Colgate University 13 Oak Drive Hamilton, NY 13346-1398 Joe Bello Capital Projects Office Merrill House Garden Level 2014 Capital Projects Merrill House Window Replacement Projected Construction Completion: October 1, 2014 Project Manager: Robert Dwyer The proposed Merrill House window replacement project was generated due to the aged, ill functioning and extremely drafty existing windows presently in the building. However, due to the types of windows; leaded glass, harlequin patterned and curved glass; this is not an average window replacement project. We will be replacing the 2 nd & 3rd floor windows with the exception of the leaded glass and curved glass units. The first floor windows interior wood work will be touched up as needed and sealed with polyurethane. The exterior of the building will be painted as part of the project as well. Andrews Hall Chimney Removal Scheduled Construction Completion: complete Project Manager: Robert Dwyer The Andrews Hall Chimney Removal project will remove the existing, non-functioning and dilapidated chimneys currently in place on Andrews Hall. The chimneys will be removed to below the roof line and roofed over to blend in with the existing slate roof and ridge cap detail. Merrill House Roof Replacement Projected Construction Completion: August 15, 2014 Project Manager: Robert Dwyer The Merrill House roof will be replaced with an architectural grade 40 year shingle over GAF stormgaurd underlayment and re-use existing copper flashings and snow slides. If the existing snow-ice barrier does not separate from the existing plywood underlayment we will have to replace the plywood and flashings. 13 OAK DRIVE, HAMILTON, NY 13346-1398 315-228-7135 jbello@colgate.edu Campus Wide Fire Alarm System Reporting System Construction: Fall 2014 Project Manager: Robert Dwyer Colgate University’s existing fire alarm reporting system must be updated for several reasons. Based on the need to improve the reliability, functionality and robustness of the existing fire alarm reporting system, it is clear that the existing system must be replaced with a dedicated, code compliant system that will allow more information to be sent to Campus Safety and facilitate quicker and more coordinated responses to alarms. We are in the process of soliciting bids for a new system that utilizes radio technology to provide signals to a receiver without the use of copper conductors or fiber optic cable. Alumni Hall Condensate Replacement Scheduled Construction Completion: August 15, 2014 Project Manager: Robert Dwyer The Alumni Hall Condensate Replacement project will replace an existing 2 1/2” condensate line that has degraded over the years and is leaking. The new 3” pre-insulated condensate line will be installed under the concrete slab in the basement of Alumni Hall. McGregory Hall Computer Science Renovation Scheduled Construction Completion: August 15, 2014 Project Manager: Robert Dwyer This project includes renovations to the entire 3rd floor, in order to meet the evolving needs of the Computer Science Department for both teaching and research. The work involves selective demolition and renovations to approximately 12,590 gsf on the 3rd floor. The layout of this area is designed to better meet the pedagogical needs of current and future faculty with dedicated teaching space, research/workrooms, conference space for small groups of students or faculty, and faculty offices. The teaching space includes two classrooms of approximately 30 seats each, one classroom of approximately 18-20 seats, one classroom for 1618 students. Departmental space includes departmental office, administrative assistant, faculty offices of a size that is consistent with current university standards (~160sf), 12 seat conference room, departmental library/testing room, and a combined faculty-student department center. In addition, the toilet rooms will be renovated and upgraded to provide additional toilet fixtures for both men and women. New flooring, ceilings and lighting will be installed throughout the renovated area. The east and west ends of the floor will maintain the ‘loft’ feeling of the existing structure, while introducing additional acoustical absorption. In addition, work will be required in the attic to accommodate exhaust and air intake for new ventilation and AC equipment to serve the 3rd floor. The base project includes air-conditioning, fire protection, lighting, HVAC, power and data of the entire floor. 2 of 6 Updated Campus Envelope Study Study Period: Fall 2014 Project Manager: Robert Dwyer The Updated Campus Envelope Study is a building envelope assessment of 48 buildings on the campus of Colgate University. This assessment will include documenting the condition of the building facades, fenestration, entrances and roofing. The purpose of this assessment is to visually document each building and produce a report that identifies the condition of the building envelope and prioritizes a recommended scope of work with associated probable project costs. This information will be used by Colgate University to establish capital planning budgets, forecast and prioritize future repairs. It is generally understood that many of the buildings in this assessment include the older and historically significant buildings on campus, dating back to 1826. These buildings include stone, masonry, wood framed and clad buildings, historic and contemporary replacement windows and a variety of steep and low slope roof materials. Alumni Affairs move to NBT Leased Space Construction/Move completion: September 8, 2014 Project Manager: Robert Dwyer The University has signed a long term lease with NBT Bank for the 2nd & 3rd floors above NBT Bank in downtown Hamilton. NBT will be renovating both floors; Alumni Affairs from the 2nd floor of Merrill House will occupy the 2nd floor of the newly renovated NBT space and the Special Events and Parents Fund group that currently resides at 10 Utica St. will occupy the 3 rd floor. Colgate’s scope has been selecting finishes for the leased space as well as fitting all of the NBT space with Colgate purchased furniture and furnishings. Campus Annual Caulking Project 2014 Construction Completion: complete Project Manager: David Schirripa This is an annual caulking/sealant project that addresses failed sealant joints on our masonry walls, window surrounds and other building soft joinery. The Dunlap Stands seating area sealant joints, will have full sealant replacement at a majority of the precast concrete element joints. This will maintain proper sealant joint condition to assist in extending the life expectancy of the precast and supporting steel structure and panel anchorage. 3 of 6 Cutten Complex Combined Flooring and Painting 2014 Construction: August 8, 2014 Project Manager: David Schirripa The scope of work includes abatement of asbestos floor tile and replacement with new carpeting on the 2nd floor core area, painting 2nd floor core and all stairwells, installation of new stair treads and risers on center and rear stairwells, removal of worn tack boards in all 144 rooms and infilling the remnant voids with gypsum board, then taped, finished and painted to match adjacent walls. Brigham has an expedited schedule to be completed by July 3rd to accommodate occupancy by summer programs, while the remaining three (3) towers, Read, Shepardson and Whitnall will consume the entire schedule. Hascal Hall Renovations 2014 Construction completion: August 15, 2014 Project Manager: David Schirripa This project is being assembled to combine and coordinate several R&R requests for the building and coordination of one already approved R&R into the total project. The scope of work includes painting entrances, installing alternate entrance flooring to replace existing carpet, paint select rooms on the 1st and 2nd levels, Renovations to Classroom #202 inclusive of new furniture, paint and flooring, and combine two (2) lower level offices #13-14 into one office with new paint and flooring. Window treatments are planned to be carried under this program however installation is not planned until after windows are replaced next year via separate project. James C. Colgate Hall Hall of Presidents Renovations 2014 Construction completion: August 15,2014 Project Manager: David Schirripa Work in Hall of Presidents: Refinish wood paneling and window sills below gold lettered storyboard with minimal wood repair; refinish lettered rail/trim featuring past presidents names and terms as well as the wood paneling surrounding the fireplace to refresh current look with no change in color; Repair major damage on windows and sills and finish to match; Data Closet finishes; Replace most data and electrical outlet covers; remove existing wire mold. Excludes: Hazardous material abatement, doors and hardware, exterior wood screen replacement and architectural and engineering fees. 4 of 6 James C. Colgate Hall Dormer Repairs 2014 Design/Bid period :Fall 2014 Project Manager: David Schirripa We are currently in progress of performing a complete condition assessment of all roof areas, dormers and dormer windows, to assess the overall roof condition, roof leaks, ice and snow issues and the thermal performance of the roof surfaces. The study shall include a basic structural analysis of the roof structure to identify roof snow loads to support proposed snow retention methods. An infrared thermo graphic scan will be performed on the roof and dormer walls to document thermal signature. Prepare a report incorporating the engineers’ observations, conclusions, options and recommendations for the above mentioned areas along with an opinion of probable cost to make the repairs. Upon completion of the study, the A/E recommendations were reviewed and translated into a request funding for the construction phase of the project. Due to the findings of the study and the conditions that were uncovered, we will be phasing this project over the next two years. Lawrence Hall Roof Repair Punchlist 2014 Construction: August 15, 2014 Project Manager: David Schirripa This summer 2014 contractor will return to the roof of Lawrence Hall to complete the punch list phase of the Lawrence Hall Roof Repairs 13-14 project. This work was curtailed from last summer’s schedule due to scheduling constraints mainly caused by weather delays. Frank Dining Hall Roof Structural Repair Construction completion: complete Project Manager: Pat Leamy This repair is a result of fatigued structural members, allowing deflection in the sloped roof window units which in turn causes fracturing of the window units. We are installing structural stiffening beams on the lower chord of the window units between the purlins. This roof area is over main lobby. 100 Broad Street Roof Structural Repair Construction completion: complete Project Manager: Pat Leamy This repair is a result of stressed rafter framing sections in the roof, allowing deflection in the sloped roof areas. We are installing additional structural stiffening beams between the purlins. 5 of 6 East Hall Women’s Studies New Handicap Ramp Construction completion: August 8, 2014 Project Manager: Pat Leamy This project is a result of the end-user requesting additional meeting space for the noon hour programs. This project is the removal and reconstruction of a new handicapped ramp with supporting space modifications to allow expanded meeting space in garden level of East Hall. Picker, Longyear, Africa House Security Project Construction completion: complete Project Manager: Pat Leamy This project is the design and installation of new upgraded security systems in the above noted art gallery areas. Work is presently underway with completion scheduled for late July 2014. New Soccer Stadium: Construction completion: August 1, 2014 Project Manager: Pat Leamy This project is the first phase of the new athletic facility project. This field will replace existing Van Doran Field. We are presently constructing the new field adjacent to Tyler’s Field. This new filed will be a FIFA 2 Star Turf field, with new bleachers, press box, home and visiting team rooms, Musco sports lighting and support IT infrastructure. The field work will be completed by end of July with full completion by August 1. Huntington Hall Room 303 Dance Floor Construction completion: August 1, 2014 Project Manager: Pat Leamy This project is to install a new Harlequin sprung dance floor. This project will also include the installation of a new acoustical drop ceiling with lighting, smoke detection system and sound system. James B. Colgate Hall Window Replacement Project 2014 Construction completion: August 1, 2014 Project Manager: Pat Leamy This project is the installation of the remaining 131 high performance Marvin windows in JBC. This project will also include the asbestos abatement of existing window caulk during the removal of the old windows. 6 of 6