Method Statement: Foundations and ground bearing slab Project Ref: P4 - 02 Rev No: A th Date: 6 November 2012 CONTRACT: Willmott Dixon – The Bay, Sandown, Isle of Wight 1. Details 1.1 Setting out, excavation, formation of foundations and slab 2. Sequence of operations: 2.1 Site induction undertaken by WMD 2.2 Setting out engineer will set out grid lines and levels under supervision of the site supervisor 2.3 The area of the works will be segregated with signage and heras fencing to create a working zone 2.4 Excavation of the foundation / slab will be carried out by machine excavators to the required depth not, 300mm 2.5 Formwork will be constructed to the beams and slab edges using ply and hand held tools 2.6 The steel reinforcement will be delivered by flatbed lorry and mechanically lifted into position by the use of lifting chains and under supervision of the banksman 2.7 The steel will be tied by hand and checked for accuracy by our engineer 2.8 Mushroom caps will be placed over exposed steel 2.9 A concrete pump permit will be completed and signed 2.10 The pump lorry will reverse under supervision of the banksman to the works area and set up in accordance with the manufacturer’s instructions 2.11 The outriggers of the pump will be supported on railway sleepers 1.2m long x 1.2m wide 2.12 The pump operator will move the boom into position with the operative located at the end to move the pipe to the desired location 2.13 The foundations / slab will be poured, all exposed steels will have mushroom caps 2.14 The formwork to the foundations / slab will be struck after is has cured in accordance with the engineers guidelines 2.15 A concrete washout area will be agreed and constructed 2.16 A jet wash will be available at the site entrance for wheel washing 2.17 The pump will be cleaned out by the use of a pig and ball, the ball is put on the end of the hose and sucked back by vacuum into the recess at the rear of the shute. 3. Duration: 3.1 In accordance with the master programme 4. Preparation: 4.1 A CAT and genie survey of the area will be carried out prior to starting and hand digging 4.2 The service avoidance plan will be available 5. Access: 5.1 Access to the site is via the main entrance Page 1trial of 3version www.pdffactory.com PDF created with pdfFactory Method Statement: Foundations and ground bearing slab Project Ref: P4 - 02 Rev No: A th Date: 6 November 2012 CONTRACT: Willmott Dixon – The Bay, Sandown, Isle of Wight 6. Permit to dig: 6.1 A permit to dig is required 6.2 A permit to pump concrete is required 6.3 The site supervisor will enforce the permit 6.4 Completed permits will be retained at the site office and copies will be forwarded to the head office by WDC 7. Supervision & Operatives: 7.1 The site supervisor will supervise all excavations 7.2 The Site supervisor holds a current SSSTS certificate 7.3 Supervisor plus 6 operatives including banksman and pump operator 8. Training: 8.1 All operatives hold a current CSCS or CPCS cards and will have them on them at all times 9. Plant: 9.1 Excavator and concrete pump – test certificate will be made available by the driver 9.2 Roller – test certificate will be made available by the driver 9.3 Dumpers – test certificate will be made available by the drive 10. PPE: 10.1 10.2 10.3 Hard hat, Hi-viz, safety boots and gloves must be worn at all times Wellington boots will be used if in contact with concrete Key fobs will be used by all plant operators 11. Risk assessments: 11.1 COSHH concrete 11.2 Manual handling 11.3 Heavy Plant 11.4 Buried services 11.5 Reversing lorries 11.6 Manual handling limit of 20kg per operative will be in operation 12. Waste: 12.1 All waste will be treated in accordance with the site waste management plan 13. Control measures: 13.1 Fire extinguishers are located as per the fire plan 13.2 In the event of an emergency the site supervisor will contact the emergency services in accordance with WDC emergency plan 13.3 Permits to dig Page 2trial of 3version www.pdffactory.com PDF created with pdfFactory Method Statement: Foundations and ground bearing slab Project Ref: P4 - 02 Rev No: A th Date: 6 November 2012 CONTRACT: Willmott Dixon – The Bay, Sandown, Isle of Wight Prepared by Position Date Nick Fairweather Project Surveyor 19/06/12 Checked by John Peck Position Date Director 19/06/12 Approved WMD I confirm that I have received a site induction by the main contractor, read the above method statement and fully understand safe methods of work and agree to carry out the work in accordance with the procedure stated. Name Company Page 3trial of 3version www.pdffactory.com PDF created with pdfFactory Date Signed