JAIP-substation-civil estimate

advertisement
ITB-2013-216
DESCRIPTION
ITEM
1.00
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
Unit
BoQ Revised on 8/14/2013
QTY Unit price $
Earthworks, Excavation, Backfilling and Site Works.
Site excavation for the entire sub-station site area (about 24X22
M2) down to a level below the building and boundary wall footings at
-3.5 . Price to include removal of excavated soil, debris, and organic
1.01
materials to an adjacent low area. Bidders are encouraged to visit
the site and become aware of the existing topography and nature of
the site.
Supply, spread and compact 20cm layers of imported approved
base course material , watered and compacted to 100% according
1.02 to modified AASHTO Density Test. Price includes cost of the
necessary testing; all as per drawings, specifications and the
Engineer's instruction.
LS
1
M3
1900
M3
25
M2
220
Total Earthworks, Excavation, Backfilling and Site Works
2.00
Concrete Works:
The price of concrete works shall include:
1.
All form works and shuttering in any form, shape and size. Making
chamfered and curved edges, allowing for and making grooves and
sleeves and the like; removal of forms and cleaning of all exposed
tie wires and rods; making good the harmed surfaces..;all as per
drawings, specifications and the Engineer's instruction and approval.
2. Supplying, casting, vibrating and curing as per specifications.
3. Approved additives and admixtures.
4. cost of concrete testing including 15cmX15cm concrete cubes.
(B300 should have 30 Newton/mm2 after 28 days)
5. Incurred costs on Concrete Mix Designs, Sample taking, testing
and providing test results certificates, storing and saving of
samples, and preparation of bar bending schedules and workshops.
6. Supplying and fixing of steel reinforcement of any size and
lengths as detailed in the drawings, storing on site including cutting,
bending and fixing in position and providing all tying wires, spacers,
shop drawings, testing and bar bending schedules
7. Painting of exposed surfaces of underground reinforced concrete
elements with two coats of approved Bituminous Emulsion, supply
and lay of polyethylene sheets under slabs on grade,3 mm thick.
8. Steel bars used for alignment and fixing of reinforcement works,
and extra steel added to assure proper detailing and safety.
9. Measurement of concrete elements shall be the net dimensions
as detailed in the drawings. All recesses, openings and voids shall
be deducted.
2.01
Supply and cast plain concrete; B200 blinding concrete 10cm thick
under foundations, ground beams., transformer concrete base ..etc
Supply and cast concrete grade 'B 300'. for 12 cm thick slab on
hard core, Including surface leveling, smooth finishing, epoxy
hardeners, polyethylene sheets 3mm thick, construction joints and
2.02 all related works. Price shall include cost of supplying and fixing
the required steel angles for the electrical trenches, as well as, the
required steel reinforcement for the slab on grade of 8 mm dia @
20cm distances in both directions.
UNDP-PAPP
1 of 14
Total amount $
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
DESCRIPTION
ITEM
Supply and cast concrete grade 'B 300' for footings of the building
and the boundary walls. Price includes cost for supply and
2.03
workmanship of the required steel reinforcement, as per drawings
and engineer's instructions
Ditto, but for columns necks and columns.
BoQ Revised on 8/14/2013
Unit
QTY Unit price $
M3
110
M3
6
Ditto, but for ground beams including projections to support the
2.05
stone cladding
M3
6
2.06
Ditto, but for the reinforced walls under and above the level of slab
on grade of the building, the transformers and trenches, and where
required as per the Engineer's instructions.
M3
80
2.07
Ditto, but for walls of the boundary walls walls including the required
steel reinforcement as in the above bill item.
M3
80
2.04
Supply and cast concrete grade 'B 300' for suspended ribbed slabs
.Price to include projected beams, other beams and projections,
supply, lay and arrange hollow concrete blocks 'Grade 35' for ribbed
2.08 slabs, using closed end blocks at all ends, edges, openings,
M.S.
services location etc, as per drawings. Price shall also include cost
of supply and fixing the required steel reinforcement as per
drawings.
2.09
Ditto, but for the suspended cantilevered solid slab for trenches.
Total for Concrete Works
UNDP-PAPP
2 of 14
M.S
110
20
Total amount $
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
DESCRIPTION
ITEM
3.00
3.01
3.02
3.03
3.04
BoQ Revised on 8/14/2013
Unit
QTY Unit price $
M.S
220
M.R
44
MR
18
MR
40
Stone Works
Supply and build stone walls Njassa minimum 5cm stone or
equivalent to the full length and height, as shown in the
drawings(Mattabah stone dressing). First grade first class white
stone uniform in color and texture and first quality, rough textured
for facades with 25cm thick plain concrete (B-250) for stone
backing. Price to include all required stone pieces such as stone
corners, lanterns, jambs and for doors and windows and stone
pointing with 2:1 cement sand mortar. Price shall include cost of 4
" UPVC pipes and two 20X 20cm rigid plastic roof drains ,READY
type, including the required boxes, smoothing of surface around the
drains, and all necessary fitting and accessories for rain water
drainage, all as per drawings, specifications and the Engineer's
instructions.
Supply and install 5cm thick stone copping for the roof parapet
Supply and build 3cm thick local marble for windows sills and doors
thresholds
Supply and build 4cm thick and 35 cm wide stone cladding, polished
from one face . The stone shall be first grade Njasa or equivalent
uniform in color. Price shall include cost of fixing the stone to the
walls by steel anchorage at maximum distance 50cm, fixing mortar
and all associated cost as per drawings and the Engineer's
approval. Samples of stone shall be provided for the Engineer's
approval.
Total for Stone Works.
4.00
Plastering
Prepare surfaces, apply 13mm thick plaster on walls composed of
two coats of cement sand plaster (rough and fine finish) over 1:2
sand cement splashing coat. The price includes angles beads, wire
mesh on all kinds of joints especially electro-mechanical.
4.01
Internal plaster :Two coats of cement : sand plaster over one 1:2
cement sand slurry coat, to walls and ceilings and where required.
M.S.
400
4.02
Ditto, but external plastering, price includes waterproofing additive
M.S.
and "Shepretz" finished coat with white cement.
600
Total for Plastering works
5.00
Painting Works
5.01
Supply and paint three coats polycide paint for ceilings and drop
beams(sides and bottom) of high quality. Samples of painting shall
be provided for the Engineer selections and approvals.
Supply and paint high quality emulsion paint, for walls as per
indicated in finishing tables, on one priming coat and two finishing
5.02 coats, using two coats of complete putty, as per satisfaction of the
supervisor engineer. Samples of painting shall be provided for the
Engineer selections and approvals.
Total for Painting Works
UNDP-PAPP
3 of 14
M.S
120
M.S
170
Total amount $
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
DESCRIPTION
ITEM
6.00
Unit
BoQ Revised on 8/14/2013
QTY Unit price $
Metallic Works
Metallic fencing for boundary walls: Price shall include the
following: a-supply and install 2 " galvanized steel pipes 230 cm
length at 200 cm spacing, including inclined pipes of same
diameters at 800 cm, which should be fixed in concrete 30cm deep
including V shaped branches 50cm high inclined at 45 degree at
both directions'- Supply and install 2.8 mm galvanized diagonal
6.01
M.S.
mesh fence 50X50 cm including 4mm tie wires at 70 cm distance
canter to center. c- supply and install circular razor blade wires
60cm diameter to be install on top of the fence and supported by V
pipes. d- supply and 10 cm thick concrete for fixing the fence with
the wall, all as per the drawings and the Engineer's instructions and
approvals.
Metal gate for the substation: Supply and install iron gate
"Fassoun" of cross section 1.25 " with rubber. The gate panels
shall have two metal sheets 1.50 mm thick on both faces of the door
6.02 panel. The price shall include cost of the galvanized metal frame 2
mm thick, handles, hinges, steel protection, painting with oil paint
three coats; all as per the drawings, specification and Engineer's
instruction.
200
6.02a As above, single door 100* 260 cm
No
1
6.02b As above, but double door 250 * 375 cm, as per drawings.
No
1
Sliding metal gate for the external yard: Supply and install
sliding iron gate dimensions as per drawings. Price includes cost of
1.25 inch metal profile and rubber , 1.5mm thick metal sheets on
both sides of the leafs, 2cm galvanized metal frame, hinges,
6.02c fasteners, and all associated costs, reinforced concrete beam
bellow the gate. Price shall also include cost of painting with oil
paint three coats and primer, the color of paints shall be as selected
and approved by the Engineer. The contractor shall provide shop
drawings for the engineer's approval.
No
2
Supply and install protection steel grills for windows. Price to
include fixation, accessories, welding, grinding & smoothen, oil
6.0d1
painting three coats; all as per the drawings, specification and
Engineer's instruction. Dimensions 200*105 cm
No
6
As above, but with 4 mm diameter 3*3 cm steel protection
mesh for the opening dimensions 200*105 cm, including fixation of
6.0d2 4mm thick and 2cm wide metal strip in the middle. Price includes
cost of frame, all as per the drawings, specification and Engineer's
instruction.
No
6
No
6
Total for Metallic Works
7.00
Aluminum Works:
7.h
Supply and fix 3 tracks aluminum sliding windows equal to 7700 of
profile section not less than10.2*5.8cm. And 4400 for pivot
windows profile # 910 and for the doors 2000. Price shall include
cost of glass( 6mm thick glass for windows above than 1.4m2 and
4 mm thick glass for windows less than 1.5m2) fiber glass insects
mesh, fixing, accessories, cylindrical locks handles and special
ground jacks, water drains, air valves..etc. Window dimension 200*
105 cm.
Total for Aluminum Works
8.00
Transformer base and trenches works
UNDP-PAPP
4 of 14
Total amount $
ITB-2013-216
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
DESCRIPTION
ITEM
Unit
Supply and install galvanized steel mesh, heat resisting, bellow
stone gravels for the transformers. Price includes cost of the
8.01
external frame for fixation and all associated axially material as per
drawings and the Engineer's instructions.
8.02
Supply and spread smooth stone gravels( Alwadi aggregate) , the
aggregate size should not be more than 10cm; all as per the
Engine's instruction and approvals.
Supply and install iron profile # I-section-IPE200 of 400cm length for
the transformers channels . Price includes three coats of oil paint
8.03 and primers and all associated costs including welding, fixing of the
channels, as per drawings, specifications and the Engineer's
instruction and approvals.
8.04
Supply and install chequerd metal covers 4mm thick of dimension
60*80 cm, including frames L shape, steel angels,..etc, all as per
the Engineer's instruction and approvals.
Total for Transformer Base and Trenches Works
UNDP-PAPP
5 of 14
BoQ Revised on 8/14/2013
QTY Unit price $
M2
25
M3
8
No
4
No
30
Total amount $
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
DESCRIPTION
BoQ Revised on 8/14/2013
Unit
QTY Unit price $
.MS
108
Supply and apply of an approved type waterproofing membrane of
bitumen rolls, 4.5 mm thick, (of density 180g per m.s. of reinforced
polyester sheets) covered with layer of crushed white stone with
9.02 overlaps of not less than 15 cm. price to include primer coat at rate .M.S
off application 1/2 kg/m2, and all sheets flashing, treatment of the
joint at the roof drains and angles by special water proofing material
such as Sika Flex or equal.
108
ITEM
9.00
Insulation Works:
Supply and cast B300 concrete screed on the roof, with 1.5 slope
cast to falls not less than 5cm thickness in the drain point. Price
shall include cost of hunching 15x15 cm with (45˚) to the edge of
9.01 roof screed and parapet, include smooth surface finish to receive
bitumen and all requirements; all as per specifications, drawings
and .Engineer's instructions. the insulation work shall be measured
horizontally as per the roof plan.
Total for Insulation Works
10.00 Trenches works
10.10 Covers to internal the trenches
Supply and install metallic chequerd plate covers 4 mm thick as.
per, drawings and specification. Price includes fixing on L shaped
.steel angels, welding, and painting with 3coats of approved oil paint
Price in also include fixing of U channel in the smooth concrete
slab (the U channels will be .provided, by the E electric Company
and supervised by the engineer form the electric company and as
..per the attached detail
10.1a As above, dimensions 80*60cm
No
25
No
6
Supply and install 6" PVC pipes between trenches and filing around
10.1b the pipe by 20cm sand encasement, including the required sleeves
in the trenches walls.
Total for Trenches Works
External Works-Asphalt: Supply , spread and pave 6cm asphalt
layer( after compaction) for yards and wherever needed as per
drawings and specifications. Price includes applying the primer,
excavation for site leveling from the natural ground levels to the
11.00 required level, supply and compact 20cm base course layer to min MS.
95% according to modified AASHTO Density and all associated
works including cost of performing the necessary tests for the for
completing the works in accordance with the drawings and
engineer's instructions.
Total for External-Asphalt Works
UNDP-PAPP
6 of 14
300
Total amount $
ITB-2013-216
DESCRIPTION
ITEM
12
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
Unit
Electrical and Communication Works
Preamble:
*
The contractor shall, when pricing the rates of the following
electrical bills take into consideration including and allow for the
cost expenses of all requirements stipulated in the preambles,
drawings and technical specifications of the tender.
*
All Supplied Materials Should be class A , new , not used and Free
From any Defects, Having the Supervisor approval Certificate .
*
The contractor's total price for works shall include the supply,
execution, completion and testing of the whole of electrical
installation works and related systems in accordance with the
drawings, bill of quantities and specifications.
*
the rates includes connection to existing system were applicable
and or adjustment of non removed or cancelled network to allow for
new networks or system .
*
The contractor shall coordinate his works with the decoration works,
furniture, changes in the positioning of ceiling light fixtures due to
partitioning changes and any other changes which require design
changes on the tender drawings.
*
The contractor must consider all these changes in the shop
drawings which must be submitted and approved before
commencement of works.
*
Plates, labels and tags for the identification of plant, equipment,
cables, switches ,sockets and the like.
*
the unit rate including for Forming or cutting holes, chases,
channels etc. in reinforced concrete structures and block works
*
*
Jointing, saddles, clamps, brackets, hangers and providing steel
pipes sleeves with plates.
All electrical and low voltage conduits for all different items in the
main B.O.Q. installed above false ceiling level must be colored, fire
proof and first class taken quality for all main and sub main feeders
circuitsNetc.
*
The contractor must consider keeping the system running where
needed during the whole construction period.
*
The contractor's rate must include the supply and install internal sea
sand plastering for the electrical conduits on wall . composed of two
coats base coat ,finish coat . The rate includes all necessary
patching works ,expanded metal latch mesh , plastering layers must
be applied to meet plastering thickness
*
The contractor shall submit all samples needed for all electrical and
low voltage points, fittings , accessories and fixtures and to take the
approval from the supervision engineer before starting works.
*
The contractor shall submit a time schedule for all the works
showing start and end dates for each item in B.O.Q..
*
the contractor should have his electrical engineer available in a daily
bases and on call to arrange with the Consultant representative
engineer on site and for all written communications and works
UNDP-PAPP
7 of 14
BoQ Revised on 8/14/2013
QTY Unit price $
Total amount $
ITB-2013-216
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITEM
DESCRIPTION
*
All electrical conduits under tiles, floor, wall should be protected by
cement mortar or concrete layer and all electrical excavation works
should be removed from site as specified in the technical
specification and drawings.
*
Making holes by hilti for all holes size where required including all
necessary water proofing material ( Sikaflex).for any kind of
electrical and low voltages works.
*
The above mentioned shop drawings, electrical switchboards shop
drawings, as built drawings and all other required detailed drawings
are to be included in the rates for no additional cost.
12.1
Unit
BoQ Revised on 8/14/2013
QTY Unit price $
Earthing system
Furnishing, connection and installation complete earthing system
including all required materials, cables, conduits, wires, electrodes,
strips and connectorsmanholes and covers, including also all
required excavation and covering all to get the required earthing
resistance not more than one ohm, all according to drawings,
specifications and Engineer instructions.
a.
Earthing system for Distribution Boards
LS
1
b.
Earthing system for low current systems
LS
1
Total of Earthing System Carried to Summary Sheet
UNDP-PAPP
8 of 14
Total amount $
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
DESCRIPTION
ITEM
12.2
Unit
BoQ Revised on 8/14/2013
QTY Unit price $
Electrical Distribution Boards:
*
Supply of electrical switchboard to site including all associated
materials and labor, as described in the technical specifications
and drawings. Cabinets with no access from the rear , made up
of Galvanized 2mm sheet metal cabinets with 25% surplus space.
Price to include all MCCB's,MCB's type Moller or equal approved,
structural elements required in order to install the switchboard
including all bus bars , terminals , wiring , bolts , clamps, master
keys for all different panels doors, measuring instruments, all
required conduits and manholes etc. and for the equipments as per
dwg specification and Eng. Instructions.
a.
MDB
Unit
1
b.
LVB
Unit
1
Total of Electrical Distribution Boards Carried to Summary
Sheet
12.3
Installation in the Building Points
Furnishing and installation of wall, ceiling or false ceiling mounted
lighting point normal, waterproof, emergency or exit (Price includes
16mm diameter conduit , 3x1.5 mm2 cross section wire or cable ,all
12.3.1 required swiches or push bottoms, ceiling box and phase line for
emergency lighting point , with 60 W lighting bulb and leading from
the switch panel to the point including any needed boxes or
accessories).
a.
Internal Lighting point
No.
10
b.
External lighting point
No.
6
Furnishing and Installation of Standard 1 ph socket outlet point
normal (Price includes 16mm dia. conduits , 3x2.5mm2 wire OR
CABLES , with 16A socket Gewiss Type or equivalent including
12.3.2
switch and sign lamp, Boxes, Supports & Plates and leading from
the switch panel to the point , including all accessories) all
according to specification, drawings and Eng. Instructions
12.3.3 Sockets and Feeding Points
a.
1 phase socket
No.
4
b.
Ditto but Double socket
No.
4
c
Sockets for chargers
No.
2
Telephone connection point wall or table mounted (Price includes
16mm diameter conduits Nacy , hadash plast type or equivalent,
with 4 pairs computer cable shielded type CAT7 , telephone socket
12.3.4
Legrand Type Arteor Model with Brilliant White Finish Color or
equivalent, Including Boxes, Supports & Plates and leading from
point to the COMPUTER HUB).
No.
2
Computer outlet connection point wall or table mounted (The price
includes 16mm2 conduits with 4 pairs computer cable shielded type
CAT6A and leading from the telephone communication cabinet or
11.3.5
computer HUB to the points as well an outlet with a plastic socket
GEWISS Top System GW20243 type or Biticino, Legrand or
equivalent including Boxes, Supports & Plates and all accessories).
No.
4
Total of Installation Works Carried to Summary Sheet
UNDP-PAPP
9 of 14
Total amount $
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
DESCRIPTION
ITEM
12.4
Unit
BoQ Revised on 8/14/2013
QTY Unit price $
Lighting Fixtures and Accessories
Note: work for lighting fixtures is to include supply of the fixtures
specified, installation of same connection, wiring, commissioning,
lamps OSRAM type, tubes, starters louvers, connections,
suspension, clamps and all other accessories necessary to provide
a complete fitting with all terminals and rates also includes all L,Z
and omega profiles if needed , great opening for lighting fixtures in
gypsum board and all other details , as specified in the technical
specifications and drawings and as approved by the engineer.
a.
Type (K)2x55w light fixture with parabolic louver .
Unit
6
b.
Type (KE) Ditto but with emergency battery charger 3 hours
duration or equivalent.
Unit
2
c.
Type (X2) Projector unit with (250) Metal Halide with aluminum
body, includes water proof connection box (10x10)cm. Wall
mounted weather proof type. IP65 include boxes , switches and
(3x2.5 )wire and (3/4") pipes as detailed on drawings
Unit
6
Total of Lighting Fixtures and Accessories Carried to Summary
Sheet
12.5
Cables & Conductors / Leads
Supply, install, test and connect the following electrical cables ,
including conduits, trunks, manholes, complete ready for work,
including insertion into conduit or attachment to structural elements
or laying in ductwork, including all associated materials, insulation
materials, unions, labeling and connection of cable at both ends and
all accessories).
a.
3x25+16 sq.mm +16mm2 CU cross section XLPE/PVC/PVC cable.
M.L.
50
b.
5x6 sq.mm cross section N2XY cable.
M.L.
50
Total of Cables & Conductors Works Carried to Summary Sheet
12.6
Fire Alarm System
Supply install and connect fire alarm addressable system
including of the equipment specified, installation of same
connection, wiring commissioning and all of the details as specified
in the technical specifications and drawing with complete operation
capacity.
a.
Fire alarm control panel, 1 loop, expandable, , and 230V, gray.
No.
1
b.
Analogue addressable photoelectric smoke detector.V-PS
No.
4
c
Analogue addressable heat detector.V-HRD
No.
2
d
Analogue manual call break glass station.GSA-M270
No.
2
e
Indoor fire siren.G1RF-P
No.
1
f
Fire alarm outdoor siren with strobe.757-7A-T
No.
1
g
Automatic telephone dialerDL-125C
No.
1
Total of Fire Alarm System Works Carried to Summary Sheet
UNDP-PAPP
10 of 14
Total amount $
ITB-2013-216
DESCRIPTION
ITEM
12.7
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
Unit
BoQ Revised on 8/14/2013
QTY Unit price $
CCTV System
Supply , install and connect the CCTV System type
(DAY)(PROVISIONAL NIGHT) including (Port 8) and 6 External
Cameras IP 65 Night light all according to drawings and
specifications, the price also includes all required outlet boxes ,
cover plates, and all necessary connections , complete with
operation, soft ware to connect the system with the computer
network and JEDCO offices, (DVR CARD) and connection with the
Data center, testing and commissioning works as shown on the
drawings and as per specifications. The CCTV System shall
include also all required instruments and equipments and CARDS ,
complete ready for work all according to Specification and Eng.
requirements.
LS
1
Total of CCTV System Works Carried to Summary Sheet
12.8
Fire Fighting System
Supply install and connect complete in place and in an operable
manner the Fire Fighting system (F200) For main distribution board
. The work is to include the supply of the equipment specified,
installation of same connection, wiring commissioning and all of the
details .
a.
Automatic Valve Cylinder 200 KG Kidde FM 200 180 Degree
Pendant Nozzle , 3/8" Check Valves , Bracket , Pressure Gauge ,
Copper pipe , Safe Cap N...with all accessories needed )
No
1
b.
Main Control Panel 4- Zone Telefire 2-B or equivalent
No
1
c
Photoelectric Smoke Detector MIR-338H / TFO-440 or equivalent
No
2
d
Heat detector - S.S 5601 P / TFH-220F or equivalent
No
2
e
Indication lamp TFL-1N or equivalent
No
2
f
Break glass unit TPB-10 R or equivalent
No
1
d
Fire Indoor Horn TIP-224A or equivalent
No
1
e
Supply and install portable fire extinguishers "BFARYA" LAHAVOUT
or equal. The extinguishers shall be of dry powder 6 kg with
hangers and shall be valid for three years form the date of signing
the Contract.
No
4
Total of Fire Fighting System Works Carried to Summary Sheet
UNDP-PAPP
11 of 14
Total amount $
ITB-2013-216
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
BoQ Revised on 8/14/2013
Civil Works Summary
Bill No.
Description
1
Total Earthworks, Excavation, Backfilling and Site Works
2
Total for Concrete Works
3
Total for Stone Works.
4
Total for Plastering works
5
Total for Painting Works
6
Total for Metallic Works
7
Total for Aluminum Works
8
Total for Transformer Base and Trenches Works
9
Total for Insulation Works
10
Total for Trenches Works
11
Total for External-Asphalt Works
Total for Civil Works carried to grand summary
UNDP-PAPP
12 of 14
Total US$
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
BoQ Revised on 8/14/2013
Electrical Works Summary
Bill No.
Description
1
Total of Earthing system.
2
Total of Electrical Distribution Boards .
3
Total of Installation Works .
4
Total of Lighting Fixtures and Accessories.
5
Total of Cables & Conductors Works .
6
Total of Fire Alarm System Works
7
Total of CCTV System Works
8
Total of Total of Fire Fighting System Works
Total for Electrical Works carried to grand summary
UNDP-PAPP
13 of 14
Total US$
JAIP Electric Sub-Station - Jericho
Contruction of the Transformers House
ITB-2013-216
BoQ Revised on 8/14/2013
Grand Summary
Bills
Description
Amount $
1
Total for Civil Works
2
Total for Electrical Works
Grand total
Discount percentage (if any) :
Discount amount:
Net Grand Total Total Excluding Value Added Tax (VAT): :
Grand Net Total in Words:
Name of the Contractor:
Address:
Authorized person Name :
Signature & Stamp :
Date:
UNDP-PAPP
14 of 14
Download