JSA/SWMS - Elite Roads

advertisement
Job Safety Analysis / SWMS
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
Prepared By:
ASP001
Project:
Date:
2/4/12
Address: Various
Asphalt Paving
Deon Coote
Signature:
Reviewed By Safety Officer
YES
NO
Signature:
Approved by: Deon Coote
Signature:
Reviewed By Environmental Officer YES
NO
Signature:
Type of Permit/Licence Required: (please indicate by marking yes or no box)
YES
NO
YES
NO
YES
NO
YES
NO
YES
Are permits required?
Lock Out
Scaffolding / Scafftag
Gas Test
Gov Authority
Excavation Asset ID
Radiation
Explosives
Disposition or Transport of
Solid/ Liquid Waste
Asbestos
Hot Work
Traffic Control*
Confined Space
Air/Water Emissions
Personnel Cage

NO
PPE Requirements: (please indicate by marking yes / no box)
Goggles / Glasses*
Gloves*
Respirator
Safety Harness
Chemical resistant gloves
Hi-Vis Clothing/Vest
Hearing Protection*
Dust Masks*
Static Line
Clothing for Welding
Face Shield
Fire Extinguisher
PPE for Asbestos
Other: White overalls
(Night works)
Helmet (Hard Hat)
*
Safety Boots
Training/Qualifications e.g. Hiab,
first aid, traffic control, confined space,
crane operator, dogman etc
Demonstrate competency for
relevant plant
Site Specific & Industry Card
Induction
Signage
Fire Blankets
Training details are located at the
Other JSA/SWMS relevant to the
Project/Site office in the:
task
Site/Project Training Records Folder
ASP002 Asphalt Site Inspection
Other (specify):
First Aid Certificate
Chem. resistant clothing
Codes of Practice, Legislation, Standards that apply to this activity
The Documents listed are located or able to be accessed from the internet in the Site Office: (List relevant
regulations and standards in space provided)
OHS and Env Regulations and Acts
OH&S Act 2004, 2007 Regulations
Australian Standards
Site Specific OH&S Plans
Codes of Practice and Guidelines
Fulton Hogan Work Procedures
Plant, Equipment and Tools
required for this activity
e.g. ladders, excavator etc
Equipment Maintenance Checks required
for this activity
Have the listed basic required checks/inspections
been completed where applicable:
Potential Environmental Hazards
This is a prompt list only. (expert advice
from a Fulton Hogan Environment Officer
on site or other may be required)
Hazardous Substances / Dangerous
Goods
List any hazardous substances / dangerous goods
to be used or that may affect operations
Noise/Vibration
Air emissions (incl dust)


Current MFB/CFA permits must be carried
Scaffold inspections
Resource use & waste

and followed when working on total fire ban
Shovel, asphalt rake, broom
Jack hammer, vibrating plate
compactor, gas bottle hose & lance
Tipper trucks, Shuttle Buggy
Daily Plant inspection
Heritage disturbance
Concrete Saw
Tools (ladders etc)
Paver, multi tyred & steel drum roller
Tractor broom &/or skid steer
Daily Plant/Equip inspections
Daily Site inspections
Crew truck / bus, tack coat sprayer
Daily EWP inspection
Electrical equipment
YES
NO
Hazard to flora or fauna
days
Emergency Response
Consider fire extinguishers, rescue gear, evacuation
procedure, muster locations etc)
Follow Site Emergency Procedure
Fire extinguishers are available
Muster/Evacuation point located: At vicinity of
crew bus or as determined at prestart
meeting.

Other
NOTE: The above checklist is a guide only and does not seek to identify all potential hazards. A specific risk assessment of the above activity shall be carried out by the responsible supervisor and the employees doing the work
PPE marked with * - refer to specific activities detailed within and the site specific assessment
Content ID: AU_00006980
Revision: 2
Revised:13-0720102
Page 1 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
1
ASP001
Project:
Job Safety Analysis / SWMS
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
Mobilisation to Site
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard


Collisions with public road users

11 H



Arrive at site – park vehicles

Site hazards – pits, ditches, culverts, soft
edges, drop offs ledges, environmental
flora/fauna, other traffic
4L



3
4
2/4/12
Address: Various

2
Date:
Where traffic control is required, ensure that
it is implemented prior to commencing
works
As per Traffic Management SWMS
(see site specific risk assessment for risk
score)
Carry out daily pre-start toolbox, complete
site specific induction and review the
SMWS relevant to activities
Site environment / job plan not understood
Content ID: AU_00006980
Revision: 2



11 H

Adhere to all road rules
Give sufficient warning using vehicle
indicators
Park legally and out of the path of
traffic
Attach and activate amber flashing light
to warn traffic users
Drive to the conditions
Ensure traffic management plan is
approved and implemented where
required
Familiarise yourself with site
Identify safe parking area which
maintains safe distance from
embankments, ditches, soft edges,
vulnerable flora/fauna and allows safe
access to and from work vehicles
Park equipment on level sealed ground
Avoid parking within a 10m radius of
stormwater entry points
Ensure spill kits are available &
representative trained
Residual
Risk
Score
8M
Drivers
1L
Drivers
Operators
As per Traffic Management SWMS
Check that the traffic control has been
implemented in accordance with the
traffic management plan and crew
members are fully aware / understand
paving plan & traffic control plan
Engagement and feedback from all
crew members
Acknowledgement “sign off”
Revised:13-0720102
Page 2 of 21
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
Foreman / Crew
manager
6L
All Foreman / Crew
manager &
Subcontractors
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
5
ASP001
Project:
Job Safety Analysis / SWMS
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
Conducting general duties whilst on site
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Working in exposed environment
Initial
Risk
Score
7M
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard



8M
Working around machinery – onsite traffic




12 H
Public traffic



Content ID: AU_00006980
Revision: 2
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
All Visitors
Correct PPE in accordance with PPE
procedure including sun hat, long
sleeved shirt,& sunscreen
Provide cool water on site and drink
regularly.
All personnel on site to wear approved
high visibility clothing. For night works
and Vic Roads works approved
reflective vests must be worn.
5L
Crew members
Adopt Vehicle Movement guidelines –
3m front and rear clearance, 1 m side
clearance all mobile plant. 5 m
clearance all sides of skid steer except
front
A truck controller shall be appointed for
all reversing vehicles with restricted
rear vision & all trucks tipping into the
paver.
All personnel on site to wear approved
high visibility clothing. For night works
and Vic Roads works approved
reflective vests must be worn.
Mobile phones must not be used whilst
operating mobile plant or within the
active work area. Refer to Mobile
Telephone Policy
6L
Crew manager /
engineer
Crew members
6L
Crew manager /
engineer
Crew members
Maintain clearance to traffic in
accordance with site specific induction
Ensure that traffic control has been
implemented in accordance with the
traffic management plan.
Appoint a traffic control stop/slow
Revised:13-0720102
Page 3 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard


Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
spotter to control traffic where there is a
need for mobile plant to cross active
traffic lanes or roads.
All personnel on site to wear approved
high visibility clothing. For night works
and Vic Roads works approved
reflective vests must be worn
When crossing the road cross at traffic
control points wherever possible
If it isn’t possible to cross at a traffic control
point then before crossing the road - STOP,
LOOK, LISTEN and THINK:





8M
Pedestrians
Content ID: AU_00006980
Revision: 2


STOP one step back from the kerb or
well back on the shoulder of the road if
there is no footpath.
LOOK in all directions for approaching
traffic.
LISTEN in all directions for
approaching traffic.
THINK about whether it is safe to cross
the road – when the road is clear or all
traffic has stopped.
When crossing, walk straight across
the road. Keep LOOKING and
LISTENING for traffic while crossing
Ensure that the traffic management
plan covers management of pedestrian
traffic where required.
Plant operators and spotters to remain
Revised:13-0720102
Page 4 of 21
6L
Crew manager /
engineer
Crew members
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard

Content ID: AU_00006980
Revision: 2
vigilant of errant pedestrians and
personnel.
Where pedestrian crossings are within
work site either shut the pedestrian
crossing or make the crossing safe for
pedestrian use.
Revised:13-0720102
Page 5 of 21
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
6
ASP001
Project:
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
Night works
Job Safety Analysis / SWMS
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Low visibility
Initial
Risk
Score
12 H
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard






Fatigue
12 H

Low visibility hazard must be
emphasized in toolbox meeting
Sufficient site lighting for job where
required when street lighting absent or
insufficient to perform work safely
White overalls with reflective tape
Fit all plant with plant task lighting
Red/Green light batons to be used for
guiding all reversing vehicles or
constant radio contact to be maintained
whilst reversing.
Minimum 10 hours break required
between shifts
Adhere to good fatigue management
practices:
o Get a good session of sleep prior to
commencing shift.
o Avoid alcohol use in between shifts.
o Report all medication which may have
side affects of drowsiness (on label).
o Report to foreman/supervisor when
symptoms of fatigue affect safe
operation.

Content ID: AU_00006980
Revision: 2
Program works to conclude within 10
hour shifts. Where this is not achieved
give due consideration to breaks and
subsequent shift durations.
Revised:13-0720102
Page 6 of 21
Residual
Risk
Score
8M
8M
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
Crew manager /
Project Manager /
engineer
Crew manager /
engineer
Crew members
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard
Profiling (if required)
Refer to Profiling SWMS
Refer to Profiling SWMS
8
Clean pavement surface with rotary broom
or suction sweeper. Hand broom may also
be used for tight areas or joints
Refer to suction sweeper SWMS (if used)
Manual Handling
Refer to suction sweeper SWMS
 Use mechanical means where ever
practical
 Warm up exercises, correct posture,
and correct technique
 Take regular breaks/rotate work
 Wear dust mask if conditions require
 Wear gloves if conditions require.
5L
10
2/4/12
Address: Various
7
9
Date:
Remove raised reflective pavement
markers (cat’s eyes) – this may be done
with a pick or loader bucket
Set out paver runs and levels (line mark
with paint)
Dust/debris
4L

Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
Crew manager /
engineer
Crew members
Subcontractor
3L
1L
Crew manager /
engineer
Crew members



Use mechanical means where ever
practical
Warm up exercises, correct posture,
and correct technique
Eye protection where required
Respiratory protection where required
Assess adjacent obstructions, parked
vehicles, traffic etc for risk of flying
debris/dust and remove obstruction or
place traffic control measures to
mitigate risk

Projectile cat’s eye
2L

Wear eye protection
1L
Crew members
Manual handling
4L

Ensure that extension arm is used with
paint can to minimise bending of the
back
Wear eye protection when cleaning
spray nozzles
1L
Crew manager /
engineer
Crew members
Do not wrap string around fingers.
Release tension in string line when
vehicles crossing
3L
Crew manager /
engineer
Crew members

Entanglement with string line (if
construction traffic entangles with string
line)
Content ID: AU_00006980
Revision: 2
5L

Revised:13-0720102
Page 7 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
11
ASP001
Project:
Job Safety Analysis / SWMS
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
Jack hammering
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard
Noise
4L

Hearing protection must be worn
1L
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
Crew members
Debris
4L

Wear eye protection
1L
Crew members
Vibration
4L

Wear Anti-vibration gloves
1L
Crew members
Manual Handling
9M

Maintain good manual handling
techniques
Attend manual handling training
Rotate duties
Take rest breaks as required
2L
Crew members
Long sleaved clothing, safety footwear,
gloves and eye protection.
Handle chemical in accordance with
material safety data sheet
Assess adjacent obstructions, parked
vehicles, traffic etc for risk of
contamination and remove obstruction
or place traffic control measures to
mitigate risk
1L
Crew members



12
Date:
Tack coating (including use of hand lance)
Chemical exposure during hand spraying –
eye, skin
2L



Residual
Risk
Score
Ground personnel
8M

Maintain vigilance for ground personnel
during spray run. Sound horn twice
before commencing spraying. Maintain
clearance distance and stop if
clearance distances are breached
6L
Crew members
Truck when hand lancing for large areas –
being pulled along by truck or becoming
entangled in hose
5L

Appoint spotter/hose handler who also
guides movement of sprayer
3L
Crew members
Contact with overhead structures / trees
7M

Refer to pre-start site inspection
(obstructions identified & eliminated or
3L
Crew manager /
engineer
Content ID: AU_00006980
Revision: 2
Revised:13-0720102
Page 8 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Job Safety Analysis / SWMS
Project:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard

Falling from cab
4L



Runoff and spills
4L





13
Date:
Laying asphalt with paver which is filled
from tipper. Some manual laying using
shovels & rakes required. Some cleaning
may be required at the front of the paver
Manual handling
9M




Reversing vehicles with restricted rear
vision (tipping asphalt into paver)
12 H




Content ID: AU_00006980
Revision: 2
Residual
Risk
Score
mitigated)
Appoint spotter where required
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
Crew members
Always use three points of contract
when entering and exiting vehicle, do
not jump
Always face vehicle when entering and
exiting
Do not use steering wheel as hand hold
1L
Crew members
Ensure spill kit is on truck
Do not spray if rain is likely
Do not overspray or allow emulsion to
pool in areas
Use splash boards if necessary
Park away from pits and culverts
1L
Crew members
Use mechanical means where ever
practical
Warm up exercises, correct posture,
and correct technique
Take regular breaks/rotate work
Wear gloves as required
2L
Crew members
All trucks to have completed a
company induction before arriving at
job site.
All trucks to complete an operators prestart checklist & be fitted with reversing
beepers & rotating flashing beacon
Do no reverse into hopper until under
the guidance of the Tipman in the
yellow / green vest
Maintain contact with Tipman via Two
8M
Drivers
Crew members
Revised:13-0720102
Page 9 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard





Overhead obstructions
12 H










Content ID: AU_00006980
Revision: 2
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
way Radio or the use of hand signals
Reverse at walking pace
Sound horn to warn people of your
presence
Always use mirrors and look in
direction of travel
No ground personnel permitted in front
of paver when truck reversing
Refer to Vehicle Movement Procedure
Treat all powerlines as live
Strictly follow directions of Spotter
Maintain radio contact with Tipman /
Spotter.
Maintain a minimum clearance of 6.4 to
3.0 metres if an OCEI trained spotter is
in place
Lower the body of the truck
immediately after tipping. (Not to drive
off with the body up unless directed by
tipman/spotter)
Take special precautions in wet
weather or damp conditions to avoid
arcing
Assess the work to determine if work
can be safely carried out without
encroaching on the No Go Zone
(anywhere within 3m of the power line).
Notify Client if the work cannot be
completed outside the No Go Zone
Ensure that all persons working on site
are made aware of the location of each
line and the minimum clearances,
during the site induction
Advise all site personnel to be
Revised:13-0720102
Page 10 of 21
8M
Drivers
Crew members
Spotters
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard


Working with hot mix (hand laying when
required i.e. unable to lay with paver)
2L




Moving parts / entanglement – paver
10 H





Fumes
7M


Content ID: AU_00006980
Revision: 2
Residual
Risk
Score
constantly aware of the danger of
overhead power lines (look up and
live!)
Mark the location of overhead power
lines by placing out yellow traffic
cones
Ensure that all persons working on site
are made aware of the location of other
overhead obstructions such as tree
branches or canopies during the site
induction
Long sleeved clothing, protective
footwear
Handle hot mix with shovel or
mechanical aid
No direct contact. If need to directly
touch hot mix, wear protective gloves
Wear gloves as required
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
Crew Manager /
Foreman
1L
Crew members
Do not clear hopper with shovel whilst
slat conveyor is operational
Do not raise or lower hopper wings
without first checking for the presence
of workers
Stay clear of augers
Spotter required to watch for vehicle
movement whilst crew member cleans
front of paver
Wear gloves as required
5L
Crew members
Spotter
Ensure mix is at the specified
temperature to avoid excessive fuming
Wear supplied P2 respirators as req.
3L
Crew members
Drivers
Supply plant
personnel
Revised:13-0720102
Page 11 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
4L
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard

Do not use excessive release agent in
hopper or in truck bodies

Do not touch any part of the paver
which may be hot
Wear riggers gloves if contact with hot
surfaces is necessary
Carry out with two people wherever
possible
Heat from side of roller wherever
possible
Roller to maintain a min 1.5 m
clearance
Roller to travel no quicker than ground
personnel
Roller to stop when directed or if
contact lost with ground personnel
Ensure regulator and hose connections
are sound and well maintained
Point gas torch away from personnel
when lighting and when alight
Do not leave torch unattended when
gas torch is alight
Crew members must be familiar with
location of nearest extinguishers
On days of total fire bans or working
within 2 metres of combustible goods,
an observer with a fire extinguisher is
required
Maintain safe distance from edge of
drop off (assess and communicate
distance during toolbox and site risk
assessment meeting).
Select low amplitude.
Use vibrating plate or smaller roller

Heating joints – using hand lance in front of
roller
Roller traffic
11 H





Gas torch
11 H





15
2/4/12
Address: Various
Hot surfaces
14
Date:
Compact with steel roller, pneumatic (multi
tyred) roller and vibrating plate.
Vehicle turnover (eg drop offs, steep grade
>~10% cross fall)
11 H



Content ID: AU_00006980
Revision: 2
Revised:13-0720102
Page 12 of 21
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
1L
Crew members
8M
Crew members
8M
Crew members
8M
Crew members
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Job Safety Analysis / SWMS
Project:
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard


Longitudinal steep grades - vehicle
turnover/run away
11 H
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
near drop offs
All rollers to be fitted with ROPS
Seatbelts to be worn at all times
For rollers which are not hydrostatically
driven:
8M
Crew members
o Select correct gear before ascending or
descending.
o Do not attempt to change gear.
o Do not descend grades with gear in
neutral position
Noise
Striking people on site
7M
11 H

Refer to plant noise rating and adopt
hearing protection if deemed
mandatory
3L
Crew members



Ensure rotating flashing beacon is on
Do not roll up too close behind paver
Sound horn to warn people of your
presence
Always use mirrors and look in
direction of travel
When using worker to assist cleaning
the drum, always move away from the
worker
8M
Crew members
8M
Crew members


Collisions with other plant and vehicles
11 H




Content ID: AU_00006980
Revision: 2
Activate amber flashing light
Always check mirrors and look in
direction of travel
Ensure Operators Checklist has been
completed
Adhere to Vehicle Movement
Procedure
Revised:13-0720102
Page 13 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
16
ASP001
Job Safety Analysis / SWMS
Project:
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
Raking & shovelling
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Manual Handling
Initial
Risk
Score
10 H
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard











Hot Asphalt
4L



Slips, trips and falls
Being struck by moving machinery and
vehicles
7M
11 H








Content ID: AU_00006980
Revision: 2
Use skid steer loader to pick up and
spread asphalt when possible
Ensure shovels and rakes are in good
condition before use
Warm up muscles prior to work
Place feet apart and assure adequate
footing
Use legs to drive shovel into mix
Bend your legs, keep your back straight
Hold shovel close to body
Shift feet with load, do not twist body
Do not overload the shovel beyond
your physical capacity
Keep shovel and rake lubricated with
release agent
Use shovel to spread large amounts of
asphalt prior to raking; do no push
large amounts of asphalt with rake
Wear long sleeves and long pants
Take precaution when tossing asphalt
not to spray on fellow workers
Don’t touch or pick up asphalt with
hands
Avoid crossing screed
Wear lace up steel cap boots at all
times
Watch where you are walking
Do not run or rush
Ensure pits are covered
Do not use mobile phone
Check for oncoming vehicles or plant
prior to moving
Remain alert to vehicle and plant
movements around you
Revised:13-0720102
Page 14 of 21
Residual
Risk
Score
5L
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
Crew members
2L
Crew members
3L
Crew members
6L
Crew members
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard





Fatigue
8M


17
Date:
Parking of mobile plant at the completion of
work
Animal bites and or stings
5L



Public traffic – hazard to the public
7M




o
o
o
Content ID: AU_00006980
Revision: 2
Do not walk behind reversing plant
Remain clear of operating plant if your
presence is not required
Do not walk between reversing trucks
and the paver
Remain in operator’s view when
working around plant
Do not rely on operators to see you,
remain vigilant
Minimum 10 hours break required
between shifts
Rotate roles as required based on site
and environmental conditions
Wear long clothing
Do not venture into long grass
Do not intentionally aggravate or
pursue insects or animals with the
potential to cause harm
Park in accordance with signed parking
requirements & mobile plant and
equipment procedure
Make sure that the parked width of the
vehicle is not impinging the safe
passage of traffic through the roadway
This may require the removal of any
attachments/equipment which is
protruding into the roadway
If there is no signed parking, then on
roads where the signed speed is:
<60km/hr – park with care and abide
with all parking signage.
>60 km/hr – vehicles must be parked
with a 3 metre clearance to all traffic.
>80 km/hr – vehicles must be parked
Revised:13-0720102
Page 15 of 21
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
6L
Crew members
3L
Crew members
3L
Crew members
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
with a 6 metre clearance to all traffic
Theft
9M


18
Density Testing


As per testing SWMS
Radioactive source

19
Clean up site & reload equipment
Manual handling
7M



Floats
20
Demobilise traffic controls if required
As per Traffic Management SWMS
Working Outdoors in the Cold
Hypothermia / Cold Stress


Dehydration
M7
Content ID: AU_00006980
Revision: 2
As per testing SWMS
All site personnel to stay clear of area
when being tested
ARPANSA Code of Practice and Safety
Guide Portable Density / Moisture
Gauges Containing Radioactive
Sources to be followed
Operator to be licensed
Use mechanical means where ever
practical
Use good manual handling technique
and team lift where required

3L
Crew members
Subcontractor / FH
Subcontractor / FH
All Personnel
Wear appropriate PPE that is warm,
light weight and water proof as to allow
for freedom of movement. Including
gloves.
Rotate staff if able and plan works in
relation to weather forecast
L3
Keep supplies of clean cool water within
work area taking time to drink at least
two glasses of water every hour
L3
Revised:13-0720102
Page 16 of 21
Crew manager
Crew members
Lab personnel
Crew members
Refer to SWMS for loading and unloading
plant
 As per Traffic Management SWMS
M7
Working Outdoors in the Heat
2L
Park in accordance with mobile plant
and equipment procedure
Do not leave loose items or equipment
trailers onsite overnight unless they are
in a secured compound
All Personnel
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
STEP
NO.
ASP001
Project:
Job Safety Analysis / SWMS
Date:
2/4/12
Address: Various
Asphalt Paving
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard

Appropriate Clothing
M7
particularly in hot weather. Rotate staff
if able or ensure adequate breaks.
Ensure that appropriate clothing is worn
during the job and enforce that hats and
sunscreen is worn when in direct
exposure
Residual
Risk
Score
L3
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
All Personnel
Note *Operating plant (paver, levels, rollers) is not considered a manual handling task and therefore do not require the use of gloves unless maintenance, lubricating
or refuelling processes are undertaken
STEP
NO.
JOB STEP
List the steps required to perform the
task in the sequence they are carried
out.
POTENTIAL HAZARDS/RISKS
Against each step list the potential /
risk hazards that could cause injury /
damage when the task step is
performed.
Initial
Risk
Score
REQUIRED HAZARD CONTROL
For each hazard identified, list the
control measures required to eliminate or
minimise the risk of the hazard
Additional site specific risks
Content ID: AU_00006980
Revision: 2
Revised:13-0720102
Page 17 of 21
Residual
Risk
Score
PERSON
RESPONSIBLE
Nominate the
person who will
action the controls
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
ASP001
Project:
Job Safety Analysis / SWMS
Address: Various
Asphalt Paving
The steps which are considered to determine the most
appropriate control measures are as follows
1.
2.
3.
4.
5.
Elimination - eliminate the work practice, material, plant equipment responsible for the hazard
Substitution - substitute the work practice, materials, plant, equipment for a safer alternative
Engineering Control - re-design the work practice use of materials, plant or equipment to attain a safer alternative
Administrative Control - changing the deployment of personnel to reduce exposure (job rotation, training, etc)
Protective Equipment for Personnel - select appropriate equipment/apparel to reduce risk/exposure
Content ID: AU_00006980
Revision: 2
Revised:13-0720102
Page 18 of 21
Date:
2/4/12
ABN 79 152 328 704
JSA/SWMS No.
ASP001
Job Safety
Analysis / SWMS
Project: Vic Roads Contract No.
8208
Date: 2/4/12
Address: Various Arterial Roads
within South Western Victoria
Job Description:
Asphalt Paving
I certify by my signature below that I have had attended, understood and been given the opportunity to
comment on the content of the JSA/SWMS and I am aware of:
 the risks involved in the work and the control measures required to control those risks. I agree to
implement those control measures as I perform the work
 my obligation to perform tasks in a safe and appropriate manner
 my duty and responsibility to maintain a safe work environment as detailed in this JSA/SWMS
Name
Content ID: AU_00006980
Revision: 2
Company/Division
Signature
Date
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
Revised:13-0720102
Page 19 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
ASP001
Job Safety
Analysis / SWMS
Project: Vic Roads Contract No.
8208
Date: 2/4/12
Address: Various Arterial Roads
within South Western Victoria
Asphalt Paving
Risk Assessment Matrix (RAM)
To be used during Risk Assessment in the creation of a JSEA/SWMS for an activity as per Section 4. of the
JSEA/SWMS Procedure
Step 1 - Determine the probability of an event occurring
PROBABILITY
COMMENT
VERY LIKELY
A 70% OR GREATER CHANCE THAT THIS WILL HAPPEN
POSSIBLE
A 50% TO 70% CHANCE THAT THIS WILL HAPPEN
(2) UNLIKELY
A 20% TO 50% CHANCE THAT THIS WILL HAPPEN
(1) EXTREMELY UNLIKELY
A 10% OR LESS CHANCE THAT THIS WILL HAPPEN
Step 2 - Assess the most likely consequence of the event
CONSEQUENCE
SAFETY
ENVIRONMENT
MINOR
 FAC or MTI
 Vehicle Incident
 Up to $10,000 damage
MODERATE
 LTI
 e.g. Fall from height, Falling objects, Plant
collision (plant/people), vehicle rollover
 Up to $100,000 damage
MAJOR




As above
Fatality
Structural collapse
More than $100,000 damage
Step 3 - Determine the level of risk: LOW = .Green_, MEDIUM =
 Isolated community complaints (<5)
 Impact confined to site
 Requiring action/control but with minimal
impact
 Several community complaints (5-10)
 Local media interest
 Off-site impact contained (e.g.: spill on
impermeable area)
 Possible infringement notice
 Multiple community complaints (>10)
 Regional media interest
 Off-site impact uncontained (e.g.: polluted
waterway groundwater, drain)
 Possible prosecution
_Orange_, HIGH = _Red__
MINOR
MODERATE
MAJOR
MEDIUM (9)
HIGH (10)
HIGH (12)
POSSIBLE
LOW (4)
MEDIUM (7)
HIGH (11)
UNLIKELY
LOW (2)
LOW (5)
MEDIUM (8)
EXTREMELY UNLIKELY
LOW (1)
LOW (3)
LOW (6)
MATRIX
VERY LIKLEY
RISK
PARAMETERS
HIGH
[10 – 12]The activity MUST NOT proceed. Alternate work methods must be identified
MED
[7 – 9] The activity can proceed so long as the highest level and most appropriate risk control
measures have been identified and implemented
LOW
[1 - 6] The activity may proceed with normal supervision after implementing the control measures
Content ID: AU_00006980
Revision: 2
Revised:13-0720102
Page 20 of 21
ABN 79 152 328 704
JSA/SWMS No.
Job Description:
ASP001
Job Safety
Analysis / SWMS
Project: Vic Roads Contract No.
8208
Date: 2/4/12
Address: Various Arterial Roads
within South Western Victoria
Asphalt Paving
Content ID: AU_00006980
Revision: 2
Revised:13-0720102
Page 21 of 21
Download