ITB-2013-216 DESCRIPTION ITEM 1.00 JAIP Electric Sub-Station - Jericho Contruction of the Transformers House Unit BoQ Revised on 8/14/2013 QTY Unit price $ Earthworks, Excavation, Backfilling and Site Works. Site excavation for the entire sub-station site area (about 24X22 M2) down to a level below the building and boundary wall footings at -3.5 . Price to include removal of excavated soil, debris, and organic 1.01 materials to an adjacent low area. Bidders are encouraged to visit the site and become aware of the existing topography and nature of the site. Supply, spread and compact 20cm layers of imported approved base course material , watered and compacted to 100% according 1.02 to modified AASHTO Density Test. Price includes cost of the necessary testing; all as per drawings, specifications and the Engineer's instruction. LS 1 M3 1900 M3 25 M2 220 Total Earthworks, Excavation, Backfilling and Site Works 2.00 Concrete Works: The price of concrete works shall include: 1. All form works and shuttering in any form, shape and size. Making chamfered and curved edges, allowing for and making grooves and sleeves and the like; removal of forms and cleaning of all exposed tie wires and rods; making good the harmed surfaces..;all as per drawings, specifications and the Engineer's instruction and approval. 2. Supplying, casting, vibrating and curing as per specifications. 3. Approved additives and admixtures. 4. cost of concrete testing including 15cmX15cm concrete cubes. (B300 should have 30 Newton/mm2 after 28 days) 5. Incurred costs on Concrete Mix Designs, Sample taking, testing and providing test results certificates, storing and saving of samples, and preparation of bar bending schedules and workshops. 6. Supplying and fixing of steel reinforcement of any size and lengths as detailed in the drawings, storing on site including cutting, bending and fixing in position and providing all tying wires, spacers, shop drawings, testing and bar bending schedules 7. Painting of exposed surfaces of underground reinforced concrete elements with two coats of approved Bituminous Emulsion, supply and lay of polyethylene sheets under slabs on grade,3 mm thick. 8. Steel bars used for alignment and fixing of reinforcement works, and extra steel added to assure proper detailing and safety. 9. Measurement of concrete elements shall be the net dimensions as detailed in the drawings. All recesses, openings and voids shall be deducted. 2.01 Supply and cast plain concrete; B200 blinding concrete 10cm thick under foundations, ground beams., transformer concrete base ..etc Supply and cast concrete grade 'B 300'. for 12 cm thick slab on hard core, Including surface leveling, smooth finishing, epoxy hardeners, polyethylene sheets 3mm thick, construction joints and 2.02 all related works. Price shall include cost of supplying and fixing the required steel angles for the electrical trenches, as well as, the required steel reinforcement for the slab on grade of 8 mm dia @ 20cm distances in both directions. UNDP-PAPP 1 of 14 Total amount $ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 DESCRIPTION ITEM Supply and cast concrete grade 'B 300' for footings of the building and the boundary walls. Price includes cost for supply and 2.03 workmanship of the required steel reinforcement, as per drawings and engineer's instructions Ditto, but for columns necks and columns. BoQ Revised on 8/14/2013 Unit QTY Unit price $ M3 110 M3 6 Ditto, but for ground beams including projections to support the 2.05 stone cladding M3 6 2.06 Ditto, but for the reinforced walls under and above the level of slab on grade of the building, the transformers and trenches, and where required as per the Engineer's instructions. M3 80 2.07 Ditto, but for walls of the boundary walls walls including the required steel reinforcement as in the above bill item. M3 80 2.04 Supply and cast concrete grade 'B 300' for suspended ribbed slabs .Price to include projected beams, other beams and projections, supply, lay and arrange hollow concrete blocks 'Grade 35' for ribbed 2.08 slabs, using closed end blocks at all ends, edges, openings, M.S. services location etc, as per drawings. Price shall also include cost of supply and fixing the required steel reinforcement as per drawings. 2.09 Ditto, but for the suspended cantilevered solid slab for trenches. Total for Concrete Works UNDP-PAPP 2 of 14 M.S 110 20 Total amount $ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 DESCRIPTION ITEM 3.00 3.01 3.02 3.03 3.04 BoQ Revised on 8/14/2013 Unit QTY Unit price $ M.S 220 M.R 44 MR 18 MR 40 Stone Works Supply and build stone walls Njassa minimum 5cm stone or equivalent to the full length and height, as shown in the drawings(Mattabah stone dressing). First grade first class white stone uniform in color and texture and first quality, rough textured for facades with 25cm thick plain concrete (B-250) for stone backing. Price to include all required stone pieces such as stone corners, lanterns, jambs and for doors and windows and stone pointing with 2:1 cement sand mortar. Price shall include cost of 4 " UPVC pipes and two 20X 20cm rigid plastic roof drains ,READY type, including the required boxes, smoothing of surface around the drains, and all necessary fitting and accessories for rain water drainage, all as per drawings, specifications and the Engineer's instructions. Supply and install 5cm thick stone copping for the roof parapet Supply and build 3cm thick local marble for windows sills and doors thresholds Supply and build 4cm thick and 35 cm wide stone cladding, polished from one face . The stone shall be first grade Njasa or equivalent uniform in color. Price shall include cost of fixing the stone to the walls by steel anchorage at maximum distance 50cm, fixing mortar and all associated cost as per drawings and the Engineer's approval. Samples of stone shall be provided for the Engineer's approval. Total for Stone Works. 4.00 Plastering Prepare surfaces, apply 13mm thick plaster on walls composed of two coats of cement sand plaster (rough and fine finish) over 1:2 sand cement splashing coat. The price includes angles beads, wire mesh on all kinds of joints especially electro-mechanical. 4.01 Internal plaster :Two coats of cement : sand plaster over one 1:2 cement sand slurry coat, to walls and ceilings and where required. M.S. 400 4.02 Ditto, but external plastering, price includes waterproofing additive M.S. and "Shepretz" finished coat with white cement. 600 Total for Plastering works 5.00 Painting Works 5.01 Supply and paint three coats polycide paint for ceilings and drop beams(sides and bottom) of high quality. Samples of painting shall be provided for the Engineer selections and approvals. Supply and paint high quality emulsion paint, for walls as per indicated in finishing tables, on one priming coat and two finishing 5.02 coats, using two coats of complete putty, as per satisfaction of the supervisor engineer. Samples of painting shall be provided for the Engineer selections and approvals. Total for Painting Works UNDP-PAPP 3 of 14 M.S 120 M.S 170 Total amount $ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 DESCRIPTION ITEM 6.00 Unit BoQ Revised on 8/14/2013 QTY Unit price $ Metallic Works Metallic fencing for boundary walls: Price shall include the following: a-supply and install 2 " galvanized steel pipes 230 cm length at 200 cm spacing, including inclined pipes of same diameters at 800 cm, which should be fixed in concrete 30cm deep including V shaped branches 50cm high inclined at 45 degree at both directions'- Supply and install 2.8 mm galvanized diagonal 6.01 M.S. mesh fence 50X50 cm including 4mm tie wires at 70 cm distance canter to center. c- supply and install circular razor blade wires 60cm diameter to be install on top of the fence and supported by V pipes. d- supply and 10 cm thick concrete for fixing the fence with the wall, all as per the drawings and the Engineer's instructions and approvals. Metal gate for the substation: Supply and install iron gate "Fassoun" of cross section 1.25 " with rubber. The gate panels shall have two metal sheets 1.50 mm thick on both faces of the door 6.02 panel. The price shall include cost of the galvanized metal frame 2 mm thick, handles, hinges, steel protection, painting with oil paint three coats; all as per the drawings, specification and Engineer's instruction. 200 6.02a As above, single door 100* 260 cm No 1 6.02b As above, but double door 250 * 375 cm, as per drawings. No 1 Sliding metal gate for the external yard: Supply and install sliding iron gate dimensions as per drawings. Price includes cost of 1.25 inch metal profile and rubber , 1.5mm thick metal sheets on both sides of the leafs, 2cm galvanized metal frame, hinges, 6.02c fasteners, and all associated costs, reinforced concrete beam bellow the gate. Price shall also include cost of painting with oil paint three coats and primer, the color of paints shall be as selected and approved by the Engineer. The contractor shall provide shop drawings for the engineer's approval. No 2 Supply and install protection steel grills for windows. Price to include fixation, accessories, welding, grinding & smoothen, oil 6.0d1 painting three coats; all as per the drawings, specification and Engineer's instruction. Dimensions 200*105 cm No 6 As above, but with 4 mm diameter 3*3 cm steel protection mesh for the opening dimensions 200*105 cm, including fixation of 6.0d2 4mm thick and 2cm wide metal strip in the middle. Price includes cost of frame, all as per the drawings, specification and Engineer's instruction. No 6 No 6 Total for Metallic Works 7.00 Aluminum Works: 7.h Supply and fix 3 tracks aluminum sliding windows equal to 7700 of profile section not less than10.2*5.8cm. And 4400 for pivot windows profile # 910 and for the doors 2000. Price shall include cost of glass( 6mm thick glass for windows above than 1.4m2 and 4 mm thick glass for windows less than 1.5m2) fiber glass insects mesh, fixing, accessories, cylindrical locks handles and special ground jacks, water drains, air valves..etc. Window dimension 200* 105 cm. Total for Aluminum Works 8.00 Transformer base and trenches works UNDP-PAPP 4 of 14 Total amount $ ITB-2013-216 JAIP Electric Sub-Station - Jericho Contruction of the Transformers House DESCRIPTION ITEM Unit Supply and install galvanized steel mesh, heat resisting, bellow stone gravels for the transformers. Price includes cost of the 8.01 external frame for fixation and all associated axially material as per drawings and the Engineer's instructions. 8.02 Supply and spread smooth stone gravels( Alwadi aggregate) , the aggregate size should not be more than 10cm; all as per the Engine's instruction and approvals. Supply and install iron profile # I-section-IPE200 of 400cm length for the transformers channels . Price includes three coats of oil paint 8.03 and primers and all associated costs including welding, fixing of the channels, as per drawings, specifications and the Engineer's instruction and approvals. 8.04 Supply and install chequerd metal covers 4mm thick of dimension 60*80 cm, including frames L shape, steel angels,..etc, all as per the Engineer's instruction and approvals. Total for Transformer Base and Trenches Works UNDP-PAPP 5 of 14 BoQ Revised on 8/14/2013 QTY Unit price $ M2 25 M3 8 No 4 No 30 Total amount $ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 DESCRIPTION BoQ Revised on 8/14/2013 Unit QTY Unit price $ .MS 108 Supply and apply of an approved type waterproofing membrane of bitumen rolls, 4.5 mm thick, (of density 180g per m.s. of reinforced polyester sheets) covered with layer of crushed white stone with 9.02 overlaps of not less than 15 cm. price to include primer coat at rate .M.S off application 1/2 kg/m2, and all sheets flashing, treatment of the joint at the roof drains and angles by special water proofing material such as Sika Flex or equal. 108 ITEM 9.00 Insulation Works: Supply and cast B300 concrete screed on the roof, with 1.5 slope cast to falls not less than 5cm thickness in the drain point. Price shall include cost of hunching 15x15 cm with (45˚) to the edge of 9.01 roof screed and parapet, include smooth surface finish to receive bitumen and all requirements; all as per specifications, drawings and .Engineer's instructions. the insulation work shall be measured horizontally as per the roof plan. Total for Insulation Works 10.00 Trenches works 10.10 Covers to internal the trenches Supply and install metallic chequerd plate covers 4 mm thick as. per, drawings and specification. Price includes fixing on L shaped .steel angels, welding, and painting with 3coats of approved oil paint Price in also include fixing of U channel in the smooth concrete slab (the U channels will be .provided, by the E electric Company and supervised by the engineer form the electric company and as ..per the attached detail 10.1a As above, dimensions 80*60cm No 25 No 6 Supply and install 6" PVC pipes between trenches and filing around 10.1b the pipe by 20cm sand encasement, including the required sleeves in the trenches walls. Total for Trenches Works External Works-Asphalt: Supply , spread and pave 6cm asphalt layer( after compaction) for yards and wherever needed as per drawings and specifications. Price includes applying the primer, excavation for site leveling from the natural ground levels to the 11.00 required level, supply and compact 20cm base course layer to min MS. 95% according to modified AASHTO Density and all associated works including cost of performing the necessary tests for the for completing the works in accordance with the drawings and engineer's instructions. Total for External-Asphalt Works UNDP-PAPP 6 of 14 300 Total amount $ ITB-2013-216 DESCRIPTION ITEM 12 JAIP Electric Sub-Station - Jericho Contruction of the Transformers House Unit Electrical and Communication Works Preamble: * The contractor shall, when pricing the rates of the following electrical bills take into consideration including and allow for the cost expenses of all requirements stipulated in the preambles, drawings and technical specifications of the tender. * All Supplied Materials Should be class A , new , not used and Free From any Defects, Having the Supervisor approval Certificate . * The contractor's total price for works shall include the supply, execution, completion and testing of the whole of electrical installation works and related systems in accordance with the drawings, bill of quantities and specifications. * the rates includes connection to existing system were applicable and or adjustment of non removed or cancelled network to allow for new networks or system . * The contractor shall coordinate his works with the decoration works, furniture, changes in the positioning of ceiling light fixtures due to partitioning changes and any other changes which require design changes on the tender drawings. * The contractor must consider all these changes in the shop drawings which must be submitted and approved before commencement of works. * Plates, labels and tags for the identification of plant, equipment, cables, switches ,sockets and the like. * the unit rate including for Forming or cutting holes, chases, channels etc. in reinforced concrete structures and block works * * Jointing, saddles, clamps, brackets, hangers and providing steel pipes sleeves with plates. All electrical and low voltage conduits for all different items in the main B.O.Q. installed above false ceiling level must be colored, fire proof and first class taken quality for all main and sub main feeders circuitsNetc. * The contractor must consider keeping the system running where needed during the whole construction period. * The contractor's rate must include the supply and install internal sea sand plastering for the electrical conduits on wall . composed of two coats base coat ,finish coat . The rate includes all necessary patching works ,expanded metal latch mesh , plastering layers must be applied to meet plastering thickness * The contractor shall submit all samples needed for all electrical and low voltage points, fittings , accessories and fixtures and to take the approval from the supervision engineer before starting works. * The contractor shall submit a time schedule for all the works showing start and end dates for each item in B.O.Q.. * the contractor should have his electrical engineer available in a daily bases and on call to arrange with the Consultant representative engineer on site and for all written communications and works UNDP-PAPP 7 of 14 BoQ Revised on 8/14/2013 QTY Unit price $ Total amount $ ITB-2013-216 JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITEM DESCRIPTION * All electrical conduits under tiles, floor, wall should be protected by cement mortar or concrete layer and all electrical excavation works should be removed from site as specified in the technical specification and drawings. * Making holes by hilti for all holes size where required including all necessary water proofing material ( Sikaflex).for any kind of electrical and low voltages works. * The above mentioned shop drawings, electrical switchboards shop drawings, as built drawings and all other required detailed drawings are to be included in the rates for no additional cost. 12.1 Unit BoQ Revised on 8/14/2013 QTY Unit price $ Earthing system Furnishing, connection and installation complete earthing system including all required materials, cables, conduits, wires, electrodes, strips and connectorsmanholes and covers, including also all required excavation and covering all to get the required earthing resistance not more than one ohm, all according to drawings, specifications and Engineer instructions. a. Earthing system for Distribution Boards LS 1 b. Earthing system for low current systems LS 1 Total of Earthing System Carried to Summary Sheet UNDP-PAPP 8 of 14 Total amount $ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 DESCRIPTION ITEM 12.2 Unit BoQ Revised on 8/14/2013 QTY Unit price $ Electrical Distribution Boards: * Supply of electrical switchboard to site including all associated materials and labor, as described in the technical specifications and drawings. Cabinets with no access from the rear , made up of Galvanized 2mm sheet metal cabinets with 25% surplus space. Price to include all MCCB's,MCB's type Moller or equal approved, structural elements required in order to install the switchboard including all bus bars , terminals , wiring , bolts , clamps, master keys for all different panels doors, measuring instruments, all required conduits and manholes etc. and for the equipments as per dwg specification and Eng. Instructions. a. MDB Unit 1 b. LVB Unit 1 Total of Electrical Distribution Boards Carried to Summary Sheet 12.3 Installation in the Building Points Furnishing and installation of wall, ceiling or false ceiling mounted lighting point normal, waterproof, emergency or exit (Price includes 16mm diameter conduit , 3x1.5 mm2 cross section wire or cable ,all 12.3.1 required swiches or push bottoms, ceiling box and phase line for emergency lighting point , with 60 W lighting bulb and leading from the switch panel to the point including any needed boxes or accessories). a. Internal Lighting point No. 10 b. External lighting point No. 6 Furnishing and Installation of Standard 1 ph socket outlet point normal (Price includes 16mm dia. conduits , 3x2.5mm2 wire OR CABLES , with 16A socket Gewiss Type or equivalent including 12.3.2 switch and sign lamp, Boxes, Supports & Plates and leading from the switch panel to the point , including all accessories) all according to specification, drawings and Eng. Instructions 12.3.3 Sockets and Feeding Points a. 1 phase socket No. 4 b. Ditto but Double socket No. 4 c Sockets for chargers No. 2 Telephone connection point wall or table mounted (Price includes 16mm diameter conduits Nacy , hadash plast type or equivalent, with 4 pairs computer cable shielded type CAT7 , telephone socket 12.3.4 Legrand Type Arteor Model with Brilliant White Finish Color or equivalent, Including Boxes, Supports & Plates and leading from point to the COMPUTER HUB). No. 2 Computer outlet connection point wall or table mounted (The price includes 16mm2 conduits with 4 pairs computer cable shielded type CAT6A and leading from the telephone communication cabinet or 11.3.5 computer HUB to the points as well an outlet with a plastic socket GEWISS Top System GW20243 type or Biticino, Legrand or equivalent including Boxes, Supports & Plates and all accessories). No. 4 Total of Installation Works Carried to Summary Sheet UNDP-PAPP 9 of 14 Total amount $ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 DESCRIPTION ITEM 12.4 Unit BoQ Revised on 8/14/2013 QTY Unit price $ Lighting Fixtures and Accessories Note: work for lighting fixtures is to include supply of the fixtures specified, installation of same connection, wiring, commissioning, lamps OSRAM type, tubes, starters louvers, connections, suspension, clamps and all other accessories necessary to provide a complete fitting with all terminals and rates also includes all L,Z and omega profiles if needed , great opening for lighting fixtures in gypsum board and all other details , as specified in the technical specifications and drawings and as approved by the engineer. a. Type (K)2x55w light fixture with parabolic louver . Unit 6 b. Type (KE) Ditto but with emergency battery charger 3 hours duration or equivalent. Unit 2 c. Type (X2) Projector unit with (250) Metal Halide with aluminum body, includes water proof connection box (10x10)cm. Wall mounted weather proof type. IP65 include boxes , switches and (3x2.5 )wire and (3/4") pipes as detailed on drawings Unit 6 Total of Lighting Fixtures and Accessories Carried to Summary Sheet 12.5 Cables & Conductors / Leads Supply, install, test and connect the following electrical cables , including conduits, trunks, manholes, complete ready for work, including insertion into conduit or attachment to structural elements or laying in ductwork, including all associated materials, insulation materials, unions, labeling and connection of cable at both ends and all accessories). a. 3x25+16 sq.mm +16mm2 CU cross section XLPE/PVC/PVC cable. M.L. 50 b. 5x6 sq.mm cross section N2XY cable. M.L. 50 Total of Cables & Conductors Works Carried to Summary Sheet 12.6 Fire Alarm System Supply install and connect fire alarm addressable system including of the equipment specified, installation of same connection, wiring commissioning and all of the details as specified in the technical specifications and drawing with complete operation capacity. a. Fire alarm control panel, 1 loop, expandable, , and 230V, gray. No. 1 b. Analogue addressable photoelectric smoke detector.V-PS No. 4 c Analogue addressable heat detector.V-HRD No. 2 d Analogue manual call break glass station.GSA-M270 No. 2 e Indoor fire siren.G1RF-P No. 1 f Fire alarm outdoor siren with strobe.757-7A-T No. 1 g Automatic telephone dialerDL-125C No. 1 Total of Fire Alarm System Works Carried to Summary Sheet UNDP-PAPP 10 of 14 Total amount $ ITB-2013-216 DESCRIPTION ITEM 12.7 JAIP Electric Sub-Station - Jericho Contruction of the Transformers House Unit BoQ Revised on 8/14/2013 QTY Unit price $ CCTV System Supply , install and connect the CCTV System type (DAY)(PROVISIONAL NIGHT) including (Port 8) and 6 External Cameras IP 65 Night light all according to drawings and specifications, the price also includes all required outlet boxes , cover plates, and all necessary connections , complete with operation, soft ware to connect the system with the computer network and JEDCO offices, (DVR CARD) and connection with the Data center, testing and commissioning works as shown on the drawings and as per specifications. The CCTV System shall include also all required instruments and equipments and CARDS , complete ready for work all according to Specification and Eng. requirements. LS 1 Total of CCTV System Works Carried to Summary Sheet 12.8 Fire Fighting System Supply install and connect complete in place and in an operable manner the Fire Fighting system (F200) For main distribution board . The work is to include the supply of the equipment specified, installation of same connection, wiring commissioning and all of the details . a. Automatic Valve Cylinder 200 KG Kidde FM 200 180 Degree Pendant Nozzle , 3/8" Check Valves , Bracket , Pressure Gauge , Copper pipe , Safe Cap N...with all accessories needed ) No 1 b. Main Control Panel 4- Zone Telefire 2-B or equivalent No 1 c Photoelectric Smoke Detector MIR-338H / TFO-440 or equivalent No 2 d Heat detector - S.S 5601 P / TFH-220F or equivalent No 2 e Indication lamp TFL-1N or equivalent No 2 f Break glass unit TPB-10 R or equivalent No 1 d Fire Indoor Horn TIP-224A or equivalent No 1 e Supply and install portable fire extinguishers "BFARYA" LAHAVOUT or equal. The extinguishers shall be of dry powder 6 kg with hangers and shall be valid for three years form the date of signing the Contract. No 4 Total of Fire Fighting System Works Carried to Summary Sheet UNDP-PAPP 11 of 14 Total amount $ ITB-2013-216 JAIP Electric Sub-Station - Jericho Contruction of the Transformers House BoQ Revised on 8/14/2013 Civil Works Summary Bill No. Description 1 Total Earthworks, Excavation, Backfilling and Site Works 2 Total for Concrete Works 3 Total for Stone Works. 4 Total for Plastering works 5 Total for Painting Works 6 Total for Metallic Works 7 Total for Aluminum Works 8 Total for Transformer Base and Trenches Works 9 Total for Insulation Works 10 Total for Trenches Works 11 Total for External-Asphalt Works Total for Civil Works carried to grand summary UNDP-PAPP 12 of 14 Total US$ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 BoQ Revised on 8/14/2013 Electrical Works Summary Bill No. Description 1 Total of Earthing system. 2 Total of Electrical Distribution Boards . 3 Total of Installation Works . 4 Total of Lighting Fixtures and Accessories. 5 Total of Cables & Conductors Works . 6 Total of Fire Alarm System Works 7 Total of CCTV System Works 8 Total of Total of Fire Fighting System Works Total for Electrical Works carried to grand summary UNDP-PAPP 13 of 14 Total US$ JAIP Electric Sub-Station - Jericho Contruction of the Transformers House ITB-2013-216 BoQ Revised on 8/14/2013 Grand Summary Bills Description Amount $ 1 Total for Civil Works 2 Total for Electrical Works Grand total Discount percentage (if any) : Discount amount: Net Grand Total Total Excluding Value Added Tax (VAT): : Grand Net Total in Words: Name of the Contractor: Address: Authorized person Name : Signature & Stamp : Date: UNDP-PAPP 14 of 14