Microsoft Word - 2012 RNA Assumption Matrix

advertisement
Base Case Modeling Assumptions
For 2012 RNA – Lock down April 5, 2012
Parameter
Peak Load
Load Shape Model
Load Uncertainty Model
2012-2013 IRM Study
Modeling Assumptions
Oct 1, 2011 Forecast: 33,335 MW for NYCA,
11,607 MW for zone J, and 5521 for zone K
2002 Load Shape
Zonal model updated to reflect current data.
Solar Resource Modeling
Forecast of 38.5 MW of total solar capacity.
See Attachment B-2.
Wind Resource Modeling (1,648 MW) Derived from hourly wind data
resulting in an average Summer Peak Hour
availability of approximately 11%. See Attachment
B-1.
Wind Shape Model
2002 Wind Generation Profile
Existing Generating Unit
Capacities
Proposed New Units
Retirements
Forced & Partial Outage
Rates
Planned Outages
Updated DMNC test values. Use the minimum of
DMNC or CRIS values.
Those listed on Attachment B.
578.1 MW of retirements and mothballing as listed
in Attachment B-3
5-year (2006-10) GADS data. (Those units with less
than five years data could use available
representative data.)
Based on schedules received by NYISO & adjusted
for history.
Model change
For 2012 RNA
Update per 2012 Gold Book
Same, stay with 2002 Load Shape
Same
Same, 2012 Gold Book
Same, 2012 Gold Book
Update to Wind Study and 2012 Gold Book
Same, 2012 Gold Book
2012 Gold Book
2012 Gold Book
Same, update one year
Same, 2012 Gold Book
Parameter
Summer Maintenance
Combustion Turbines
Ambient Derate
Environmental Impacts
Non-NYPA Hydro
Capacity Modeling
Special Case Resources
EDRP Resources
External Capacity Purchases
Capacity - Sales
Capacity Wheels-through
EOPs (other than
SCR and EDRP)
2012-2013 IRM Study
Modeling Assumptions
Use nominal value of 50 MW after reviewing last
year’s data.
Derate based on provided temperature correction
curves.
No impacts for base case.
45% derating.
2192 MW (Jul 12) based on registrations and
NYISO growth rate forecast. Monthly variation
based on historical experience.
148 MW registered; modeled as 95 MW in July and
Aug and proportional to monthly peak load in other
months. Limit to 5 calls per month.
Grandfathered amounts of 50 MW from NE, 1080
MW from PJM and 1,090 MW from Quebec. All
contracts modeled as equivalent contracts.
Long term firm sales of 303 MW (nominal value).
None modeled. A sensitivity case will be run.
735 MW of non-SCR/EDRP MWs.
Interface Limits
All changes viewed and commented on by TPAS.
New Transmission
Capability
Transmission Cable
Forced Outage Rate
None Identified.
All existing Cable EFORs updated on LI and NYC
to reflect 5 year history.
Model change
For 2012 RNA
Same
Same
2012 Gold Book
Same, 2012 Gold Book
Same, 2012 Gold Book Forecast is flat for ten year period
Same, 2012 Gold Book Forecast is flat for ten year period
2012 Gold Book
2012 Gold Book
None modeled
Same, 2012 Gold Book
Also Based on RNA specific Transmission Adequacy
Analysis
2012 Gold Book
Same
Parameter
Unforced Capacity
Deliverability Rights
(UDR)
2012-2013 IRM Study
Modeling Assumptions
No new projected UDRs
Version 3.12
Model Version
Outside World Area Single Area representations for Ontario and Quebec.
Four zones modeled for PJM. Thirteen zones
Models
Reserve Sharing
between Areas
Other
modeled for New England.
All NPCC Control Areas have indicated that they
will share reserves equally among all.
Model change
For 2012 RNA
Modeled as in previous RNA, Add HTP at firm withdrawal
rights
Most recent approved
Same as sensitivity
Same
TRANSMISSION SECURITY / FAULT CURRENT
Modeling Assumptions
Source
Comments
Parameter
Peak Load
Load model
System
representation
NYCA baseline coincident summer peak forecast
ConEd: voltage varying
Rest of NYCA: constant power
Per updates received through Databank process
Inter-area
interchange
schedules
Inter-area
controllable tie
schedules
In-city series and
shunt reactors
Consistent with ERAG MMWG interchange schedule
SVCs, FACTS
Transformer &
PAR taps
Switched shunts
Fault current
analysis settings
Set at zero pre-contingency; allowed to adjust post-contingency
Taps allowed to adjust pre-contingency; fixed post-contingency
Consistent with applicable tariffs and known firm contracts or
rights
Consistent with ConEdison operating protocol
Allowed to adjust pre-contingency; fixed post-contingency
Per Fault Current Assessment Guideline
2012 Goldbook
2012 FERC 715 filing
NYISO RAD Manual,
2012 FERC 715 filing
Subject to RNA
basecase inclusion
rules
2012 FERC 715 filing,
MMWG
2012 FERC 715 filing
2012 FERC 715 filing,
ConEd protocol
NYISO T&D Manual
2012 FERC 715 filing
2012 FERC 715 filing
NYISO Fault Current
Assessment Guideline
All series reactors
in-service for
summer
Download