:Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 1 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari 1. PURPOSE This document defines the PCR (Process Change Request) process for Suppliers to MAYSTEEL LLC. The PCR process controls changes to MAYSTEEL LLC products, supplier materials or processes. The PCR review process is designed to evaluate proposed changes while providing an assessment of risk to product reliability and compatibility with other manufacturing processes. Changes implemented without PCR notification and approval may generate non-compliant product material(s) rejectable by MAYSTEEL LLC. 2. SCOPE 2.1 The PCR procedure applies to suppliers of component parts and partial or finished assemblies used to produce MAYSTEEL LLC products whether supplied to MAYSTEEL LLC or to a MAYSTEEL LLC Subcontractor. 2.2 The PCR procedure applies to all MAYSTEEL LLC product components and finished assemblies unless specifically waived by MAYSTEEL LLC. Lack of a waiver shall default to the requirements of this specification. 2.3 The PCR process does not apply to materials, services or finished products purchased by MAYSTEEL LLC but not directly used to manufacture or deliver MAYSTEEL LLC products unless so designated in the related purchase documents. 3. DEFINITIONS 3.1 PRC: Change to a process as identified in this work instruction 3.2 PCR Change Request Form: document used to request and detail the change to process 3.3 POR: Supplier Process Of Record, documentation provided by the supplier that identifies in detail the manufacturing process used for parts, assemblies and finished goods supplied to MAYSTEEL LLC. 4. FORMS The following documents are referenced in this specification; 4.1 MAYSTEEL LLC ECN Work Instruction 4.2 Part or Product specific requirements specifications 4.3 ASL Approved Supplier List (MAYSTEEL LLC confidential) 4.4 MAYSTEEL LLC SPOC manual 4.5 Process Change Request Form 5. INPUTS 5.1 5.2 5.3 5.4 Process Change Request from a supplier Process Of Record for Supplier MAYSTEEL LLC specifications and documentation MAYSTEEL LLC customer specifications and documentation 6. SCHEMATIC OVERVIEW: Diagram of PCR operational flow. :Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 2 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari Fig 1: Schematic of PCR process flow Mfgr wants to request a change in manufacturing process or specs Mfgr prepares a PCR request detailing change Gather requested non-product data PCR REQUEST SUBMITTED TO Maysteel Quality Engineering Review Engineering Review Purchasing Review PCR Acceptable No Supplier Mgmt Review Need more data Yes No Maysteel Personnel generate ERN to implement PCR PCR Rejected Notify Submitter Change Implemented Notify Submitter and all other affected Suppliers Yes :Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 3 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari 7. Procedure 7.1 A PCR form is required to be completed by the responsible Supplier and submitted to MAYSTEEL LLC for any process, equipment, or material change that has the potential to affect the form, fit, function or reliability of any MAYSTEEL LLC product. Since not all ultimate product effects are apparent when evaluating the impacts of a change, it is required to err on the side of caution and notify MAYSTEEL LLC though the PCR process of all Supplier manufacturing changes. 7.2 A PCR must be sent to MAYSTEEL LLC before implementation of a change. MAYSTEEL LLC will review and respond as soon as possible. 7.3 Initial Request: The supplier will initiate a PCR request by describing the proposed change, the expected effect and providing reliability or performance data to support the request. See Appendix A for a PCR request form. 7.4 MAYSTEEL LLC Review: The request will be processed by the appropriate Supply Chain Manager who will review the PCR request and forward copies to MAYSTEEL LLC Project Engineering, Quality Engineering, and Purchasing for additional review. All sections will determine the acceptability of the request. MAYSTEEL LLC may also contact other suppliers of a MAYSTEEL LLC product number that would be affected by a PCR request for comment. 7.5 Response to PCR: After review, MAYSTEEL LLC will respond to the PCR request as follows; 7.5.1 Accept: The requested change is determined to be acceptable to MAYSTEEL LLC. The Supply Chain Manager will notify the request initiator and will begin the ERN process if required to incorporate the change into the necessary product specs or supplier Process of Record (POR). PCR or ERN approval is required prior to implementation. All suppliers will be notified of the changed product requirements when the PCR or ERN is complete. Only the initiator will be notified regarding a PCR change. A phase-in plan may be developed as necessary. 7.5.2 Reject: MAYSTEEL LLC determines that the request is unacceptable. The Supply Chain Manger will notify the request initiator of MAYSTEEL LLC decision. MAYSTEEL LLC may, but is not required to, share the reasons for refusal. 7.5.3 Request more information: MAYSTEEL LLC determines that additional information is needed to make a decision. The Supply Chain Manager will contact the request initiator to inform of status and request the desired information or, at MAYSTEEL LLC option, authorize testing by use of a controlled lot to use the requested change. The initiator may elect to collect the information and re-submit the PCR request or to cancel the request. No product or process change is allowed without the completed PCR or ERN documentation. 7.5.4 Additional Information Only- MAYSTEEL LLC will contact the submitter with a request for additional information. No product testing is required or authorized. 7.5.5 Additional Information through product testing – will generate a request for suitable test lot(s) with the requested change to be processed. The request will include PCR data collection requirements and acceptance criteria. The request will also document the product acceptance and field release criteria. On successful completion of the request the PCR will be approved and implemented. 7.5.6 PCR Documentation: Upon accepting a PCR, the Supply Chain Manager will be responsible for submitting the necessary PCR / ERN requests to implement the requested change. :Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 4 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari 7.5.6.1 Supplier POR – Changes to the supplier’s Process of Record (POR) will be updated by the Supply Chain manager to reflect the new process. No notification to other suppliers is allowed. 7.5.7 8 Notification: Upon approval of the PCR implementing an MAYSTEEL LLC product change, all affected suppliers will be notified of the modified requirements. Approval of a supplier specific POR change will be communicated only to the initiator. RESPONSIBILITIES 8.2 Supplier: A supplier to MAYSTEEL LLC or MAYSTEEL LLC sub-contract manufacturers is required to maintain a controlled, consistent process. The supplier is responsible to notify MAYSTEEL LLC through the PCR process of process or material changes and to provide supporting data showing yield or reliability improvement. 8.3 MAYSTEEL LLC Supply Chain Manager: To coordinate the PCR review within MAYSTEEL LLC. Responsible to generate and process any necessary ERN documents to implement a PCR. Responsible to add non-documented PCR’s to the supplier’s history file. 8.4 MAYSTEEL LLC Purchasing: Responsible to review PCR requests in a timely manner. To notify suppliers of changed purchase requirements. 8.5 MAYSTEEL LLC Project Engineer: Responsible to review PCR requests in a timely manner. To review PCR requests for potential issues in hardware/software interactions, product performance or reliability issues. 8.6 MAYSTEEL LLC Quality Engineer: Responsible to review PCR requests in a timely manner. To review PCR requests for potential issues in manufacturing operations, product performance or reliability issues. 8.7 Other (as necessary): Secondary suppliers responsible to review change requests as potential future requirements and highlight issues or concerns. 9 OUTPUTS / RECORDS 9.2 Completed and approved PCR Form 9.3 Updated POR for supplier :Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 5 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari APPENDIX “A” SAMPLE: “PCR PROCESS CHANGE REQUEST FORM” ================================================================ Section 1 (completed by Supplier) Fabricator: ____________________________________________ Address: Page: 1 of 3 Date: _____________ _______________________________________ _______________________________________ _______________________________________ _______________________________________ Detailed Description of Proposed Change: _____________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Reason for Change :_______________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ :Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 6 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari MAYSTEEL LLC Products numbers affected by this PCR: _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Effect if not implemented : _________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Evidence supporting change :_______________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Alternatives ‘:____________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Page 2 of 2 MAYSTEEL LLC RESPONSE Section 2 (completed by MAYSTEEL LLC) ACCEPT / REJECT / MODIFY: ____________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ ERN Required: ______________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ ERN ____________________________________________________________________________________ Product Part Number______________________________________________________________________ Quantity _________________________________________________________________________________ Data Collection____________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Acceptance Criteria________________________________________________________________________ :Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 7 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari _________________________________________________________________________________________ _________________________________________________________________________________________ Field Release Plan_________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Request for Additional Information: _________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ Phase in plan (with completion dates): ________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ _________________________________________________________________________________________ PCR Request Form Page 3/3 PCR REVIEW PARTICIPANTS ___________________________________________ MAYSTEEL LLC Project Eng ____________________ Date ___________________________________________ MAYSTEEL LLC Supply Chain Manager ____________________ Date ___________________________________________ MAYSTEEL LLC Quality Engineer ____________________ Date :Work Instruction Description: Supplier Process Change Request Revision Date: 5-24-10 Date Issued: 5-24-10 WI# 7410-000-006-0 COR Page 8 of 8 Written By: Jim Bonner Approved By: Prasenjit Adhikari ___________________________________________ MAYSTEEL LLC Purchasing ____________________ Date ___________________________________________ Request Initiator ____________________ Date