1 Cost and Management Accounting 202 (CMA612S) Feedback Tutorial Letter Assignment 1 – sem 2 of 2015 QUESTION 1 (25 marks) 1. BEP in N$ = Total fixed costs Contribution margin per unit = N$2 000 000 N$7 500 BEP in N$ = 267 canopies = Total fixed costs Contribution margin ratio = N$2 000 000 0.6 = Or; N$3 333 333 = 266.66666666..canopies x N$12 500 = N$3 333 333 2. Sales Propose(A) Proposed (B) Proposed (C) N$ N$ N$ 3 840 000 2 530 000 4 050 000 (1 600 000) (990 000) (1 800 000) 2 240 000 1 540 000 2 250 000 (2 000 000) (2 000 000) (1 800 000) 240 000 (460 000) 450 000 Less: Variable costs Contribution Margin Less: Fixed costs Net profit 2 Comment: None of the above proposed situations will achieve the targeted annual after-tax of N$450 000, however proposed in (C) is a bit better compares to (A). However the proposed in (B) is results on a loss, and should not be recommended at all. 3. Limitations of the Cost-Volume-Profit-Analysis (CVPA): • Costs are assumed to behave in a linear fashion. Unit variable costs are assumed to be constant and fixed costs are assumed not to change. This is not true because in reality there are semi variable and semi fixed costs which do not behave that way. • Sales revenue is assumed to be constant for each unit sold. This is unrealistic because of the necessity to reduce selling price to achieve higher volumes. • It assumes there are no inventories which is not realistic. • It assumes activity is the only factor affecting costs and factors such as inflation are ignored. • The analysis only works in short term. • It assumes that as long as an activity is above breakeven point then it’s profitable. This is not realistic because changes in cost and revenue pattern may result in breakeven points after which losses are made. QUESTION 2 (20 marks) 1. Weighted average contribution (P/V) ratio = Total contribution x 100% Total sales = N$36 100 000 x 100% N$73 333 333 = 49.22….% Or: Weighted average contribution (P/V) ratio = Weighted average contribution x 100% Weighted average sales = N$902.50 x 100% N$1 833.32 = 49.22…..% Please see the workings below: 3 Mini-phone N$ Direct materials (N$50 x .95) Net-phone N$ 47.50 47.50 Direct labour 550.00 (550 x 1.5) 825.00 Variable overheads¹ 150.00 150.00 Variable production cost per unit 747.50 1 022.50 Sales commission per unit (5%) 100.00 75.00 847.50 1 097.50 Variable production overheads¹ = High/low method used: = N$8 000 000 - N$5 000 000 40 000 – 20 000 = N$150 per unit Fixed cost = N$8 000 000 – (N$150 x 40 000) = N$2 000 000 Or = N$5 000 000 – (N$150 x 20 000) = N$2 000 000 Details Sales Less: Total variable costs variable production costs Sales commission (5%) Contribution Mini-phone Net-phone Total (40 000 x 2/3)N$ (40 000 x 1/3)N$ N$ 53 333 333 20 000 000 73 333 333 (22 600 000) (14 633 333) (37 233 333) 19 933 333 13 633 333 33 566 666 2 666 667 1 000 000 3 666 667 30 733 333 5 366 667 36 100 000 Less: Fixed costs 3 500 000 (N$1 500 000 + N$2 000 000) Net profit 32 600 000 Weighted Selling price per unit x Sales mix Sales (N$) Mini-phone N$2 000 0,6667 1 333.32 Net-phone N$1 500 0,3333 500.00 4 1 833.32 Weighted Contribution per unit x Sales mix contribution (N$) Mini-phone N$1 152.50 (N$2 000 - N$847.50) 0,6667 768.33 N$402.50 (N$1 500 – N$1 097.50) 0,3333 134.17 902.50 Net-phone Fixed costs 2. Break-even point in units = Weighted average contribution per unit N$3 500 000 = N$902.50 = 3 878 units Break-even point in sales value = Break-even point in units x Weighted average selling price = 3 878… units x N$1 833. 32….. = N$7 109 829 Or; Fixed costs Break-even point in sales value = Weighted average contribution ratio N$3 500 000 = 0.492275 = N$7 109 847 3. Net profit ratio = Net profit x 100% Total sales = N$32 600 000 x 100% N$73 333 333 5 = 44.45% 4. Margin of safety (%) = Total sales – Break-even in N$ x 100% Total sales = (N$73 333 333 - N$ N$7 109 847) x 100% N$73 333 333 = 90.3….% Or; Margin of safety (%) = Sales in units – Break-even in units x 100% Sales in units = 40 000 units – 3 878 units x 100% 40 000 units = 90.3….% QUESTION 3 (20 marks) has been cancelled because there was some missing information, given that, the students cannot able to answer the requirements. Please see the question below equivalent to question 3 with its solution for learning purpose. REVIEW QUESTION Helao Ltd manufactures two products. Details of the two products and budgeted information are given below for one period. Product Production units Cost per unit Production cost Machine hours (per unit) X Y 200 150 N$ N$ 73 960 2 65 350 3 The above production costs contain only a prime cost and a fixed production overhead of N$52 275.The fixed production overhead is currently absorbed by using a machine hour rate. The company has decided to change to an activity based costing system and the total of the fixed production overhead has been analyzed as follows: N$ Machining costs 20 800 6 Set-up costs 10 500 Stores ordering costs 7 200 Quality inspection 4 575 Stores issues 9 200 52 275 The company has also provided you with the following information: Product X Y 200 150 10 5 Inspections per production run 5 2 Number of issues from stores 400 300 Budgeted production units Units per production run Product X and product Y are sold in batches of 50 units and 30 units per order respectively. Required: 1. Calculate the predetermined overhead rate using traditional costing system based on direct labor- hours. 2. Calculate the amount of prime cost each product if all overhead costs are absorbed on a machine hours basis. 3. Calculate the total cost for each product if all overhead costs are absorbed on a machine hours basis. 4. Calculate the total cost of each product, using activity-based costing. Calculate and list the unit costs from your figures in (a) and (b) above, to show the differences and comment briefly on any conclusions which may be drawn which could have pricing and profit implications. 7 Solution to review question: 1. POR = Budgeted production overhead cost Budgeted machine hours = N$52 275 850¹ = N$61.50 per machine hour 850¹ = (200 units x 2 machine hour per unit) + (150 units x 3 machine hours per unit) 2. Production cost Less: Overhead cost¹ X Y N$ N$ 73 960 65 350 (24 600) (27 675) 49 360 37 675 Prime cost Overhead cost¹ = N$24 600 (200 x 2 x N$61.50) and N$27 675 (150 x3 x N$61.50) 3. X Production cost Product unit cost Y N$73 960 N$65 350 ÷ 200 units ÷ 150 units N$369.80 N$435.67 4. (a) Overheads absorbed based on ABC Overhead costs N$ level of activity cost/activity Machine costing 20 800 850¹ N$24.47…/hour Set-up costs 10 500 50* N$210.00/run Ordering costs 7 200 9* N$800/order Inspection/quality costs 4 575 160* N$28.59../inspect. Stores issues 9 200 700 N$13.14..per issue Workings: 8 850¹ = (200 units x 2 machine hour per unit) + (150 units x 3 machine hours per unit) *No. of production runs = {(200÷ 10) + (150 ÷ 5)} = 50 *No of orders = {(200 ÷ 50) + 150 ÷ 30)} =9 *Inspection = {(20 runs x 5) + {30 runs x 2)} = 160 Total costs based on ABC Prime cost X Y N$ N$ 246.80 251.17 Machine costs 48.94 73.41 Set up costs 21.00 42.00 Ordering costs 16.00 26.67 Inspection 14.30 11.44 Stores issues 26.29 26.28 373.33.. 430.97.. Production cost/unit Output in units Total production costs 200 150 74 666 64 645 Alternative a) ABC Prime cost X Y N$ N$ 49 360 37 675 Machine costs 9 788 11 012 Set up costs 4 200 6 300 Ordering costs 3 200 4 000 Inspection 2 859 1 716 Stores issues 5 257 3 943 74 664 64 646 200 150 Total production cost Output in units 9 Production cost/unit 373.33 430.97 5. Comparison of the two unit costs calculated in (a) and (b) above Based on machine X Y N$ N$ 369.80 435.67 Hour rate ABC method Difference 373.33 430.97 3.53 4.70 Products X and Y have the largest differences. The ABC approach in theory, attributes the cost of resources to each product which uses those resources on a more appropriate basis than the traditional method. Traditional costing method over allocates overheads to low volume products in this case product Y (by N$4.7), under allocates overheads to higher volume products in this case X (by N$3.53). The result is that it leads to wrong decisions. For example when this cost information is used for pricing purposes, the price arrived at would not be realistic.