E. Materials and Supplies Inventory

advertisement
(PG&E-7)
1
2
3
4
5
6
PACIFIC GAS AND ELECTRIC COMPANY
CHAPTER 5
SUPPLY CHAIN – MATERIALS HANDLING AND INVENTORY
A. Introduction
1. Scope and Purpose
The purpose of this chapter is to demonstrate that Pacific Gas and
7
Electric Company’s (PG&E or the Company) operating costs and capital
8
expenditures forecasts for materials and supplies (M&S) inventory and
9
warehousing and distribution services provided by Supply Chain - Materials
10
Operations (Materials Operations) are reasonable and should be adopted
11
by the California Public Utilities Commission (CPUC or Commission).
12
In support of PG&E’s ongoing maintenance and construction activities,
13
Materials Operations warehouses and distributes materials and supplies to
14
the field organizations throughout PG&E’s service territory. In addition,
15
Materials Operations provides inventory control and management and other
16
supply chain-related support services, including electric equipment repair,
17
transportation logistics and risk management.
18
19
2. Summary of Dollar Requests
Materials Operations’ capital expenditures and operating costs are
20
included in the revenue requirement calculation in eight ways:
21
(1) As M&S inventory, an element of rate base;
22
(2) As plant additions or replacements for materials handling tools and
23
24
25
26
27
equipment, an element of rate base;
(3) As direct capital salvage labor charges for the disposition and sale of
scrapped equipment (surplus, obsolete or damaged);
(4) As direct capital removal credits from the revenues received for
scrapped equipment (surplus, obsolete or damaged);
28
(5) As direct materials in expense and capital projects;
29
(6) As materials burden in expense and capital projects;
30
(7) As direct expense charges for electric equipment repair and scrapping;
31
and
5-1
(PG&E-7)
1
(8) As provider cost center (PCC) charges in expense and capital for
2
intra-company mail services.
3
In this chapter, PG&E is requesting that the Commission adopt its 2005
4
through 2007 forecasts for Category 1 and 2005 through 2009 forecasts for
5
Categories 2 and 3 as detailed below. Requests for the costs associated
6
with Categories 4 through 8 are included in the forecasts of other programs
7
and, therefore, are not requested in this chapter. Categories 4 through 8
8
are referenced here for informational purposes only.
9
For Category 1, M&S inventory, PG&E requests that the Commission
10
adopt its weighted average forecasts of $32.6 million for 2005, $33 million
11
for 2006 and $33.1 million for 2007. PG&E’s 2007 forecast in the amount of
12
$33.1 million for the weighted average of M&S inventory is 5.7 percent
13
higher than the 2004 recorded adjusted weighted average of $31.3 million.
14
This request covers M&S inventory needed to support the maintenance and
15
construction activities of electric and gas distribution. M&S inventory
16
balances for Generation are included in Chapter 11 of Exhibit (PG&E-3),
17
Electric Generation Rate Base.
18
For Category 2, handling tools and equipment, PG&E requests that the
19
Commission adopt its total-Company capital expenditures forecasts of
20
$164,000 for 2005, $561,000 for 2006, $594,000 for 2007, $547,000 for
21
2008 and $534,000 for 2009. PG&E’s 2007 expenditures forecast in the
22
amount of $594,000 for tools and equipment is 330.4 percent higher than
23
the 2004 recorded expenditure of $138,000. The allocation of these
24
forecasts to electric and gas distribution is discussed in Exhibit (PG&E-2),
25
Chapter 8, Electric, Gas and Common Plant.
26
For Category 3, direct capital salvage labor costs related to the
27
disposition and sale of PG&E’s surplus, obsolete or damaged equipment,
28
PG&E requests that the Commission adopt its total-Company capital
29
expenditures forecasts of $234,000 for 2005, $382,000 for 2006, $392,000
30
for 2007, $404,000 for 2008 and $418,000 for 2009. PG&E’s 2007
31
expenditures forecast in the amount of $392,000 for investment recovery is
32
14.3 percent higher than the 2004 recorded expenditure of $343,000. The
33
allocation of these forecasts to electric and gas distribution is discussed in
34
Exhibit (PG&E-2), Chapter 8, Electric, Gas and Common Plant. For
5-2
(PG&E-7)
1
Category 4, PG&E’s direct capital removal credits from the revenues
2
generated through the disposition and sale of PG&E’s surplus, obsolete or
3
damaged equipment are included in the depreciation chapter.
For Category 5, PG&E’s forecast for direct materials costs is included in
4
5
the expense and capital project forecasts of other programs and, therefore,
6
is not requested in this chapter. Direct materials costs are not part of the
7
M&S inventory rate base because they are issued and charged to capital
8
and expense projects.
For Category 6, PG&E’s forecast for materials handling costs is
9
10
included in the expense and capital forecasts of other programs as
11
materials burden and, therefore, is not requested in this chapter.
12
For Category 7, PG&E’s forecast for the repair and scrapping costs of
13
electric equipment is included in the expense forecasts of other programs
14
and, therefore, is not requested in this chapter. The allocation of this
15
forecast is discussed as major work categories (MWC) BG and BK in
16
Exhibit (PG&E-4), Chapter 2, Electric Distribution Maintenance.
For Category 8, PG&E’s forecast for operating costs related to the
17
18
handling of intra-company mail is included in the expense and capital
19
forecasts of other programs and, therefore, is not requested in this chapter.
20
The allocation of this forecast to other internal operating clients is based on
21
the amount of square footage occupied.
22
3. Support for Request
PG&E’s forecasts for M&S inventory, tools and equipment, and salvage
23
24
costs are reasonable and necessary because the Company:
25

Uses over $500 million worth of materials and supplies annually to
26
support its ongoing maintenance and construction activities to provide
27
safe, reliable service;
28

70,000 square mile service territory;
29
30
Manages a large supply chain distribution network throughout PG&E’s

Provides materials and supplies to the field organizations during
31
emergencies (e.g., storms, earthquakes, car pole accidents, major
32
mudslides, etc.);
5-3
(PG&E-7)
1

Establishes key supply chain metrics (e.g., order fill rate, inventory
2
turns, inventory count accuracy, returns rate, etc.) to measure operating
3
and financial performance and to drive improvements and cost savings;
4

Implements process improvement initiatives (e.g., reducing goods
5
receipt cycle time, enhancing internal controls, etc.) that increase
6
operational efficiency and inventory accuracy; and
7

Identifies and implements inventory reduction opportunities
8
(e.g., inactive inventory review, standardization of materials, vendor-
9
direct shipments to jobsites, etc.).
10
4. Organization of the Remainder of This Chapter
The remainder of this chapter is organized as follows:
11
12

Program Management Process;
13

Estimating Methods;
14

Costs by Major Activities;
15

Materials and Supplies Inventory; and
16

Cost Tables.
17
18
B. Program Management Process
The supply chain director and the immediate Materials Operations staff
19
manage all aspects of the organization including its expenditures. This
20
management team is responsible for the oversight of PG&E’s materials,
21
information, and finances as they move through the supply chain process. On a
22
monthly basis, the management team monitors the department’s year-to-date
23
expenditures to ensure consistent and rigorous accountability over costs and
24
spending. The Materials Operations staff regularly reviews anticipated materials
25
demand with the internal operating clients to establish appropriate inventory
26
levels, to adjust burden rates, and to improve mutual performance metrics.
27
28
C. Estimating Methods
In forecasting the M&S inventory under Category 1, the 2005 through 2007
29
forecasts are based on the 2004 recorded weighted average, which includes
30
adjustments for inactive inventory and unbilled receipts. Stock is considered
31
inactive if it has been in inventory for more than three years. Unbilled receipts
5-4
(PG&E-7)
1
are stock items that have been received from vendors, but have not been
2
invoiced to PG&E for payment.
3
In forecasting the capital expenditures needed for materials handling tools
4
and equipment under Category 2, MWC 05, Materials Operations evaluated the
5
condition and quantity of the equipment currently used in its operations and
6
determined whether it was necessary to repair or replace the existing equipment
7
or acquire additional equipment.
8
9
In forecasting the capital expenditures needed for direct salvage labor costs
related to the disposition and sale of PG&E’s equipment under Category 3,
10
Materials Operations evaluated the quantity of equipment that is expected to be
11
salvaged based on historical trends and the related resources needed to sell
12
and dispose of such equipment.
13
In forecasting the direct capital removal credits from the revenues generated
14
through the disposition and sale of PG&E’s equipment under Category 4,
15
Materials Operations evaluated the quantity of equipment that is expected to be
16
salvaged and compared the forecast with historical trends. As noted earlier,
17
Category 4 is referenced here for informational purposes only.
18
In forecasting the expenditures needed for managing and distributing M&S
19
inventory under Categories 5 and 6, the materials required for anticipated
20
maintenance and construction activities were estimated and compared with
21
historical labor costs of Materials Operations. As noted earlier, Categories 5
22
and 6 are referenced here for informational purposes only.
23
In forecasting the expenditures needed for repairing electric distribution
24
equipment under Category 7, the equipment required for anticipated
25
maintenance and construction activities was estimated and compared with
26
historical labor costs of Materials Operations. As noted earlier, Category 7 is
27
referenced here for informational purposes only.
28
In forecasting the operating costs needed to provide intra-company mail
29
services under Category 8, historical labor and contract and materials costs
30
associated with such services were used. As noted earlier, Category 8 is
31
referenced here for informational purposes only.
5-5
(PG&E-7)
1
2
3
D. Costs by Major Activities
1. Supply Chain – Materials Operations
Materials Operations has 348 employees located throughout the PG&E
4
service territory who are responsible for the day-to-day operation and
5
execution of the four core activities described below.
6
7
2. Warehouse Distribution
Through its warehouse distribution group, Materials Operations
8
manages and operates a network of three major distribution centers to fill
9
orders, manage inventory and returns, and deliver materials. These
10
distribution centers are strategically located in Fremont, Marysville, and
11
Fresno to deliver materials and supplies directly to PG&E’s field
12
organizations (including gas and electric distribution, information systems
13
technology services, metering services, gas transmission, electric
14
transmission, and electric generation). The three major distribution centers
15
occupy 54 acres of land and approximately 177,000 square feet of enclosed
16
storage space to receive, store, and issue PG&E’s inventory. In 2004, the
17
warehouse distribution group logged over 1.8 million miles to deliver
18
materials to the client organizations throughout PG&E’s service territory.
19
The warehouse distribution group is also responsible for maintaining
20
and overseeing PG&E’s Materials and Fleet Coordination Center (MFCC) in
21
Fremont to support and respond to major emergencies and catastrophic
22
events. The primary purpose of the MFCC is to operate as a 24/7 resource
23
during emergencies, to coordinate the delivery of materials, supplies,
24
equipment, vehicles, and to provide other logistical support as needed. The
25
warehouse distribution group prepares for storm seasons by adjusting
26
inventory levels in anticipation of spikes in demand for items commonly
27
used for service restoration. In addition, the warehouse distribution group
28
provides ongoing emergency training to its employees and participates in
29
companywide emergency drills and mandatory practice exercises.
30
Other services provided by the warehouse distribution group include
31
procuring fuel for all of PG&E’s service centers, substations and other
32
facilities. In 2004, the warehouse distribution group purchased nine million
33
gallons of fuel valued at $17.6 million. In addition, this functional group
5-6
(PG&E-7)
1
manages overnight deliveries of intra-company mail to 175 office locations,
2
covering approximately 680,000 miles per year.
3
As stated earlier, PG&E is not requesting in this chapter handling costs
4
under Categories (6) and (8) associated with warehouse distribution and
5
intra-company mail because such costs are included in the forecasts of
6
other programs. However, PG&E is requesting in this chapter that the
7
Commission adopt its 2005 through 2009 total-Company capital
8
expenditures forecasts for materials handling tools and equipment under
9
Category 2 needed to support warehouse distribution.
10
11
3. Materials Field Services
The materials field services group within Materials Operations provides
12
yard stock, on-site materials management, and other local supply chain
13
support to the internal operating clients at over 130 sites throughout PG&E’s
14
territory. These sites provide PG&E’s crews with immediate access to the
15
yard stock and materials needed to perform maintenance and construction
16
activities. The materials field services group is responsible for:
17
(1) replenishing and managing appropriate yard stock levels at these remote
18
locations; (2) receiving shipments from PG&E’s distribution centers and
19
suppliers; and (3) arranging the yard stock and materials for the crews.
20
Additionally, this group delivers materials directly to jobsites and supports
21
emergency power restoration efforts in coordination with the warehouse
22
distribution group.
23
As stated earlier, PG&E is not requesting in this chapter materials
24
handling costs under Category 6 associated with materials field services
25
because such costs are included in the forecasts of other programs.
26
However, in this chapter, PG&E is requesting that the Commission adopt its
27
2005 through 2009 total-Company capital expenditures forecasts for
28
materials handling tools and equipment under Category 2 needed to support
29
materials field services.
30
31
4. Electric Equipment Repair Services
Materials Operations operates an electric equipment repair and
32
refurbishment facility in Emeryville. This facility provides scheduled in-shop
33
inspection and cost-effective repair and refurbishment of electric distribution
5-7
(PG&E-7)
1
equipment, primarily transformers, regulators and reclosers. It also
2
performs scheduled and emergency field repairs of in-service electric
3
equipment. As part of its repair and refurbishment program, the Emeryville
4
facility engages in the disposition and salvage of outdated and damaged
5
electric equipment, which includes recycling waste oil. This group also
6
provides insulation testing of rubber goods (e.g., blankets, hoses, and
7
jumpers, etc.) and inventory management of the Company’s emergency
8
substation equipment.
9
Through its repair, refurbishment and recycling services, the Emeryville
10
facility has captured $9.9 million in 2003 and $8.1 million in 2004 in avoided
11
purchase costs for electric distribution equipment. Avoided purchase costs
12
are achieved by repairing or refurbishing existing equipment (when it is
13
economically feasible to do so) and placing the equipment back into service.
14
Through the use of recycled oil, PG&E is able to avoid the purchase of new
15
oil for its repaired or refurbished electric equipment. The duration of
16
outages can often be reduced by performing on-site repairs of electric
17
equipment rather than removing the defective unit and replacing it with new
18
equipment.
19
As stated earlier, PG&E is not requesting in this chapter repair and
20
scrapping costs under Category 7 associated with the Emeryville facility
21
because such costs are included in the forecasts of other programs.
22
However, in this chapter, PG&E is requesting that the Commission adopt its
23
2005 through 2009 total-Company capital expenditures forecasts for
24
materials handling tools and equipment under Category 2 needed to support
25
the Emeryville facility.
26
5. Materials Planning
27
The materials planning group provides the following four supply chain
28
services to the other functional groups within Materials Operations:
29
(1) inventory planning and management; (2) oversight of inbound and
30
outbound transportation logistics; (3) investment recovery of PG&E’s
31
surplus, obsolete or damaged assets; and (4) coordination of risk
32
management and compliance activities.
33
34
The inventory planners are responsible for forecasting inventory
requirements and collaborating with internal operating clients and PG&E’s
5-8
(PG&E-7)
1
vendors to minimize inventory levels while maintaining required service
2
levels. They also assist in controlling the cost of freight transportation by
3
managing most of the shipments from PG&E’s suppliers to ensure the
4
lowest possible rates.
The investment recovery specialists determine the best options for the
5
6
disposal of surplus, obsolete, or damaged materials and equipment.
7
Redeployment, sales, and recycling are used to maximize the return on
8
PG&E’s investment. These investment recovery efforts also demonstrate
9
PG&E’s commitment to environmental stewardship because they reduce the
10
Company’s use of local landfills. In 2004, PG&E recycled over 34 million
11
pounds of materials and equipment (including metals and plastics) and over
12
500,000 gallons of used mineral oil. The Company’s overall investment
13
recovery strategies in 2004 generated $10.6 million in credit to accumulated
14
depreciation.
The materials planning group also handles the risk management and
15
16
regulatory compliance activities of Materials Operations, including
17
Sarbanes-Oxley compliance, hazardous materials management, and
18
business process documentation and management.
As stated earlier, PG&E is not requesting in this chapter direct capital
19
20
removal credits and materials handling costs associated with the materials
21
planning group under Categories 4 and 6 because such costs and credits
22
are included in the forecasts of other programs. However, in this chapter,
23
PG&E is requesting that the Commission adopt its 2005 through 2009
24
total-Company capital expenditures forecasts for direct capital salvage labor
25
charges under Category 3 needed to support the materials planning group.
26
6. Special Projects
Materials Operations engages in process improvement initiatives to gain
27
28
operational efficiencies, improve service levels, and optimize PG&E’s
29
utilization of its assets. Materials Operations has been working on the
30
following key initiatives since 2004:
31
a.
32
Warehouse Operational Improvements Initiative
The purpose of the warehouse operational improvements initiative
33
is to increase the efficiency of PG&E’s materials management
34
processes by identifying and implementing operational improvements at
5-9
(PG&E-7)
1
its three main warehouses. These improvements will enable Materials
2
Operations to increase its service levels to the field organizations and
3
reduce operational and inventory costs at the distribution centers. The
4
initiative has resulted in increased inventory accuracy, shorter receiving
5
time, and improved supplier delivery performance. An updated
6
performance scorecard has been established for each warehouse,
7
which management reviews monthly.
8
b. Yard Stock Reduction Initiative
The purpose of the yard stock reduction initiative is to identify,
9
10
reduce (as appropriate), and improve the management of materials
11
staged for use at over 100 yards in the PG&E service territory. Over a
12
five-year period, PG&E estimates a $5 to $8 million reduction in yard
13
stock with any surplus either worked down through normal consumption
14
or returned to the distribution centers for re-stocking.
15
16
c.
Electric Equipment Repair to Stock Initiative
The purpose of the electric equipment repair to stock initiative is to
17
consolidate stock management of regulators and reclosers in order to
18
create systemwide visibility of these assets and to capture potential cost
19
savings. By monitoring and controlling stocking levels centrally in the
20
materials planning group, Materials Operations can ensure that there
21
are optimal numbers of regulators and reclosers available to meet
22
ongoing needs for new installations, scheduled replacements, and
23
emergency response. Over the next two years, PG&E estimates that
24
$1.5 million worth of regulators and reclosers will be worked down
25
through normal consumption or returned to the distribution centers for
26
re-stocking.
27
28
7. MWC 05—Capital Tools and Equipment
The 2005 through 2009 capital expenditures forecasts under
29
Category 2, MWC 05, to support Materials Operations is based on PG&E’s
30
evaluation of existing tools and equipment as described in Section C of this
31
chapter. PG&E is requesting that the Commission adopt its total-capital
32
expenditures forecasts to:
5-10
(PG&E-7)
1

and materials field services;
2
3
Ensure that tools and equipment are available for warehouse operations

Ensure that specialized tools are available to install, test, repair or
remove electric distribution equipment;
4
5

Ensure safety and productivity within Materials Operations; and
6

Replace defective, worn out or obsolete tools and equipment, including
7
those that pose safety or ergonomic risks.
8
Tools and equipment that are commonly used by Materials Operations
9
include, but are not limited to, wrapping and strapping machines, electric
10
testing equipment, materials storage racking, and handling equipment.
11
Departmental policy requires that all major tools and equipment purchases
12
are subject to the supply chain director’s pre-approval. Each purchase
13
request to the supply chain director contains a cost/benefit analysis that
14
includes safety considerations and the availability of other cost-effective
15
options (e.g., sharing, repairing, leasing or substituting).
16
17
E. Materials and Supplies Inventory
As discussed earlier in this chapter, M&S inventory is positioned throughout
18
PG&E’s service territory to support maintenance and construction activities.
19
M&S inventory is necessary to support new business, planned and unplanned
20
maintenance, required upgrades to facilities, new business capacity projects,
21
and emergency response.
22
Materials Operations has established guidelines and procedures for the
23
ongoing replenishment and management of M&S inventory to ensure the lowest
24
total cost of ownership. The Company’s practices for managing M&S inventory
25
include, but are not limited to:
26
Maintaining an effective materials distribution system;
27
Monitoring materials warehouse performance through the use of metrics and
28
29
30
31
32
industry benchmarks;
Performing periodic audits (e.g., wall-to-wall inventories and compliance
reviews, etc.) to ensure optimal inventory management;
Performing quarterly Sarbanes-Oxley testing to ensure that effective internal key
controls are in place;
5-11
(PG&E-7)
1
2
Managing inventory levels through the use of forecasting tools, replenishment
guidelines and performance metrics;
3
Managing surplus and inactive materials and supplies; and
4
Sustaining an integrated warehouse management system.
5
6
F. Cost Tables
The capital expenditures and operating costs estimates for Materials
7
Operations are summarized in the following tables:
8
Table 5-1 summarizes total capital expenditures for MWC 05 under Categories
9
2 and 3 for recorded year 2004 and forecast years 2005 through 2009;
10
Table 5-2 summarizes the weighted average balances of active M&S inventory
11
under Category 1 for recorded year 2004 and forecast years 2005 through
12
2007 for electric and gas distribution.
5-12