3. The dust concentration level in the chimney will be periodically monitored. Corrective steps will be taken, if the concentration is not as per the acceptable limits. 7.2.2 Sulphur-di-oxide and Nitrogen-di-oxide The main fuel in the proposed plant is Bio Mass, which does not have significant Sulphur in it. Hence, the Sulphur dioxide will not be produced. However, the stack height will be as per the local pollution control board stipulations. The nitrogen-di-oxides are not produced in firing. 7.2.3 Fly Ash and Bottom Ash The ash collected from the bottom of furnace (bed ash) and the ash collected in the air heater hoppers and ESP hoppers are taken to an ash silo through a series of conveyors. The ash from the silo will be disposed off to farmers, who can use the ash as manure for the crops. 10 MW Biomass Based Power Plant ABEIL CONTROL METHODS FOR WATER POLLUTION 1) Effluents from Water Treatment Plant The water drained from the water treatment plant will have to be treated so that the water let out is neutral (pH 7.0). To achieve this the water drained from the water treatment plant is pumped to a neutralization pit. The neutralization pit will have acid resistant brick lining. Depending on the quality of water collected in the pit, either an alkaline medium or acidic medium will be pumped into the pit to neutralize the water. 2) Boiler Blowdown In order to maintain the solid concentration in the boiler feed water, two types of blow down are employed in the boiler. One type is continuous blow down and the other intermittent blow down. The blow down water will be at a temperature of 100 0C. The quantity of blow down will be around 1.5 tph. This water can be taken to the effluent ponds, where it will get cooled naturally. 3) Sewage from the Power Plant Buildings The sewage from the various power plant buildings will be taken to a common septic tank through trenches. The sewage from the septic tank will be disposed off through concrete trenches. As the sewage is taken in trenches the soil will not get contaminated. 7.3 CONTROL METHODS FOR THERMAL POLLUTION The water used in the surface condenser to condense the steam will be cooled in a cooling tower of either induced or forced draft type. The water let out from the cooling tower will have a temperature very close to the ambient. CONTROL METHODS FOR NOISE POLLUTION The major source of noise pollution in the power plant power plant is from the following: Rotating equipments like ID, FD and SA fans - Feed pumps Boiler and superheater safety valves Start up vent Steam turbine 10 MW Biomass Based Power Plant 7.4.1 ABEIL DG Sets As per OSHA standards, the sound level from the rotating equipments shall be 85 to 90 dBA. The rotating equipments will be designed to achieve this. The start up vent, safety valve outlets and the DG sets will be provided with silencers to reduce the noise level to the acceptable limits. The power house building will be constructed suitably to keep the noise level within the acceptable limits. Promoters are aware of their social obligations and will be establishing an effluent treatment plant to treat its liquid effluents. The Pollution Control Board norms for air, water and sound is given below: Tolerance Limits for Discharge of Trade Effluents Tolerance Limits for discharge of Trade Effluents Characteristics Inland Surface Water On land for Irrigation 100 200 2100 2100 5.5-9.0 5.5-9.0 40 at the point of discharge 45 at the point of discharge Oil and grease (mg/lit.) 10 10 Biochemical Oxygen Demand (BOD) for 5 days at 20 0C 30 100 Suspended solids (mg/lit.) Dissolved solids-Inorganic (mg/lit.) PH value Temperature (0C) Chemical (mg/lit.) Oxygen Demand (COD) 250 Chloride (as CL) (mg/lit.) 1000 600 Sulphates (SO4) (mg/lit.) 1000 1000 10 MW Biomass Based Power Plant ABEIL Ambient Air Quality Standards Concentration (mg/m3) Characteristics SPM So2 CO NOX Industrial and mixed use 500 120 5000 120 Residential & Rural 200 80 2000 80 Sensitive 100 30 1000 30 Emission Standards for Boilers Capacity of Boilers (tons/h) Particulate Emission Limits (mg/Nm3) Less than 2 1600 2 to 15 1200 More than 15 150 This requirement is applicable for boilers using any type of solid fuel. In the case of industries where particulate emission control are adopted to the limits prescribed, the stack height can be relaxed to H = 74 Qp0.27, where Qp = Particulate emission in Tons per hour. Permissible Noise Levels Exposure Duration per Day Sound Level dB (A) 8 90 6 92 4 95 3 97 2 100 1 102 10 MW Biomass Based Power Plant ABEIL 8. POWER PLANT LAYOUT 8.1 CRITERIA FOR THE POWER PLANT LAYOUT The general criteria for the power plant layout are as follows: 8.2 a. The main steam piping to the turbogenerator shall be as short as possible. This is to avoid excessive pressure and temperature drop in the steam line, which would affect the turbine performance. Also, the material used will be alloy steel, which is very costly. b. The length of the HT cables from the TG hall to the switchyard shall be minimum. c. The length of the slat conveyor from the storage area to the boiler etc. has to be minimum. This is to reduce the auxiliary power consumption and the cost of the equipment. d. Fuel storage yard shall be far away from the equipment so that there will not be any dust nuisance. e. The switchyard, ash handling area and Fuel storage handling area has to be accessible by roads. BOILER LAYOUT The layout for the boiler 1 x50 tph will be on the eastern side of the Plant. The feeding system for fuel will be located in the boiler front. The operating floor for the boiler will be concrete and at a elevation of 5 Mts. from the ground level. The boiler will be provided with 800 mm width floors, wherever required. The boiler will be top supported. The economizer and the air heaters will be located just after the boiler bank one over the other. The air heater will consist of two blocks. Suitable space will be provided and provision made for cleaning of the air heater tubes. The boiler feed water pumps will be located below the deaerator storage tank, at the ground floor of TG building. The feed water control station will be located in the boiler operating floor. The chimney height will be decided based on the local pollution control norms. 8.3 TG BUILDING LAYOUT The TG building will be located adjacent to the boiler area. The TG building will be sized to accommodate the 11 MW turbogenerator and its auxiliaries. The turbine will be located at an elevation of 6 Mts. from ground level. The building will be steel structure with regular roof with side cladding. The floors will be made from pre cast slabs, which gives better appearance and 10 MW Biomass Based Power Plant ABEIL the installation time will be less. The condenser will be located just below the TG at ground level. The condenser extraction pumps and the evacuation system will also be located at the ground floor. The TG building will be provided with a Crane for lifting the turbine parts for maintenance. 8.4 ELECTRICAL AND CONTROL ROOMS Both the electrical and control rooms will be located in the TG building. The battery charger room and office will also be located at this floor at elevation 6 Mts. The location of the control room will be such that the boiler and the turbine will be clearly visible from the control room. 8.5 FUEL STORAGE AREA Power plant shall have a planned fuel storage yard to store the fuel quantity 8.6 ASH HANDLING SYSTEM The ash handling system consists of scrapper conveyor, belt conveyors and screw conveyor. The ash from the travelling grate hopper, plenum chamber, air heater hopper and the ESP hoppers will be collected and conveyed to a main ash silo which will be located close to the chimney. 8.7 SWITCH YARD The biomass power plant shall have a well planned power evacuation switchyard of 132 kV. 10 MW Biomass Based Power Plant ABEIL 9. PROJECT SCHEDULE AND IMPLEMENTATION 9.0 PROJECT IMPLEMENTATION 9.1 PROJECT SCHEDULE The schedule for the implementation of the biomass power project of Amrit Bio Energy and Industries Ltd Jagi Road in Mayong Circle of Marigaon district in Assam with a capacity of 11 MW is enclosed. The project schedule indicates the various activities, which includes Engineering, Detailed Engineering, Procurement, Erection and Commissioning of the project. The project needs 18 months from the date of financial closure and placement of orders for critical items like, Boiler and Turbine. 9.2 PROJECT MANAGEMENT Engineering Management system, is a functional strategy developed to meet the tasks of the engineering division keeping in view the overall project and the company’s objectives. It is a set of planned and well-defined systems and procedures for each activity and subactivity for engineering tasks to complete the project from feasibility, conceptual design, detailed engineering upto commissioning and operation of the plant. The following major constituents of the Engineering management systems are being used for the execution of this project: Division of Responsibility & Authority, which defines the role and responsibilities against the tasks identified for the engineering services, project engineering and Quality Assurance & Inspection services in various disciplines such as Civil, Mechanical, Electrical, Controls and Instrumentation. Engineering and Monitoring System covers identification of various Engineering activities and sub-activities both pre-award and post-award of the main plant equipment for this project. The monitoring of the progress reports and look ahead planning is made on the basis of Scheduled dates against the actual date of completion of the activities or anticipated dates to complete the activities for every month. 10 MW Biomass Based Power Plant ABEIL Vendor Drawing Control System provides the status reporting and monitoring for Vendor submitted drawings, which give the clue to identify the vendor drawings, falling in different approval categories, drawings which are over due for submission by the vendor, drawings which are pending for transmittal of the comments / distribution etc. This is very important from the point of vendor progress monitoring. Drawing Control Procedure elaborates how to control drawings received from the vendor or developed in-house. The system identifies how the drawings are to be processed and who has the authority to approve these drawings / documents and transmittal of the drawings to the site office concerned, project consultant and to the vendor. 9.2.1 System for Feed Back This project has got a group of field engineers, which will perform the engineering tasks at site office and support the engineering group concerned at the Head office. The engineering group is the focal point for all engineering issues and the field problems pertaining to engineering. They also receive drawings and documents and distribute amongst the various departments of the project, provide any clarification or modification of any nature and give the feed back during construction and commissioning stage of the project. They are also responsible to generate project drawings and data to AS-Built information. 9.2.2 Computer Aided Design The use of Computer Aided Design (CAD) for development of engineering design and drawings is being emphasized by the company. Presently almost all the engineering tasks are performed using CAD with the software programs already available and developed within the company. 9.2.3 Assurance of Engineering Quality With the use of standardized document, model technical specification, design guidelines and checklist, the required engineering quality is possible to achieve. Cost Control: In order to have control on the overall cost of the project, the project is split into no. of packages and the cost is worked on the basis of the price data obtained from various vendors, as well as on the basis of the trends of the cost variations in the present day market. 10 MW Biomass Based Power Plant ABEIL Time Control: This is achieved during project planning and monitoring system. Monitoring is done at every place - Regional office, Consultant’s office and the Site office. 9.3 CONSTRUCTION MANAGEMENT 9.3.1 Power Plant and Facilities Site activities of project group shall be carried out as per Consultants, Construction Management Manual advice prescribing systems and procedures, their scope of responsibilities, inter-relationships as outlined in the various chapters. Organization tasks and framework for construction management has been organized in four distinct headings namely: a) b) c) d) Construction Management Tasks. Construction Management Organization. Functional Boundaries & Scope of Work. Construction Management Interface. The Construction Management Tasks cover the following: i) ii) ii) iv) v) vi) vii) viii) ix) x) xi) 9.4 Infrastructure development Construction execution supervision Safety and security Planning, Scheduling, Reviewing and Control. Field quality surveillance Site contracting Material Management Cost control Liaison with external agencies Personnel administration and welfare Finance and Account. CONSTRUCTION MANAGEMENT ORGANISATION Construction Organization at project site is headed by a project manager, a senior executive from the plant assisted by a consultant engineer from the consultant side. The project manager is assisted in carrying out site functions by functional heads viz. Head of project construction, planning, scheduling and project co-ordination. Head of Personnel Management, which includes finance and accounts. 10 MW Biomass Based Power Plant ABEIL The construction, erection and commissioning is carried out by the contractors with the technical supervision from the Consultant / Customer Engineers in association with the representatives of equipment manufacturer to the satisfaction of the plant engineers. The tools and plants for construction are brought by the contractor. The functional boundaries and scope of work cover the following areas: i) ii) iii) iv) v) vi) vii) viii) 9.5 Construction planning and scheduling, Civil construction Equipment erection Site contract group, which provides centralized services at site for awarding work contracts. Material management functions cover activities of material planning, procurement, storage issue etc. Site service is a centralized service group which provides and maintains all common construction facilities, tools, plants and construction utility services. Personnel and Administration group at site is guided by the HRD division at Head quarters and it is responsible for man power planning, recruitment etc. Finance & Accounts. INFRASTRUCTURAL FACILITIES & CIVIL SYSTEM The existing biomass power plant has well developed infrastructure facilities and civil for structures like office building, power plant buildings and other storage yards etc. Separate infrastructure facility is not required for this power plant. 9.6 QUALITY ASSURANCE & INSPECTION The procedure for the Quality Assurance and Inspection is evolved by the consultant in coordination with the power plant engineers. In order to ensure high reliability and better performance, quality assurance programs have been developed for all packages. For this purpose, bid documents for all contract packages stipulate that the bidders have to submit their own quality assurance programs for manufacturing and field activities. They include identification of a) b) c) d) e) f) Quality organization. Documentation control. Procedure for purchase of materials, parts, components and selection of subcontractors, services including vendor analysis, source inspection, raw material inspection etc. Control and testing of calibration, testing of measuring and testing equipment. Handling, storage and delivery. Maintenance of records to meet all the contractual requirements. 10 MW Biomass Based Power Plant ABEIL All the contractors are required to develop such QA programs after the review of all technical specification and contract requirements. The QA programs of the vendors are taken into consideration during bid evaluation by the consultants. At the time of finalization of the agreement with the successful vendors, a detailed quality plan setting and the quality practices and procedures, relevant standards and acceptance level for all the components of all the equipment will be mutually discussed and agreed to. Further, consultant / client witnesses tests / inspection etc as per the customer hold points (CHP) to be selected by the consultant in quality plans, beyond which the work will progress only with the consent of the consultant. Apart from this, the quality surveillance of the system and procedures of the contractor’s quality control organization will be carried out for monitoring the implementation status. In addition, the consultant / customer will carry out quality audits on the systems and processes for the areas of manufacture and field activities to determine the effectiveness of implementation and to ensure conformance to code, contract and procedure requirements. Control of quality in the field right from the stage of material receipt till final commissioning will be effected by the field quality control group. This group will be independent of actual execution schedules and costs and will function under technical guidance from the consultant’s QA group. 9.7 MAN POWER TRAINING & PLACEMENT The existing power plant is having proper Organization structure. The existing biomass power plant has well trained technicians and other labors. This new plant needs some more technicians and labors for its operation and maintenance. 10 MW Biomass Based Power Plant ABEIL 10 MW Biomass Based Power Plant ABEIL 10 MW Biomass Based Power Plant ABEIL 10. OPERATION AND MAINTENANCE The proposed Organization structure for the operation and maintenance (O&M) of the power plant is presented in the exhibit. In order to ensure a high level of performance of the power plant, it is proposed to induct experienced O&M engineers from the very beginning of the project. 10.1 BASIC STRUCTURE OF THE O&M TEAM The basic structure and the broad functional area within the O&M organization would be as follows: The Plant Manager would have the primary responsibility for the O&M of the power plant. The organization will comprise of four broad functional areas viz. Operation, maintenance, technical and administration. The basic duties covered under each of these functional areas would be as follows: 10.1.1 Operation Operation of main generating equipment, fuel handling systems, water systems including water treatment plant, switch yard and other auxiliary plant. Except for the Power Station Superintendent all other operating personnel would work on three shift basis. Shift personnel manpower planning for key areas has been generally done on 3+1 concept, to take into account leave taken by shift personnel. The day to day operation of the power plant will be controlled by the Manager who will be assisted by the Control room operators and shift engineers. 10.1.2 Maintenance Maintenance of mechanical and electrical plant, control systems, buildings, roads, drainages and sewage systems etc., Operation of the plant workshop, planning and scheduling maintenance works and deciding the requirement of spare parts. The Plant Manager will be assisted by departmental engineers, who take care of the maintenance aspects of all mechanical, electrical and I&C requirements. Trained technicians will be employed to assist the maintenance group in day to day maintenance of the plant 10 MW Biomass Based Power Plant ABEIL 10.1.3 Administration The main responsibilities of this department will be as follows: 10.2 Purchase Plant Security Liaison with local labor officers Stores management Finance & Accounts Medical Services Secretarial & Clerical Transport services HRD and Training FACILITIES TO BE EXTENDED TO THE EMPLOYEES The number of employees required for the proposed power plant will be around 40. The personnel required for administration and finance & accounts also will be provided. The following facilities will be provided in the power plant: 10.3 Administration building and technical office Construction offices and stores Time and security offices First aid and fire fighting station Canteen and welfare center Toilets and change rooms Car parks and cycle/scooter stands. STATION OPERATION PHILOSOPHY The power generated from this plant is exported to ASEB Grid. Necessary software and hardware features are required for effective operation and maintenance management system. Software system manages and provides the information needed to manage daily operations, improve labor productivity, reduce maintenance costs, and monitor preventive and predictive maintenance programs. Through more effective scheduled and preventive maintenance, the costs associated with emergency breakdowns can be greatly reduced. This includes savings from reduced payroll overtime, fewer defective products and reduced down time losses from disrupted production schedules. 10 MW Biomass Based Power Plant 10.4 ABEIL STATION MAINTENANCE PHILOSOPHY The based power plant maintenance philosophy is based on the following aspects: 10.4.1 Ordinary Maintenance Ordinary Maintenance, which covers routine checking and minor and refurbishment activities to be performed according to operating manuals on component / equipment in operating conditions. 10.4.2 Emergency Maintenance Emergency Maintenance, which is a corrective maintenance to be performed when a significant failure occurs. To minimize forced outages duration, an effective Emergency Maintenance must be supported by: A proper stock of spare parts. Permanent monitoring and diagnostic systems for main components. 10.4.3 Maintenance Plan and Scheduled maintenance Scheduled maintenance is carried out according to maintenance plan, which should be discussed and optimized according to the needs of the customer/client. The maintenance plan is based on scheduled outages for the following components: 10.5 Boiler Steam Turbine Alternator Switchyard equipment MAINTENANCE MANAGEMENT SYSTEM The maintenance of this plant will be carried out as per the above philosophy. This system aims at maximizing the availability of the plant, while ensuring minimum maintenance cost and safety of the plant and personnel. Meetings are convened by various departmental Heads to accelerate the decision making process and to lay down the priorities and guidelines for maintenance work to be taken up. 10 MW Biomass Based Power Plant 10.6 ABEIL SPARE PARTS MANAGEMENT SYSTEM The primary objective of spare part management system will be to ensure timely availability of proper spare parts for efficient maintenance of the plant without excessive build-up of nonmoving and slow moving inventory. The spare parts management system for this project will cover the following areas: 10.7 Proper codification of all spares and consumables. Spare parts indenting and procurement policy. Ordering of critical mandatory and recommended spares. Judicious fixation of inventory levels and ordering levels for spare parts based on experience. Development of more than one source of manufacturer/ supplier Whenever practicable. AVAILABILITY OF O & M MANUALS All contracts include provision of at least 6 sets of detailed O & M manuals, which will be distributed to all departments concerned well in advance from the commissioning date of the power plant to avoid problems in preparation of commissioning documents as well as proper installation and commissioning procedures of various equipment. 10.8 SPECIAL TOOLS AND TACKLES All contracts will include the provision for supply of one set of all types of special tools and tackles, which are required for installation, commissioning and proper maintenance of plant and equipment. 10.9 OPERATION REQUIREMENTS With the completion of the official hydraulic test of the boiler, the pre-commissioning and commissioning activities start. Pre-commissioning checks of the individual equipment will lead to safe commissioning of the equipment. Installation procedure and commissioning procedure as stipulated in the O & M manuals supplied by the various equipment suppliers shall be carefully followed. Wherever possible, it is advisable to keep the vendor’s representative at site for commissioning the auxiliary equipment of the power plant. However, the boiler, turbo-alternator and other critical equipment have to be commissioned by the supplier itself, as the performance guaranties lie with them. 10 MW Biomass Based Power Plant ABEIL Controls and Instrumentation system along with alarm and trip interlocks should be put into operation to safeguard the equipment as well as the operating personnel. 10.10 CHECKLISTS AND PROTOCOL A detailed checklist for the various equipment, supplemented with the checklist submitted by the supplier shall be drawn and logged for future reference. This will also form part of the plant’s base history / datum. Whenever an equipment in commissioned, the important parameters of that particular equipment should be observed for a period of eight hours and the readings shall be logged as per the log sheets. These activities shall be performed in the presence of the customer / consultant and a protocol shall be signed. 10.11 ORGANISATION LEVELS & GRADING OF POSITIONS Every position in an organization is graded within these decision-taking bands based on a short description mentioned below. These grading levels range from A Band (unskilled labor) to E- Band (Top Management). The definitions for the classification of different positions are as follows: A-Band Basic elementary decisions where the options and alternatives are limited. Information required by the worker is limited, simple, and easy to understand. It mainly requires unskilled labor and training requirements are minimum. B Band Operational decisions in a logical sequence of elements Experience and practice is essential for taking decisions in this band. Training normally takes a few months. C Band Process decisions in a systematic sequence of operational activities. Problems have to be diagnosed and the best solution form a range of alternatives needs too be selected and implemented. A broad spectrum of intensive formal education, as well as experience, is required for these jobs. D Band Interpretative decisions by middle Management. E Band Strategic decisions by Senior Management. 10 MW Biomass Based Power Plant ABEIL . STATUTORY CLEARANCES REQUIRED The following are the statutory clearances required for the proposed power plant of ABEIL at Jagi Road in Mayong Circle of Marigaon district in Assam. Details of Approvals are given in the notification, which is enclosed. 11.1 Approval from AEDA ABEIL shall file an application with AEDA for sanction of project as per the Government of Assam notification of power projects. ABEIL, will also need to enter an agreement with AEDA as facilitator. 11.2 Tariff Fixation from AERC ABEIL Ltd,should file an affidavit with AERC for obtaining the tariff. 11.3 Power Purchase Agreement with ASEB After obtaining the approval from AEDA, and ASEB, ABEIL,need to enter Power Purchase agreement with ASEB. 11.4 Approval for Parallel Operation Approval of the Government of Assam through ASEB for parallel operation of generating set with ASEBGrid, shall be sought. Scheme has to be approved by ASEB Inspectorate. 11.5 Pollution Control Board Initially consent to establish to be obtained from the Assam State Pollution Control Board for the air pollution, water pollution and noise pollution. The source of pollution and the control methods proposed are discussed in the chapter, “Environmental Impact and Pollution Control”. On commissioning, consent to operate need to be obtained from Pollution Control Board. 11.6 The Land Use Clarification Clearance From Govt. of Assam Approval for the layout and buildings of the power plant is required from the Town Planning Department of Govt. of Assam. 10 MW Biomass Based Power Plant 11.7 ABEIL Approval for the Electrical Installation The electrical installations like transformers, switch yard equipment etc., shall be approved by the Chief Electrical Inspector, for the safety features, location etc. 11.8 Boiler and Pressure Part Components The approval from the Chief Inspector of Boilers, Assam is required for the installation and operation of the boilers, steam and water piping. 11.9 Ground Water Board The make up water for the power plant is proposed to be pumped from the nearby take and borewell available in the site. Clearance from the Central Ground Water Board is required for using the ground water. 11. 11 Irrigation Department It is better to have the permission from Irrigation department for drawal of water from the canals. 11.12 Information to MNES Ministry of Non Conventional Energy Sources, (MNES) extends the capital subsidy. Promoter need to apply to MNES through AEDA, after obtaining the loan sanctioned from Financial Institution. MNES needs the following documents enclosed to their application and check list: a. b. c. d. e. f. Detailed Project Report Project Approval from AEDA Power Purchase Agreement with ASEB Consent to Establish from Assam State Pollution Control Board. Sanction Letter from Financial Institution Appraisal Report from Financial Institution MNES gives the principal approval initially, and sanctions the Capital subsidy after commissioning. MNES is yet to issue administrative approval. 11.13 Duty Exemption: Govt of India had issued the notification, exempting the Excise Duty and Custom Duty for setting up these plants. Govt of India Notification is already given in Chapter 1. Promoter should take advantage of this. Suppliers of the equipment are need to be taken, Duty Exemption Certificates from MNES. 10 MW Biomass Based Power Plant ABEIL 12. COST ESTIMATES 12.1 GENERAL ABEIL is planning to install 11 MW Biomass based Power Plant at Jagi Road, Mayong Circle, Marigaon District. As this plant is situated in Assam, transportation charges, erection and commissioning charges are more compared to the other parts of India. Even Govt. of Inia gives the special incentives for the North Eastern States. This chapter deals with the estimates of the total cost of the power project. The estimate is also based on the budgetary offers received from the various manufacturers for the major equipment and in house cost data compiled for power plants. Contingency provision has been made, but not the escalation, as the project is expected to be implemented within short period. Ministry of Finance, Govt of India, had issued the notification No: 33/2005 – Central Excise dated 8th Sept 2005, exempting the custom duty and excise duty for the plat and machinery required for biomass based power plants. Hence, the project cost is exclusive of these duties. This chapter deals with the estimates of the total cost of the power project. The estimate is also based on the budgetary offers received from the various manufacturers for the major equipment and in house cost data compiled for power plants. Contingency provision has been made, but not the escalation, as the project is expected to be implemented within short period. The cost of the power plant given in this chapter, covers all the costs associated with the construction of the plant, and includes the civil construction cost, cost of equipment for power generation, cost of auxiliaries and utilities. The total cost is arrived at by adding to this cost, the pre operative expenses inclusive of project design and engineering, start up and training expenses, interest during construction and the margin money for working capital. Table 12.1 to 12.4 gives the details of the project works cost estimate including Civil, Mechanical and Electrical cost. Table 12.5 to 12.9 gives the details of the estimate of the project cost which includes the contingency, preoperative expenses including the IDC and working capital margin. The table also gives the drawl of the term loan during the project construction period and the calculation of the IDC is based on that. It is presumed that the 10 MW Biomass Based Power Plant ABEIL term loan disbursement is proportional to the amount of the equity invested. Table 12.10 gives the consolidated details of the total cost of the project. 12.2 LAND AND SITE DEVELOPMENT This company is planning to procure the land with the help from Revenue Officials of Morigaon District. The proposed site is just behind 132 kV Substation of Jagi Road , Mayong Circle. . Table 12.1 – Land and site Development (Rs. Lakhs) Particulars Amount Cost of Land to be acquired 45.0 Cost of leveling and development 10.0 Cost of laying of roads Internal roads for the Factory 5.0 Approach road connecting the Main Road 5.0 Internal roads for the Township 5.0 Cost of fencing/compound wall Cost of Gates Total 12.3 15.0 2.0 87.0 CIVIL AND STRUCTURALS The civil work includes the earthwork and concrete work for the power house building, equipment foundations, tanks, cooling tower basin etc. The cost of laying of in plant roads, fencing drains and sewers is also included as part of civil cost. The RCC/structural steel work for the turbogenerator building is also included under the heading of Civil Works cost. No piling has been envisaged for the building as well as for equipment foundations and only open foundations are considered. The civil work quantities and the cost of civil are only estimates and will have to be suitably modified and firmed up after the equipment supply is finalized and adequate data regarding the loading dimensions of equipment are available from the manufacturers and suppliers during the engineering stage, and also on the actual soil conditions encountered at different stages of construction. The estimates given here are based on the soil bearing capacity of 35 Tones/Sq. mtr at 3.5 meter depth. 10 MW Biomass Based Power Plant ABEIL The total cost of civil works including equipment foundations, buildings, cost of land development, roads, and miscellaneous foundations etc is estimated at Rs. 317.78 Lakhs. Table 12.2 Civil Works Cost Estimate Sl. No. Description Unit Quantity Rate Rs. Cost (Rs. Lakhs) 7.0 Power plant building 7.1 Excavation m³ 2015 120 2.42 7.2 Backfilling with approved earth m³ 1495 108 1.61 7.3 PCC m³ 195 4560 8.89 7.4 RCC grade M20 including formwork m³ 371 6000 22.23 7.5 Reinforcement Steel T 36 48000 17.47 7.6 Brick work m³ 520 2400 12.48 7.7 Windows, doors etc. m² 260 2160 5.62 7.8 Plastering m² 13351 108 14.42 7.9 Flooring m² 1729 600 10.37 7.10 Painting m² 8671 84 7.28 7.11 Structural Steel T 87 43200 37.63 7.12 Grating m² 104 1800 1.87 7.13 Plumbing LS 1.50 7.14 Precast RCC Roof Slabs, 125 mm thick LS 1.50 7.15 Weathering Course LS 1.50 7.16 False ceiling LS 1.00 8.0 Foundation for boilers, turbogenerator, transformers & other equipment 0 8.1 Excavation m³ 2925 120 3.51 8.2 Backfilling with approved earth m³ 2470 108 2.67 8.3 PCC m³ 135 4560 6.17 8.4 RCC grade M25 including formwork m³ 527 6000 31.59 8.5 Reinforcement Steel T 60 48000 28.70 8.6 Micellaneous (Embedments, Foundations etc.) LS 9.0 Cooling tower basin, raw water tank, pumps and miscellaneous foundations 0 9.1 Excavation m³ 1300 120 1.56 9.2 Backfilling with approved earth m³ 1040 108 1.12 2.20 10 MW Biomass Based Power Plant ABEIL 9.3 PCC m³ 91 4560 4.15 9.4 RCC grade M20 including formwork m³ 455 6000 27.30 9.5 Reinforcement T 35 48000 16.85 10.1 Excavation m³ 1950 120 2.34 10.2 Backfilling with approved earth m³ 1560 108 1.68 10.3 PCC m³ 137 4560 6.22 10.4 RCC grade M20 including formwork m³ 644 6000 38.61 10.5 Reinforcement T 59 48000 28.08 10.6 Embedments, flanges, ladders & platforms T 20 50400 9.83 10.7 Refractory lining millboard etc. LS 6.00 12.0 Temporary stores, office building, garage, etc. LS 4.20 Misc. civil works for conveyor supports, ducitng 13.0 supports, fuel handling system etc. LS 16.80 Factory buildings for auxiliary services like water 14.0 supply, laboratary, workshop LS 14.00 15.0 Administrative buildings & guest house LS 25.20 Misc. non-factory buildings like canteen, time 16.0 office, change room LS 11.20 17.0 Garage / Parking LS 2.80 18.0 Architect fees LS 35.00 10.0 RCC Chimney and foundation 11.0 Switch Yard Civil Foundation TOTAL 12.4 475.58 MECHANICAL AND ELECTRICAL WORKS The project cost estimate includes the cost of all other auxiliary systems of the power plant, like the cooling water system consisting of cooling tower, and the pumps, DM water system, compressed air system. AC and ventilation system, fire fighting etc. Steam piping, high pressure and low pressure, feed water piping, cooling water piping and all other piping of the power plant. The 132 kV transmission lines for evacuating power are also considered in the electrical estimates. The cost of the generator transformer for stepping up the generated voltage to the exportable voltage level, the distribution transformers for meeting the power requirement at 415 level for power plant, the power control center for feeding power to the plant, the cables 10 MW Biomass Based Power Plant ABEIL and bus ducts, complete earthling of the plant and lighting are included in the works cost estimate. Cost towards the plant erection, testing and commissioning have been included in the equipment cost indicated. Also the cost estimates given in the report are inclusive of the taxes and duties, freight and insurance. The cost of the two years spares is estimated to be two percent of the mechanical and electrical equipment cost which is included in the cost of the equipment included in the works cost estimate. The total cost of the mechanical and electrical works is expected to be around Rs. 3236 Lakhs Table 12.3 Machinery Cost including Electricals Equipment/ Machinery Steam Turbine & generator (11 MW bleed cum condensing) (Rs. in Lakhs) Amount 1050.00 Boiler & BOP Boiler 1200.0 DM plant 30.0 Cooling water system and piping 60.0 Fuel handling system 140.0 Ash handling system 45.0 EOT Crane 25.0 Substation 210 Plant electricals 50.0 Cooling tower 60.0 Fire protection 25.0 Air conditioning & Ventilation 40.0 Utilities like water & comp.air 50.0 Erection 80.0 Transmission lines system Miscellaneous like weigh bridge, chippers etc., Total 121.0 50.0 3236.00 10 MW Biomass Based Power Plant ABEIL Table 12.4 Electrical Cost Estimation Sl. No Description Amount in Lacs 1 11 KV Panel 1 37.00 2 NGR and Surge arrestor 1 5.00 3 33 KV SF6 Breaker 1 8.00 4. 33 KV control & Relay Panel 1 8.00 5 33 KV Isolator 2 4.50 6. CT 1 1.00 7. PT 1 1.00 8. Power Transformer – 12.5 MVA 1 80.00 9. Auxiliary Transformer – 1.25 MVA 1 20.00 10. MCC Panel 1 7.50 11. 110 Volts Battery set 1 2.50 12 110 Volts Battery Charger 2 10.00 13 DCDB 1 1.00 14 UPS 1 1.00 15 Cables 1 10.00 16 Lighting materials 1 2.00 17 Earthing 1 2.00 18 Steel Structure in tonnes 5 3.50 19 Erection Charges - 6.00 Total 12.5 Quantity 210.00 CONTINGENCIES A provision of about 5% of the costs of the civil and structural work, mechanical and electrical equipment and other costs has been provided towards the contingencies, during the construction of project. This contingency provision works out to Rs. 220.92 Lakhs. 10 MW Biomass Based Power Plant ABEIL Table 12.5 Contingencies Particulars Cost Site development Contingency Provision 87.00 5% 4.35 475.58 5% 23.78 Plant & Machinery 3236.00 5% 161.80 Misc. Fixed assets 92.00 10% 9.20 435.75 5% 21.79 Buildings Pre-Operative Expenses Total 12.6 (Rs. in Lakhs) Amount 220.92 NODAL AGENCY’S REQUIREMENT AEDA is the nodal agency to give approval to this project. They will also act as coordinators for this project. As the policy is not yet announced, provision for nodal agency fee is taken as Rs. 2.00 lakhs. 12.7 MISCELLANEOUS FIXED ASSETS The cost of Miscellaneous fixed assets is estimated at Rs.92 Lakhs based on the budgetary estimate received from the suppliers. The details are as under: Table 12.6 Miscellaneous Fixed Assets Particulars The laboratory equipment 30.00 Workshop equipment 30.00 Vehicles 20.00 Furniture 5.00 Office equipment 7.00 Total 12.9 Amount Rs in Lakhs 92.00 WORKING CAPITAL MARGIN The working capital shall meet the requirements of raw material costs and the receivables. 70% will be bank finance and the 30% will be the margin money to be capitalized. The financial analysis takes into consideration an interest rate of 12.25% for working capital financed by bank. Working capital requirement in first year is Rs. 424.09 Lakhs. The total 10 MW Biomass Based Power Plant ABEIL requirement of margin money for working capital is estimated at Rs. 106.02 Lakhs on the basis of raw material for 180 days and the debtors for 60 days in first year. On the above basis, the total working capital loan requirement for the first operation year is estimated at Rs 318.07 Lakhs. In third year working capital requirement increases to Rs.576.50 lakhs and the requirement of working capital margin money increases to Rs. 148.49 Lakhs. Table 12.7 Working Capital Particulars / Years (Rs. in Lakhs) 4th year 5th year 1st year 2nd year 3rd year 125.53 147.77 171.23 176.36 181.65 7.50 7.88 8.27 8.68 9.12 Sundry Debtors 2 months 291.06 242.62 397.01 408.92 421.19 Total Current Assets 424.09 498.26 576.50 593.96 611.96 Less: Margin Money (25%) 106.02 124.57 144.13 148.49 152.99 Bank Finance Required 318.07 373.70 432.38 445.47 458.97 Current Assets Holding level in months Raw-Material 6 months Stores 6 months 12.9 INTEREST DURING CONSTRUCTION (IDC) The interest during construction period is capitalized to calculate the project cost. The IDC is calculated considering the phasing of the capital expenditure given below. 12.9.1 Phasing of Capital Expenditure The project construction period is 18 months from the date of ordering the main equipment. The following gives the phasing of the capital expenditure on quarterly basis from the date of ordering of the boiler and the turbo generator, which contributes the major expenditure. Interest on loan for the construction period is taken as 12.25%. Interest during construction is rounded off to Rs.412.00 Lakhs. Table 12.8 Phasing of Capital Expenditure & IDC Quarter (Rs. in Lakhs) Term Loan Interest till the date of Completion Capital Expenditure Equity 1 1421.48 355.37 1066.11 171.90 2 947.65 236.91 710.73 96.61 10 MW Biomass Based Power Plant Quarter ABEIL Capital Expenditure Equity Term Loan Interest till the date of Completion 3 710.74 177.68 533.06 63.97 4 710.74 177.68 533.06 47.97 5 473.82 118.45 355.37 21.32 6 473.82 118.45 355.37 10.66 Total 4738.27 1184.57 3553.80 412.43 It is assumed that, equity will be 30% of the project cost, i.e. Rs1421lakhs While calculating the IDC, it is considered that the drawl of long term loan from Financial Institution will commence simultaneously with the bringing in the equity. 12.10 PRE OPERATIVE EXPENSES Pre-Operative Expenses are estimated on the basis of expenditure incurred during the implementation of the project. This is inclusive of the amount to be paid to AEDA, front end fee, and the fees to be paid to obtain the statutory approvals including the registration of company. Detailed engineering and consultancy charges are not included in the preliminary expenses. Implementation period is around 18 months. The details of pre operative expenses are as under: Table 12.9 Pre Operative Expenses Particulars Nodal Agency's Fee Travelling (Rs. in Lakhs) Amount 2.00 10.00 Ireda Application Fee 0.00 Front end Fee 0.00 Company Incorporation Charges 8.00 Deposits 0.00 Trial run Expenses 3.75 Interest during the construction period 412.00 Total Pre-Operative Expenses 435.75 IREDA does not take the registration fee, and front end fee for the projects implemented in North Eastern states. Hence this amount is not considered. 10 MW Biomass Based Power Plant 12.11 ABEIL Detailed Engineering Fee A provision of Rs. 70.00 Lakhs has been made towards the fees for detailed Engineering. 12.12 TOTAL PROJECT COST Project Cost : Rs. 4738.27 Lakhs It is assumed that 30% of the above total project cost, i.e. Rs.1421Lakhs will be met from equity. The loan component of the project cost works out to Rs. 3317Lakhs. Table 12.10 Summary of Project Cost Estimate Particulars Land & Site Development Buildings Plant & Machinery (Rs. in Lakhs) Amount 87.00 475.58 3236.00 Mice. Assets 92.00 Detailed Engineering 70.00 Contingencies Preliminary Expenses .22092 15.00 Pre-Operative Expenses(incl.IDC) 435.75 Margin Money for Working Capital 106.02 Total 4738.27 10 MW Biomass Based Power Plant ABEIL 13. FINANCIAL ANALYSIS 13.1 GENERAL Financial Analysis carried out with the assumption of finance from IREDA. IREDA gives the special interest rate reduction of 1% from the regular states biomass based power plant interest rate and they don’t charge registration fee and Front end fee.. Assumptions for financial analysis is given below: A. B. C. D. E. F. Debt equity ratio is 70:30 Interest rate 12.25% Repayment period of 9 years including 2 years moratorium Project completion period – 18 months Repayment of loan in 28 quarterly installments Biomass(rice husk) Price: Rs. 1500.00 per tonne in first year and increases by 5% per annum 13.1.1 This section of the report gives the financial analysis of the power project using rice husk as fuel and the proposed tariff calculations(based on the ‘Cost Estimates’under section 12) for sale of power to the grid. 13.2 MODE OF FINANCING 13.2.1 The total project cost with the interest during construction and working capital margin is estimated to be Rs. 4738 Lakhs as given in ‘Cost Estimate’. Since the project fulfills the norms of renewable energy biomass based projects, it is expected that the project will get the eligibility of 70% of the project cost as long term loan. 13.2.2 Thirty percent (30%) of the total project cost i.e. Rs. 1421 Lakhs will be brought in as the equity for the project by the Management of the power plant. The balance of Rs. 3317 Lakhs will be mobilized as long term loan from financial Institutions. 13.2.3 It is assumed that this loan amount will be repaid in Seven (7) years in 28 equal installments and there will be an initial moratorium of two (2) years on the loan repayment. An interest rate of 12 % is considered on the term loan, and it is assumed that the interest payment and the loan repayment will be quarterly. 13.2.4 This Power Plant will be located at Jagi Road, Morigaon District. 10 MW Biomass Based Power Plant ABEIL 13.2.5 The project envisages no foreign exchange out flow, since all the equipment are assumed to be bought from indigenous suppliers and foreign exchange if any will be organized by the suppliers of the equipment. 13.3 PLANT OPERATION ABEIL is planning to operate the plant for nearly 330 days. Installed capacity is 11 MW. The in house consumption for power plant will be around 1 MW. It is estimated that, this plant will be in a position to export around 10 MW to the grid. The plant load factor is taken as 90% 13.4 Raw Material Requirement and cost: On an average biomass requirement is around 1.25 tonnes per generation of 1 MWh. Plant will be operating for nearly 330 days, i.e. 7884 hours, including annual maintenance.. The capacity utilization assumed is 90% from the first year itself. This assumption is mainly for financial analysis. The price of rice husk is taken as Rs.1500 per ton as per current rate with an escalation of 5% per annum. 13.5 SALABLE ELECTRICITY 13.5.1 The Gross generation of power in the new power plant will be 11000 kW. Out of this, around 10% of power will be consumed in the power plant, i.e.1000 kW. The balance power of 10000 kW can be supplied to the grid. This exportable power with a plant capacity utilization of 90% will be supplied to the ASEB grid. This will work out to (7884x10000)kwhr i.e.78.84 million units per annum. 13.5.2 The power generated is proposed to be sold to the ASEB at present, as ASEB is directed by Govt. of Assam. 13.5.3 UNIT CAP PRICE OF ELECTRICITY The Ministry of Non-Conventional Energy Sources, have recommended a price of Rs. 2.25 per kWh, for the base year 94-95. They have also recommended an escalation of 5% on the Unit price every year. While, many SEBs have not yet fully implemented these recommendations, Govt. of Rajasthan had issued the notification indicating the base price of Rs.3.52 for the year 2004-05. Since ASEB is having a deficit of 221 MU after the contractual purchases in 2006-07, it has to make up the deficit by purchasing power from Power Traders at a high rate of Rs.3.57(avg) as indicated under 10 MW Biomass Based Power Plant ABEIL clause 2.7 earlier.We are assuming that, Assam State Electricity Regulatory Commission will give the cap rate of sale of biomass based power of at least Rs.3.50 per unit upto a limit of 200 million units in the year 2007-08 to make up the deficit of power. 13.6 OPERATION AND MAINTENANCE COST The repairs and maintenance cost for this project has been assumed as Rs.61.56 Lakhs in first year with escalation of 5% per annum. The salaries and wages of the operation and maintenance personnel of the power generation plant is separately considered (Refer table enclosed to the section on Manpower and Training) and the same have been worked out as Rs.68.36 Lakhs, including a provision for contract labor service charges. Table 13.1 Price escalations Expenses Amount Escalation per year Repairs and Maintenance 61.56 5% Salaries and Wages 68.36 5% Consumables 15.00 5% 13.7 ADMINISTRATION, OVERHEADS AND SELLING EXPENSES The Cost included under this head is Rs. 75.28 Lakhs including Rs. 25.00 Lakhs for insurance. This also includes the general administrative expenses. Table 13.2 Administration, Overheads and Selling Expenses Expenses Amount Escalation per year Managerial and Administrative salaries 45.28 10% Selling and Other Expenses 5.00 0% Insurance 25.00 0% Both Operation & Maintenance and Administration Overheads/Insurance are considered under O&M Expenses in the calculations for generation cost. 13.9 TAXES ON GENERATION AND SALES No expense under this head is considered since this is not applicable. 13.10 ESCALATION PROVISION FOR VARIOUS COSTS AND EXPENSES 10 MW Biomass Based Power Plant ABEIL An escalation of 5% on the salaries and wages, 5% on the administrative expenses and 5% on the cost of utilities is considered in the financial analysis. An escalation of 5% is considered on the cost of fuel in the financial analysis. 13.11 DEPRECIATION A straight line depreciation rate of 3.6% for the plant and machinery as provided in the Gazette for a life span of 25 years is considered in the financial analysis. The depreciation based on the above rates works out to Rs.170.57 Lakhs for a full year. 13.12 CAPITAL SPARES 1% of gross fixed assets amounting to Rs.Rs.47.38 lacs is taken as capital spares per annum. 13.12 GENERATION COST and PROPOSED TARIFF The annexed schedule gives the estimate of cost of production of electricity, for ten (10) years operation from plant commissioning and the proposed tariff for sale of power to the grid after considering a 14% ROI. Plant capacity utilization of 90% has been considered from first year onwards in the analysis..