0001 1 STATE OF RHODE ISLAND SENATE COMMITTEE ON GOVERNMENT OVERSIGHT 2 3 4 5 6 7 8 9 10 . . . . . . . . . . . . . . . . PROCEEDINGS AT HEARING : : IN RE: : CENTER FOR BIOTECHNOLOGY AND : LIFE SCIENCES BUILDING AT : UNIVERSITY OF RHODE ISLAND : . . . . . . . . . . . . . . . . DATE: TIME: PLACE: 11 APRIL 21, 2008 3:30 P.M. SENATE LOUNGE STATE HOUSE PROVIDENCE, RI 12 13 14 15 16 17 18 19 20 21 22 23 24 0002 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 PRESENT: SENATOR LENIHAN, CHAIRMAN SENATOR CICCONE SENATOR SHEEHAN SENATOR SOSNOWSKI MS. GEORGE, COMMITTEE COUNSEL RHODE ISLAND COURT REPORTING 747 NORTH MAIN STREET PROVIDENCE, RI 02904 (401) 437-3366 (COMMENCED AT 4:02 P.M.) SENATOR LENIHAN: If the committee will come to order, please. This is the April 21st meeting of the Senate Committee on Government Oversight. It's a continuation of our hearings into a technique or methodology used for the awarding of construction contracts, looking into the construction manager at risk form of that. And the case study we have before us is Center for Biology, Biotechnology and Life Sciences at URI. Before we get into the meat of the matter this afternoon, I want to make some introductory remarks. When we met two weeks ago prior to the spring break, we had a hearing in which the representatives of the university, I think were at something of a disadvantage, that even though we had indicated that we wanted to 19 20 21 22 23 24 0003 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0004 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0005 talk about the specifics of the contract that was arrived at between the Gilbane Building Corporation and URI, the specifics of what we were asking for was not clearly indicated. And as a result, they couldn't be as responsive as they wanted to be. I will take responsibility for that. I would also say that in the interim as Vice President Weygand from URI had indicated, they would be as cooperative as they possibly could in supplying information and documents to us, and they have done just that. In fact, my legal counsel indicated that her experiences with URI during that period of time has been, quote, "terrific," unquote. So I thank the university for that willingness, and at this point I think we should begin these hearings on a level of what is cooperation, a positive note, and any negativity that was attached to the first meeting should disappear. In effect, we're rebooting the committee process, to start where we would have liked to have started two weeks ago. Speaking of rebooting, I also have to indicate as an introductory remark that we've been having some problems with our PowerPoint presentation. Periodically it's been crashing for reasons that no one, other than the computer fairies, can figure out. And as a result, we may have to adjust as we go through the afternoon, depending on how willing it is to cooperate with us. The way we're going to proceed this afternoon is we're going to go through the changes to the standard AIA contract which was described at the first hearing and the contract which was agreed to between Gilbane and the university. We're going to be operating in a way which says these are the changes that were made, the legal counsel will make a series of introductory remarks about that change so the committee is familiar with what we're doing. A series of questions will be asked by the committee members about those changes and we'd ask, at that point, we'd ask that URI respond. To that end, we have with us this afternoon the vice president, one of the vice presidents at URI, Mr. Robert Weygand, Paul DePace, a professional engineer and the Director of Capital Projects at URI, and Mr. Christopher C. Whitney, who was one of the legal counsels which was employed in arriving at this new contract. If a question is asked of one of you and someone else is better prepared to answer it or wants to build off your answer, please feel free to do so. I would ask the committee members that 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0006 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0007 1 2 3 4 5 6 7 these questions are going to be structured according to the individual terms of the contract. If we can, let's not jump off the contract provision we're discussing at the time. Otherwise, we're going to get lost in a blizzard of legalese which is difficult enough to follow as nonattorneys and I'd like to have us have a solid understanding of what transpired and the reasons for it as we go forward. At this point, I would call upon the committee counsel, please, Ms. Linda George, to give us an introduction to the first part of the presentation. MS. GEORGE: Certainly, Mr. Chairman. As Mr. Chairman indicated, we're continuing with the previous hearing and we will be speaking to the changes in the standard contract versus the contract between URI and Gilbane Building Company. And we will also be looking at the inconsistencies between the scope of the work described in the RFP and the scope of the work negotiated in the contract which established the guaranteed maximum price, the contract between URI and Gilbane. We will start with the scope of the work. The first issue we'll address is bonding. The request for proposal states that a bond is required. The winning proposal submitted by Gilbane Building Company includes a line item for a performance bond in the amount of $286,700. Rhode Island General Laws requires a bond for contracts over $50,000. The law also requires that the bond be between 50 and 100 percent of the value of the contract. However, the CBLS contract, that's the Center for Biology, Biotechnology and Life Sciences contract does not require a bond. That would be the first issue that the committee will address. SENATOR LENIHAN: Linda has spoken to the change that we're referring to here, the deletion of the bond requirement for Gilbane, and I would ask the folks from URI as to why in particular that requirement was deleted? MR. WEYGAND: Thank you, Mr. Chairman. First of all, prior to answering that, I want to thank you and the committee members and legal counsel for allowing us to come back before the committee again to testify. I want to -- I think that all of our records were provided, as you said, to the legal counsel and your staff members, and we'll continue if there are other questions or other documents that are needed or asked for, we'll be happy to comply with anything that you're looking for. 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0008 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0009 1 2 3 4 5 6 7 8 9 10 11 12 13 14 What I'd also like to say is, very briefly, without getting into any details, at the last hearing I submitted to you copies of or a listing of all the colleges and universities in New England and the state of Rhode Island and throughout the country who utilize this methodology of construction delivery. I also wanted to give to the committee, just for their information purposes, a listing of all of the major science buildings and institutional buildings of this nature that use this same form of construction contracting. You will see that it's a very laudable list and the list of clients and contractors are some of the best in the country. So that you all know that this is not a unique form of contracting for the University of Rhode Island alone, but it is utilized throughout the country, throughout New England by all of our peers, Massachusetts, Connecticut, New Hampshire, Maine and Vermont very successfully. With that, Mr. Chairman, let me answer this specific question and I will try to defend as many -- defend any one of these, but also Paul, Chris, as well as Vern Wyman, who is the Assistant Vice President for Business Service is here, and Lou Saccoccio, our inside legal counsel may also be able to provide some information. The amount of bonding that is provided for this project is in multiple different pockets, if I could use that term. It's actually in the form of subcontractor bond as well as the CM fee bond. There is approximately $39.5 million worth of performance bonding that is in this project, not all held by Gilbane. It's held by the subcontractors and the University of Rhode Island is named as the recipient with regard to that. So traditionally under some forms of bonding, you may have one contractor that holds the whole amount of bond. In this case, we have that CM holding the portion that is his bonding for his fee and then all of the subcontractors for their individual bonding, limits of their performance of the work. So if you have an electrical contractor who is doing $5 million of work, we have bonding for that $5 million. HVAC, concrete, painting, whatever it may be, totaling nearly $40 million in bonding for the project. We also have a number of other forms of bonding that in the RFP was identified to all of the respondents, not just Gilbane, but everybody. It is called the OCIP Plan, or the Owner's Controlled Insurance Program, where we have a range of multiple kinds of insurances that 15 16 17 18 19 20 21 22 23 24 0010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0011 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 we hold because it's cheaper for us to hold it. We get a better premium price than many of the contractors and we've been doing this for a number of years successfully to reduce the cost of insurance on projects. The amount of OCIP, and it's in different subcontracts as well, some of it is for workers' compensation, some of it is for general liability. It's in excess of $80 million that we hold in various parts for insurance on this project as well. Chris Whitney, I think, can explain the legal aspect of why we suggested what we're doing. But before we leave that, the $286,700 that was part of the proposal, the RFP, included this bonding. We took that not as a gift back to Gilbane, not at all, this was a credit to our account. We can still buy that insurance, but it would be duplicative of what the other subs presently have and that's available to us, but we took that as a credit to the job, not as an elimination of Gilbane's responsibilities and duties without any benefit to the project. Perhaps Chris Whitney can explain the legal aspects of this. MR. WHITNEY: Actually, before I get to the legal, just a brief comment on the economic considerations that contributed to this decision to which I alluded two weeks ago. Just to recap what I think I testified to two weeks ago, I've negotiated many cost plus construction management at risk contracts over the years, many of which use the form A 121. On every -- I can't recall a single private project that was delivered in that manner that did not involve the owner's decision to waive the bond on the part of the construction manager, and in lieu thereof, to require that the trade contractors be bonded. And it goes, again, I don't want to repeat myself, but I'll try to be brief, but the theory is very simple. A construction manager under this form of delivery will insist for its own protection that its trade contractors be bonded. It will insist on that. And it will expect to pass through the cost of those bonds to the owner. So it begs the question, all right, if the owner bonds the construction manager as well, then there is a double layer of bonding at twice the expense with minimal increased protection to that second layer of bonding because the first layer of bonding should be more than enough. So the question arises in virtually 22 23 24 0012 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0013 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0014 1 2 3 every construction management contract. What was different about this situation was the issue became whether it was legal under the Rhode Island statutes and I know you have a copy of the memo that I produced. I was asked that question. I wasn't sure of the answer to it. You see the memo that I produced and the memo analyzed the statutes and concluded that I thought it was probably legal based on a Rhode Island Supreme Court case that I had cited, the Accent versus Marathon case in which our Supreme Court had made the statement that strictly construed, Section 37-13-14 neither prohibits the waiver of a bond nor provides a remedy if a bond has not been obtained. I did note that case, but not withstanding that, that was the type of language in the case that appeared to admit of a legal option of waiving the bond requirement for the CM in this instance. And the analysis, while it's not in my memo, there were further discussions that I had with Mr. DePace over his perception and understanding of our public procurement laws that would require that the parties actually performing the construction be bonded and that, in this case, is the trade contractors. And then ultimately I understand that the university looked for guidance as well to the Purchasing department, the Department of Administration. So that was a decision that involved a lot of consideration from a lot of the parties involved. I played a role in it and the university did go to me for my thoughts on the legality of it. MR. WEYGAND: Paul, could you also convey to them your conversations with the Department of Administration and why you decided on this? MR. DePACE: Following up on the discussions that we saw an opportunity for crediting the contract and bringing $286,000 back to the construction aspect of the project which is our prime responsibility, at a discussion with Lou DeQuattro of the Department of Administration to ask if this was now possible, and if it were, what steps would we need to go through in order to credit the bonding expense for the CM. And we discussed how all of the subcontractors would be bonded and the Board of Governors for Higher Education and the university would be named on those performance bonds, that Gilbane was themselves doing no direct work, they were not installing any of the work. Therefore, the financial capability of 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0016 1 2 3 4 5 6 7 8 9 10 the Gilbane Building Company then came into question. Mr. DeQuattro asked that we have a knowledgeable person review the financial statements of Gilbane, which they had submitted to us as part of the RFP process. Our controller, Sharon Bell, did do that review. We have a letter in the file saying that, indicating that she said that they were a healthy organization, provided that letter to Lou DeQuattro, we agreed that therefore that the bond could be waived. I have to admit as Counsel George has pointed out to us that there is not one specific, a single specific document in the file that says, that asks "May we?" And then a responding letter that says, "Yes, you may." However, Attorney DeQuattro will confirm that we had this conversation and that he -- the Department of Administration did agree that this could be waived. And it was indeed waived in the course of the placement of the purchase order with Gilbane Building Company on this project. SENATOR LENIHAN: When did that conversation take place? MR. DePACE: It took place prior to the final submission of the GMP and the signature of the contract, which I believe -SENATOR LENIHAN: March 20th. MR. DePACE: -- is dated March 20th or April 20, 2007. March 20, 2007, yes. SENATOR LENIHAN: That's when the document was signed, but when did Mr. DeQuattro give you his feedback? MR. DePACE: It would have been within probably the week before that. SENATOR LENIHAN: So I'm summing up here, the answer to the question is that your read of the law, not the law, the case law, was that the Supreme Court had rendered another decision that in effect the statute was silent on whether or not you had to have it or whether or not you had the authority to waive it. And if so, there was no penalty attached to it anyway; am I missing something here? MR. WHITNEY: No. The statute does say you have to have it. This case seemed to say that it, strictly construed, it doesn't prohibit waiver. So it's in the statute. This case suggests it could be waived. And yes, if it were waived, this case stands for the proposition that a party wouldn't have a private cause of action as a consequence of the waiver. SENATOR LENIHAN: Let me ask Paul, just for the record, because the public watching this has no idea who Mr. DeQuattro is, could you identify him in terms of his position? 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0017 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0018 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 MR. DePACE: I think the proper term is, I believe he's chief legal counsel for the Department of Administration. MR. WEYGAND: He's chief legal counsel for the Department of Administration. SENATOR LENIHAN: And do you know what his duties are with regard to the A, E and C Committee? MR. DePACE: He's the chairman of the Architect Engineer Consultant Selection Committee. MR. WEYGAND: There's two other, which we've testified, Mr. Chairman, there's two other parts of this. One is the legal part of it that you mentioned. The second part is that this would actually be a savings to the project by doing this. This was not a giveaway that they don't have to do it. They gave us a price for doing this, which no matter who was selected, whether it was this firm or another firm, if we went this avenue, they would all give us roughly the same amount for not utilizing this aspect. And the third part is that there is subcontract coverage bonding for all of the construction work that's out there, so it's not as if there is no bonding for the project, it's just not all bonded under Gilbane's roof. SENATOR LENIHAN: That brings me to another question. I was reading an article this afternoon of an arrangement under a CMAR out of state where the owner of the building being constructed had a problem. When it came time to file a suit, instead of filing suit against a single entity, had to file suit against multiple entities, in this particular case it was something like 16 or 17 entities. And I'm not suggesting that that scope would apply here as well, but isn't that something of a disadvantage to the state or to the university, if we had to go looking to multiple suits to take and recover for damages for liability? MR. WHITNEY: I would agree it's a slight disadvantage, Mr. Lenihan, but the reality is what would happen if you can sue the construction manager directly is you sue the CM directly and then the CM, as you probably understand, brings in third party claims against any sub that may arguably be responsible. So you end up in one case with all the same parties, multiple attorneys with unfortunately the expense and complexity of those kinds of cases whether you have to sue directly the subs or whether you can sue directly your CM. SENATOR LENIHAN: Okay. We may 18 19 20 21 22 23 24 0019 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0020 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 revisit that at a future date. We got some indirect feedback from people who had experience in the past with this type of construction methodology that the money for the bond, in this case the $286,000, would have been money exceptionally well spent. But in this case, you presented an alternate approach to it and we'll take that into consideration. You have already told us that your discussions with DOA were with Mr. DeQuattro, was there anybody else at DOA that you had communications with? MR. DePACE: No. SENATOR LENIHAN: Okay. And again, I'm repeating something, but again, just to make sure I understand it, there are no written documents memorializing your conversations with Mr. DeQuattro? MR. DePACE: Not the final decision. There were other e-mails that I provided to counsel saying that the conversation was happening, along with the copy of the letter from our controller. SENATOR LENIHAN: And that's the extent of those communications that were memorialized? MR. DePACE: Yes, sir. SENATOR LENIHAN: Was deleting this bond requirement, I think you've responded to this tangentially, was deleting the bond requirement a material change to the request for proposal? MR. WEYGAND: Within the RFP, all of the CM at risk respondents provided for the bond. It was at our selection or election to decide to pull that out after we got legal advice and looked at could we save money for the project and put it back into the project and that we had adequate bonding by all the subcontractors. In other words, we had $40 million worth of construction performance bonding in place. If we had all of that, this would be a second layer of insurance or bonding. And for that purpose, it was Paul's decision that we should move forward with trying to remove it. SENATOR LENIHAN: In other words, the equivalent -- the cost for the bond requirement was essentially the same in all of the proposals, so deleting it from one -MR. WEYGAND: Would have been deleted from any one -SENATOR LENIHAN: -- comparison between one proposal and the other and the other. MR. WEYGAND: To give you an idea in terms of calculation, generally speaking, the 0021 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0022 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0023 1 2 3 4 5 6 construction manager at risk fee -- I'm sorry, bonding, for all of the work is normally about three quarters of one percent of the entire construction cost. So a $40 million project would be someplace in the neighborhood of around $300,000 for the cost of the project and here it was $286,700. That would have been given to us by any one of the three respondents if we took it back. SENATOR LENIHAN: That three quarters of one percent, would that also apply to those individual subcontractors when they went out for bonding? MR. WEYGAND: Theirs is a little bit more. It's more like 1.1 percent. SENATOR LENIHAN: That brings me actually into another section. In the -MR. WEYGAND: It all depends, of course, on the history of the individual subcontractor, their bonding fluctuates by their performance, et cetera, but generally it's in that neighborhood. SENATOR LENIHAN: The value engineering log, you indicate and it shows in the log itself that the construction manager's bond, quote, "partially offset by Subguard." Could you explain that, please? MR. DePACE: The value engineering log that was in the documents that we transmitted to counsel was an interim step document. The initial costing of this job put the price of the construction work beyond the university's ability to fund it. We had to continue to do value engineering to get the price in a range where we could handle the project. So we continued for an extended period, longer than was originally contemplated, value engineering the scope of work down to something that we could handle. There are a number of items that we chose to accept. One of the proposals, I believe that the document that's referred to there is one of those interim or iterative steps as we were working toward value engineering. Subguard is an insurance product that has some similarities to bonding. It works well for the contractor or the construction manager because it allows the construction manager, I believe, to step in immediately and make corrections to the work and get compensated. Whereas bonding, if a contractor defaults under bonding, and we did have a contractor default under bonding on this project already and it was immediately handled, the bonding company has the responsibility of 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0024 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0025 1 2 3 4 5 6 7 8 9 10 11 12 13 providing a new contractor to do the work. So Subguard was something that was proposed by Gilbane and something that they had used on other projects. We researched it, both ourselves and with Mr. DeQuattro, decided it was not appropriate for this project, that payment performance bond in the traditional sense was what was necessary, so that's what we installed. So the terminology there, Subguard was an interim discussion point rather than a completion. SENATOR LENIHAN: Two questions. Quick one, is Subguard some kind of a trade-marked product out there? MR. DePACE: I believe it is. I believe it's a registered trademark of a particular insurance company's product. SENATOR LENIHAN: You made the decision not to go with that because why? MR. DePACE: It's a fairly new product. We discussed it, as I say, with counsel. We discussed it with Lou DeQuattro. We felt that -- we were discussing it at the same time that we were talking about eliminating or crediting back the cost of the CM's proposal. We decided that we needed the stability and perhaps, and I'll let counsel speak to that if he wishes, it was more in keeping with the state law which said payment performance bonds are required on construction projects over $50,000, so we decided payment performance bond in the traditional sense with the University Board of Governors for High Education named was the most appropriate coverage. SENATOR LENIHAN: It is your position, and I'm just understanding, that if you had chosen to go with Subguard that still would have been in conformance with the statue that required the performance bond? MR. DePACE: Senator, I'm not an attorney and I don't play one on TV. SENATOR LENIHAN: That makes two of us. MR. DePACE: It is my personal opinion that that is correct. Perhaps someone who does play the part of a counselor would be better to answer that. MR. WHITNEY: Thanks for noting that I just play the part, Paul. I'm not certain. I would have some trouble with it and I may even have weighed in with that opinion. I know that I weighed in against Subguard on this project because I researched it. It is really a new product. I only could find two articles that had been published on it. It was a pro and con article published in a 14 15 16 17 18 19 20 21 22 23 24 0026 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0027 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 publication that I'm pretty familiar with, American Bar Association publication on Construction Industry. And the cons just seemed to outweigh the pros, too untested. Unlike a bond, for instance, Subguard can be cancelled for nonpayment of premiums. Not to suggest that we're worried about Gilbane not paying the premium, but the point is once a bond's issued, it's there and it can't just go away, whereas insurance can. And there was the legal issue insurance versus bonding. As you know, there's a lot of similarities between insurance and bonding, but there are a lot of important differences as well. So all in all, even though it was some additional savings, and quite frankly, particularly because we had decided not to require Gilbane to post a bond, I was not comfortable further departing from what perhaps people are accustomed to doing here, we wanted the protection of the subcontractor bonds. SENATOR LENIHAN: My other question to Mr. DePace, the initial maximum price that was offered by Gilbane was on January 21st of 2007. You changed that because it was too high a figure, and as a result, you received an approved second proposal on March 21, 2007, two months later, I'm not hung up on the individual day, but just approximately, and that was the document which formed the basis of your agreement with Gilbane? MR. DePACE: Yes. SENATOR LENIHAN: My question is the value engineering log that I referred to earlier, you said this was an interim document, was there more than one that was produced between January and March? MR. DePACE: To my recollection, there were several iterations of that document as we were -- our approach to value engineering was that the team, and that meant both architects of the Gilbane team and the university team, including what we would consider our user, our customer, which is the department, the College of The Environmental Life Sciences, would sit down in long meetings and identify opportunities for saving. And that could be shelving space, it could be using a different material. It could mean using, for instance, VCT tile, vinyl composition tile rather than ceramic tile for the floors. We had to continually move a number of these things through our heads, price them out either with subcontractors or with estimators to try and work our way through. So this particular 21 22 23 24 0028 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0029 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0030 1 2 document that you have there is one of those steps in there. So I think there were some before, there may have been one after that. MR. WEYGAND: There were a number of exercises, both work sessions as well as documents that brought us down to that final price in March 20th, 21st of 2007. If you do not have them, we will search to make sure you get them. But there is an exhaustive value engineering exercise that we go through with all of the players as well as an outside estimating firm above and beyond that of the architect to be sure that we're getting the best pricing for the work. SENATOR LENIHAN: The major changes that showed up as cost savings that I could see between January and March were first off what we're discussing here, the cost of the bonding, the second was utilities, the third was the demolition of the existing building. Calling those here in our terminology and discussion "major changes," were there -- were those three a constant in the series of interim documents? Was that something you said, "These are our major changes to save us a considerable sum of money to bring us down within our budget," was that basically your thinking from beginning to end until you signed in March? MR. WEYGAND: Not so much in the beginning. We had always hoped that those portions of that work would be included. When the pricing actually came in from the architect and the architect's outside estimator, as well as from Gilbane, we started going through items. But certainly the demolition and the North District Utilities were the largest ticket items, but there were many other items that are in there value engineered that aren't of the same value as aggregates, but in composite they are very large items. We can provide you with that information so you can see every little $2000, $5000, $20,000 item that we went through. You may have simple things like the surfaces of casework in the laboratory spaces, the construction of the ceiling, the walls, et cetera, where we may modify or change the type of material to get it down to a lesser cost and we do that in value engineering. But certainly, Mr. Chairman, not as large as utilities or the demolition of BSC. SENATOR LENIHAN: I asked the question regarding subcontractors. Who specifically or what group specifically approved the bonding of the individual subcontractors? In 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0031 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0032 1 2 3 4 5 6 7 8 9 other words, plumbing or someone is doing electrical work, who determined the amount of the bond necessary for those individual components? MR. DePACE: The bonding for each contractor was in the total amount of the bid, so if a contractor bid $5 million for a particular scope of work, he was bonded to the level of $5 million. SENATOR LENIHAN: Okay. So basically once they got the bid that's -MR. WEYGAND: That's the value of their bond, that's correct. SENATOR LENIHAN: Not that you'd have any reason to do so, but was there any need to discuss the subcontracting bonding with DOA, Department of Administration? MR. DePACE: We saw no reason to do that and we did not. SENATOR LENIHAN: Okay. The cost of the $286,000 bond if it had been left in there would have been an expense to the university, correct? MR. WEYGAND: To the project, yes. SENATOR LENIHAN: What was the total cost to URI for the subcontractor bonding? MR. WEYGAND: I don't know if we have it all calculated, but I think you do. I think there was a document that we provided legal counsel that showed the premium costs. I don't know if that document that Linda has also shows the total dollar amount of it, but it should be total construction value of around $39-and-a-half-million and I'm not sure what the estimated premium costs. MR. DePACE: $415,000. SENATOR LENIHAN: Legal counsel indicates that she had been provided with that document, but until she just produced it for me, we couldn't find it. That's why I was asking about it, so the cost for the subs to bond were $415,210? MR. WEYGAND: Again, if you go back to what I said before earlier about the 1.1 percent times $39-and-a-half-million dollars for the construction costs, you get around 400 and some odd thousand dollars for a bonding premium. That's pretty traditional in the business. It waivers or changes depending upon the contractor though. SENATOR LENIHAN: I understand why Gilbane might want to do so, but if we had chosen to go with the bonding requirement of Gilbane, two hundred and some odd thousand dollars, 286, why is it still necessary to have a bond for the subcontractors from the state's perspective, not 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0033 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0034 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Gilbane's, from the state's perspective? Wouldn't that agreement, that bond with Gilbane cover the state's exposure? MR. WHITNEY: I mean, I think the answer is from the state's perspective, yes, the answer to your question is it would. But the reality is Gilbane, like every other CM at risk, insists on bonding its trade contractors to protect itself against risk. Because its bond -any bond that Gilbane posts doesn't protect Gilbane from subcontractor default. So every CM at risk that I've ever dealt with on a contract like this, always starts and insists successfully that they will bond their subs and the owner will pay. SENATOR LENIHAN: Since it's a pass through expense to the state, is there any reason why Gilbane, and I'm not sure there is, is there any reason why Gilbane would have liked to see the elimination of the $286,000 bond? MR. WHITNEY: Yes. But of minor, minor consequence. Any company has limits on their bonding capacity, even a mighty company like Gilbane. And every bond eats into that bonding capacity and so theoretically depletes the bonding capacity to that extent. Is it likely that Gilbane had any problem posting a bond here and having that diminish its bonding capacity to the extent that it prevented it from bidding other work? Very unlikely. So my instincts would overwhelming suggest that while in a perfect world, Gilbane would prefer not to bond, the fewer bonds the better, that it was not an issue of consequence to Gilbane. MR. WEYGAND: I would also add, Mr. Chairman, that today as we speak, we can ask for the reinstallation of that bond right now and expend another $286,700 and we could do that. Gilbane has that capacity and we could ask for that. Certainly that would be an additional expense to the project which we could absorb at the detriment of some other aspect of the project, but that could go back in. Some might also say, "Well, why did you have both of them in there?" Then I would guess one could perhaps argue you should have one or the other, the $410,000 worth or the $287,000 worth. SENATOR LENIHAN: When you were talking about the comparison of one proposal from one building company, A to B to C, as we're discussing the bonding that would have been imposed upon the construction company, your logic was it was essentially the same amount from 17 18 19 20 21 22 23 24 0035 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0036 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 proposal A, B and C, so a change in one could have automatically been a change in the other, so it still allowed you to make a cost comparison, correct, among the other entities? MR. WEYGAND: That's correct. SENATOR LENIHAN: In the case of the subcontractors, I'm assuming that each of the construction managers were free to select their own subcontractors? MR. WEYGAND: Actually, there's a process that we went through and they had to be approved by the university before they're awarded. They go through a very open and competitive process which is overseen or at least we look at it and make sure it's done in a very positive way. None of the subcontracts are awarded unless Paul reviews them and then approves them, that's the process we presently have. And we make sure that indeed they are qualified to do the work and that it's just not Gilbane's choice, but it's actually a choice that is concurred by the university. Paul, would you like to explain some of the details of that? MR. DePACE: Yes. We observed -Gilbane managed, but we observed the entire procurement process of each one of the trade contractors. That meant that through their website bid program, they invited contractors to bid. The bids were received online. I have each of the bids for each of the trade contractors and broken down in complete detail, including actually a line for the payment performance bond, which is why we're able to produce this spreadsheet for you which shows the individual sheets. Following the bid, the apparent low bidder is brought in for what's called a scope review. That means a meeting with the Gilbane project management, the design team from Payette and myself. We went through the individual work items on there to ensure that the contractor understood everything, that had everything covered. And that was in place and at sometime following that, Gilbane made a written recommendation to us with all of this back-up information, a recommendation to me to award this subcontract, to which I signed off on each individual one. SENATOR LENIHAN: So I understand the process better, let's assume that each of the competing firms when they decided to award the component of the project for electric, that there were easily, you know, half a dozen or a dozen firms out there that are qualified to do the work, 24 0037 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0038 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0039 1 2 3 4 5 who had a performance record that indicated that they were reliable and so forth, that they met whatever criteria you set up. MR. DePACE: Yes. SENATOR LENIHAN: As you looked at them and you looked at what they were pricing out, what their portion of the job was, if you saw that one company offered a price under one of these proposals that was less than the price offered by the firm which you ultimately awarded to, say Gilbane, would you say to Gilbane, "You can take and chop $50,000 off this contract if you used A, B, C Electric instead of C, D, E Electric"? MR. DePACE: I think in each case, I think that the record will clearly show that in each case, the low bidder was selected. We have all of the bid documents. We allowed counsel to look at our records and for each of the some 30 bid packages, we have each bid and you can identify that it was the low qualified bidder. Now, in some cases a bidder withdrew, and I can't remember the scope it was, because they misunderstood the bid and did not have the appropriate scope of work covered. So they withdrew, but at each case, it was the lowest cost. SENATOR LENIHAN: So there is nothing to prevent you, you in fact have utilized that fact that you had information from each of the competing proposals in the firms and you had the authority to not only pick which is the best overall, but also to take and ensure that each of the component parts was the low bidder? MR. DePACE: I think, Senator, you're getting right to the core of why one of the principals of construction management that we believe is good, we -- "we" the owner -- see the sum of the low bids. With the general contractor, some other form -- we don't know exactly what the bids are or the contractor bought them out. He may be selecting another contractor rather than the low bid price for other reasons, perhaps tradition, perhaps relationships. Perhaps he trusts that contractor more than the low bidder, but could have other reasons in mind for selecting the low bidder. We clearly have the sum of all of the low bids for each of the packages. MR. WEYGAND: And we also have, Mr. Chairman, the ability to say no to a particular selection if we don't think that Gilbane is awarding it in the proper fashion with the best price and the best qualified bid. We go about that in a way that is expeditious but also 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0040 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0041 1 2 3 4 5 6 7 8 9 10 11 12 in the best interests of the project. SENATOR LENIHAN: Now, final question, this sort of sums up a lot of what's in this section. At the end of all of this, who in particular, who specifically is responsible for delivering the project on time and at or under cost? MR. WEYGAND: It's the construction manager. SENATOR LENIHAN: And if that project is not delivered on time and at or under cost, there is a provision later on, I believe it's $2,500 a day figure that kicks in? MR. WEYGAND: There's actually, in the RFP, the original in the RFP was only supposed to be $1,000 per day penalty or reward. You have to have both. If you have one, you have to have the other. And we upped that because we wanted more of a provision to $2,500 a day. So we changed it from about a $30,000 per month penalty to a $75,000 penalty if they don't provide the work on time. SENATOR LENIHAN: And if they bring it in a month early? MR. WEYGAND: They benefit as well. There's another provision in there -- Paul has pointed out a couple of what may seem nontraditional to Rhode Island, but it's very traditional throughout the country about how construction management projects work. We have another one and that is where the contractor, the CM, can point out various savings in the project that will still give us the qualitative project that we require but at a lesser price, there's a savings provision within it. So if the contractor identifies he can provide that door, that window, that wall covering, that flooring for just the same quality as you want, but I can get it in a different material that looks like this and you're good with it and we can save $10,000, traditionally what happens is normally the price is split. The savings is split by the owner and the contractor. They get 50 percent, we get 50 percent. The highest level, I think Chris would probably tell you, is normally around a 75 percent to the owner, 25 percent to the contractor. We negotiated an 80/20, 80 percent to the owner, 20 percent to the contractor which is a great savings for us if we realize savings. And they can't hide that savings and keep it for themselves, we would be able to see it. SENATOR LENIHAN: By the way, I'll 13 14 15 16 17 18 19 20 21 22 23 24 0042 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0043 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 do something now so everyone understands, each of you gentlemen was sworn at the previous hearing, you understand you're still under oath? Thank you. Now I want move on to the demolition phase here. Attorney George will first offer an introduction and then Senator Ciccone has some questions to ask. MS. GEORGE: Continuing with the scope of work issues, comparing the RFP to the contract between Gilbane and URI. Demolition of the existing Biological Science Center was identified as part of the scope of work in the RFP. However, the Gilbane proposal also includes demolition of the BSC after the Center for Biotechnology is completed. In the value engineering log, the demolition of the BSC is deleted with a deferment of savings of $883,210 and I say deleted because the building must be deleted, it just wouldn't be deleted under the contract we're discussing. MR. DePACE: Demolished. MS. GEORGE: Demolished under another contract. SENATOR LENIHAN: Senator Ciccone. SENATOR CICCONE: Thank you. Who at URI made the decision to delete the demolition of the building and why? MR. WEYGAND: Let me refer to this, the chairman and senator had just talked about this a little while ago. There's actually two items and I don't know if the next slide is going to talk about the second item, but let me try to handle both of them and anticipate the second one, and that is the Biosciences building,. The present building that exists at URI is an underground concrete structure that we want to demolish for various reasons. It's leaking. There's all kinds of problems that exist with the building and we want to remove it for a lot of very good reasons. We also wanted for, under this project, in the scope of this overall project to construct utilities to this North District of the university campus that are necessary, gas, water, electric and a number of others, steam included. There are two parts of the RFP that one must look at. One is the scope which identifies everything that you wish would be included in the work that they would do. The CBLS building, utilities and the demolition of the BSC building. The second proposal is on page 6 of the proposal or the RFP that also identifies a total construction cost estimated at $42 million. Those two things must be taken into consideration when 20 21 22 23 24 0044 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0045 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0046 1 you consider scope. They tell you as an owner, will tell you to the contractor what we hope we can construct and we're also going to give you the cap in the terms of the dollar amount of which we are going to construct. And the latter one is important because they base their fee, estimating based on the amount of construction, not necessarily all the work. As we start going through the design of the project, unfortunately the project grew in scope and cost because of inflation and other things and exceeded the $42 million. We then value engineered it down and in doing so you eliminate certain things. And so therefore, Senator Ciccone, it was -- the BSC demolition as well as the utilities were pulled out to stay within the $42 million cap that's identified in the RFP because if we didn't, then they would have had a claim against us for additional fees for exceeding the cost of construction and that would have been a justifiable claim against us as well. SENATOR CICCONE: In order to stay within the cap, you said the decision was made; who made that decision to eliminate that aspect of the project? MR. WEYGAND: All of the deletions are agreed to by the university administration; first at the recommendation of Paul DePace and Capital Projects. Also concurrence with our architect Payette, their estimator and all those other people that are involved that are outside of Gilbane, then it's brought through Vern Wyman. And it goes through legal counsel if there's a legal issue and in many cases it's a cost estimating issue, not a legal issue, and then we approve it, meaning myself who is the vice president and then of course the president, et cetera. That is not an uncommon procedure whether it be CM or whether it be a GC. And let me give you an example. We have a project at the university, two projects right now that are general contractor projects, not CM projects, but GC projects. And when it's bid, we really don't know versus with the CM what the bid price is going to be until it's brought in. But we know that it may in fact go over the scope of the work. So we add or deduct alternates to try to get us within the price. And this is just another methodology of doing the same thing. That approval for removing or adding an extra project, an add or delete item, Senator, is also at our discretion in the same fashion I just described. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0047 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0048 1 2 3 4 5 6 7 8 SENATOR CICCONE: Do you have any documents that memorialize the decision to eliminate this from the project? SENATOR LENIHAN: Other than the value engineering log? MR. DePACE: The value engineering log is the item. SENATOR CICCONE: Thank you. Was the decision once you reached it discussed with anyone in the Department of Administration to eliminate this aspect of the project? MR. DePACE: No, Senator, it was not. SENATOR CICCONE: Let me ask it a different way. Did you notify anyone at the Department of Administration that you were going to delete this aspect of the project to keep them aware of you trying to stay within the $42 million cap? MR. WEYGAND: Well, within the GMP which is submitted and is approved, in the contract, is approved at DOA. It, by way of omission, deletes those items on there and only includes those items they're responsible for. So in that sort of way, it does inform them, but not in a proper positive way of notifying, unless Paul, I'm mistaken here. MR. DePACE: No. You've characterized it correctly. SENATOR CICCONE: Looking at the demolition costs, in one estimate it shows that it was $840,000 originally and then as we're looking at the slide here, as you're looking at your value engineering log, it jumped up approximately $43,000 more to $883,000, how did the change take place? MR. DePACE: To tell you frankly, I don't remember. MR. WEYGAND: We'll try to get the two numbers for you and find out the justification between them. I have the sense it was probably timing and inflation, but I don't know and we'll get back to you on that. MR. DePACE: The way some of these numbers are come up with, besides using our professional estimator that came through the architect's office and using Gilbane's extensive estimating department, in some cases the best way to do that is bring in a subcontractor and ask for a courtesy explanation on what it would cost to demolish the building to get a budgetary number, it's not uncommon in the industry to rely on good subcontractors to give you budgetary figures to help you in making decisions. I believe that's kind of what I remember happening in this 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0049 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0050 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 particular case. MR. WEYGAND: Let us get the information for you to try to determine the timeline of when it was 840 and when it was 883. SENATOR CICCONE: Thank you. At the time that the determination was made, I'm going to assume that your answer is going to be it was made towards the latter part, closer to the March date, when you were ready to do the contract, so realistically then anyone else that bid on this didn't have the advantage of knowing that you were going to eliminate the demolition of the building; is that correct? MR. WEYGAND: Well, in the respect that the RFP, which everybody was privy to and knowledgeable of, the total construction cost was to be capped at $42 million. That no matter who it would have been as CM they would have required us to either compensate them more or keep it within the $42 million. We would have gone through this same exercise no matter who was the construction manager. It's a process of getting within the construction funds that you have available to you, the $42 million and value engineering out items that you can't afford to do, whether that has to do with the inflation or whatever the cause is from, but it would have been common to all. No one person was given the advantage of knowing that we would have eliminated or included a demolition or a utility project. They all had, which we had to keep to, the $42 million cap on construction. SENATOR CICCONE: I'm going to ask a Chairman Lenihan question since I'm not sure and I didn't look at all the bids. Assuming that you were going to stay within the $42 million cap, company A, construction managers, submit their response to the RFP, their proposal, staying within the $42 million to include the demolition of the building, company C in your competitive negotiations as you're continuing, is a little bit higher, reduces during your competitive negotiations, well the two items you talked about, the utilities, and in this case, the demolition, and stays within the 42, is there like an advantage or disadvantage that's given to one company or the other? MR. DePACE: The way that our RFP was structured, all the bidders or respondents understood that we were asking them to manage $42 million worth of construction and that the total project cost was budgeted at $55 million, soft costs being the difference. They were also defined a very detailed scope of work as to what they were to provide for 16 17 18 19 20 21 22 23 24 0051 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0052 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 services and they were given a detailed outline of what the university required for core management team on the job. We said we wanted and we did this identifying the weeks that we would want each individual profession on the job. We wanted a project manager for 100 percent of the time, 104 weeks, it was a two-year program. We wanted an office engineer, we wanted quality engineers on the job. We needed a site superintendent and we defined all of that. So while the exact scope of work, none of them saw what the building design was, except schematically, they saw some photographs of some renderings of it. None of them saw -- they were able to see the biological sciences building, but from our point of view they knew it was $42 million worth of management, they knew what the schedule was, they knew what the exact professions that we required on the job; therefore, they had to fill in their rates for those individual professions, extend them and that was their price. So I don't think anyone was disadvantaged -- clearly no one was disadvantaged by not knowing exactly whether the demolition was in or out. SENATOR CICCONE: Well, I understand what you're saying and the original RFP had it in, so everyone bid with it in? MR. DePACE: Yes. SENATOR CICCONE: Obviously what I'm understanding now is that everyone that bid came over $42 million; is that what you're telling me? MR. WEYGAND: No. MR. DePACE: No. Again, all the individuals -- the selection of construction manager at risk for this project was 80 percent qualifications and team, 20 percent on cost. The identification of cost was a pretty defined spreadsheet that said this many people for this amount of time on the job, you fill in the rates as to how much you're going to pay those people, extend them, multiply them through, some to a bottom number, and that's your price. So they knew not specifically -- it made no difference to them from my point of view whether they knew the scope was in or out. They knew they were managing. Remember, they're bidding management services, not construction services. They're bidding only the management -MR. WEYGAND: Let me try to get to the senator's question. I think I know what he's talking about. Could possibly somebody know that we were not going to demolish the BSC building, 23 24 0053 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0054 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0055 1 2 3 4 not going to construct the North District Utilities before they bid on this? Anybody could guess. Certainly we didn't provide any information because we didn't know at that time that we couldn't afford it. For instance, we could have done this, constructed the North District Utilities, demolish the BSC building and built a CBLS building that had many of these features, but was smaller, cheaper and fell within the $42 million. Could have done the whole thing, but what we decided on again was trying to deliver the program for the College of Environmental Life Sciences with the research and laboratory spaces and all the other elements that are necessary, that building grew in cost and unfortunately pushed out some of these other things. But we could have constructed all three of those elements and cheapened the CBLS building and still done the same job for under $42 million. So while the scope is there, and a lot of times -perhaps you could take a look at someone who wants to build their home. I want four bedrooms, I want two baths and I want a living room, et cetera and I want it to be approximately $500,000 in value. Well, you may be able to give that to me, but it may not be the 4,000 square feet I wanted, it may be 3,000 square feet to fit it in. So we give them both scope, as well as dollar amount. And sometimes the scope changes if the cost of the scope rises and exceeds the dollar amount. It's not uncommon. SENATOR CICCONE: I think I had one more question. When you deleted the demolition project, did you see that as a material change to the RFP? MR. WEYGAND: No, not at all. Certainly it's actually an easier scope review, management of a demolition contract, it's pretty simple. It's much more difficult to oversee and manage the construction of a high technology research laboratory, so no, not at all. SENATOR CICCONE: Let me ask this question, so the demolition project has been put on hold, correct? MR. WEYGAND: At this time, yes. SENATOR CICCONE: At this time. You have another building that's going to be going up where you have to put utilities in also? MR. WEYGAND: We have to proceed with utilities, yes, we do. SENATOR CICCONE: I'm going to assume that when you proceed with the next building, I believe it's your pharmacy building? 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0056 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0057 1 2 3 4 5 6 7 8 9 10 11 MR. WEYGAND: That's correct. SENATOR CICCONE: Included in that cost would be the demolition again and probably the utilities, correct? MR. WEYGAND: That's correct. So somehow we have to pay for it at some point in time. SENATOR CICCONE: Right. MR. WEYGAND: Whether it's under this contract, by extending that contract past $42 million or doing it under another contract, you're right, Senator. And we'll have to pay for that because the cost of construction has gone up, no doubt about it. SENATOR LENIHAN: The response by the various firms to your RFP, did each of those responses break out the demolition costs as a line item? MR. WEYGAND: No. No. Again, as Paul said, this is a management fee that they submitted and the scope of services. They did not put in actual prices for the building, utilities demolition, not at all. It's just that your management fee will cover $42 million worth of construction work which may include the utilities, the demolition and the construction of the building. SENATOR LENIHAN: So at the point where you're just making the decision to go ahead with the contract, you don't really know what your actual demolition costs are going to be? MR. WEYGAND: At the initial part of the construction manager at risk we are hiring them for, there's really two parts to it, one is for the management services which is pre-construction, during the construction document phase of the work. At that point in time, we go through all the design work and estimating with the architect and with the CM on board at that time, providing us with input and suggestions and revisions that he thinks could save us money and get us within the price we have. We do the value engineering and then they submit to us a guaranteed maximum price for the work. That occurred around April 2007. At that point in time, after we have done our due diligence with our outside estimating firm and our architectural firm, we either agree or disagree with the guaranteed maximum price. At that point in time when we do that, Senator, that's when they go forward with the construction, not until then. We also have the option at that point in time to say, "We don't want the project, we disagree with your pricing, 12 13 14 15 16 17 18 19 20 21 22 23 24 0058 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0059 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 we think that we can't work it out with you. We want to go to a general bid." We have that option as well under this contract. We decided not to opt to that direction because all of the advice received from outside estimating firms, outside architecture and engineering companies all said this was a good contract and this was a good price. SENATOR LENIHAN: Senator Ciccone asked for the reasons why there was a differential between the demolition costs of $840,000 to $843 and change. Your response was that there was a cost increase due to inflation and other things. MR. WEYGAND: I surmised that. I need to get that information. SENATOR LENIHAN: I understand that and I guess this may be something you have to get back to us with. I understand the inflation aspect of it, what other things are you referring to here in terms of why the costs increased? MR. WEYGAND: Now it could be that there are some unforeseen circumstances that all of a sudden popped up like removing some additional utilities in or around that building that may have added to the estimate. At this point in time, we really don't have that information in front of us. We should really provide that without trying to surmise or guess what it would actually be. SENATOR LENIHAN: Fair enough. Any further questions from the committee on this aspect of the contract change? Ms. George. MS. GEORGE: I have one question. You've explained that cost is a consideration in postponing the deletion of the biology building, the existing building; was time also a consideration? In other words, did deferring the I'm not sure. demolition of the biological sciences building to another contract at a later date, did that also save time and help keep the CBLS on schedule; was that a consideration? MR. WEYGAND: You always go -I'll be very candid with you. You look at keeping that project on time so you don't have cost overruns as a result of us delaying the project because if it's delayed by our costs, they get additional fees for that delay. We don't want to do that. The other part of it is you always wonder if you delay the demolition is it going to cost you a little bit more because of inflation. So you weigh those things and that's not easy to do but the real reason why we eliminated that scope within this project was we just didn't have the money to do it. If we had the money, that 19 20 21 22 23 24 0060 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0061 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0062 would have been on our list to be done. MS. GEORGE: Okay. Thank you. SENATOR LENIHAN: I'd like to move on to one of the other deletions from the work and that's the North District Utilities, one of the other significant sums in here. And again ask Attorney George to offer some introduction. MS. GEORGE: We've already mentioned that North District Utilities, this was included in the RFP for construction of associated utilities and site improvement, the value engineering log which was part of the GMP, guaranteed maximum price, deletes or defers the North District Utilities with a cost savings of $4.9 million. And I say savings, but it has to be paid for at some point. MR. WEYGAND: That's correct, at some point in time. MS. GEORGE: I'm just using that term. MR. WEYGAND: Correct. This I would say again, counsel, is the same thing, the same argument as the previous one. It exceeded the $42 million that we had available to us within the project. It was one of the items that we had to cut out of it and you're absolutely correct, we have to put it back in at some point in time, but within the bond that we had for the project and the money available to us, we couldn't afford to do it under this project. SENATOR LENIHAN: Other than the explanation you've given us, several points, that you simply didn't have enough money to do it, were there any other reasons why the North District Utilities were deleted from this initial contract? MR. WEYGAND: Not at all. Both of these elements quite frankly are critical to full development of the North District for the university's Health and Life Sciences campus, whether it be for chemistry, pharmacy, CBLS, nursing, all of these buildings need the North District Utilities improvements on the campus and we need to do it. Frankly, it's just a matter that we did not have enough money within the contract to complete this work. SENATOR LENIHAN: This question is redundant in the sense that it's asked repeatedly, who at the university made the decision to delete this particular item? MR. WEYGAND: It's the same as we did before. It initially goes through our review team which consists of the office at Capital Projects and Paul DePace with concurrence and agreement by our architect, Payette Associates and 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0063 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0064 1 2 3 4 5 6 7 their independent estimators as to the value of what this is. It is then brought through Vern Wyman and through administration meetings with me. And then it's approved at that point in time. Anticipating your next question, is there any specific notice to the Department of Administration? It's just like the other one. As a way of giving them the GMP by way of omission or elimination out of there, that's the only notice that we really give them. There may have been conversation, but I don't know if there's any documentation that that occurred. SENATOR LENIHAN: You were quite correct, that was going to be my next series of questions. But also as one little addendum to that first set, other than anything you have already provided us, were there any physical documents referencing this decision to delete the utilities from the CBLS contract? MR. WEYGAND: What I would like to do is, just as Senator Ciccone asked me a similar question on the biosciences demolition, let us research again our documents to be sure that there aren't other value engineering logs, e-mails, minutes or other kinds of notices or information that would shed more light on to it and provide it to counsel. MR. DePACE: If I may add a statement there about your question about the notification to Division of Purchases, the university has had an office of Capital Projects starting in 1988 that has been responsible for numerous construction projects over the course of the years. And you may remember that I mentioned when the committee made the site visit that since the year 2000, fiscal 2000, we have installed $346 million worth of work in place at the university, all campuses. I think that I'd be clear in saying and I think the Department of Administrations would also reiterate this, that they have a certain degree of confidence in our ability to deliver projects and therefore to make decisions that stay in concert with the law, but the ability to deliver, so I think that there was that bit of confidence that when our projects come forward, that they understand that we have given them due diligence in review and discussion. SENATOR LENIHAN: Could you describe for us, the terminology's been put out here several times in responses to the North District Utilities. I know we saw because we made our site visit, we looked at the maps you had out. Could you describe again for the committee and 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0065 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0066 1 2 3 4 5 6 7 8 9 10 11 12 13 14 those who are watching today what exactly this North District is? MR. WEYGAND: Yes. In 2002, the university updated its master plan for the campus specifically with an intention to improve the area from Flag Road south to approximately Alumni Avenue, that's a north to south direction. East to west would be upper College Road all the way down to Heathman Road. That area has a, I could say, an eclectic group of buildings, if I could use that term, such as the old Rodman Hall which used to be an armory and basketball court to Chafee Hall to Woodward Hall to the Coastal Institute of the Cooperative Extension Center to a range of other buildings. None of them really designed with any land use in mind or any relationship of the curriculum and how we deliver it to the location of buildings. Generally you like to juxtapose buildings of similar kinds of curriculum near each other so there is resource sharing and a nexus of activity that goes with it. That was not done. So in 2002, we contracted with an outside firm from the University of Virginia who developed a master plan which showed us how we should really rearrange and develop our buildings in this area. And we've dedicated that North District to curriculums that deal with health and life sciences; nursing, biological sciences, chemistry, pharmacy, and related social sciences as well. They would all be located there. And as some of these new buildings which would come on line, biosciences, biotech building that we're talking about today, pharmacy, chemistry and nursing, those need to be serviced with new utilities because existing utilities are at their maximum. We don't have the capacity of electricity or gas or water. We need to bring lines to those new buildings. So the North District Utilities are to service that area and also be a primer for the new technology park which would be on the north side of Flag Road as well. So it's really to get us going in the direction that we need to for that portion of the campus which is really the heart and the soul of our life sciences, scientific research and hopefully the future research and technology park. SENATOR LENIHAN: Okay. Thank you for setting that background up for us. In terms of the nuts and bolts that go into supplying this district with what it needs, let's direct ourselves to the utilities questions. How do you expect or when did you expect or under what conditions do you expect that the 15 16 17 18 19 20 21 22 23 24 0067 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0068 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 North District Utilities will be installed? When it is going to be done, when it is going to be paid for, what is the source of money to do that? Because as you've acknowledged in your previous testimony, the costs that would have been applied to this first building, the biotech building has been kicked down the road because there wasn't enough money to do it now. Could you give us an idea of what's to come? MR. WEYGAND: We're actually going to have to fund it through revenue bonds that will be paid for the university itself out of its general fund to be able to pay for this. We're not asking for a general obligation bond or RICAP funding because frankly although I would love to have -- the university would love to have the assistance of the General Assembly to pay for this out of RICAP, we don't foresee that, so we've decided that we need to move forward with this with our own initiative and pay for this out of our own university funds through a revenue bond that would normally go through RIPAC. SENATOR LENIHAN: That's the first time I've heard about that. The revenue bonds, what's the source of the revenue to pay those bonds? MR. WEYGAND: Our general fund money comes in primarily from two areas. One is the general revenue from the state of Rhode Island which is anticipated to be at a 25-year low this year at about $65 million and the rest of it comes primarily from tuition from students. This is additional sources that come in, which is more minor from outside sources such as foundation and other kinds of gifts in kind. Our general operating fund is approximately $300 million per year. That does not include such revenues for housing, dining, health care services. Those are all separate. Those are restricted funds for those purposes. This comes out of the general fund that goes to pay for the general operation of the university. SENATOR LENIHAN: How big an impact is it going to be to those items that would normally be paid for out of your general operating revenue? To what extent are they going to have to be reduced or cut back or trimmed to provide the revenue to fund these bonds? MR. WEYGAND: Well, the good news is that the demand at the university in terms of new students coming in and other students that we currently enroll is at an all time high. This year, I think we have approximately 17,000 applications, maybe it's 16,000, someplace in that neighborhood for about 3,100 seats for freshmen. 22 23 24 0069 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0070 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0071 1 2 3 But to answer your question, Senator, is primarily it comes from tutions that are paid for by students because the support by the General Assembly, as you know, has been dwindling. Two years ago the support from the General Assembly was $84 million, next year it will be $65 million and we don't anticipate that changing and that's not because of the good will of the General Assembly, it's just the finances of the state of Rhode Island. It's what's happening. So truly there are certain items that we would love to have that money used for to enhance our educational mission, but we do use moneys for purposes of physical improvements out of our general fund. This is not unusual. We don't like to do this, but it certainly is not unusual for us to do this. We do other capital projects and other revenue bonds out of our general fund money. SENATOR LENIHAN: What kind of a term would you expect in terms of repayment? MR. WEYGAND: Normally it's a 20-year note. SENATOR LENIHAN: So a 20-year note for an $800,000 bond? MR. WEYGAND: That's for demolition. I thought you were talking about utilities. We do a whole range of utilities. We would do approximately $9 million worth of utilities to really complete the entire North District Utility project, so it would be around a $10 million bond that we would be asking for. And the cost on that is generally around $800,000 per year depending upon interest rates, and they're fluctuating. But I would say, Vern, am I incorrect on that, about $800,000 per year? MR. WYMAN: A little over $1 million a year. MR. WEYGAND: It's approximately that cost per year that we would be paying for those over 20 years. That's traditional with a 20-year note. We have been very grateful and very pleasantly, not surprised, but happy that we've had tremendous support from the General Assembly. This building, the CBLS building, is a $50 million general obligation bond that is paid for by the state of Rhode Island. The pharmacy building is a $65 million bond that's paid for by the state of Rhode Island. And we have other projects that are like that. The General Assembly has also been extremely generous in helping us in capital projects like Independence Hall, Lippitt Hall, and a number of others where you've given us straight money out of the appropriation of RICAP. 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0072 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0073 1 2 3 4 5 6 7 8 9 10 We don't foresee that happening this year because of the way the state is strapped right now. If we had our druthers, we would rather have this come out of RICAP. We can't wait to get it done two or three years down the road, we need to get it done now. SENATOR LENIHAN: And again, by way of explaining something to other people who may not understand, a revenue bond is not, at least in theory, is not an obligation that the state incurs if there's a default, the bond holders are on the hook, but point of fact as a practical matter, the state's going to have to step forward to take on the bond, so that while it may not require voter approval, it's still going to be an obligation which at least in theory could fall upon the general fund. MR. WEYGAND: Without a doubt, Senator. The main bond rating for the university and Board of Governors is underpinned by the State of Rhode Island bond rating and being a legislator for a long time, I know that is indeed what happens. It has never happened that any bond has been defaulted on by the University of Rhode Island and we do keep our general fund revenue bond that are very good percentage, a very low percentage. We don't do very many of these at all. We have done some in the past and we will look at them very judiciously before we advance them, but this is important, utilities and demolition, as well as hopefully the new chemistry building and nursing building to really move the University of Rhode Island to the level that it needs to be to serve the people of Rhode Island in terms of nurses, in terms of pharmacists and pharmacist-related practices as well as biology and biotechnology and all areas related to that. These projects will move the university to a level that you can all be very proud of and provide economic impact to the state of Rhode Island. That is really what we should be doing. So these bonds, for whether it be utilities or whether it be for the building themselves, are extremely well spent and try to save every penny and sometimes we may do things that seem outside of the box to try to save the penny and squeeze something here or there or get something a little bit different than what may be tradition or the norm, but we do that because we really believe in our mission of providing a quality higher education for Rhode Islanders and I think we're doing that here. Sorry to get off on the tangent of the building. 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0074 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0075 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 SENATOR LENIHAN: Okay. Tooting your own horn is a good idea from time to time. MR. WEYGAND: Don't get too often to do that. SENATOR LENIHAN: The amount that was included under the RFP for this particular building, what did that represent in terms of the total cost of installing and relocating utilities for the North District, to the North District? MR. WEYGAND: I don't want to get off the cuff and I will get this to you. I will get you our original original. This goes back to 2004 cost estimate of how we tried to figure out what the -- how we constructed the $42 million worth of estimates. And we'll have Paul put that together for you so that it shows you, what, $2 million or $3 million for utilities, was it a half million for the demolition, how much was it for the building? Off the top, we don't have the records in front of us, but we will supply that. That goes back to the November 2004 bond issue and how we originally constructed that at that time. SENATOR LENIHAN: Without then going into the specifics or the figures, you had at that time some idea at least of what you envisioned were going to be the total costs of utilities for the district. MR. WEYGAND: Yes. And we'll provide you with that. I just don't know what that is right now. SENATOR LENIHAN: How did you determine how much of that was going to be included under the contract for the biotech building? MR. WEYGAND: I'm of the assumption that what we did was we took -- what we anticipated at that time was the cost of the utilities, the cost of the demolition, and the cost of the building more than likely based upon a per square foot price that we saw around the New England region and said if we want to have -- if we can spend $50 million on the whole project, how much can we build? And I would provide you with that. I just don't know what that is off the top of my head. SENATOR LENIHAN: The figure that I was supplied was that the guaranteed maximum price that was submitted by Gilbane in January, the one that you couldn't agree to because it was too costly. Item one is the North District Utilities at an amount of approximately $1.9 or $2 million. MR. WEYGAND: I think that would probably only be one aspect of it. There may be electricity and then there's gas, there's steam, 18 19 20 21 22 23 24 0076 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0077 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 there's water and there's other utilities as well. That might have only been one piece of the entire utility. We will be able to break that out for you too, as well. SENATOR LENIHAN: The reason I supplied that amount was that the guaranteed maximum price submitted by Gilbane two months later on March 19, 2007 itemized the North Utilities District costs at zero dollars and it was explained, but the value engineering log deletes the North District Utilities from the GMP showing a savings of 4.9 million. And I'm just trying to understand where the figure -- how did you reconcile the figure of 1.9 in January with the figure of 4.9 in March? MR. WEYGAND: Paul, any -- without guessing, that is. MR. DePACE: We don't want to guess. We want to provide you with the complete information. I don't have the original GMP in front of me, but I think that you could see that the bid packages, item 2-C, North District Utilities in the final GMP was then lined out as not in contract and there were several lines that fed to that, including Flag Road electrical distribution and there is another line in here that I can't find at the moment, the steam distribution, but we did not have them fully designed at that point, nor does my recollection say that we clearly had the concept of the entire fit-out of the North District quadrangle, meaning the services for pharmacy, chemistry and nursing, the future buildings clearly in our head at that time. So that we had some allowances in there that was started off at some educated projections as to what we thought it might be, but they hadn't been designed at that point. So we were speculating back and forth between Gilbane's estimator, our private estimators and our engineers trying to determine what they might be. When we saw they started to get to this scale, we knew that this scale was unachievable in the budget that we had so we had to move them out. We have continued to redesign those and we have firmer figures actually now for the services. SENATOR LENIHAN: When you get a look at your materials, if you could address that change in the estimates, educated projections. MR. WEYGAND: So we'll do is we'll track them so that you can see the scope of what the utilities were at a particular time in the logs and then how it either modified or changed, but we'll get you that information. MR. DePACE: You didn't want to 0078 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0079 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0080 1 2 3 4 5 6 hear the term "Wild ass scientific guess," did you? SENATOR LENIHAN: No, I didn't hear that in a formal meeting of the Senate. MR. DePACE: I can see at least two items that jump right out at me and that's item 16-D which is the Flag Road electrical distribution, $2.7 million and the North District Utilities, which in this context means the steam system, that was $1 million, 972, so just between those, we're at $4 million right there between those two. So that's my recollection as to how, but again -MR. WEYGAND: Let us get the numbers to you so we're really firm. SENATOR LENIHAN: I understand and I appreciate that. That's the kind of thing which is legitimate. Let me just come down to the hub of it then. Well, first off, do you regard this as a material change in your RFP? MR. WEYGAND: Not a material change in the RFP. Obviously it's a reduction in the scope, but it's still within the dollar amount. So again, it's hard to look at, "Well, you told me you were giving me 5 bedrooms and now you're going to give me 4 bedrooms," but it's still within the $42 million of project that we talked about. SENATOR LENIHAN: In your judgment, would it have made a difference to the competing firms to have known that this was going to be deleted from the RFP? MR. WEYGAND: No. Because their fee is really based upon $42 million worth of construction, whether it's one item, five items or two items. SENATOR LENIHAN: Just to sum up, the dollars to come to pay for these utilities is going to have to come from revenue bonds and the revenue stream to pay those revenue bonds have either got to be by appropriation from the state or from student generated tuition fees? MR. WEYGAND: Our proposal is because we don't anticipate the General Assembly to give us money from RICAP, that they will come from the general fund, of which of the $300 million that's in that fund, $65 million comes from the state, the rest of it comes from other sources, which is primarily -- two-thirds of which is student fees. SENATOR LENIHAN: As far as the inability to access the RICAP funds, the gist of your testimony to us is that in the short-term, you don't think you'll be able to get it; in the 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0081 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0082 1 2 3 4 5 6 7 8 9 10 11 12 13 long-term it will be too late to serve the needs of the university because you want to go forward with the project because every day that you're not doing something with the project, it's costing you additional money? MR. WEYGAND: It is. And inflation will have a heavy toll on these utilities as we all know. I would like to leave the door open, if the General Assembly at a year from now or two years from now would like to help us with the cost of this so we can pay down the bond in a much quicker fashion and perhaps even extinguish it through RICAP. That would be a certain and welcome change to us at a later point in time that would help us, but we must move forward on these utilities now to get these buildings in place properly. SENATOR LENIHAN: I wish you good luck with that. It took me three years of negotiating the Senate's position when I was Finance chair to get the House and the Governor's Office, the previous governor, to go along with the early payment of the bonds for consequences of RISDIC. Not an easy process. MR. WEYGAND: Not an easy process but it is very possible to be done and frankly that's the kind of thinking, Senator, I applaud you on that, that we should have because that is a way of us and the state of Rhode Island diminishing some if its debt load. And if we can afford to do it through RICAP, that's the kind of vehicle you could utilize that would not have an impact on other parts of the state budget. SENATOR LENIHAN: If there are no further questions on this I want to move to the next slide. Ms. George. MS. GEORGE: This slide shows what we've been discussing here, the scope of the work as addressed in the RFP had to be narrowed because of the costs. The guaranteed maximum price, we had that as $44.6 million. I understand through conversations with Mr. DePace that's gone up a little bit since the initial contract. If you add to it the bond for the Gilbane and the demolition of the biology building, the existing building, and the North District Utilities, you get a total of approximately $50.7 million which was over the amount of money that you had budgeted for this project. MR. WEYGAND: Right. That's correct. SENATOR LENIHAN: Is there any reason or are there reasons you could use to give the committee some insight here as to why the RFP 14 15 16 17 18 19 20 21 22 23 24 0083 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0084 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 proposal was significantly over the amount that you had in mind when the project was first being put together? MR. WEYGAND: Some of it is actually backed into, the project itself was a total project cost including soft costs which are not shown up here on this particular slide. Soft costs include the cost of bond issuance, architectural and engineering fees and other kinds of soft nonconstruction costs which amount to, in this project, approximately $10 million, Paul; is that about right? MR. DePACE: Yes. MR. WEYGAND: About $10 million. So if you added the soft costs to that number that counsel has put up there, the total project cost under this scenario would be about $60 million. We had a bond issue approved by the voters for $50 million and the College of Environmental Life Sciences has raised approximately $4 million. So we have a total project funding available to us of $54 million versus $60 or $61 million. And clearly, we would love to be able to have more fundraising by the College of Environmental Life Sciences to $60 million, which is where they had originally hoped it would be. They hoped they would be able to fund that extra $10 million, $50 plus another $10 fundraising to $60 million, but unfortunately, that has not occurred. As a result, we have to now downscale the project to where we presently are for a total project cost of around $54 million. SENATOR LENIHAN: So the discrepancy then is the outside fundraising, outside the normal appropriation of dollars to the university and the student generated funds, that that raised a significant amount of money but not the amount of money you needed to make the $60 million dollar one? MR. WEYGAND: That's accurate. That's very accurate. SENATOR LENIHAN: Was inflation a significant factor? MR. WEYGAND: Certainly it is in various items. In some items, inflation was rather standard at five to six percent annual inflation. There were other items that escalated to 15 percent per year. SENATOR LENIHAN: Could you give us an example? MR. WEYGAND: We'll provide you with that. We'll get that through our contracts just so you can see some of the inflationary costs. This will not come from the contractor but 21 22 23 24 0085 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0086 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0087 1 2 primarily from the trades which have tracked this over time. It varies depending upon the item. Steel and concrete were going through the roof at one point in time to the point where we couldn't even properly estimate it, so when you get a good price, you nail it down and you take it because tomorrow it will probably be another five percent higher. There are other items that were pretty traditional and standard. Frankly, right now with the cost of gasoline and diesel, delivery to the job, we have quite a deal because the price of delivery is already locked in as of a year ago and the price of gasoline has gone up by, as you know, 75 cents a gallon. So we're not paying inflationary costs for those kinds of things. But we will get you those numbers to show you what are primarily the big items that really had huge inflationary increases. SENATOR LENIHAN: As you look ahead to future construction, is there any kind of a figure that you're using yourself internally? Say, for inflation, you'd better figure in at least "X." MR. WEYGAND: Yes, we have. We do that now and we did it before, too. But over the last five years, it has been, I hate to say this term, but it's been almost a crap shoot at times. SENATOR LENIHAN: What are you currently using as an assumption? MR. WEYGAND: Five-and-a-half to six percent per year for the entire cost of the project, not just for one item. SENATOR LENIHAN: Right. MR. WEYGAND: Some items may be at three, others may be at ten. I would also surmise, again, I don't like to estimate, but the cost of delivery of materials to the job site now is going to be, we're going to pay a heavy price for that, that premium right now because whether it's bringing in steel, whether it's hauling in concrete or whatever materials we're bringing in, that cost of transportation is going to go through the roof because of the cost of gasoline. SENATOR LENIHAN: Again, if you would give us by way of example that differential of the inflation? MR. WEYGAND: What we'll try to do is break it out by trade, concrete versus electrical versus HVAC versus all the others. SENATOR LENIHAN: That's fine. Thank you. I want to go now to slide seven. SENATOR SHEEHAN: followup question. Just one 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0088 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0089 1 2 3 4 5 6 7 8 9 SENATOR LENIHAN: Certainly. Senator Sheehan. SENATOR SHEEHAN: Did I understand this correctly, Mr. Vice President, that there was approximately some $10 to $11 million not included in the scope of the work; is that what you had stated? So it's somewhere between, the total cost was between $50 and $65 in actuality, including what you had deemed soft costs? MR. WEYGAND: I'm not sure if I understand your question. The total project costs, if we included North District Utilities, demolition of BSC, bond for CMAR, GMP, and the soft cost, the total project if it was all of that that we had hoped for would be about $61 million, total project cost. SENATOR SHEEHAN: So my question to you would be why wouldn't the soft costs be included in the overall price? MR. WEYGAND: We do. We put it in the project, but the GMP is only with regard to the construction. SENATOR SHEEHAN: Just for the construction end of it? MR. WEYGAND: Right. SENATOR SHEEHAN: But not the soft costs which basically would be incurred by the university? MR. WEYGAND: Right. It's part of the project but it's not part of Gilbane's responsibility to take care of. SENATOR SHEEHAN: Thank you. SENATOR LENIHAN: Okay. I'll call upon legal counsel in order to get to slide 7. MS. GEORGE: We're going to shift the focus now from the differences in the scope of work contained in the RFP and the scope of work contained in the contract between Gilbane and URI. And we're going to look at the differences or changes from the standard AIA contract and the language, whether the standard AIA contract versus the contract between Gilbane and URI, whether additions or deletions in the language were made. As was discussed at our last hearing, the standard AIA contract is the starting point from which parties negotiate and they are free to and generally do change those terms by either adding or deleting. So the first one we'll look at is the limitation of liability. In the AIA contract there's no provision concerning this. However in the contract between Gilbane and URI, language is added that provides as follows: "The construction manager's total liability to URI for breach of contract, warranty, 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0090 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0091 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 negligence or otherwise is limited to the construction manager's fee." SENATOR LENIHAN: Which is approximately $3.4 million? MS. GEORGE: Well, I believe it has gone up a little bit since then I believe Mr. DePace had advised me. MR. DePACE: Yes. SENATOR LENIHAN: Okay. The person who will be asking the questions in this category is Senator Sheehan. You may proceed, Senator. SENATOR SHEEHAN: $3.4 approximate million is the standard fee? MR. WEYGAND: That's correct. SENATOR SHEEHAN: The first obvious question, this can go to anyone here you see fit, why did URI agree to this particular provision, especially since URI waived the bond requirement, how does it benefit URI? In other words, when you negotiate a contract, you usually end up with something that may be mutually beneficial; was this something URI was willing to basically take kind of a backseat on and then take a front seat for something else? Why would you waive this particular provision as a deviation from the standard contract, the pro forma contract? MR. WEYGAND: This goes back to actually the very first question that was asked, very similar, but I would like Paul to probably best respond since he negotiated this area. MR. DePACE: Really speaking about the whole area of section 9 in the contract and the university took proactive steps to mitigate its risk on this project. If I might go through this. There are risks during the construction process and there are risks that are covered by insurance. First let me, minimizing this risk, mitigating this risk was an important action, all of our construction management programs, even our lump sum bid programs. First of all, we require the CM in all of our CM work to go through interdisciplinary constructability review. The purpose of this is to identify any discrepancy or confusing items in the architect's plans early on in the process and we direct the architect to clarify those. So therefore, the documents that finally go out to bid to the subcontractors have been cleansed of whatever can be found of discrepancies or confusing ideas that could result in change orders. The university requires that in this particular case, this was something new for us, 17 18 19 20 21 22 23 24 0092 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0093 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 required that the CM bring in a third party to evaluate the building envelope; roof, windows, masonry to ensure the original designer had properly designed them and that the flashing and opportunities for moisture to get in the building had been covered. And this was done, again, before the documents went out to bid. The university requires the CM to hire an independent commissions agent. This agent is to review all of the mechanical systems designed to monitor the construction, while under construction the indoor air quality plan during construction and then overseeing that all of the equipment properly comes on-line. This is done so that we work out all the bugs in the system, the mechanical system. There are two things that can really cause a problem. One, if it rains on people's heads, so you want to make sure that the building envelope has been double-checked so that you don't get into a dispute with the subcontractors or the CM about whether the building is watertight or not. You've gone through that extra level upfront before it goes out to bid. Less trouble for everybody else, prove out your design. The second is where you can get into trouble in a building is whether people are cold when they want to be warm and warm when they want to be cool. So having the commissioning agent also part of our Lead program to review the mechanical design, prove the indoor air quality. And we actually have a construction plan for monitoring indoor air quality during construction as well as turning the equipment, putting the equipment in place at the end in operation is again a way of mitigating risk to the university, to the project. You've heard that from a risk point of view that the university -- well, actually we haven't talked much about the owner's controlled insurance program, but the university has a proven program where it brings the workers' compensation, the general liability, excess liability insurance coverage to the project, buying it as you might say on a grander scale on any individual contractor could buy; therefore buying it at a better cost and we manage the safety with the construction manager of the program. And we have documents that we would certainly be able to provide to the committee that show how our owner's controlled insurance program has saved the university, back into the projects of about $5 million over the past 6 years. We'd be happy to provide that to you. 24 0094 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0095 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0096 1 2 3 4 5 But in this coverage the university provides $41 million worth of builder's risk coverage, $54 million worth of general liability, excess liability and additional excess liability on the project. Again, we're able to buy it less expensive and without the contractor's overhead involved and bring that to the project, again, mitigating the risk to the project. And we cover Workers' Comp. We have $1 million per occurrence Workers' Comp. coverage. Again, we're able to provide it to the contractors on the job through this coverage through our carrier and our broker, we bring additional safety inspectors to the job on a weekly basis to inspect the job and ensure that we are actually running a safe job. We and the university reap the benefit of less loss. By loss control, we manage loss control, again, the money comes back to the university and is in that $5 million that I'm talking about. Also, the CM does not perform any construction work on the job. We specifically say they are management services, all the work is covered by, and the subcontractors are responsible for, covered by bonds, all of the work in place. MR. WEYGAND: Those bonds amount to $39 million additionally from what we're talking about. They really are the performance coverage for the project. SENATOR SHEEHAN: Mr. Vice President, is that then covered, is that cost covered in the overall expense of the project, insuring the subs? MR. WEYGAND: Yes. It's part of the subs cost when they submit their bid. SENATOR SHEEHAN: Do you know how much that costs, what is the cost to the project itself for the subcontract performance bond? MR. WEYGAND: We mentioned it earlier. I think it was $410,000 or thereabouts for all of the premiums for all of the subcontractors. SENATOR SHEEHAN: Versus what would have been $280,000? MR. WEYGAND: $286,000. SENATOR SHEEHAN: For the CM? MR. WEYGAND: And the reason for that, I think Chris will be able to tell you that, but let me just capsulate. Your question, Senator, was on risk. And are we exposed to risk if there is a nonperformance by Gilbane? SENATOR SHEEHAN: Actually, I haven't asked that question. You're ahead of me, but I certainly will get to that question. But 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0097 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0098 1 2 3 4 5 6 7 8 9 10 11 12 what I just wanted to know specifically was, so in sum, what is the benefit to the University of Rhode Island, is it saving money; is that what the impetus was behind this standard deviation or this deviation from the AIA contract pro forma? MR. WEYGAND: In many cases, the A 121 allows for very specific clauses to be included in the contract. You will look at the final contract, in large share, almost every single one of those was completed. There is a report called our standard additions or deletions form from the A-21 and those happen sometimes where there is clear negotiating going on between the owner and the contractor, or that there is no provision or specific provision within the AIA 121 for that particular area and we add some language in there. But what you're talking about is clearly a negotiated portion of this that we, that Paul when he negotiates it looks at the best interests of the university, can we save money, are we exposed to any risk, what are the benefits of doing this, what are the downsides to doing this? SENATOR SHEEHAN: After doing a cost benefit analysis of waiving the particular bond that we have with Gilbane as CM, it was determined, at least by your analysis, that this would save the overall project, hence the university, some money? MR. WEYGAND: Small amount, $286,000. Also we wanted to be sure with legal counsel that we could do this and Chris earlier explained -SENATOR SHEEHAN: So weighing all the potential costs, the benefit really certainly is the $286,000 that would not have to be paid in this bonding issue? MR. DePACE: That's again simply the bonding issue. The other items that I've mentioned about the owner's controlled insurance program, that's the insurances end of it. SENATOR SHEEHAN: On the employees? MR. DePACE: Yes. Workers' Comp. for the trade contractors, the general liability for the project. SENATOR SHEEHAN: So you have that covered? MR. WEYGAND: We decided some years ago to go to the owner's controlled insurance programs. Some people like it, some people don't. It's very much like a self-insurance program. We monitor it, we go into the job site, we have our outside firms look at them, be sure it's a good safe site. 13 14 15 16 17 18 19 20 21 22 23 24 0099 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0100 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 And we, as Paul had said, realized over a number of projects within the last five years approximately $5 million worth of sayings that we've brought back to the university and the projects. It would be simply very easy to say, "Forget about trying to do that and just go the traditional way and lose the $5 million." We went out of the way and some people like this, some people really dislike it and say you're losing money. You're losing money. The fact is that we've seen a realization of $5 million worth of savings and we'll put that up against other people and most other companies try to self-ensure and look at self-insurance as a way of reducing your cost of insurance. SENATOR SHEEHAN: So given the cost benefit analysis, you thought this would benefit the overall project in terms of saving some money, at least namely the $286,000. Who was party to that decision at the University of Rhode Island? MR. WEYGAND: It's the same process we go through. Initially it looks at -it's by Paul's recommendation, his negotiation, going through Vern Wyman. And if there's any question on it, like in this case, there was a legal question on it and the legal counsel was brought in on that and reviewed that. SENATOR SHEEHAN: In addition to any documentation you may have already provided the committee or counsel, is there anything else that would show us the reasoning, is that set to paper or is that oral? MR. WEYGAND: I don't know if there's one document, Jim, that would actually say, "This is all the reasons why we decided to do this." It's probably dispersed among e-mails, correspondence and other things. If you want, we will try to encapsulate it in one series of documents so that you can see it, but I don't think there is one specific document that says this is why we did it. SENATOR SHEEHAN: I appreciate that offer. I'll talk to the chairman and counsel to see if that would be necessary. Was this ever discussed, this waiver of liability here of the bond with DOA? MR. WEYGAND: Yes. With specifically Lou DeQuattro. MR. DePACE: Of the bond. SENATOR SHEEHAN: The bond. That was with DeQuattro? MR. DePACE: I don't think we should confuse what he's asking here and the bond. MR. WEYGAND: There's 20 21 22 23 24 0101 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0102 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0103 1 differences -SENATOR SHEEHAN: The limited liability of not having the bond on the CM is what I'm talking about. It was discussed with DeQuattro over at the DOA? MR. DePACE: The bond, yes. SENATOR SHEEHAN: Was anything else discussed with him that relates directly to this issue? I don't know, maybe you were confused, maybe there's a couple of issues there. MR. DePACE: I started to enumerate some of the areas where the university mitigated risk on the job that made us feel comfortable with this limited. MR. WEYGAND: But with regard to Lou DeQuattro, are you asking specifically with regard to DOA? SENATOR SHEEHAN: DOA specifically, yes. MR. DePACE: I'm sorry, could you ask that question again? I'm sorry, I misunderstood. SENATOR SHEEHAN: Was this limit of liability discussed with anyone at DOA and I believe it was to the affirmative relative to the bond being waived, that was with counsel of DOA; was there anybody else involved in that decision-making process? MR. DePACE: I don't recall ever discussing this in particular; bonding for sure. SENATOR SHEEHAN: Not the contractual language, but the actual waiving of the bond was discussed with DeQuattro in-house? MR. DePACE: Yes. SENATOR SHEEHAN: Is there any documentation that you haven't provided us yet to date that would relate to that, specifically that transaction or communication? MR. DePACE: No. SENATOR SHEEHAN: So that was more of a verbal or oral discussion? MR. DePACE: Yes. Again, there's correspondence that goes around it, but there is no specific, "Do you approve?" "Yes, I concur." There's no one document that says that. MR. WEYGAND: We did confirm though with Mr. DeQuattro that he indeed would testify to the fact that that occurred. SENATOR SHEEHAN: Did you require his approval for that or was that just kind of apprising him of what was going to be transacted? MR. WEYGAND: We talked to him. We thought it was important for DOA to sign off on this. 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0104 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0105 1 2 3 4 5 6 7 8 SENATOR SHEEHAN: Are they required, Bob, or is that just information? MR. WEYGAND: That I don't know. I don't want to say one way or the other. We don't really know that the regulation provides for a mandatory letter and approval from DOA. I just don't know that. SENATOR SHEEHAN: Next question, Mr. Chairman, what is Gilbane at risk for? It says this limits some exposure here to various risks, could you give me a general statement, maybe a for instance, as to what Gilbane would be on the hook for if they didn't perform as they should have as the CM. MR. DePACE: Well, certainly the limit of their fee at $3.4 million is no small number. But they are responsible for the delivery of the project, the overall delivery of the project. SENATOR SHEEHAN: On time? MR. DePACE: On time. SENATOR SHEEHAN: Within budget? MR. DePACE: Within budget. And through that, the payment of the subs because the payment of the subs goes through that. We have taken steps to ensure to mitigate the risk to the university to ensure that the subs are paid by our process. I can go through that in detail if you like. SENATOR SHEEHAN: Could they be held in part for anything such as breach of contract or warranty or negligence or would a dollar amount be ascribed to any one of those occurrences and that could be basically applied against their fee which is $3.4 million? MR. WHITNEY: Gilbane could be held liable on any of those theories. SENATOR SHEEHAN: But the cap would be $3.4 million in terms of what they would pay out? MR. WHITNEY: That's correct. And keeping in mind that cap in terms of the magnitude, Senator, that's just not their anticipated overhead and profit. That's really Gilbane's general conditions cost, its management cost to run this project. So it's at risk really for virtually every dime it's going to bill on this project on its own account over the life of the project. It could lose it all if it is were to breach the contract or otherwise incur liability. SENATOR SHEEHAN: So Gilbane is in essence, or in fact rather, responsible for delivering of the building on time and at cost; is that factual? 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0106 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0107 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 MR. WEYGAND: Yes. MR. DePACE: Yes. SENATOR SHEEHAN: So then the only penalty here and the only one you can go after if the building was not on time or was well over cost, big cost overruns, would be Gilbane but limited to the amount of $3.4 million? MR. WHITNEY: No, that's not true, just to clarify. The university is what's called a dual obligee on the bonds posted by the subcontractors. And so to the extent that any problems were created by the performance or lack thereof by any of the subs, the university would have claims against those performance bonds of the subcontractors. The reality is that while you can envision on the one hand a scenario where Gilbane's mismanagement might have caused delay or extra cost where they would be liable up to 3.3, 3.4 million, playing the odds, it's much more likely that it would be some kind of defalcation or poor performance by a subcontractor that leads to those damages and the university would have recourse against those trade contractors for those amounts. SENATOR SHEEHAN: Do you have any provision, I don't know if maybe you have insurance or whatnot that would do this, but accounting for legal expenses, if you had to under my wording, chase down a couple of subcontractors for nonperformance as opposed to if Gilbane was on the hook for managing the project overall, might be more simpler to go after that kind of a big dog as opposed to going after the little puppies that may be running off into the corners? MR. WHITNEY: I guess I see your point. I mean, as you're probably aware, there is a contract provision that Gilbane negotiated that does provide that they may be reimbursed for certain legal fees they may incur in pursuing subcontract performance, but critically subject at all times to the guaranteed maximum price, number one, so that any expenses that they might be reimbursed for that in the project's best interests are still subject to the guaranteed maximum price. And secondly, that provision, which is found, if I recall, somewhere in Article 9, is very similar to language that is standard language in the AIA, A 121, very similar language providing for reimbursement of the construction management's certain legal mediation and arbitration costs. That provision term was slightly modified by taking out a phrase having to do with the owner's permission, which may not be 16 17 18 19 20 21 22 23 24 0108 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0109 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 unreasonably withheld and that was, in my opinion, a very minor consequence. So my point is there actually is language addressing it. Some of the language that was added, very similar to the standard language in the document anyways and if that ever occurs, it's Gilbane's entitlement to reimbursement is always subject to the guaranteed maximum price. SENATOR SHEEHAN: So just to recap then, and first with a question. Do you under normal circumstances require and I guess we've debated whether or not case law requires, I guess you would agree that subcontractors on any project require a bond to be bonded? MR. WHITNEY: I haven't analyzed that issue myself and weighed in on it. I know it is Paul's opinion and the university's that that's a proper interpretation of state law and on the surface, being familiar with the state law, certainly resonates with me because they're the contractors doing the work. SENATOR SHEEHAN: And given that same interpretation or similar interpretation by the university, this fee here -- it's really not a fee, scratch that. This bond issue worth -- the state would have had to pay $286,000 that could be waived, that was the interpretation that counsel had. MR. WHITNEY: That's correct. SENATOR SHEEHAN: And that would be a savings of some $286,000, so doing the cost benefit analysis in the grand scheme of things, it's in the university's perhaps decision-making estimation that barring any maybe massive lawsuit, where you had to go after several subs and you might have to incur legal expenses, that maybe that is an expense kind of worth taking in the cost benefit analysis ratio? MR. WHITNEY: Yes. I generally agree with your statement. I'm not sure that it would cost, and I think it goes to a question that the chairman had asked earlier, I'm not sure -- if there became a problem, I'm really not sure you'd spend, the university would spend any less money in attorney's fees if it were only pursuing this construction manager and its bonding company and they in turn impleted everyone or whether the university is suing the subs directly. I'm not sure that that -SENATOR SHEEHAN: $3.4 million is a lot of money, at least for me, I can say that myself, but in terms of doing large construction projects, I can only imagine that that is a relatively smaller amount of money, given the scope of the project at some $50 million, that 23 24 0110 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0111 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0112 1 2 3 4 perhaps if the overarching manager of the project, there probably isn't a lot they could do within the purview of their job description. In other words, that they'd be liable for, that could create through maybe cost overruns or problems with the building, worst case scenario, a wall falls down and maybe they had managed -- maybe they had the wrong timing of what they were putting in, wait for the cement to dry, whatever it maybe, that could cost in excess of $3.4 million. My question would be is it worth paying? And your response was no. Is it worth paying the $286,000 to cover any possible liability that may occur in more of an extreme problematic situation. MR. WHITNEY: Senator, you hit the nail right on the head. There is a direct link between the university's decision to agree to this limitation of liability and the university's decision not to require Gilbane to post a bond, but to require the subcontractors to post bonds. If the university had required Gilbane to post a bond, this provision would have been problematic because if Gilbane had posted $40 million bond, then its bonding would have attempted to use this as a shield to liability, and on a $40 million bond, we're liable up to $3.3 million. But when the decision was made to have the subs bonded, the subs are not protected by this limitation of liability, so the theory really is this limitation, which is substantial, the fee, is to protect against problems created by Gilbane and problems created by the subs are all going to be covered by $39 million worth of performance bond posted by subcontractors. SENATOR SHEEHAN: So it's in your estimation, educated projections, that damage that could be done by the subcontracts could run up to almost the total cost in theory of the project, but yet the manager for the project, what damage they could basically visit upon the project would only be limited to about $3 to $4 million. MR. WHITNEY: First of all, just to be clear. Theoretically, there is not any connection between the amount of a contract and the amount of a bond and the amount of liability, so that $39 million worth of subcontractor bonds, I can't tell you that you couldn't have $100 million worth of liability, that's highly, highly unlikely. The reality of the industry is you typically have claims that are far less than the total penal sums of the bond. So that, so it's 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0113 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0114 1 2 3 4 5 6 7 8 9 10 11 highly, highly likely that there is a tremendous excess of protection here to the university. SENATOR SHEEHAN: I'll just make one more point or actually, I'll phrase it in the from of a question, Mr. Chairman. Of the $3.4 million, is there any coverage under the owner's controlled insurance for death? Let's say, God forbid, that one of Gilbane's workers is in a certain area and slips and falls off and dies. Didn't mop the floor, who knows, whatever it was, but the liability would rest with Gilbane and not anybody else; what would happen then if there were a lawsuit for $5 million for death resulting? MR. WHITNEY: You've hit the other nail on the head because the other key connection here for the decision to agree to this on the part of the university is the fact that the university has this OCIP program. Now, I didn't review the OCIP policy. I have discussed it generally, the owner's controlled insurance program. And the point that you correctly alluded to this is, the OCIP provides tremendous amount of coverage, liability, Workers' Comp., I think it's $4 million in the aggregate. There a $25 million dollar -SENATOR SHEEHAN: So is that for more personnel purposes as opposed to property damage? MR. WHITNEY: Yes. Technically the OCIP, as I understand it, I may be corrected, does not technically include the property coverage, but the university has substantial property coverage as well, the builder's risk policy. So the point is that this limitation here, limitation of liability, would not limit the available insurance coverage in my opinion. So if you had a $15 million loss because of a death, it would be paid for by the OCIP liability carrier and would not be limited by this limitation of liability. So basically the university's calculus was in terms of the breach of contract problems, you've got $39 million worth of bonds, plus $3.4 million approximately. And in terms of liability issues -- and that could include property damage issues, property or liability, they have tremendous coverages under the owner controlled insurances, under the OCIP and the builder's risk. SENATOR SHEEHAN: And hypothetically if Gilbane were to, and this is a very big hypothetical, walk away from this project, you think that would cost in excess of $3.4 million in terms of delays in construction and maybe idling of the entire workforce, so to 12 13 14 15 16 17 18 19 20 21 22 23 24 0115 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0116 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 speak, there at that construction site? MR. WHITNEY: Well, anything is possible, but I would say this, it's highly unlikely. First of all, were Gilbane to walk away or be terminated by the university and under standard contract language, I haven't gone back to review this but I know it's in there, the university has the right to assume, step into Gilbane's shoes in terms of the trade contracts. So the vast majority of the work would be being done by the trade contractors, it should be a relatively seamless transition for the owner to step in and continue -SENATOR SHEEHAN: So URI would manage the project in that case? MR. WHITNEY: Well, they could hire, they'd probably hire a consultant, but your point is well taken, they would probably hire somebody to come in, exactly as the vice president says, assume the management role that Gilbane played and that party might charge a higher fee than Gilbane because it's coming in after the fact, but would $3.4 million be sufficient to cover that? It certainly should be when you think about, for instance, the liquidated damages here, which are substantial at $75,000 a month, that's about $900,000 a year and you've got three plus years of coverage just there. So I think the university really carefully mitigated its risk before it agreed to this. And I understood, by the way, Senator, I understood there was a quid pro quo to this and I can't speak to it because I wasn't involved at the time, but Mr. DePace may be able to and it goes to a question I thought you asked earlier which is why did you do this. And I think I've explained two reasons, the OCIP and the subcontractor bonding, but as I understood it, I understood Gilbane offered some quid pro quo for this as well that was my understanding. Mr. DePace can speak to that better than I could. SENATOR SHEEHAN: Actually, I'm satisfied. MR. WHITNEY: Okay. Thank you. SENATOR LENIHAN: Does this owner's controlled insurance program, does this work like my car insurance that if I make claims against it, my premium goes up? MR. WEYGAND: There's a history. MR. DePACE: I don't know about your car insurance, but I can tell you the owner's controlled insurance program is bid out on a 3-year basis or actually a 40-month basis, we're actually in our third iteration of the plan. 19 20 21 22 23 24 0117 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0118 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0119 And we bid out both the management of it to a broker and bid out the insurance coverage cost to the large insurance companies, Zurich Insurance, Zurich Casualty has won, over the past, has won each time that the project has gone out to bid. Let me paraphrase the last report that we got from them and say that they say that we have an extraordinarily low loss ratio. In other words, a lot of the premium has been returned to the university because of the very low injury on the jobs. So we haven't seen the other end of it where we would have claims that would push the limits, we've actually seen less and that is the benefit to the program of this, that we're paying for the coverage and we're managing the losses with the insurance company; therefore, we see the benefit when there are little or no losses on the job. MR. WHITNEY: To take the analogy further, I'm not aware of any auto policy insurer sending money back for good claims history, except for I think it's Allstate or one of those that have been advertising that lately, that they treat certain customers better by giving some money back. But generally speaking, auto policies don't do that. You can have a perfect record for twenty years and you don't get money back. OCIP operates differently. SENATOR LENIHAN: Counsel George, do you want to ask a question? MS. GEORGE: I have a question. I understand that you've all said URI has reached its limit of liability because of those various ways to mitigate risk. You've gone through all that. But all those ways to mitigate risk cost money. OCIP costs money, liability insurance costs money, the envelope review that you explained to make sure the building is watertight things. To say no to Gilbane to this clause would cost URI no money and would provide certainly a measure of comfort. Why limit the exposure here? The risk here to the construction manager, when there's no cost or downside that I can see to URI and maybe that gets to the quid pro quo that was alluded to earlier. MR. DePACE: First, let me say, counselor, that risk on the project in general will be paid for by someone. So if it becomes part of the CM's responsibility, they would propose it in the cost of the work and you would 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0120 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0121 1 2 3 4 5 6 7 end up seeing it in the cost of the work. We believe that we've brought the insurances to this project at a much better cost for the university and as I say, we can prove it, as we have seen savings that we're able to go back to individual projects of $5 million over the last seven years. The balance of that I can say is that commercial contracts like this are a negotiation. There are give and take and there are things that the university wants in the contract that push the RFP and I believe we've got some things back from the RFP that is substantial for us, including increased liquidator damages which as you hear is $75,000 a month. The other items are is that typically in these projects there is no retainage held by the university by the owner on the CM fee. We have a percentage of the construction contract where retainage is held on the project and we continue to hold that until the end of the job. I think that contractors will tell you that you mentioned previously that our general conditions, sometimes referred to as the 201 section of the contract is different from the AIA contract and we're thankful that it is. As I said the last time that we spoke, the AIA is an Association of Architects, the AGC is an Association of Contractors. They each feel that they have their own nuances in contracts prepared by them. We believe that we need a strong owner approach contract. We believe that our general conditions, now called Division 007 for us, are very strong in protection of the owner and those were not necessarily part of the RFP, but were the general conditions that we required on this project. We think that was received for the value for limiting the liability risk in trade. Also, the RFP spoke to responsibilities for ambiguities of the contract. Excuse me, conflicts, ambiguities and problems from lack of coordination within the subcontractor bid packages. That was originally called in the RFP to be part of the owner's contingency. As counsel had mentioned earlier, that's now shifted and is now a responsibility under the CM's responsibility. I think that's a very important shift in responsibilities. That plus the other mitigation actions that we took in place, I think are very important, where we ensure that areas where the CM could default, we have covered by processes. In other words, let me identify a couple of them. One of the areas where previous faults 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0122 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0123 1 2 3 4 5 6 7 8 9 10 11 12 13 14 in construction contracts is that the general contractor or CM doesn't pay the subcontractors. I can tell you my first project in this business was with a company that halfway through the project stopped paying its subcontractors and this was an $8 million project. It was our field house. You could tell that the CM was about to go out of business. We had to take over that contract and actually start paying the subs individually because we didn't have all the right protections in place back then. The contractor eventually went out of business but every one of those subs got paid. We made sure that that happened. And so we learned some things from that. And therefore, on each project that we have, with every invoice and we allow them to invoice monthly, we get a release of liens from all of the trade contractors who performed work on that contract for the previous month's payment. So that means if we pay Gilbane in January by the time February's invoice hits my desk, it should be accompanied by a release of liens from all of the subcontractors saying that they have gotten paid for the January invoice. That's the only way that I will sign the February invoice. So that ensures -- that mitigates the risk because we know that the subs are being paid. And beyond that is the fact that we only pay the CM their fee monthly. Therefore, the most that we could be at risk at any one time is the work that they put in on the previous month. So should they default on the project or go south, we have the balance of the contract where we had money allocated for that project where we could then pay someone to take the place. I'd like to say, by the way, just for the sake of it that we're talking about what if's here. The project is almost exactly at 50 percent complete, $22 million spent, $22 million left to go. And we're running smooth, we're on schedule, we're going to complete this building and deliver it to the university in December, on December 29th. I mentioned the analysis of their finances before we went into the waiving of the bonds. At the time of the awarding of the purchase order and the GMP, all of the trade contractors were actually bid so the costs were not speculative, there was not some kind of scientific guess at that point presented by the contractor, we had all hard bids from trade contractors that summed up, showed us what the cost of the work was. So the risk again was mitigated at that point. MR. WEYGAND: I think she has it. 15 16 17 18 19 20 21 22 23 24 0124 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0125 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 MR. DePACE: I think that will show you the way we approached it, so we had to manage this portion of it and understand what the risk was. MR. WEYGAND: Mr. Chairman, if I could, our legal counsel has some time constraints tonight I don't know if you have other things here that we may need response from legal counsel because I know Chris has to leave in about ten minutes. SENATOR LENIHAN: It was my intention, I was going through these questions by category. There are a total of eighteen different areas, we're on number seven right now. Although some of the ones that are briefer, in fact in some cases are covered with a single question. I don't think we are going to finish all these this evening. What is the time you have to leave in actual time? MR. WHITNEY: Well, I'm supposed to be in Bristol at 7:00 for my class. I put it back an hour again as I did two weeks ago. So I'm getting a little nervous, I like to be on time. I have 46 students and I don't have the number for any of them to call them and tell them I'm running late. SENATOR LENIHAN: I think what I'm going to try and do this evening is we're going to try and finish one more set of questions. If there are any that pertain to the legal aspects of what's going on, you will be returning at some future date and we'll ask you to address it then. MR. WHITNEY: I'd be happy to do that. I'd be happy to come back. SENATOR LENIHAN: And if that is an issue for you, make us aware of that. MR. WEYGAND: Be happy to do so, Mr. Chairman. MR. WHITNEY: Okay. With that am I excused now or do you want me to stay around? I'll take that as a yes. Thank you, Mr. Chairman, and members. SENATOR LENIHAN: Ms. George, any questions? MS. GEORGE: I merely wanted to summarize what you said today that this contract clause was part of a quid pro quo during negotiations, that you wanted retainage, you wanted greater liquidated damages than were required in the RFP, some give and take, and that with all the other ways you have mitigated risk, OCIP, the bonds for the subs, that you felt comfortable in negotiating this particular section in order to get something you wanted in another position of the contract; am I accurately stating 22 23 24 0126 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0127 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0128 1 2 3 that? MR. DePACE: Yes, counselor, that's a fair statement. Thank you. MS. GEORGE: Did you get anything else for this section, just the liquidated damages and the retainage? MR. DePACE: Again, we mentioned the liquidated damages change, we mentioned the retainage, we mentioned the fact that we introduced our general conditions which are strong and not typical in the industry. They are university, burnished in fire I might say, over learning over the course of the years. And the adjustment of the CM, of the contingency for the responsibility for contingency that was in the RFP and owner's contingency responsibility for conflict and ambiguities or problems from lack of coordination among the subs and move that appropriately to the CM. So I think it was a good pro quo and let's just say the project is running well here, so I think that we made a good decision. MS. GEORGE: Thank you. SENATOR LENIHAN: I just want to give you notice, I'm going to steal that burnished in fire quote and I'll use it on the floor sometime. MR. DePACE: Do I get a footnote on that? Are you going to use wild ass scientific guess, too? SENATOR LENIHAN: No. SENATOR SHEEHAN: Just a mechanical question in terms of finances, when the project is being paid for, does that money go to the CM and then to the subs? MR. WEYGAND: Yes. SENATOR SHEEHAN: Or directly to the subs? MR. WEYGAND: It goes directly to the CM, who is then responsible for paying the subs. And the following month, as Paul said, they provide a release of lien to show that indeed the subs have been paid that previous month. SENATOR SHEEHAN: How much would that be approximately a month? MR. WEYGAND: It varies. SENATOR SHEEHAN: How much is it this month or last month, just to give me an idea? MR. WEYGAND: Well, we've been into the project for about twelve months and we've expended $22 million worth of money. MR. DePACE: Two million a month. SENATOR SHEEHAN: A couple of million a month? 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0129 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0130 1 2 3 4 5 6 7 8 9 10 MR. DePACE: Yes. SENATOR SHEEHAN: I ask that because that could be another damage one could go after Gilbane for if they received money and didn't disburse that money as they should have to the subs. MR. WEYGAND: As we said, we do not release the next month's payment unless we have a lien release that says they have been paid. SENATOR SHEEHAN: And I would have asked this of counsel in terms of just technically, what does it mean to have a contract? We talked about Supreme Court case law and that one could waive this bond. To me, basic contract law says -- I guess it could be a contract, but usually it has to be some type of payment. So if the payment technically comes from Gilbane, I'm wondering if the contract here, the construction contract, is not just specifically with Gilbane but not necessarily with the subcontractors because they're getting compensation consideration from Gilbane, but that would be a legal question. I don't know if anyone has an answer for that. MR. DePace: I'm not going to try. MR. WEYGAND: I prefer legal counsel. This is Mr. Lou Saccoccio who is the University of Rhode Island's chief legal counsel. SENATOR SHEEHAN: Mr. Saccoccio, will you be sworn in, please. LOUIS J. SACCOCCIO Being duly sworn, testifies as follows: THE REPORTER: State your full name for the record, please. THE WITNESS: Louis J. Saccoccio. SENATOR SHEEHAN: Again, is this basic contract law, that obviously to have a contract, one party needs to receive, get a service for consideration, in exchange for consideration. If then the monies are actually -there's a contract with Gilbane to have subcontractors do business on their behalfs. So is technically the contract then, I mean the construction contract, only with Gilbane and not necessarily with the subs? MR. SACCOCCIO: The contract is directly with Gilbane, not with us. SENATOR SHEEHAN: And not with the subcontractors? MR. Saccoccio: The university has no contractual relations with the subcontractors. SENATOR SHEEHAN: So by definition then if we could go back and I don't want to rehash that other situation, but would it not be 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0131 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0132 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 the case then we might be ill-advised to waive a bond for the only contracted party in this construction project, which is Gilbane, as opposed to the subcontractors? MR. Saccoccio: We are also protected under subcontractor's bonds. SENATOR SHEEHAN: Against a lawsuit is what I was saying. MR. Saccoccio: Performance, yes. SENATOR SHEEHAN: In terms of the law, that was something we're getting back to and I know you can't probably speak to this. But in terms of the state, whenever it has a contract with a construction company, they need to be bonded, but I well the subs contract with only one that think the part of the reason was are bonded. But there is no the subs, then by definition the has a contract is then the manager. MR. SACCOCCIO: Our protection is with the bonding company. We are a third party beneficiary on the bond itself. As Gilbane will benefit from the bond, we have a right to take direct action against the bond. SENATOR SHEEHAN: Thank you. I thank you for your information. Thank you, Mr. Chairman. SENATOR LENIHAN: There's one more category, one other category I want to get to, I want to include because it also deals with limits of liability, in this particular case, just with the environmental issues. Again, Attorney George, if you'd start us with an intro. MS. GEORGE: This slide concerns limitation of liability, environmental limitations. In the standard AIA contract, it's not addressed. The change in the contract between Gilbane and URI add this language, that the construction manager is not liable for any environmental matters including mold, air quality, contaminants and solid waste disposal, and I'm summarizing. And this disclaimer of liability shall apply to all claims against the construction manager. SENATOR LENIHAN: Okay. I've been looking at some articles from various newspapers off the net on previous experiences regarding environmental matters and construction. And I'm struck looking over again at how many times mold is one of those issues that keeps jumping out. That's just one of these categories, but in view of this, can you explain to me why URI agreed to absent Gilbane from any liability on those environmental matters? MR. DePACE: Okay. First, let me say that I would have of course been much more 18 19 20 21 22 23 24 0133 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0134 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 comfortable and I admit that the university would be better if this phrase, if the reference to mold was not in the contract. I do have to say though that the issues about mold as you're reading about them on the web is a fairly new phenomena. Maybe within the past three, maybe max at five years, have you really started to see claims or issues about mold in construction projects where things are actionable. Many contracts leave mold simply out of the contract or liability of mold. It is difficult, so our insurance carriers tell us, to get a policy that covers against mold. So it is a new phenomenon and it is new, something that the university should have protection on, but let me tell you where we believe our coverages are in this area. So that again, we took the approach of mitigating risk to the university before agreeing to this. There are at least two ways that you can get mold in a construction project or in a completed building. The two ways are you allow moisture to come into the building and it soaks into some material, say the drywall, and mold starts to grow. Any time you get the right temperature, a little bit of germ, a little bit of bacteria, a wet area where it's the right conditions, mold will grow. That's one area where it can happen. Another area where you can get it in the building is if the HVAC system is not properly designed, then you're bringing in moisture and the moisture's allowed to accumulate somewhere. Or if you had bad construction practices that allows moisture to get into the HVAC system while you're building it, so that it can breed. We've taken mitigated steps in this process to avoid this happening. Let me say, number one, we don't allow the drywall or interior finishes to go up. We finish, the finish trade contractors to come in before the building is weather tight. That means the roof has to be tight, the windows either have to be in place or have to be blocked up with plastic or appropriate material so that you're not getting water in the building. Once you get water in the building, then it's going to breed material. So we make sure that that happens, make sure the building is weather tight before we allow the finish trades to get in. Secondly, as I mentioned, we have a commissioning agent on board that is our policeman for indoor air quality during construction and therefore by process of them monitoring the situation through, ensures that the end built 0135 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0136 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0137 1 2 3 4 5 6 product is covered, is as mold free as is possible in good modern techniques. For instance, as the committee went through the building, you may remember I pointed out the fact that all of the ductwork ends were covered with plastic to keep air from getting in there. That keeps mold from getting into the duct systems therefor breeding and producing the mold problem. The building, as I say, would be weather tight and was weather tight before we start allowing any of the finish trades to come in. So we believe that we have covered those particular areas. We actually monitor indoor air quality during the construction of the project and actually have an indoor air quality plan for construction. And we don't even allow smoking in the building and if you can imagine what that is with construction workers to say you can't smoke in the building while you're working, you have to go outside to smoke and away from the building during the course of construction. So we monitor indoor air quality. So we believe that we've put what is the best possible hands around the mold issue and believe that we have minimized the risk in there. I will admit however we would be better served in future contracts if the reference to mold, at least in this paragraph, would be deleted. So that's my lessons learned on the project and I'll admit to that. SENATOR LENIHAN: All right. Given your reservations and also given the ways that you think the university is protected by the construction techniques that you're following, given all that, in conclusion, why did you agree, why did URI agree to this provision? MR. DePACE: It was, again, part of the give and take of the negotiation for the business portion of the contract. SENATOR LENIHAN: Well, clearly this was a give, what was the take? MR. DePACE: The take were the items that I mentioned earlier. We were not one for one items in exchange, we were negotiating the whole contract at that particular time. So the items that I mentioned earlier about the liquidated damages and moving the contingency and the fact again, mitigation and understanding what the risk is, felt comfortable in moving forward and we don't have any mold in the building. SENATOR LENIHAN: There are all kinds of ways that the owner, in this case URI, is 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0138 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0139 1 2 3 4 5 6 7 8 9 10 11 12 13 exposed to potential problems. I'm assuming in this case the construction firm introduced this as one of their proposals to reduce their exposure, to the extent that it reduced their exposure and increased URI's, did it not? MR. DePACE: I would say that the shift, if it is not covered by the construction management, could be covered in other ways and the processes I laid out. I might also say that our builder's risk policy, should a mold growth or such a problem arise from damage, for instance, a wind blown tree up against the building that broke a window, allowed moisture to get in, and from that could be traced to mold growth in the drywall, that's covered by our builder's risk insurance. So again, another step that we took to mitigate the issue. MR. WEYGAND: Let me try to capsulize Paul's report to you here. This is clearly something that after we have reviewed this, brought to the attention, to our attention by the committee, Paul has reviewed it over and over again, and this is clearly something that we would like to change and would change, not only for we'd like to change it for this contract, but will change for all future contracts. This is the kind of thing that we would say has marginal benefit, if any benefit whatsoever to the university, versus quid pro quo. And so therefore this is one area that while there may be agreements on other parts, this is one place that Paul and Capital Projects and all of us believe that we could have done a little bit better on this and we're going to try to make a modification in the existing contract to correct this. SENATOR LENIHAN: Maybe I'm wrong in this, but it's my understanding that in your request for proposals regarding the pharmacy building you have attached this contract, and I'm assuming it includes this provision which waives the environmental liability? MR. WEYGAND: We still have the opportunity to modify and change that contract. SENATOR SHEEHAN: Is it your intention to do that? MR. WEYGAND: Yes, it is. SENATOR LENIHAN: I want to get the time frame on this. When you sent out or solicited RFP's, were you aware at that time or was it your opinion at that time or still in the formulation stages that this is probably something which wasn't to the best interests of the university? MR. WEYGAND: Not at the time it 14 15 16 17 18 19 20 21 22 23 24 0140 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0141 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 went out, no. SENATOR LENIHAN: Then assuming as you, I think indicated, but just so it didn't get lost in the back and forth of the committee, it is your intention specifically to address this issue by way of amending the example contract that you've attached to the new RFP's, to change that? MR. WEYGAND: That's correct. MR. DePACE: Yes, it is. SENATOR LENIHAN: Generally speaking then, who is responsible for overseeing environmental matters in building construction? MR. WEYGAND: Are you talking about from a contractual standpoint or from the university's side? SENATOR LENIHAN: From the university's side. MR. DePACE: While they're under construction it is, we have our safety inspectors who look for all types of hazards while the building is under construction. MR. WEYGAND: We use our own Office of Safety and Risk Management with safety inspectors. MR. DePACE: Those are mostly for finished buildings although they do walk through and do verify certain aspects during the design phase and, for instance, the fire alarm phase. Our own Office of Safety and Risk Management does have responsibilities. SENATOR LENIHAN: For example, you offered us the example of taking the caps off all the ductwork. Somebody had to think of that idea. It's a good one obviously, where did that come from? MR. DePACE: That came as a product of our hiring of the commissioning agent. That was his direction. As you know, that we are trying to achieve a Lead Silver certification on this building. Lead Silver means that you have to, among other things, protect the quality during construction as well as design things in from the very beginning. So it was part of our construction, our commissioning agent's responsibility to identify, create a construction indoor air quality plan and to monitor it. So it's our commissioning agent. MR. WEYGAND: There may be many places where recommendations will come with regards to averting risk and improving the quality of the building, including a number of issues with regard to fire, safety, health, other types of risks. They may come from our safety and risk management, they may come from the building 21 22 23 24 0142 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0143 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0144 1 2 inspector's office, they may come from our commissioning agent, they may come from the fire marshal and fire inspection, it can come from a range of different places and all of them contribute to making the building safer and better. And we incorporate those as we go along. That covering of ductwork, the basis of that is clearly to receive Lead Silver certificate points toward our obtaining our Lead Silver certificate. That's where we got that idea. It wasn't because of someone coming in and saying well that's going to prevent mold. Someone else came in and said this will prevent mold and also helps you toward your Lead certification. SENATOR LENIHAN: Is this certification something that you seek -MR. WEYGAND: On all projects. On all projects, we seek to receive Lead certification. We strive -- in this building, I think we will accomplish Silver certificate which is what we like to have as our standard. The same way with the pharmacy. Our dining services building received, I believe, Lead Silver as well. MR. DePACE: It was close. MR. WEYGAND: That close. As you know, certification doesn't come until after the building is completed, until it's all commissioned and everybody certifies the various things that you completed properly. SENATOR LENIHAN: Okay. I still have more questions. SENATOR SHEEHAN: Just a question here, clarification, going back to the mold issue. You said it was a part of your managing the risk for averting problems from the get-go, safeguards you put into place like making sure the plastic covers the outside so moisture doesn't get in to the finished work or covering the ducts and so forth. Is it your commissioning agent, as you called that person, would it be their responsibility, his or her responsibility, to go in and say, "Oh, look, plastic's not up." Who would go in and do that? MR. DePACE: If it came to the ductwork, yes, that's the commissioning agent's responsibility. SENATOR SHEEHAN: So they are responsible for putting plastic on the ducts so the rain doesn't come in? MR. DePACE: If it came to the windows, there are several people that are responsible for that. Certainly among others that watch it on the job site for us is the building 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0145 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0146 1 2 3 4 5 6 7 8 9 commissioner's office. They will not allow any electrical work, either rough or finish trades, to go on within the building until it's weather tight. In order to push the schedule, the CM has to use his creativity to ensure that either the roof is on the building or that the roof is covered. And either the windows are in the building or that the building is completely encased in plastic as it was so that we could work through the winter. SENATOR SHEEHAN: Now assuming for the moment the CM were negligent in that undertaking those types of safeguards which have been specified in advance, at least from your perspective, would that be an automatic breach -would that be some form of breach of contract at that point? Would that be included and would you consider that breach of contract in part, anyways? MR. WEYGAND: Well, it could be actually due to a couple of different reasons. One would be that there wasn't proper supervision by the CM. The other could be that it was also the responsibility of the mason who was bricking up the outside of the building to make sure all the windows were properly secured and closed in. So it could fall onto any one of those people depending upon where the negligence happened to be. SENATOR SHEEHAN: Okay. Would that be actionable at that particular time or would one have to wait? Let's just say that maybe the plastic went up belatedly but enough moisture had gotten into the building until after the fact. We've had issues at various universities with mold and so forth, because frankly that could cost a pretty penny to go back and get that out. Those are not habitable buildings with mold spores. MR. WEYGAND: Yes. SENATOR SHEEHAN: Would you have to wait until after the fact to say enough moisture had gotten in or is there any way to hold them to account at that particular time? MR. DePACE: I think we would hold them to account at that particular time. I know we would hold them to account at that particular time. If moisture were found and mold were identified as having grown in the location, it becomes pretty obvious when it is. We understand what mold is. We had, in some of our older buildings, we have seen issues associated with that. We would, in this particular case, direct immediate rework of that area so that the mold is like a seed, it multiplies if it stays in place. So it 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0147 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0148 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 has to be immediately removed. We would direct that it become immediately removed from the process. MR. WEYGAND: Anecdotically, let me tell you that we did have a project, not this project -SENATOR LENIHAN: If I may interrupt, some of the questions are going beyond the process, the meat of what we've got here. SENATOR SHEEHAN: Sorry. I hadn't seen those. Just for my edification, I know there's -- hopefully it's on your list, the Chafee building, was that mold or was that -MR. WEYGAND: PCB's. MR. DePACE: PCB's. Originally it was actually asbestos, 15 years ago. SENATOR SHEEHAN: Contaminants at URI. MR. DePACE: Contaminants and PCB's, yes. SENATOR SHEEHAN: That might be a good clause to include, contaminants, given that personal experience with the university. Thank you, Mr. Chairman. SENATOR LENIHAN: If there is an environmental issue that has resulted from Gilbane's failure to properly supervise and/or manage, this clause exempts them from any liability. Who then is now responsible for the damage of the exposure? MR. DePACE: I don't read it. Again, I'm not the attorney. I don't want to use that phrase again. I'm not an attorney, but this is not from negligence. If they're negligent in supervising the project, I believe that they are liable, and not under this clause but under others. I would leave that to the attorney though to better speak. That's the way we would manage the project is that this is -- they have responsibility to manage the project. And if they are not managing the project and there are subcontractors and some of this results, they have a responsibility to direct the subs to correct. SENATOR LENIHAN: I would like specifically at the next hearing to take this up, if that could be addressed by your legal counsel. I know you've answered this to some degree, but as the building is going forward and you're trying to mitigate any potential environmental problems, who's doing the inspecting, who's supposed to be doing the inspecting? MR. WEYGAND: I'm sorry, Mr. Chairman. SENATOR LENIHAN: As you're going 17 18 19 20 21 22 23 24 0149 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0150 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 forward and constructing the buildings, you want to take and mitigate any -- not any possibility, that's impossible, but you want to mitigate as much as possible any environmental risk or exposure. Who's doing the inspecting to see that that doesn't happen? MR. DePACE: During the course of this particular project, we have Payette Architects that are responsible overall for the construction administration and we pay them for that as part their contract. They have a representative that is on-site regularly to observe the work that is going on. And believe me, Mike Carr is his name, a very detail individual. Payette Associates have also contracted with a local architectural firm Lerner Ladds Bartels, who also provide construction inspection during the course of the project. The gentleman that they have on the job is also very detailed and on the job site on a regular basis. That's enhanced by the fact that they have a project going on at the next building over so that they do double duty when they're on the site. We also have the Rhode Island Building Commissioner's Office that inspects the building for -- they have a general building inspector plus an electrical, a plumbing and a mechanical inspector. They are on the job regularly and examine, for instance, what's going on, what's being installed within the walls before we allow the walls to go up. That's done on a regular basis. And of course we have the commissioning agent who is on site on a regular basis inspecting for the items within his purview. SENATOR LENIHAN: You mentioned earlier that the construction is essentially at the halfway point, you've spent about half of the money, so you have 50 percent. Up until this point, as we speak, have been there been any environmental issues that have come forward? MR. DePACE: There have been none. SENATOR LENIHAN: So there are no associated costs, no one has had to remedy anything? MR. DePACE: Yes, sir. SENATOR LENIHAN: At the University of Rhode Island, your perspective, who was it that approved this liability exclusion clause? MR. DePACE: I have the primary responsibility for negotiating the contract. SENATOR LENIHAN: You are the negotiator, but I assume someone has to ratify -- 24 0151 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0152 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0153 1 2 3 4 5 I assume you give a recommendation to someone. MR. DePACE: My recommendation goes up through the chain of command. As the vice president has mentioned they lean heavily on my recommendation with regard to this. So it goes up through the chain of command. The document, of course, was eventually sign by the university, signed by the vice president and by Gilbane Building Company. MR. WEYGAND: And the Department of Administration. SENATOR LENIHAN: Okay, but from the university's side, the buck stops at your desk? MR. WEYGAND: Yes. SENATOR LENIHAN: But it also requires a sign off at DOA? MR. WEYGAND: That's correct. SENATOR LENIHAN: And who would provide that sign off at the Department of Administration? MR. WEYGAND: Director of Administration. SENATOR LENIHAN: Thank you. On your recommendation in this particular case, I'm assuming that came in the form of some kind of document, your request as you passed it along the chain of command, Mr. DePace? MR. DePACE: Not specifically for this, but in a recommendation to sign the entire contract when we were done negotiating. I did not particularly flag this or any other sections of the contract at that time. SENATOR LENIHAN: Do we have all of the written documents that exist relative to that general approval, that general recommendation and consequent approval? MR. DePACE: Yes, you do. SENATOR LENIHAN: I think we've asked this so many times you can probably anticipate it, was this discussed with anyone at DOA? MR. WEYGAND: This particular clause? SENATOR LENIHAN: Yes. MR. WEYGAND: Not to my knowledge. SENATOR LENIHAN: As a result of this clause, does Gilbane have any responsibility here? MR. WEYGAND: I think Paul was alluding to he believes that they do in other parts of the contract, but we really want to confer with Chris Whitney before we respond to that. 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0154 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0155 1 2 3 4 5 6 7 8 9 10 11 12 SENATOR LENIHAN: Okay. I was going to ask a question but it's regarding the $3.4 million cap, but if this is absent from Gilbane's liability, it doesn't matter what the cap is because it's not their problem. You raised a point by mentioning the fact that one of the other -- for want of a better term, the inspecting entities taking a look at this on an ongoing basis, Payette Architectural firm. In the contract we have with Payette and/or the local, I've forgotten the exact citation, but the local architectural firm -MR. DePACE: Lerner Ladds & Bartels. SENATOR LENIHAN: Do we have a contract with them? MR. WEYGAND: They are a subcontract to the architectural firm, so it's not a direct contract with us. SENATOR LENIHAN: What about Payette, do we have a contract with them? MR. DePACE: Yes, we do. MR. WEYGAND: Payette is the direct contractor for the University of Rhode Island as an architectural firm. They have various subcontractors, including Lerner Ladds, engineering firms as well as estimating firms. SENATOR LENIHAN: In their contract, are there any such exclusions that absent them from liability in certain areas? MR. WEYGAND: Have to review the architectural contract between the State of Rhode Island, the university and Payette. There is the standard errors and omissions requirement for the architect, meaning if that there is an error or omission on their part, that they're liable for it. But we'd have to review that. We're talking specifically to this clause? SENATOR LENIHAN: What I'm looking at is, this is a -- you mentioned that they were involved in this process, and it suddenly occurred to me if they're involved in this process, they obviously have liability as an architect, the total process to get this building from a bright idea to something that's sitting on the ground. And it occurred to me that their contract may contain in it terms which are parallel to or complementary to the ones that appear in the contract with Gilbane and I just wanted to know if the state or URI has to go looking for someone for responsibility and if Gilbane is absented here, is the architectural firm also freed from any liability if there was a design flaw that allowed the introduction of any one of these environmental factors. 13 14 15 16 17 18 19 20 21 22 23 24 0156 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0157 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 MR. WEYGAND: Well, I can tell you that a design flaw is part of what we call errors and omissions and that has to be covered by the architect. SENATOR LENIHAN: Is there a cap on that E & O policy, liability? MR. WEYGAND: Dollar amount. I don't recall. MR. DePACE: There is a requirement, and I don't know whether it's by statute or by regulation, as to what the design agents need to carry for their errors and omission policy. sure. It might be a million dollars, I'm not MR. WEYGAND: It might be a million or two in aggregate. I'm not sure. SENATOR LENIHAN: I'm not trying to be snide with this comment. MR. WEYGAND: No, it's a good question. There is a provision in there that pertains to state law with regard to the limits of the errors and omissions insurance. And we'll be happy to pull that out. MR. DePACE: It's a requirement by the purchasing agent before such a contract is put in place and approved by the purchase order, that these insurances are assured to be in place. SENATOR LENIHAN: I guess the point I'm getting to is, your outside legal counsel, Mr. Whitney, informed you that even though statute says that the performance bond has to be in place, he gave you a legal argument as to why in fact you didn't have to conform to that. I'm looking at the fact that while it may be a state law regarding the responsibility of this architectural firm, I just want to make sure that there's no creative legal mind that's found a way to conform to state law and not conform to state law at the same time. MR. SACCOCCIO: It's fair to say that the architectural contract was entered into well before this one. And certainly none of us have actually looked at it in a while. I think I know what you're asking, you're asking whether or not there are similar limitation in liability clauses in the architect's contract. We can certainly get that for you. SENATOR LENIHAN: We'll give you a series of questions that I anticipate you will respond to next time, not asking for a response now because your legal counsel isn't present. MR. WEYGAND: But I would like to add that again the idea of the "quote" "waiver for liability with Gilbane," was that the liability was resting in the subcontract's performance bonds 20 21 22 23 24 0158 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0159 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0160 1 so that we're still being covered but not by one policy with Gilbane, but multiple policies with the subcontractors. SENATOR LENIHAN: I don't have too much of a problem constructing a scenario where you ask the subcontractor -- the contractor may be at fault, but so might also Gilbane if a building envelope design was fine and will provide for a water tight enclosure, but if it's not built according to spec and design and there's a problem, yes, it may be a responsibility of the individual subcontractor, but up until this exclusion or the cap, Gilbane's absented from responsibility here, that's my point. Up until now we've been talking specifically about mold and I mention that only because I saw that pop out of a number of news stories from elsewhere. I'm assuming that there are potentials for legitimate environmental problems in areas that have nothing to do with mold. For example, demolition of the old building. I don't know what the materials are in there, but assume for a moment there was asbestos in the site and it wasn't recognized and dealt with, you have an environmental problem. Are there other environmental problems that you have to sort of look out for in particular as you go through the balance of this process? MR. DePACE: In the case of demolition of bioscience, for instance, it was a biological science building, so there are chemicals in there. We intended to do and have an allowance for in our own budget for a sweep of the building to ensure that all of those were removed. We're learning about environmental hazards all the time. As even as recently as the articles last week about biphenyls, plastic bottles that affect individuals and have been for years and baby's bottles that could adversely affect their health. There's no proven documentation on that but you can see that Walmart's taken them off of the shelves already because they anticipate something. So there continues to be evidence about environmental hazards that we don't know about now. We do our best to try and stay abreast of the scientific documentation. We have firms under contract that do our asbestos abatement plans. They also -- we have firms available to us to test for items such as PCB's. The reason why we did a major surgery on our Chafee building because we found trace amounts of PCB's in the project. Several, I guess maybe 15 years ago, 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0161 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0162 1 2 3 4 5 6 7 8 time is going by, we tried to flush all of our transformers on campus about oils that may contain PCB's because that was a proper product to be using in the oils and transformers and we flushed that out, but we're continuing to find things. And as I say, mold is a relatively new phenomenon, maybe two to five years old that have had the issues come to the surface, that is something you should be aware of. MR. WEYGAND: There are in our buildings, there can always be the potential for hazardous material, whether it be a chemical in a science laboratory building or something that came out of an electrical transformer or some other element like that. In all of those cases, regardless of the kind of bid, general contractor, construction manager, whoever is doing the work, that burden of payment for the removal of that waste is always going to be ours. It is not something that someone will pick up out of the grace of God because they happen to have bid the demolition of BSC if we didn't already tell them it was already there. So if there's an unforeseen circumstance, there's a chemical, there's a solvent, if there's some kind of waste that we did not know about and that comes up, we bear that burden no matter who the contractor is. MR. DePACE: So it's burden on us, the owner, to do a full examination of a building that we're undergoing renovations, say our Lippitt Hall, for instance, to determine where and how much asbestos is in there, where the lead is, if there's lead paint in it and where it is, and if there are any other wastes within the building and idea that to the contractor. We have a responsibility to identify it. You certainly simply can't back them into the fact that it was identified as waste -- that hazardous waste was in the building. If we didn't identify it and tell them to take care of it and expect them to take the burden of removing it. I don't think that that would stand up in any courtroom. SENATOR SHEEHAN: Just a question, the question is this, if the CM in this case, could the CM, I guess it could have, could have been bonded for the full amount of their part of the project, kind of an umbrella? MR. WEYGAND: You mean the $44 million? SENATOR SHEEHAN: Well, no. If they had done the bond here which would have cost $286,000, you were trying to save that money. They could have done that if they wanted to. 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0163 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0164 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 MR. WEYGAND: Absolutely. If we wanted. SENATOR SHEEHAN: Pass the costs, along with the fee. Might that have acted as an umbrella so that nothing essentially would fall through the cracks; is that a fair statement? We've covered some major aspects, personnel, there's some aspect of damage that might have been covered, but it would have been maybe kind of a catch all for any type of problems that may have occurred. MR. WEYGAND: With regard to perform but not hazardous waste because that would be totally different. Unless the hazardous waste was the result of their performance, but if their -- it had to be a chemical or something else that was found on the site or in the demolition of a building, that clearly falls outside of their performance bond responsibility. It falls on us to have identified it ahead of time and then they would have properly bid on it. If it's not properly identified, then it's our burden to pay for it. SENATOR SHEEHAN: That $286,000, what amount is that bonded up to? What would that have paid for if you had taken out -MR. WEYGAND: That was the performance bond for the construction of the building. SENATOR SHEEHAN: Up to what dollar amount would that have covered for the liability? MR. DePACE: Up to $44 million. SENATOR SHEEHAN: So the whole nut? MR. DePACE: Would have been the second layer. MR. WEYGAND: Because the subs are already covered. MR. DePACE: The first is covered. This would have been another layer on top to ensure that the construction manager ensured that the subs performed. SENATOR SHEEHAN: So the $286,000 covers the full cost of the project, from the university's perspective? MR. DePACE: Yes. SENATOR SHEEHAN: Is it conversely true, could the CM actually have said, "Well, my subs don't need to be bonded as I assumed the responsibility?" So, for example, could the subs have gone without being bonded to this project and only the CM could have been bonded; is that possible? MR. DePACE: I think the CM could 16 17 18 19 20 21 22 23 24 0165 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0166 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 have proposed that and in that case we would not have waived the CM's bond. SENATOR SHEEHAN: Okay. MR. WEYGAND: I don't want to speak for the general contractor, but I would imagine that the general, the CM would probably say if that sub isn't bonding this, then I'm not so sure I want to cover that unless there's a savings to the CM as a result of that. SENATOR SHEEHAN: Okay. But in theory, the university could have been protected if Gilbane was bonded or were to have been bonded for the $286,000 and the subs were not. The subs, if we add the total amount that they paid for their performance bond, that was $410,000 as I heard it, unless I misheard it, versus $286,000 for the CM, might it be prudent, at least from a financial perspective for the university to say to the next CM of X Y Z project, why don't you be bonded for the full amount and then whatever you do with the subcontractors, we're just going to hold you as one entity responsible for our satisfaction for the entire project. MR. DePACE: I would say, my guess is that the CM, any CM would say be glad to do that and it will cost you $686,000 to do that, because they need to ensure the performance of their subs. They're not performing any of the work so it would simply be the number would be that much higher because they're now taking on the responsibility for the subs, if you would find a CM to do that. SENATOR SHEEHAN: But wouldn't that amount have been covered by the $286,000 bond issue? MR. DePACE: I don't think 286 would be the number. If the CM was not able to bond his subs, which I'm sure he would want to, then I'm sure the number would not be $286,000. SENATOR SHEEHAN: So even though that this amount here, this $286,000 covers in theory at least up to the total price of the project itself. So there would be in excess of that, maybe personnel got hurt or something; is that what you're saying? MR. DePACE: I think the best way and maybe the CM would be best to say how the number was put together, but my guess is that the CM bond of $286,000 was with the understanding that the subs would be bonded and that was already in the cost of the work. If the subs were not bonded, the CM would have to protect itself and would want to hire a number of bonding. SENATOR SHEEHAN: From an 23 24 0167 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0168 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0169 1 2 3 4 actuarial point of view, and I'm no expert, it would seem to me that the bonding company, that the insurance company that was doing the bonding, if they knew that the subs would be bonded, I'm wondering why they would have assessed $286,000 in cost? Maybe it would have been a much smaller number seeing how the subcontractors were already bonded; is that a fair statement or am I misunderstanding? MR. DePACE: I think that each of the proposers against the RFP understood and included that the subs would be bonded. SENATOR SHEEHAN: That was understood? MR. DePACE: Actually, the instructions in the RFP said everybody would be bonded. SENATOR SHEEHAN: So the instruction was everyone be bonded, including the CM and the subs. And with that understanding the number of $286,000 come forward in terms of what it could cost the CM, in this case Gilbane, to get that bond? MR. DePACE: The incremental cost above what the subs would be bonded at. In other words, 286 was incremental, assuming the subs were bonded. If the subs were not going to be bonded, then it would have been higher, I would expect. SENATOR SHEEHAN: Okay. Might it cost more that the CM were not covered? Could it have cost the subcontractors more money because now you've taken the CM out of the risk equation? In other words, it would transfer -MR. WEYGAND: I don't think we have the expertise to answer that, maybe someone in risk management and insurance -SENATOR SHEEHAN: It just seemed logical to me that if it's factored in, $286,000, assuming that the subs would be bonded as well as the CM, what happens if you take them out of the equation? Does that mean that somebody will say well, probably going to be on the hook for more money if subcontractors get sued or something may happen, like more money, maybe more than the $410,000 as we heard. MR. WEYGAND: It could very well be. It would be inappropriate for us to try to answer that without the advice from someone from risk management. SENATOR SHEEHAN: Thank you. SENATOR LENIHAN: Any further questions? If there are no further questions at this time, I want to thank you for your input this afternoon. It's been exceptionally helpful. 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0170 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0171 1 2 3 4 5 6 7 8 9 10 11 There's a lot of material here for us to digest but certainly it's a much more fulfilling afternoon than it was a couple of weeks ago from all points of view. I'm going to tell you ahead of time that we'll be returning to this particular matter and the balance of our questions two weeks from today, not next week. We have about a dozen bills that are before the committee and we need to take and deal with those the just because we're approaching that deadline, that's the reason for the postponement of this for two weeks. At that time, those questions that needed the input from legal counsel can be responded to and we'll go on with the balance of questions. Do you have any questions for us as a committee? MR. WEYGAND: It's really, this has followed pretty much the previous outline. It's very similar to those. We can perhaps try to expedite some of the next or two weeks from now hearing, if we were to understand that the other the rest of the remaining portions of our original Power Point are where we're going to, we could try to prepare some succinct answers for you because we did ramble a little bit today and I don't want to continue to say we'll get more information and get it back to you. So if we are to understand that the remaining portion of the questions will really pertain to the remaining portion of the PowerPoint from two weeks ago, that's fine. We'll contain our responses. SENATOR LENIHAN: As I envision it, the next time around that's exactly what we'll do. We'll deal with the balance of the PowerPoint and the questions that are contained. Finally now we are finished with the issue of the contract and contract provisions. Now hopefully between now well, it will be more than two weeks from now, say three from now, we will have received information from the Department of Administration to allow us to begin to address the process which is a totally different thing. And as I indicated to you when we talked several weeks ago, that's being segmented apart from the contract itself. But we can't go forward with that until we have further information from DOA. I had a conversation with Mr. Williams as recently as this afternoon and I believe we're going to be receiving that information forthwith, and if that's true, you can probably anticipate that three weeks from now you may well might have to come back to speak to the issue of the process 12 13 14 15 16 17 18 19 20 21 22 23 24 0172 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 0173 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 rather than just the contract itself. MR. WEYGAND: We will make sure we schedule our next Mondays with Mike. SENATOR LENIHAN: I would also advise you to do what I think you've already been doing, that is in the interim if you have particular questions, by way of helping your presentation to organize it correctly, I'm as close as a phone call or legal counsel for the committee will glad to respond to any questions that you have as well. MR. WEYGAND: We greatly appreciate the cooperation and assistance in this and I know that we had hoped to be more prepared the last time around but now with the PowerPoint that we received last week, we can clearly address the questions very pointedly, very succinctly for you, so I greatly appreciate that and we'll move forward and be ready for two weeks from today. SENATOR LENIHAN: Anything further to come before the committee this afternoon? Hearing none, we'll call the hearing to an end. Thank you again for coming and we'll see you in a couple of weeks. (ADJOURNED AT 7:10 P.M.) * * * * * * * * * * * * * * C E R T I F I C A T E I, Claudia J. Read, Notary Public, do hereby certify that I reported in shorthand the foregoing proceedings, and that the foregoing transcript contains a true, accurate, and complete record of the proceedings at the above-entitled hearing. IN WITNESS WHEREOF, I have hereunto set my hand this 5th day of May, 2008. CLAUDIA J. READ, NOTARY PUBLIC/CERTIFIED COURT REPORTER MY COMMISSION EXPIRES NOVEMBER 2, 2008. 19 20 21 22 23 24