JANUARY 10, 2014 REPORT NHA STATUS REPORT Iloilo River

advertisement
JANUARY 10, 2014 REPORT
NHA
STATUS REPORT
Iloilo River Plains Subdivision Phase 1
Iloilo City
(As of 08 January 2014)
Iloilo River Plains Subdivision Phase 1
Brgys. Camalig and Lanit, Jaro, Iloilo City
Land Development and Housing Construction
Area
:
56,385 square meters
TCT Nos.
:
T-167282 & T-167283
No. of parcels
:
2
Landowner
:
City of Iloilo
No. Generated Lots
:
1,000
Contract Cost
:
P 169,394,766.07
Original Contract Duration :
330
Revised Contract Duration :
490
Contract Start
:
16 August 2012
Contract Completion (Orig) :
11 July 2013
Revised Completion Date
Due to Time Adjustment
:
March 31, 2014 (Base on Catch up recommended)
 Physical accomplishment as of 08 January 2014 is computed 88.26% compared
to a target accomplishment of 86.83%.
Subject to a contract Catch up
Schedule/program already recommended to VMO’s appropriate action.
 Started lay-out of proposed Integrated School December 28, 2013
 Land Development
:
27.55%
 Housing Construction
:
59.20%
 Housing Constructed
:
971 units
 Housing Completed
:
489 units
84 units inspected and accepted
405 units inspected by acceptance committee
• Partially Completed
:
445 units
• Foundation Lay-out
:
37 units
ILOILO RIVER PLAINS SUBDIVISION
Brgys. Camalig/ Lanit, Jaro, Iloilo City
STATUS/ACCOMPLISHMENT REPORT






Housing Construction inspected and accepted for turn-over, ( 84 units)
Inspection by acceptance committee, (163 units) July 23, 2013
Inspection by acceptance committee, (242 units) Nov 19-20, 2013
Housing Construction partially completed, (445 units)
Housing Construction foundation lay-out, ( 37 units)
Road network @ 10 meters wide
ACCOMPLISHMENT as of January 08, 2014
(Base on time adjustment)
TARGET: 86.83%
ACTUAL: 88.26%
1
DENR
MANGROVE REMOVAL, TRANSFER/HAULING AND TRANSPLANTING ACTIVITY
BATIANO RIVER
Budget: 2.077 Million
Activity
Poles
Implementer: Mun. Government of Oton
Acc%
Saplings
Acc%
Wildlings
Acc%
Nipa
Acc%
1.Mangroves
balled/removed
93
100%
752
100%
188
100%
4203
100%
2.Transfer of
balled
mangroves
93
100%
752
100%
188
100%
4203
100%
4203
100%
3.Hauling and
Transport of
Clumps
4.Mangroves
Transplanted
93
100%
752
100%
188
100%
4203
100%
TOTAL
93
100%
752
100%
188
100%
4203
100%
Note: Details to be reported by LGU OTON
DUNGON CREEK
Wildlings
Acc%
Poles
Saplings
Implementer: City Government of Iloilo
Tree
Budget: 2.296 Million
Acc%
1.Mangroves
balled/removed
757
100%
284
100%
587
100%
38
100%
2.Transfer of
balled
mangroves
757
100%
284
100%
587
100%
38
100%
Activity
Acc%
Acc%
Nipa
Acc%
630
100%
630
100%
630
100%
3.Hauling and
Transport of
Clumps
4.Mangroves
Transplanted
757
100%
284
100%
587
100%
38
100%
TOTAL
757
100%
284
100%
587
100%
38
100%
Note: Details to be reported by City ENRO
2
PPA
Proposed Development at Brgy. Progreso-Libertad, Lapuz, Iloilo City.
 Construction of Berthing Facilities at Iloilo River Wharf, (Brgy.
Progreso-Libertad), Iloilo City
 Contractor: IBC International Builders Corporation
 Approved Budget for Contract: Ph126.00M
 Contract Cost : Ph 115.30M
 Scope of works:
a) construction of berthing facilities, (232.00 m)
b) r.c. platform (26.00mx15.00m) and roro ramp (9mx11m)
 Duration : 450 calendar days
• Contract completion date: 3 April 2014
 Status : On-going w/ 70.013% accomplishment as of January 5, 2014
Slippage : -6.599%
Proposed Development at Brgy. Progreso-Libertad, Lapuz, Iloilo City.
 Construction of Passenger Terminal Building (PTB) at Iloilo
River Wharf, (Brgy. Progreso-Libertad), Iloilo City
 Contractor: RRL Builders Corporation
 Approved Budget for Contract: Ph18.00M
 Contract Cost
: Ph 17.31M
 Revised Contract Cost : Ph 19.03M
 Scope of works:
a) construction of passenger terminal building
floor area = 1,000.00 sq. m.
 Duration : 330 calendar days
• Contract Completion Date: 30 March 2014
 Status : On-going, 75.42% accomplishment as of
January 10, 2014.
Proposed Development at Brgy. Progreso-Libertad, Lapuz, Iloilo City.
 Proposed Site Development at iloilo River Wharf, (Brgy.
Progreso-Libertad), Iloilo City
 Contractor: F. GURREA CONSTRUCTION, INC.
 Contract Cost : Ph 24.56M
 Scope of works:
a) site development
b) proposed fence & gates
c) construction of guardhouse
 Duration : 290 calendar days
 Status : suspended temporarily
3
ICUPAO
Barangay
No. of Families
1. North San Jose, Molo
79
2. San Rafael to Bolilao, Mand.
8
(Diversion Road Widening project)
3. Magsaysay Village, Lapaz (Dungon Creek)
25
4. Alalasan, Lapuz (Budburan Creek)
18
5. San Pedro to Tap-oc, Molo (Drainage)
21
6. Bolilao, Mand. (Dungon Creek)
100
7. Our Lady Lourdes, Jaro (Dungon Creek)
61
8. San Vicente, Jaro (Dungon Creek)
19
9. Bakhaw, Mand. (Dungon Creek)
133
10. Desamparados, Jaro (Dungon Creek)
23
11. Sta. Rosa, Mand. (Dungon Creek)
9
12. Dungon A, Jaro (Dungon Creek)
7
13. Taft North, Mand. (Dungon Creek)
54
14. Calubihan, Jaro (Dungon Creek)
73
15. Cuartero, Jaro (Dungon Creek)
23
Date of transfer
April, 2013
August, 2013
August, 2013
December, 2013
December, 2013
January, 2014
February, 2014
February, 2014
March, 2014
April, 2014
May, 2014
May, 2014
June, 2014
July, 2014
August, 2014
NIA
PROPOSED DRAINAGE IMPROVEMENT OF CALAJUNAN CREEK
STATION 0+000~STATION 6+400
Major Work Items
1. Mobilization and Demobilization
2. Desilting
 Clearing and Grubbing
 Mechanized Excavation
Total Cost
Amount
No. of CD
57,501.41
2
484,975.50
15,842,483.25
16,384,960.17
30
55
60
DECEMBER 12, 2013 REPORT
DPWH
ILOILO CIRCUMFERENTIAL ROAD
SECTION “A”
Construction of Iloilo Bridge II including Access road from Iloilo-Antique Road to Iloilo Bridge
(Km0+000 – Km0+938)
LENGTH
: 833l.m.
CONTRACT AMT.
: 90.0M
CONTRACTOR : International Builders Corporation (IBC)
Construction/Widening of Iloilo Bridge 2, Phase 2
LENGTH
: 833l.m.
CONTRACT AMT.
: 50.0M
CONTRACTOR : International Builders Corporation (IBC)
Accomplishment
: 60% as of December 10, 2013
4
SECTION “A-2” Access road from Iloilo Bridge to Mandurriao
Sooc Road (Km0+938 – Km002+165)
PHASE I
LENGTH
: 2.2 Km.
CONTRACT AMT.
: 45.70M
CONTRACTOR : East Asia Construction Inc.
Accomplishment
: Substantially Completed
PHASE II
Allocation
: 32.00M
Status
: Bid Out
SECTION “A-3” Access road from Mandurriao Sooc Road to Oton-Pakiad Road and construction of
Mandurriao Bridge I
(Km002+165 – Km002+568)
LENGTH
: 409 l.m.
CONTRACT AMT.
: 47.0M
CONTRACTOR : Readycon Trading & Construction Corp.
Accomplishment
: 80.00% as of December 10, 2013
SECTION “A-4”
Access road from Oton-Pakiad Road to Savanna Subdivision
(Km002+568 – Km005+200)
PHASE I
LENGTH
: 2.62Km.
CONTRACT AMT.
: 40.49M
CONTRACTOR : F. Gurrea Const. Inc.
Accomplishment
: Substantially Completed
PHASE II
Allocation
: 33.00M
Status
: Bid Out
Construction of Mandurriao Bridge II
CONTRACT AMT.
: 46.5M
CONTRACTOR : International Builders Corp. (IBC)
Accomplishment
: 80.00% as of December 10, 2013
PHASE II
Allocation
: 33.50M
Status
: Bid out
SECTION “B”
From Iloilo San Miguel Road to
Iloilo- Sta. Barbara Road
(Km005+900 – Km008+600)
LENGTH
:
CONTRACT AMT.
: P 67.046
CONTRACTOR : Uy Construction @ Development
Accomplishment
: Substantially Completed
PHASE II
Allocation
: 51.50M
Status
: Bid Out
5
WIDENING/IMPROVEMENT OF
BENIGNO. S. AQUINO AVENUE
(ILOILO-JARO DIVERSION ROAD)
PHASE 1-A
Project Limit : Iloilo Bridge to Tabucan, San Rafael Road .
Length
: 640 l.m.
Allocation
: 96.0 M
Contractor
: GEO Transport
Accomplishment : 82.27% as of December 10, 2013
(ILOILO-JARO DIVERSION ROAD)
PHASE 1-B
Project Limit : Tabucan, San Rafael to Jalandoni Street
Length
: 640 l.m.
Allocation
: 88.59M
Contractor
: F. Gurrea Construction
Accomplishment : 75.64% as of December 10, 2013
CONSTRUCTION OF PEDESTRIAN OVERPASS
Contract Amount : 18.48 M
Contractor
: GOOD FURTUNE INTERNATIONAL, INC.
Status
: ON-GOING
ACTIVITIES:
- Test Pile Driving
WIDENING/IMPROVEMENT OF ILOILO DUMANGAS COASTAL ROAD
LENGTH
: 8,896.70 l.m.
Section I
: 676.5 l.m.
Section II
: 5,297 l.m.
Section III
: 1,301.20 l.m.
Section IV
: 1,622 l.m.
Contract Cost
: 90.607 M
Contractor
: F. Gurrea Construction
Accomplishment
: Substantially Completed
Remarks:
Savings was utilized for Shore Protection Works.
PROPOSED ILOILO CONVENTION CENTER
CONTRACT AMT.
: P 479,847,504.47
CONTRACTOR
: HILMARC’S CONSTRUCTION CORP.
NO. OF DAYS
: 300 C.D.
NOTICE TO PROCEED
: December 9, 2013
Target Date of Completion : October 5, 2014
as per Contract
WIDENING OF ILOILO BRIDGE
LENGTH
Contract Amount
Contractor
Accomplishment
: 143.95 l.m.
: 79.94 M
: International Builders Corp. (IBC)
: 77.57 as of December 10, 2013
6
AUGUST 23, 2013 REPORT
Ongoing/Completed Project in Iloilo – Batiano River
1. Dredging/Desiltation Project
• Port Area
$ 6.50 M
• Outside Port Area
$ 0.36 M
2. Clearing of Waterways
• Derelict/Sunken Ships
$ 0.28 M
• Removal of Vegetation
$ 0.10 M
• Removal of Illegal Structures $ 0.03 M
3. Park Development
• Esplanade 1 & 2
$ 2.42 M
4. Relocation of Informal Settlers/Housing
• Iloilo River Plains I & II
$ 4.26 M
5. Livelihood Program for Fisher Folks & Informal Settlers
• Iloilo City Beneficiaries
$ 0.03 M
• Oton Beneficiaries
$ 0.02 M
6. Urban Greening
• Palm Tree
$ 0.04 M
7. Survey Works
• Dungon Creek and Batiano
8. Soil Erosion and Sedimentation Study
9. Knowledge Sharing
• 1st Batiano-River Summit
1st Iloilo River Summit
1st Philippine International River Summit
10. Port Emission Study
11. Port Development
• Iloilo-Bacolod Fast Craft Terminal
• Phil. Fish Port Development
12. Planning
• Iloilo River Master Plan
GRAND TOTAL
$ 0.28 M
$ 0.03 M
$0.01 M
$0.01 M
$0.16 M
$ 0.01 M
$ 3.80 M
$ 3.40 M
$ 0.04 M
-----------$21.78 M
(Php 936.54 M)
Upcoming Projects
1. Dredging
• Part of Iloilo River
$ 0.60 M
2. Guimaras – Iloilo Ferry Terminal System
$ 11.16 M
GRAND TOTAL $ 11.76 M
(Php 505.68 M)
Other Projects in the River Vicinity
1. Road Widening
2. Iloilo Convention Center
$ 4.30 M
$ 11.63 M
GRAND TOTAL $15.93 M
(Php 685.00 M)
7
Meeting with Fishpen Owners in Oton January 19, 2012
 40 fishpen owners were given livelihood assistance of P10,000 each for a total amount
of P400,000.00
(P 350,000 coming from Sen. Drilon and P 50,000 from LGU-Oton)
 14 fishpen owners received an additional P 10,000 from the DSWD through the SEA-K
Program
 57 households given P5,000 each for moving temporarily = total of P285,000
Iloilo City: 72 Fisher folks beneficiaries
 Total Project Cost: P864,000.00
Providing alternative livelihood to fisher folks affected by the removal of illegal fish pens
1.26 km Iloilo River Esplanade I
 Project Cost: P 83.5 Million
SLOPE PROTECTION WORKS ALONG ILOILO RIVER (Esplanade 2)
Length
: 314 l.m.
Contract Cost
: P 33.9M
Target Completion Date : August 3, 2013
February 14, 2013
Remarks
: Driving of Steel Sheet Piles will start on March 15, 2013
Total Project Cost : PhP150.64 million
(Site Development, Berthing Facilities & Passenger Terminal)
Perspective of Guimaras-Iloilo Ferry Terminal
Total Project Cost : P 479, 828,500
NHA
ILOILO RIVER PLAINS SUBDIVISION PH-2
Original plan
 Total Gross Area: 26, 995. 00 sq.m
 Total Project Cost (508 units and Land Development): P 18, 671, 255. 04
Revised plan
 Area of Circumferential Road Traversing the Subdivision: 6, 418. 00 sq.m
 Total Gross Area: 20, 577. 00 sq.m
 Total Project Cost (358 units and Land Development): P 12, 864, 053. 64
JUNE 29, 2013 REPORT
ILOILO RIVER SUBDIVISION PLAINS I
 Land Dev’t Cost : P48,907,746.07
 Housing Cost : P 120,487,024.01
 No. Of Units : 1000
 Total Area : 5.6385 has.
 Location : Brgy. Lanit, Jaro, Iloilo City, Brgy. Camalig, Jaro, Iloilo City
 Grand Total : P 169,394,770.08
ILOILO RIVER SUBDIVISION PLAINS II
 Land Dev’t Cost : P18,671,255.04
 Housing Cost : P 47,327,924.70
 No. Of Units : 503 (508)
 Total Area : 2.6995 has.
 Location : Brgy. Sooc, Mandurriao , Iloilo City
 Grand Total : P 65,999,179.74
8
MAY 25, 2013 REPORT
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
Construction of Iloilo Fish Port Complex Breakwater (Phase I)
Brgy. Tanza, Iloilo City
Contractor: IBC
Contract Amount: 102,380,000.00
9