EVALUATION OF THE OCEANS SUBPROGRAMME UNITED NATIONS ENVIRONMENT PROGRAMME Project Design and Evaluation Unit Dr. K. J. Whittle (Consultant) October 1997 Na.97-8409 231297 /... CONTENTS EXECUTIVE SUMMARY......................................................... 6 I. INTRODUCTION.......................................................... 9 A. Background.................................................... 9 B. General objectives of the 1990-1995 system-wide medium-term environment programme............................ 13 C. Objectives of the medium-term plan 1992-1997................. 13 D. 1. Key issues............................................. 13 2. Overall strategy....................................... 14 3. Objectives identified for the subprogramme............. 14 4. Action proposed........................................ 15 Objectives of the 1992-1993 subprogramme oceans.............. 16 ..................................... E. F. G. 2. Objective.............................................. 16 3. Strategy............................................... 16 Objectives of the 1993-1994 subprogramme oceans and coastal areas: regional seas programme.................. 16 1. Key issues............................................. 16 2. Objective.............................................. 17 3. Strategy............................................... 17 Objectives of the subprogramme element 1.1 of the 1996-1997 programme of work: Caring for freshwater, coastal and marine resources, as this relates to oceans...... 17 1. Key issues............................................. 17 2. Strategy............................................... 17 3. Objectives relevant to the oceans component............ 18 4. Purpose of evaluation.................................. 18 Methodology of evaluation.................................... 19 1. Terms of reference..................................... 19 2. Scope.................................................. 19 /... 2 1. 3. II. Approach and sources................................... 19 PROGRAMME DESIGN AND ACCOMPLISHMENTS................................ 20 A. B. C. Appropriateness of the subprogramme.......................... 20 1. 1992-1993 subprogramme oceans and coastal areas........ 20 2. 1994-1995 subprogramme oceans and coastal areas for the biennium 1994-1995............................. 21 3. 1996-1997 subprogramme element: Caring for freshwater, coastal and marine resources............... 22 Efficiency and effectiveness of the subprogramme objectives...................................... 23 1. 1992-1993 subprogramme................................. 23 2. Expert assessment of the effectiveness of the regional seas programme......................... 26 3. 1994-1995 subprogramme................................. 27 4. 1996-1997 Subprogramme................................. 28 Quality and utility of subprogramme outputs.................. 31 1. 1990 evaluation of the Global Plan of Action for the Conservation, Management and Utilization of Marine Mammals...................................... 31 2. December 1994 evaluation project FP/ME/5101-1993-03, on support of IAEA marine environmental laboratory for the regional seas programme........................ 32 3. October 1995 evaluation of regional support, regional cooperation and regional advisory services.... 33 4. May 1996 evaluation of project FP/1111-1994-17 on public awareness of coastal and marine environmental issues, East African Seas, EAS/29, phase 1........................................ 34 5. May 1996 evaluation of project FP/0201-1994-20 on the integrated management of water-sheds in relation to management and conservation of near-shore coastal and marine areas in East Asian Seas Region, EAS/35, phase 1........................... 35 6. June 1996 evaluation of project FP/EA/5101-1993-01-03 on the Eastern African coastal and marine environment resources database and atlas, EAF/14, phase 1 and 2.......................................... 35 /... 3 D. Regional seas programme...................................... 36 E. Global Programme of Action for the Protection of the Marine Environment Pollution from Land-based Activities...... 37 F. Capacity-building............................................ 38 G. Publications................................................. 39 1. H. III. IV. V. Impact................................................. 39 Organizational structures.................................... 40 1. OCA/PAC-Water branch institutional structures.......... 40 2. Financial arrangements................................. 42 3. Collaboration, cooperation and coordination............ 44 PROBLEMS AND CONSTRAINTS ENCOUNTERED............................... 45 A. Programme and project development and management............. 45 B. Inter-agency and Government cooperation...................... 46 C. Resource allocation.......................................... 47 LESSONS LEARNED..................................................... 47 A. Programme and project development and management............. 47 B. Inter-agency and Government cooperation...................... 48 C. Resource allocation.......................................... 49 D. Evaluation................................................... 49 RECOMMENDATIONS...................................................... 50 Tables Table 1 OCA/PAC-Water Branch. Changes in oceans programme related staff 1992 to 1997................... 52 Table 2 Environment fund programme activities expenditure........................ 53 Table 3 Trust fund expenditures.................................................. 54 Appendices Appendix 1 (in photocopy only) /... 4 Report outline and terms of reference.................................... 55 Appendix 2 (in photocopy only) Documents-reports, studies, publications................................. 60 Appendix 3 (in photocopy only) Memoranda and correspondence............................................. 66 Appendix 4 (in photocopy only) Annex to the report of the preliminary meeting of experts to assess the effectiveness of the regional seas agreements. UNEP/LBS/WG.1/1/3. Nairobi, December 1993............................... 83 Appendix 5 (in photocopy only) Recommendations of relevant evaluation reports........................... 96 Appendix 6 (in photocopy only) OCA/PAC-Water branch publications up-dated list Oct'97.................. 120 /... 5 EXECUTIVE SUMMARY 1. The oceans subprogramme no longer exists as such. It was a key element of the so-called sectoral approach followed by the United Nations Environment Programme (UNEP) to the environment agenda. Now marine and coastal activities are linked with those of the freshwater basins in an integrated approach to water management for sustainable development. This evaluation effectively looks back to see what lessons have been or can be learnt from what was generally regarded as a very successful UNEP activity, the regional seas programme, for which the UNEP Water Branch provides the secretariats in some regions. It is also an assessment of how oceans activities are faring in the first stage of integration of oceans and freshwater activities in a holistic water management approach, in which the effective integrating instrument is the Global Programme of Action for the Protection of the Marine Environment from Land-based Activities, for which the Water Branch also provides the secretariat. 2. UNEP initiated and promotes this concept of integrated management of watersheds, river basins, estuaries and the marine and coastal areas into which they flow, as a comprehensive practical approach to sustainable coastal management linked, as appropriate, to river basin management and land-use plans. This approach also applies to the special problems of small island developing States. In developing the successful regional seas programme over almost 20 years, as the cooperative regional framework within which to assess and promote marine environmental protection, the lessons learnt were put to good effect in 1993, in the follow-up to the United Nations Conference on Environment and Development (UNCED), to develop a global programme of action for the protection of the marine environment from land-based activities, which was adopted at the Intergovernmental Conference to Adopt a Global Programme of Action for the Protection of the Marine Environment from Land-based Activities, held at Washington, D.C., 23 October-3 November 1995. The regional seas programme provides the framework for implementing the first phase of the Global Programme of Action. The initiative was a direct response to the 1990 report of the joint Group of Experts on the Scientific Aspects of Marine Environmental Protection (GESAMP) on the state of the marine environment. It found that the major threats were not to the open seas but to coastal ecosystems from land-based point and non-point sources of pollution. Indeed, the Global Programme of Action calls for periodical reviews of the state of the marine environment, as well as regional implementation of actions plans on land-based activities. Work is already underway on a global assessment of land-based activities in 1998 and the state of the marine environment in 2002. 3. The International Coral Reef Initiative (ICRI) and the associated Global Coral Reef Monitoring Network (GCRMN) implement agreements under Agenda 21 through the sustainable use and conservation of national living marine resources, and in turn, are implemented through the regional seas programme. Priority threats have been identified in five regions, resulting in the development of strategies and action plans. The Global Plan of Action for Marine Mammals is being revised and refocused to deal with current threats. The Water Branch provides the secretariat. These three activities are global partnerships of Governments and inter-governmental, United Nations and non-governmental organizations. /... 6 4. All the activities described above constitute means of implementing the agreements of Agenda 21 and taking forward the conclusions of the special session of the United Nations General Assembly for the purpose of an overall review and appraisal of the implementation of Agenda 21, particularly those for which a sense of urgency was expressed. 5. Evaluation of the activities and projects relating to coastal and ocean management from 1992 to date identified highlights as well as constraints. The constant growth of the regional seas programme, which now has 14 regions encompassing about 150 countries, and the rapid development, adoption and implementation of the Global Programme of Action are the two highlights of the three bienniums. A disappointment, and a constraint to further progress, is that although a large body of knowledge and valuable experience in the development of coastal management schemes have been built-up, the ability and accumulated expertise to tackle complex issues and conflicts relating to the use and management of coastal zones has not been used and implemented on the scale required by national Governments or intergovernmental bodies in the regions, so as to make a significant impact and to ensure real progress on a global or regional basis. The means are available but not yet the will, although the development of the coastal resource atlas for East Africa is generating much interest in that region among research and development stakeholders, planners, Governments and industrial concerns, particularly in Kenya. This interest needs to be built upon. 6. The major constraints requiring urgent action have their origins, however, in the financial crisis which has beset UNEP in the current biennium as a consequence of the severe reduction in contributions to the Environment Fund. Unfortunately, UNEP was not fully prepared for the scale of this emergency, although the question was posed in the follow-up period to UNCED, namely, what would be the consequence of the serious constraints caused by unpredictable and inadequate resources? Unfortunately, the beginning of this biennium coincided with a 22 per cent reduction in funding for the combined water programme as compared with the previous biennial funding for the Oceans and Coastal Areas Programme Activity Centre (OCA/PAC) alone. It coincided with the establishment of the new Water Branch, with a new management team, through the combination and physical collocation of the Freshwater Unit with OCA/PAC. It coincided with the loss of experienced staff with oceans expertise, with the launching of the Global Programme of Action, a high profile activity, and with emerging problems of staffing in some of the regional seas coordination units, in part, the result of previous weak management in OCA/PAC. The combined effects of reduced funding and a high degree of uncertainty in the cash flow within the biennium, the erosion of the skills base, and all these other factors, mean that the Water Branch is effectively at critical mass. The priorities it has had to deal with have forced it to operate under crisis management conditions throughout 1996 and 1997. It is indeed a tribute to the efforts of management and staff that the Branch is functioning at all and has successfully managed to launch the Global Programme of Action. Important activities have had to be drastically cut back, however, and the situation must be retrieved by an improvement in funding allocation and increased recruitment to prevent further scoping back. This is considered to be of such critical importance to the future well-being of the Branch that most of the recommendations flow from these /... 7 issues. 7. The successes that have been achieved in coastal management through the regional seas programme have not thus far attracted, for the most part, the necessary financial commitment of Governments and donors to the trust funds to enable local successes to be translated into national planning, regional cooperation and global improvement. The funding crisis - for that is what it is - needs critical attention. All the schemes suggested to enhance the level of funding, by increased donor contributions, by environmental taxation, by larger contributions from non-governmental organizations and from industry (on the polluter pays principle) need to be examined, to investigate whether new and innovative fund-raising partnerships can be developed. If there is a role for the UNEP regional offices to play effectively, it is in the area of fund-raising, both to support the essential regional seas coordination and implementation network and also for the development and implementation of projects in the integrated water programme. 8. Most of the critical issues arising can be related directly to the level and uncertainty of funding, and the erosion of the staff resource to critical mass. Both problems need to be addressed urgently through the allocation of staff resources, up to four Professional staff members and a greater allocation of funds for the integrated water programme. Not only will this enable the Branch to focus its efforts more effectively, it will also free energies for development of new project proposals, the securing of more stable funding from non-UNEP sources and the provision of more technical support to the regions. A more balanced staff structure in the Water Branch and the enhanced operation of the regional seas coordinating units with high calibre staff will enable greater delegation of responsibility within the Branch in Nairobi, and to the regional coordinating units of the regional seas programme with respect to project and budget procedures. Having thus far been preoccupied with its financial uncertainties and the attendant problems of continually having to prioritize activities and to cope with the implementation of the flagship Global Programme of Action, the new Water Branch needs now to develop and project its new identity and image in keeping with the perceived benefits of the integrated water programme strategy. 9. It will be important to reappraise the future role and priorities of the regional seas programme within the evolving integrated water programme, in the circumstances of reduced financial resources and changing environmental priorities. The last expert review of the effectiveness of the regional seas programme was conducted in 1993, and it was thought that the then existing legal regimes were simply not adequate to deal with the threat of land-based sources of pollution to the marine environment, which was why the overall situation in the marine environment was far from satisfactory. Since then, protocols on land-based sources have been introduced and the Global Plan of Action has been launched. In the meantime, the range between a well developed, self-dependent region, such as the Mediterranean, and the others has widened further. Within a region there can also be a wide range of difference in national and environmental priorities, in political stability, wealth, and capacity at all levels. Regions which comprise a large number of States, say 10 or more, and embrace a large coastline or large hinterland or both, pose very difficult problems for coordination and multiple dialogue, even with the best of /... 8 modern telecommunications. It may be necessary, for example, to think in terms of reorganization into more manageable subregions, which would be more effective in terms of coordination and delivery. To achieve this, it might be necessary to work closely with a partner agency, such as the Food and Agriculture Organization of the United Nations (FAO), to make use of its effective country-oriented office network, especially in the developing world. 10. The suggestion is that, in view of these issues, uncertainties in the flow of funds, and the unlikelihood of their significant growth in real terms, UNEP and its Water Branch, in consultation with the governing bodies of the regions, should in the near future develop a clear set of priorities for the further development of the regional seas programme. Resources will have to be prioritized to meet the most pressing needs of Governments in the regions. This will be no easy task. It is essential to find a way in which the network can be efficiently maintained and developed in the face of reduced financial resources. 11. The regional seas programme still has much to offer in its catalytic role of encouraging integrated coastal management to ensure real progress on a regional and global basis in the protection of ecosystems and living marine resources, the prevention of coastal degradation and the reduction of marine pollution from the most important sources through integrated regional and national management systems. The regional seas network and activities are integral to all the present global initiatives which relate to the marine environment. Enhanced inter-agency cooperation and collaboration, through the pooling of resources where appropriate, is essential to this goal and to ensuring the optimal use of the limited resources. In the meantime, it is important to continue to strengthen and revitalize the current regional seas framework along the present lines, as resources permit, to prevent any deterioration of the framework or erosion of its credibility. 12. In order to release more productive time and resources for the operational units, and to reduce the cost of overheads, UNEP administrative mechanisms urgently need to be streamlined throughout the organization from the top down to branch and unit level, and UNEP should consider the potential operational benefits and, arguably, greater financial flexibility and fluidity of having four-yearly financial cycles covering two bienniums. I. A. INTRODUCTION Background 13. In 1972, the United Nations Conference on the Human Environment, held in Stockholm, 5-16 June 1972 (Stockholm Conference), adopted the Action Plan for the Human Environment, including the general principles for assessment and control of marine pollution. Subsequently, the United Nations General Assembly established UNEP as a focal point for environmental action and coordination within the United Nations system. The UNEP Governing Council chose "Oceans" as a priority area in which to fulfil its catalytic and coordinating role and, to that end, set up OCA/PAC. /... 9 14. From the outset, the oceans programme was conceived as an action-oriented, global programme, focused not only on mitigation but also on the causes of environmental degradation. It was implemented on a regional basis to control marine pollution and manage marine and coastal resources through a network of action plans under the regional seas programme, launched by UNEP in 1974. It also encouraged the regions to cooperate on common problems. Subsequently, this regional approach was endorsed by the Meeting of Government Experts on Regional Marine Programmes, convened by the Executive Director of UNEP in Nairobi, in 1982. It was found to be an effective way to protect and develop the marine environment and provide a sound basis for global action. By then the regional seas programme included 10 regions, with the participation of more than 120 coastal States. It currently includes 14 regions, 12 with action plans, with the participation of more than 150 coastal States. Interim arrangements for secretariats have been made and negotiations on institutional structures and action plans are under way in the other two regions, the southwest Atlantic and the east central Pacific. Exploratory steps are being taken to include the Arctic and Antarctic regions. 15. The 1990-1995 United Nations system-wide medium-term environment programme, published in 1988, was derived directly from the first system-wide medium-term environment programme, for the period 1984-1989, and was seen as the main means of harmonizing and coordinating the environmental activities of the United Nations system. It was intended, inter alia, for the 1990s to advance understanding of sustainable development and the means of achieving it, as well as understanding environmental problems that can hamper the achievement of sustainable development and the ways of solving or alleviating them. Relevant issues and actions for the human environment were first, coastal and island systems and, second, oceans. The latter was subdivided into three parts: regional environments, the global marine environment and living marine resources. The main thrusts of the system-wide medium-term environment programme, involving research, assessment, technical assistance and training, were directed towards achieving environmentally sound and sustainable development, reducing the impacts of environmental degradation and pollution and rehabilitating ecosystems that had already been degraded or polluted. /... 10 16. In 1990, GESAMP published a report on the state of the marine environment, for which input was provided by reports from regional seas task forces, giving global coverage. This report set the scene. It concluded that the open sea was still relatively clean. The major causes of immediate concern for the global marine environment were coastal development and the attendant destruction of habitats, eutrophication, the microbial contamination of seafood and beaches, the fouling of the seas by plastic litter, the progressive build-up of chlorinated hydrocarbons, especially in the tropics and subtropics, and the accumulation of tar on beaches. Concerns differed from region to region, reflecting local situations and priorities. Although public perception throughout the world still tended to give greater importance to other contaminants such as radionuclides, trace elements and oil, these were now regarded as being of lesser concern. The concern was that too little was being done to correct or anticipate situations that required action. Not enough consideration was being given to the consequences of coastal development. Activities on land continued with little regard for their effects on coastal waters. With the growth, in particular, of the human population in mind, the fear was that the marine environment could deteriorate significantly in the next decade unless strong coordinated national and international action was taken immediately. This required the concerted application of measures to reduce wastes and conserve raw materials. 17. In 1991, the Global Environment Facility (GEF) was set up for a three-year pilot phase with the participation of UNEP, United Nations Development Programme (UNDP) and the World Bank. It was envisaged as a collaborative international effort that would identify and support innovative environmental protection activities and, in the pilot phase, it focused on protecting biodiversity, reducing global warming, protecting international waters, and decreasing ozone depletion, all very relevant to the oceans programme. The independent evaluation at the end of the pilot phase noted, inter alia, that only a few of the GEF projects had actually been developed and placed in the context of the priorities defined by the policy frameworks of the existing regional programmes and agreements, mostly for international waters. Thus, the advantage offered by the existing infrastructures and cooperative arrangements of these programmes remained largely untapped. In addition, it was noted that restoring damaged systems should have high priority in the focal area of international waters protection. Subsequently, the GEF Operational Strategy adopted by the GEF Council in October 1995, set out ten operational programmes in the four focal areas. These are reviewed periodically to respond to changing circumstances and the programme issued in 1997 contains four programmes (programmes 2,8,9 and 10) relating to marine and integrated water issues. 18. In June 1992, UNCED, the so-called "Earth Summit", adopted Agenda 21, the Programme of Action for Sustainable Development, which was immediately endorsed by the General Assembly. Chapter 17 of Agenda 21 addresses the "protection of the oceans, all kinds of seas, including enclosed and semi-enclosed seas, and coastal areas, and the protection, rational use and development of their living resources". This chapter on oceans is the longest and one of the most complex chapters of Agenda 21 and includes the following programme areas: integrated coastal zone management; marine environmental protection, including land and sea-based sources of marine pollution; sustainable use and conservation of high seas living resources; /... 11 sustainable use of living marine resources under national jurisdiction; addressing critical uncertainties for the management of the marine environment and climate change; strengthening international, including regional, cooperation and coordination; and the sustainable development of small islands. The objectives were expressed in terms of States' commitments to the: integrated management and sustainable development of coastal areas and the marine environment; to the prevention, reduction and control of degradation of the marine environment; so as to maintain and improve its life-support and productive capacities; to the conservation and sustainable use of marine living resources on the high seas; to the conservation and sustainable use of marine living resources under national jurisdiction and other areas; and, in accordance with provisions of the United Nations Convention on the Law of the Sea on marine scientific research, to improving the understanding of the marine environment and its role in global processes. 19. UNCED confirmed the original mandate of UNEP but posed new questions: (a) How are environment and development linked? (b) How can UNEP contribute to the implementation of sustainable development? (c) How can UNEP avoid duplication of effort? (d) How can UNEP set priorities among growing expectations, and the serious constraint of unpredictable and inadequate resources? 20. Governments expected UNEP to reorient its programme to take account of social and economic factors in an integrated approach to developments and also to improve its effectiveness and responsiveness. Consequently, the scarce resources of UNEP had to be directed to those activities which would have an impact. It is significant, in this respect, that UNEP had recognized and endorsed the successful way in which integrated planning and management applied to specific geographic areas had been fundamental to the formulation and implementation of action plans for regional marine environments under its regional seas programme, and the model was used as a justification for the application of similar principles to the programme for environmentally sound management of inland waters (EMINWA). 21. The revision and adoption in 1992 by the General Assembly at its forty-seventh session of the medium-term plan for the period 1992-1997, followed the adoption of Agenda 21 at UNCED. It was published in 1993, and effectively provides the mandate for the oceans-related work programmes in the three bienniums 1992-1993, 1994-1995, 1996-1997 covered in this evaluation. The details of this mandate will be considered below. 22. UNEP introduced a new management strategy in 1993, which focused on achieving results providing responsive services, partnerships, regional delivery and integration. This was used as the framework for the realignment of the 1994-1995 programme, which led to the formulation of detailed individual programmes of work for each subprogramme. 23. In 1997, the special session of the United Nations General Assembly , for the purpose of an overall review and appraisal of the implementation of /... 12 Agenda 21, was convened to review and appraised the implementation of Agenda 21. This forum, the "Earth Summit + 5", was generally regarded to be a sobering reminder that little progress had been made over the previous five years in implementing key components of Agenda 21 and moving towards sustainable development. In respect of oceans and seas, it noted a need to continue to improve decision-making in this area at the national, regional and global levels. Urgent action was called for in the following areas: to ratify or accede to the relevant agreements and to ensure effective implementation of such agreements as well as relevant voluntary instruments; to strengthen institutional links between intergovernmental mechanisms involved in the development and implementation of integrated coastal zone management; to ensure a better identification of priorities for action at the global level; to prevent or eliminate overfishing and excess fishing capacity; and to improve the quality and quantity of scientific data as a basis for effective decisions. B. General objectives of the 1990-1995 system-wide medium-term environment programme 24. The general objectives of the 1990-1995 medium-term environment plan were the following: (a) For coastal and island systems, to achieve integrated management and sustainable development and rehabilitate them where they had been degraded; (b) For regional marine environments, to maintain and enhance the quality of the environment, including open seas beyond national jurisdiction as well as coastal and island ecosystems, to prevent and manage the environmental problems of regional marine environments, and to achieve the sustainable use of the resources of marine regions; (c) For the global marine environment, to improve the understanding of the role of the oceans in the operation of biogeochemical cycles and processes, to accumulate knowledge of the status of trends in and effects of ocean pollution, to strengthen international cooperation for the prevention and control of pollution from all sources, and to encourage the sustainable use of the seabed resources; and (d) For living marine resources, to protect and manage substantial examples of marine and estuarine ecosystems, to ensure their long-term viability to maintain genetic diversity, and to provide for the sustainable use of living marine resources and their habitats. C. Objectives of the medium-term plan 1992-1997 25. The revised plan was adopted by the General Assembly in December 1992, following the adoption of Agenda 21 at UNCED. 1. 26. Key issues The general key issues were identified as: (a) Environmentally unsound uses of natural resources that lessen the productive capacity of the biosphere; /... 13 (b) Pollution that threatens human well-being, health and even life itself; and (c) How to operationalize the firm linkage between environment and development into strategies for sustainable development that can help to combat poverty. 27. As GESAMP had concluded in 1990, although the problems related to marine environment had not changed much in the previous 20 years, the perceived major threats and solutions had changed significantly on the basis of assessments conducted over that period. It was clear that existing problems, as well as the first signs of emerging problems were most likely to arise in waters close to land. Nevertheless, a watchful eye still had to be kept on levels of contamination in the open ocean and there was still a need for the elucidation of major oceanic processes. Consequently, the overall priority was protection of the health of coastal waters, especially in closed and semi-enclosed seas, and the quality and resources of the coastal marine environment. The threats were seen to come from the continued growth of coastal populations, coastal recreation, industrial development and environmental degradation adversely affecting both exploitable living marine resources in coastal waters and marine biodiversity. 2. Overall strategy 28. The overall strategy of UNEP was summarized as environmental assessment, environmental management, and capacity building, environmental awareness and training. Specifically, as applied to the subprogramme, "Environmental management of oceans and coastal area management", the strategy was an interdisciplinary and integrated approach to elucidate ocean dynamics and to control and reduce marine pollution (most problems were thought to be regional and site-specific), through a globally coordinated regional approach. Effectively, this was an endorsement of the regional seas programme and its strengthening and development as the vehicle of implementation. At this stage, the programme encompassed more than 130 States, bordering 12 different regional sea areas around the world. 3. 29. Objectives identified for the subprogramme The following objectives were set for the subprogramme: (a) To improve regional and interregional cooperation in the protection and integrated management of marine regions, island ecosystems and their coastal zones; (b) To assist Governments in setting up a system for global ocean monitoring and to support the continuing development and enforcement of international law related to the protection of the marine environment; and (c) To promote the formulation and implementation of consistent /... 14 policies and programmes for the protection and sustainable use of living marine resources and their habitats, particularly marine mammals. 4. 30. was: Action proposed The proposed course of action for the medium-term period 1992-1997 (a) In the area of regional marine environments: (i) Continuing to coordinate the promotion and early stages of the implementation of regional action plans; (ii) Continuing to support the action plans for the protection of the marine environment and coastal areas, especially those which enjoy a high degree of commitment and involvement from the participating countries; (iii) Developing regional information and databases in coordination with existing information systems and regular reports on the state of regional seas and coastal areas; (iv) Assisting in developing the capability of countries gradually to assume full technical and financial responsibility for regional seas programme; and (v) Effectively applying the regional legal agreements relating to the protection of the marine environment; (b) In the area of the global marine environment, the UNEP strategy was centered on: (i) Integrating the national and regional monitoring and assessment programmes for coastal development and pollution abatement into a globally coordinated effort; (ii) Assisting in the formulation of a feasible integrated global ocean monitoring programme; (iii) Helping to establish a coordinated data-processing mechanism based on the GEMS; and (iv) Participating in sealevel-rise studies; (c) In the area of living marine resources, UNEP would continue assisting international efforts aimed at the conservation, management and sustainable utilization of marine living resources. Emphasis would be placed on: (i) The implementation of the Global Plan of Action for the Conservation, Management and Utilization of Marine Mammals; (ii) An ecosystems approach to the management of other marine resources; and /... 15 (iii) An assessment of the environmental impacts of coastal and marine developments of living marine resources with particular emphasis on aquaculture. D. Objectives of the 1992-1993 subprogramme oceans 1. Key issues 31. The major immediate events influencing preparation of this programme were the resolutions of the General Assembly on the management of hazardous wastes, biological diversity, the promotion of sustainable development, and the convening of UNCED in 1992. The programme was developed against a background of quickly changing perceptions and quickly emerging policies with regard to environmental priorities. 2. Objective 32. The subprogrammes objective was identified as the control of pollution in regional seas and proper management of their coastal areas. 3. Strategy 33. The strategy followed in the implementation of the subprogramme comprised the following elements: (a) Adoption of a multidisciplinary approach to identify sources of ecological deterioration and prevention rather than cure; (b) agencies; Major emphasis on closer working relationships with cooperating (c) Increased assistance for developing countries for institution-building and national legislation; (d) Promotion of technology transfer; (e) Elaboration of environment and economics issues; (f) Greater emphasis on the regional approach; (g) Integration of environmental considerations into development planning and activities; (h) Conservation of biological diversity within a broad social and economic context; (i) Minimization of hazardous wastes; and (j) Initiation of new convention on marine pollution. E. Objectives of the 1993-1994 subprogramme oceans and coastal areas: regional seas programme 1. Key issues /... 16 34. The 1994-1995 programme of work was regarded as transitional, incorporating the new UNEP management strategy which was intended to give greater consistency, transparency and effectiveness. An attempt was made to reorient the subprogramme explicitly towards sustainable development, responsive to Agenda 21 and the expressed needs and aspirations of Governments. Objectives were expressed in terms of "mission" and "needs". 35. Under the subprogramme "Oceans and coastal areas", there were four subprogramme elements: (a) Integrated coastal area management; (b) Living marine resources; (c) Land-based sources of pollution; and (d) Sea-level rise. 2. Objective 36. The objective of the oceans and coastal areas subprogramme is the achievement of environmentally sound and sustainable development at national, regional and international levels, ranging over policy analysis and development to capacity-building and resource mobilization. 3. Strategy 37. The stated mission of the regional seas programme is to support and coordinate on an international, regional, subregional, national and local level, the rational management of the marine environment as a whole and the coastal areas specifically. F. Objectives of the subprogramme element 1.1 of the 1996-1997 programme of work: Caring for freshwater, coastal and marine resources, as this relates to oceans 1. Key issues 38. As explained in the 1996-1997 programme of work under this programme element, freshwater hydrological cycles are inseparably linked with marine systems and the problems besetting river basins have a profound effect on the coastal and marine environment. Pollution from land-based sources is the most pressing problem affecting aquatic biological resources and biodiversity. Coastal ecosystems, especially those of small island developing States, are at special risk. 2. Strategy 39. The following strategies are advocated for the implementation of this programme elements: (a) Strengthen internationally coordinated action to alleviate common global problems assailing water resources; (b) Address problems besetting river basins and the coastal marine /... 17 environment through integrated management of watersheds and coastal areas, with focus on control of pollution from land-based sources; (c) Expand areas covered by regional seas conventions and action plans to include the respective river drainage basins; redesign action plans to focus on integrated management of river basins and coastal zones; (d) Connect existing action plans for the management of river basins, lakes and marine areas into organically linked management units; and (e) Base the integrated management of watersheds, lakes and marine areas on scientifically sound, realistic and policy-relevant assessments. 3. Objectives relevant to the oceans component 40. The following objectives were set for the implementation of ocean-related activities under this programme: (a) To develop tools and guidelines for the sustainable management and use of freshwater and coastal resources; (b) To promote international cooperation in the management of river basins and coastal areas focusing on land-based activities and the special needs of small island developing States; and (c) To support the regional seas conventions and action plans. 4. Purpose of evaluation 41. The assignment given to the present author was to evaluate the performance of the oceans subprogramme, covering the three work programmes of the 1992-1993, 1994-1995 and 1996-1997 bienniums, within the context of the United Nations medium-term plan for the period 1992-1997. The evaluation forms part of the original plan and timetable prepared by the Central Evaluation Unit at United Nations Headquarters, covering the three bienniums 1992-1993, 1994-1995 and 1996-1997. It is a requirement of the United Nations for submission to the General Assembly at its fifty-second session, in October 1997. 42. In broad terms, the requirements of the assessment are as follows: (a) To review the appropriateness of these subprogrammes, and the efficiency and effectiveness of the objectives; (b) To review the financial arrangements for the management of the subprogrammes and implementation of the projects; (c) To identify the problems and issues affecting the subprogrammes and present concrete recommendations; (d) To recommend the way forward for the subprogramme, taking account of reduced financial resources and the role of UNEP vis-à-vis the recommendations of the General Assembly at its special session for the purpose of an overall review and appraisal of the implementation of Agenda /... 18 21; and (e) To demonstrate how the subprogramme will remain relevant for the future. H. Methodology of evaluation 1. Terms of reference 43. The report outline and detailed terms of reference may be found below, in appendix 1 to this report. 2. Scope 44. During the period 1992-1997, subprogramme 4.0, "Oceans" for the 1992-1993 biennium, was succeeded by subprogramme 4.0, "Oceans and coastal areas", for the 1994-1995 biennium. As a result, however, of the revision, integration and reorganization of the UNEP programme, the merging of both the oceans and water subprogrammes, and the merging of OCA/PAC and the Freshwater Unit into a single Water Branch in January 1996, the oceans subprogramme was assimilated in the biennium 1996-1997 into programme element 1.1, "Caring for freshwater, coastal and marine resources", in subprogramme 1.0, "Sustainable management and use of natural resources". 45. The water subprogramme was previously evaluated in October 1993. In discussions with Mr. Backson Sibanda, Chief, Project Development and Evaluation Unit, and Mr. Walter Rast, Deputy Director Water Branch, it was agreed on 23 September 1997 and confirmed by memorandum of 24 September 1997, that the components in programme element 1.1 of the 1996-1997 work programme relevant for inclusion in the current oceans evaluation assignment should be 1.1.3, except "Conduct of regional training courses"; 1.1.4, except: "Development of strategic action plans for integrated river basin management" and "Development of a strategic action plan on sustainable tourism development in small island developing States"; 1.1.5 and 1.1.6. 46. For the purposes of this evaluation, the appropriate cut-off point for 1997 was taken as July, coincident with revision 3 of the umbrella project on support to the sustainable management and use of freshwater, coastal and marine resources. 3. Approach and sources 47. It was clear from the outset that, within the recently established Water Branch, which had embarked on an integrated water programme, there was no longer any in-depth, "institutional", first-hand experience and detailed memory of OCA/PAC activities and organization. This was a result of the changes in professional and support staff, management and programme that had taken place since 1992, and it contributed to the difficulties of the assignment. In order to try and bridge this gap to some extent, in as short a time as possible, feedback was sought from all the regional organizations of the regional seas programme, and from the well-respected Dr. Stjepan Keckes, who has remained relatively close to the programme since the end of 1990, either as a consultant in various capacities or as an experienced and expert participant in relevant international meetings, /... 19 workshops and working groups, etc. Dr. Keckes declined to comment, feeling that his contribution would not be seen as objective. As of 17 October, responses had only been received from the Black Sea, Caribbean, South Pacific, West and Central Africa and Mediterranean regional programmes. The last simply referred to the very recent evaluation of the Mediterranean Action Plan (MAP), which arrived too late to be considered in this evaluation, and the South Pacific programme could not meet the time-scale for response. The replies have been included in appendix 3 for reference. 48. The author has also culled relevant information on budget and activities prior to 1992 to provide a lead into the programme of work initiated in the 1992-1993 biennium, and has had the opportunity to look at the 1998-1999 programme proposals. 49. A desk evaluation was conducted, on the basis of the following: (a) A review of documentation, including previous relevant evaluation reports, work programme and budget documents, annual, biennial and project reports, OCA/PAC and Water Branch internal records, publications, reports, brochures and newsletters; (b) A routine Water Branch staff meeting, chaired by the Director; (c) Informal discussions with the Director, Deputy Director, programme officers and support staff in the Water Branch and staff in the Fund Programme Management Branch, the Environmental Law and Institutions Programme Activity Centre (ELI/PAC) and the GEF Coordination Unit; (d) Requests for specific feedback from key staff in all the regions of the regional seas programme and from Dr. Stjepan Keckes, solicited by fax and e-mail. 50. Appendix 2 lists the documentation and appendix 3 contains relevant memoranda and correspondence. 51. The programme has been assessed against the objectives set out in the medium-term plan and against those defined for each biennium, taking into account the strategies adopted, targets set, resources actually allocated and the outputs achieved, particularly in terms of training and capacity-building, information and publications, conventions and action plans, environmental assessments and regional delivery. II. A. PROGRAMME DESIGN AND ACCOMPLISHMENTS Appropriateness of the subprogramme 52. Although the combined period of the three bienniums, 1992-1997, is covered by the UNEP medium-term plan for the period 1992-1997, the appropriateness of the subprogramme is discussed in turn, for each biennium because of the significance of the decisions of UNCED and the consequential changes to the priorities and organization of UNEP. 1. 1992-1993 oceans and coastal areas subprogramme /... 20 53. The three subprogramme elements covering regional and global marine environments and living marine resources fully reflected the objectives identified in the 1990-1995 system-wide medium-term environment programme and the actions proposed in the 1992-1997 medium-term plan with the overall objective of control of pollution in regional seas and proper management of their coastal areas. The specific activities identified under the three programme elements, as set out in 16 specific annexes to the umbrella project providing support to the oceans and coastal areas, took account of recent resolutions of the General Assembly on, for example, biological diversity, the promotion of sustainable development and the management of hazardous wastes. A new annex dealt with sustainable development in small island States. 54. Thus, the programme was sensitive to changing perceptions and emerging priorities and tried to anticipate, to the extent possible, the outcome of UNCED. In particular, at the regional level, in the regional seas programme, considerable budgetary impetus was given to implementation of the Wider Caribbean Region Action Plan, to interregional activities, to development of the Northwest Pacific Action Plan and the Convention on the Protection of the Black Sea against Pollution and the Bucharest Declaration. At the global level, work was initiated on a new global conference on the sustainable development of small island developing States. 2. 1994-1995 oceans and coastal areas subprogramme for the biennium 1994-1995 55. The four elements covered under this subprogramme comprised integrated coastal area management, land-based sources of pollution, sea-level rise and living marine resources, in order of decreasing financial priority. This provided both continuity with the previous programme and responsiveness to the priorities of chapter 17 of Agenda 21, taking into account of previous commitments and the funding restrictions of UNEP. These elements addressed the general objective that the regional seas programme, in cooperation with other appropriate bodies, supported and coordinated on an international, regional, subregional, national and local level, namely, the rational and holistic management of the marine environment and specific coastal areas. Emphasis was placed on integrated management, sustainable development, cooperation, regional delivery and the achievement of results based on need. But the programme as a whole was regarded as a transitional one, following the decisions of UNCED and the reorganization of UNEP. 56. The element on integrated coastal areas management addressed the need for protection and integrated management, for the sustainable development of coastal and marine areas, for the strengthening and extension of regional coordination and for the integration of technical, institutional, economic, social, environmental, legal, and policy capabilities. 57. The element on land-based sources of pollution addressed the need to update the Montreal Guidelines, to prevent, reduce and control marine and coastal degradation from land-based activities and to quantify major pollutant risks from land-based sources, including rivers. 58. The element on sea-level rise addressed the need to assess the /... 21 influence of climate change and variability on sea-level rise and the role of the oceans as a global carbon sink. 59. Finally, the element on living marine resources addressed the need to review and assess the state of coastal and marine ecosystems and the living resources of critical habitats. 3. 1996-1997 subprogramme element: coastal and marine resources Caring for freshwater, 60. This new programme represented the integrated work plan covering marine, coastal and freshwater resources, designed to address the challenge of getting more results with fewer resources, following the merger of the oceans and freshwater activities into the Water Branch with effect from January 1996. The detailed activities support the perceived principal environmental challenges of sustainable management and use of natural resources, sustainable production and consumption, understanding the relationships between environmental degradation, pollution, human health and social and economic factors, and the continuing need for global and regional responses to environmental threats. These issues had of course evolved from previous biennial programmes, providing continuity with those outputs. 61. Components 1.1.1 and 1.1.2, of the subprogramme element have, to date been exclusively concerned which relate entirely to freshwater activities and are not considered further. The following four components relate to "Oceans": (a) Component 1.1.3 addresses the need to develop practical tools and guidelines for the sustainable management and use of freshwater and coastal resources, as well as new or revised contingency plans for national or regional oil or chemical spills; (b) Component 1.1.4 promotes the development and strengthening of regional agreements and comprehensive action plans for integrated river basin and coastal zone management, and resolution of conflicts, with provision for capacity-building, training courses and workshops, and pilot projects in the regional seas areas; (c) Component 1.1.5 focuses on land-based sources of pollution and the special needs of small island developing States, through the promotion of international cooperation under the new Global Programme of Action for the Protection of the Marine Environment from Land-based Activities; (d) Component 1.1.6 provides for the continuing support and coordination of the regional seas coordinating units, conventions and action plans and publications and for the updating of regional reviews on the state of the marine environment; The relevant priority issues addressed by the Oceans activities were: first, the consequences for marine resources and biodiversity of rapidly growing coastal populations, and, second, a holistic understanding of the impact of freshwater hydrological cycles and land-based sources of pollution on coastal marine environments and ecosystems, particularly those of small island States which were at special risk. Diagnostic studies were /... 22 particularly appropriate for the latter. 62. These evolving themes were given substantial impetus at the global and regional level by the emergence of the flagship activity, the Global Programme of Action for the Protection of the Marine Environment from Land-based Activities. This became the priority oceans-related activity in this biennial programme involving all the regional seas areas, and it was widely seen and promoted as the means of revitalizing the regional seas programme, by giving it new direction. 63. The basic strategy of the Global Programme of Action was to expand the areas covered by regional seas conventions and actions plans to include the relevant river drainage basins, to target the assessment and control of pollution from land-based sources, including river inputs, and to develop further the action plans to ensure their concentrating on the integrated management of river basins combined with relevant coastal zones. This would be supported by developing and making available new and practical systems and methods of holistic integrated management, embracing appropriate legal, economic and social aspects, which could be applied at regional, subregional and national levels. B. Efficiency and effectiveness of the subprogramme objectives 64. The next section provides a summary, on a biennial basis, of the achievements of the targets and activities of the subprogramme elements. 1. 1992-1993 subprogramme 65. At the end of 1992, within the period of this biennium, the medium-term plan for the period 1992-1997 was adopted. The OCA/PAC umbrella project, which had been running since 1990, was further modified through its annexes in 1993, to make new provisions for land-based sources of pollution and preparations for the Global Conference on the Sustainable Development of Small Island States. 66. The focus of the Oceans Subprogramme had been to strengthen regional and sub-regional cooperation to manage the environment in an integrated and sustainable manner. This took account of the impact of climate-change, sea-level rise, social and economic factors and marine biodiversity, and continued the consistent development of the network of agreements by which adjoining countries of a region could take joint action to conserve common seas. 67. The achievements in the regional context are summarized on a region by region basis: (a) The Mediterranean Action Plan was developed and strengthened further to include programmes to resolve issues of general environmental degradation caused by uncontrolled coastal development. Two draft protocols on offshore and hazardous wastes reached the final stages. Measures to protect against pollution by carcinogenic, mutagenic and teratogenic substances were approved in 1993. The foundations were laid for the development of environmental legal and policy issues in the MAP. Seven case studies were published, relating either to cost/benefit analyses on environmental degradation by land-based sources of pollution, or to /... 23 climate change, and four training courses were held on conservation. The contracting parties to the Barcelona Convention approved important proposals on; first, a new regional remote sensing activity centre; second, enlargement by three additional coastal States; and third, establishment of the Mediterranean Revolving Fund; (b) Under the Kuwait Action Plan, major activities covered an updated scientific report on the environmental consequences of the Iraq/Kuwait conflict, fund-raising for a rehabilitation programme, and cost-effective ways to tackle the long-term effects of large oil spills; (c) Caribbean activities concentrated on sea-turtle recovery plans for seven locations; the development of draft guidelines for managing protected areas in the wider Caribbean; and the preparation of databases covering land-based sources of pollution, environmental legislation and institutional capacity; (d) Under the West and Central Africa Region (WACAF) Action Plan, the contracting parties to the Convention for Cooperation in the Protection and Development of the Marine and Coastal Environment of the West and Central African Region (Abidjan Convention) endorsed recommendations for the protection and development of the marine and coastal environment and for the implementation of chapter 17 of Agenda 21 at the regional level. They agreed to establish a UNEP Regional Coordinating Unit for the WACAF Action Plan in Abidjan to strengthen cooperation in the region. A regional report on land-based sources of pollution was completed. National contingency plans for the control of marine pollution were updated for two countries and reports completed for the Gambia on coastal erosion and the economic contribution of the ocean sector to the gross national product; (e) Within the Action Plan for the protection, management and development of the marine and coastal environment of the Eastern African region, the OCA/PAC project on an Eastern African coastal and marine environmental resource database and atlas (EAF/14) was launched, to provide the region with the first natural resource atlas of its type, supported by the Belgian Government and the East African Trust Fund. It will now be completed in 1999, one year behind the original schedule, the delay being due to operational factors. The major business of the second Intergovernmental Meeting was to consider the establishment of a Regional Coordinating Unit in the Seychelles as secretariat to the Action Plan and Convention. Project EAF/5, on the protection and management of marine an coastal areas in Eastern Africa, was launched in 1993 and was interlinked with EAF/14 and the OCA/PAC Programme. The main objective was to develop self-reliance in the integrated management and sustainable development of coastal environments. It was planned in three phases: a pilot training phase, a planning phase and an implementation phase, and was a collaborative approach between UNEP, FAO, PAP/RAC and trust funds; (f) The East Asian Seas Action Plan activities progressed with the establishment by UNEP of a Regional Coordinating Unit in Bangkok, on the recommendation of the Coordinating Body on the Seas of East Asia (COBSEA). A project to develop management plans for endangered coastal and marine living resources was completed. A workshop in collaboration with the Economic and Social Commission for Asia and the Pacific (ESCAP) and South Asia Cooperative Environment Programme (SACEP) identified the need to /... 24 formulate national programmes on integrated coastal zone management and regional capacity-building. Work in progress related to development of a management information system, the feasibility of developing a comprehensive regional emergency response plan, and the preparation of a programme to control land-based sources of pollution; (g) In the Red Sea and Gulf of Aden Action Plan, national projects in Yemen and Egypt on marine ecosystems and resources were developed further to introduce a regional component; (h) Under the South Pacific Action Plan, the South Pacific Regional Environment Programme (SPREP) became an autonomous intergovernmental agency and an agreement was signed by 15 countries, covering biodiversity, climate change, coastal management and planning, the prevention and management of pollution, environmental education, training and information and regional and global issues; (i) For the South East Pacific, the main achievements of the Action Plan included a draft protocol to control transboundary movements of hazardous wastes, progress to extend the Action Plan to the Pacific coast of Central America through the incorporation of three new countries, with two more in the pipeline; 68. OCA/PAC substantially expanded its activities in the Black Sea region. The Bucharest Convention was signed in 1992 and the Odessa Declaration on the protection of the Black Sea was adopted, which established explicit environmental goals, a time-frame to mobilize resources and introduce the most effective measures, a common policy framework to respond to changing problems and a mechanism of regular evaluation of progress and amendment. Following the lead of UNCED, the Odessa Declaration sought to establish a sustainable process for enhancement and conservation to combat the crisis in the Black Sea environment. 69. In addition, the UNEP Governing Council approved the preparation of action plans for new areas not yet covered under the regional seas programme, the Black Sea and the Northwest Pacific. At Bangkok in November 1993, five States confirmed that they were willing to cooperate to protect the regional marine environment. 70. Among the global activities, the Joint International Atomic Energy Agency (IAEA)/International Maritime Organization (IMO)/UNEP Working Group under the auspices of the IMO Maritime Safety Committee (MSC) and Marine Environment Protection Committee (MEPC), drafted a Code for the Safe Carriage of Irradiated Nuclear Fuel, Plutonium and High-level Radioactive Waste in Flasks on Board Ships, which was approved by the IMO Assembly. Eleven regional task teams prepared overviews on the implications of climate change, as well as on social and economic activities and structures. 71. On living marine resources, arrangements were put in hand to revise the Marine Mammal Action Plan and to review legislative issues. The main issue was to clarify threats and hazards faced by marine mammals. The Convention on the Prohibition of Fishing with Long Driftnets in the South Pacific was adopted. A methodology was drafted and piloted in two /... 25 countries to provide States with guidelines to evaluate the actual contributions of the marine sector to the gross national product (GNP) and estimate the sensitivity of GNP to changes in the quality of the marine environment. 2. Expert assessment of the effectiveness of the regional seas programme 72. Agenda 21, in paragraph 25 of chapter 17, envisaged, inter alia, the need to assess the effectiveness of existing regional agreements and action plans, with the intention of finding ways to strengthen action to prevent, reduce and control marine degradation caused by land-based activities. The main reason for this approach was the view that the existing agreements were not effective as currently constructed and applied and that, irrespective of implementation, were inadequate to deal with current and emerging threats of pollution from land-based activities. 73. By its decision 17/20, of 21 May 1993, the Governing Council of UNEP requested the Executive Director to convene a preliminary meeting of experts to take account of the experience of regional and subregional agreements, in preparation for an intergovernmental meeting on the protection of the marine environment from land-based activities, to be convened by UNEP in 1995. The experts meeting was held in Nairobi, December 1993, and considered the experiences of other regions, such as the Baltic, in addition to that of the UNEP regional seas programme. 74. Appendix 4 provides the detailed discussion from ten regions in response to the attached questionnaire. For regions at different stages of development, it is not surprising that there was a wide spectrum of comment. In general, the conventions and action plans were regarded as positive developments and protocols were already developed, in hand, or envisaged, to deal with land-based activities and sources of pollution. The main constraints identified were financial, while problems were also posed by the lack of capacity and certain legal and political obstacles. 75. In considering the effectiveness of existing agreements, the secretariat's preliminary review held that, while there had been some positive achievements notably in the Mediterranean and Baltic, the overall situation was far from satisfactory. The evidence available suggested that the existing agreements, even in those cases which included specific protocols and programmes targeted at land-based sources of pollution, had not as yet had much effect in helping to improve the state of the environment or in preventing further degradation. This was not solely due to a lack of willingness or ability of States to take the necessary measures to implement them. There was a strong case that existing legal regimes, in the global, regional and national contexts, were simply not adequate to deal with the threat of land-based sources of pollution to marine and coastal areas. 76. The Expert Group made a long series of recommendations, beginning with the need for the regional seas programme to adopt the relevant chapters of Agenda 21 and for States to take action to reduce pollution to inland waters and lakes in regions where the management of river basins and related catchment areas influenced the health of the marine environment. Further recommendations covered regional cooperation in the global context and, in the regional context, monitoring and assessment, information, /... 26 awareness and public participation, management of marine degradation, and the means of implementation through capacity-building, training, technical cooperation, financial measures and enforcement. 3. 1994-1995 subprogramme 77. This biennium represented the transition from previous programmes which were considered largely sectoral towards a fully integrated programme to be launched in the 1996-1997 biennium. It was the first full opportunity to develop a programme with the implementation of Agenda 21 in mind. The major achievements are presented with reference to the activities of the subprogramme. 78. In the global and regional contexts, the Northwest Pacific Action Plan (NOWPAP) for protection of the coastal and marine environment was adopted in 1994. This first stage clearly demonstrated political will, but no convention was adopted and political factors have hindered progress on the incorporation of all the relevant countries. Financial arrangements for contributions to the trust fund were drafted subsequently and Water Branch provides the secretariat. 79. Negotiations were successful in promoting cooperation between Argentina, Brazil and Uruguay towards formal agreement on the protection and management of the south-west Atlantic region, which will become the thirteenth member of the UNEP regional seas programme. 80. In 1995, after many years of patient effort, the States of the south asian seas region adopted the South Asian Seas Action Plan, which included both institutional and financial arrangements for implementation. Capacity-building, land-based sources of pollution and oil spills were the themes of meetings and technical reports. 81. In the Mediterranean region, the contracting parties to the Barcelona Convention finalized important revisions to the Regional Convention and the Protocol for the Prevention of Pollution of the Mediterranean Sea by Dumping from Ships and Aircraft. A new Protocol concerning Specially Protected Areas and Biological Diversity in the Mediterranean, a new Mediterranean Action Plan, and a Mediterranean Commission on sustainable development within the MAP were developed. These revisions were intended to ensure that an integrated approach was developed for the protection and management of both the marine environment and associated coastal watersheds. Some 50 or more technical reports were produced and numerous training courses organized. 82. The Marine Environment Laboratory of IAEA held, inter alia, ten training sessions related to the Mediterranean Region and seven related to other regions. It re-issued, revised, prepared, edited or published some forty analytical methods for reference, produced numerous publications and undertook some 30 instrument-maintenance or quality-assurance missions. 83. Under the East African Action Plan, phase I of project EAF/14 completed the coastal resources geographical information system (GIS) database and maps for Kenya, including successful capacity-building. Extension to other countries was under way. Training workshops and technical reports were prepared, to cover a variety of activities. A /... 27 successful newsletter was circulated to maintain awareness and interest in the progress of the project. In project EAF/5 in Mozambique, the first version of a profile of the coastal district of Xai-Xai was published in 1994 in Portuguese and, in 1995, a new working team was formed to work on the coastal management plan. 84. Within the WACAF Action Plan, a training workshop related to the quantitation of land-based effluents was completed, together with seven technical reports covering regional and national requirements on pollutant loads and sources and coastal erosion. Unfortunately, the planned Fourth Meeting of the Contracting Parties could not raise a quorum. 85. In the wider Caribbean region, work for the Convention began on a Protocol dealing with pollution from land-based activities, and technical reports were produced ranging over integrated management plans for small islands, ecotourism, changing coastal land-use patterns and a comprehensive regional overview of land-based sources of pollution. 86. In the global context, seven technical publications and reports were prepared, covering regional seas programmes, the implications and impacts of climate changes, small island ecosystems and integrated coastal management. 87. The climax of the biennium was the unanimous adoption of the Global Programme of Action for the Protection of the Marine Environment from Land-Based Activities and the Washington Declaration by the Intergovernmental Conference in Washington D.C., October/November, 1995. UNEP was designated as the secretariat, to promote and coordinate the Global Programme of Action at national, regional, and global levels, in close cooperation with United Nations, inter-governmental and non-governmental agencies. This high priority task has fallen to Water Branch, to promote the objectives of sustainable development and integrated water management, in order to protect the marine environment from land-based sources of pollution in associated river basins and coastal watersheds. 88. Under the subprogramme element on living marine resources, support was provided for ICRI and the secretariat of the Marine Mammal Action Plan. Guidelines for the management of endangered sea turtles and a regional management plan for the West Indian manatee were produced for the wider caribbean region, and sea turtle recovery action plans were implemented in a number of countries as priority activities. 4. 1996-1997 subprogramme 89. Following reorganization and the creation of the Water Branch, merging freshwater and oceans activities, this was the first fully integrated biennial programme. Only the oceans-related elements are considered here. 90. The single major priority and activity in this biennium was the implementation of the Global Programme of Action for the Protection of the Marine Environment from Land-based Activities. UNEP proposals were considered by the Commission on Sustainable Development at its fourth session from 18 April to 3 May 1996. A revised plan for institutional /... 28 arrangements was submitted and adopted by the UNEP Governing Council at its nineteenth session, from January to February 1997. 91. The Global Programme of Action for the Protection of the Marine Environment Against Pollution from Land-based Sources required collaboration and cooperation throughout the entire United Nations system and, in providing the secretariat for the Global Programme of Action, UNEP coordinates the activities of partner agencies. It is establishing a clearing-house mechanism of major pollution sources (including a data directory and information network), and a mechanism for intergovernmental meetings to review progress on implementation of the Global Programme of Action. 92. The Water Branch, by means of an interim coordination office and acting coordinator appointed in May 1996, is coordinating implementation of the Global Programme of Action through the well established, institutional, organizational and legal infrastructure of the regional seas programme, which already provides a global dimension. At the time of writing, agreement had been reached to establish the permanent Global Programme of Action Coordination Office in the Hague (responsible to the Director of Water Branch), with support from the Government of the Netherlands. The key staff appointments are about to be made. In the meantime, it has been agreed that the Administrative Committee on Coordination (ACC) Subcommittee on Oceans and Coastal Areas will also act as the steering committee to facilitate technical coordination and cooperation and consider the Global Programme of Action on an annual basis. A technical meeting held in September 1996 prepared the preliminary specifications for the clearing-house, to be based, to the extent possible, on existing systems. 93. The first two of a series of workshops on implementation of the Global Programme of Action within the regional seas programme were held at the end of 1996 in the south-east Pacific and the Kuwait Action Plan and Regional Organization for the Conservation of the Environment of the Red Sea and Gulf of Aden regions. Four will have been completed in 1997, and four are now scheduled for 1998. These workshops constitute the first stage in adapting existing regional and national action programmes (or promoting and facilitating their development), in preparing regional assessments on the impact of land-based activities, and in making a global assessment of the effects of land-based sources of pollution on the marine, coastal and associated freshwater environment. It seems likely that regions which have already firmly established protocols relating to land-based activities, such as the Mediterranean and the Black Sea, may not host workshops in this initial series. 94. In response to the global assessment required under the Global Programme of Action, a GESAMP Standing Working Group on Marine Environment Assessments, with UNEP as the lead agency, was established in March 1996, with a sub-group to report on land-based sources and activities affecting the quality and uses of the marine, coastal and associated freshwater environment. Working procedures have been set up. The first task was to prepare assessments for regions where reviews did not previously exist; five reports had been drafted at the time of writing and preparation of the global assessment had begun. 95. Closely related to the Guideline activities, the Global International /... 29 Waters Assessment Expert Workshop on the Formulation of a Geographic Framework for the Analysis of International Waters Issues of Transboundary, or Regional and Global Significance took place in June 1997. It examined a number of case-studies on transboundary diagnostic analysis aimed at identifying the root cause of water-related (marine and freshwater) environmental problems in terms of market failures, inadequate policies and governance, and deficiencies in information, in order to enable the prioritizing of remedial actions. The Global International Waters Assessment, if adopted, will provide GEF with targets on which to focus its programme. 96. Around the regions, the Mediterranean has produced an updated survey of land-based sources and the relevant protocol was amended in 1996. A new Protocol on the Prevention of Pollution of the Mediterranean Sea by Transboundary Movements of Hazardous Wastes and their Disposal was adopted. A detailed evaluation of the Mediterranean Action Plan is the subject of a separate evaluation report. 97. In the Caribbean, the First Meeting of Legal/Technical/Policy Experts for the Development of a Protocol Concerning Pollution from Land-based Sources and Activities was convened and the Convention is negotiating a protocol concerning pollution from land-based sources and activities in the wider Caribbean region. A series of assessments is expected to be completed in the action plan, covering such issues as non-point sources, sewage, heavily contaminated areas, pesticides, tourism and data management, together with a comprehensive, revised and up-to-date assessment of the protected areas system in the wider Caribbean. The Caribbean Environment Programme for the period 1992-1995 has been evaluated and a draft strategy has been developed for the period 1996-2001. A number of activities have been delayed or deferred as a result of the funding crisis and earlier staffing difficulties in the Regional Coordination Unit. 98. In East Africa, a review of land-based activities affecting coastal waters of the region will be completed. Project EAF/14 has moved to phase 3, but phase 4 in Madagascar and Mauritius cannot be carried out because of lack of funds. There are also insufficient funds to publish the maps for all the countries of the region, although the database will be complete. In project EAF/5, the integrated coastal area management working team drafted the coastal profile for Xai-Xai district in Mozambique and a report was published on the development of a methodology for the rapid assessment of coral reefs for management purposes. The First Meeting of the Contracting Parties to the Convention for the Protection, Management and Development of the Marine and Coastal Environment of the Eastern African Region was held in March 1997, and the Regional Coordinating Unit was finally established in Seychelles with an interim coordinator. The Unit's first major activity was the preparation of a project development proposal, funded by GEF, to carry out a transboundary diagnostic analysis of the western Indian Ocean. 99. Progress in the Northwest Pacific had been relatively slow. In this biennium, the pace has quickened somewhat. A meeting of experts and national focal points was convened in preparation for the second Intergovernmental Meeting of the Northwest Pacific Action Plan in 1996. It seems unlikely that the third meeting will be held in 1997. The Action Plan was finally implemented by the first meeting of the Forum in 1997 to /... 30 discuss Marine Pollution Preparedness and Response. It agreed to establish a pollution reporting system, further focal points and an information system, to assess training needs and to consider the mobilization of resources in the event of an emergency. The delays in implementation of the Action Plan were due to delays in the preparation of a programme document, the protracted negotiation of contributions to the Trust Fund and political problems. 100. The Action Plan adopted by the Conference on the Human Environment in the South Pacific was revised in 1996. 101. In the south Asian seas region, plans to start pilot projects on integrated coastal area management and a regional programme for the control of land-based activities were dropped, because of the lack of financial resources and manpower. 102. In the south-east Pacific, protocols on environmental impact assessment in marine and coastal waters and on the prohibition of transboundary movements of hazardous wastes and their elimination are both in the process of negotiation. 103. The subprogramme element on living marine resources was marked by publications on the West Indian manatee, on the status of sea turtle conservation in the western Indian Ocean and on biodiversity of the seas, which collated the available information on a regional basis. Legal aspects of the protection and sound management of aquatic mammals were reviewed in depth, providing an input to the review of the Marine Mammal Action Plan and the revision of the Marine Mammal Action Plan was completed and submitted and is still under consideration. 1997 is the International Year of the Reef marked by progress in the establishment of the Global Coral Reef Monitoring Network Strategic Action Plan which has now been finalized for publication. The 1996 Report of the Session on Sustainable Development welcomed the 1997 International Year of the Reef and the goals of ICRI. The rapid assessment methodology for coral reef management was further developed and modified for wider application in the regional seas programme. C. Quality and utility of the subprogramme outputs 104. This section considers the outputs from the three biennial subprogrammes as a whole, considered in terms of their major evaluations and activities. Six previous evaluation reports are listed in appendix 2 in chronological order and were completed in the period 1990-1996. The conclusions and recommendations are pertinent to the present evaluation and are appended in full (appendix 5). 1. 1990 evaluation of the Global Plan of Action for the Conservation, Management and Utilization of Marine Mammals 105. Developed between 1978 and 1983, the Global Plan of Action for the Conservation, Management and Utilization of Marine Mammals was endorsed in 1984 by the United Nations General Assembly as a matter of high priority. The conclusions of this 1990 in-depth evaluation were in general terms, that implementation of the Global Plan of Action had not been satisfactory /... 31 and that its recommendations had, at best, only been partly carried out. The reasons were considered to be changing government priorities and lack of political will, severe budget constraints, insufficient clarity of action in the Global Plan of Action, and insufficient promotional effort for implementation by the collaborators. Specifically, the institutional arrangements for promotion were weak, there was no clear strategy for implementation with priorities, targets and timescales, no clear framework for action, no secure funding, and the Global Plan of Action concentrated on projects rather than strategic action. The contribution of UNEP as secretariat to the Global Plan of Action had been less vigorous than expected and had been unable to tackle the main functions of the secretariat. The Global Plan of Action needed substantial revision, backed by appropriate institutional and financial arrangements. 106. Following this negative evaluation, UNEP set up the Ad Hoc Planning and Coordination Committee identified in the Global Plan of Action. It set priority actions for the next two years on drift-net fishing. UNEP also agreed to set up an ad hoc scientific advisory committee to the Global Plan of Action, to have its first meeting in 1991. In addition, UNEP began to restructure the secretariat, set up memoranda of understanding with the bodies responsible for implementation of the Global Plan of Action, and establish a network of institutions with an interest in collaborating on implementation. A collaborative assessment of the status of marine mammals was set in hand for completion in 1991. 107. The fourth meeting of the Ad Hoc Planning and Coordination Committee in 1992 decided to revise the Global Plan of Action, particularly to include clarification of threats and hazards faced by marine mammals, but considered the structure still to be appropriate. The fifth meeting decided to implement the previous year's decision to revise the Global Plan of Action. At the sixth meeting in 1994, the secretariat introduced a paper reviewing the original Global Plan of Action and outlined proposed changes. The Ad Hoc Planning and Coordination Committee agreed that a consultant should produce a first draft of a revised document. At the seventh meeting, the first draft was reviewed and the eighth meeting reviewed the second draft in 1996. The revised Marine Mammal Action Plan was presented to the ninth meeting in 1997, and is being considered further. 2. December 1994 evaluation project FP/ME/5101-1993-03, on support of the IAEA Marine Environmental Laboratory for the regional seas programme 108. The evaluation considered the period 1993-1994. Overall, the project had made good progress and was a good example of interagency cooperation. The project was rated a success from the scientific and technical viewpoints, i.e., the development of reference methods and materials, data quality assurance, inter-calibration between laboratories, and training. The Marine Environment Laboratory was considered a good partner for UNEP. Better geographical coverage worldwide was required, however, and the Intergovernmental Oceanographic Commission (IOC) of the United Nations Educational, Scientific and Cultural Organization (UNESCO) needed to be more closely involved. The weaknesses were in project management: there had been a lack of control over project implementation; no programme /... 32 officer in OCA/PAC had overall charge; the 1994 work plan had not been revised and the Advisory Group had not functioned as intended. In addition, there were cash flow problems, relating to the release of funds from the Environment Fund and the Mediterranean Trust Fund, not entirely solved by the institution of the "umbrella" project mechanism. 109. The recommendations related to project development, financial resources and project management. It was essential to release and focus the expertise of the Marine Environmental Laboratory in support of the wider regional seas programme and to devolve some quality assurance activities for the Mediterranean to other laboratories in that region. UNEP needed to review the role and mechanism of its support for laboratories, based on the Mediterranean experience, to lead in the longterm to the establishment of comparable centres of excellence in other regions. It was essential to make provision for continuity of funding in the short and longterm, but related to justifiable, agreed, up-to-date and detailed work plans. It was important to explore urgently alternatives sources of funding to deal with financial uncertainty. Tighter project and financial management based on the umbrella concept was required, with clear overall project supervision to expedite precise work plans, project implementation and allocation of financial resources. The Advisory Group needed to provide the necessary policy guidance and ensure delivery. 110. The Mediterranean programme is the subject of a separate, in-depth external evaluation, currently under preparation. Therefore there is no need here to deal in detail with the situation since 1995. Suffice it to say that the Marine Environmental Laboratory continues to turn out high quality analytical and support work, reference methods and technical reports. But considerable problems remain with the timely provision of financial resources from UNEP, exacerbated particularly in the 1996-1997 period by the reduction in funding for Water Branch activities, incompatible with prior commitments made by previous OCA/PAC management. Even the publication of methods and reports, etc., has been hit by reduced funding. The services of the Marine Environmental Laboratory remain essential to the support of the regional seas programme, until other centres of excellence can be set up in the other regions to assure the quality of analytical output. UNEP will have to find a suitable mechanism to provide essential funding in the region of $200,000 per year. 3. October 1995 evaluation of regional support, regional cooperation and regional advisory services 111. This evaluation ranged over the period 1990-1995. It dealt with the activities of the six regional offices of UNEP, which are not to be confused with the regional seas programme of OCA/PAC. The relationship of the regional offices with OCA/PAC, wand then Water Branch, is, however, relevant to this evaluation, in particular, with respect to the successful implementation of the Global Programme of Action, to regional support for the regional seas programme and to assistance with fund-raising. 112. Over the period 1990-1995, the role of the regional offices changed significantly, in the aftermath of UNCED, with expanded responsibilities for identifying regional priorities, mobilizing resources, enhanced representation and direct management responsibility for the regional performance of UNEP. During the period under review, the new arrangements /... 33 were still settling down. Overall, the evaluation noted that the activities conducted by the two offices operating in Europe and North America were, of necessity, different from the four operating in the developing world. 113. The recommendations called for improved strategic and proactive planning at the regional level, more effective communications and flow of information to and from headquarters, the phasing out of regional advisory services, the strengthening of regional cooperation agreements as a means of improving identification of regional priorities and provision for increased overheads flowing from increased responsibility. 114. From the perspective of this evaluation, it has been very difficult to identify any really substantial benefits flowing from the Regional offices in support of OCA/PAC - or, as the case may be - Water Branch activities, particularly in relation to the regional seas programme, apart from the recent installation of the Global Programme of Action Coordination Office in the Hague. There is a strong feeling that there should have been much greater support for fund-raising from the regional offices, as the contributions of States to the Environment Fund fell and Water Branch was unable to provide the necessary level of support to consolidate previous achievements in the regional seas programme. In the implementation of the Global Programme of Action for the Protection of the Marine Environment Against Pollution from Land-based Sources, delays to the workshop for the south-west Atlantic can be attributed firmly to the Regional Office for Latin America and the Caribbean (ROLAC). In the Caribbean, there is concern that there has been inappropriate coordination and communication between the UNEP Regional Coordinating Unit for the Caribbean Action Plan and the Regional Office for Latin America and the Caribbean. 4. May 1996 evaluation of project FP/1111-1994-17 on public awareness of coastal and marine environmental issues, East Asian Seas, EAS/29, phase 1 115. The project began in October 1994. It was clearly relevant to Agenda 21 with outputs greater than envisaged. The project was rated a success: it led to spin-off activities and had good potential for further enhancing public awareness of the need to take proper care of the region's coastal and marine environment and protect biodiversity. Phase 1 fell four months behind schedule, however, owing to difficulties with implementation in Malaysia. 116. It was recommended that work should continue on further phases project, targeted to national and regional themes or activities and extended to all groups of people, in addition to youth. It was felt publicity material was required from (IPA), to reinforce the success project and its future potential. It remains unclear, however, what anything - has happened since. of the that of the - if /... 34 5. May 1996 evaluation of project FP/0201-1994-20 on the integrated management of water-sheds in relation to management and conservation of near-shore coastal and marine areas in East Asian Seas Region, EAS/35, phase 1 117. The project was thought to serve an extremely well-chosen purpose, with national, regional and global significance. It was considered a landmark undertaking, representing the first occasion on which two units of UNEP, the Freshwater Unit and OCA/PAC, had collaborated in cross-sectoral activities of regional scope to integrate the management goals of both the coastal and marine areas and their related catchment areas. Administrative delays caused a late start to the project, which began in February 1995, resulting in a much tighter implementation schedule. In turn, problems arose in the final stage of completion of project reports, due to technical editing delays and staffing difficulties, so that completion was more than three months behind schedule. Lack of integrated project management at the administrative level was considered to be the root cause of these problems. Implementation in the field, on the other hand, was well managed and successful. 118. The main recommendation was that resources should be provided to prepare follow-up phases for this project, to consolidate the achievements already attained. 119. The period under review covers the end of one director's term, an interim management phase, the merging of OCA/PAC and the Freshwater Unit into the single Water Branch, appointments to the new posts of Director and Deputy Director of Water Branch, and a number of changes in Professional staff. A consultant has been engaged to complete the report. 6. June 1996 evaluation of project FP/EA/5101-1993-01-03 on the Eastern African coastal and marine environment resources database and atlas, EAF/14, phases 1 and 2 120. Phase I of this project began in January 1993 and was piloted in Kenya for subsequent application in the other countries. The database and provisional maps produced were of high quality and detail and were thought to provide an excellent management tool for future development planning. All short-term objectives were achieved, except the final printing of maps and atlas. The delays occurring in phases 1 and 2 were considered to be the result of bureaucratic, technical and logistical constraints, rather than project mismanagement. More support and in-house training was urgently needed for the Kenya Marine and Fisheries Research Institute (KMFRI) staff, to enable them to cope with increased demands for information generated by the project. A well defined system and schedule of financial reporting was needed to avoid serious questioning of financial accountability by the donor organization. Although there were no irregularities, this problem and others could have been avoided by a memorandum of understanding at the commencement of the project and, had evaluation not been delayed from 1994 to 1996, the problems would have been rectified sooner. As a result of the financial questions, the cash-flow for this project was reduced by a total of $100,000 for 1995. 121. The recommendations were as follows: that a memorandum of understanding between UNEP and the donor, Belgium, should be drawn up /... 35 without delay; that a financial assistant should be assigned specifically to handle project EAF/14; that a Junior Professional Officer should be appointed to assist the Project Coordinator; that in-house training in GIS should be provided for four staff-members at KMFRI; and that UNEP should seek approval from the donor for any modifications to budget, or project content and phasing. 122. Partly as a result of the financial questions and partly as a result of a misunderstanding by the donor Government as to the distinction between funding for GEF and for project EAF/14, funding for the project was cut by $50,000 so that the money will run out in 1998, with loss of the project coordinator in 1997. A Junior Professional Officer, financed by the Belgian Government, is proceeding with the project on a two-year contract until June 1999. The project finance has been readjusted to cover this but there will be no funds to publish the atlas, although the digital database for each of the five countries will be complete and uniformly formatted to form a single consolidated database. New funds are needed to complete the project as planned and to reap the full benefits of its achievements. The project has developed excellent public relations, largely thanks to the circulation of its own newsletter. D. Regional seas programme 123. Since 1992, the effort to establish conventions and action plans has focused on the south Asian seas, north-west Pacific, Black Sea, south-west Atlantic and east central Pacific areas. It now covers 14 regions, including over 150 countries. The programme remains a successful, rational, structured approach to the coordinated assessment and management of coastal and marine resources and control of marine pollution. It is an action-oriented programme dealing with the causes, consequences and solutions to environmental degradation, but there are insufficient resources at present for it to operate with vigor in all regions. 124. Regional and subregional cooperation is a prerequisite for the development and implementation of actions to protect the environment and manage transboundary environmental issues in a given region. It facilitates the identification of these issues, the assessment of their importance and the prioritizing of appropriate action and is much more effective than isolated national initiatives. Such cooperation ensures more effective training, strengthens capacity-building, provides a mechanism for subsequent adjustment of adopted measures and early warning of emerging problems, and establishes a framework for global assessment and the introduction of new initiatives, such as the Global Programme of Action for the Protection of the Marine Environment Against Pollution from Land-based Sources. /... 36 125. The strength of the regional seas programme is that each regional programme is tailored ab initio to the needs of the region, as expressed by the Governments, and develops according to their collective will. The weakness is that the rate of progress may be too slow for the overall benefit of the environment. The cooperative agreement is usually embodied in a legal framework, a convention, supported by protocols and dealing with financing. The protocols variously deal with specific issues in different regions on an as-required basis, such as emergency response to oil spills, specially protected areas, the prevention of dumping, exploitation of the seabed, pollution from land-based activities and radioactive contamination. The cooperative actions or activities of the regional programme are laid out in the action plan and implementation is effected by nominated national institutions under the overall authority of the Governments party to the convention. The underlying concept is that these regions will develop self-dependence at different rates, supported by growing trust funds, as is demonstrated by a comparison of the highly evolved Mediterranean region with the emerging south-west Atlantic or east central Pacific regions. 126. There is clear evidence within the regional seas programme that such measures as transsectoral approaches, capacity-building, integrated environmental management and the sustainable management of resources were already being put in place in the strategy before they were widely promulgated elsewhere. 127. The actions and activities supporting the programmes, such as case-studies, diagnostic studies, pilot studies, full project development and implementation, workshops, training courses, technical support, coordination and networking, local environmental assessments, biodiversity assessments, regional overview assessments and public awareness projects, have all been essential to the building of capacity, the development of better integrated management tools and approaches, the provision of information to Governments, enabling them to set priorities for environmental protection, the formation of a global picture of the state of the marine environment and the campaign to inform the public, thereby enabling people to pressurize Governments to act in the interests of the environment. 128. The overall measure of the convincing strength of the programme's approach is that, over 20 years after the programme was set up in 1974, there are still new regions which wish to join. E. Global Programme of Action for the Protection of the Marine Environment from Land-based Activities 129. The Global Programme of Action for the Protection of the Marine Environment from Land-based Activities was adopted by 110 Governments in 1995. UNEP provides the secretariat to oversee implementation and one of its major tasks will be to address the global threat posed by persistent organic pollutants. 130. It is still too early to pronounce on this programme, for which an acting coordinator was only appointed in May 1996, entrusted with its implementation. Six regional workshops will have been held within the regional seas framework by the end of 1997, although this total is less than that originally envisaged. Thanks, however, to the considerable /... 37 priority attached by the UNEP Governing Council to this process, in the follow-up to UNCED, from 1993 work was of a high quality, achievements were significant and progress was comparatively rapid, through the preparations leading to an intergovernmental meeting in 1995, the detailed planning and development of the institutional arrangements, adoption, and implementation within existing resources. The process really began, however, with a UNEP Governing Council decision in 1982 to establish a Working Group of Experts in 1983, which resulted in the Global Programme of Action for the Protection of the Marine Environment against Pollution from Land-based Sources in 1985. Thanks to the high profile of this initiative, it has already led to the adoption of new protocols on land-based sources of pollution in four regions of the regional seas programme. 131. The usefulness of the Global Programme of Action is that it uses the regional seas framework and implementation takes place at national, regional and global levels concurrently. It is linked with the protection of the oceans, enclosed and semi-enclosed seas and coastal areas, and with the protection, rational use and development of their living resources. It is closely linked with integrated coastal area management, through basin management and land use plans and with protection of the marine environment from pollution from land-based sources, both of which relate closely to the issues facing small island developing States. These two aspects aim for the sustainable use and conservation of living marine resources, which are also objectives of ICRI. The Global Programme of Action also requires periodical reviews of the state of the marine environment, which will be executed through GESAMP, as well as a dialogue on the implementation of regional action programmes. F. Capacity-building 132. The OCA/PAC and Water Branch programmes over the period 1992-1997 have been successful in continuing to build and maintain capacity in the regions within budgetary and manpower constraints. The demand for training, technical support, and assessment has always been greater than the resources available, particularly during the current biennium, requiring much ad hoc prioritization. 133. The areas of expertise provided in support, guidelines, training courses and workshops have included, inter alia, integrated coastal areas management, e.g. coastal profiles; strategies and management plans; assessment and control of pollution; assessment and monitoring of the current state of the environment; conservation and management of coral reefs and marine mammals; impact assessment of climate change and adaptation strategies; hazardous waste management; promotion and transfer of environmentally sound technologies; prevention of and response to environmental emergencies such as oil spills; sustainable tourism; state-of-the-environment reporting methods; sustainable development indicators; data collection; processing and database management methods; GIS; information systems and networks; legislation and institutional arrangements for environmental management; valuation and accounting of environmental impact assessments; environmental objectives for sustainable development; and public awareness. Many of these training activities are conducted with partner organizations, such as UNESCO, UNDP, FAO, the World Health Organization (WHO), IAEA, IOC and the United Nations Industrial Development Organization (UNIDO). /... 38 G. Publications 134. The most recent catalogue of regional seas publications was No. 11, 1995. An up-to-date list (appendix 6) has been compiled for the purposes of this evaluation, itemizing the variety of publications over the period 1992 to date. A number of these publications clearly relate to activities completed in previous years. Output has declined, compared with the previous six years, which included a period of intensive preparation for and publication of the GESAMP report on the state of the marine environment, as well as emergency activities as a result of the armed conflict in the Kuwait Action Plan area. Some thirty publications were printed or prepared in 1991, together with three regional seas conventions and protocols, plus 46 other publications in the series UNEP Reference Methods for Marine Pollution Studies, forming part of the UNEP Regional Seas Reports and Studies. In 1996-1997, in particular, reduced funding has resulted in deferment of the publication of some reports and has prevented the Branch from making optimum use of IPA facilities and expertise. H. Impact 135. Continued support and development of the regional seas programme and framework has encouraged the development of new protocols, particularly on land-based sources of pollution, specially protected areas and emergency response, and has encouraged cooperation, conventions or action plans in the east Asian seas, the south Asian seas, the Black Sea, the north-west Pacific and the south-west Atlantic regions. 136. The regional seas network is fundamental to the successful implementation of the Global Programme of Action, which clearly represents the flagship activity within this period of evaluation. The emphasis on an integrated approach to land-based sources of pollution and sustainable development includes an assessment of the severity and impact of persistent organic pollutants. Important related developments were the Barcelona Convention for the Protection of the Mediterranean Sea Against Pollution in 1995, and the commitment under the Barcelona Resolution, to reduce emissions and discharges of, inter alia, persistent organic substances by the year 2005, and the follow-up, together with the International Expert Meeting on Persistent Organic Pollutants: Towards Global Action, held in Vancouver in 1995. 137. The period has seen patient efforts but slow progress by the UNEP secretariat towards the strengthening of the Marine Mammal Action Plan, by revising, refocusing, updating and completing a new action plan to deal with the new issues which have arisen since 1984, when the original action plan was adopted, such as incidental catches, mass mortalities, habitat loss, pollution and coastal degradation. The Mediterranean, wider Caribbean and south-east Pacific regional action plans have specific marine mammal components and are integral parts of the Global Plan of Action for Marine Mammals. /... 39 138. The Global Conference on the Sustainable Development of Small Island Developing States, held in Barbados in 1994, adopted the Programme of Action. The implementation of the Global Programme of Action gives special consideration to the small island developing States. Support is also provided for the implementation of regional seas protocols on specially protected areas and wildlife for the Caribbean and east African small island developing States, and the implementation of regional action plans and strategies in small island developing States under ICRI. 139. ICRI focuses on coral reefs and associated seagrass and mangrove ecosystems. The first international ICRI Workshop, held in Philippines in 1995, set in motion arrangements within the supporting framework of the regional seas programme to identify the priority threats to coral reefs and to develop and implement regional action plans through six regional workshops. I. 1. Organizational structures OCA/PAC-Water Branch institutional structures 140. Direction of the oceans programme has changed hands a number of times between 1992 and the present. The previous Director of OCA/PAC, appointed in December 1990, was expected to complete his term by January 1995, but a new appointment was not made and his contract was extended to April 1995. The Deputy Director remained in the capacity of Acting Director until the end of December 1995, when he took up an appointment in Bahrain. In response to UNCED, the Governing Council of UNEP adopted an integrated work programme. In support of this, the new Water Branch was formed through the merging of OCA/PAC and the Freshwater Unit in January 1996. The present Director took office on 6 January 1997 to head the new Water Branch, with virtually no useful overlap with the previous administration, and was joined by the new Deputy Director from the Freshwater Unit. The Freshwater Unit physically joined the OCA/PAC offices in the middle of 1996. Considerable professional staff changes took place about the same time, severely depleting the marine expertise. Consequently, the Freshwater Unit staff took up various marine-related coordination or focal point activities within the regional seas programme. This was a period of massive disruption in a small branch, and the consolidation of the two components in the new structure is still under way. 141. Table 1 shows the oceans-related staff changes between 1992 and the present. The high turnover throughout and, in particular, the depletion of staff with an oceans background in 1996-1997 and the loss of continuity is self-evident, virtually halving the experience and skills base in 1997, necessitating the assignment of staff from the Freshwater Unit to support the regional seas programme coordination and support roles. The position in 1996-1997 in Nairobi is actually worse than that shown in table 1. It has been exacerbated by loss of posts in the UNEP redeployment exercise, the transfer of three staff members to provide support and interim coordination in the regions, and staffing problems in some of the coordination offices in the regions, which have necessitated dismissals, placing further strain on financial and support resources. It is a tribute to the dedication of the management and all the staff that the Branch has remained functional /... 40 142. The Water Branch serves as the secretariat to the west and central Africa and north-west Pacific regions, and provides initial secretariat services in support of the south-west Atlantic and the east central Pacific regions. The regional coordinators for the eastern African, Mediterranean, wider Caribbean and east Asian regions report to the Director, Water Branch. In other regions, secretariats are headed by a Director or Secretary-General who reports directly to the relevant intergovernmental meeting. In addition, Water Branch provides the secretariats to the Marine Mammal Action Plan, The Global Programme of Action and GESAMP and is a part of the tripartite joint planning committee for the Marine Environment Laboratory of (IAEA). With implementation of the Global Programme of Action, four programme officers have now been assigned to the new Coordination Office in the Hague and the Coordinator will report directly to the Director, Water Branch. 143. The new water programme recognized that an integrated management strategy involves river basins and the coastal zone into which the rivers flow, the basis for the Global Programme of Action. The Global Programme of Action involves most United Nations agencies in implementation and thus, to facilitate implementation, consultations have been held with secretariats of regional programmes and a joint intersecretariat-interagency consultation was held in 1996. The former were concerned with interregional cooperation and cooperation with international organizations and the latter with the need to establish an interorganizational mechanism for coordinated implementation of The Global Plan of Action. 144. Water Branch is provided with the services of a Law Officer in the Legal Unit, and contributes the officer's salary, although there is some confusion among the parties as to what this service constitutes. Previously, the Law Officer was a programme officer located in OCA/PAC, and there are strong arguments: first, for the status quo, which provides effective legal support, review, supervision and enhanced experience for the law officer; and, second, for the Law Officer to be seconded to and located within the Water Branch, to provide instant access, direct line management, and ownership and to expedite handling of the expected increased legal needs in 1998 and beyond. This is a delicate staff and management matter which is purely for UNEP to resolve. 145. Good, prompt communication and consultation between Water Branch programme officers and ELI/PAC will avoid misunderstandings and possible resulting friction. For example, prior consultation over the proposed amendment of the Nairobi Convention, which has taken 11 years to come into force in the east African region, would have elicited the legal view that it was more effective (more environmentally effective and more cost-effective to make an accurate assessment of its strengths and weaknesses. The latter can then be addressed by updating protocols. 146. The 1996-1997 programme of work introduced the arrangement for the operational units to share, for example, the cost of posts in the UNEP regional organizations. It was generally not perceived as "value for money" by any of the contributing units including Water Branch. This universally unpopular initiative will be discontinued in the 1998-1999 biennium. /... 41 147. OCA/PAC and, subsequently, Water Branch produced a wide range of publications and reports, well written and informative. With greater support from IPA, the presentation and image of the documents could be made more attractive and a new style developed to project the new image of Water Branch. With the drastic budget reductions in the current biennium, some publications were deferred for budgetary reasons. Less resources were available, so that less assistance could be obtained from IPA. The 1998 United Nations Year of the Oceans offers an opportunity to redress the balance and proposals are in hand to use all aspects of the modern media to get the message across. 148. The last six years have seen a large increase in the number of projects initiated in OCA/PAC which were not formally closed, so that by 1996 these numbered in the region of 50. This seems to indicate poor management control in the period up to 1996 over the formal mechanisms of closing completed projects, discontinuity in responsible project officers as a result of staff turnover and preoccupation with other priorities. Although a fund management officer in OCA/PAC was designated to bring the situation under control, no real progress was made and steps are now being taken to redress the situation. 149. The current official filing arrangements within Water Branch are in need of urgent attention, following the merger of OCA/PAC and the Freshwater Unit. All current files are not centrally located and available and files removed from the filing room are not returned promptly. Programme officers have been allowed to indulge in the bad habit of keeping central files with their own files, which denies access, or makes access more difficult, particularly when absent on mission. In addition, at some stage, an attempt was made to recatalogue some OCA/PAC files, so that these are no longer identifiable by the file catalogue number. Files are closed and new sequence files opened, without completing the date of last entry on the previous file. In a situation of rapid turnover of staff, frequent absences on mission, and the acquisition of new responsibilities, it is essential that access to valuable information in previous files is not hindered. Until the present filing control initiative restores order to the Water Branch filing system, a designated member of the support staff should have the responsibility of ensuring that standard practices are followed for registering, cataloguing, tracking and gaining access to files. Ideally, there should be little need to maintain copy files, if the in-house system is efficient, but there is no reason why personal copy files should not be kept, if it gives a sense of security to the user, provided that the central files are intact and up-to-date. 2. Financial arrangements 150. The Oceans programme activities have been financed by the Environment Fund, regional trust funds set up for the coordination and implementation of regional activities and action plans and specific donor or multi-donor contributions to projects or activities. 151. Table 2 presents a summary of sources of expenditure from the Environment Fund for oceans programmes, from 1990 to the present, with expenditure under the umbrella projects shown separately. Table 3 shows the contributions from trust funds for the respective regions. The information was provided by the Fund Programme Management Branch. /... 42 152. Oceans received and spent a smaller proportion of the available Environment Fund from the 1992-1993 biennium onwards. OCA/PAC expenditure increased by about 3.7 per cent overall in 1992-1993, by a further 7 per cent in 1994-1995, equivalent to an increase of some $900,000, but the new Water Branch has faced at least an estimated 22 per cent reduction in expenditure in 1996-1997 for the combined programme, and the final reduction in the out-turn figures for the biennium may be even lower. The allocation for the combined oceans and freshwater functions of Water Branch in 1996-1997 was only some 88 per cent of the 1994-1995 allocation for oceans, whilst the total expenditure actually budgeted for Water Branch for 1996-1997 is only 78 per cent of the oceans expenditure in 1994-1995. All expenditure from the Environment Fund in 1996-1997 was via the umbrella project. Actual expenditure in 1996 for combined oceans and freshwater activities represented underspending against the approved budget of some $170,000, which was carried forward. 153. By August 1997, the total expenditure of $5 million, against the total expenditure budgeted for of $7 million, indicates the danger of an underspend in the biennium. The figures also show that less than half the expenditure budgeted for the year had been spent by 31 August. Whatever happens, considerable effort will be expended on setting up activities which can go ahead at short notice in the last quarter of 1997. The important point is that only these activities which can be initiated at short notice will benefit, which will not necessarily coincide with those of highest priority. 154. Unpredictability of funding for the biennium as a whole and the uneven cash flow within the biennium were major problems in 1996-1997, and demanded unprecedented and continuous efforts at all levels to handle the knock-on effects. From the programme management point of view, the problem was exacerbated by severe glitches and break-downs in the new financial management system introduced by New York for 1996-1997. Consequently, timely and accurate financial information has not always been available to the Branch, at the very time that there was a pressing need to prioritize activities and spending. Programme officers' timely decisions have the major impact on expenditure in a given year, and it is essential that they receive accurate monthly financial information related to allocations and expenditure on activities for which they are responsible, so that they can plan ahead. The present two-year time-frame is too short to accommodate the severe uncertainties experienced in 1996-1997. The Director requires similar user-friendly financial information for the Branch activities, to make maximum use of limited financial resources to ensure that the high priority activities can be initiated early in the biennium, particularly if they require a long lead time. 155. It is important to note also that, given the large overall reduction in the expenditure of OCA/PAC, and then of Water Branch, between 1992 and 1997, the UNEP charge-out rates for all staff continued to increase in an alarming manner. Much of this increase can be attributed to UNEP overheads, over which the operational units have no control. For example and this is not the worst case scenario - the charge-out rate for D1 and D2 posts increased between 1992 and 1997 by about 100 per cent. During a period of world recession, when organizations in the "real" world were acting to reduce overheads in the face of reduced income, UNEP seems to have allowed the opposite to occur. In these difficult financial /... 43 circumstances it is vital also that the operational units, such as Water Branch, continuously look for potential savings in the costs of their activities which can be allocated to more pressing needs. 3. Collaboration, cooperation and coordination 156. This requirement for collaboration and cooperation is essential, given the catalytic and coordinating role of UNEP and notwithstanding the fact that the oceans programme has always been action-oriented and results oriented (but in a much wider context than the UNEP "results" model). Indeed, OCA/PAC and Water Branch activities have always required a large measure of United Nations agency, government agency and non-government agency collaboration, cooperation and financial support, none more so than implementation of the Global Programme of Action. Thus, the current initiatives to promote agency-wide, international and regional cooperation have been noted above, under section E. The trust fund expenditures (table 3) from the regional trust funds administered by UNEP are testimony to both regional collaboration at all levels and successful delivery, totalling $27 million over the period 1992-1996, notwithstanding the fact that about 70 per cent is accounted for by the Mediterranean Trust Fund. Trust funds need to be enhanced. As pressure is placed on UNEP funds and, consequently, those of the operational units, there will inevitably be reduced availability of seed funds to prime or initiate activities and UNEP will continue to be looking for greater contributions from implementing agencies and other donors. There is, of course, a great danger that reduced funds consequently reduce the power of UNEP to operate in the catalytic mode, in that the financial capacity to influence events is diminished and credibility is lost, particularly if the priming funds expected are not forthcoming. It is important too that the six regional offices of UNEP, if they have any significance at all for the regional seas programme, should play an enhanced role in raising donor funds for the regional and subregional activities of Water Branch. /... 44 III. A. PROBLEMS AND CONSTRAINTS ENCOUNTERED Programme and project development and management 157. The last three bienniums have been characterized by a high degree of rapid change in all aspects of programme and project development and management. These changes have occurred in policy, where the strategy has shifted from a sectoral to an integrated and sustainable approach; in institutional arrangements relating to structural, financial and operational mechanisms and human resources; in the restructuring and redeployment exercises; in the needs, concerns and priorities of Governments towards environmental issues, which have not been matched by their contributions; in the shift of focus from the open seas, to coasts, to water basins; in the unpredictable fluctuations of the Environment Fund and cash-flow to programme and projects; in the consequential uncertainty and the need for frequent revision of priorities for programme and projects at all levels, particularly in 1996-1997; in the turnover and lack of continuity of programme and project officer staff and the loss of professional expertise, skills and experience, particularly in 1996-1997; at the sharp end, in the continual and changing need to replenish previously conferred training and skills (because of the movement of trained people to other work), in order to continue to reap the benefits from previous achievements; and in the certain loss of credibility which occurs with partners at the practical level when funds dry up and new initiatives inevitably have to be shelved, because it damages the image and perception of Water Branch and UNEP. 158. All these have created problems and constraints. A financial crisis is a very effective way of exposing all the inadequacies in the system, such as the lack of timely, accurate financial information in 1996-1997, the administrative burden, and slow procedures. In general terms, in order to cope with these problems, management and administrative systems at all levels need scrutiny throughout the UNEP organization down to branch level. They have to become much more responsive, less cumbersome and time-consuming. Productive time has to be enhanced. More control, with concomitant responsibility and accountability, has to be delegated, and slick prioritizing has to become a priority. Projects need to be even more highly focused and targeted to maximize the results from the solutions most appropriate to the problem tackled, in return for the least expended effort. It is important, too, in a reorganization such as the emergence of the new Water Branch, that the new organisation quickly establishes a holistic identity and a feeling of ownership by the participants, in order to facilitate and gain maximum benefit from the work of the integrated body. 159. The consequence of the financial crisis in 1996-1997 is that there are insufficient financial and manpower resources to complete the original programme and activity proposals. The main priority had to be to ensure that the Global Programme of Action was implemented, although even here some of the proposed workshops for 1997 have had to be deferred. Planning, in the accepted sense of the word, has not been possible. Crisis management has been the order of the day, in a constant process of reacting to the problems arising from all the factors discussed above. 160. The main constraints identified in the regions in 1993 (see section 2 /... 45 above and appendix 4), namely, financial, lack of capacity, legal and political, are broadly those that remain relevant today. It is essential to have dependable, able, experienced UNEP coordinators in the regional seas programme, operating at arm's length in the appropriate regions, in which the coordinator is responsible to the Director, Water Branch. Poor selection in the past has resulted in a number of dismissals having to be made in this biennium by the present Director. This does nothing for credibility in the regions, disrupts progress with action plans and diverts attention and effort away from the programme issues. 161. The newly reorganized Regional Coordinating Unit for the Caribbean Action Plan and the restructured Caribbean Environment Programme have, we may hope, put the Wider Caribbean Regional Coordinating Office back on track again, restoring confidence and improving the flow of funds in support of the Convention and its protocols. An important issue, which is essential to the performance of the office and to regional delivery, is the need, as confidence is restored, to delegate responsibilities to the regional office in order to improve project and budget approval procedures and to build successfully on the improvements which have already been achieved. 162. Previous lax management in the period 1992-1994 resulted in the accumulation of a large number of administratively unclosed projects. The backlog is still being cleared, but is hampered by the non-continuity of project officers from that period and, of course, it places an unnecessary, additional burden on already stretched current resources. 163. The concept of an "umbrella" project with subsequent revisions to cover new or changing activities was developed to overcome the problem of a slow and cumbersome mechanism for setting up projects from internal funds. As activities under umbrella projects grew in complexity and timescale, however, internal and external audits criticized this arrangement, being concerned about accountability. The OCA/PAC umbrella project, FP/5101-90-03, which was closed at the end of 1994, had gone through fifteen revisions in a span of five years, covering an expenditure of about $10 million. A new policy was adopted, requiring activities under umbrella projects to be completed within the respective biennium. This did not prevent the necessary follow-up activities from being initiated in subsequent bienniums, but it does seem to have prevented the ring-fencing of resources for long-term activities (such as support for the Marine Environmental Laboratory), and it has inflicted constraints on the type of project or activity which can be initiated in the climate of uncertain funding conditions, as experienced in the 1996-1997 biennium. B. Inter-agency and government cooperation 164. Progress with the development of conventions and action plans in the regions can be hindered by political disagreement. Countries where there is no sitting Government, such as Somalia, pose a problem for UNEP, whereas this poses no problem for FAO. Project EAF/5 is a good example, illustrating the different levels of collaboration and how the problems can be overcome. Preparatory work was begun in 1992 and the project commenced in 1993, initiated with trust and UNEP funds, with FAO as the implementing agency, and was the first time that such an arrangement was set up. In 1995, the project was able to continue as a result of the injection of /... 46 funds by the Swedish International Development Cooperation Agency (SIDA), to the Trust Fund. Cooperation among the east African countries is good but commitment to placing funds with the Trust Fund has not been consistent. The advantage of FAO is that it can use its country offices to monitor consultants, local experts and institutions, and can disburse the funds directly. 165. In the Caribbean, for example, the relationship between the UNEP Regional Coordinating Unit for the Caribbean Action Plan and some Governments and donors still needs to be improved. Aside from the weaknesses in national institutions and policies in the wider Caribbean region, however, there is counterproductive competition between United Nations organizations in the region. There should be a clear redefinition of the mandate of different United Nations and international agencies. At present, organizations like UNDP, the Economic Commission for Latin America and the Caribbean (ECLAC) and the World Bank are working with environmental projects with little coordination with regional environmental agreements. Sometimes it leads to wasteful duplication of activities. C. Resource allocation 166. Section D and table 1 present the picture of staff resources for the oceans programme from 1992 to the present time, outlining the factors affecting the reduction in staff resources and the consequences for the skills base, while table 2 indicates the reduction in supporting finance in 1996-1997. There are insufficient resources to carry out the programme as planned, so priority support has had to be provided to implement the Global Programme of Action, through the interim coordinator and the supporting team of two additional staff members. Staff have been seconded to the regions, such as the Caribbean, to help recover lost ground due to problems in the regional coordination office, whereas the UNEP financial contribution has now ceased. Two acting coordinators have been appointed to regional seas coordination offices from Water Branch resources. The oceans-related activities in the Branch are now at the level of critical mass and need to be augmented by 3-4 posts. Six Professional and about four support posts in total are required in the Hague to operate the Coordination Office for the Global Programme of Action. 1996-1997 has seen publications substantially reduced, owing to lack of funds, and the support and expertise which might have been expected from IPA was not forthcoming. 167. OCA/PAC, and subsequently Water Branch, have been successful in winning GEF projects and the Branch is actively developing new proposals to submit for support from GEF. There are two important constraints. The GEF financial year is six months out of phase with the UNEP financial year, and the manpower commitment to support implementation of a GEF project is of the order of 0.5 persons per year per project. IV. A. LESSONS LEARNED Programme and project development and management /... 47 168. The regional seas programme has provided a successful regional and sub-regional cooperative framework for the implementation of regional and global action plans covering the whole spectrum of protection of marine and coastal environments, ecosystems and living marine resources in an integrated way, with the aim of preventing degradation and encouraging sustainable development. The regional framework concept or model was recognized for adoption in the EMINWA project and was essential for implementation of the Global Programme of Action given the constraints of working within existing resources, and is essential for the next global assessment of the state of the marine environment. It must not be neglected but continue to be adapted and developed to meet the changed circumstances of severe financial constraints and changing priorities. 169. The problems experienced over fund management issues, such as with project EAF/14 see section 6 above), and the difficulties experienced in 1996-1997 with the unpredictable and late release of funds, has resulted in pleas for a more transparent budgetary process, for more control within the Branch over financial management, and for an explicit presentation of the make-up of fixed costs, overheads and charge-out rates to provide the transparency desired. Coordination and technical expertise support in the regional seas programme has to be linked to financial support, in order to get projects under way in a meaningful and appropriate time-scale related to the urgency of the problem, otherwise credibility is lost. Further effort has to be directed towards fund-raising for the trust funds, in order to maintain the momentum of projects initiated with UNEP seed finance. Given the priorities urged on Water Branch, the financial allocation has to be at least commensurate with the minimum resources needed to implement those priorities. 170. In view of the large budget cuts in 1996-1997, it is essential to have a well established and carefully constructed set of priorities for programme activities within different funding scenarios, depending on the level and the flow of funding during the biennium, as is being done for 1998-1999. Most progress seems to have been made where the conditions of good cooperation prevail, and applied and highly focused projects find favor with Governments in the regions because the outputs are obvious and relevant to national or regional issues. 171. It is essential to have reliable and experienced staff as regional coordinators who can coordinate regional programmes successfully at arm's length from headquarters and careful selection procedures to identify the appropriate candidates must be followed. In the past, recruitment seems to have fallen below the minimum acceptable standards in some of the regions, so that the present Director has had to dismiss staff. In planning, setting up the institutional arrangements and implementing the Global Programme of Action, UNEP has demonstrated that it can work quickly and responsively. On the other hand, in taking seven years to revise the Marine Mammal Action Plan, it has also demonstrated that due process can be quite slow, particularly when there are gaps in the continuity of the secretariat. B. Inter-agency and government cooperation 172. Development of the Mediterranean to the present level of sophistication took patience, considerable technical support, coordination, /... 48 financial support and interagency cooperation. It is highly unlikely that this level of input will ever again be possible from limited UNEP resources. Development of other regions to the self-dependent mode will require an extensive cooperative effort from the respective Governments to enhance the trust funds to achieve this, which will require greater effort on the part of UNEP to encourage fund-raising, as well as the in-kind contribution of the expertise and technical support of the UNEP Water Branch. Donor Governments or agencies must be kept informed about financial matters, project progress, and project modification, according to the terms of the respective memorandum of understanding, otherwise funding may be jeopardized. The experience of the UNEP Regional Coordinating Unit for the Caribbean Action Plan is that there should be improved coordination regarding environmental issues among United Nations Agencies working in the region and that these agencies may need some changes to their mandates. C. Resource allocation 173. Input to the oceans-related part of the Water Branch programme has sunk to critical mass and requires the allocation of additional staff resources, to enable the programme to be delivered on a reasonable time-scale and to maintain its credibility. 174. Good financial information is essential if maximum use is to be made of the limited resources. UNEP overheads must be brought under control to enable a greater share of the Environment Fund to be directed towards productive activities. 175. In order to make the best use of the expertise available from ELI/PAC and the Fund Programme Management Branch to avoid potentially damaging misunderstandings, it is essential to consult with these organizations at the earliest possible stage and to establish an agreed and lucid strategy for dealing with the particular issue in hand. 176. Fund-raising for regional activities, particularly in those regions willing to cooperate actively, must be enhanced. The conventions have shown themselves to be very responsive to new initiatives such as the adoption of new protocols dealing with land-based sources of pollution. D. Evaluations 177. Evaluations need to be preprogrammed into budgets, to avoid the problem of unforeseen expenditure. There were a number of points of confusion arising in respect of this evaluation which could probably have been avoided by better communication. It is clear from previous correspondence between Water Branch and the Project Design and Evaluation Unit that the evaluation would only be conducted on the oceans part of the current subprogramme. What was not apparently understood in Water Branch was that the evaluation would also consider the oceans subprogrammes for 1992-1993 and 1994-1995. It only became clear to the evaluator at the beginning of the evaluation in Nairobi that the oceans components and elements of the 1996-1997 programme of work had to be teased out of the integrated water programme. Perhaps as a consequence of the confusion, no systematic identification and collection of relevant documentation covering the three bienniums had been carried out in advance for the purpose of the evaluation. The mechanism for implementing the evaluation on-site needs to /... 49 be overhauled so that the essential information immediately pertinent to the evaluation can be identified in advance and made available to the evaluator at the outset. 178. Ideally, this evaluation should have been carried out at the end of 1995, prior to integration of the water and oceans programmes. This would have avoided the present rather untidy arrangement of disentangling the oceans components of an integrated water programme. It represents a contradiction in terms. The lesson to be learnt in this case is that the subprogramme evaluation process or mechanism should be more sensitive to the evolving programme and changing circumstances, so that subprogrammes are evaluated at the most apposite time and not according to a predetermined, inflexible programme or timetable, unresponsive to changing circumstances. This facility is available but was not activated at the time that the rationalization and integration of the OCA/PAC and freshwater programmes were being considered as a matter of policy. Of course, any move towards a more flexible approach must take account of the need for budgeting for evaluations. The appropriate operational unit, in this case Water Branch, and the Fund Programme Management Branch need to be made aware by the Project Design and Evaluation Unit of all forthcoming evaluations in the course of the year or biennium, which need to be flagged up and included when the programme and the budget is being assembled. This was known in 1992 and both the oceans programme and the Fund Programme Management Branch were given this information at the time; but also every biennium the evaluation plan is given to all programme managers. Programme managers do not use the information in planning their activities. V. RECOMMENDATIONS Recommendation 1 179. Since many of the issues arising can be related directly to the low level and uncertainty of funding and the erosion of staff resources to critical mass, both problems need to be addressed urgently through the allocation of more staff-members, up to four Professionals, and a greater allocation of funds for the integrated water programme. Not only will this enable the Branch focus its efforts more effectively, it will also enable energies to be released for the development of new project proposals, for the security of more stable funding from non-UNEP sources and for the provision of more technical support to the regions. Recommendation 2 180. The role of the UNEP regional organization, the six regional offices, needs to be clarified, particularly with respect to encouraging regional cooperation and fund-raising in support of the regional seas programme. Recommendation 3 181. UNEP administrative mechanisms urgently need to be streamlined, throughout the organization down to branch and unit level, to reduce overheads and to release more productive time and resources for the operational units. /... 50 Recommendation 4 182. UNEP should consider the operational benefits, and arguably greater financial flexibility and fluidity, of having four-yearly financial cycles covering two bienniums. This recommendation is partly covered by the management response to the 1996 annual evaluation recommendation on the same subject. Recommendation 5 183. A more balanced staff structure in Water Branch and the enhanced operation of the regional coordinating units with high calibre staff will enable the greater delegation of responsibility within the Branch in Nairobi and to the regional coordinating units of the regional seas programme with respect to project and budget procedures. Recommendation 6 184. A Water Branch image should be developed in keeping with the perceived benefits of the integrated water programme strategy. Recommendation 7 185. The future role and priorities of the regional seas programme within the evolving integrated water programme should be reappraised in the circumstances of reduced financial resources and changing environmental priorities. The last expert review of the effectiveness of the regional seas programme was in 1993 (see section 2 above). The secretariat's suggestion was that the then existing legal regimes were simply not adequate to deal with the threat of land-based sources of pollution to the marine environment. This was thought to be a primary reason why the overall situation in the marine environment was far from satisfactory. Since then, protocols on land-based sources have been introduced and the Global Programme of Action has been launched. In the meantime, the range between a well developed, self-dependent region such as the Mediterranean, an established but sluggish region like west Africa, a cooperative but relatively poorly endowed region like east Africa and an emerging region such as the south-west Atlantic, has widened further. Within a region there can also be a wide range of difference in national and environmental priorities, in political stability, wealth and capacity at all levels. Regions which comprise a large number of States, say ten or more, and embrace a large coastline or large hinterland or both, pose very difficult problems for coordination and multiple dialogue, even with the best of modern telecommunications. It may be necessary, for example, to think in terms of reorganization into more manageable subregions, which would be more effective in terms of coordination and delivery, and to work with a partner agency such as FAO to make use of its effective country-oriented office network, especially in the developing world. 186. In view of these issues, uncertainties in the flow of funds, and the certainty that they are unlikely to grow significantly in real terms, UNEP Water Branch should, in consultation with the governing bodies of the regions, develop in the near future a clear set of priorities for the further development of the regional seas programme and the targeting of resources which meets the most pressing needs of Governments in the /... 51 regions. This will be no easy task. It is essential to find a way in which the network can be efficiently maintained and developed in the face of reduced resources. The regional seas programme still has much to offer in its catalytic role of encouraging integrated coastal management and making real progress on a regional and global basis in protecting ecosystems and living marine resources, preventing coastal degradation and reducing marine pollution from the most important sources through integrated regional and national management systems. The regional seas network and activities are integral to all the present global initiatives which relate to the marine environment. Enhanced inter-agency cooperation and collaboration, through the pooling of resources where appropriate, is essential to this goal and to maximizing use of the limited resources. In the meantime, it is important to continue to strengthen and to revitalize the current regional seas framework along the present lines, as resources permit, to prevent any deterioration of the framework or erosion of its credibility. Recommendation 8 187. Continued efforts should be made to press forward with the implementation of the Global Programme of Action along the present lines and proposed timetable, with the establishment of the secretariat in the Hague and with implementation of the clearing-house mechanism. Recommendation 9 188. A realistic, deliverable financial arrangement should be negotiated with IAEA and other interested parties, for continued support by UNEP, in partnership with other potential donors, to maintain the basic support required from the Marine Environmental Laboratory for the regional seas programme, and continued efforts should be made to encourage similar centres of excellence to fulfil a comparable role in other regions, in line with their capabilities. /... 52