THE UNIVERSITY OF VIRGINIA REQUEST FOR PROPOSAL FOR INDEPENDENT COMMISSIONING SERVICES: COMMISSIONING AGENT Ivy Translational Research Building Ivy Trans CxA RFP Rev 5 Page 1 of 15 The University of Virginia (“University”) requests a written proposal to secure Commissioning Agent (“CxA”) services for the Ivy Translational Research Building (“Project”). The University is committed to commissioning this facility to ensure that all systems are well designed, complete and functioning properly upon occupancy, and that the University’s Operating and Maintenance staff have adequate system documentation and training. The Project is seeking a LEED Certified Silver Rating. The CxA will generate a complete and total ‘Commissioning Agent’ proposal, which may include information, items and services in addition to those required in this RFP. A copy of Schematic Design package and associated addenda are provided for the development of the proposal. This RFP document will be the basis of the contract for CxA services on this Project. It will be “conformed” to any agreedupon clarifications from the candidate’s proposal and will be the only description of the services to be provided contained in the contract. 1. Nature of the Project 1.1. Description: The Ivy Translational Research Building project will provide a new research building accommodating a mix of life sciences, including but not limited to Biology, Chemistry, Core Laboratories and Imaging for up to 30 faculty led research teams. This approximately 110,000 gross square foot building is intended to replace existing facilities and provide additional, modern research space for current faculty whose research needs are expected to grow, and for new faculty who will be coming in with research space needs of their own. As the specific end-users will not be identified for some time, the building will be planned as a “flexible/modular” laboratory facility, suitable for typical users, but also reasonably adaptable for specific needs once the individual users and their research processes are identified, possibly during or after construction. 1.2. Schedule: The selected firm must be capable of adhering to the University’s schedule. In addition, timely completion of the commissioning work provided under the contract resulting from this RFP is of the essence. The selected firm must be capable of responding promptly. 1.2.1. 1.2.2. 1.2.3. 1.2.4. 1.2.5. 1.2.6. Schematic Design: Design Development (Preliminary Design): Construction Documents: Construction Trade Packages: Construction and Commissioning: Occupancy: Competed Complete on or about 1/09 Complete on or about 5/10 Complete on or about 11/10 Complete by 2/1/13 2/2/13 2. Scope of Commissioning Services: The objective of commissioning is to provide documented confirmation that the new facility fulfills the functional and performance requirements of the University, its occupants, and the Operation & Maintenance (O&M) personnel. To reach this goal, it is necessary for the commissioning process to establish and document the University’s Project Requirements for system function, performance, and maintainability; as well as to verify and document compliance with these criteria throughout design, construction, start-up, and the initial period of operation. A Turnover Package, as defined in Exhibit 4, fully documenting the building, area, system or component that is being turned over from the Project to the Operating and Maintenance staff, shall also be provided. The CxA will be involved throughout the Project from the design development phase through the warranty phase. The primary role of the CxA during the design phase is to develop detailed commissioning specifications and review the design to ensure it meets the University’s objectives. During construction, the CxA will develop and coordinate the execution of a commissioning plan, which includes observing and Ivy Trans CxA RFP Rev 5 Page 2 of 15 documenting all system’s performance to ensure that systems are functioning in accordance with the University’s Project Requirements and the contract documents. The CxA is not responsible for design or general construction scheduling, cost estimating, or construction management, but may assist with problem-solving or resolving non-conformance issues or deficiencies. The Scope of Work of the CxA shall also generally be in compliance with ASHRAE Guide 1-1996. The building systems are being commissioned as part of a program to achieve a LEED Certified Silver Rating. All tasks must be performed to fulfill the LEED Fundamental Building Systems Commissioning and Enhanced Commissioning requirements, including compliance with LEED version 2.2. In summary, the CxA will provide the University documented verification that the Building Systems Contractors (Mechanical, Electrical, Building Automation, Plumbing, Fire & Life Safety, Security and other necessary systems) have completed their work and that the equipment and systems are fully operational, tested & balanced, meet design and contract document requirements. The CxA shall also assure that all turnovers are defined and documented in a Turnover Package. 3. Basic Services 3.1. Design Development Phase Services: 3.1.1. 3.1.2. 3.1.3. 3.1.4. 3.1.5. 3.1.6. 3.1.7. 3.1.8. Review preliminary (35%) documents and submit comments. Coordinate the commissioning work with the design team and University. Develop a design-phase commissioning plan which will be incorporated in the Division 1 (general requirements) specifications. Conduct a design-phase scoping meeting and identify responsibilities per the design phase commissioning plan. Review the University’s Project Requirements/Design Intent/Basis of Design documentation for clarity and completeness. Develop a draft design phase commissioning plan. Perform a review of the design, drawings and specifications at the end of the design development phase (35%). The design review scope is detailed in Exhibit 1. Develop a list of recommended Operating Procedures for the Project’s systems or components. Submit the list and the proposed format and content of the procedures for review and approval by the University. 3.2. Construction Documents and Bid Phase Services: 3.2.1. 3.2.2. 3.2.3. Review 95% construction documents and submit comments. Develop a draft construction phase commissioning plan. Coordinate a controls integration meeting where the electrical and mechanical engineers and the CxA discuss integration issues between equipment, systems and disciplines to ensure that integration issues and responsibilities are clearly described in the specifications. 3.2.4. Develop full commissioning specifications for all commissioned equipment and systems. Coordinate with and integrate into the specifications produced by the architect and engineers. Anticipate commissioning sections in Divisions 1 (General Requirements), 15 (Mechanical), and 16 (Electrical), plus a standalone commissioning section (typically Div. 17). One or more of the following documents can be used as a guide for content, rigor and format: 3.2.4.1. Model Commissioning Plan and Guide Specifications, USDOE/FEMP; Portland Energy Conservation, Inc. (PECI), the PECI document can be downloaded free at http://www.peci.org. Ivy Trans CxA RFP Rev 5 Page 3 of 15 3.2.4.2. The HVAC Commissioning Process, ASHRAE Guideline 1-1996, a copy of the ASHRAE document can be obtained by contacting ASHRAE at 404-636-8400. 3.2.5. The commissioning specification and the relevant equipment specifications will include a detailed description of the responsibilities of all parties, details of the commissioning process; reporting and documentation requirements, including formats; alerts to coordination issues, deficiency resolution; construction checklist and startup requirements; the functional testing process; specific functional test requirements, including testing conditions and acceptance criteria for each piece of equipment being commissioned and detailed training requirements for the components and systems. 3.2.6. Conduct a commissioning specification review meeting with the University and Project Design Team. 3.2.7. At the direction of the University Project Manager, establish the names, sequencing and boundaries of the systems, areas, buildings or components of the Project that will be the basis of the Turnover Packages. 3.2.8. Perform a review of the design, drawings and specifications during the contract document phase prior to issuing the contract documents for construction. 3.2.9. Attend pre-bid meeting(s) to answer commissioning related questions. 3.2.10. Participation in the contractor(s) (Refer to Section 4.1 for list) interview process, if requested. 3.3. Construction Phase Services: 3.3.1. Coordinate and direct the commissioning activities in a logical, sequential and efficient manner using consistent protocols and forms, centralized documentation (web-based data base and electronic submittal collection, O&M manuals and issues resolution in one central system is preferred), clear and regular communications and consultations with all necessary parties, frequently updated timelines and schedules and technical expertise. 3.3.2. Coordinate the commissioning work and, with the Construction Manager and Contractors, ensure that commissioning activities are being scheduled into the master schedule. 3.3.3. Revise, as necessary, the construction phase commissioning plan developed during design, including scope and schedule. 3.3.4. Plan and conduct commissioning meetings as needed and distribute minutes. 3.3.5. Request and review additional information required to perform commissioning tasks, including O&M materials, contractor start-up and checkout procedures. Before startup, gather and review the current control sequences and interlocks and work with contractors and design engineers until sufficient clarity has been obtained, in writing, to be able to write detailed testing procedures. 3.3.6. Review selected contractor submittals applicable to systems being commissioned for compliance with commissioning needs. Review submittals concurrent with A/E review but prior to A/E submittal approval. 3.3.7. Review, as requested, requests for information and change orders for impact on commissioning and the University’s objectives. 3.3.8. Review start-up and initial systems checkout plans developed by contractors for selected equipment and systems. 3.3.9. As necessary, observe component and system installations. 3.3.10. Attend selected planning and job-site meetings to obtain information on construction progress. 3.3.11. Review construction meeting minutes for revisions/substitutions related to the commissioning process. Assist in resolving any discrepancies. 3.3.12. Witness HVAC piping pressure test and flushing, sufficient to be confident that proper procedures were followed. Include testing documentation in the Commissioning Record. Ivy Trans CxA RFP Rev 5 Page 4 of 15 3.3.13. Witness any ductwork testing and cleaning sufficient to be confident that proper procedures were followed. Include documentation in the Commissioning Record. 3.3.14. Document start-up and start-up checkout plans completion by reviewing completed construction checklists and by selected site observation. 3.3.15. Approve air and water systems balancing by spot testing and by reviewing completed reports and by selected site observation. 3.3.16. With necessary assistance and review from installing contractors, write the functional performance test procedures for equipment and systems. This will include manual functional testing, energy management control system trending and may include standalone data-logger monitoring. Submit to Construction Manager (“CM for review and approval if required. 3.3.17. Analyze functional performance trend logs and monitoring data to verify performance. 3.3.18. Coordinate, witness and document manual functional performance tests performed by installing contractors. Coordinate retesting as necessary. The CxA will direct the retesting of the equipment once at no “charge” to the University for their time. The CxA’s time for a second retest, if required due to no fault of the CxA, will be compensated by the University. The functional testing shall include operating the system and components through each of the written sequences of operation, and other significant modes and sequences, including startup, shutdown, unoccupied mode, manual mode, staging, miscellaneous alarms, power failure, security alarm when impacted and interlocks with other systems or equipment. Sensors and actuators shall be calibrated during construction check listing by the installing contractors, and spot-checked by the CxA during functional testing. Tests on respective HVAC equipment shall be executed during both the heating and cooling season. However, some overwriting of control values to simulate conditions shall be permitted. Functional testing shall be done using conventional manual methods, control system trend logs, and read-outs or stand-alone data loggers, to provide a high level of confidence in proper system function, as deemed appropriate by the CxA and the University. 3.3.19. Maintain a master issues log and a separate record of functional testing (web-based is preferred). Report all issues as they occur directly to the University Project Team with copy to the CM. Provide directly to the University Project Team and CM written progress reports and test results with recommended actions. 3.3.20. Review equipment warranties to ensure that the University’s responsibilities are clearly defined. 3.3.21. Oversee and approve the training of the University’s O&M personnel. 3.3.22. Review and approve the preparation of the O&M manuals for commissioned equipment. 3.3.23. Compile a Commissioning Record, which shall include: 3.3.23.1. A brief summary report that includes a list of participants and roles, brief building description, overview of commissioning and testing scope, and a general description of testing and verification methods. For each piece of commissioned equipment, the report should contain the disposition of the CxA regarding the adequacy of the equipment, documentation and training meeting the contract documents in the following areas: 3.3.23.1.1. Equipment meeting the equipment specifications 3.3.23.1.2. Equipment installation 3.3.23.1.3. Functional performance and efficiency 3.3.23.1.4. Equipment documentation 3.3.23.1.5. Operator training. 3.3.23.2. A list of all outstanding non-compliance items shall be specifically listed. Each non-compliance issue shall be referenced to the specific functional test, inspection, trend log, etc. where the deficiency is documented. 3.3.23.3. Recommendations for improvement to equipment or operations, future actions, commissioning process changes, etc. shall also be listed. Ivy Trans CxA RFP Rev 5 Page 5 of 15 3.3.23.4. Also included in the Commissioning Record shall be the issues log, commissioning plan, progress reports, submittal and O&M manual reviews, training record, test schedules, construction checklists, start-up reports, functional tests, and trend log analysis. 3.3.24. Develop a Systems Energy and Management Manual (also referred to by LEED as the Systems Manual) that consists of the following: Final version of the University's project requirements and basis of design, As-built sequences of operations for all equipment as provided by the design professionals and contractors, including time-of-day schedules and schedule frequency, and detailed point listings with ranges and initial set points, ongoing operating instructions for all energy- and water-saving features and strategies, functional performance tests results (benchmarks), blank test forms, and recommended schedule for ongoing benchmarking, seasonal operational guidelines, recommendations for recalibration frequency of sensors and actuators by type and use, single line diagrams of each commissioned system, troubleshooting table for ongoing achievement of the University's project requirements and guidelines for continuous maintenance of the University's project requirements operational requirements and basis of design (basis of operation). 3.3.25. Collect or generate, as applicable, the documents/records and conduct commissioning to provide the information required by the Turnover Package Checklist, refer to Exhibit 4. The Turnover Package will be prepared by the CxA and shall include all items listed in Exhibit 4. Included in the CxA’s Turnover Package responsibilities are: 3.3.25.1. Generate the final operating procedures for the building systems or components as agreed during the preliminary design process. Earlier drafts of these procedures shall be generated such that they can be used in the training program. 3.3.25.2. Based on the recommendations of the equipment manufacturers, generate maintenance procedures for every item requiring periodic maintenance. This data shall be provided in an approved format similar to that shown in Exhibit 5. It shall be provided in an Excel spreadsheet formatted for ready entry by an administrative employee of the University into the Maximo maintenance system. (The CxA may also, subject to University approval, implement a process by which this information is entered directly into the Maximo system.) 3.3.25.3. Generate a spare parts list as defined in Exhibit 4. 3.4. Warranty Period Services: 3.4.1. 3.4.2. Coordinate and supervise required opposite season or deferred testing and deficiency corrections and provide the final testing documentation for the Commissioning Record and O&M manuals. Return to the site at 10 months into the 12 month warranty period and review with facility staff the current building operation and the condition of outstanding issues related to the original and seasonal commissioning. Also interview facility staff and identify problems or concerns they have with operating the building as originally intended. Make suggestions for improvements and for recording these changes in the O&M manuals. Identify areas that may come under warranty or under the original construction contract. Assist facility staff in developing reports and documents and requests for services to remedy outstanding problems. 4. Systems to be Commissioned The following systems and assemblies will be commissioned: Ivy Trans CxA RFP Rev 5 Page 6 of 15 4.1. Heating, ventilating and air conditioning systems including controls 4.2. Lighting and control systems 4.3. Verify Testing and Balancing (TAB) 4.4. Energy Plant, including 4.4.1. Hot Water Boilers and associated equipment 4.4.2. Chillers and associated equipment 4.4.3. Emergency generator and associated equipment 4.5. Main electrical switchgear 4.6. Laboratories and their systems 4.7. Laboratory Hoods 4.8. Air lock systems, Pressurization between air locks 4.9. Building Automation System (BAS, Spec. Division 17) 4.10. Security systems 4.11. Biological safety cabinets 4.12. Biosafety lab pressure monitoring systems 4.13. All MEP systems (major mechanical and plumbing equipment, including pumps, heat exchangers, decontamination equipment, etc.) 4.14. Elevators 4.15. Fire & Life Safety systems Minimum Sample for Commissioning: For the purposes of this Project, the minimum sample must be no less than 10 percent and no less than ten units. In this context, a “unit” is one item of a larger group of the same type of items (e.g., diffusers, VAV boxes, fan coil units, sensors, and dampers). Control Points: The CxA must verify that the control system was checked and that it is commanding, reporting and controlling as specified in the construction documents. Verification must include a minimum sample of each type of control point. In addition, the controls that are verified must be within a minimum sample of each type of component, equipment, subsystem and system where the sensor type is installed. If any control point in the minimum sample is not commanding, reporting and controlling as specified in the construction documents, then an additional minimum sample of each type of control found not to be performing must be checked, until all control points in a minimum sample are found to be performing as specified. Sensors: The CxA must verify that all sensors have been calibrated so that the value reported in the control system represents the actual local value. Verification must include re-calibrating a minimum sample of each type of sensor. In addition, the sensors that are re-calibrated must be within a minimum sample of each type of component, equipment, subsystem and system where the sensor type is installed. If any sensor in the minimum sample is out of calibration, then an additional minimum sample of each type of sensor found to be out of calibration must be re-calibrated, until all sensors in a minimum sample are found to be in calibration. Actuators: The CxA must verify that all actuators have been adjusted to fully close and open dampers and valves, and also must verify by visual observation that the reported values in the control system are correct. Verification must include checking the operation of a minimum sample of each type of actuator, valve, and damper. In addition, the actuator, valve, and damper must be within a minimum sample of each type of component, equipment, subsystem and system where the type of actuator, valve, and damper is installed. If any actuator, valve, or damper in the minimum sample does not operate as required in the construction documents, then an additional minimum sample of each type of actuator, valve, or Ivy Trans CxA RFP Rev 5 Page 7 of 15 damper found not to be operating as required must be verified until all actuators, valves, or dampers in a minimum sample are found to be to be operating as required. Test and Balance: The CxA must verify the Test and Balance (“TAB”) by re-measuring a minimum sample of values reported for each type of component, equipment, subsystem, or system in the TAB reports. In addition, the values that are re-measured must be within a minimum sample of each type of subsystem and each type of system. If any re-measured value in the minimum sample deviates from the values in the TAB report or from the requirements in the construction documents by more than 10 percent, then an additional minimum sample must be re-measured for each type of component, equipment, subsystem or system for which there is a deviation, until all re-measured values in a minimum sample are within 10 percent of the values in the TAB report or of the requirements in the construction documents. Cost of Retesting: The following retesting provisions shall apply to this Project: For a deficiency identified, not related to any pre-functional checklist or start-up fault, the CxA will direct the up to 10% retesting of the equipment at no additional charge. The time for the CxA to direct any retesting required because a specific pre-functional checklist or start-up test item, reported to have been successfully completed, but determined during functional testing to be faulty, may be charged as an additional service once the allowance for retest has been used. Note: To minimize this retesting, CxA will check first installation of many typical units to surface any issues before multiple installations are made. These provisions shall be included in the commissioning specifications. 5. Proposal requirements: Proposals need not be voluminous, but shall provide sufficient information to allow the University to evaluate the CxA’s approach, experience, staff and availability. The proposer shall: 5.1. Provide an organization chart for managing and executing this contract. 5.2. List the individual(s) who will be the CxA for the design phase and for the construction phase of the contract (they may be different people). This information is required in addition to any resumes the proposer submits. 5.3. Provide resumes for key staff and sub-consultants. The resumes shall include specific information about expertise in commissioning tasks, (e.g. design reviews, specification writing, commissioning management, troubleshooting, test writing, test execution, energy management, etc.). 5.4. Briefly describe relevant experience of the proposer’s team in the following areas. List each party’s involvement. a) projects similar to this one; b) traditional test and balance; c) O&M experience; d) energy-efficient equipment design and control strategy optimization; e) experience in environmental sustainable design; f) project and construction management; and g) system design (specify) 5.5. Describe your proposed approach to managing the Project expertly and efficiently, including distribution of tasks, travel, and duration of which staff will be on site during what periods of time, etc. Describe what approach you will take to integrate the commissioning into the normal Ivy Trans CxA RFP Rev 5 Page 8 of 15 design and construction process in order to minimize potential time delays. Describe what you will do to foster teamwork and cooperation from contractors and Design Team and what you will do to minimize adversarial relationships. Describe how you intend to determine the appropriate level of commissioning effort for the various systems and equipment. 5.6. As an attachment, provide the following work products that members of the proposer’s team wrote. List the team member who actually wrote the document. Work from the designated CxA is preferred. a) Commissioning plan that was executed; b) Commissioning specifications; and c) An actual functional test procedure form that was executed. 6. Fee proposal: The selected firm shall submit a fee proposal as follows: 6.1. A lump sum price proposal for the Design Development Phase services. 6.2. An estimate of the price in day paid dollars (based on the schedule information provided) for all other services required by this document (i.e. from the beginning of the construction documents through the end of the CxA’s involvement in the Project as defined by this document). This estimate shall state the assumptions upon which it is based. Ivy Trans CxA RFP Rev 5 Page 9 of 15 Exhibit 1 FOCUSED DESIGN REVIEW SCOPE The Commissioning Agent will perform a review of the design documents for the following issues at: Preliminary Design (35%) Construction Documents (95%) Design Area Review Description Design narrative and design basis Ensure that design narrative and basis of design are clear, complete, and meet the original University Objectives as reflected in the Project Requirements/Design Intent/Basis of Design. Commissioning facilitation Review to facilitate effective commissioning (see Exhibit 2). Energy efficiency Review for adequacy of the effectiveness of building layout and efficiency of system types and components for HVAC systems and lighting systems. Control system & control strategies Review HVAC and lighting control system, strategies and sequences of operation for adequacy and efficiency. Operations and maintenance (O&M) Review for effects of specified systems and layout toward facilitating O&M (equipment accessibility, system control, etc.). Indoor environmental quality Review to ensure that systems relating to thermal, air quality, air distribution and ventilation are in accordance with the University Objectives. (See Exhibit 3 for IAQ checklist). O&M documentation and Turnover Packages Verify adequate building O&M and Turnover Package documentation requirements. Training Verify adequate operator training requirements. Commissioning specifications Verify that bid documents adequately specify building commissioning, including testing requirements by equipment type. University’s design guideline or standard Verify that the design complies with the University’s own design guideline or standard. Mechanical Review the mechanical concepts/design for enhancements. Division of Responsibility Review Project design and bid documents to ensure that there is a clear delineation of the responsibilities of the parties for the various commissioning and commissioning related activities. There shall be a well defined division of responsibility (DOR) between the Design Team (A/E), CM, University Staff, Contractors, Suppliers and the CxA. This DOR shall be clear and complete. This includes a clear responsibility for each item in the Turnover Package Checklist Exhibit 4. Ivy Trans CxA RFP Rev 5 Page 10 of 15 Exhibit 2 COMMISSIONING FACILITATION REVIEW The Commissioning Agent shall review the design documents for the following, but the review is not expected to be limited to only these issues: Clear and thorough design documentation, including detailed and complete sequences of operation. Access for reading gages, entering doors and panels, observing and replacing filters, coils, etc. Required isolation valves, dampers, interlocks, piping, etc. to allow for manual overrides, simulating failures, seasons and other testing conditions. Sufficient monitoring points in the building automation system (BAS), even beyond that necessary to control the systems, to facilitate performance verification and O&M. Adequate trending and reporting features in the BAS. Pressure and temperature (P/T) plugs close to controlling sensors for verifying their calibration. Pressure gages, thermometers and flow meters in strategic areas to facilitate verifying system performance and ongoing O&M. Pressure and temperature (P/T) plugs at less critical areas or on smaller equipment where gages and thermometers would be over-kill. Specification of the location and criteria for the VAV duct static pressure sensor and chilled and hot water differential pressure sensor. Adequate balancing valves, flow metering and control stations and control system functions to facilitate and verify reliable test and balance. Uniform inlet connection requirements to VAV terminal boxes and vent/drain valves at each VAV. Clear and complete commissioning specifications for the construction phase. Complete O&M documentation requirements in the specifications. Complete training requirements in the specifications. Review entire document and building information management plan from design through construction and turnover to ensure adequacy and compliance with the University’s program. Ivy Trans CxA RFP Rev 5 Page 11 of 15 Exhibit 3 INDOOR AIR QUALITY COMMISSIONING REVIEW CHECKLIST Design Phase Document the results from each of the following tasks: ___ Determine indoor air quality requirements in accordance with the initial University Objectives of the University’s needs. Codes, standards: ASHRAE Standard 62-1989, Ventilation for Acceptable Air Quality and Standard 55-1992 Thermal Environmental Conditions for Human Occupancy. ___ Identify the sources of outdoor pollutants in the vicinity of the building site: general ambient air quality, exhaust systems, nearby cooling towers, smoke stacks, parking garages, etc. ___ Review expected occupant activity, density and locations where special attention is needed: kitchens, break, photocopy, print and janitorial rooms, labs, material storage rooms, and conference rooms, etc. Review the need for exhaust systems or increased supply air capacity for each area, etc. ___ Ensure that the indoor air quality objectives established in the pre-design phase are included in the design and are well documented in the University Objectives. ___ Establish procedures for verifying and documenting ventilation rates in each area. ___ Review air flow rates for needed exhaust systems, including spot pollutant source removal. ___ Determine that adequate ventilation rates will be maintained during all occupied modes of operations, particularly during VAV terminal box turn-down. Verify laboratory pressurization control system. ___ Review air intakes and exhausts for short-circuiting and for exterior pollution sources such as garages, loading docks, and cooling towers. ___ Review the impact of the office partitions configurations with respect to ventilation effectiveness. ___ Review choice of filtration type and design, materials, and location. ___ Review HVAC material specifications and application regarding potential for airflow erosion, corrosion and microbial contamination (HVAC insulation materials, etc.). ___ Review air supply system to ensure control and minimization of the presence of free water and to minimize microbial contamination (condensate trays, humidifiers, water baffles, mist eliminators, cooling towers). ___ Verify the suitability of access doors and inspection ports to all chambers and components of air handling system plenums. Verify that proper cleaning of both sides of coils, condensate pans and/or humidifier reservoirs can be accomplished through the doors. ___ Verify that the specifications specify proper methods and conditions for operating the HVAC system prior to full control and occupancy, to minimize dirt and unwanted moisture entering the duct work, coils, building cavities and any occupied portions of the building. Note: Indoor air quality (IAQ) commissioning does not ensure that indoor air quality will be adequate or without deficiency at building turnover or during occupancy, unless the University has specifically specified that actual air quality testing be performed. Commissioning for indoor air quality entails performing tasks that minimize the potential for IAQ problems, but it does not eliminate their possibility. The primary source for this checklist was Annex C in ASHRAE Guideline 1-1989R The HVAC Commissioning Process, Public Review Draft, 1996. Ivy Trans CxA RFP Rev 5 Page 12 of 15 EXHIBIT 4: Turnover Package Checklist (exact contents to vary based on project type): Name of turnover (system, area, building or component) Boundary/footprint of turnover (description with marked-up drawing as required) Punch list of incomplete work at time of turnover (can only be items that do not affect safe functioning of the system, area, building or component) Plan for completing remaining work, discussion of any outages required and the role, if any, of the O&M staff in supporting the completion activities. O&M manuals and associated information for items within boundary o Copy of transmittal(s) Confirmation that construction tests (static testing) have been satisfactorily completed or list of outstanding items; confirmation that independent test records have been submitted and are available Confirmation that commissioning (dynamic testing) has been satisfactorily completed or list of outstanding items Final System Operating Procedures, as applicable. These operating procedures shall include an operational narrative for each system. For instance; “VAV boxes unreliable operation post power failure” Inventory/list of equipment Name of item Classification Manufacturer Model # Serial # Cost (definition TBD) Location (building, room number) Date of installation (defined as SC/BO date) Who installed Final Preventive and Corrective Maintenance Procedures, as applicable Spare parts list Provide a list of recommended spare parts for each piece of equipment installed in the facility that requires maintenance on a routine basis and items that might be required to prevent excessive down-time of building operations. This list shall be balanced to provide those materials that are deemed by the CxA to be the best economical balance between items that are a high priority to stock rather than suggesting that every possible part of a mechanical or electrical nature be stocked. This list shall complement the facility’s operational objectives. Status of extra materials (“attic stock” material) Transmittal for stock already turned over Schedule for delivery of any remaining material Confirmation (from the O&M organization) that Maintenance data has been entered into Maintenance System (Maximo) or the status of that effort Systems Control Center (SCC) Items “Points” and programs have been established on one of the existing front ends so that staff can actively monitor the new points. o Points are inputs/outputs such as temperature sensors, AHU status, etc. Appropriate alarms and trends have been established per the design documents for the various points. System Graphics have been provided as required by the design documents. Ivy Trans CxA RFP Rev 5 Page 13 of 15 Training has been provided to SCC staff regarding the new systems or points, especially focusing on any systems with unusual sequences of operation. Electronic versions of control drawings, including the sequences of operation, have been provided to the SCC Manager. MS Visio format is preferred but PDF is acceptable. Electronic versions of as-built drawings for base map updating (this will be a Final Completion item if they are not available at turnover). Training record (date, subject, list of attendees, signatures) HVAC Systems control Plumbing Electrical Fire alarm Sprinkler Systems Elevator Landscape Housekeeping Utilities Specialties Equipment Systems Status of drawings/specifications reflecting as-built condition. Note: If the work has been modified from the approved construction documents, as-built information shall be supplied for any modifications that impact the operability or maintainability of the system, area, building or component. Copy of transmittal(s) Warranty information Duration Administration per attached copy of Directive 360E Contacts Start date Substantial Completion items System performance verified Building Automation Systems head end programming complete Balance report submitted (provide date of final, accepted balance report) HECO 13.3B Checklist for Beneficial Occupancy, attached Contact list PM CAM Signature Date/Time of Turnover O&M representative’s signature acknowledging that the Turnover Package was delivered as shown. Ivy Trans CxA RFP Rev 5 Page 14 of 15 EXHIBIT 5 Ivy Trans CxA RFP Rev 5 Page 15 of 15