Case Study AC-C-022
Engineering Design & Consultancy
The Challenge
To remove an offshore carousel from its
barge following significant in situ
modifications which increased the mass,
diameter and height of the originally installed
structure.
The Solution
Key Facts:
Contract No: AC-C-022
Client: Technip Offshore Wind Ltd
Duration: 4 Months
Completion: Dec 2012
Location: North East England
Scale: 16m Diameter, 280 Tonne Lift
Design Codes: Noble Denton and DNV
Understand the revised geometry and level of load share
between the existing lift points and access the feasibility of reusing one or more of these in combination with additional lift
points.
The Work Scope
•
•
•
•
•
Equipment Survey
Feasibility Studies
Structural Analysis
Detail Design & Draughting
Manufacturing Support
Implementation
Following structural analysis and verification of the proposed
lifting arrangement a new lifting point was designed into the
existing carousel structure, allowing a cost effective three
point lift.
Vessel: UR101
The Outcome
How can we assist you?
The successful, safe and cost effective removal of a 280 tonne
carousel.
Have you any requirements for
analysis of existing structures?
We can support with equipment
surveys and 3D modelling of in-situ
equipment followed by analysis and
design modifications to incorporate
new project requirements or
facilitate decommissioning.
Contact our team for further
details.
Ardmore Craig Ltd
Office F32, Evans Business Incubation Centre
Durham Way South, Aycliffe Business Park
Newton Aycliffe, DL5 6XP
Tel: 01325 329880
Email: enquiries@ardmorecraig.com
Website: www.ardmorecraig.com
Download