(EV) Budgeted cost of work performed: The planned (budgeted) cost of tasks that are complete. This is the actual earned value of the project, because it is the value of the work that has been completed. (AC) Actual Cost of work performed: The actual costs of tasks that have been completed. (PV) Budgeted cost of work scheduled: The planned (budgeted) cost of all tasks (completed and not yet completed) that are scheduled for the time period being reported on. (CV) Cost Variance: The cost variance is the difference between planned and actual costs for completed work CV = EV- AC. (CPI) Cost Performance Index: CPI = EV / AC. Cost Performance Index indicates whether you are over (<1.0), under (>1.0), or on budget (=1.0). (SV) Schedule Variance: The schedule variance is the difference between the budgeted cost of work performed and the budgeted cost of work scheduled. SV = EV – PV. (SPI) Schedule Performance Index. SPI = EV / PV. Schedule Performance Index indicates whether you are behind (<1.0), ahead (>1.0), or on schedule (=1.0). (BAC) Budget At Completion: The total project budget. (EAC) Estimate At Completion: This is a reestimate of the total project budget. The original budget is multiplied by the actual cost and divided by the earned value (budgeted cost of work performed). EAC = original estimate * (AC / EV) = BAC / CPI = AC + BAC - EV = AC + ETC. It’s a way of saying that if the current cost performance trends continue, the final cost can be predicted. (ETC) Estimate to Completion: ETC indicates how much more must be spent to complete the project on time from today. ETC = EAC – AC. Example: (x = task complete, - = task scheduled) Task A B C D E F G H Budget 100 100 100 100 100 100 100 100 EV 100 100 100 100 AC 80 100 90 110 PV 100 100 100 100 100 100 March x x x x April May June July - - x x - As of April 30: AC = 380, EV = 400, PV = 600. CV = EV – AC = 400 – 380 = 20 which means the project is under budget. CPI = EV / AC = 400 / 380 = 1.05 which means the project is 5% under budget, so for every dollar put into this project, thus far we are getting a little more than a $1 in return. SV = EV – PV = 400 – 600 = (-200) which means the project is behind schedule. SPI = EV / PV = 400 / 600 = 0.66 which means project is 33% behind schedule and is only progressing at 66% instead of 100%. EAC = 800 * (380 / 400) = 760 which means that the project could possibly cost only $760 which is less than the $800 budgeted. ETC = EAC – AC = 760 – 380 = 400 which means $400 more must be spent from April 30 to complete the project on time by the end of July.