02922 - Sodding - Alberta Ministry of Infrastructure

advertisement
Section Cover Page
Section 02922
Sodding
2004-05-10
Use this Section to specify requirements for sodding in conjunction with Section 02911- Topsoil
Placement and Grading.
This Master Specification Section contains:
.1
This Cover Sheet
.2
Specification Section Text:
1.
1.1
1.2
1.3
1.4
General
Related Sections
Delivery, Storage and Handling
Maintenance Period
Measurement and Payment
2.
2.1
2.2
Products
Material
Sod Type
3.
3.1
3.2
3.3
3.4
3.5
3.6
3.7
Execution
Fertilizing
Laying Sod
Laying Sod on Slopes
Protection of Sodded Areas
Maintenance
Acceptance
Clean-up
BMS Basic Master Specification
Alberta Infrastructure
Master Specification System
Page 0
Section 02922
Sodding
Page 1
Plan No:
Project ID:
1.
General
1.1
RELATED SECTIONS
.1
.2
1.2
Topsoil Placement and Grading:
Exterior Landscape Maintenance:
Section 02911.
Section 02936.
DELIVERY, STORAGE AND HANDLING
.1
Use all means necessary to protect material before, during and after installation.
Provide adequate protection to materials which may deteriorate if exposed to
elements.
.2
Deliver fertilizer and store on site in waterproof bags, with label clearly indicating
net mass, analysis and manufacturer.
.3
Protect sod during transportation with tarpaulin to prevent sun scalding and drying
out. Deliver healthy sod rolled or flat to prevent tearing or breaking. Store on
pallets. Broken or irregular pieces are unacceptable.
.4
Harvest, deliver and install sod within a period of 24 hours.
.5
Protect sod that cannot be installed immediately on delivery from sun, wind,
dehydration and rain prior to installation.
.6
Dried out, deteriorated and unhealthy sod will be rejected.
.7
In event of damage or rejection, promptly remove sod from site. Make immediate
repairs and replacements at no cost to Minister.
1.3
MAINTENANCE PERIOD
SPEC NOTE: When maintenance requirements are for more than six weeks, delete this article
and include Section 02936 - Exterior Landscape Maintenance.
.1
1.4
Maintain sodded areas from time of sodding until [six] [
Interim Acceptance of the Work.
] weeks after date of
MEASUREMENT AND PAYMENT
SPEC NOTE: For Unit Price Contracts only.
.1
Quantity of sod supplied and installed on site will be paid by [lump sum] [square
metre]. Unit bid price shall include sod, fertilizer, warranty and all other work,
equipment and materials required to complete the Work.
Section 02922
Sodding
Page 2
Plan No:
Project ID:
.2
Quantity of sod maintenance will be paid [per week] [
]. Unit bid price shall
include all work, equipment and materials required to complete maintenance
requirements.
.3
[
2.
Products
2.1
MATERIAL
]
.1
Fertilizer:
.1
Complete commercial granular fertilizer, minimum of 50% of elements
derived from organic sources.
.2
Minister may adjust specified fertilizer analysis after topsoil test analysis
results are received, with no change in Contract Price.
.2
Nursery Sod: freshly cut and healthy with strong, fibrous root system, cultivated
in nursery field as turf grass crop containing maximum of 2% of other grass
species, and maximum of two broad leaf weeds and ten other weeds per 40 m2.
Thickness of sod soil portion shall be maximum of 40 mm and minimum 25 mm.
.3
Water: clean water free of contaminants that my inhibit germination and plant
growth.
.1
[General purpose use: on site source supplied and paid for by Minister.]
.2
[Water for water hauling equipment: supplied and paid for by Contractor.]
.3
[Water for hydraulic seeding and mulching equipment: supplied and paid
for by Contractor.]
.4
Staples: 25 mm wide by 200 mm deep by 3 mm diameter steel wire.
.5
Geotextile Fabric: biodegradable, [25 mm x 25 mm] [
.6
Biodegradable Pegs: 17 mm x 8 mm x 200 mm.
.7
Wood Pegs: 19 mm x 19 mm x 300 mm for sod.
2.2
] square mesh.
SOD TYPE
.1
Bluegrass/Fescue grass sod: sod grown from minimum 65% Kentucky bluegrass
blend, 35% Creeping red fescue, or approved alternative.
3.
Execution
3.1
FERTILIZING
.1
Apply fertilizer only after final grade has been approved by Minister.
Section 02922
Sodding
Page 3
Plan No:
Project ID:
] fertilizer at 3 kg/100 m2.
.2
Apply [12-51-0] [
.3
Spread evenly with calibrated mechanical distributor.
.4
Mix thoroughly into upper 50 mm of topsoil.
3.2
LAYING SOD
.1
Obtain Minister's approval of sodbed finish grades, final tilth, surface flatness and
fertilizer application before laying sod.
.2
Firm sodbed by rolling before laying sod.
.3
Do not lay sod over frozen soil, wet soil conditions or snow covered soil.
.4
Rake soil immediately before sodding. Lay sod smooth with tight butt joints. Do
not leave visible open joints or overlap adjacent pieces of sod. Lay adjacent rows
of sod in a staggered sequence.
.5
Finish sod edges at walks, curbs, planting, edgers, manholes, sprinkler heads, and
other vertical surface by cutting neatly and fitting tightly to edge and line.
.6
Lay sod with top flush with adjacent hard surface and seeded areas. Remove
excess soil when necessary before placing sod.
.7
Where new sod joins existing lawns, cut straight and neatly into existing lawn and
level subgrade to allow height to match.
.8
Cut and remove all irregular, unhealthy and thin sections of sod. Replace with
new sod.
.9
Place sod so that watering will not interfere with other work.
.10
Water immediately in sufficient quantities to obtain moisture penetration through
sod and into upper 100 mm of topsoil.
.11
After sod and soil have dried from initial watering, roll sod to ensure sod contact
with topsoil and to remove minor depressions and irregularities.
3.3
LAYING SOD ON SLOPES
.1
For grades exceeding 3:1, start laying sod at bottom of slope. Lay sod sections at
right angles to slopes and secure with 4 to 5 pegs/m2, to prevent shifting. Drive
pegs flush with sod surface.
.2
Where additional sod establishment support is required on steep slopes over 3:1,
and in areas indicated, place geotextile fabric on topsoil before placing sod.
Section 02922
Sodding
Page 4
Plan No:
Project ID:
.3
3.4
Lightly cover fabric with topsoil. Lay sod at right angles to slope. Secure fabric
and sod with wooden pegs in accordance with manufacturer’s instructions.
PROTECTION OF SODDED AREAS
.1
Immediately after sodding, provide adequate protection against erosion, pedestrian
and vehicular traffic damages. Remove protection after sod areas become
established or as directed by Minister.
.2
Keep site well drained and landscape excavations dry.
.3
Cover and protect sod edges by banking with moist topsoil at transition from sod
to seed areas. Place topsoil to obtain a smoothly graded transition into seed area.
3.5
MAINTENANCE
SPEC NOTE: When maintenance requirements are for more than six weeks, delete this article
and include Section 02936 - Exterior Landscape Maintenance.
.1
Apply water in sufficient quantities to prevent grass and underlying soil from
drying out.
.2
Areas with no irrigation system: supply labour, all hoses and attachments
necessary to provide adequate watering to prevent grass and underlying soil from
drying out.
.3
Provide clean water and water hauling vehicle with proper attachments to provide
efficient and adequate watering of sodded areas when necessary.
.4
Cut grass at regular intervals and maintain to minimum height of 60 mm. Do not
cut more than 30% of blade at any one mowing. Remove clippings that will
smother grass.
.5
Repair areas which show root growth failure, deterioration, bare or thin spots, or
which have been damaged by any means or cause, including replacement
operations.
.6
Fertilize sod areas during establishment period, approximately six weeks after
sodding, with 27-14-0 fertilizer or as directed by Minister. Spread evenly at rate
of 3 kg/100 m2, water in well.
.7
Control and eliminate weed growth and turf damaging insects. Remove and
dispose of debris, rubbish and animal waste from lawn areas before mowing.
.8
Postpone fertilizing until spring if application falls after August 15th.
Section 02922
Sodding
Page 5
Plan No:
Project ID:
.9
Repeat rolling of sod as required to maintain a smooth grass surface.
.10
Maintain daily maintenance log throughout contract. Submit copy of log data to
Minister each week for verification. Record all maintenance activities performed
on site.
.11
Minister may extend maintenance period at no additional cost when Contractor
fails to maintain an accurate log, submit log when required or when unsatisfactory
and inadequate maintenance occurs.
3.6
ACCEPTANCE
.1
3.7
Sodded areas will be accepted by Minister at end of maintenance period provided:
.1
Sodded areas are properly and well established.
.2
Sod is healthy, even coloured, free of weeds and other pests.
.3
Sodded areas are free of bare and dead spots.
.4
Sod is recently mowed and thoroughly watered.
.5
Required applications of fertilizer have been provided.
.6
All installation and maintenance requirements have been provided.
CLEAN-UP
.1
Broom clean pavement and sidewalks. Clear soil and rubble from underground or
surface storm sewer lids.
.2
Clean up immediately any soil or debris spillage on hard surfaces.
.3
Leave site in neat and clean condition free of all litter. Remove and dispose of
grass clippings, debris and excess materials at approved disposal site.
END OF SECTION
Download