EMIS 8364 ENGINEERING MANAGEMENT Fall 2009 Ganesh Harpavat, Ph. D., M.B.A. Tel. No. (972) 691 - 2850 Lecture # 10 Topic: Managing Production Operations Management of Production Operations Involves: In-house or outsourcing decisions Site selection Facility design and construction Plant layout Human resource planning Production process planning Manufacturing planning and control Quality control Distribution resource planning Inventory control and management Repair and warranty management Facilities Design Projects: New facility construction New design in an existing facility Redesign of a restricted area Adding a machine in an existing facility Computer Routines for Facilities Layout: Construction type Improvement type Plant Layout: Fixed position layout EMIS 8364, Engineering Management 1 Product layout Process layout Group Technology Computer Aided Layout: Computerized Relative Allocation of Facilities Technique (CRAFT) Computerized Facilities Design (COFAD) Plant Layout Analysis and Evaluation Technique (PLANET) Computerized Relationship Layout Planning (CORELAP) Automated Layout Design Program (ALDEP) Types of Inventory: Raw Material Purchased Parts Supplies Work-In-Process Finished Goods Break-even analysis: The break-even point for any product is the volume beyond which profit is realized and below which the product is not profitable. There should be sufficient volume to cover the fixed cost for the product. Assume: Variable cost = V per unit Price = P per unit Variable contribution = P – V Total fixed cost = F No. of Units required to cover fixed cost is called the break-even point. Vb = F / ( P – V ) Example 1: Price P = $1.2 per unit, Variable cost V = $0.5 per unit, Total fixed cost F = $100,000, then the break-even volume Vb is given by: Vb = 100,000 / (1.2 - .5) = 142,857 EMIS 8364, Engineering Management 2 Example 2: Price P = $250 per unit, Variable cost V1 = $150 per unit, Total fixed cost F1 = $100,000, then: Vb1 = 100,000 / (250-150) = 1000 Automation or upgrade involves increasing the investment in production equipment (fixed cost) in order to make production more efficient, i.e., reducing the variable cost. For example, if an additional investment of $80,000 (i.e., the total fixed cost is increased to F2 = $180,000) results in decreasing the variable cost by $50 per unit ( i.e., the variable cost per unit V2 is decreased to $100 per unit), then the break-even volume is given by: Vb2 = 180,000/(250-100) And Vb2 = 1200 (Increase) Generally speaking, an increase in fixed cost will result in a higher break-even volume and therefore additional investment is only justified based on the actual production volume. The additional investment will not generate a higher profit at the new break-even volume. In fact, a higher profit will be generated only at a volume above the point of no difference. The point of no difference is defined as the point where the two costs, (i.e., total cost with additional investment and total cost without additional investment) are equal. Mathematically , the point of no difference volume Vnd is given by: Vnd = (Increase in the fixed cost) / (Decrease in variable cost per unit) In the above example, Vnd = 80,000/50 = 1,600 units and the additional investment of $80,000 will generate a higher profit if the actual production volume is above 1,600 units. Experience (Learning) Curve: The experience curve describes how the time required (cost) vary with volume. Manufacturing tasks are learned by operators, so they take less time to complete. It is observed that in many repetitious human activities, the time required to produce a unit of output is reduced by a constant factor when the number of units produced is doubled. With a 90% learning curve, for example, if the first unit takes 1000 hours to produce, the second will take 900 hours, the fourth 810, the eighth 729, and so on. Mathematically speaking, if it takes Y1 time to make the first unit, Y2 time to make the second unit, Y3 time to make the third unit and … Yn to produce the nth unit, then we have: Y2 / Y1 = k EMIS 8364, Engineering Management 3 Y4 / Y2 = k Y8 / Y16 = k Y2n / Yn = k And, Yn = Y1 . n –b Or, ln Yn = ln Y1 – b ln n ( b = - ln k / ln 2 and a straight line on a ln – ln graph paper) For the 90% curve, b = 0.152 (Y2 / Y1 = k = 0.9 = 2-b ) What will be the value of b for a 80% learning curve? Production Planning Steps: Process Planning (Routing) Loading Scheduling Dispatching Production Control There is no such thing as a perfect plan Manual Process Planning: A skilled individual examines a part drawing to develop the necessary instructions for the process plan. Requires knowledge of the manufacturing capabilities of the factory: machine and process capabilities, tooling, materials, standard practices, and associated costs. Little of this information may be documented. Often this information exists only in the minds of the process planners. Widely used, time consuming, plans developed over a period of time may not be consistent nor objective. Manual process planners must have sufficient knowledge and experience. It may take a relatively long time and is usually costly to develop the skill of a successful planner. The Computer-Aided Process Planning Method: EMIS 8364, Engineering Management 4 Computer-Aided - key factor in CAD/CAM Computer Integrated Manufacturing (CIM) cannot occur until process planning is automated, consequently, automated process planning is the link between CAD and CAM. The process planning function converts the design into instructions used to make the specific part. Group technology is an important element in CAD/CAM integration, because it provides a basis and a methodology for engineering and manufacturing communications. Computers in Process Planning: Systematically produce accurate and consistent process plans. Reduce the cost and lead time of process planning. Reduce skill requirements of process planners. Increase productivity of process planners. The application programs such as cost and manufacturing lead time estimation can easily be interfaced. Routing can be consistently optimized. Reproduction lead time can be reduced. Responsiveness to engineering changes can be increased. The Variant CAPP Method: A process plan for a new part is created by recalling, identifying, and retrieving an existing plan for a similar part and making necessary modifications for the new part. Provide an interactive environment between the planner and the computer. This type of system is geared to planners with limited computer knowledge. The process planning task for a new part starts with coding and classifying the part into a part family using group technology. Requires a data base containing standard process plans which consists of all instructions (such as operations, tools, and notes) for any part in that family. Requires editing programs. Variant Process Planning Approach: Define the coding scheme - adopt existing or develop a new coding scheme to label parts for classification. Group the parts into families. Develop a standard process plan - Develop a plan for each part family based on the common features of the part types. This process plan can be used for every part type within the family with suitable modifications. EMIS 8364, Engineering Management 5 Retrieve and modify the standard plan - assign new parts to a part family based on the coding and classification scheme and retrieve and modify the standard plan to accommodate the unique features of the new part. Variant Process Planning Advantages: Efficient processing and evaluation of complicated activities and decisions. Standardized procedures Lower development and hardware costs and shorter development times. Variant Process Planning Disadvantages: Inconsistency in editing. Adequately accommodating various combinations of material, geometry, size, precision, quality, alternative processing sequences and machine loading among many other factors is difficult. Process plan quality depends on the knowledge and experience of the process planners. The Generative CAPP Method: Process plans are automatically generated by means of decision logic, formulas, technology algorithms, and textual and geometry based data. Process knowledge in the form of decision logic and data - the automatic matching of parts geometry requirements with the manufacturing capabilities using process knowledge in the form of decision logic and data. Geometry - Based Coding Scheme - define all geometric features for all process related surfaces together with feature dimensions, locations, and tolerances and the surface finish desired on the features. Manufacturing Planning and Control System (MPCS): Primary objective of an MPCS: Ensure that the desired products are manufactured at the right time, in the right quantities, meeting quality specifications, at minimum cost. Translating end-item demand into feasible manufacturing plans, establishing detailed planning of material flows and capacity to support the overall manufacturing plans, and finally helping to execute these plans by such actions as detailed cell scheduling and purchasing. Major Elements of a MPCS: EMIS 8364, Engineering Management 6 Demand management Aggregate production planning Master production schedule Rough-cut capacity planning Material requirements/Manufacturing or Enterprise resources planning Capacity planning Order release Shop-floor scheduling and control Demand Management: Demand forecasting Order transactions entry Customer contact - related activities Physical distribution management Forecasting Approaches: Qualitative approaches: Rely on the opinions of experts to predict certain events of interest Techniques for making prediction for technological forecasting and long-range planning (5-20 years) Explanatory approaches: Include econometric models and casual relationships Descriptive approaches: Includes statistical models Assumption - the demand history in the form of time series can be analyzed for the constant component, trends, seasonalities, and then extrapolate into future. Aggregate production planning: Objective - reconcile the difference between the forecast demand of products and manufacturing constraints, such as capacity and availability of material and labor over the planning horizon. ( Level the production schedule so that the workforce can be stabilized and production costs are minimized.) Appropriate for firms with a large variety of products, time-varying demand, a long planning horizon, and fixed available resources. Demand and production EMIS 8364, Engineering Management 7 requirements are represented in common, manageable aggregate units such as plant hours or direct labor hours (not individual products). Typically an aggregate plan is composed of 12 one-month intervals. Each interval denotes a planned level of production, required workforce, and anticipated inventory levels. Master Production Schedule: Specifies the quantity of each product to be produced in each period during the planning horizon. Dis-aggregation of the aggregate plan to designate required quantities of specific finished goods by time period. Not an executable manufacturing plan - capacities and inventories have not been considered. Rough-cut capacity planning: Objective - ensure that master production schedule is feasible and identify capacity restrictions. Available resources are compared with the resource requirements profile obtained from all the work centers considering all the product families. Material Requirements Planning (MRP): Objective - determine how many of each item in the bill of materials must be manufactured or purchased and when ( detailed production plans). Information system consisting of logical procedures for managing inventories of component assemblies, subassemblies, parts, and raw materials in the manufacturing environment. Bills of materials for each product to be produced are examined to ascertain what detailed parts are needed. Next, the requirements for each of detailed part are determined. Then these requirements are reduced by the inventories on hand and parts on order. The result represents the amount of each detailed part that must be produced in each planning interval in order to satisfy the master production schedule. MRP - Key Concepts: MRP requires the following data: Master production plan Independent versus dependent Demand Replenishment rules by item EMIS 8364, Engineering Management 8 Order quantity Gross requirements Scrap allowance Common-use items Safety stock Scheduled receipts Bill of Materials On-hand inventories Parts explosion Net requirements Purchased or manufactured order status by item Planned order releases Lead time Replenishment Rules: Fixed order quantity Economic order quantity (EOQ) Lot for lot Fixed-period order quantity Manufacturing Resource Planning (MRP II): It incorporates machine capacity, personnel planning and total integrated manufacturing control systems. Enterprise Resource Planning (ERP): ERP is concerned with making sure that a firm’s manufacturing decisions are not made without taking into account their impact on the supply chain, both upstream and downstream and all other major areas in the business, including engineering, accounting, and marketing. Most of the ERP systems include a DRP, MRP or MRP II module, or a capacity planning link. ERP Software package options: A basic information systems infrastructure, or “open computing environment,” with third party companies writing programs that work within the system and its standards. Bundle together programs that support different business functions into separate “module”; then buyers decide which modules to include in their package. EMIS 8364, Engineering Management 9 Capacity planning: Determining available resources such as labor and equipment in order to develop an executable manufacturing plan. The process of evaluating the capacity requirements of a tentative manufacturing plan begins with the due dates of each order. Using lead times, bills of materials, and routines, each order is back-scheduled from the due date through the required operations to determine when a particular work center will be utilized. Overload conditions may be revealed. Since the capacity and order release are constantly changing, some types of adjustment to the manufacturing plan are occurring daily. Resolving Overload Conditions: Changes in the master production schedule Overtime/multiple shifts/subcontracting options Developing alternative process plans for effective resource utilization Splitting lots Increasing or decreasing employment levels to respond to capacity changes Maintain uniform production rate and absorb demand fluctuations by accumulating inventories. Increasing capacity by adding capital equipment. Explore the possibility of planned backlogs if customers are willing to accept delays in filling their orders. Or combination of these strategies Order Release: A directive to work, released to the shop floor, which involves: Scheduling of job orders on the work centers Sequencing of jobs on the work centers Allocation of jigs and fixtures Loading of work centers considering optimal loading conditions Coordination of material handling, storage, warehousing, and machine tools Material inventories allocated to the order Documentation to provide information required for completing the job and monitoring the status. Shop Floor Control: EMIS 8364, Engineering Management 10 Major functions of a shop-floor control system - schedule job orders on the work centers, to sequence the jobs in order on a work center, and to provide accurate and timely order status information. Work order status information is used: To determine the progress of manufacturing activities To determine priorities for scheduling jobs in the shop in response to changes in job order status. To maintain and control work in progress To provide output data for capacity control purposes Order Status Information: Data collected from the shop floor is utilized in several ways, such as to develop new schedules, to provide order status visibility, and to generate measures of performance. The following order status information is representative of what a good shop-floor control system might provide: Current location of parts, tools, operators, etc. Estimated completion date Remaining operations Times for all remaining operations Starting batch size and current batch size Job efficiency to date Through-put Time: Work-order manufacturing through-put time is composed of the following elements: Run time (Operation or machine run time multiplied by batch size) Setup time Move time Queue time Shop Floor Control - Operations Scheduling Machine loading - Allocation of work orders to the work centers such that due dates are satisfied Job sequencing - Determining the sequence of each work order through each work center. EMIS 8364, Engineering Management 11 Typical scheduling objectives: Meeting due dates Minimizing manufacturing throughput time Minimize work-in-process Maximize work center utilization Job Sequencing and Priority Rules: First-come, First-served (FCFS) Shortest processing time (SPT) rule gives the highest priority to the job with the shortest processing time. Earliest due date (EDD) rule gives the highest priority to jobs with the earliest due date Least slack (LS) rule assigns the highest priority to the job with least slack. Least slack per operation (LSPO) rule assigns priority based on the smallest value obtained by dividing the slack by the number of operations remaining. Critical ratio (CR) rule assigns priority based on a ratio of the time remaining until due date to the lead time remaining. Finite Capacity Scheduling: A finite capacity scheduler is a software tool that takes a list of manufacturing requirements and system constraints (in the form of machine hours, or labor hours, for example), and produces a feasible schedule. The schedulers typically use deterministic methods or algorithms to find a solution schedule, which may not necessarily be the “best”, but is a great improvement over manual scheduling. An approach growing in popularity is to use a scheduler to determine a good schedule, then use a simulation model to simulate the proposed schedule and see how well the system really performs. Distribution Resource Planning (DRP): DRP - Management of inventory throughout the supply system Due to the many sources of variation throughout the supply chain, current inventory management practices tend to be reactive Many firms today consistently target the logistics and distribution areas as processes that could provide significant future cost savings. By integrating the output of an MRP II module with a raw materials inventory management tool, one has much better insight into the raw materials warehouse functioning (upstream integration). Push System Manufacturing Characteristics: EMIS 8364, Engineering Management 12 Large lot sizes and long production lead times. The lot being produced may not be correct in relation to the master production schedule of end items because of the dynamic nature of the demand and production processes. Starving - parts are not completed and required at the successive stages, causing shortages. Blocking - too much inventory of some components at a stage, interferes with flow from the preceding stage. A single flow process in which both information and material flow in the same direction from one stage to another. Just-in-Time (JIT) and Pull System Manufacturing: Just-in-Time(JIT) is a method involving very small raw material or in-process inventory quantities, small manufacturing lots, such that a small batch of each component or subassembly is produced and delivered "just in time" to be used in the next production step. This is also called a Pull System. Pull System is Characterized by: Feedback information moves from the subsequent to proceeding stages. MPS is used only to give a broad outline of the requirements for resources. MPS is not used to decide the production rate for each workstation. Kanban is used to trigger production at every stage. A Kanban represents the immediate requirements of the next stage. Kanban: Kanban - a card attached to a standard container that authorizes the production and withdrawal of parts between workstations. Withdrawal (or Conveyance) Kanban - authorization for movement (withdrawal) of parts from one work center to another Production Kanban - release an order to the preceding process to build the number of parts equal to the lot size specified on the card. Rules for Operating a Kanban: Rule 1: No withdrawal of parts without a Kanban - a Kanban controls production on a just-in-time basis, producing necessary parts in the right quantities at the right time. Rule 2: The subsequent process comes to withdraw only what is needed, specified by the Kanban. Waste would occur if the preceding process supplied more parts than are actually needed. EMIS 8364, Engineering Management 13 Rule 3: Do not send the nonconforming parts to the subsequent process. This rule requires that: The process should be designed such that the nonconforming parts are identified at the source and the problem in the process is brought to the immediate attention. More Rules for Operating Kanban: Rule 4: The preceding process should produce only the exact quantity of parts withdrawn by the subsequent process. To ensure minimum inventory, it is necessary to have: 1) No more production than is required by the number of Kanbans, and, 2) Production in every work center in the sequence in which the Kanbans are received. Rule 5: Smoothing of production. Otherwise, peak demand will decide the inventory levels, equipment, and workers. Rule 6: Fine tuning of production using Kanban. Small variations in production requirements are adjusted by: Stopping the process if the production requirements decrease and using overtime and improvements in the processes if the production requirements increase. Alternative JIT Systems: Periodic Pull system - manual information processing of a standard Kanban is replaced by on-line computerized processing. Constant Work-in-process Systems (CONWIP) - Pull based production system used in environments where the standard Kanban system is impractical because of a large number of part types or significant setup times. In contrast to Kanban cards, which are part number specific, CONWIP production cards are assigned to the entire production line. Long Pull System - one unit is allowed to enter the system at the same time one unit is pulled at the end of the pull. No one best Kanban for every situation Other variations can be developed as needed. Just-in-Time Purchasing Activities: Determine the purchase lot size Selecting suppliers Evaluating suppliers Receiving inspection Negotiating and bidding process Determining product specification Paperwork EMIS 8364, Engineering Management 14 Packaging Flexibility: A collection of properties of a manufacturing system that support changes in production activities and capabilities. The ability of the manufacturing system to respond effectively to both internal and external changes by having built-in redundancy of versatile equipment. The ability to economically change from one product to the next. The ability to ramp production volumes up and down to fit the demand of the market. Involves increasing range, increasing mobility, or achieving uniform performance across a specific range. Types of Flexibility: Machine Flexibility - the capability of a machine to perform a variety of operations on a variety of part types and sizes Routing Flexibility - part(s)can be manufactured or assembled along alternative routes on alternative machines, in alternative sequences, or with alternative resources. Process Flexibility (mix flexibility) - ability to absorb changes in the product mix by performing similar operations or producing similar products or parts on multipurpose equipment. Product Flexibility (mix change flexibility) - ability to change over to a new set of products economically and quickly in response to markets or engineering changes. Expansion Flexibility - ability to augment manufacturing system to accommodate a changed requirements. Flexible Manufacturing System: Series of flexible machines, automated material - handling system, automated tool changer, and other equipment such as coordinate measuring machines and part washers Under high-level centralized computer control. FMS Physical Subsystem: Workstations – Numeric Control (NC) machine tools, inspection equipment, washing devices, load and unload areas, and work areas. Workholding and tooling systems - tooling, tool storage and tool changers, tool identification systems, coolant, and chip removal systems. EMIS 8364, Engineering Management 15 Storage-retrieval systems - consisting of pallet stands at each workstation other devices such as carousels used to store parts temporarily between workstations or operations. Material-handling systems - consisting of powered vehicles, towline conveyors, automated guided vehicles (AGVs), and other systems to transfer parts between workstations. FMS Control Subsystem: Control system - required to organize, coordinate, and control various subsystems: Work-order processing and part control system Machine-tool control system including inspection machines Tool management and control system Quality control management system Maintenance control system Management control system Interfacing of subsystems with central computer FMS Detailed Decision Making: Part selection and tool management Fixture and pallet selection Machine grouping and loading, considering part and tool assignments Part selection and tool management: Determination of a subset of part types for processing Considerations include due date and availability of tools. Alternative methods include the batching approach, the flexible approach Tool Allocation: Allocation strategies to insure proper tools are available at the right machines at the desired times for processing of the scheduled parts: Bulk Exchange Policy Tool Migration Policy Resident Tooling Policy Tool Sharing Policy Flexibility Study: Paper Industry: Paper products are comparable across plants. EMIS 8364, Engineering Management 16 Paper products differ in small number of ways, mostly by basis weight, or area density, or the paper and grade, (Each particular pulp and weight combination is a grade.) Differences are straightforward to measure. (Enabled the concrete measures of both the range of products that a given plant could produce and the time it took a plant to switch from making one product to making another product.) Paper Industry Flexibility Study Findings: No clear link between the scale of an operation and its ability to change swiftly between products. Newer, large scale processing resulted in better capability to perform quick changeovers than older, smaller machines. Direct inverse relationship between the scale of an operation and the breath of products it could produce (larger plants made a smaller range of product characteristics). No relationships among the various forms of flexibility. The more experience a workforce had (as measured by length of service), the greater the range of products the plant could make. However, changeover times, (mobility), were worse in plants with more experienced workforces. Paper Industry Computer Integration Findings: Little correlation between the degree of computer integration and the degree of operational flexibility. Computer integration did not decrease the time needed to switch from making one product to making another. While the worst manual-change system took much longer than the slowest computer-integrated system, the best manualchange teams were much faster than the computer integrated system. Computer hardware and software designed specifically for the purpose of improving the changeover process, such as automatic grade-change systems, did not decrease the time required to make grade changes in the plants and actually inhibited the ability of plants to produce a broad range of grades. Pursuing Flexibility: What form of flexibility does the company need from its plants? Determine the type of workforce or equipment they need to enhance flexibility. Find ways to measure the type of flexibility sought and emphasize the importance of those measures to the workforce. Training Case: Kildare: EMIS 8364, Engineering Management 17 Kildare Paper Mill: a complex equipped with medium-size paper machines making relatively high-volume fine papers with 1,500 employees. In the early 1990s, Kildare’s markets were a severe slump, and mills with giant, lower-cost machines dominated the industry. Several competitors had launched reengineering programs aimed at improving their responsiveness to customers. Kildare followed suit and began to reengineer the order-to-delivery process to make the mill even more responsive than the competition. Kidare’s Initial Response: The mill created a training program to teach operators the skills that would enable them to make the swift product changeovers required by the new strategy. The computerized recipes and other procedures used to produce each grade of paper were documented and standardized. The measurement and reward system continued to focus on the plant’s capacity utilization rate, By mid-1993, after an intense, yearlong effort, Kildare had cut its lead times in half and had achieved its target of becoming world class in responsiveness. The mill’s improved responsiveness had enabled it to hold on to existing customers, who were pleased by Kildare’s ability to fill their orders more quickly The mill had not been able to increase its market share or sales significantly. Lean Manufacturing (Toyota Production System): Lean manufacturing also called the Toyota Production System is basically about getting the right things to the right place at right time in the right quantity, while minimizing waste and being flexible and open to change. The lean manufacturing approach is characterized by an emphasis on speed and flexibility rather than volume and cost; employees should be broadly trained rather than specialized; communication should take place informally and horizontally among line workers rather than through prescribed hierarchical paths. Production throughput time is more important than labor or equipment utilization. Inventory, like rejects, is considered waste. Supplier relationships should be long term and cooperative. Activities associated with product development should be done concurrently, not sequentially, and should be carried out by crossfunctional teams. The key principles are as follows: Perfect first time quality – zero defects Waste minimization – capital, people and resources Continuous improvement Pull, just in time production Flexibility without sacrificing efficiency Vendor partnership – Long-term relationship EMIS 8364, Engineering Management 18 Toyota is often credited with pioneering the key elements of the lean production model. In the United States, one of the best documented of Toyota’s plants is the Toyota-General Motors joint venture, the New United Motor Manufacturing, Inc. (NUMMI) plant in California. NUMMI Organization: NUMMI teams are composed of four to five workers. Work cycle approximately sixty seconds. Both team members and team leaders are hourly workers. Teams are responsible for quality assurance, preventive maintenance, and internal job rotation schedules. Teams define work methods and standards. Teams are linked in series, in a traditional assembly line pattern. Job designs are very Tayloristic in their narrow scope and gesture-by-gesture regimentation. Union representatives and managers jointly select team leaders based on objective tests. No pay premium offered for the accumulation of new skills. Lean Supply Chain: The Lean Supply Chain is characterized by long term and cooperative relationships with fewer suppliers. Approaches to reduce the number of suppliers: Tier Suppliers - subcontract entire subsystems Simplify design - eliminate parts and part numbers by using common parts Consolidate purchases Develop long term single source agreements Industry consolidation Human Centered Manufacturing: Human -centered manufacturing is characterized by greatly lengthened work cycles and a return to craft like work forms that give teams substantial latitude in how they perform their tasks and authority over what have traditionally been higher-level management decisions. Volvo’s Uddevalla plant exemplifies the human - centered alternative. Uddevalla Organization: Uddevalla teams are composed of ten workers. Work cycle approximately two hours. Eight production teams, working in parallel, assemble vehicles from the subsystems up. Teams have much broader responsibilities than at NUMMI. EMIS 8364, Engineering Management 19 Teams focus on the aggregate balance of tasks within the whole assembly cycle, not detailed gesture-by-gesture standardization. Teams select their own team leaders, decide job rotation schedules, hires, and overtime schedules. Team members’ pay is increased with the accumulation of proved expertise. NUMMI vs. Uddevalla: Performance: NUMMI took over a closed GM plant in Fremont, CA and hired about 85% of its workforce from the ranks of laid-off GM-Fremont workers. Pilot production began in December 1984, and by 1986, NUMMI was almost as productive as its sister Toyota plant in Takaoka and more productive than any other GM plant. Total hourly and salaried hours per vehicle (1986 average) NUMMI: 20.8 Takaoka: 18.0 GM-Framingham 40.7 Old (1978)GM-Fremont: 43.1 Uddevalla(1991 est.): 40.0 Quality of Worklife: NUMMI: Absenteeism: 3%. Participation in the suggestion program increased to over 90%, workers made over 10,000 suggestions in 1991 (average of about 5/worker), implementation rate for suggestion is over 80%. Proportion of people describing themselves as satisfied or very satisfied with their job: 76% in 1987; 85% in 1989; 90% in 1991. Uddevalla: Absenteeism: 22% (12% sick leave, 10% LTD - typical of other Volvo manufacturing facilities) A survey of worker satisfaction across Volvo plants revealed that Uddevalla scored in a similar range to the Volvo Torslanda (traditional assembly line manufacturing) plant. NUMMI’s Productive Superiority: NUMMI’s effort to constantly improve the details of the production process is the key to productivity and quality in a product as standardized as automobile. This constant EMIS 8364, Engineering Management 20 improvement effort creates a certain level of stress, but as the worker attitude surveys show, the level is not so high as to degenerate into strain and distress. Uddevalla workers had detailed information on their work cycle performance, but with a two hour long cycle, they had no way to track their task performance at a more detailed level. You cannot sustain continual improvement in the production of products as standardized as automobiles without clear and detailed methods and standards. Uddevalla ahead of its time? In response to tight Japanese labor market, the difficulty of attracting workers to auto assembly, and long-term projections of labor shortages, Nissan has eliminated the conveyor belt, has installed significantly more automation, and is using many of the ergonomic job designs that characterized Uddevala. Toyota’s new Tahura plant embodies many similar innovations. (Japanese auto executives were among the most frequent visitors to Uddevalla) Hybrid manufacturing lines: a form of cellular manufacturing, at NEC and Sony currently combine mass production techniques with craft-based manufacturing practices to produce goods in small lots with the flexibility to make changes. EMIS 8364, Engineering Management 21