CONTRACT NO. T-12-16 CONCRETE DATE: August 2012 DIVISION 3 - CONCRETE Division 03 2011-03-15 Page 1 of 1 CONTRACT NO. T-12-16 TABLE OF CONTENTS DATE: August 2012 SECTION NO. 03100 03200 03300 03345 03450 SECTION NAME CONCRETE FORMS AND ACCESSORIES CONCRETE REINFORCEMENT CAST IN PLACE CONCRETE CONCRETE CURING AND FINISHING ARCHITECTURAL PRECAST CONCRETE Division 03 2011-03-15 Page 1 of 1 CONTRACT NO T-12-16 CONCRETE FORMS AND ACCESSORIES DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 Section 03100 2011-03-15 Page 1 of 4 GENERAL Related Sections .1 Section 03200 - Concrete Reinforcement .2 Section 03300 – Cast in Place Concrete .3 Section 03345 – Concrete Curing, Finishing, and Repair .1 The Work outlined in this Section shall be included in the lump sum price for Section 03100 – Concrete Forms and Accessories as indicated in Schedule ‘A’ of the Bid Form. .1 Canadian Standards Association (CSA) .1 CAN/CSA A23.1-04, Concrete Materials and Methods of Concrete Construction. .2 CAN/CSA O86.1-01, Engineering Design in Wood (Limit States Design). .3 CSA O121 M1978(R2003), Douglas Fir Plywood. .4 CSA O151-04, Canadian Softwood Plywood. .5 CSA O153 M1980(R2003), Poplar Plywood. .6 CSA O437 (R2006) Series 93, Standards for OSB and Waferboard. .7 CSA S269.1 1975(R2003) Falsework for Construction Purposes. .8 CAN/CSA S269.3 M92(R2003), Concrete Formwork. .2 Council of Forest Industries of British Columbia (COFI) .1 COFI Exterior Plywood for Concrete Formwork. .1 Indicate the method and schedule of construction, shoring, stripping and re shoring procedures, materials, arrangement of joints, ties, liners, and locations of temporary embedded parts. Comply with the requirements of CSA S269.1 for falsework drawings, Comply with the requirements of CAN/CSA S269.3 for formwork drawings. .2 Indicate formwork design data, such as the permissible rate of concrete placement, and temperature of concrete, in forms. Where superplastizer is used in the concrete mix; design the forms for full hydrostatic pressure. Indicate re-shoring below slabs or beams supporting the shoring above. Provide a lateral bracing system. Measurement and Payment References Shop Drawings CONTRACT NO T-12-16 CONCRETE FORMS AND ACCESSORIES DATE: April 2012 1.5 Section 03100 2011-03-15 Page 2 of 4 .3 Indicate the sequence of erection and removal of the formwork/falsework for review by the Consultant. .4 Each shop drawing submission shall bear the stamp and signature of a qualified professional engineer registered or licensed in the Province of Ontario, as required by the Ministry of Labour. .5 Submit samples for form ties. Waste Management and Disposal .1 Place materials defined as hazardous or toxic waste in designated containers in accordance with the requirements of the Workplace Hazardous Materials Information System (WHIMIS) and Occupational Health and Safety Act (OHSA). .2 Ensure that emptied containers are sealed and stored safely for disposal. .3 Use sealers, form release agents and stripping agents that are non-toxic, biodegradable and have zero or low volatile organic compounds (VOC). .1 Formwork materials: .1 For concrete without special architectural features, use removable wood and wood product formwork materials in accordance with CSA O121. Non-removable formwork shall utilize stainless steel materials. .2 Form ties: .1 For water holding structures including exterior walls provide ties with following: 1. Integral steel water stop 2.6 mm thick and 16 mm in diameter continuously welded to the tie. 2. Neoprene water stop 5 mm thick and 24 mm in diameter whose centre hole is ½ the diameter of the tie or molded plastic water stop of a comparable size. 3. Orient the water stop perpendicular to the tie and symmetrical about the centre of the tie. 4. Through bolt ties are not permitted for water holding structures. .2 Use removable or snap off metal ties, fixed or adjustable length; use removable cones the concrete surface so that ties break off below the surface. .3 Form: .1 Plywood: high density overlay Douglas Fir in accordance with CSA O121 # 1 grade, square edge, 20 mm thick. PART 2. PRODUCTS 2.1 Materials CONTRACT NO T-12-16 CONCRETE FORMS AND ACCESSORIES DATE: April 2012 .2 Section 03100 2011-03-15 Page 3 of 4 Use stay-in-place, stainless steel composite form deck where forms will stay-in-place and be inaccessible. .4 Form release agent: non-toxic, biodegradable, low VOC. .5 Falsework materials: in accordance with CSA S269.1. .1 Verify all lines, levels and centres before proceeding with formwork/false work and ensure that the dimensions agree with the Contract Drawings. .2 Fabricate and erect falsework in accordance with CSA S269.1 and COFI Exterior Plywood for Concrete Formwork. .3 Do not place shores and mud sills on frozen ground. .4 Provide Site drainage in order to prevent the washout of soil supporting mud sills and shores. .5 Fabricate and erect formwork in accordance with CAN/CSA S269.3 to produce finished concrete conforming to the shape, dimensions, locations and levels indicated within the tolerances required by CAN/CSA A23.1. .6 Align form joints and make them watertight. Keep form joints to a minimum. Use stainless steel closure plates, caulk, and/or tape to seal formwork against leakage. .7 Use 25 mm chamfer strips on external corners and/or 25 mm fillets at interior corners and joints. .8 Form chases, slots, openings, drips, recesses, expansion and control joints as indicated in the Contract Documents. .9 Build in anchors, sleeves, and other inserts which may be required to accommodate the Work specified in other Specification Sections. Ensure that all anchors and inserts will not protrude beyond the surfaces designated to receive applied finishes, including painting. .10 Clean all formwork in accordance with CAN/CSA A23.1, before placing concrete. .1 Leave formwork in place for the following minimum periods of time after placing concrete: .1 One (1) Day for walls and sides of beams. .2 One (1) Day for columns. .3 Remove formwork after concrete has reached 75% of its specified 28 Day compressive strength determined by a field cured test cylinder for beam soffits, suspended slabs, decks and other structural members. PART 3. EXECUTION 3.1 3.2 Fabrication and Erection Removal and Reshoring CONTRACT NO T-12-16 CONCRETE FORMS AND ACCESSORIES DATE: April 2012 .4 .5 Section 03100 2011-03-15 Page 4 of 4 One (1) Day for footings and abutments. The Contractor is advised that low ambient conditions will require additional curing time at the sole discretion of the Consultant. .2 Provide all necessary reshoring of members where the early removal of forms may be required or where members may be subjected to additional loads during construction as required. .3 Space reshoring in each principal direction; no more than 3,000 mm apart. .4 Do not re-use damaged forms. Re-use formwork and falsework subject to the requirements of CAN/CSA-A23.1. END OF SECTION CONTRACT NO T-12-16 CONCRETE REINFORCEMENT DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 Section 03200 2011-03-15 Page 1 of 4 GENERAL Summary .1 This Section includes materials and/or Products that are required by Section 01611 – LEED Product Requirements to incorporate recycled materials, and/or regional content. The acceptability of materials or Products is subject to the requirements of Section 01611 – LEED Product Requirements. .1 Section 01611 – LEED Product Requirements .2 Section 03100 – Concrete Forms and Accessories .3 Section 03300 – Cast in Place Concrete .4 Section 03345 – Concrete Curing, Finishing, and Repair .1 The Work outlined in this Section shall be included in the lump sum price for Section 03200 – Concrete Reinforcement as indicated in Schedule ‘A’ of the Bid Form. .1 ASTM International (ASTM) .1 ASTM A185/A185M-05a, Standard Specification for Steel Wire Welded Wire Fabric, Plain, for Concrete Reinforcement. .2 ASTM A497/A497M-05a, Standard Specification for Steel Wire Welded Wire Fabric, Deformed, for Concrete Reinforcement. .3 ASTM A82/ A82M-05a, Standard Specification for Steel Wire, Plain for Concrete Reinforcement. .2 Canadian Standards Association (CSA) CAN/CSA A23.1 04, Concrete Materials and Methods of .1 Concrete Construction. .2 CAN3 A23.3 04, Design of Concrete Structures for Buildings. .3 CAN/CSA G30.18 (M92)(R2002), Billet Steel Bars for Concrete Reinforcement. .4 CAN/CSA G40.20-04 /G40.21 -04 ,General Requirements for Rolled or Welded Structural Quality Steels. .5 CSA W186 M1990( R2002), Welding of Reinforcing Bars in Reinforced Concrete Construction. .3 Reinforcing Steel Institute of Canada (RSIC): .1 RSIC Manual of Standard Practice Related Sections Measurement and Payment References CONTRACT NO T-12-16 CONCRETE REINFORCEMENT DATE: April 2012 1.5 Section 03200 2011-03-15 Page 2 of 4 Shop Drawings .1 Recycled Content: Provide LEED submittals in accordance with Section 01611 - LEED Product Requirements. .2 Regional Materials Content: Provide LEED submittals in accordance with Section 01611 - LEED Product Requirements. .3 Indicate on the shop drawings, bar bending details, lists, quantities of reinforcement, sizes, spacings, locations of reinforcement and mechanical splices if approved by the Consultant, with identifying code marks to permit correct placement without reference to the structural drawings. Indicate the sizes, spacings and locations of chairs, spacers and hangers. Prepare reinforcement drawings in accordance with the Reinforcing Steel Manual of Standard Practice by the Reinforcing Steel Institute of Canada. .4 Detail lap lengths and bar development lengths in accordance with CAN3 A23.3. Provide type B tension lap splices unless otherwise indicated on the Contract Drawings. PART 2. PRODUCTS 2.1 Materials .1 Substitute different sized bars only if permitted in writing by the Consultant. .2 Reinforcing steel: billet steel, grade 400, deformed bars in accordance with CAN/CSA G30.18, unless indicated otherwise on the Contract Drawings. .3 Reinforcing steel: weldable low alloy steel deformed bars in accordance with CAN/CSA 30.18. .4 Cold drawn annealed steel wire ties: in accordance with ASTM A82/A82M. .5 Welded steel wire fabric: in accordance with ASTM A185/A185M. Provide in flat sheets only. .6 Welded deformed steel wire fabric: in accordance with ASTM 497/A497M. Provide in flat sheets only. .7 Chairs, bolsters, bar supports, spacers: in accordance with CAN/CSA A23.1. .8 Mechanical splices: .1 Dowel bar splicer DB -SAE by NCA/ Acrow Richmond Ltd. .2 Lenton Form Saver by Erico Canada Inc. .3 D150 DRB Coupler and Dbr Setting Splice Bar with size equivalent to DB SAE .4 Dowel in bar: 1. Di by NCA/ Acrow Richmond Ltd. 2. Splice bar by Erico Canada Inc. CONTRACT NO T-12-16 CONCRETE REINFORCEMENT DATE: April 2012 3. 2.2 2.3 Section 03200 2011-03-15 Page 3 of 4 D-51, D-52 or D53 with size equivalent to dowel in bar by Dayton Superior Corp. .9 Plain round bars: in accordance with CAN/CSA G40.21. .1 Fabricate reinforcing steel in accordance with CAN/CSA A23.1, ANSI/ACI 315, and the Reinforcing Steel Manual of Standard Practice by the Reinforcing Steel Institute of Canada. .2 Obtain the Consultant’s approval for the locations of reinforcement splices other than those shown on the Contract Drawings. .3 Only upon the approval of the Consultant, weld reinforcement in accordance with CSA W186. .4 Ship bundles of bar reinforcement, clearly identified in accordance with bar bending details and lists as shown on the reinforced steel shop drawings. .1 Provide the Consultant with a certified copy of the mill test report of reinforcing steel, showing the physical and chemical analysis, prior to commencing any reinforcing Work. Fabrication Source Quality Control .2 Upon request, inform the Consultant of the proposed source of material to be supplied. PART 3. EXECUTION 3.1 3.2 3.3 Preparation .1 Clean reinforcing steel prior to placing so as to remove any particles that may impede a proper bond. .1 Do not field bend or field weld reinforcement except where indicated in the Contract Documents or authorized by the Consultant. .2 When field bending is authorized, bend without heat, applying a slow and steady pressure. .3 Replace all bars which develop any cracks or splits. .1 Place reinforcing steel as indicated on the Contractor’s reviewed placing drawings and in accordance with CAN/CSA A23.1. Field Bending Placing Reinforcement CONTRACT NO T-12-16 CONCRETE REINFORCEMENT DATE: April 2012 3.4 Section 03200 2011-03-15 Page 4 of 4 .2 Use plain round bars as slip dowels in the concrete. Paint the portion of the dowel which is intended to move within the hardened concrete with one coat of asphalt paint. When the paint is dry, apply a thick even film of mineral lubricating grease. .3 Prior to placing any concrete, obtain the Consultant’s approval of the reinforcing material and placement. .4 Ensure that the cover to the reinforcement is maintained during concrete placement. Comply with the erection tolerances of CSA A23.1 .1 The Consultant will review the reinforcing steel once it has been placed and will check for conformity with the shop drawings and bar lists. .2 Notify the Consultant a minimum of two (2) Working Days in advance of the date of the proposed review. .3 Concrete placement will only be authorized after the Consultant reviews the placed reinforcing steel. .4 The Consultant’s review does not relieve the Contractor of its responsibility for correctly placing and adequately supporting the reinforcing steel. Inspection END OF SECTION CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 PART 1. 1.1 1.2 1.3 Section 03300 2006-08-30 Page 1 of 14 GENERAL Summary .1 This Section specifies the requirements for the supply of all labour, materials and equipment required to complete the concrete Work as indicated on the Contract Drawings, as specified in the Contract Documents, and as required in order to complete the Work. .2 Comply with the requirements of CSA 23.1 and CSA 23.2 except where noted otherwise in the Contract Documents. Do not use materials that are toxic in their installed condition. .3 This Section includes materials and/or Products that are required by Section 01611 – LEED Product Requirements to incorporate recycled materials, and/or regional content. The acceptability of materials or Products is subject to the requirements of Section 01611 - LEED Product Requirements. .4 This Section includes requirements for preliminary verification of in-place compressive strength of existing concrete. .1 Section 01611 – LEED Product Requirements .2 Section 03100 – Concrete Forms and Accessories. .3 Section 03200 – Concrete Reinforcement. .4 Section 03345 – Concrete Curing, Finishing, and Repair .5 Section 05500 – Metal Fabrications - General .1 The Work outlined in this Section shall be included in the lump sum price for Section 03300 – Cast In Place Concrete as indicated in Schedule ‘A’ of the Bid Form. .2 Heating of water and aggregates and providing cold weather protection will not be measured but will be considered incidental to the Work. .3 Cooling of concrete and providing hot weather protection will not be measured but will be considered incidental to the Work. .4 Supply and installation of anchor bolts, nuts and washers and bolt grouting will not be measured but will be considered incidental to the Work. .5 Supply and installation of water stops will not be measured but will be considered incidental to the Work. Related Sections Measurement and Payment CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 1.4 Section 03300 2006-08-30 Page 2 of 14 References .1 ASTM International (ASTM) .1 ASTM C 109/C 109M, Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2 in. or 50 mm Cube Specimens). .2 ASTM C 260 95, Specification for Air Entraining Admixtures for Concrete. .3 ASTM C 309, Specification for Liquid Membrane Forming Compounds for Curing Concrete. .4 ASTM C 494, Specification for Chemical Admixtures for Concrete. .5 ASTM C 827, Test Method for Change in Height at Early Ages of Cylindrical Specimens from Cementitious Mixtures. .6 ASTM C 939, Test Method for Flow of Grout for Preplaced Aggregate Concrete. .7 ASTM C 1017-92, Specification for Chemical Admixtures for Concrete. .8 ASTM D 412, Test Methods for Vulcanized Rubber and Thermoplastic Rubbers and Thermoplastic Elastomers Tension. .9 ASTM D 624, Test Method for Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomer. .10 ASTM D 1751, Specification for Preformed Expansion Joint Fillers for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types). .11 ASTM D 1752, Specification for Preformed Sponge Rubber and Cork Expansion Joint Fillers for Concrete Paving and Structural Construction. .2 American Concrete Institute (ACI) .1 ACI 304.2R-96, Placing Concrete by Pumping Methods. .3 Canadian General Standards Board (CGSB) .1 CAN/CGSB 37.2, Emulsified Asphalt, Mineral Colloid Type, Unfilled, for Dampproofing and Waterproofing and for Roof Coatings. .2 CAN/CGSB 51.34, Vapour Barrier, Polyethylene Sheet for Use in Building Construction. .3 CGSB 81 GP 1M, Flooring, Conductive and Spark Resistant. .4 Canadian Standards Association (CSA) .1 CSA A23.1 04, Concrete Materials and Methods of Concrete Construction. .2 CSA A23.2 04, Methods of Test for Concrete. .3 CSA A283 – Qualification Code for Concrete Testing Laboratories CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .4 .5 .6 .7 .8 1.5 CSA A3001 -03 Cementitious Materials for Use in Concrete CSA A3002 -03 Masonry and Mortar Cement CSA A3003 -03 Chemical Test Methods for Cementitious Materials for Use in Concrete and Masonry CSA A3004 -03 Physical Test Methods for Cementitious Materials for Use in Concrete and Masonry CSA A3005 -03 Test Equipment and Materials for Cementitious Materials for Use in Concrete and Masonry Performance Requirements .1 28 Day Compressive strength: 1. 30 Mpa for structural concrete 2. 15 MPa for fill concrete .2 Low Shrinkage concrete with 28 Days of drying not greater than 0.04 percent for concrete made with 40 mm aggregate and 0.055 percent for concrete made with 20 mm aggregate when tested in accordance with modified ASTM C157 as accepted by the Ready Mix Concrete Association of Ontario. Normal density concrete unless specified otherwise in the Contract Documents. Bond strength of 1.2 MPa for toppings. Construction tolerances: Comply with Clause 6.4 of CSA A23.1- 4 unless noted otherwise in the Contract Documents. .3 .4 .5 1.6 Section 03300 2006-08-30 Page 3 of 14 Submittals .1 Recycled Content: Provide LEED submittals in accordance with Section 01611 - LEED Product Requirements. .2 Regional Materials Content: Provide LEED submittals in accordance with Section 01611 - LEED Product Requirements. .3 A minimum of 15 Working Days prior to commencing the Work, inform the Consultant of the proposed source of aggregates and provide access for sampling. .4 A minimum of 15 Working Days prior to commencing the Work, submit to the Consultant catalog cuts for each of the following materials proposed for use: .1 each admixture .2 curing compound .3 joint fillers .4 each type of waterstop .5 Drying Shrinkage Tests: CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .1 .2 .3 .4 .5 Section 03300 2006-08-30 Page 4 of 14 Perform laboratory trial mixes of concrete used for the Contract. Make two sets of three specimens for each shrinkage test. Specimens: Fabricate, cure, dry and measure as specified in ASTM C157 and modified as follows: 1. Remove specimens from moulds aged 23 hours, ± 1 hour after trial batching. 2. Immediately place in water at 22.8 degrees Celsius (C) ± 2 degrees Celsius for a minimum of 30 minutes. 3. Measure within 30 minutes thereafter to determine the original length and then submerge in saturated limewater at 22.8 degrees Celsius, ± 2 degrees Celsius. 4. Measure specimens at age 7 Days to determine expansion expressed as a percentage of the original length. The length at age 7 Days shall be the base length for drying shrinkage calculations (0 Days drying age). 5. Store specimens immediately in a humidity controlled room maintained at 22.8 degrees Celsius, ± 2 degrees Celsius and 50 percent, ± 4 percent relative humidity for the remainder of the test. 6. Measure to determine shrinkage expressed as a percentage of the base length and report separately for 7, 14, 21, and 28 Days of drying after 7 Days of moist curing. Computing Drying Shrinkage Deformation of Each Specimen: 1. Difference between base length (at 0 Days-drying age) and length after drying at each test age. Compute the average drying shrinkage deformation 2. to the nearest 0.001 percent at each test age. 3. If the drying shrinkage of any specimen departs from the average of that test age by more than 0.004 percent, disregard the results obtained from that specimen. Concrete Shrinkage at 28 Day Drying Age: 0.040 percent maximum for laboratory trial mixes of proposed concrete made with 40 mm aggregate and 0.055 percent maximum for 20 mm aggregate for construction. If shrinkage specimen tests for concrete exceed the shrinkage limits, modify the concrete mix to reduce shrinkage. Repeat the tests with the new mix. Provide shrinkage tests for each type of structural concrete; two for 40 mm and two for 20 mm aggregate concrete mixes. CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 1.7 1.8 1.9 Section 03300 2006-08-30 Page 5 of 14 Certificates .1 A minimum of 15 Working Days prior to starting any concrete Work, submit, to the Consultant, the manufacturer's test data and certification by a qualified independent inspection and testing laboratory acceptable to the Region, that the following materials will meet the specified requirements: .1 Portland cement. .2 Blended hydraulic cement. .3 Grout .4 Aggregates are not subject to deleterious expansion. .5 Water. .6 Water stops. .7 Water stop joints. .8 Joint filler. .2 Provide certification that the mix proportions selected will produce concrete of a quality, yield and strength as specified in the concrete mixes and shall comply with the requirements of CAN/CSA A23.1. Submit design mixes to the Consultant for review a minimum of twenty-eight (28) Days prior to starting any concrete Work. Tabulate concrete mixes indicating the size of aggregates, water/cementitious materials ratio, admixtures, air content, and location of use for each mix. .3 Provide certification that crack injection materials are suitable for continuous submersion and that they will not release toxic material into the water. .4 Submit a detailed plan for cold weather concrete curing and protection of concrete placed and cured in weather below temperatures of 5 degrees Celsius. .5 Submit a detailed plan for hot weather placements including curing and protection for concrete placed in ambient temperature over 27 degrees Celsius. .1 Prior to start of any Work, the Contractor shall hire and pay for the services of an Independent Testing Laboratory to verify concrete compressive strength of the existing concrete floor at the Generator Room; refer to the requirements of Part 3 below. .1 A minimum of 15 Working Days prior to starting any concrete Work, submit to the Consultant the proposed quality control procedures for the following items: Preliminary Verification Quality Assurance .1 .2 Hot weather concrete. Cold weather concrete. CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .3 .4 Section 03300 2006-08-30 Page 6 of 14 Curing. Finishes. .2 Concrete Testing .1 Testing of fresh concrete for materials and compression will be done by third party agencies designated and paid for by the Region. .2 The Contractor shall pay for additional testing required because of changes in material or the mix proportions, as well as any extra testing of the concrete or materials occasioned by the Contractor’s failure to meet the Specification requirements. .3 The use of testing services does not relieve the Contractor of its responsibility to provide materials and construction in compliance with the Contract Documents. .3 Pre-placement Meeting .1 Hold a meeting a minimum of 28 Days prior to the initial placement of concrete to review the detailed requirements for preparing the concrete design mixes, finishes, and procedures for concrete placement for the structures. .4 Arrange for the attendance at the meeting of the Consultant, the Region, and the concrete Subcontractors, manufacturers, and suppliers including, but not limited, to the following: .1 Contractor's superintendent. .2 Ready mix concrete producer. .3 Admixture manufacturer(s). .4 Concrete pumping and conveying equipment supplier. .5 Concrete formwork and finishing Subcontractors. .6 Notify the Consultant a minimum of 10 Working Days prior to the scheduled date of the meeting. .7 The Consultant will set an agenda for the meeting a minimum of 5 Working Days prior to the scheduled date of the meeting. .1 Cold Weather Requirements - The following requirements are in addition to the requirements of CSA A23.1-04, Clause 7.4.2.5 Cold Weather. Provide temperature-controlled enclosures for areas where .1 concrete is to be placed whenever the ambient air temperature is 5 degrees Celsius or lower. .2 Protect concrete from the adverse effects of space-heated enclosures including local overheating and combustion products. .3 Heat mix water and, if necessary, aggregates when the air temperature is at or below, or predicted to go below, 5 1.10 Site Conditions CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .4 .5 .6 .7 .8 Section 03300 2006-08-30 Page 7 of 14 degrees Celsius at any time during the next 24 hours following placement of the concrete. Maintain the temperature of reinforcing bars and forms above 10 degrees Celsius prior to placing the concrete. Maintain the temperature of concrete, when deposited in forms at not less than 15 degrees Celsius and not higher than 25 degrees Celsius. Maintain the temperature of concrete at surfaces at least 10 degrees Celsius for a minimum period of 7 Days after placing and achieving a minimum of 75 percent of the specified strength. The concrete temperature may then be lowered to ambient air temperature at a rate of 0.5 degrees Celsius per hour or 10 degrees Celsius per Day Use additional protection if full 28 Day compressive strength is required at an early age. Keep concrete continuously moist during the curing period. .2 High temperature Control Requirements - The following requirements are in addition to the requirements of CSA A23.1 04, Clause 7.4.2.4 - Hot Weather. .1 Limit the peak temperature during the curing period to a maximum of 40 degrees Celsius. The placing temperature that will satisfy this requirement depends on the ambient temperature, humidity at the time of placing, thickness of the concrete, and curing methods employed. .2 Consider the use of retarders, low heat cement, slag replacement, ice in mixing water, pre-cooling of aggregates, cooling of concrete through continuous wet curing, and similar methods in order to prevent concrete temperatures from exceeding 40 degrees Celsius at any time. .3 Monitor concrete temperatures for walls and slabs 500 mm or more in thickness. After the concrete temperature has peaked, control the rate of cooling to ambient air temperature to 0.5 degrees Celsius per hour in order to prevent cracking. .4 Notwithstanding the requirements of the subsections above, do not place concrete with a temperature higher than 25 degrees Celsius. Concrete with a temperature in excess of 25 degrees Celsius upon arrival at the Site will be rejected. Remove all rejected concrete from the Site. .3 Protection .1 Protect freshly placed concrete from damage due to construction operations and from cold, heat, rain, snow, running water, drying winds, and any other factors which would likely cause deterioration of concrete quality. .2 Use waterproof insulated covers or other suitable materials to enclose freshly placed concrete under these conditions. .4 Frost Protection for Slabs on Grade CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .1 Section 03300 2006-08-30 Page 8 of 14 Provide continuous protection for slabs on grade to prevent the subgrade below from freezing during cold weather. Provide heated enclosures and insulation as required. .5 Influence of Ambient Concrete Temperature on Concrete Crack Control .1 To minimize the formation of thermal cracks during placement and curing, maintain previously cured concrete and concrete that will be placed against it at the same temperature. .2 Failure to minimize temperature differential between adjacent concrete placements could result in temperature induced cracking. Repair such cracks as specified in this Section at no additional cost to the Region. .6 Backfilling and Service Loads Restrictions .1 Verify that backfill is not higher than the finished grades indicated on the Contract Drawings. .2 Verify that the concrete in walls has attained the specified compressive strength before backfilling against walls or subjecting walls to service loads. As an alternate, in order to discontinue dewatering efforts (at which time the vault must be fully backfilled), brace wall construction prior to proceeding with early backfill; refer to Vault Notes on the Contract Drawings. .3 Use field cured test cylinders to determine in-place concrete strength prior to backfilling. .1 Portland cement: in accordance with CSA 23.1 Type GU General Use. Type HE, High-Early strength hydraulic cement may only be used where the prior approval of the Consultant is obtained by the Contractor. .2 Water: in accordance with CSA A23.1. .3 Aggregates: in accordance with CSA A23.1. Coarse aggregates are to be rough and angular gravel or crushed stone of normal density. .4 Air entraining admixtures: in accordance with ASTM C 260. .5 Chemical admixtures: in accordance with ASTM C 494. The Consultant is to approve all accelerating or set retarding admixtures during cold and hot weather placing. .6 Concrete retarders: in accordance with ASTM C 494 water based. Do not allow moisture of any kind to come in contact with the retarder film. PART 2. PRODUCTS 2.1 Materials CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 Section 03300 2006-08-30 Page 9 of 14 .7 Shrinkage compensating grout: premixed compound consisting of non-metallic aggregate, cement, water reducing and plasticizing agents. .1 Compressive strength: 35 MPa at 28 Days. .2 Consistency: 1. Fluid: in accordance with ASTM C 827. Time of efflux through flow cone (ASTM C 939), under 30 seconds. Flowable: in accordance with ASTM C 827. Flow 2. table, 5 drops in 3 seconds, (ASTM C 109, applicable portion) 125 percent to 145 percent. 3. Plastic: in accordance with ASTM C 827. Flow table, 5 drops in 3 seconds, (ASTM C 109, applicable portions) 100 percent to 125 percent. 4. Dry pack to the manufacturer’s requirements. .8 Dowelling adhesive: .1 HIT-RE 500-SD by Hilti Corporation .2 SET-XP by Simpson Strong-Tie Anchor Systems .9 Non-premixed dry pack grout: composition of non-metallic aggregate Portland cement with sufficient water for the mixture to retain its shape when made into a ball by hand and capable of developing a compressive strength of 35 MPa at 28 Days. .10 Ribbed waterstops: 150 mm wide extruded PVC with shop welded corner and intersecting pieces .1 Tensile strength: in accordance with ASTM D 412, method A, Die"C". .2 Elongation: in accordance with ASTM D 412, method A, Die"C", minimum 275 percent. Tear resistance: in accordance with ASTM D 624, method .3 A, Die"B" .4 Type: Centre bulb with parallel ribs or protrusions on each side. .5 Manufacturers and Products: 1. Greenstreak Plastic Products: Catalogue Style No 716 (152mm by 9.5mm) 2. Vinylex Corporation: Catalogue No. RB6-14 (152mm by 9.5mm) 3. Or approved equivalent. .11 Expandable hydrophilic waterstop: Use approximate size 10 mm thick by 20 mm wide, non-bentonite rubber strip. Attach to concrete surface using a water-swelling sealant/adhesive and concrete nails or screws. .1 Manufacturers and Products: 1. Greenstreak Group, Inc., Greenstreak Plastic Products: Hydrotite catalog No Cl-1020-2K with Leakmaster LV-1. CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 2. 2.2 Section 03300 2006-08-30 Page 10 of 14 Adeka Corporation: MC-2010MN with Ultra Seal P201. .12 Waterproofing: Sealtight Mel Rol waterproofing system by W.R. Meadows Inc. of Canada or approved equivalent. .1 Proportion normal density concrete in accordance with CAN/CSA A23.1. .1 Cement: Type GU Portland cement. Fly ash shall not be permitted. Type HE cement where approved in advance by the Consultant .2 Minimum compressive strength at 28 Days: 30 MPa. .3 Maximum cement content: 300 kg/m3 of concrete. .4 Class of exposure: F-1, Table 2 of CSA A23.1 .5 Nominal size of coarse aggregate: 40 and 20 mm. .6 Water/cement ratio 0.42 for all concrete. .7 Air content: CSA 23.1 .8 Chemical admixtures: following admixtures in accordance with ASTM C 494 including type, quantity, water reducing, strength increasing, air entraining, super plasticizers, rust inhibitors. .9 Submit the mix design with test results to the Consultant for review a minimum of 28 Days prior to placing concrete. .10 Wall concrete mixes shall include the use of a super plasticizer added at the plant, in accordance with CSA A266.6 such as Rheobuild 1000 by BASF Construction Chemicals LLC, or an approved equivalent. The maximum slump is anticipated to be 25 mm to 40 mm prior to adding the superplasticizer and tests shall be in conformity with CSA Specification A23.2. The slump at the Site should not exceed 150 mm after the plasticizer is added to the concrete. .11 No amount of calcium chloride in any chemical form shall be used in any concrete mix or as a de-icing agent in the forms. All concrete mixes shall contain a water reducing agent in .12 accordance with ASTM C494 Type A such as “Pozzolith” by BASF Construction Chemicals LLC, or an approved equivalent, used in accordance with the manufacturer’s instructions. .13 All concrete shall contain an air-entraining agent in accordance with ASTM C494. Total air content shall be in accordance with CSA A23.1 for the class of exposure and the maximum size of coarse aggregate specified in the Contract. .14 All admixtures shall be supplied by the same manufacturer and shall be compatible. Mixes CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .2 Section 03300 2006-08-30 Page 11 of 14 Base of Wall Grout mix: .1 Minimum cementing material: 600 Kg/cubic metre .2 Coarse aggregate: none .3 Maximum Water/Cement ratio: 0.42 .4 Provide minimum 100 mm depth of grout at the base of all walls. Place grout immediately prior to placing balance of wall concrete. PART 3. EXECUTION 3.1 3.2 Preliminary Verification .1 The Contractor shall ensure that the independent testing laboratory retained by the Contractor (the Testing Laboratory) will determine the in-place concrete compressive strength of the Generator Room structural floor concrete. Coordinate locations with the Consultant to core drill and obtain three test specimens within the Generator Room floor area. .2 The Contractor’s shall ensure that the Testing Laboratory will core drill through the concrete topping into the structural concrete floor slab below. After core specimen is obtained, the floor shall be repaired using non-shrink grout including re-setting of the tile if possible. Otherwise grout shall be struck off flush to surrounding surface and the area left clean. .3 The Contractor shall ensure that the Testing Laboratory will test the three specimens for compressive strength. Provide a brief written report to show results of testing. .4 If any result is less than 20MPa, notify Consultant immediately. Preparation .1 Obtain the Consultant’s approval before placing any concrete. Provide a minimum of 2 Working Days notice prior to the placing of concrete. .2 Pumping of concrete is permitted only after approval of the equipment and mix has been obtained from the Consultant. .3 Ensure that the reinforcement and inserts are not disturbed during concrete placement. .4 Prior to placing of the concrete, obtain the Consultant’s approval of the proposed method for protection of the concrete during placing and curing in adverse weather. .5 Maintain accurate records of concrete placed, indicating the date, location, quality, air temperature and test samples taken. .6 In locations where new concrete is dowelled to existing work, drill holes in existing concrete. Place dowels of deformed steel reinforcing bars using adhesive as specified above. CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 3.3 Section 03300 2006-08-30 Page 12 of 14 .7 Do not place loads upon new concrete until authorized by the Consultant. .1 Perform cast in place concrete Work in accordance with CAN/CSA A23.1 .2 Vibrators 1. 2. Concreting 3. 4. 5. 6. The use of mechanical vibrators is required. A sufficient number of vibrators shall be employed to ensure complete compaction. A minimum of one (1) extra gasoline powered vibrator shall be on hand for emergency use. Vibration shall not be continued to the extent that water forms a surface on the concrete. Avoid any disturbance to concrete which has become too stiff to regain plasticity when vibrated. Vibration shall not be applied directly to steel which extends into partially hardened concrete. .3 Sleeves and inserts. .1 No sleeves, ducts, pipes or other openings shall pass through joists, beams, column capitals or columns, except where indicated in the Contract Documents or where approved by the Consultant. .2 Where approved by the Consultant, set sleeves, ties, pipe hangers and other inserts and openings as indicated on the Drawings or specified elsewhere in the Contract Documents. Sleeves and openings which are greater than 100 mm x 100 mm and which are not indicated in the Contract Documents must be approved by the Consultant. .3 Do not eliminate or displace reinforcement to accommodate hardware. If inserts cannot be located as specified, in the Contract Documents, obtain approval of any modifications from the Consultant before placing the concrete. .4 Check the locations and sizes of the sleeves and openings shown on the Contract Drawings. .5 Set special inserts for strength testing, as indicated in the Contract Documents and as required by a non-destructive method of testing concrete. .4 Anchor Rods: .1 Set anchor rods to the templates under the supervision of the appropriate Subcontractor prior to placing the concrete. .2 With the prior approval of the Consultant, fix anchor rods in holes drilled after the concrete has set. Drilled holes are to be in accordance with the manufacturers’ recommendations. CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .3 .4 .5 Section 03300 2006-08-30 Page 13 of 14 Protect anchor rod holes from water accumulations, snow and ice build-ups. Set rods and fill holes with adhesive as specified above. Locate the anchor rods used in connection with expansion shoes, rollers and rockers with due regard to the ambient temperature at the time of erection. .5 Drainage Holes and Weep Holes: .1 Form weep holes and drainage holes in accordance with the requirements of Section 03100 – Concrete Forms and Accessories. If wood forms are used, remove them after the concrete has set. .2 Install weep hole tubes and drains as indicated in the Contract Documents. .6 Grouting: .1 Grout under base plates and/or machinery using procedures in accordance with the manufacturer's recommendations which result in 100 percent contact over the entire grouted area. .2 Deposit 100 mm of wall grout evenly along the horizontal construction joint in the bottom of the form through an elephant truck immediately before placing wall concrete. After placing 300 mm of wall concrete vibrate concrete such that grout and concrete are well integrated. .7 Finishing: .1 Finish in accordance with the requirements of Section 03345 - Concrete Curing, Finishing, and Repair. .8 Water stops. .1 Install water stops in order to provide a continuous water seal. Do not distort or pierce the water stop in such a way that may hamper its performance. Do not displace reinforcement when installing water stops. .2 Tie PVC water stops rigidly in place. .Use sealant/adhesive plus nails or screws to attach expandable hydrophilic waterstops. .3 Use equipment in accordance with the manufacturer’s instructions to field splice PVC waterstops. Use only straight heat sealed butt joints or factory welded corners and intersections unless otherwise approved by the Consultant. .4 For expandable hydrophilic waterstops, side lap or butt splice using liberal application of water-swelling sealant/adhesive to ensure continuity. .5 Vibrate concrete around the waterstops to remove air voids, however, ensure that the waterstops are not damaged or moved by the vibrator. .9 Joint fillers. CONTRACT NO T-12-16 CAST IN PLACE CONCRETE DATE: April 2012 .1 .2 .3 .4 3.4 3.5 Section 03300 2006-08-30 Page 14 of 14 Furnish filler for each joint in a single piece for the depth and width required for the joint, unless otherwise authorized by the Consultant. When more than one piece is required for a joint, fasten abutting ends and hold securely to shape by stapling or other positive means of fastening. Locate and form isolation construction expansion joints as indicated in the Contract Documents. Install joint filler. Use 12 mm thick joint filler to separate slabs on grade from vertical surfaces and extend joint filler from the bottom of the slab to within 12 mm of the finished slab surface unless indicated otherwise in the Contract Documents. .10 Repair of temperature and shrinkage induced cracks. .1 Repair cracks in the completed structure employing a suitable polyurethane injection technique to make such cracks completely water tight after the repair. .2 Remove surface injection material and finish areas to match surrounding concrete. .11 Waterproofing Membrane .1 Clean concrete surfaces in accordance with manufacturer’s recommendations. .2 Apply waterproofing membrane where indicated in the Contract Documents around concrete walls from base slab to finished grade. .1 Concrete tolerance shall be in accordance with CAN/CSA A23.1 .1 Inspection and testing of concrete and concrete materials will be carried out by a testing laboratory designated by the Consultant in accordance with CAN/CSA A23.1. .2 The Region will pay for the cost of the tests. .3 The Consultant will take additional test cylinders during any cold weather concreting and shall cure cylinders at the Site under the same conditions as the concrete which they represent. .4 Non-destructive methods for testing concrete shall be in accordance with CAN/CSA A23.2. .5 Inspection or testing by the Consultant will not augment or replace the Contractor’s quality control obligations nor will it relieve the Contractor of any of its responsibilities or obligations under the Contract. Site Tolerance Field Quality Control END OF SECTION CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 Section 03345 2011-03-15 Page 1 of 10 GENERAL Summary .1 This Section specifies the requirements for concrete finishes and curing of freshly placed concrete. .2 This Section also specifies the requirements for repair of concrete floor cracks at existing concrete. .1 Section 03100 – Concrete Forms and Accessories .2 Section 03300 – Cast in Place Concrete .1 Canadian Standards Association (CSA): .1 CSA A23.1 Concrete Materials and Methods of Concrete Construction .2 Canadian General Standards Board (CGSB): .1 CGSB 51-GP-51M Polyethylene Sheet for Use in Building Construction. .3 ASTM International: ASTM C309 Specification for Liquid Membrane Forming .1 Compounds for Curing Concrete. .2 ASTM C1315 Specification for Liquid Membrane-Forming Compound having Special Properties for Curing and Sealing Concrete. .3 ASTM C109 Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2 in. or 50 mm Cube Specimens Related Sections References Measurement and Payment The Work outlined in this Section shall be included in the lump sum price for Section 03345 - Concrete Curing, Finishing, and Repair as indicated in Schedule ‘A’ of the Bid Form. 1.5 Submittals .1 Product Data Sheets .1 Submit manufacturer's Product data sheets including installation, application, and maintenance instructions for: CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 1. 2. 3. 4. 5. 1.6 1.7 1.8 Section 03345 2011-03-15 Page 2 of 10 Curing compound Surface sealer Control joint sealant Polyethylene sheet Epoxy repair adhesive .2 Shop Drawings and Submittals .1 Submit shop drawings detailing finishes for floors and walls. .2 Submit curing methods proposed. .3 Submit outline crack repair procedure. .1 Concrete finishers: Skilled personnel with a minimum of five years of proven satisfactory experience finishing concrete work of comparable size and scope. .2 Engage the manufacturers' representative for on Site supervision prior to, during, and after applications. Verify that the specified Products are correctly applied and that the amounts and finishing procedures comply with the manufacturer's printed instructions for the Work. Quality Assurance Delivery, Storage and Handling .1 Prevent the deterioration or contamination of stored materials. Deteriorated or contaminated materials will be rejected and must be removed immediately from the Site. .1 Comply with any special requirements of Section 03300 - Cast in Place Concrete for Work under cold weather and warm temperature conditions. .1 Curing compound: ASTM C309 .1 Type 2 .2 Combination curing and sealing compound: ASTM C1315, clear, non-yellowing compound; .1 Florseal by Sika Canada Inc. .2 Masterkure CR (Clear) by Master Builders Technologies Inc. .3 Super Diamond Clear by Euclid Admixture Canada, Inc. .3 Surface sealer: Clear, liquid surface hardener and dust roofer; .1 Sealhard 400 by Sika Canada Inc., Site Conditions PART 2. PRODUCTS 2.1 Materials CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 .2 .3 Section 03345 2011-03-15 Page 3 of 10 Floor Seal by Euclid Admixture Canada, Inc., Day Chem Sure Hard (J 17) by Dayton Superior Canada Limited. .4 Control joint sealant: Bondflex by W.R. Meadows Inc. of Canada, or approved equivalent. .5 Polyethylene sheet: CGSB 51 GP 51M; 0.15 mm thick. .6 Wet curing materials: Non staining waterproof curing paper, burlap, or canvas coverings. .7 Bonding agent: Suitable for the conditions of service and the performance requirements of this Section. .8 Non-shrink, non-ferrous grout: Pre-blended hydraulic cement grout; .1 In Pakt Pre Mix by C C Chemicals Limited .2 Masterflow 713 Plus Grout by BASF Construction Chemicals LLC. .3 M Bed Standard by Sika Canada Inc. .9 Epoxy repair adhesive shall be a 2-component, high strength, lowviscosity epoxy specifically manufactured for gravity feed into cracks in concrete. Use Sika Canada Inc., Sikadur 35, Hi-Mod LV or approved equivalent. .1 Determine the requirements for any applied finishes prior to placement of concrete. .1 Finish surfaces to the following tolerances in accordance with CSA A23.1, Clause 7.5.1.2 Straightedge Method. PART 3. EXECUTION 3.1 3.2 Preparation Tolerances .1 3.3 Flat: Finish tolerance 5 mm in 3000 mm. Surfaces of concrete toppings; and exposed surfaces of concrete topping and floors or slabs. Concrete Finishing .1 General .1 Concrete finishing effort is directly dependent on forming, concrete placing, and curing techniques. Perform finishing procedures until the specified finishes are achieved. .2 Complete concrete finishing in areas where mechanical and electrical equipment will be installed prior to the commencement of any such installations. .3 Coordinate the construction schedule to allow for application of special floor coatings and sealers after the CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 Section 03345 2011-03-15 Page 4 of 10 concrete has attained the required moisture condition and provide the required preparation and cure time for the coating system, as specified by the coating/sealer manufacturer. .2 Slab or Floor Surfaces .1 General 1. Carry out finishing operations in accordance with CSA A23.1, Clause 7.5 – Finishing and Treatment of Slab or Floor Surfaces. 2. Initial finishing operations shall consist of placing, consolidating, and screeding, immediately followed by straightedge, bull floating, or darbying. Complete all levelling and consolidation before free moisture or bleed water rises to the top of the surface. 3. Provide at least one standby power trowel. Provide sufficient finishers and equipment for the Work. Take all precautions necessary in order to protect 4. the finish against inclement weather. 5. Commence final finishing operations, consisting of floating and trowelling, when the concrete has stiffened sufficiently to prevent the working of excess mortar to the surface and is able to sustain foot pressure, and after removing any free bleed water. 6. Restraighten with a straightedge as often as necessary in order to achieve the specified floor tolerances. .2 Float Finish Type S-1 1. After initial finishing, provide a float finish in accordance with CSA A23.1, Clause 7.5.4.2 Floating. .3 Trowel Finish Type S-2 After initial finishing and floating, trowel the surface 1. with a steel hand or power trowel in accordance with CSA A23.1, Clause 7.5..4.3.2 Trowel, keeping the blade flat at first and raising the blade angle a little more on subsequent passes. Leave the surface smooth, dense, of fine uniform texture without a swirl and free of blemishes. .4 Non-Slip Finish Type S-3 1. Apply a transvers fine broom finish to walking surfaces, interior and exterior. Surface Sealer Type S-4 .5 1. Treat all concrete surfaces which are subject to traffic in the finished structure, such as slabs, concrete toppings, landings, walkways, and similar locations, with a surface sealer except if the CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 2. 3. .3 Section 03345 2011-03-15 Page 5 of 10 surfaces have been cured with a dual purpose curing and sealing compound. Apply the sealer in accordance with the manufacturer's printed instructions. Do not use a surface sealer where bonded finishes or waterproofing is scheduled in the Contract Documents. Formed Surfaces (walls and underside of elevated slabs) .1 General 1. Provide a smooth form finish in accordance with CSA A23.1, Clause 7.7.3.6 - Smooth Form Finish, unless noted otherwise in the Contract Documents. 1. Remove the face formwork as soon as practical in order to facilitate the repair of any surface defects. Surface defects include but are not limited to formwork tie holes, bugholes with a nominal diameter or depth greater than 6 mm, honeycomb and defective concrete, fins, projections, irregularities, offsets, spalled corners, and other defects. 2. Avoid damaging corners and keep edges sharp. .2 Formwork Tie Holes 1. Cut formwork ties 25 mm from the surface of the concrete. 2. Make edges of depressions sharp. 3. Fill depressions with pre-blended, non-shrink, nonferrous grout of the same colour as the concrete for any exposed concrete surfaces. .3 Irregularities 1. Grind smooth fins, projections, irregularities, and offsets, including those at visible construction joints. 2. Where irregularities and offsets cannot be remedied by grinding, chip the concrete surface sufficiently deep and apply thoroughly bonded preblended, non-shrink, non-ferrous grout in a method similar to that for the repair of honeycomb and defective concrete. .4 Surface Depressions 1. Fill bugholes, and other surface depressions with a sand cement mortar to match the surface of surrounding concrete. .5 Spalled Corners 1. Use repair materials of a similar appearance and strength as the surrounding concrete to reconstruct the corner to match the adjacent corners. .6 Honeycomb and Defective Concrete CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 1. .7 .8 .9 Section 03345 2011-03-15 Page 6 of 10 Do not repair honeycomb and defective concrete until it has been reviewed by the Consultant and permission has been granted to proceed with the repair work. 2. Remove honeycomb and defective concrete down to sound concrete with the edges slightly undercut or perpendicular to the surface. Remove to a minimum depth of 25 mm. No feather edges are permitted. 3. Pre-dampen the patch area. 4. Use pre-blended, non-shrink, non-ferrous grout of the same colour as the concrete for any exposed concrete surfaces. 5. Use bonding agents in patching work. 6. Patch surfaces slightly higher than the surrounding concrete. 7. Wet cure patches to the equivalent of 10 Days minimum. 8. When the patched surface has hardened, rub the surface with carborundum brick to form a true surface, free from streaks, discolourations, and other imperfections to match flush with the surrounding concrete. Smooth Rubbed Finish Type W-5 1. Do not commence rubbing or grinding operations until all surface defects are repaired and all patching materials have hardened. 2. Dress surfaces by rubbing or grinding with bricks of carborundum, emery, or other abrasive material to a smooth and even surface. Wet and rub surfaces until surfaces are even and of a uniform smooth appearance. Prevent rounding of edges, obliterating the bevel lines on edges and corners, and chipping or cracking the finished edges. Sack Rubbed Finish Type W-6 1. After completion of the surface preparation of the smooth rubbed finish, apply a sack rubbed cement finish to form a smooth finish of uniform appearance as specified in CSA A23.1, Clause 7.7.3.7.4 Sack Rubbed Finish. Apply a second coat of sack rubbed cement finish to produce a smooth uniform appearance if required in order to obtain acceptance. Demonstrate on a sample panel prior to production finishing. 2. Upon completion, thoroughly wash the surfaces with clean water Related Unformed Surfaces 1. Screed and float tops of walls or buttresses, horizontal offsets, and similar unformed surfaces CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 Section 03345 2011-03-15 Page 7 of 10 occurring in units cast in forms to a texture consistent with that specified for the formed surface unless some different finish is specified elsewhere in the Contract Documents. 3.4 Curing Concrete .1 Preplan curing methods prior to placement of concrete. Have required materials on-site prior to delivery of concrete. .2 Begin curing immediately following placing and finishing in accordance with CSA A23.1 except as noted below. The rate of evaporation is dependant on the relative humidity, concrete temperature and wind velocity. For the rate of evaporation of moisture from a concrete surface covered with water, see CSA A23.1 Appendix D Guidelines for curing and protection. .3 Wet cure for 10 consecutive Days at a minimum temperature of 10 degrees Celsius. This requirement supersedes the requirements of Table 20 Allowable Curing Regimes of CSA23.1. .4 Establish the requirements of the specified finishes for concrete surfaces before applying the curing compound. Verify that the curing compound is compatible with the applied finishes. .5 Do not use curing compounds on surfaces: .1 Where bonded concrete topping will be applied. .2 Where high temperature control requirements are in force. .3 For potable water structures. .6 Formed Surfaces (Walls and Columns) .1 Wet cure as specified by pouring water between the formwork and the concrete surface, where possible. .2 As an alternative, cure as specified above until the formwork is removed. Immediately after removal of the formwork, provide 24 hours of saturation followed by the application of a curing compound in accordance with the manufacturer's printed instructions. .7 Unformed Surfaces (Slabs) .1 Cover with absorbent material kept continuously saturated as soon as the cement will not wash out or the finish will be damaged. .2 As an alternative, wet cure for 24 hours then seal with two complete coats of curing compound applied in accordance with the manufacturer's instructions. Maintain the coating during the curing period. .8 Bonded Concrete Toppings .1 Wet cure for 10 consecutive Days if no bonding agent has been used. .2 If a bonding agent has been used, employ curing methods for the concrete topping which will produce a cure equivalent to 10 Days wet curing and which is in CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 .3 .4 3.5 3.6 3.7 Section 03345 2011-03-15 Page 8 of 10 accordance with the bonding agent manufacturer's printed instructions. Protect and prevent damage to concrete topping floor finishes. Repair any damaged sections. Protect the topping from freezing for a minimum of 14 Days after placing. Protection .1 Keep traffic which would affect or disturb the curing procedures off of the finished surfaces for a minimum period of 7 Days. .2 Protect all exposed concrete finishes against damage until acceptance of the Work by the Region. Do not allow rain, sleet, or snow to increase mixing water or to damage the surface finish. .3 Protect floors which are to receive architectural finishes against contamination by oil, paint, or other deleterious materials which may affect their finish. .4 Protect any items set into floors from damage. Verify that the alignment is not disturbed. .1 Vapour Transmission Test: Conduct tests on new and existing concrete to show that no surface moisture exists prior to application of the specified special floor treatment, as follows: .1 Place a polyethylene plastic sheet, a minimum of 1.2 m by 1.2 m in size, and sealed along four sides with duct tape to prevent moisture transmission by evaporation, over the concrete floor area for 24 hours. .2 An indication of moisture transmission will be apparent by the accumulation of moisture on the enclosed surface of polyethylene plastic sheet. .3 Do not apply a concrete bonding agent until the test results indicate that moisture is not being transmitted from the concrete surface. .1 Provide the services of a manufacturer's representative at the Site for installation assistance, inspection and certification of proper installation, and the training of application personnel. .1 The manufacturer’s representative shall provide technical assistance to ensure and certify the application and installation of the system being used. .2 The manufacturer’s representative shall provide consultation, direction, and certification of the mockup, for full-scale application of floor finishes, and at other times as needed. Tests and Inspection Manufacturer’s Services CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 3.8 3.9 Section 03345 2011-03-15 Page 9 of 10 Field Quality Control .1 Measure the floor slab flatness and levelness, as applicable, in accordance CSA A23.1 Straightedge Method. .1 Concrete Slab Finishes .1 Type S-1 Float Finish: 1. Provide float finish to concrete surfaces prior to other scheduled finishes. .2 Type S-2 Trowel Finish: 1. Provide trowel finish for concrete surfaces which are exposed; concrete floors, mechanical and electrical bases, and bonded concrete toppings. Provide only a light trowel finish when a non-slip finish is scheduled to follow. 2. Do not use dry cement or additional water during trowelling. Excessive trowelling will not be permitted. Do not use a power machine when the concrete 3. has not attained the necessary set to allow finishing without introducing high and low spots in the slab. 4. The Contractor shall first perform steel trowelling for a Type S-2 finish by hand. .3 Type S-3 Non-Slip Finish: Provide a non-slip broom finish for walkway slabs 1. (interior concrete floor slab in the diesel fuel vault, top surface of removable vault roof slabs, and other areas which are exposed to foot traffic.) .4 Type S-4 Surface Sealer 1. Seal the tops of all interior or exterior concrete slab surfaces. .2 Concrete Wall Finishes .1 Ordinary Wall Finish: 1. Patch tie holes. 2. Knock off projections. 3. Patch defective areas. 4. For exterior below grade concrete walls of the diesel fuel vault to receive a waterproof coating. .2 Type W-5 (Smooth Rubbed Finish): 1. Patch tie holes. 2. Grind off projections, fins, and rough spots. 3. Patch defective areas and repair rough spots resulting from the form release agent’s failure or any other reason, in order to provide a smooth uniform appearance. 4. Interior wall surfaces and ceiling of the diesel fuel vault. Schedule of Finishes CONTRACT NO T-12-16 CONCRETE CURING, FINISHING, AND REPAIR DATE: April 2012 .3 Section 03345 2011-03-15 Page 10 of 10 Type W-6 (Sack Rubbed Finish): 1. Provide a sack rubbed finish on any other vertical concrete surfaces that would be visible after completion of construction including: 1. Equipment supports/pads, concrete restraint blocks, housekeeping pads, etc. 3.10 Crack Repair .1 Identify cracks for repair, verify that width of crack is adequate for gravity feed of epoxy. .2 At crack width deemed too small for successful gravity feed of epoxy, “vee” out the top of the crack to facilitate application of epoxy. .3 Use oil-free compressed air to blow the crack clean, combined with vacuum as needed to adequately clean and prepare crack. .4 Pour neat epoxy into the crack, using a small squeegee to brush product back and forth over crack until the crack is full. .5 At larger cracks that do not fill, it may be necessary to add a fine oven-dried aggregate either directly into the crack or mixed with epoxy to create a slightly thicker slurry to fill the crack. .6 Wait long enough for the epoxy to set, verify after 24 hours that the crack is filled to the surface, reapplying epoxy as needed until the crack remains full. .7 Wipe up excess epoxy materials with clean rags to leave the areas reasonably neat in appearance. There should be no puddles, dribbles, and spills left unattended. END OF SECTION CONTRACT NO T-12-16 ARCHITECTURAL PRECAST CONCRETE DATE: April 2012 PART 1. 1.1 1.2 1.3 1.4 Section 03450 2012-01-27 Page 1 of 4 GENERAL Section Includes .1 Architectural precast concrete solar reflective roof pavers including related trim pieces and required support accessories. .2 This Section includes materials and/or Products that are required by Section 01611 – LEED Product Requirements to incorporate recycled materials, and/or regional content. The acceptability of materials or Products is subject to the requirements of Section 01611 - LEED Product Requirements. .3 Non-woven Geotextile Drainage and Membrane Protection Composite .1 Section 01352 – General LEED Requirements .2 Section 01611 – LEED Product Requirements .3 Section 07200 – Insulation .1 Canadian Standards Association (CSA) .1 CAN/CSA A23.1 04, Concrete Materials and Methods of Concrete Construction. .2 CAN3 A23.3 04 , Design of Concrete Structures for Buildings. .3 CAN3 A23.4 05, Precast Concrete Materials and Construction. .2 ASTM International (ASTM) .1 ASTM A185/A185M-05a, Standard Specification for Steel Wire Welded Wire Fabric, Plain, for Concrete Reinforcement. ASTM A497/A497M-05a, Standard Specification for Steel .2 Wire Welded Wire Fabric, Deformed, for Concrete Reinforcement .3 ASTM A82/ A82M-05a, Standard Specification for Steel Wire, Plain for Concrete Reinforcement.trc vxz vcc .1 Tolerance of precast elements in accordance with CAN3 A23.4, Section 10. .2 Solar Reflective Index (SRI) shall be not less than 78. Related Sections References Performance Requirements CONTRACT NO T-12-16 Section 03450 ARCHITECTURAL PRECAST CONCRETE Page 2 of 4 DATE: April 2012 1.5 1.6 1.7 Measurement and Payment .1 The Work outlined in this Section shall be included in the lump sum price for Section 03450 – Architectural Precast Concrete as indicated in Schedule ‘A’ of the Bid Form. .1 Product Data .2 Manufacturer’s Product data indicating concrete content, strength, standard paver sizes, certified test results. indicating solar reflectance ranges, and maintenance requirements. .3 Samples .1 The Contractor shall submit 2 full size samples of the selected pavers, illustrating quality of finish, colour and texture. .4 LEED: .1 Recycled Content: Provide LEED submittals in accordance with Section 01611 - LEED Product Requirements. .2 Regional Materials Content: Provide LEED submittals in accordance with Section 01611 - LEED Product Requirements. .1 Precast concrete elements are to be fabricated and erected by a manufacturing plant certified by the Canadian Standards Association in the appropriate categories as required by CSA A251. .2 The precast concrete manufacturer is to be certified in accordance with the CSA's certification procedures for precast concrete plants. The Contractor is to verify the current certification of the plant. .3 Only precast elements fabricated in such certified plants will be acceptable to the Region, and plant certification is to be maintained for the duration of the Contract and until the warranty expires. .1 Cement, aggregates, water, admixtures: in accordance with CAN/CSA A23.1 and CAN3 A23.4. .2 Welded wire fabric: in accordance with ASTM A185/A 185M. .3 Hardware and miscellaneous materials: in accordance with CAN/CSA A23.1. Submittals Qualifications PART 2. PRODUCTS 2.1 Materials CONTRACT NO T-12-16 Section 03450 ARCHITECTURAL PRECAST CONCRETE Page 3 of 4 DATE: April 2012 2.2 2.3 2.4 2.5 2.6 .4 Forms: in accordance with CAN3 A23.4. .5 Air entrainment admixtures: in accordance with CSA/CAN3A266.1 M78. .6 Chemical admixtures: in accordance with CSA/CAN3-A266.2 M78. .1 Concrete. .1 Proportion normal density concrete in accordance with CAN/CSA A23.1. .2 Minimum compressive strength at 28 Days: 35 MPa. .3 Nominal size of coarse aggregate: 15 mm. .1 Manufacture units in accordance with CAN3 A23.4, and CSA A251. .2 White Solar Reflective Roof Pavers as manufactured by Armtec Infrastructure Inc., or approved equivalent. Size: 610 mm x 610 mm x 57mm .1 .2 Weight: 46kg per panel .1 Standard Matte Finish by Armtec Infrastructure Inc., or approved equivalent. .1 Provide the Consultant with certified copies of quality control tests related to this Contract as specified in CAN3 A23.4 and CSA A251. .2 Provide records from the Contractor’s in house quality control program based upon plant certification requirements to the Consultant for inspection and review. .3 The Contractor shall ensure that precast plants will keep complete records of the supply source of concrete material, steel reinforcement, prestressing steel and provide them to the Consultant for review upon request. .1 Double sided non-woven Membrane Protective Geotextile over Drainage Core (Composite). Core Material .1 1. Extruded HDPE Mixes Manufactured Units Finishes Source Quality Control Accessories CONTRACT NO T-12-16 Section 03450 ARCHITECTURAL PRECAST CONCRETE DATE: April 2012 Page 4 of 4 2. .2 .3 .4 Thickness: 0.635cm (0.25-inch), nominal, normal duty. 3. Compressive strength: 1915 kN/m2 4. Flow Q: 106.0 lpm/m width in accordance with ASTM D4716. Geotextile Protection Layer 1. Material: Non-woven needle punch polypropylene 2. Weight: 136 g/m2 J-Drain 1000 series by JDR Enterprises, Inc. Or approved equivalent Product. PART 3. EXECUTION 3.1 3.2 Erection .1 Perform precast concrete Work in accordance with CAN3 A23.4 and CAN3 A23.3 CAN/CSA S6. .2 Place in locations as indicated in the Contract Documents, using care to prevent damage to substrate or adjacent materials. .1 Obtain approval of cleaning methods from the Consultant before cleaning soiled precast concrete surfaces. Cleaning END OF SECTION