This sample chapter is for review purposes only. Copyright © The Goodheart-Willcox Co., Inc. All rights reserved. 168 Unit 12 Foundation Prints Technical Terms Auger cast pile Basement plan Caissons Concrete masonry units Floating slab construction Footings Foundation plan Friction pile Frost line Grade beam Keyway Monolithic slab Slab-on-grade Steel pile Waterproofing Learning Objectives After completing this unit, you will be able to: • Identify footings on a foundation plan. • Identify types of foundation support systems. • Identify various components of a foundation system. • Recognize reinforcing steel on prints. Once the building has been located on the plot and the necessary site clearing and excavation is complete, work begins on the concrete footings and foundation walls. The details of construction for the footings and foundation walls for residential-type construction are found on the foundation plan (or basement plan). The footings and walls must be carefully laid out because the entire structure is built upon the footings and foundation walls and depends on their accuracy. To make print reading easier, this unit explains how footings and foundations are located, excavated, and constructed. Slab-ongrade floor construction is also discussed. Footings Footings are the “feet” upon which the entire building rests, Figure 12-1. The sizes of the footings are shown on the foundation plan or on a detail of the foundation wall. The footing size is determined by architects and engineers, based on the type of soil (determined by tests) and the weight of the building. The load of the building is transferred through the upper portion of the Reinforcing steel Section 4 Reading Prints Footings are also required under columns. These footings frequently are wider and thicker than footings for foundation walls, because the column loads are concentrated in one spot. See Figure 12-2. Fireplace chimneys and similar concentrations of weight also require larger footings. Footings are located using strings attached to batter boards set back from the excavation. The footings can be trenches cut into the floor of the excavation, or they can rest on the excavation floor. In the latter case, boards are used to form the footing sides to the proper width and height. Footings must rest on undisturbed earth below the frost line, the deepest point to which the ground will freeze in a given region. The local building code will give the depth of the frost line, and how far below it the bottoms of the footings must be placed. Steel reinforcing rods are placed in the footings. This is especially important when footings must pass over earth previously disturbed due to an earlier excavation. When a poured concrete foundation wall is to be erected on the footing, the Keyway for poured wall Reinforcing steel Column Figure 12-1. Footings are designed to carry the weight of the entire building and to transfer that weight to the earth below. Depth structure down to the foundation walls onto the footings and into the ground. There are many types of foundation systems; this unit will cover those listed below. • Footings and walls • Grade beams • Auger cast piles • Caissons • Steel H-piles Square Figure 12-2. Footings for columns have a larger cross section than wall footings. A square shape is normally used. drawing may call for a keyway to be cast in the footing to anchor the wall. Refer to Figure 12-1. On a foundation plan, footings are shown as hidden lines, Figure 12-3. The width of the footing under the foundation walls and columns is shown. Reinforcing rods are shown as dots in sectional views. On elevation drawings, these rods are indicated by long dashed lines. In addition, notes on the drawing and in the specifications must be carefully checked for details relating to construction of the footings. Foundation Walls Foundation walls are the base of the building. They transfer the weight of the building to the footings and to the ground below. Foundation walls can be poured-in-place concrete or concrete masonry units (concrete block). Poured-in-place concrete is used where soil and weather conditions exert considerable side pressure on the walls. Where feasible, the use of concrete masonry units is an efficient way of constructing a foundation wall, because no forms are required. Usually, both poured and block walls are reinforced with steel rods. Foundation walls and columns are shown as solid lines on the foundation plan. The space between the lines represents the material used. Foundation walls and footings are shown as hidden lines in elevation views, Figure 12-4. A foundation wall section is shown in Figure 12-5. The symbols used in the section indicate the general type of material used. However, these materials will be detailed in notes on the drawing or in the specifications. Fireplaces and chimneys are shown on the foundation plan with appropriate dimensions. Details are drawn to provide construction details, Figure 12-6. Unit 12 Foundation Prints 169 170 Section 4 Reading Prints Concrete wall Concrete wall flooring Concrete column Column footing Wall beam spanning wall footings Top of footing elevation TOF = 91′-4″ Top of footing elevation TOF = 89′-4″ Pilaster Footing steps Figure 12-3. Wall and footing partial foundation plan. Figure 12-5. A foundation wall section provides a detailed view of the footing and wall construction. Note the wider footing, which indicates that this wall is being used as a retaining wall. Grade Beams Figure 12-4. Elevation view of a residence, showing foundation wall and footing as hidden lines. A reinforced concrete beam that spans from footing to footing is called a grade beam. The beam is formed on the ground, or formed by a trench in the earth. It is typically used to span over weak disturbed spots in the soil support system. See Figure 12-7. Unit 12 Foundation Prints 171 172 Section 4 Reading Prints system on a drawing, you will see that there are usually several auger cast piles clustered together. They are topped with a pile cap to make the cluster work as a total load system, Figure 12-8. removed and the bottom of the caisson tested for soil load capacity. After the hole passes inspection, a steel reinforcing cage is installed, and the hole is filled with concrete. Caissons Steel Piles Caissons are also drilled, and are usually from 18″–72″ in diameter, Figure 12-9. Caissons are drilled to design depth. The drill is then A steel pile is a long H-shaped (H-pile) or round (pipe pile) steel member that is hammerdriven into the earth. The pile is driven to a PLAN VIEW Building load Column Pile cap Figure 12-6. This sectional view of a fireplace provides the needed construction details and dimensions. Auger cast pile Piles and Caissons Auger cast piles, caissons, and steel piles all are used to transfer loads down through unsuitable soil to more appropriate load carrying materials. Pile socketed into rock for support A Auger Cast Piles Earth provides the form for the concrete Figure 12-7. A grade beam serves as a building support. This type of foundation system is drilled with a 12″–14″ steel auger to the appropriate design depth. While the drilling shaft is being raised out of the hole, concrete is pumped down the shaft to fill up the cavity. When you view an auger cast pile B SECTION VIEW Figure 12-8. Section and plan of auger cast piles. A—Friction pile. B—Pile drilled and socketed into rock. Unit 12 Foundation Prints 173 Section 4 Reading Prints foundation, the elevations will be given for various parts of the system. For wall footings, the top of the footing is given an elevation marked, for example, as TOF = 91′-4″ and 89′-4″. Sometimes, the bottom of the footing will also be marked as an elevation. For auger cast piles, caissons, and steel piles, the top of the pile cap (upon which the structure is going to be built) is the elevation given. All the information is defined in details and schedules. Each engineer and project will have its own special elevation designation system. Become familiar with the plans early in the preconstruction phase to work out any coordination problems. Concrete or steel column Pile cap (not always required with caissons) Caisson typically 18″ to 72″ in diameter 174 PLAN VIEW 1/2″ expansion joint Floating slab 4″ Gravel Compacted fill or undisturbed soil Foundation wall Footing Figure 12-12. A slab floor poured within the foundation walls. Slab-on-Grade Building load Concrete pile cap Suitable soil support material or rock Rock Soil Figure 12-9. Drilled concrete caisson. Steel H- piling Soil resistance is the primary support suitable support stratum or driven to friction resistance of the soil (this type of pile is referred to as a friction pile). A friction pile works on the principle of frictional resistance on the sides of the pile from the soil into which it has been driven. When you look at this type of foundation system on a drawing, you will usually see several steel piles clustered together and topped with a pile cap to make the cluster work as total load system. See Figure 12-10. A concrete slab poured at ground level is called a slab-on-grade. Concrete slabs are used as both basement floors and main floors. Basement floors are poured after the footings and foundation walls are in and sometimes, in residential construction, before the rough framing starts. Floating slab construction uses a monolithic slab (one continuous unit), Figure 12-11. Another method of producing a slab floor is to first pour the foundation walls to floor height. Then, the area within the walls is filled with soil and gravel. Finally, the floor is poured within the walls, separated by an expansion joint, Figure 12-12. Load-bearing walls over slab floors require a thickened slab, Figure 12-13. These areas are indicated by hidden lines and a note. No. 3 at 12″ OC both ways PLAN VIEW SECTION VIEW Figure 12-13. The slab is thickened to create a beam below loadbearing walls. 4″ Slab Reinforcement Below frost Foundation Elevations A critical part of starting a building properly is constructing the foundation at the designed elevation. Elevations for a foundation are marked on the foundation plan view. Depending on the type of Masonry ledge Stirrup Reinforcing steel Gravel 8″ SECTION VIEW 4″ Compacted fill or undisturbed soil 2 #4 Cont. Figure 12-10. Building foundation system using steel H-piling. Figure 12-11. A monolithic slab foundation. 4″ 12″ A slab-on-grade is not considered a structural slab, but can have reinforcement to assist in loadcarrying and resistance to cracking. Steel reinforcing rods or welded wire fabric are cast in the concrete when a slab is subjected to drying shrinkage. Reinforcement is also used when the concrete slab is expected to be subjected to tension due to the settling of a dirt fill or heavy load. A typical note specifying welded wire fabric Unit 12 Foundation Prints 175 or reinforcing rods in a concrete floor would read as follows: Test Your Knowledge 5″ thk. slab w/ 6 × 6 – W10 × W10 WWF OVER Write your answers in the spaces provided. ABC GRAVEL SUBBASE ______ 1. When a footing must be placed above ground that has been disturbed, it should be _____. A. twice as thick as usual B. twice as wide as usual C. reinforced with bars D. no different than usual E. None of the above. or #4 @ 18″o/c EW OVER 4″ABC Waterproofing Foundations Waterproofing of foundation walls is needed in areas where soil and climatic conditions demand protection from underground water. Residential waterproofing can be done with a variety of materials, but usually consists of mopping the outside of the foundation wall with tar or asphalt, Figure 12-14. Sometimes, a polyethylene sheet is applied over the tar. Drawings for a foundation to be waterproofed will have a heavy black line on the exterior wall with a note indicating location. Also, the building specifications may specify the exact material and process to be used. A layer of crushed rock or gravel is laid below the floor area. This layer is then covered with a heavy plastic vapor barrier to keep the dampness in the ground from transferring to the slab. ______ 2. On a foundation plan, footings are shown as _____. A. continuous lines B. hidden lines C. phantom lines D. dotted lines E. Footings are not shown on foundation plans. ______ 3. _____ rods are used to reinforce footings, slabs, and foundation walls. A. Iron B. Deformed steel C. Aluminum D. Tungsten E. All of these are used. ______ 4. A(n) _____ is placed between a slab and a wall. A. air gap B. roll of insulation C. reinforcing bar D. expansion joint E. All of these are commonly placed between a slab and a wall. ______ 5. Welded wire fabric is used to _____. A. reinforce steel beams B. protect basement windows C. reinforce concrete slabs D. protect welders from heat E. None of the above. Figure 12-14. Tar being applied to a residential foundation wall for waterproofing. 176 Section 4 Reading Prints ______ 6. True or False? Footings are only needed below the perimeter walls of a building. ______ 7. True or False? The positions of footings are determined by stretching lines between batter boards. ______ 8. True or False? The frost line is the depth at which the ground is frozen when the temperature is 25°F (–4°C). ______ 9. True or False? Normally, a column footing is larger than a footing below a wall. ______10. True or False? Foundation walls do not allow water to pass through. 11. What are the five types of foundation systems described in this unit? ______________________________________________________________________ 12. How does a steel friction pile support a load? ______________________________________________________________________ 13. What is the purpose of the pea gravel around the foundation wall? ______________________________________________________________________ 14. What does the term TOF indicate? ______________________________________________________________________ 15. What is the purpose of the reinforcement in a slab-on-grade? ______________________________________________________________________ Unit 12 Foundation Prints Figure 12-15. Use with Activity 12-2. This is Sheet 2 of the footing and foundation print. 177