Homework-Chapter 16 Problem 1 a) The lead time for a computer is 3+2 = 5 weeks The answers for b,c and d are the last 3 rows of the following table. Month Demand Invent. Returns Net.Requir. 3 Prod./Order Mboard 140 4 175 Orders DiskDrives 5 6 210 70 7 175 - 9 125 - 10 70 - 175 70 8 170 40 130 280 130 140 125 125 70 280 350 260 250 140 560 Note: we assume that returns occur at the beginning of each month. Problem 2 a) lot-for-lot scheduling Week Demand Orders 50 Set-up Cost 120 Inventory 1st Nov 50 83 120 0 2nd Nov 83 27 120 0 3rd Nov 27 55 120 0 4th Nov 55 0 Total cost =4*120= $480 b) Economic Order Quantity First we find the demand for the month of November = 50+83+27+55=215 So annual demand = 12*215=2,580 units Also annual holding cost =52*1 (since it’s $1 per week) So, order size =[ ( 2*2,580*120) / (52) ]1/2= 109 units Week Demand Scheduled Rec. Sched. Order 109 End.of period Inv Setup cost 120 Inv. Holding Cost 1st Nov 50 109 109 59(=109-50) 120 59 2nd Nov 83 109 0 85 (=59+109-83) 3rd Nov 27 0 0 58(=85-27) 4th Nov 55 0 0 3(=58-55) 85 58 3 11 300 20 280 Total cost = 2*120 + 59+85+58+3 = $ 445 c) Least Unit Cost heuristic Cover week 1 : Order 50 units setup cost= 120 and inv. cost= 0 => cost/unit = 120/50=2.4 Cover weeks 1&2 : Order 133 units Setup cost= 120 Inventory cost = (133-50)* 1 = 83 so cost/unit= 203/133= 1. 526 < 2.4 so continue Cover weeks 1&2&3 : Order 160 units Setup cost= 120 Inventory cost = (160-50)* 1 + (110-83)*1 = 137 so cost/unit= 257/160= 1. 61 >1.526 so stop. So we should only cover periods 1 and 2. We start over from week 3. Cover week 3 : Order 27 units Setup cost= 120 Inventory cost = 0 so cost/unit= 120/27= 4.44 Cover weeks 3&4 : Order 82 units Setup cost= 120 Inventory cost = 55 so cost/unit= 175/82= 2.134 < 4.44 so order this quantity. So our total cost will be the cost of ordering at the beginning of week 1 and 3. That is, (120 + 83) + (120 +55) = $378 which is the lowest among options a,b, and c.