5/31/04 Missing recommended projects and nature and distribution of benefits of projects Chapter 7 Benefits and Costs of Transmission Expansion Generic Benefits and Costs of Transmission Expansion Benefits of investments in transmission expansion may include: Improved access for utilities to purchase lower cost power; Greater liquidity and price competition in power markets, including mitigation of market power by generators; Increased ability of generators to diversify fuels used to serve their customers, which can help minimize fuel price risks and broaden access to renewable resources; Tax revenue and other economic benefits to communities and states where development takes place; and Improved reliability and greater flexibility for maintenance, and other operational purposes. The cost of new transmission includes the capital cost of building the line, operating and maintenance costs over the life of the line, environmental impacts from construction of the line, and changes in property values resulting from the location of the line. It is the common assumption that property values decline in the vicinity of a transmission line, however, property values could increase, particularly for industrial properties, from access to transmission lines. Discussion of Types of Benefits and Beneficiaries1 Lower Cost Generation: Benefits of accessing lower cost generation flow to utilities and their customers and to certain generators. RMATS alternatives entail reductions in variable O&M on a West-wide basis. This new access to lower cost generation can also reduce net revenues for some existing generators, whose higher cost generation may be displaced. Enhanced Competition in Energy Markets: In concept, by relieving congestion, liquidity and competition in energy markets will become more robust. This may lead to lower and more stable prices, especially in short-term markets, and may help to mitigate exercise of generator market power, creating benefits which flow to utilities and their customers within and outside the RMATS region. 1 Presumably under Order 888 the benefit of owning transmission to block competitors having access to one’s power markets has been eliminated. However, there still may be benefit to the integrated utility in owning the line since the utility will calculate and reserve ATC on the line for future load growth, thereby providing an advantage over other users of the line. Fuel Diversity: It is assumed that fuel diversity means greater reliance on fuels other than natural gas. By diversifying fuels, generators can mitigate gas price risks. Further, new access can be provided to renewable resources, helping to reduce risks and costs, stabilize customer prices, and meet environmental policy objectives, including renewable portfolio standards. Fuel diversity benefits of new transmission investments can flow to utilities and their customers. The size of benefits may depend on the value of reduced fuel price volatility to the generator, how risks and costs are calculated, and on incremental costs to utilities of alternatives for meeting Renewable Portfolio Standards, risk management goals, and environmental policy objectives. Local and State Economic Development: Construction of new power plants provides economic development benefits in terms of jobs and increased tax revenues to the communities and states hosting the plants. Tax revenue benefits for states and localities include increased property taxes, additional franchise taxes, higher utility taxes revenues, and increased state and local income taxes, offset by the state increase in rates due to the higher revenue requirement, along with secondary and tertiary induced and indirect economics and resulting taxes flowing from the investments. Reliability: All new transmission investments must meet the goal of maintaining or improving reliability and meet WECC reliability criteria. Full implementation of alternatives to new lines might have pronounced reliability benefits as needle peaks are eliminated, as overall energy use is reduced, and as new technology is implemented to provide better information flows and control potential for existing lines, thereby boosting their ability to respond to unforeseen problems. New long distance lines may not decrease reliability and, hopefully, will increase reliability beyond that required by WECC, particularly if they are oversized. Reliability benefits from an oversized line may disappear over time if new flows consume excess transfer capacity. The economic value of reliability investments may be quantified by determining the value of a reduced likelihood of forced outages. Quantifying transmission investment benefits and estimating where they fall is a challenge and matter of judgment. Where construction of a new transmission line is linked to the construction of a specific powerplant(s), there is greater ability to identify the benefits from fuel diversification and reduced costs to load serving entities. One can also identify the generator(s) that benefit from the new line. Where additional transmission investment is not linked to construction of specific power plants, it is more difficult to determine the additional investment will provide fuel diversity benefits and lower power costs to utilities since the types of generation built and the cost of power will be determined by market forces. It would also be more difficult to recoup, in advance of construction, part of the investment from generators. If new lines are built and generators secure transmission service over the lines, then revenues charged for use of the line can offset construction costs. The following diagram illustrates the potential range of benefits from a transmission project and the subset of such benefits that were modeled using ABB Market Simulator. Benefits of new transmission investment can accrue to: Load serving entities and their customers; New generators who can now reach markets, and communities and states hosting new generation; Existing generators who can reach new markets; Communities and states where development occurs; and All transmission system users where the transmission investment improves system-wide reliability. Before examining the costs and benefits of specific recommended projects, it is important to understand how the differences in how the RMATS modeling approach identified recommended lines and how decisions on transmission expansion are made in the “real world.” Comparison of the Decision Process Under RMATS Modeling Approach and Real World Decision Processes Under both decision processes, the location of new generation drives the determination of the need for new transmission. In the modeling process, the location of new generation is an assumed input. The RMATS process assumed four generation scenarios in 2013, one of which was linked to available resource plans of load serving entities in the RMATS footprint. In the Real World process, the decision on what new generation is built is largely a determined by choices of load serving entities and their regulators. Ideally, in the Real World the decision on new generation is made considering both the cost of the generation and the cost of the transmission to move the electricity to load. In the RMATS modeling process, once the location and type of generation is assumed, then the model chooses the dispatch of the existing and new generation based on the lowest variable operating and maintenance cost of the generating units without regard to plant ownership or power purchase contracts. In the Real World process in the RMATS region, the decision on which generation to dispatch is typically made by each load serving entity based on the lowest operating cost of the units it owns or power purchase contracts it has signed. In the RMATS modeling process, once the model has chosen the units to dispatch, it is assumed that all transmission paths are available to move the power to load centers without regard to contractual rights on the transmission system. The transfer of electricity from the generator to the load is only constrained by the physical capabilities of the transmission system. In the Real World process, moving power from a generator to a load can only be done pursuant to schedules over specified transmission paths or pursuant to a network service contract. To execute a schedule, a party must have rights to use specific transmission paths from the generator to the load (even though in actuality the electricity from the generator to the load will flow over other paths as well as the paths over which the power has been scheduled). In the RMATS modeling process, after the generation with the lowest operating and maintenance cost is dispatched over any combination of lines that can physically handle the transfer, the model determines if there are generators with lower operating and maintenance costs could not be dispatched because of the lack of transmission capacity and, in place of this lower cost generation, a higher cost generator was dispatch to meet demand. The model calculates the variable operating and maintenance cost for all the generation dispatched in the Western Interconnection and shows differences in dispatch costs in different bubbles in the Interconnection. Where there are significant differences in costs between the bubbles, in the RMATS process new transmission was chosen by the Transmission Working Group to enable the lower cost power to flow to load centers in order to reduce interconnection-wide variable operating and maintenance costs. In the Real World, a load serving entity examines whether new transmission would lower the cost of acquiring generating resources to meet the demands of its customers. Most of the time, the decision on what new transmission to build is made in conjunction with the decision on what new generation to acquire. Typically, only after a load serving entity has decided it wants to build a project will it inquire whether other parties would be interested in sharing the cost of the line or expanding the line. What are the linkages and disconnects between the two processes and what relevance does the modeling work have to decisions made in the real world? 1. There is a major disconnect between the way in which new generation is determined. The RMATS process tried to remedy this by: (1) including Alternative 1 which reflected the resource plans of PacifiCorp, Xcel and Idaho Power; and (2) using generation developers assumptions about where they will build new plants that will be attractive to power buyers. A significant shortcoming in the way generation decisions are made in the Real World is that each load serving entity makes decisions in isolation. Because transmission additions and some generation additions (e.g., coal) tend to be in lumpy increments (i.e., do not come in capacities sized to meet incremental needs) and because there tends to be economies of scale in building transmission (a 500 Kv line does not cost twice as much as a 230 Kv line), a transmission addition may not be economic to meet demand in of a single load serving entity, but would be economic when combined with the needs of other load serving entities. 2. The dispatch of generation in the RMATS process is optimized over the entire interconnection. In the Real World, dispatch of generation in the RMATS region is optimized by the load serving entity among the plants under its control. This leads to higher operating costs in the Real World than in the RMATS process. 3. In the Real World institutional constraints on the use of the transmission system (e.g., ownership of transmission rights) result in the transmission system being used than its physical capabilities. In some cases (e.g., West of Hatwai), these institutional constraints have been overcome by building new transmission even though the existing system may have been capable of moving the power. In the RMATS process, the use of the transmission system is optimized. How do the linkages and disconnects between the RMATS process and the Real World affect the way in which the modeling findings should be interpreted? 1. The RMATS modeling results are only as relevant as the assumptions about the location of new generation. In examining the RMATS model findings, one needs to remember that the location of the generation is an assumption. Resource planning processes by load serving entities may identify different generation choices than assumed in the RMATS modeling. Hopefully, the generation assumed in the RMATS process, particularly in Alternative 2, will inform LSE resource planning process of potentially lower cost options that they are presently considering. 2. The RMATS modeling results may understate or overstate the value of new transmission in lowering operating and maintenance costs. In the Real World, a load serving entity must utilize the portfolio of resources under its control when deciding which generation will serve its load. Had there been more transmission available, the LSE might have been able to reach lower cost generating resources. 3. The RMATS modeling will miss opportunities to build new transmission that individual market participants would find attractive. For example, lack of ownership rights on a path may preclude a generator or LSE from being able to complete an economic power deal because firm capacity on the line is not available (even when the line is not fully loaded) or there is no ability under current operations to take account of counterflows that would make capacity available. RMATS Modeling “Real World” Strength: approach spot regional generation that is lower cost than that considered by LSE Weakness: assumption do not reflect LSE decisions Generation location and size of is an assumption, except in Alternative 1 Generation location and size largely driven by LSE plans Strength: Generation does not have to be assumed; it is known Weakness: May miss lower cost regional opportunities, particularly for generation projects with a shorter lead time than related transmission Strength: Bolsters case that identified transmission additions add value for the interconnection regardless of future changes in ownership of plants and LSE configurations Weakness: Does not recognize transmission expansion that may be marginally economic from a global perspective, but makes economic sense for specific parties Optimal interconnectionwide dispatch of generation to meet demand Generation dispatch optimized for LSE but not across LSEs Strength: Reflects reality faced by LSEs today and thus it is easier to make decisions on financing of transmission projects (i.e., individual LSEs will see the benefits of a transmission project to allow them to save money by optimize the dispatch of their resources. Weakness: Does not reflect future changes in the ownership of plants and their output that would allow more optimal dispatch patterns. Strength: Provides justification for new transmission under future institutional changes, such as the formation of RTOs, and provides a compelling case for new transmission in the permitting process. Weaknesses: Does not reflect the incentives faced by those who would finance new transmission. Optimizes use of the transmission system within its physical constraints Reflects institutional constraints that results in suboptimal use of the transmission system Strength: More likely to result in projects being financed because it reflects present (and at least in the foreseeable future) rules on transmission system use. Weakness: Can result in building transmission that would not be needed if there were system operation rules that allowed more efficient use of the grid. This may make permitting of such transmission more difficult since the need for the line is based on institutional rules, not physical needs. Benefits and Costs of Each Recommended Transmission Project TBA Nature and Distribution of Benefits to Parties of Recommended Transmission Projects TBA