OSG Docdb 523-v3 October 29, 2012 Document Name Authors Change Control Process OSG Executive Board The OSG Change Control Process The purpose of this document is to describe the process for changes in the financial, schedule or technical scope for the OSG project. To achieve our goal of being a well-managed project, we require a system that allows for the evaluation of changes leading to explicit decision making and logging for each significant change; and we require that change management be simple and agile. The Project Manager is responsible for working with the requestor of the change and the OSG project to determine the impact and dependencies of a change in financial allocations, schedule and/or technical deliverables; this change control system is primarily intended to cover the work plans and related areas of budget which are retained in the OSG document repository. The project manager assists the change sponsor to then submit the change proposal, if needed, to the OSG Executive Director who makes the decision to accept or reject the change request in consultation with the OSG Executive Team. OSG implements a light-weight change control process where agreements can be made rapidly and there is a record of the decisions made and the impact and dependencies gathered. Change Control records are kept in the OSG document repository and may be accessed by a named list of OSG staff. The OSG program of work, budgets, and other significant technical decisions are kept in the OSG document repository; this change control process assures that these records are kept updated. We define three levels of change control and explain the authorities assigned for each level: Level 0 Level 1 Level 2 The change control process is not invoked. Area Coordinators have authority to decide and inform the Project Manager and Executive Director after the decision; these changes are logged and recorded in the OSG Document database. Area Coordinators present the change request to the Executive Director who decides and may consult with the Executive Team, as needed. The decision is returned to the Area Coordinator who is responsible for ensuring that these changes are logged and recorded in the OSG Document database. The Project Manager decides the level of a change in consultation with the change sponsor and with the Area Coordinators who meet weekly. Any member of the ET, Council or an Area Coordinator can request that the issue be elevated to level 1 or 2; that request will supersede the level designated by the Project Manager. All changes associated with project budgets and related financial issues require the approval of the Resource Managers, Executive Director and OSG PI. OSG Change Control Process Page 1 Guidelines for Level Thresholds 1.1 Level 0 Threshold The Change Control Process is not invoked. This applies for changes which do not trigger the Level 1 or Level 2 threshold. In these cases, the change is recorded by the area coordinator but no approvals are required. Generally these changes involve minor changes in system capability or small changes to schedules. 1.2 Level 1 Change Control Threshold The following changes will trigger a Level 1 Change Control Process: o Schedule slip of more than 3 months. o Significant changes to the technical baseline 1.3 Level 2 Change Control Threshold The following changes will trigger a Level 2 Change Control Process: o Schedule slip of more than 6 months. o Plans to offer a new OSG service or discontinue such a service o Significant changes to the technical baseline or changes in the OSG performance and scope. Implementation Method 1. All OSG work plans, budgets, and technical plans (e.g. blueprints) are stored in the OSG document repository; these are updated at least once a year as the program of work is developed and baselined for the upcoming interval (typically one year). 2. Any Area Coordinator or the Project Manager or any member of the OSG Executive Team may request a change to the baselined program of work. 3. The change sponsor consults with the OSG Project Manager to determine the level of change and implements the needed change management approval process as described above. 4. For level 1 & 2 changes, the appropriate document in the document repository is updated to provide: 1) the change description; 2) the reason for the change; and 3) date of change and how the change was approved. The updated document is submitted to the project manager who will review the documentation and submit to the OSG document repository as the permanent record of the change; each affected document will contain a change log as a separate section. OSG Change Control Process Page 2