REVIEW OF THE RURAL WATER PROGRAMME 2003-2006 VALUE FOR MONEY AND POLICY REVIEW INITIATIVE December 2007 Executive Summary (see glossary of terms p.7.) Introduction In November 2002, the European Court of Justice ruled that Ireland was in contravention of the EU’s Drinking Water Directive mainly due to the substandard quality of drinking water on privately sourced community owned Group Water Schemes. The Court threatened to impose substantial fines on the Irish State if this situation was not resolved without delay. Action Plan for Rural Drinking Water Quality 2003-2006 In response, the Department of the Environment, Heritage and Local Government initiated a major programme of capital upgrade works under the Action Plan for Rural Drinking Water Quality 2003-2006. This programme comprised five water quality upgrade solutions, involving either connection to the public water mains or the construction of standalone water treatment facilities, where public mains connection was not a viable technical option. Review Methodology This Review assessed the implementation, effectiveness and cost efficiency of the €298 million invested overall, under each of the five upgrade solutions as well as other capital measures, over the 2003-’06 period. This was achieved by taking an overview of programme implementation based on data collected in a questionnaire completed by all County Councils, implementing this devolved local authority programme. More detailed analysis of efficiency and effectiveness was carried out by examining a selection of upgraded schemes, under each solution type. The most recent EPA water quality test results for upgraded Group Schemes were checked to verify that they are now effectively complying with the Directive. Conclusions This Review found that while programme implementation to date has been substantial, there has been slower progress on the two solutions, involving connection to the public mains. According to local authority questionnaire returns, the unwillingness of some non-domestic Group Scheme consumers to pay for local authority water appears to lie at the heart of this delay in many cases. Councils have been granted additional enforcement powers under the 2007 Drinking Water Regulations to take remedial action, if necessary, on such Schemes. Although the Disinfection/Sterilisation upgrade solution was very cost efficient, schemes in 1 two out of four Counties examined continued to report exceedances of the Drinking Water Directive’s microbiological and chemical parameters, after being upgraded under this solution. Some Schemes upgraded under the Non-DBO solution also showed inconsistent effectiveness post upgrading. The Disinfection/Sterilisation and Non-DBO solutions have been designated respectively for 17% and 3% of all Schemes. In both cases, inadequate maintenance of water treatment infrastructure by some Group Scheme volunteers may be the problem. Local authorities should insist that, as a minimum, members of such Group Schemes attend the Group Scheme maintenance courses run by the Water Services National Training Group (WSNTG). The DBO treatment plant solution and the two solutions involving connection to the public mains were found to be effective. 72% of new Group Schemes built during the 2003-’06 period were publicly sourced with the number of newly constructed privately sourced group schemes decreasing each year. This is an encouraging sign as the EPA regards the quality of public drinking water as generally satisfactory. The DBO treatment plant solution was found to be the most expensive treatment solution but was the only viable technical option in cases, where the raw water chemistry was not appropriate for disinfection/sterilisation or connection to the public mains was not possible. The practice of procuring several DBO treatment plants together in bundles appears to have been successful in attracting more competitively priced bids for these bigger contracts. The cost of pipe network upgrades was found in many cases to exceed the cost of water treatment upgrades for all treatment solutions and it is essential that future such expenditure is carefully targeted. Recommendations The programme of water quality upgrades, required to comply with the Drinking Water Regulations, must be completed without delay to protect the public health of Group Water Scheme householders. It is also important that the Department reminds Councils that while a partnership approach with the Group Schemes’ sector is vital for programme implementation, the ‘most economically advantageous’ effective treatment approach must ultimately continue to be adopted in the interests of the taxpayer. There also needs to be a greater focus by Councils on source protection measures, particularly for newly constructed Group Schemes, to avoid a recurrence of water quality problems in the future requiring expensive remedial State investment. The Conclusions and Recommendations of the Rural Water Programme Review are set out in Chapter 7 on p.192. and proposed performance indicators on p. 175. 2 TABLE OF CONTENTS Executive Summary Page 1 Table of Contents Page 3 List of Appendices Page 4 Terms of Reference Page 5 List of Abbreviations Page 6 Glossary of frequently used terms Page 7 Chapter 1 Introduction to the Rural Water Programme Page 8 Chapter 2 Literature Review Page 30 Chapter 3 Methodological Approach Page 56 Chapter 4 Findings and Analysis Page 70 Chapter 5 Future Funding Needs/Alternative Approaches Page 163 Chapter 6 Proposed Performance Indicators Page 175 Chapter 7 Conclusions and Recommendations Page 192 Appendices Page 213 Bibliography Page 241 3 List of Appendices Appendix 1 Breakdown of Relevant Group Schemes by County Appendix 2 Membership of National Rural Water Monitoring Committee Appendix 3 National Federation of Group Water Schemes (NFGWS) response to questions re. Rural Water Programme Value for Money Issues Appendix 4 Circular L9/2006 and Questionnaire to Local Authorities re. Rural Water Value for Money Review Appendix 5 Drinking Water Regulations – Water Quality Parameters Appendix 6 Estimated Non-Domestic Water demand for DBO Bundles Appendix 7 Provisional Design Build Costs for completed DBO Bundles Appendix 8 Ryan Hanley Submission re. Leakage Control Appendix 9 Membership of Review Steering Group 4 Terms of Reference for Value for Money Review of the Rural Water Programme The Value for Money (VFM) Review of the Rural Water Programme during the period of the Action Plan for Rural Drinking Water Quality 2003-2006 will: 1) Identify programme objectives. 2) Examine the current validity of those objectives and their compatibility with the overall strategy of the Department of the Environment, Heritage and Local Government. 3) Define the outputs associated with the programme activity and identify the level and trend of those outputs. 4) Examine the extent that the programme’s objectives have been achieved, and comment on the effectiveness with which they have been achieved. 5) Identify the level and trend of costs associated with the Action Plan for Rural Drinking Water Quality 2003-2006 and thus comment on the efficiency with which it has achieved its objectives. 6) Evaluate the degree to which the objectives warrant the allocation of public funding on a current and ongoing basis and examine the scope for alternative policy or organisational approaches to achieving these objectives on a more efficient and/or effective basis. 7) Specify potential future performance indicators that might be used to better monitor the performance of future Action Plans for Rural Drinking Water Quality. 8) The core objective of the Action Plan for Rural Drinking Water Quality 2003-2006 is to bring the Group Water Schemes sector into compliance with the terms of the European Communities (Drinking Water) Regulations 2000. Therefore, the Small Public Water and Sewerage Scheme and Well Grant elements of the Rural Water Programme will not be reviewed as part of this study as their objectives are not directly related to the Group Water Schemes sector. 9) As the administration of the Rural Water Programme is largely devolved to local authorities, the efficiency and effectiveness of the local government system in meeting the objectives of the Action Plan for Rural Drinking Water Quality 2003-2006 will be assessed. 5 List of Abbreviations BMW CCMA CPI CRF CTPM DB DBO DWD ECJ EPA ERDF EU GWS M&E NDP NFGWS NPV NRWMC O+M P/E PMS PPP PPP PWS RWP S&E THM ToR UFW VFM WSNTG Border, Midlands and Western Region City and County Managers’ Association Consumer Price Index Capital Replacement Fund Connection to the Public Mains Design Build Design Build Operate Drinking Water Directive European Court of Justice Environmental Protection Agency European Regional Development Fund European Union Group Water Scheme Mechanical and Electrical National Development Plan National Federation of Group Water Schemes Net Present Value National Rural Water Monitoring Committee Operation and Maintenance Population Equivalent Project Programme Management System Public Private Partnership Polluter Pays Principle Public Water Supplies Rural Water Programme Southern & Eastern Region Trihalomethanes Terms of Reference Unaccounted For Water Value-for-Money Water Services National Training Group 6 Glossary of frequently used terms Client Representative Consulting Engineers jointly employed by the DBO Bundle Group Schemes and County Council to procure and oversee the work of the DBO operator during the Design Build phase of the contract Compliance Compliance with the water quality parameters of the Drinking Water Regulations 2000 Cost per House The capital cost of a Group Scheme’s water treatment solution and/or pipe network upgrade divided by the number of houses connected to the Group Water Scheme DBO Operator Consortia contracted to design and build the water treatment plants in a DBO Bundle and operate the plants for 20 years Design Capacity The maximum amount of water that the plant is designed to treat Drinking Water Regulations, which came into effect on January 1st 2004, transpose the Regulations 2000 EU’s Drinking Water Directive into Irish law. The Drinking Water Regulations 2007 recently superceded the 2000 Regulations DBO Bundle A number of water treatment plants serving individual Group Water Schemes procured together as one contract DBO Sub-bundle Two or more Group Water Schemes being served by the same water treatment plant within a DBO Bundle contract ECJ Ruling 2002 European Court of Justice (ECJ) ruling that Ireland’s private water supplies i.e. Group Schemes are in contravention of the Drinking Water Directive Groundwater Water sourced from underground aquifers. Group Water Scheme Private entities involving two or more premises abstracting water from a common water source and sharing a pipe distribution system Network Upgrade Upgrade works relating to the water pipe distribution network Operation and Fixed and Volumetric Costs involved in treating Group Scheme water Maintenance and maintaining the pipe distribution network Parameters Minimum water quality standards categorised into microbiological, chemical and indicator parameters Private GWS Group Water Scheme served by a private water source Public GWS Group Water Scheme connected to the public mains Rationalisation The merger of two or more Group Schemes into a single legal entity to be served by a single treatment plant Raw Water Untreated source water Source Protection Measures to protect source of drinking water supplies Subsidy Annual payment to Group Schemes to subsidise the domestic household portion of the operational costs of Group Water Schemes Surface Water Lake or River Water Sources Treatment Solution Upgrade works relating to improving water quality Unaccounted for Water that is lost out of the water distribution system through leakage Water (UFW) and wastage 7 Chapter 1 Introduction to the Rural Water Programme 8 Background to the Group Water Schemes’ Programme The Group Water Schemes’ Programme was introduced in 1962 to provide capital grant aid to rural dwellers for the construction of water distribution systems to pipe water from local water sources such as lakes or boreholes into their homes and farms. Communities set up voluntary co-operative structures known as Group Water Schemes to privately manage these water distribution systems with current operating costs being funded through contributions from Group Scheme members. Groups varied in size from a minimum of two houses sharing a water connection to the same source to over a thousand houses in some cases (Dept of Finance 1989, p1.) The number of Group Water Schemes increased throughout the 1960s, facilitated by the rural electrification programme, which provided the power to pump water (Fitzpatrick Associates 2005, p.9). Many of these new Group Schemes were connected up to the public water mains but retained control over their pipe distribution network. There are now estimated to be over 5,500 Group Water Schemes in Ireland serving up to 300,000 households (Fitzpatrick Associates 2005, p.11). The twin objectives of the Group Water Schemes Programme, from its inception, were quantity and quality. The quantity objective was to provide a sufficient quantity of piped water in as many houses as feasible. The quality objective was to ensure that water provided was of a suitable quality for drinking water (Dept of Finance 1989, p.2.). Any uncertainty as to the definition of suitable drinking water quality was removed with the enactment into Irish legislation in 1988 of the European Communities (Quality of Water intended for Human Consumption) Regulations (ibid, p.3). The allocation and payment of capital grants under the Group Water Schemes’ Programme was administered centrally by the then Department of the Environment. Departmental inspectors provided technical advice to Groups and certified completed works for payment. In most counties, the local authorities’ role was minimal and was generally limited to approving water sources, the designs of Group schemes and liaising with Departmental inspectors (ibid, p.6-7.). Existing Group Schemes were also entitled to receive second grants in cases where the existing water supply had become ‘seriously deficient’ due to capacity constraints or a decline in water quality (ibid, p.5). Since 2002, the Department of Community, Rural and Gaeltacht Affairs also provides ‘top up’ capital grants to Group Water Schemes in Clár areas (Fitzpatrick Associates 2005, p.36.). 9 Devolution of the Group Water Schemes Programme In January 1997, the Minister for the Environment announced that responsibility for the operation and administration of the Group Water Schemes’ Programme was to be devolved to local authorities (Circular L1/97). The Department would continue to pay block capital grants to local authorities but the appraisal and approval of applications for individual Group Scheme capital grants was solely a matter for the relevant County Council with no Departmental involvement. Group Water Scheme Subsidy In 1997, the Government abolished public water charges for domestic households and instead funded the operational costs of supplying treated water through the Local Government Fund (LGF). In the interests of equity, the Government also introduced a subsidy payment to Group Scheme households to cover the operating cost of providing for their domestic water needs. The payment is made directly to Group Schemes rather than individual householders by local authorities. The statutory basis for this scheme is Section 26 of the Local Government (Sanitary Services) Act, 1948. The annual domestic subsidy rates per household were increased to their current levels on 28th March 2000. The current subsidy levels are 100% of the qualifying expenditure as approved by the local authority, subject to a limit of:- - €50.79 for each house in a Group Scheme supplied from a local authority source; - € 101.58 for each house in a Group Scheme supplied from a private source - €196.81 for each house in a Group Scheme where water disinfection and/or treatment is provided under a Design, Build, Operate (DBO) contract or where the water disinfection/treatment plant is operated and maintained by a contractor by way of a bona fide Operational and Maintenance Contract. The conditions for the domestic subsidy scheme are set out in a Subsidy Explanatory Memorandum issued by the Department. Two of the eligibility conditions for the Group 10 Scheme subsidy are that it is providing a supply of water for domestic purposes which is, in the opinion of the local authority, satisfactory, and water conservation measures are being actively implemented (Department of the Environment, Heritage and Local Government 2002). National Rural Water Monitoring Committee and the Rural Water Programme In February 1998, the Minister for the Environment and Local Government launched the Rural Water Programme with substantially increased capital provision for the improvement of rural water systems, with a strong focus on improved drinking water quality (NRWMC 2003, p.1). In May 1998, the Minister established the National Rural Water Monitoring Committee (NRWMC) “to advise the Minister on national policy on rural water services and to monitor the implementation, by local authorities, of the devolved rural water programme” (Preface, NRWMC – June 1999). The NRWMC comprises all the main stakeholders in the Rural Water sector including central and local government officials, farming organisations and most crucially the National Federation of Group Water Schemes (NFGWS) as representatives of the Group Water Schemes sector. The Department has developed a partnership approach in working with the NFGWS to meet the objectives of the Rural Water Programme. The member organisations of the National Rural Water Monitoring Committee are listed in full in Appendix 2. In March 2000, the Minister announced new capital grant structures for water quality upgrades based on advice from the NRWMC. The current capital grant levels are set out in Departmental Circular L11/04. Rural Water Strategic Plans The NRWMC “began a process of strategic planning for rural water supply and water quality in 1999” (NRWMC, foreword, May 2002). All County Councils were required to draw up Strategic Rural Water Plans for supplying rural water needs in their county and upgrading water quality. The NRWMC issued Strategic Plan guidance documentation to all County Councils in June 1999 and May 2002. County Councils were required to identify the most suitable water quality upgrading solution for Group Schemes in their area in consultation with the Group Scheme members. Both versions of the Strategic Guidance documentation specified that Councils should cost and consider all water quality upgrade options and select the most ‘economically advantageous’ solution (June 1999, p.2.15 & May 2002, p.4.7). Local 11 Monitoring Committees were also established to monitor water quality issues on a County basis. The 1998 Drinking Water Directive and 2002 European Court of Justice Ruling On the 14th November 2002, the European Court of Justice (ECJ) ruled that Group Water Schemes serving more than 50 people (i.e. more than 15 houses) fell within the terms of the new 1998 Drinking Water Directive, which was due to come into effect under Irish law on 1st January 2004. This case had been originally initiated against Ireland for contravention of the previous Drinking Water Directive. This ruling had particular consequences for Group Water schemes with private water sources i.e. non-local authority water supply as the quality of the water in many of these schemes was not compliant with the new Directive. In its 2002 ruling, the ECJ found that 453 Group schemes serving more than 50 persons were non-compliant. A subsequent June 2006 Report to the European Commission, based on the latest local authority data, found that there were in fact 729 Group Schemes in Ireland each serving more than 50 persons, which required upgrading. A county breakdown of the 729 Schemes is provided in Appendix 1. The remainder of the estimated 5,500 Group Schemes in Ireland (Fitzpatrick Associates 2005, p.11.) are either already connected to the public mains and receiving good quality water or are exempted from compliance with the Drinking Water Regulations, due to their small size. In the event of non-compliance with the Drinking Water Directive, Ireland could receive substantial fines from the European Court of Justice. These fines could include both a lump sum fine equalling the cost savings to Ireland from not investing in the necessary water treatment infrastructure to make Group Schemes compliant as well as a daily fine for each day that the Group Schemes remain non-compliant. Substantial fines were imposed on Spain in November 2003 for failing to comply with the Bathing Water Directive. Most significantly of all in Case C-304/02 of 2005, “the ECJ ordered France to pay both a penalty payment of €57,761,250 for each period of six months, from the 12th July 2005 onwards and a lump sum of €20,000,000 for not adequately enforcing EU rules in relation to the sale of undersize fish.” The potential size of the financial penalties that could be imposed on Ireland means that the full implementation of the required water quality upgrades on Group Water Schemes is now a national priority for the Irish Government. Further information on ECJ fines is available at 12 (http://europa.eu/rapid/pressReleasesAction.do?reference=MEMO/05/482&format=HTML&a ged=0&language=EN&guiLanguage=fr) . Action Plan for Rural Drinking Water Quality 2003-’06 In response to the ECJ Ruling, the National Rural Water Monitoring Committee (NRWMC) prepared an Action Plan for Rural Drinking Water Quality 2003-’06. This Plan identified a number of upgrading solutions for the non-compliant Group Water Schemes serving more than 50 persons. Local authorities were requested to identify and oversee the implementation and upgrading of each of the relevant Group Schemes using the most appropriate water quality upgrade solution. Water Quality Upgrade Solutions 729 Group Water Schemes serving 89,570 houses are being upgraded under this Action Plan. The National Rural Water Monitoring Committee and County Councils have identified five water treatment solutions for 584 of these 729 schemes, three of which involve stand-alone treatment and two of which involve connection to the public water supply. All of these 584 Schemes are receiving their water from private sources. The remaining 145 Schemes are Group Schemes, which are already connected to a local authority water source but have water quality problems in their distribution network. Stand-alone Treatment Solutions Water Schemes is Design Build Operate (DBO) water treatment. where a single service provider / contractor designs, builds and operates water treatment facilities for schemes over a 20-year period. The Group Water Scheme continues to be responsible for the operation and maintenance of the pipe network distribution system. The proposed solution for 21 schemes (3%) is the construction or upgrading of an existing non-DBO water treatment plant. The Group Water Scheme continues to be responsible for the operation and maintenance of the water treatment infrastructure and pipe network distribution system. 13 where the chemistry and quality of the private schemes source is appropriate. The Group Water Scheme continues to be responsible for the operation and maintenance of the water treatment infrastructure and pipe network distribution system. Solutions involving connection to the public water supply nnected to public supply, while retaining their status as a group water scheme. The Group Water Scheme continues to be responsible for the operation and maintenance of the pipe network distribution system and pays the local authority for the public water supply. 65 schemes (9%) are to be taken in charge by the Local Authority. These Group Schemes will cease to exist after takeover and its members will be treated as public Public Source Schemes 145 schemes (20%) are already connected to the public water mains. These substandard public source Group Water Schemes will either receive pipe network upgrades or be taken over by their local authority. The above information is illustrated in the pie chart below (June 2006 Report, p.23.) 14 Implementation Status of Group Water Schemes by upgrade solution category The implementation status of each of the water quality upgrading solutions as of June 2006 is itemised in the table below. Data was not compiled in this format previously for the 729 schemes so it is not possible to track scheme implementation from 2003 to 2006. This report does, however, provide a snapshot in time of implementation to date. Updated implementation figures became available in May 2007 after completion of this Review and are detailed on p.195. Table 1.1 Implementation Status of Group Water Schemes by upgrade solution category Treatment Solutions DBO Non-DBO Connect to Public Main Council Takeover Disinfection/Sterilisation Public Source Total No. of Schemes % implementation % Solution In Work in Upgrades Total % Upgrades breakdown Planning Progress Complete Schemes complete 35% 3% 16% 9% 17% 20% 100% 19 7 85 35 19 21 209 9 27 27 11 15 30 5 6 3 92 109 258 21 118 65 122 145 186 26% 298 41% 245 34% 729 12% 24% 5% 5% 75% 75% Ref. Figures derived from June 2006 Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive Response of the European Commission The European Commission recognises that Ireland is taking significant steps to comply with the Drinking Water Directive but regards implementation progress to date as unsatisfactory. In an April 2006 letter, the Commission reminded the Irish Government that substantial financial penalties in terms of lump sums and daily fines could be imposed on Ireland for noncompliance with the Directive. The European Commission wrote to the Irish Government on 21st March 2007 to deliver a reasoned opinion that Ireland had failed “to take all necessary measures to comply with the judgement of the Court of Justice of the European Communities of 14th November 2002, case C316/00 Commission v Ireland, concerning drinking water”. The Commission reminded the Government of the financial penalties that the European Court of Justice (ECJ) may impose on a member state, which fails to comply with its judgement. 15 “When the Commission refers a case to the Court of Justice, it specifies the amount of the lump sum, of the penalty or of both, to be paid by the Member State concerned, which it considers suited to the circumstances”. The European Commission based its opinion on the water quality compliance data available in the 2007 EPA Drinking Water Quality Report. It should be noted though that this report is based on 2005 data, which doesn’t reflect implementation of upgrading works since then. Ireland has so far avoided court penalties by demonstrating that it is actively seeking to meet the terms of the Drinking Water Directive. A revised implementation report, which updates the June 2006 report to the European Commission, was sent to Brussels in May 2007 to respond to the Commission’s reasoned opinion. However, until such time as all the relevant schemes meet all the minimum water quality criteria, Ireland will technically be in breach of this Directive. Water Services Act 2007 Progress to date on the Action Plan has been due to the voluntary co-operation of most Group Schemes with the Rural Water Programme, under the leadership of the National Federation of Group Water Schemes (NFGWS). There are still, however, a substantial minority of Group Schemes, who are not co-operating with the Rural Water Programme or the NFGWS and have not agreed to implementation of the water quality upgrading solutions identified for their scheme. A Water Services Act was passed by the Oireachtas in May 2007 and provides for a statutory licensing system for the Group Water Scheme sector for the first time. This licensing system provides local authorities with the legal means to require privately owned Group Water Schemes to observe drinking water standards. The agreement of all Group Scheme members is currently required to have a Scheme taken over by its local authority. This has created delays in taking over Schemes, were one or more members objected to Council takeover. The new Water Services Act provides for legal takeovers based on the agreement of two thirds of Group Scheme members. The National Rural Water Monitoring Committee is also placed on a statutory footing as the National Rural Water Services Committee to provide advice to the Minister on rural water policy. County Councils were already empowered to take prosecutions against non-co-operative Group 16 Schemes under the 2000 Drinking Water Regulations, which transposed the Drinking Water Directive into Irish law. Councils have been given additional enforcement powers under the recent 2007 Drinking Water Regulations to take direct remedial action on Group Schemes, without members’ consent, if necessary, and to be financially recouped by the Group Scheme. Current position It is clear that there has been a major shift in the focus of the Rural Water Programme since the late 1990s. Up to 1998, the main objective of the Group Water Schemes programme was to fund the provision of infrastructure to provide piped water to rural dwellers with water quality as a secondary objective. The 1998 Rural Water Programme, however, placed a stronger emphasis on rural water quality. The Action Plan for Rural Drinking Water Quality 2003-’06 lists the quality of drinking water in rural areas as its highest priority. The current Rural Water Programme Action Plan outcome i.e. objective is to ensure that the water coming out of household taps in the 729 Group Water Schemes meet EU drinking water quality standards. The programme inputs is the capital expenditure incurred on the various water quality upgrade solutions as well as investment in pipe network distribution system upgrades. The Programme outputs are the completion of infrastructure works and the production of treated water. Terms of Reference for Value for Money Review of Rural Water Programme One of the first issues to be considered in carrying out a Review of the Rural Water Programme is to determine the period of the Review. Five natural evaluation periods present themselves; 1989-2006 – Group Water Schemes programme since last Review in 1989 1997-2006 – Group Water Schemes programme since devolution to local authorities 1998-2006 – Group Water Schemes programme since the start of the Rural Water Programme 2000-2006- Rural Water Programme during period of the NDP 2000-‘06 2003-’06 – Rural Water Programme during the period of the Action Plan for Rural Drinking Water Quality 2003-‘06 17 It was decided to opt for the final evaluation period as it reflects the outcome of the 2002 ECJ ruling, which has driven policy implementation since then. The Review will not include the Small Public Water and Sewerage Scheme and Well Grant elements of the Rural Water Programme as their objectives are not directly related to the private Group Water Schemes sector. The Terms of Reference for this Review (see Page 5) are in line with the recommended Department of Finance template. Capital Expenditure Measures under Rural Water Action Plan 2003-‘06 The table below shows expenditure on each of the capital measures during the period of the Action Plan for Rural Drinking Water Quality 2003-‘06. An explanation of each of the spending measures and the grant conditions are also provided below. It should be pointed out that the €6,476 (IR£5,100 approx. i.e. 85% of £6,000) per house grant limits referred to below were decided by the Minister for the Environment, Heritage and Local Government in March 2000. However, there does not appear to be any documented information available within the Department as to how this grant level was determined, apart from Ministerial instruction. Table 1.2 Annual Expenditure on Capital measures under the Rural Water Programme Expenditure on Capital Measures (€ million) Design Build Operate (DBO) DBO Advance Work LA Takeover 2003 2004 2005 2006 Total 8.723 21.194 33.812 31.568 95.297 - 16.874 18.464 35.338 9.467 8.91 10.884 16.924 46.185 Upgrade of GWS networks 30.352 20.323 25.738 28.996 105.409 Connect to the Public Main - 5.367 6.751 3.895 16.013 55.794 94.059 99.847 298.242 Total 48.542 Source: Department of the Environment, Heritage and Local Government DBO Treatment Plants The Department funds 100% of the cost of the mechanical and electrical works component of water treatment plants. The civil works contract, which includes the plant building, access roads, reservoirs and rising mains is 85% funded by the Department with a 15% contribution 18 from the Group Scheme. The total Departmental grant cannot exceed €6,476 per the number of houses served by the Group Scheme (Circular L11/04). The Group Scheme must pay the operation and maintenance costs (O&M) of the DBO water treatment plant and the pipe network distribution system but domestic householders each receive an annual operating subsidy from the Department of €196.81 for each house in the Scheme. This high rate of subsidy is paid in recognition of the fact that the Group Schemes are paying a professional DBO operator to treat their water. DBO plants are usually procured as bundles with several DBO treatment plants in a County being procured as part of a single contract to achieve economies of scale and attract more competitive bids from large consortiums. In some cases, it has been decided to use interconnecting pipes to connect a number of Group Schemes to the same treatment plant as a sub-bundle to achieve further cost economies. In the case of a DBO sub-bundle, any interconnector pipes linking several Group Schemes to one treatment plant, are 100% funded by the Department within the overall €6,476 per house grant limit. DBO Advance Works In some Group Schemes, it has been decided to proceed with certain elements of the civil works contract ahead of the DBO contract due to delays in finalising the DBO bundle. The cost of these Advance DBO works is also contained within the Department’s grant limit of €6,476 per house for the overall DBO project. Non-DBO Treatment Plant This is the water quality upgrade that has been identified for 21 of the 729 schemes (3%). It encompasses all water quality upgrade solutions involving the installation of a stand alone treatment facility, not procured by way of a DBO contract. In some cases, it simply involved upgrades to existing treatment infrastructure. It is currently funded out of the network upgrade capital measure in Table 1.2 above. The operational and maintenance costs of the treatment infrastructure and the pipe network distribution system are paid for by the Group Scheme but they receive a domestic subsidy towards it from the Department of €101.58 for each house in the Scheme. Group Schemes can claim the higher €196.81 rate where the water 19 disinfection/treatment plant is operated and maintained by a contractor by way of a bona fide Operational and Maintenance Contract. Local Authority Takeover of Group Schemes All costs incurred by the local authority in completely taking over the Group Scheme including connection to the public mains and upgrading or replacement of existing pipe networks, is recoupable from the Department. There is no spending limit specified by the Department although this is under review. Group Scheme domestic households receive no subsidy post-takeover as they have been fully absorbed into the public water system so pay no direct water charges. The Department has made a conscious decision not to require a 15% capital contribution from Group Schemes under this solution to encourage Group Schemes to accept complete takeover by local authorities. This is the best guarantee of ensuring that Group Scheme consumers receive high quality water as the water is treated and the pipe networks maintained by professional local authority staff. Connection to the Public Mains (CTPM) Some Group Schemes have accepted connection to the public mains (CTPM) but want to remain independent of the local authorities and maintain their own pipe distribution network privately. 85% of the costs incurred in connecting the Scheme to the public mains is recoupable with a 15% Group Scheme contribution. The overall costs cannot exceed €6,476 per the number of houses served by the Group Scheme. Prior to 2004, the costs involved in connecting Schemes to the public mains were paid under the network upgrade measure. The Group Scheme funds the operation and maintenance (O&M) costs of the pipe network distribution system but domestic householders receive an annual operational subsidy from the Department of €50.79 per house in the Scheme. Group Schemes connected to the public mains, generally referred to as Public Group Schemes, receive a lower rate of subsidy as they do not have to pay for water treatment costs. They do have to pay local authorities for their water supply but the Department recommends that each domestic household should receive 50,000 gallons per year from the Council for free. This means in practice that only nondomestic water users on Public Group Schemes pay local authority water charges in the same way as other commercial operations on the public water system. 20 Disinfection/Sterilisation Group Schemes make a 15% contribution towards this treatment solution with the remaining 85% funded by the Department. The maximum grant aid cannot exceed €6,476 per the number of houses served by the Group Scheme. This water quality upgrade solution is funded out of the Network Upgrade measure. In 2007, the Disinfection/Sterilisation solution received a separate annual allocation of €1.07 million for the first time. The operational and maintenance costs of the treatment infrastructure and the pipe network distribution system are paid for by the Group Scheme but they receive a domestic subsidy towards it from the Department of €101.58 for each house in the Scheme. Group Schemes can claim the higher €196.81 rate where the water disinfection/treatment plant is operated and maintained by a contractor by way of a bona fide Operational and Maintenance Contract. Capital Expenditure on Non-Water Quality Upgrade Solutions Network Upgrades This was the original grant measure for the Group Water Schemes programme to fund the construction and upgrade of the pipe network system connecting Group Scheme households to their water source. Departmental funding cannot exceed €6,476 per the number of houses served by the Group Scheme and Scheme members must make a 15% capital contribution towards the network upgrade. A second network upgrade grant can only be paid to Group Water Schemes connecting to a DBO water treatment plant. Network upgrades for the other treatment solutions must not exceed the overall €6,476 grant limit for their water quality upgrade solution. Councils are asked to only prioritise critical mains upgrades, which are a necessary part of reducing water leakage on Schemes undergoing water quality upgrade works. It is notable that this was the second highest spending capital measure (after the DBO measures) with expenditure of €105 million between 2003-’06. It must be remembered though that Non-DBO, Disinfection/Sterilisation and New Schemes works [and CTPM works before 2004] were also funded under this spending measure. New Schemes Since 2006, funding for new Group Scheme pipe networks and extensions to existing Group Schemes have been allocated under a separate New Schemes measure. The allocation for 21 2006 was €9.583 million and it was €12 million for 2007. Prior to 2006, New Schemes were funded under the Network Upgrades measure. However, New Schemes outturn expenditure for 2006 was still recorded under the 2006 Network Upgrades outturn total of €29 million (see Table 1.2 above) so there is no separate outturn figure available for New Schemes. New Group Scheme applicants must make a 15% contribution towards the capital cost and the Department funds the remaining 85% up to a limit of €6,476 per house. This is a particularly important measure as it adds to the number of Group Schemes that the State is responsible for funding. The Department is unofficially encouraging County Councils to only fund new Group Schemes, which are connected to the public mains as new Group Schemes with private water sources will only potentially add to the list of deficient Group Water Schemes, which may require future water quality upgrading works. However, the Department has never issued formal instructions to Councils to stop authorising applications for new Private Group Schemes in their area. Fitzpatrick Associates predicts that the recent guidelines on rural housing will lead to an increase in demand for water in rural areas and increased demand for connections to Group Water Schemes. It will also increase the potential risk to groundwater (2005, p.45). The issue of New Group Schemes and their potential future funding implications for the State will be discussed in Chapter 4 of this Review. Current Expenditure – Annual Domestic Subsidy Annual expenditure under the domestic household subsidy scheme is set out in Table 1.3 below. Annual expenditure has increased by approx. 50% between 2003 and 2006. Table 1.3 - Expenditure on Domestic Subsidy 2003-‘06 Expenditure (€ million) 2003 2004 2005 2006 Domestic Household Subsidy 5.305 5.276 7.141 7.957 Source: Department of the Environment, Heritage and Local Government The number of Group Schemes in receipt of the subsidy under the different categories is outlined in Table 1.4 below. The subsidy is a relatively small element of annual expenditure 22 under the Rural Water Programme. However, it is an ongoing annual cost to the taxpayer and as such it will be reviewed in Chapter 4. Table 1.4 - Number of Group Water Scheme claims per subsidy category No. of Group Water Schemes claiming Subsidy Public GWS Subsidy (€50.79 per house max.) Private DBO Subsidy (€196.81 per house max.) Private Non-DBO subsidy (€101.58 per house max.) Total No. of Group Schemes 2003 2004 2005 2006 128 130 111 82 23 24 27 33 520 518 467 316 671 672 605 431 Source: Q. 26. Compiled from Local Authority Questionnaire Returns 2007 Other Current Expenditure The Department funds a Rural Water Liaison Officer post in most County Councils at a cost of approx. €35,553 per Council per year. The Department also contributes towards a portion of Councils’ annual administration costs under the Rural Water Programme and paid out a total of €2 million for administration costs in 2006. It is not proposed to review these expenditure elements as they also relate to administration and liaison work carried out by Councils on Rural Water Programme measures, outside this Review’s terms of reference. An annual grant of €500,000 is also paid by the Department to support the full time activities of the National Federation of Group Water Schemes (NFGWS). The Federation makes a strong case for retention of their annual subvention due to their active participation in delivering implementation of the Action Plan, in partnership with the Department (See NFGWS submission -Appendix 3). Given the Federation’s crucial and active role as the recognised representatives of the Group Schemes’ sector in Ireland, it is not proposed to review the payment of their annual grant at this sensitive time in the delivery of water quality upgrade works under the Rural Water Programme. 23 Issue of Private Group Schemes It should be emphasised at this point that the major current concern of the European Commission is the sub-standard level of water quality in privately sourced Group Water Schemes. The Environmental Protection Agency’s (EPA) Drinking Water Quality Reports have highlighted problems with microbiological contamination and the presence of E.coli in these Schemes over many years. The Department has accordingly instructed local authorities to progress water quality upgrades on privately sourced Group Schemes as a matter of priority. Works on publicly sourced Group Schemes should be given a lower priority. Therefore, the main focus of this Review will be on the efficiency and effectiveness with which local authorities have implemented the five water quality upgrade solutions for the 584 privately sourced Group Schemes. Issues to consider in a VFM Review of the Group Water sector It is important to first get an overview of each stage of the water treatment cycle and its consequent cost implications. The diagram below provides a very basic representation of a water treatment and distribution system for a Group Water Scheme. Raw water is abstracted from either a surface water (river or lake) or groundwater source and is pumped to a water treatment plant for treatment. The treated water is then usually pumped to a water storage facility/reservoir. As the water is required, it is then pumped into the pipe network and distributed to the homes of water consumers. Abstraction from Water Source Water Treatment Plant Water Storage/ Reservoir Water Distribution Network House Tap 1 House Tap 2 Farm Tap 24 The table below illustrates the respective responsibilities of Group Water Schemes (GWS), DBO providers and the local authorities (LAs) for each stage in the water treatment cycle for each of the five water quality upgrade solutions for Group Water Schemes. Water Quality Upgrade Water Water Water Water Measures Source Abstraction Treatment Distribution DBO treatment plant GWS DBO provider DBO GWS provider Non-DBO treatment GWS GWS GWS GWS Disinfection/Sterilisation GWS GWS GWS GWS Connect to public main LA LA LA GWS LA Takeover LA LA LA LA There are a number of cost issues relating to each stage of the process, which are outlined below. Water Source and abstraction The quality of the raw untreated water at source will be a major determinant of the cost of treating it. Waters are generally classified as Grade A1, A2 and A3 for the purposes of assessing treatment requirements. The European Commission and the Environmental Protection Agency have particularly identified Group Water Schemes with private water sources (i.e. not receiving their water from a public supply) as a major concern. The EPA has reported that the quality of the raw source groundwater has declined in many places in recent years due to pollution caused by inter alia certain farming practices and contamination by faulty septic tanks in the area. This includes contaminants such as faecal coliforms and high nitrate concentrations, which have been linked to methaemoglobinaemia [blue baby syndrome] (Water Quality in Ireland 2006, p.21.). The issue of water source protection will be addressed in Chapter 5 and the work of the National Pilot Source Protection project on the Churchill-Oram Group Water Scheme will be considered. Another issue that also must be borne in mind is the level of water abstraction from a water source as over abstraction from water sources can have knock on environmental consequences for the ecosystem. Fitzpatrick Associates (2005, p.vii) have noted that these environmental costs also need to be factored 25 into the process. There are also specific environmental issues in relation to water quality upgrade works in Special Areas of Conservation. Water Treatment As already stated, the nature of the source water quality will be a major determinant of treatment costs. There will also be pumping costs involved in transferring the water from its abstraction point. In a limited number of cases where the source water is of particularly good quality, it may be possible to treat it using basic disinfection and sterilisation. This is a very cost effective solution but there are concerns as to its sustainability and also the possible health risk caused by using chlorination (carcinogenic THMs). These issues will be teased out in the section on the disinfection and sterilisation upgrade solution in Chapter 4. In most cases, a water treatment facility will be required to treat the water. This usually involves two core work contracts, a civil works contract and a mechanical and electrical contract. The civil works contract usually involves the construction of the treatment plant building, a water storage reservoir and necessary rising mains to pipe the water between the source, treatment plant, reservoir and the start of the distribution network. The Mechanical and Electrical contract (commonly referred to as the Mec& Elec contract) involves the installation of the water treatment technology as well as any pumps needed to transfer the water. The size of the water treatment plant and its plant capacity will be determined by the population needs of the plant as well as the quantity of source water available. The procurement of a water treatment plant can generally be done in three ways, traditional, design build or design build operate. Traditional procurement involves separate procurement of contracts to design and build the plant. Design Build involves a single contract for the design and build of a treatment plant. Design, Build, Operate (DBO) involves procuring a single contractor to design, build and operate a treatment plant usually over a 20 year period. The DBO procurement approach has been favoured in recent years as it is regarded as providing best value for money particularly as the whole life cost of operating and maintaining the plant are included in the contract cost along with the initial capital cost of construction. 26 Water Distribution Network After the water is treated, it is usually stored in a reservoir in order to ensure that there is available water supply to meet various demand levels at different times of the day. Reservoirs are often located on a high level so that water can flow down to recipient households using gravity. If households are located at a high level or are distant from the reservoir, there may be additional costs involved in pumping water to those houses. Because of the dispersed nature of rural populations, the pipe networks are generally far longer than those serving individual households in urban areas. Apart from the cost of additional piping, this also adds to the problem of Unaccounted for Water or UFW as water leaks out of the pipe network including at pipe joints. This partially explains why UFW is so high in rural areas. Longer pipe networks also mean increased pipe network maintenance costs. Poorly maintained pipes can lead to leaks, which increases the level of UFW in the pipe network. Increased UFW reduces the level of treated water available to households and can potentially result in water shortages. The major cause of UFW is overuse of water by certain consumers particularly as most rural water supply usage is not metered. Water providers generally have two choices either, to try and reduce UFW through pipe network upgrades or alternatively to increase plant capacity. Leakage control studies of rural water usage in Mayo and Galway have shown that active leakage control policies, including the installation of water meters on all connections, are a very cost effective means of reducing water demand and avoid the need for unnecessary treatment capacity increases (Ryan Hanley, 2004 & 2005). Poorly maintained and sub-standard pipe networks can also create another serious problem –recontamination of treated water in the pipes. This problem can be addressed by ensuring that there is sufficient residual chlorine in the water post treatment to ensure that the water is not re-infected by contaminants within the pipe. It is important that the quality of the water flowing into the last household at the end of the pipe network is regularly checked to ensure that it contains sufficient chlorine levels. It is important to note that the DBO operator does not have any role in the maintenance of the pipe network and their responsibility ends when the treated water is released into the Group Scheme network. The National Federation of Group Water Schemes and the Water Services National Training Group have established a Performance Management System (PMS) for 27 DBOs and run training courses for Group Water Schemes in the management of pipe networks. This has traditionally been done on a voluntary basis by individual Group Schemes, however, there is an increasing recognition by the National Federation (Cavan Annual Conference – September 2006) and practitioners in the field that there is a need for professional paid staff to carry out this operational and management role. Non-Domestic Users and the Water Pricing Framework As can be seen from the above diagram (p.24.), treated water is also used for non-domestic purposes particularly for farming purposes. Current Government policy is that the cost of treating and supplying water for non-domestic purposes must be recovered from those users in accordance with the Water Pricing Framework. This includes the volumetric costs of supplying the water as well as the marginal capital cost of providing the treatment infrastructure to meet non-domestic demand. Non-domestic water charges are a particularly contentious issue in connecting Group Schemes to the public mains. Farmers originally built many Group Water Schemes, on a voluntary basis, to provide piped water for their farming needs. They own their group schemes and in some cases see little need for water treatment. The application of the Water Pricing Framework will be considered during the course of this study. Benefits of a Rural Water Programme Value for Money Study At its most basic, this value for money study is examining the effectiveness and efficiency of the Rural Water Programme and assessing the rationale for its continuance. This includes an assessment of the solution selection criteria and the implementation and cost efficiency of the water treatment solution identified for each of the relevant Group Water Schemes (GWS). More importantly has the identified solution resulted in the water coming out of household taps meeting EU Drinking Water criteria? For example, does the construction of a state of the art DBO water treatment plant guarantee that clean water will arrive in households through the GWS distribution system? How is the quality of this drinking water monitored and verified? On a similar theme, are there measures in place to protect the water quality source from pollution to minimise water treatment costs? Was too little or too much treated water produced to meet the needs of a GWS? How much water was lost in the distribution system as UFW and is this cost carried by the taxpayer? As it is Government policy to recover non- 28 domestic water charges, did this occur in the GWS sector and was the marginal capital cost of capital works recovered? It could be argued that much of this is of little more than academic interest as the Irish Government is committed to providing water treatment infrastructure without delay to avoid incurring large fines for non-compliance with the Drinking Water Directive. However, the 729 Group Schemes may be the start of a longer term investment commitment in the Rural Water Sector. Group Schemes with less than 50 persons but with one or more commercial connections e.g. a pub, a B&B or even a dairy farm also fall within the criteria of the Drinking Water Directive (EPA Circular DW 01/06). There are several hundred additional Group Water Schemes with <50 persons and it is estimated that a considerable proportion of these may have such a commercial connection. There is also a steady demand for government funding to build new Group Water Schemes. At the same time, the Water Services Act 2007 provides a statutorily enforceable licensing system for the first time to ensure that Group Water Schemes meet basis water quality standards. It is, therefore, an opportune time to reassess the rationale for the Rural Water Programme and question whether the current approaches provide best value for money and achieve necessary water quality outcomes. 29 Chapter 2 Literature Review - Rural Water Programme 30 Rural Water Programme Literature Review Introduction The Rural Water Programme has evolved considerably since its original inception in the early 1960s as the Group Schemes Programme and this is reflected in the available literature. This chapter is divided into three sections. The first deals with background literature, which is important to gain an understanding of how the modern Group Water Schemes Programme has evolved. It is also a vital aid to putting many of the issues that will be encountered in this Value for Money Review in context, particularly as some issues will be unique to the Group Schemes’ sector. The second part of this review looks at comparative European literature to assess how other EU member states, with private water supplies, have implemented the Drinking Water Directive. This is important in identifying possible alternative policy approaches for Ireland. Finally and most importantly, the third part of this literature review examines previous analytical studies of the Irish water services sector. This is an essential aid to identifying issues of efficiency and effectiveness in the Irish water sector and possible methodological approaches for the Value for Money Review of the Rural Water Programme. Background Literature Historical Context A useful starting point for understanding the background to the Group Schemes’ sector in Ireland is Professor Mary E Daly’s “The Buffer State: The Historical Roots of the Department of the Environment” (IPA, 1997), which draws heavily on Departmental archives. According to the 1956 Census, only 3% of rural households, had access to public water supplies. By contrast, the ESB had connected over 50% of rural households (163,000 consumers) between 1947 and 1956, under the rural electrification programme (p.483.). In 1959, the Government approved a £35 million ten year programme, submitted by the then Department of Local Government to provide running water in rural areas. This programme would be funded through a combination of central Government grants and local authority rates. The Department of Local Government initiated a national publicity campaign on the 31 merits of piped water but encountered strong opposition from the National Farmers’ Association (NFA), the precursor to the Irish Farmers’ Association (IFA). The NFA “objected to the additional cost imposed on [local authority] rates” as “most larger farmers, who dominated the NFA, already had piped water in their homes and saw no benefits from the scheme” for them personally (p.484). The then Minister for Local Government’s [Neill Blaney) main opponent in cabinet was the Minister for Agriculture (Paddy Smith), who supported the NFA position. “In January 1962, Smith informed Blaney that there was growing opposition among rural organisations and farming interests to any extension of regional water schemes….He argued that individual or group schemes using ground water were preferable” on cost grounds (ibid, p.485.). Minister Blaney rejected the argument that regional water supply schemes were too expensive. However, as a compromise, “the 1962 Government (Sanitary Services) Act provided a new scale of grants and loans for group and private schemes in an effort to silence those who claimed that the government was biased in favour of elaborate regional schemes” (p.487.). The Department of Agriculture relinquished control of its own rural water grants scheme to Local Government and the modern Group Schemes Programme, as we know it began to evolve “This new emphasis on group water schemes continued for the remainder of the 1960s …and by 1964 promotional activities had as their main theme…the encouragement of private enterprise, particularly by co-operative group schemes” (p.487.). The regional water supply programme was cut back in 1965/66 to give priority to housing and never regained the momentum lost ‘because of ratepayer/farmer resistance” (p.488.). By 1969, the primary object was to improve water and sewerage facilities in built-up areas. Rural needs would continue to be met as far as possible, with local authorities providing head works and trunk mains, which would be linked to co-operative group schemes (ibid). “The Buffer State” (1997) provides enlightenment into how the modern Rural Water Programme, based on a Group Schemes structure, evolved. It also shows that there was a period, when extensive regional public water supply schemes were being promoted by central government but this was opposed by big farming and other ratepayer interests, in favour of Group Water Schemes. It certainly refutes any argument that central government ignored the 32 needs or will of rural Ireland, albeit the NFA big farmers, in determining how water infrastructure should be provided to rural communities. Evolution of the Group Scheme Programme While the scope of this Review is the 2003-’06 Action Plan period, it is important to track how the Scheme has developed in recent decades. A useful starting point, in this regard, was the last comprehensive Review of the Group Water Schemes Programme published by the Department of Finance in May 1989. The terms of reference of the Review were broadly similar to this Value for Money Review in that it sought to analyse the efficiency and effectiveness of the Scheme in meeting its objectives. The objective of the Scheme at the time, however, was to ‘provide water of adequate quality to as many houses as is feasible’ (Department of Finance 1989, p.i). There was an equal focus on water supply and water quality at the time. The report concluded that “it would appear that the Group Water Schemes Programme is a cost effective means of providing water supplies in rural areas” (p.21.). It must be remembered, however, that Group Scheme grants at that time were mainly for pipe networks rather than for water treatment infrastructure. At that stage, water quality had not taken priority to the same extent as it has today. The Review did, however, made some preliminary observations in relation to initial water quality test result data, which had been collected in accordance with the 1988 EC Regulations on water quality. “First indications from these tests are that there are bacteriological problems with water quality in a number of group water schemes…Based on the EC regulations, there must be some question as to the success of the Group Water Schemes Programme in providing water of an acceptable quality for human consumption” (p.17.). In considering the pro and cons of Group Schemes versus public water supply schemes, the Review recognised that community initiative expedited the development of Group Schemes far quicker than the development of public schemes. It also recognised that Group Schemes could be delivered and operated at a lower cost due to the voluntary efforts of its members. However, it also concluded that it was difficult for local authorities to enforce water quality regulations on privately owned group schemes and that water was not being properly treated or treated at all in many Group Schemes (p.30.). “The small size of most groups makes the 33 provision of more sophisticated water treatment facilities uneconomical”(p.31.) “In some cases also, resistance to water rates may result in them refusing to accept better quality supplies from public sources” (ibid). The Review recognised that there was no easy solution to Group Schemes’ resistance to paying for public water supplies but “that there was a need to take a flexible pragmatic approach in encouraging groups to accept greater local authority involvement in helping to improve water quality in their schemes” (p.53.). It was recommended, however, that additional conditions in relation to water quality standards, be made a requirement for payment of grants for new Group Schemes to try and avoid future water quality problems (p.51). In 1989, Group Schemes Programme grants were centrally administered and scheme proposals technically assessed by the Department of the Environment with minimal involvement by the relevant local authorities. The Review considered the possibility of devolving the administrative and/or the technical functions from the Department to local authorities. It recognised the benefits of accumulating local knowledge in devolving the Programme to local authorities (p.39.) but also warned of the dangers of Councils diverting funds from group schemes to public schemes (p.38.). There were also concerns that interest in the Group Schemes’ sector could differ between local authorities and that there could be a reduced interest in cost control with funds coming directly from the Department via the local authorities (p.38.) The Review recommended either the retention of the existing centralised system or the devolution of the technical inspection role only although recognised that this was a matter for the Minister for the Environment to decide (p.45.). The Minister for the Environment subsequently fully devolved the Group Schemes Programme to local authorities in 1997. The 1989 Review concluded overall that the Rural Water Programme constituted value for money and should continue, albeit with a greater proportion of its expenditure on water quality investment (p.61-63.). The 1989 Review provides an early insight into many of the issues that now dominate the sector and, in particular, the water quality issue. While acknowledging that the Group Scheme model was cost effective in the past, it recognised that in future water treatment costs could become a major issue. It also predicted difficulties in persuading privately owned Group Schemes to adopt water quality measures and particularly being connected to the public mains 34 because of local authority water charges. This was somewhat prescient of the difficulties currently involved in implementing the two treatment solutions involving connection to the public mains, which will be discussed in Chapter 4. The recommendation that greater conditionality be placed on new Group Schemes in order to avoid future costly water quality problems has even greater relevance today and will be considered when reviewing the New Schemes element of the current Programme. Action Plan for Rural Drinking Water Quality 2003-2006 In 2003, the National Rural Water Monitoring Committee (NRWMC) launched the Action Plan for Rural Drinking Water Quality 2003-2006 “with the objective of bringing the quality of rural water supplies into compliance with the Drinking Water Regulations 2000, and to achieve this within the shortest possible timeframe (NRWMC 2003, p.3.). The Action Plan recognised that there were water quality problems with some publicly sourced Group Schemes, which should be addressed with improved operation and maintenance (O&M) of the Group Scheme network, including ensuring that there was adequate residual chlorine in the water supply entering the pipe network, to avoid re-infection (ibid, p.5.). The Action Plan, however, identified Group Schemes with private water source as being the biggest compliance concern. The Action Plan recommended that there be a focused programme of capital investment over the 2003-06 period in order to bring sub-standard privately sourced schemes into compliance with the Drinking Water Directive. It recognised that it was unrealistic to aim for full compliance by the 1 January 2004 deadline but did recommend that all actions required for compliance be “fully in place within the timeframe of the NDP (i.e. end 2006)”. The Action Plan “reflects that timeframe” (ibid, p.9). The Action Plan acknowledges the €644 million available under the NDP 2000-2006 for delivery of the Rural Water Programme (ibid, p.9). It proceeds to identify the various water quality upgrade solutions involving either connection to the public mains or stand alone treatment i.e. DBOs and Disinfection/Sterilisation. It also recommended “that investment in network renewal should be the priority once the source quality issue has been dealt with” (ibid, p.11). While the implementation of capital works being undertaken under this Action Plan are the main focus of this Value for Money (VFM) Review, it is useful to note other issues raised by the NRWMC in the Action Plan. The NRWMC emphasised the important of putting in place 35 effective Project Management Systems, particularly for large-scale bundled DBO projects. This should include the setting up of Steering Committees for each DBO bundle to oversee the project with a project manager i.e. Client Representative reporting jointly to the Group Schemes and local authority during the Design Build phase of the project. There should also be a Rural Water Liaison Officer in every local authority working full-time on progressing the implementation of the County’s Rural Water Strategic Plan. Finally, there should be a National Projects Manager overseeing the implementation of the DBO Bundles’ projects nationally and reporting to the NRWMC (ibid, p.11-12.). The Action Plan also recognised the need for capacity building to ensure that Group Scheme personnel were adequately trained to administer and manage their new responsibilities to get the full benefit from capital investment (ibid p.12.) The Department adopted all of these measures. The Action Plan also considered the two important issues of source protection and water conservation. The Plan states that “the task of supplying quality water should not rely solely on water treatment strategies” (p.13.). There needs to be a greater focus placed on source protection. Therefore, the NRWMC proposed “to develop a model of best practice in the monitoring and protection of catchment areas” (p.13.). This project has proceeded as the National Source Protection Pilot Project, which will be discussed in Chapter 5 of this Review. The Action Plan also recognised the growing issue of water conservation and the costs of treating and pumping treated water instead of raw water to households. “In many instances, it is far more cost effective to conserve water by way of an active programme of leak detection and eradication, as opposed to upsizing the capacity of the plant or commissioning additional sources” (p.13.). The NRWMC recommended the installation of bulk and district metering on all DBO projects and consideration of usage of rainwater collection technologies for agricultural and non-domestic Group Water Scheme consumers (p.14.). Towards Quality Water: A review of the work of the NRWMC and implementation of the Action Plan 2003-2006 This Review was published in early 2005 at the mid point of the Rural Water Plan and also to coincide with the end of the NRWMC’s second 3 year term. The Review recalled that the numbers of sub-standard privately sourced Group Water Schemes and the short timeframe for 36 bringing them into compliance with the Drinking Water Directive “raised obvious questions as to the feasibility and (cost effectiveness) of resolving non-compliant schemes one at a time” (2005,p.4.). NRWMC members visited a number of small communities in Brittany, France in 2000 to see how they dealt with water and wastewater treatment. Although the Brittany plants were under State control, the small plant treatment technologies used in these rural areas were very relevant to Ireland. “The potential benefits of adopting a design, build, operate (DBO) approach and of bundling smaller schemes as part of a larger contract were apparent…. Market soundings at home and abroad indicated strong interest by major DBO consortia, provided projects had critical mass. Given the relatively small scale of group water schemes , critical mass could only be achieved if a number of schemes were to be bundled as part of a single contract” (2005, p.4.) The Review goes on to explain how the Action Plan for Rural Drinking Water Quality 20032006 and its implementation timeframe was driven by developments at the European level and particularly by the 2002 ECJ ruling. The Action Plan was accepted by the European Commission “as the nucleus of a coherent strategy” (p.5). The Review examines implementation at that point under the Action Plan. Significantly, it noted that “local authorities have identified 191 schemes as requiring disinfection only. The NRWMC questions the sustainability of this approach and recommends that each Council review the quality of raw water (based on source monitoring) and look again at the appropriateness of this solution” (p.8.). The Review also referred to successive EPA reports, which showed that local authority testing of Group Water Schemes was inadequate in many cases and needed to be improved. It also referred to the fact that the testing parameters were broadened in 2003 to address concerns of Trihalomethane (THMs) contamination, due to incorrect water chlorination (p.10-11.) This is a possible risk factor for the Disinfection/Sterilisation treatment solution. The 2003 Action Plan and its 2005 Review clearly illustrate the complexities involved in tackling water quality problems in a Group Scheme sector, where there is no neat ‘one size fits all’ solution. Group Schemes, with private water sources, have clearly been identified as being the core problem. The need to comply with the Drinking Water Directive and avoid 37 ECJ fines meant that a major infrastructural programme needed to be carried out within a short timeframe. This also required a project management structure to be put in place at both central and local government level to ensure implementation and control costs. The small scale of many Group Schemes raised serious cost effectiveness issues and the DBO Bundle procurement strategy evolved based on an examination of the Brittany approach to providing small public water treatment infrastructure to rural communities. This practice of procuring a number of DBO plants together created a large enough contract to attract interest from international consortia and thus encouraged competitive market bids for the contracts. The Action Plan and its 2005 Review also raise important points in relation to the need for greater water conservation and pipe network renewal investment, as well as source protection, in the Group Schemes sectors. The issue of water quality monitoring, the THM risk factor and the questions in relation to the sustainability of the Disinfection/Sterilisation treatment solution also need to be considered further in this Report. The Action Plan also reminds us that Group Schemes are privately operated voluntary organisations and the critical success factor of “ongoing co-operation and partnership between the key stakeholders to the RWP” is perhaps the most important in implementing the objectives of the Action Plan (2003, p.14.). National Federation of Group Water Schemes -Strategic Plan 2006-2008 The National Federation for Group Water Schemes (NFGWS), usually referred to as the Federation, was founded in 1997 as an umbrella representative body for the Group Schemes sector. In recognition of the Federation’s role, it has been represented on the National Rural Water Monitoring Committee since its inauguration in 1998. It is important, therefore, to consider the Federation’s perspective, particularly in relation to the future direction of the Rural Water Programme. In its Strategic Plan 2006-’08, it states that “we want to get to the point where the Federation effectively services the needs of communityowned group water schemes run to a professional standard. We want to finally resolve the issue of deficient water quality and move beyond the present focus on end-of-pipe solutions to providing sustainable quality water supplies through an increasing emphasis on source protection and water conservation”.(2006, p.1.) 38 This is a very significant statement as it demonstrates that the Federation realise that source protection and water conservation provide a more sustainable future for the Group Schemes’ sector than just water treatment solutions alone. The Federation see the reduction of UFW and the promotion of wider strategies arising from the completion of the National Source Protection Pilot Project as tangible ways of meeting these objectives (2006, p.5.). The Federation also see an urgent need to ensure that all Group Schemes serving less than 15 houses but with a public or commercial function are identified as they must also comply with the Drinking Water Regulations. Cost effective treatment solutions must be identified for these schemes (2006, p.2.). This indicates that the Federation believe that there are several small Group Schemes requiring upgrading yet to be identified, which will have cost implications for the State. On a similar theme, the Federation recognises that many smaller Group Schemes will not be financially viable in the future, especially where water quality upgrades are required. For those schemes, amalgamation with neighbouring schemes or connection to the public mains may be the only option (2006, p.5.). The issue of smaller schemes will be an issue, which will be examined later on in this Report in the context of new schemes and alternative policy approaches. Naturally as the representative body for the Group Schemes’ sector, the Federation want to see the continuation of operational costs subsidy for domestic consumers on Group Schemes. Their objective is “to defend current subsidy arrangements and to pursue enhanced grant aid towards the operational and maintenance costs of group schemes” (p.5, 2006). The Federation’s views on the future of the operational subsidy for domestic households are characteristic of any proactive interest group. Their views on water conservation, source protection and the viability of smaller Group Schemes do, however, demonstrate a considerable level of enlightened self-interest, which sets out a sustainable blueprint for the future of the Group Schemes’ sector. It has generally been acknowledged that the Federation have played a vital partnership role in assisting the Department and local authorities in implementing water quality upgrades in the Group Schemes’ sector so it is important that their views are considered in future policymaking in that sector. 39 Comparative International Studies European Perspectives The need for Ireland’s Group Scheme sector to comply with the Drinking Water Directive raises the inevitable question of what other EU member states are doing about bringing private water supplies in their jurisdictions into compliance with the Drinking Water Directive. The answer to this in many cases is unclear. An informal group comprising officials from EU member states with responsibility for implementing the current and previous Drinking Water Directives was formed in 1995. This group known as the European Network of Drinking Water Regulators (ENDWARE) meets twice a year and this forum “provides an informal route of communications with the Commission” (www.europa.eu). An official from the Environmental Protection Agency (EPA) currently participates in this informal network. In 2005, the ENDWARE members participated in a survey by the Webbased European Knowledge Network on Water (WEKNOW) and a report entitled “Small Systems Large Problems: A European inventory of small water systems and associated problems” was subsequently published online (Hulsman, June 2005 http://www.weknowwaternetwork.com). The report includes a disclaimer that the data collected was not officially approved by respective national Governments and that it was possible that some of the information contained therein is not entirely correct (p.1.). The report estimates that “at least one in ten Europeans (40 to 50 million people) receives their daily drinking water from small and very small supplies, including private wells. There is an urgent lack of reliable information on the number of such supplies and the number of people served by such supplies” (p.7.). In this report, small supplies are defined as supplies serving between 50 and 5,000 people, while very small supplies are defined as serving less than 50 persons. Small supplies are required to comply with the Drinking Water Directive, while very small supplies are exempt unless they are connected to a premises serving a commercial or public function (p.9.). The report concludes that most EU countries have little or no information on the number of small or very small supplies in their country and this equally applies to both the 15 ‘old’ and 10 ‘new’ member states (p.7). “Most countries report that they have no information on the number of small supplies that are used for public or commercial activities” even though such supplies must comply with the 40 Drinking Water Directive (ibid). Microbiological contamination by faecal matter as indicated by the presence of E.coli, coliforms and faecal streptococci “is by far the major problem with water from small and very small supplies” (p.8.). With regard to water treatment solutions, “connection to a centralised water supply (and sewerage) system is by far the most popular remedial action countries see for problems associated with small and very small supplies…very rarely nowadays decentralised water treatment options are promoted for (very) small supplies” (p.8.). Finland, Romania and Slovakia are listed as countries that have adopted a decentralised treatment approach. It would appear, however, that Ireland’s extensive decentralised treatment plant programme approach is not generally being adopted in other EU states. The report does comment, however that “it is surprising that very little use is made of new decentralised treatment options that are available nowadays”. It also comments that connection to a centralised water supply is not always the most sustainable treatment solution for remote rural areas (p.31.). The report also considered the issue of risk assessment/risk management of small water supplies. This is already being adopted in many EU states, including Ireland, for public water supplies and should also be considered for small supplies (p.35). In this context, the report refers to a then recently published Scottish Executive consultation paper on private water supplies regulations and grant aid. Scottish Initiative There were major developments in the regulation of the Scottish private water supplies sector in 2006 to bring it into compliance with the 1998 Drinking Water Directive. “Around 150,000 people in Scotland rely on a private water supply - any water supply not provided by Scottish Water - for their drinking water. Instead of Scottish Water, the owner or person who uses the supply is responsible for its maintenance. Supplies vary in size from those that serve one household to those that serve hundreds of people…. The 2006 Regulations, which came into force on 3 July 2006, incorporate the latest advances to improve drinking water quality including the use of risk assessments from 'source to tap' as part of an effective drinking water surveillance programme…. Grants of up to £800 [€1,178 per premises] are available from your local authority provided certain qualifying conditions are met.” (http://www.scotland.gov.uk/Topics/Environment/Water/pws/pws1). 41 The Scottish Executive have set up a dedicated website, with advice in relation to private water supplies http://www.privatewatersupplies.gov.uk/. It expressly encourages private water consumers sharing the same water source to make joint grant applications as “in the majority of cases a joint approach is likely to provide the most effective long term solution to improve your water quality”. A Private Water Users: Technical manual and consumers manual has also been published on this website. The technical manual explains that “research carried out for the Scottish Executive indicated that improvement costs are likely to vary greatly, largely in the range of £125 - £2,500 per premises, but that the most important health benefits are usually gained from installing ultra violet treatment and appropriate pre-filters. The £800 grant will meet or make a substantial contribution towards the costs faced by the majority of users. There will be cases where the supply requires work, which exceeds this maximum and in such cases, and subject to regulation 8(2) of the Grants Regulations, it will be the responsibility of the eligible person to meet the additional costs”. (Technical manual Section 9, P.44.) “During the autumn of 1996 and early 1997 a spate of outbreaks of E. coli O157 infections resulted in the deaths of 20 elderly people in Scotland although not all outbreaks caused deaths to occur. One of these non-fatal outbreaks was attributable to a private water supply at Dunecht in North-East Scotland (Technical Manual 2006, Section 4, p.22.) This prompted a focus on improved source protection guidance for water supplies. The 2006 Regulations require that Scottish local authorities carry out risk assessments on all Type A private water supplies i.e. all private water supplies required to comply with the Drinking Water Directive. Risk assessments, seen as an essential element of an effective drinking water quality surveillance and control programme, include • identification of potential sources of contamination and how they can be controlled; • validation of control measures employed to control hazards; • implementation of a system for monitoring the control measures within the private supply; • timely corrective actions to ensure that safe water is consistently supplied; and • undertaking verification of drinking water quality to ensure that the recommendations arising from the risk assessment are being implemented correctly and that quality standards 42 meet the prescribed concentrations or values set down in the 2006 regulations.” (Section 9, p.21) A risk assessment is a perquisite for receipt of remedial grant aid from the Scottish Executive’s grant programme. This risk assessment approach complies with the latest guidance from the World Health Organisation (WHO), which confirms that “the most effective means of consistently ensuring the safety of a drinking water supply is through the use of a comprehensive risk assessment and risk management approach that encompasses all steps in water supply from catchment to consumer”. At 618 pages, the Scottish Executive’s Private Water Supplies Technical Manual 2006 provides a rich source of best practice advice, which could be of potential benefit to policy makers in the Irish group scheme sector. When compared against our European counterparts, Ireland seems to have been quite proactive in identifying and addressing the issue of water quality in private water supplies in the Group Schemes’ sector. If nothing else, Ireland’s Environmental Protection Agency (EPA) has reported annually on the water quality in these Group Schemes for many years even if local authorities’ monitoring coverage is less than perfect. It would appear that Ireland is, in many respects, a victim of its own transparency in highlighting the water quality problems on its Group Schemes, thereby incurring the attention of the European Commission, as watchdog of the Drinking Water Directive. The evidence suggests that other EU states have not even properly identified their private water supplies. It is also interesting to note that the European Commission and the Council of Ministers decided to include certain private water supplies, within the terms of the Drinking Water Directive, with apparently little substantial information about this sector. That said, Ireland must meet its statutory obligations and the Scottish approach to making risk assessments of private water supplies mandatory could point the way towards a more robust approach to source selection and source protection, particularly in relation to grant aiding new Group Schemes. This could avoid the need for expensive and economically unsustainable treatment solutions for smaller Group Schemes in the future. It is also interesting to note that Ireland’s investment in decentralised water treatment solutions is relatively unusual by European standards but could be a more sustainable use of new small plant technologies. 43 Finally, Ireland’s grant aid limits of €6,476 per house for water quality upgrade solutions appears to be quite generous, when compared against the Scottish Executive’s grant limit of £800 (€1,178 per premises). That said, it must be borne in mind that the Scottish grant programme only commenced in 2006 whereas Irish grant levels were only raised to their current levels in 2000, based on experience of the real costs of upgrading group schemes’ water quality. Comparative Analytical Literature Comparative National Studies of the Irish Water Services Sector Evaluation of Water Services Investment in the National Development Plan (NDP) and Community Support Framework (CSF) for Ireland 2000-2006 Fitzpatrick Associates Economic Consultants carried out this evaluation in 2005 on behalf of the Department of Finance’s NDP/CSF Evaluation Unit. This document is an invaluable recent study of the overall national water investment programme. Because of its breadth, the report only carried out a limited review of rural water p.26-28. (water quality in Group Water Schemes) . However, the report’s findings do reflect on issues, which are relevant to this study. The Review explained that due to the bespoke nature of many water treatment schemes (p.5-6. & p.121.) serving widely varying population densities, it is not possible to set precise benchmarks in terms of cost efficiency. “What may be good value in one place may be bad value in another: depending on circumstances” (p.131.). The report does, however, look at the benefits of new innovative procurement practices such as DB and DBO compared to traditional procurement (p.94 & 140.). Such approaches reduces the incentive for local authorities and consultants to understate final cost at scheme approval stage in the knowledge that cost overruns on schemes in progress will be paid by central government in order to ensure scheme completion.(p.iv). It also improves market competition in service delivery with the effect of maximising plant efficiency and minimising costs over the lifetime of the project (p.140.). 44 Fitzpatrick does, however, conclude that it will take several years to assess the value for money (VFM) of DBO projects (p.96.). The report calculates the cost /per population equivalent (pe) ratio of several completed water treatment schemes (p.121-128.) and concluded that there is clear evidence that there are economies of scale to be had from larger rather than smaller schemes. There are also administration and management economies of scale to be had where smaller numbers of qualified staff can monitor and manage a number of water facilities remotely. The report explains that while it is not cost efficient to have several small water plants within the same water catchment areas, it is equally inefficient and expensive to distribute water over large water networks in rural areas because of piping and pumping costs (p.144.) The Report also comments on the over emphasis on “big engineering” over more “mundane activities” (p.138.) such as water conservation projects. The report expresses concern at the lack of data available in relation to water consumption, production and leakage i.e. Unaccounted for Water (UFW) because of the lack of metering (p.viii & ix). The report raises the possibility that due to UFW, “Ireland could be as a country producing (i.e. extracting, treating and sending down the pipe) about twice the level of water that would be reasonable to assume we need”. (p.21.) The report also reminds readers of the environmental costs of water treatment as water extraction places demands on primary water sources and water treatment has energy costs (p.vii). It also predicts that the recent guidelines on rural housing will lead to an increase in demand for water in rural areas and increase demand for connections to Group Water Schemes. It will also increase the potential risk to groundwater (p.45.) Fitzpatrick balances the advantages and disadvantages of the Group Water sector and concludes on balance that the status quo should prevail for the moment at least as in its absence the public sector would have to provide for the “existing customers” anyway (p.146) Fitzpatrick Associates draw four specific conclusions in relation to value for money in Ireland’s public water services sector. (p.146 - 147 ). 1. While unit costs such as cost per p/e can be calculated, “they are very location specific and only limited interpretation of them is possible”. The market competition offered by DBO contracts, rather than traditional procurement, provides a better chance that the most cost effective solution for a location will be secured. 45 2. Positive benefit/cost ratios only provide reassurance that projects are worthwhile, but not whether they achieve maximum efficiency. 3. There is clear evidence that larger schemes with high density catchments involve lower unit cost. However, in lower density areas, the pumping costs of water over long distances outweigh the benefits of larger plant economies of scale. The second point is particularly relevant to Group Schemes, when considering the cost alternatives of building a small stand alone water treatment plant to connection to the nearest public main or connection to a larger Group Scheme plant some distance away. 4. Many of the main Value for Money (VFM) issues in the water sector relate to macromanagement issues rather than micro project level cost efficiencies. “They relate to whether, however cost effectively or ineffectively, we are producing more water than we need, losing more than we need consuming more than we need and treating more than we need. If we are doing more than we need, no amount of project-level efficiencies will get away from a situation of poor value for money” (p.147.). This comment relates to the whole water sector in Ireland rather than the Group Water sector but it illustrates that many of the issues in the Group Schemes sector in relation to water conservation, leakage and metering are mirrored if not magnified in the public water sector. Fitzpatricks points out that the lack of metering and water charging of domestic households on the public water supply means that water leakage and overuse cannot be monitored. It states that the National Federation of Group Water Schemes (NFGWS) has estimated that the cost of metering a new house is €50 and it is €250 for an existing house (p.152). [The Department’s Inspectorate believes that this figure is too low and that a more realistic cost estimate is €600 rather than €250 per existing house]. Fitzpatricks draws an unfavourable comparison between the management of the water services and the ESB system in terms of lack of management information (p.153.). The current management of water services in Ireland is akin to “attempting to run a national electricity grid without electricity meters.” (p.155.). 46 This report is important as it explores several themes relevant to the Group Water sector and adds to the body of knowledge on the water treatment system in Ireland. The most significant point that it makes from the perspective of this study is the difficulty with making cost comparisons and benchmarking in the water services sector. A “distinct feature of the sector, which has very direct relevance to any evaluation that addresses value-for-money issues, is that water infrastructure and plant is designed on a quite bespoke basis for particular locations. In practice this makes benchmarking and cost comparisons across projects and locations even within Ireland, never mind internationally, difficult.” (2005, p.6.) This point will have to be borne in mind in designing a methodology for analysing the value for money of the Rural Water Programme. Expenditure Review of Exchequer Financed Water and Sewerage Schemes This Review was submitted to the Department of Finance in December 2002 and made the case for continued funding of this programme. The objectives of the programme were, inter alia, to meet domestic and broader economic water and sewerage treatment needs and to comply with various EU directives, to reduce environmental pollution. The Review referred to the Government policy that there should be full cost recovery of the operation and maintenance cost of providing water services to the non-domestic sector. It also states that there should be cost recovery of the marginal capital cost of infrastructure provision for nondomestic purposes (p.28.). The Review explained that due to the varied size of schemes under the Programme, it proved difficult to assess the overall effectiveness of the programme. As there was no common cost benefit technique available, it was decided to take a number of schemes varied as to size, objective and location and assess each scheme by way of a multicriteria analysis. The same methodology was used in the Mid-Term Evaluation of the Operational Programme for Environmental Services 1994-1999 (p.30.). The multi-criteria analysis looked at the various impacts of the Schemes but did not involve a financial analysis apart from a reference to final scheme cost and whether the tender price was exceeded. The Review also refers to weaknesses in the water distribution system due to substantial losses through leakage (p.25 & 58.). The Expenditure Review concluded that “the continued availability of exchequer funding in addition to the other specified funding sources is vital to ensure that we are able to meet the demands of our growing economy and achieving an 47 appropriate balance between the requirements of that economy and the protection of our environment” (p.61.). It is interesting that in this report too there are difficulties expressed in relation to comparing and assessing the relative cost effectiveness of various water projects. The alternative multi-criteria analysis approach used very little financial data but there is obviously a subjectivity problem in determining the weighting for different criteria for this approach. Mayo Bundle 2 – Leakage Control Strategy – March 2005 The above reports have highlighted the problems of water leakage and the need for greater water conservation in the Irish water services sector. In 2004, Ryan Hanley Engineering Consultants were commissioned to carry a leakage control study of group schemes in Co. Galway and in 2005, they were engaged by Mayo County Council to carry out a similar study of Mayo group schemes. These studies are very significant as they provide a clear illustration of the problems with Unaccounted for Water (UFW) in the group scheme sector and an economic assessment of the most cost effective approach to addressing this issue. The counties involved are also very significant as Galway and Mayo have respectively the greatest and second greatest number of group schemes in the country. Over 60% of the schemes requiring upgrading, to comply with the Drinking Water Regulations, are located in these two counties. Both leakage control reports follow a similar format so the Mayo Report will be considered here, as it is the most recently published of the two reports. The Mayo Leakage Report looked specifically at 21 group schemes being considered for the procurement of DBO treatment plants together as Mayo DBO Bundle No. 2. The Leakage Control Strategy found that bursts and leakage represent the single largest component of UFW, which was estimated to be “between 26.3% and 79.9% of total demand” on individual Group Schemes in the Mayo Bundle No. 2 (2005, p.5). The report states, “rural schemes also generally exhibit a higher percentage loss than urban systems, simply because of the much greater pipe length required per consumer” (ibid). It acknowledges, “it is unrealistic to expect any buried system to be leak free” which is why the target UFW level of 25% set by the Department is a reasonable one (p.8.). The report predicts “that there would be a progressive increase in unaccounted for water over time” in the absence of remedial measures (ibid, p.6.). 48 It is explained that a “strategy for leakage control is governed by three main factors: a) Security of Supply – the need to keep demand below the reliable yield of the raw and treated water resource facilities, thus avoiding the need for rationing or other demand control measures which impact on the community, b) Economics – the reduction of leakage levels to point where the additional cost of saving an extra cubic metre of water is more than the cost of producing it, and c) Environmental – the impact on the natural environment of the abstraction of water that is not beneficially utilised”. (ibid, p.8) From an economic and value for money perspective, the report found that out of 21 group schemes in Mayo Bundle No. 2, it was cheaper to carry out leakage control measures on 19 of the schemes rather than build additional water treatment plant capacity to allow for continuing water wastage at the existing UFW levels. In the case of the other 2 schemes, building additional treatment capacity would not be sustainable in the future due to worsening UFW in one case and in the other case, the additional treatment capacity would have placed too much abstraction demand on the water source (p.1.), with possible knock on environmental consequences for fish, flora and fauna (p.11.). These findings are significant as they demonstrate that UFW represents a significant additional capital and current cost for water treatment on group schemes and that targeted leakage control measures can significantly reduce these costs. The report also makes some pointed remarks about the absence of water meters on the Mayo Bundle No. 2 group schemes at that time. “The installation of consumer meters should lead to a significant reduction in waste, as many consumers will be unaware of what normal consumption for their premises should be. The fact remains that without metering there is no incentive to conserve water and minimise waste” (2005, p.13.). As already discussed in the Fitzpatrick Associates’ report, these remarks, about the lack of metering of domestic connections, are just as relevant to the public water supply sector as to the group scheme sector. 49 Rural Water Programme - Outputs Measurement Report to the European Commission on measures to bring Group Water Schemes into compliance with the Drinking Water Directive – Department of the Environment, Heritage and Local Government - June 2006 This Departmental report is vital in providing a detailed picture of progress to date in upgrading all Group Schemes, subject to the ECJ ruling. As well as a national overview, it provides breakdowns of implementation on a county, solution and scheme by scheme basis. This report measures outputs from investment to date under each water quality upgrade solution. The lists of upgraded schemes will facilitate the selection of a number of group schemes, under each treatment solution, for case study review. The report is more a quantitative update of programme implementation rather than an analytical review. However, it appears that implementation of the Design Build Operate (DBO) standalone treatment solutions is far more advanced than the two solutions involving connection to the public mains. This Review will examine the reasons for this apparent imbalance in programme implementation to date in Chapter 4. Rural Water Programme – Outcomes Measurement The Quality of Drinking Water in Ireland – A Report for the Year 2005 (Environmental Protection Agency 2007) In many respects, this is the most important report in this Literature Review as it goes right to the heart of the issue driving investment under the current Rural Water Programme. The EPA publishes a drinking water quality report each year based on the results of water testing carried out by local authorities, as required under the 2002 Drinking Water Regulations. The report estimates that 6.4% of the total population is served by private group water schemes and 3.4% by public group water schemes (p.9). Previous reports have highlighted problems with water quality on privately sourced Group Schemes in particular and the 2007 Report is no different. It states in unambiguous terms that in 2005 the “quality of drinking water supplied to public group schemes was satisfactory while the quality of drinking water supplied by private group schemes was unsatisfactory” (p.56.). The report also comments that 50 the “high percentage of samples indicating contamination with E.coli in the private group water schemes is of great concern” (p.20.) It was also noted that in 2005 “for the first time in 5 years there has been an increase in the percentage of samples contaminated with human or animal waste”(ibid). The Report explains that there are 46 water quality parameters under the 2000 Drinking Water Regulations broken down into the categories of microbiological, chemical and indicator parameters. Water samples, for each Group Scheme required to comply with the Drinking Water Regulations, must be tested at least twice a year. Where a microbiological or chemical parameter exceedance occurs on a Group Scheme, the local authority is required to serve a notice on the person responsible for the supply within 14 days of receipt of the results. The notice must require the Group Scheme to prepare an action plan within 60 days of receipt of the initial result. The measures proposed in the action plan must be implemented within one year for failures that present a risk to public health and within two years for exceedances that do not present a risk to public health. In the case of an indicator parameter exceedance, the Council must first determine whether or not the exceedance poses a risk to human health. If it does, the Group Scheme is required to carry out the corrective actions already outlined for a microbiological or chemical parameter exceedances (2007, p.6-7.). The report recommends that “sanitary authorities should ensure each group water scheme (public or private), where microbiological quality problems were identified, has an action programme prepared to address the quality deficiency” (ibid). It also recommends that in cases where group schemes have not prepared an action plan to improve the quality of their water supply or have failed to implement it “the sanitary authority should use all the enforcement powers available to it to rectify problems including, where necessary, prosecution.” (p.56-57). County Councils, as sanitary authorities, are empowered to take prosecutions against non-co-operative Group Schemes under the 2000 Drinking Water Regulations and have been given additional powers to take remedial action themselves under the updated 2007 Drinking Water Regulations. The EPA noted that “no local authority audited by the Agency during the year [2005] had taken enforcement action to ensure compliance in the quality deficient group water schemes”(2007, p.1.). The report also comments that 51 “In spite of record levels of investment in the group water schemes sector, progress in upgrading schemes is simply not happening at a fast enough speed. Furthermore, while the majority of schemes have action plans in place to address the quality deficiency, a sizeable number of schemes have prepared no corrective action plan.”(2007, p.2.). In relation to group water schemes being supplied from the public mains, the report recommends that the group scheme operators “should ensure that the quality of the water supplied by the sanitary authority does not deteriorate in the group water schemes distribution network”(p.57.) This point is very significant as connecting a group water scheme to the public mains considerably reduces the risk of poor quality water, however, there is a risk of re-contamination if the pipe network is not properly maintained. One issue that the EPA is very critical of is the lack of adequate water quality monitoring by the local authorities, particularly of the Group Schemes’ sector. All Group Schemes, required to comply with the Drinking Water Regulations, must be tested at least twice a year and more often in the case of larger Group Schemes. In many cases, Group Schemes are being tested inadequately or not at all. In 2005, 65% of publicly sourced Group Schemes and 41.2% of private Group Water Schemes were inadequately monitored. 9% of private group water schemes were not monitored at all in 2005. “People supplied by these schemes may be drinking contaminated water but may not even be aware of the fact that their water is unfit for consumption” (2007, p.12.). The EPA also identified a specific issue with regard to the lack of testing of small group schemes serving less than 50 people but supplying water to a connection with a commercial or public function. Such schemes must also comply with the Drinking Water Regulations. The EPA found that such schemes had not even been identified never mind tested in 6 out of 7 counties audited by them (2007, p.47.). It must be remembered though that this is an assessment of local authority monitoring in 2005 and that the situation may have improved in 2006. Departmental officials reminded local authorities of their statutory water quality testing duties at a conference of Rural Water Liaison Officers on June 8th 2006. The EPA have been given greater powers, under the 2007 Drinking Water Regulations, to take legal enforcement action against Councils that fail to carry out their monitoring duties adequately. 52 From the perspective of this value for money review, this Drinking Water Quality Report will be a crucial tool in measuring programme outcomes. Compliance with the regulation requires water at the household tap to be of adequate quality. Therefore, the completion of treatment solutions for Group Schemes is only a measurement of outputs as it is not guaranteed that clean water from the DBO treatment plant or public water supply will come out of household taps in the same condition. As already stated above, there is a risk of re-contamination in poorly maintained Group Scheme pipe networks (2007, p.57.). Water samples are tested at the household taps so this is the true measurement of compliance or non-compliance with the Drinking Water Directive. A CD accompanies the Drinking Water Report, which should contain water quality test result data for every Group Scheme required to comply with the Drinking Water Regulations. A number of Group Schemes upgraded prior to 2005 will be selected and their test results for 2005 will be checked to verify that these upgraded Group Schemes were in fact compliant with the Drinking Water Regulations in 2005. If the completed Schemes are still non-compliant it casts a question mark over the effectiveness of that treatment solution and the financial investment in it. The measurement of outcomes will be discussed further in the methodology chapter. The 2007 EPA drinking water quality report makes stark reading for the group schemes sector. If nothing else, the fact that a report on the state of drinking water supplies nationally focuses so much on a sector that serves less than 7% of the entire population says a lot. It must, however, be reiterated that these figures are based on 2005 data and do not take into account water quality improvements since then. That said, the level of implementation of the rural water plan by June 2006 was still relatively modest, particularly in relation to solutions involving connection to the public mains. There are numerous practical problems in trying to persuade private volunteer based community water schemes to engage with the rural water programme so the local authorities job is far more complicated than dealing with public water supplies. The prosecution of some group schemes trustees could “inevitably result in committees of management simply ‘walking away’ (rather than being held legally accountable) and schemes collapsing” (NFGWS submission-Appendix 3). However, nonaction is simply not an option on public health grounds. Ultimately, “it is unacceptable for persons responsible for the management of group water schemes to supply water to members of the public that is contaminated with human or animal waste” (EPA 2007, p.42.). 53 Conclusions As can be seen from this literature review, the water services sector in Ireland and specifically the Group Scheme sector is highly complex and diverse. Professor Daly’s “The Buffer State” demonstrates that the Group Schemes’ model was the preferred approach of rural Ireland, or at least its representatives, for the provision of piped water supplies to remote areas of the country. The 1989 Review of the Group Schemes’ Programme begins to mark the shift in emphasis of the programme from a water supply to a water quality objective. The Action Plan for Rural Drinking Water Quality 2003-2006 marks the development of a coherent strategy to tackle the problems of water quality in the private Group Scheme sector, in particular, in order to avoid major EU fines for non-compliance with the Drinking Water Directive. The Action Plan also shows that there is no “one size fits all” treatment approach to solving these problems and that co-operation with all stakeholders in the Group Schemes’ sector is vital for success. The National Federation of Group Water Schemes recognise that the issues of water conservation and source protection will become more and more vital in the future. They also recognise that the future viability of smaller privately sourced Group Schemes is questionable given the additional costs of water treatment. The 2006 Fitzpatrick Associates National Review of the Water Sector raises many issues relevant to both the public and group schemes sector and specifically the ongoing problems of Unaccounted for Water (UFW) and the need for greater water conservation. In the context of VFM methodological approaches, the Fitzpatricks report and the 2002 Expenditure Review both question the usefulness of a comparative unit cost approach based on Cost per head of population (p/e) [or cost per house in the case of Group Schemes] due to the bespoke nature [i.e. individual custom made design] of individual water treatment plants serving population catchments of widely differing densities. They regard issues such as procurement approaches and leakage control as providing better indications of value for money. The latter issue is borne out by the findings of the 2005 Leakage Control Strategy for Mayo Bundle No. 2. Other methodological based literature will be considered in Chapter 3 on methodological approaches. 54 Ireland compares relatively well by comparison to other EU states in relation to our information gathering on private water supplies. Irish grant aid to the group schemes’ sector is relatively generous by comparison to Scotland. However, the Scottish focus on mandatory risk assessment and source protection could provide a model of best practice for Ireland. Finally, the Department’s June 2006 Report to the European Commission and the EPA’s Drinking Water Quality Report for 2005 will provide an invaluable source of output and outcome verification data for the purposes of this Value for Money Review. 55 Chapter 3 Methodological approaches 56 Introduction The primary objective of a methodological approach is to derive a systematic means of satisfactorily addressing each of the terms of reference for this Value for Money Review. Therefore, each of the terms of reference will be considered in turn in this chapter and the methodological approach will be outlined. The data required and how it was sourced will also be discussed. Finally, the reasons for this methodological approach and its limitations will be considered. Efficiency and Effectiveness Issues The main purpose of this Value for Money Review is to determine whether the objectives of the Action Plan for Rural Drinking Water Quality 2003-’06 are being achieved using an efficient level of resources. As previously stated, the Programme outcome i.e. objective is to ensure that the water coming out of household taps in Group Water Schemes serving 50 or more persons meet EU drinking water quality standards. The programme inputs is the expenditure incurred on water quality upgrade solutions as well as investment in source protection and pipe distribution system upgrades. The Programme outputs are the completion of infrastructure works and the production of treated water. It is usually more difficult for VFM Reviews to assess whether outcomes have been achieved as a result of Programme investment. In this case, it is relatively straightforward as the water coming out of household taps will either pass or fail the drinking water standards, thus measuring a positive or negative outcome. It is more difficult, in this case, to measure whether the investment in Programme inputs delivered outputs in the most cost efficient manner due to the number of different water quality upgrade solutions and the fact that no two water schemes are identical from a comparative perspective. The main issue here is whether it was more cost efficient to pipe and pump water out from the nearest public supply or alternatively to build or upgrade a small treatment plant to serve the Group Water Scheme or Group Water Scheme sub-bundle. Did local authorities carry out a robust assessment of the comparative costs? Also, most expenditure is focused on treatment solutions but would it not be more cost effective to invest more in source protection to reduce treatment costs. Similarly, after water treatment, it is quite possible that water may become re-contaminated in sub-standard Group Water Scheme 57 distribution systems or treated water may be lost through Unaccounted for Water (UFW). These issues must be considered when designing a methodology for assessing the effectiveness and efficiency of Rural Water Programme investment. Data Requirements and sources As the management of the Rural Water Programme is devolved to County Councils, most of the financial data on specific Group Schemes was obtained from the local authorities. In the case of DBO treatment plants, financial data was obtained directly from the DBO client representatives employed by the Councils and the Group Schemes to oversee the DBO contractors. Data in relation to overall programme implementation was sourced from the June 2006 Report to the European Commission and the attached Questionnaire, which was completed by all County Councils (Appendix 4). Data in relation to programme effectiveness was obtained from the most recent water quality test results, published by the Environmental Protection Agency (EPA), for 2005 (EPA, 2007). Water quality data, post 2005, was requested from local authorities. Stakeholder Consultation It is vital that stakeholder consultation is carried out as part of this Review, particularly given that it is a local authority managed programme and also because all of the Group Water Schemes are in private ownership. All County Councils administering Group Water Scheme upgrades were invited to make submissions in addition to completing the attached questionnaire. The Questionnaire approach was chosen to provide a structured means of collecting the necessary data from County Councils to address the terms of reference of the Value for Money Review. The issues raised in the Questionnaires were based on conversations with Departmental staff and a review of previous studies on investment in water treatment infrastructure. Both administrative and technical Departmental staff were consulted in relation to the Questionnaire before it was issued to local authorities. Officials from Mayo and Sligo County Councils were also asked to make comments on the draft Questionnaire prior to issue. All of the member groups of the National Rural Water Monitoring Committee were also invited to make submissions relevant to the Review’s terms of reference. Specific questions 58 were addressed to the National Federation of Group Water Schemes (NFGWS) as the recognised representatives of the Group Water Scheme sector. The Drinking Water Unit of the European Commission’s Environment Directorate were also invited to make a submission. The National Federation of Group Water Schemes (NFGWS) made the only submission, which is attached in Appendix 3. Methodology for addressing the Review’s Terms of Reference (in italics) Identify programme objectives The Programme objectives were identified in Chapter 4 by examining the objectives set out in the Action Plan for Rural Drinking Water Quality 2003-’06. The primary objective of the Action Plan is to upgrade drinking water quality for Group Water Schemes serving greater than 50 persons so as to comply with the European Union’s 1998 Drinking Water Directive. Subsequent Departmental Circulars to local authorities were also examined to verify programme objectives. Examine the current validity of those objectives and their compatibility with the overall strategy of the Department of the Environment, Heritage and Local Government. The current validity of these objectives was assessed in Chapter 4. The June 2006 “Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive” and the latest Environmental Protection Agency (EPA) reports on drinking water quality were examined to assess the current state of drinking water quality, in the Group Schemes’ sector. The objectives of the Action Plan for Rural Drinking Water Quality 2003-’06 were also compared with the relevant objectives of the current Strategy Statement of the Department of the Environment, Heritage and Local Government to verify their compatibility. Define the outputs associated with the programme activity and identify the level and trend of those outputs The programme outputs and level and trend of these outputs were identified in Chapter 4 by comparing the objectives of the Action Plan for Rural Drinking Water Quality 2003-’06 with the most up to date and comprehensive information on programme implementation i.e. 59 completion of Group Scheme upgrades available in the June 2006 Report to the European Commission. In addition, all County Councils were asked to respond to Questions 5 to 10 in the attached Questionnaire (Appendix 4). These questions ask Councils to explain delays in programme implementation in general and also delays in implementing particular upgrade solutions. Councils are also asked to identify any additional measures needed for successful programme implementation. There are also other works ongoing, under the Group Schemes’ Programme, in addition to the water quality upgrade solutions. These include New Schemes, Scheme Extensions and Pipe Network Upgrades. As the June 2006 Report does not contain output data on these activities, Councils were asked to provide details of output activity for these elements over the 2003-’06 period in their Questionnaire returns (Appendix 4 – Q23-Q25). Examine the extent that the programme’s objectives have been achieved, and comment on the effectiveness with which they have been achieved The effectiveness of the Rural Water Programme is equally if not more important than its cost efficiency, given its public health significance. The only test of this is whether Group Schemes comply with the Drinking Water Regulations after they have been upgraded. The Regulations set out 46 parametric values for drinking water quality broken down into three categories, Microbiological (2), chemical (26) and indicator parameters (18). These parameters are listed in Appendix 5. If a water supply, covered by the Regulations, exceeds any of the microbiological or chemical parameters, the Group Schemes is required to take action to remediate this situation. In the case of indicator parameters, remedial measures are only required if the parameter exceedances pose a threat to human health. Therefore, at a minimum, treatment solutions are required where microbiological or chemical parameters are exceeded otherwise the public or private water supplier is non-compliant with the Regulations. Local authorities are required to monitor water supplies in their administrative area and carry out testing on water samples as laid down in the Regulations. County Councils must test all Group Schemes, whether connected to the public supply or on a private water supply. These test results are then submitted to the EPA, who can audit them and also verify that local authorities have carried out sufficient testing. The most up to date test result data published by the EPA is for the year 2005 (EPA, January 2007). 60 A number of Group Schemes upgraded in the 2003-’06 period were selected from each of the five treatment solution categories. The EPA test results for the Schemes, in the year after upgrading, were checked to verify if that Scheme was compliant. If the Group Scheme water samples do not exceed any of the microbiological or chemical parameters after being upgraded, the treatment solution can be deemed to have achieved a successful outcome and be considered effective. If alternatively, the samples still show exceedances for these parameters after upgrading, then the Group Scheme is still non-compliant with the Drinking Water Regulations. In this case, a successful outcome was not achieved and the treatment solution used was not an effective use of public money. It should be noted that since the most recent published EPA data is only up to 2005, local authorities were asked to provide data on water quality results for Schemes upgraded from 2005 onwards. Overview data on effectiveness was also gathered by requesting all County Councils to respond to Questions 11 to 12 in the attached Questionnaire (Appendix 4). Councils were asked to Confirm that all Group Schemes, which have been completed i.e. upgraded under the Action Plan, now fully comply with the Drinking Water Directive i.e. have achieved their programme objectives. Identify any risk factors, which could impact on the sustainability of the completed water quality upgrade solution e.g. water source contamination or recontamination of water in the pipe network. Confirm that they have an active monitoring system in place to verify that the quality of water coming out of household taps in the upgraded Group Schemes is compliant with the Drinking Water Directive. 61 Identify the level and trend of costs associated with the Action Plan for Rural Drinking Water Quality 2003-’06 and thus comment on the efficiency with which it has achieved its objectives The level and trend of costs associated with the Action Plan for Rural Drinking Water Quality 2003-’06 was identified based on Departmental grants to local authorities and expenditure returns from local authorities for the 2003-’06 period. The efficiency of this expenditure was assessed by both an overview of local authority cost control practices and an examination of a number of case study schemes for each of the water quality upgrade solutions. Overview of cost control practices A general survey of each Council’s cost control practices was carried out to assess the overall efficiency with which the Action Plan has been implemented. All County Councils were asked to respond to Questions 1 to 4 and 14 to 22 in the attached Questionnaire (Appendix 4). A comparative analysis of all Councils’ responses to the Questionnaire was also carried out. The questions sought to address the following issues: Were all water quality upgrade solution options considered and was the most cost efficient treatment solution adopted e.g. connecting the Group Water Scheme to the public water supply rather than building a dedicated water treatment plant? Was competitive tendering used to ensure that the most cost efficient contract was awarded and was the most cost effective procurement route used? Was the cost efficiency of connecting a number of schemes to the same treatment plant considered? Were treatment plants built with the most cost efficient design capacity i.e. sufficient water treatment capacity to deal with current and future development water demand but with minimal allowance for water wastage (UFW) in the Group Schemes pipe network distribution systems? 62 In cases where Group Schemes receive their water from the public water supply, how does the Council charge domestic and non-domestic consumers for their water supply and how do these charges compare both across Councils and to charges for non Group Scheme customers? Efficiency analysis of case studies for each upgrade solution A more detailed analysis was also carried out of the cost of upgrading the water quality of a sample of schemes for each solution type. The same upgraded Group Schemes already selected for the effectiveness analysis were used in the efficiency assessment. Firstly, it was verified whether the cost control practices already outlined above were observed in the case of each upgraded scheme. The relative upgrading cost [i.e. cost per house] of Group Schemes were examined to assess cost efficiency. For each of the case study schemes; The relative cost of upgraded schemes with the same water quality upgrade solution was compared The relative cost of completed schemes with different upgrade solutions was compared There are limitations to this comparative methodological approach, which will be explained later on in this chapter, but it provides transparency on the relative cost to the exchequer of these upgrading solutions. It also provides a means of verifying that the responses provided by local authorities in the general survey are reflected in their implementation of individual Group Scheme upgrades. Care had to be taken to ensure that additional costs involved in bringing the Group Schemes into compliance with the Drinking Water Directive were factored into the overall cost of the upgrade solution e.g. the cost of upgrading the pipe network in addition to the cost of the water quality upgrade solution. Pipe network upgrade cost data was generally not available for DBO projects as these works are only getting underway in many cases. One of the benefits of DBO projects is that the whole life costs of the treatment plants, known as the Operational and Maintenance (O&M) costs, are set out in the DBO contract. However, 63 there are methodological problems in making comparisons with the O&M costs of local authority public water supplies as explained in the section on unit costs below. Evaluate the degree to which the objectives warrant the allocation of public funding on a current and ongoing basis and examine the scope for alternative policy or organisational approaches to achieving these objectives on a more efficient and/or effective basis. The continued need for public investment in the Rural Water Programme under future post 2006 Action Plans was assessed in Chapter 5 based on programme implementation to date to bring Group Schemes serving greater than 50 persons into compliance with the Drinking Water Directive. It was also assessed whether additional investment, over and above present commitments, will be required in the future e.g. upgrades of Group Schemes serving less than 50 persons. Various alternative policy and organisational approaches for achieving programme objectives were also considered and analysed based on consultations with stakeholders and other relevant/interested parties. The potential effectiveness and cost efficiency of these alternative approaches was considered. For example, the current policy focus is meeting objectives through ‘end of pipe’ solutions through the treatment of sub-standard water. There is an alternative view that it would be more effective to invest in source protection measures to protect the quality of water sources and reduce contamination of the raw water in the first place. Specify potential future performance indicators that might be used to better monitor the performance of future Action Plans for Rural Drinking Water Quality Key programme performance indicators and management information data needs were identified during the course of this Review. Recommendations are made in relation to the future collection and use of such indicators in Chapter 6 of this Review. 64 As the administration of the Rural Water Programme is largely devolved to local authorities, the efficiency and effectiveness of the local government system in meeting the objectives of the Action Plan for Rural Drinking Water Quality 2003-’06 will be assessed The role of local authorities in implementing this devolved Programme was assessed as part of the methodological approaches already outlined above. Individual County Councils are responsible for Programme implementation, efficiency and effectiveness in their areas. The role of local authorities in programme implementation was reviewed in the context of alternative organisational approaches in Chapter 5. Methodological issues In measuring the comparative cost of different water quality upgrading projects, one has to be mindful of comparing ‘like with like’ (Mulreany 2002, p.18). In “Economic and Financial Evaluation – Measurement, Meaning and Management”, Mulreany identifies a number of measurement difficulties and diseases. He gives the example of a surgeon in an urban area seeing more patients and performing more operations than his peer in a rural area. It cannot be assumed however that the urban surgeon is more efficient than his rural counterpart as he has greater ease of travel and serves a higher population density (ibid). Therefore, one is not comparing like with like. The relative cost efficiencies issue of delivering services to rural areas is very relevant to this study. Coombs and Jenkins also examine the issue of unit cost comparisons in “Public Sector Financial Management” (2002). While unit costs are a good way of measuring the efficiency of the same organisation over a period of time, they have several limitations. One of those issues is, yet again, comparing like with like. Coombs and Jenkins use the very relevant issue of the comparative cost of delivering services to urban and rural areas (2002, p.36.). Another shortcoming of unit cost comparisons is that they measure efficiency rather than effectiveness (p.34). As will be seen in Chapter 4, that point is very relevant to this Review. The Disinfection/Sterilisation water quality upgrading solution is clearly the most cost efficient on a capital cost per house basis but its effectiveness and sustainability is in question. 65 As already discussed in the literature review, in reviewing previous studies on public water services infrastructure, similar methodological problems are raised in relation to assessing the performance of public water treatment projects. The 2005 Fitzpatrick Associates’ Evaluation of Water Services Investment under the NDP 2000-’06 explained that due to the bespoke nature of many water treatment schemes (p.5-6. & p.121.) serving widely varying population densities, it is not possible to set precise benchmarks in terms of cost efficiency. “What may be good value in one place may be bad value in another: depending on circumstances” (ibid, p.131.). This problem is even more exacerbated under the Rural Water Programme due to the geographical dispersion of populations being served and the cost of distributing piped water of adequate quality to these often outlying areas by comparison with urban centres. Also, the use of five different water quality upgrading solutions means that it will be difficult to reliably compare the cost of different solutions e.g. comparing the cost of connecting a Group Scheme to an existing public water supply to the cost of building a treatment plant for the Group Scheme. A 2002 Expenditure Review of Exchequer financed Water Services Schemes used multicriteria analysis to assess the overall effectiveness of the programme based on the precedent of the Mid Term Evaluation of the Operational Programme for Environmental Services 19941999. However, this approach gave very little information in relation to the cost efficiency with which the Programme under review was implemented. Also, Multi-Criteria analysis can be quite subjective in weighting the relative importance of different criterion (Regulatory Impact Assessment Guidelines 2005, p.116.). Given the difficulties in making reliable ex-post unit cost comparisons and the vagaries of multi-criteria analysis, the verification of pre-project appraisal comes to the fore in trying to review value for money decision-making. Basically, did the local authority consider all options at the start in determining which water quality upgrade solution to adopt. The Department of Finance’s “Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector” advises that all options for achieving project objectives should be identified, considered and costed (February 2005, p.33.). The Guidelines specifically emphasise the importance of objectivity as “there is a danger that the selection of options may be manipulated in order to make a case for a course of action which is already 66 favoured” (ibid). This is a very relevant point when carrying out a Review of the Rural Water Programme where more than one water quality upgrade option was available. For example, there is anecdotal evidence backed up by local authority questionnaire responses that some Group Schemes favour the construction of standalone DBO treatment plants over connection to the public mains, due to local authority water charges for non-domestic users. It is important, therefore, that the Value for Money Review verifies that different options were costed and that the most economically advantageous option was selected as specified in the National Rural Water Monitoring Committee’s guidance documentation to local authorities (June 1999, p.2.14 ) (May 2002, p.4.7). This was the motivation behind Questions 1 and 2 in the attached Questionnaire to local authorities (Appendix 4) In many cases, however, the remoteness of a Group scheme from the public mains may mean that the construction of a DBO water treatment plant was the only technical solution available to upgrade the water quality of the Group Scheme. The issue of procurement then comes to the fore in ensuring that the contract that goes to tender has been designed so that the most competitive market bids will be attracted. As already discussed in the literature review, Fitzpatrick Associates have argued that the market competition offered by DBO contracts, rather than traditional procurement, provides a better chance that the most cost effective solution for a location will be secured (2005, p.146.). An analysis of the viability of rationalising the number of DBO water treatment plants needed through connecting two or more Schemes to the same plant may also achieve greater cost savings. Questions 3 and 4 were put to local authorities to measure the usage of procurement strategies to achieve efficiency savings, particularly where the alternative option of connection to the public mains was not available. A significant proportion of investment to date under the current Rural Water Action Plan has gone on the construction of DBO water treatment plants. While it will be difficult to make reliable comparisons of the relative costs of the pipe networks connecting the treatment plants to households, it should be possible to roughly compare the cost of the treatment plants on a cost per house basis. Another measurement issue to be careful of is that significantly larger treatment plants will have economies of scale relative to smaller plants although generally 67 Group Scheme plants are smaller relative to those constructed for public water supply schemes because of their smaller population catchment. In any case, it is vital that even with the comparative problems stated above, that the full cost of bringing individual Group Schemes into compliance with the Drinking Water Directive under the different upgrade solutions are compared from the perspective of transparency and accountability to the taxpayer. Therefore, the upgrade cost per household in Group Schemes will be used as a basis for making rough cost comparisons between solutions, subject to the substantial qualifications already outlined above. Operation and Maintenance Unit Cost Issues Unit cost approaches are also used in calculating the operation and maintenance (O&M) costs of supplying a certain quantity of water to the public or private group schemes sector. There is, however, no standard method in Ireland for calculating the unit cost of supplying treated water. Local authorities use different methodological approaches for calculating their O&M costs based on allocating various overheads incurred by the councils in managing the production and distribution of treated water to households. North Tipperary County Council have developed a standard template for calculating local authority water costs and charges, which has been made available to other Councils on the Water Services National Training Group’s website (www.wsntg.ie). This template is for guidance purposes only and allows for Councils to add or subtract overheads to the template to fit with their own cost absorption policies. Coombs and Jenkins also highlight the issue of different overhead apportionment systems in UK local authorities, which makes reliable inter-authority cost comparisons extremely difficult (2002, p.37.). The current position is that capital works for constructing public water schemes are funded by direct capital grants from central government. The O&M costs for the supply of non-domestic water supplies is fully recouped from the commercial sector. The O&M costs of supplying public water to the domestic sector is recouped by local authorities from central government, through the Local Government Fund (LGF). The recoupment of domestic water O&M costs is not ring fenced within the Local Government Fund so it’s not clear to local authorities which element of their LGF receipts are water and non-water. The public schemes sector lies 68 outside the terms of reference of this study but it is instructive to note the non-existence of a standard water unit cost for either capital works or O&M costs at local authority level. This makes it particularly difficult to compare the O&M costs of different local authorities and also to make comparisons with Group Schemes O&M costs. This was an important issue in trying to compare the O&M cost of supplying treated water to a Group Scheme from a public water supply to the O&M costs of running a Group Scheme water treatment plant, in Chapter 4. It was not possible to include the Disinfection/Sterilisation and non-DBO solutions in this comparative O&M exercise as their water treatment infrastructure is maintained voluntarily so no O&M cost data is available. The Department may wish to look at the issue of standardising the calculation of local authorities’ O&M costs for public water services, for comparative purposes, in a future study. 69 Chapter 4 Analysis and Findings 70 Table of Contents Overview p.72. DBO Solution p.86. Non-DBO Solution p.108. Public Water Supply Solutions p.113. Disinfection/Sterilisation Solution p.129. Comparison of solution costs p.141. Network Upgrades and Leakage Control p.143. Rural Water Subsidy p.152. New Group Schemes p.159. 71 Overview Introduction In this chapter, the terms of reference of the Review will analysed using the methodological approach set out in the previous chapter. As there are five different water quality upgrade solutions being implemented under the current Action Plan, the outputs/programme activity, effectiveness and efficiency elements of the terms of reference will be addressed individually for each treatment solution. There will also be some comparisons made between the implementation, effectiveness and efficiency of the water quality upgrade solutions as well as comparisons with the public schemes sector. The new group water schemes and pipe network upgrade measures will also be considered as well as the annual operational subsidy for domestic water consumers on group schemes. Terms of Reference No. 1 Identify programme objectives The primary objective of the Rural Water Programme during the period of the Action Plan for Rural Drinking Water Quality 2003-2006 is to bring “the quality of rural water supplies into compliance with the Drinking Water Regulations 2000, and to achieve this within the shortest possible timeframe” (Foreword). Departmental Circular letter L11/2004 to County Councils states that “The Action Plan for Rural Drinking Water Quality 2003 –2006, published by the National Rural Water Monitoring Committee, sets out a national strategy for bringing privately sourced group water schemes into compliance with the Drinking Water Regulations”. The Regulations apply to all Group Water Schemes “currently providing more than 10m3 [of water] per day or supplying a commercial or public activity” (Department of the Environment, Heritage and Local Government 2006, p.6.). In practical terms, the 10m3 of water per day threshold applies approximately to all Group Schemes serving greater than 15 houses or 50 persons. There are a number of capital measures under the current Rural Water Programme, which have no relationship to the Drinking Water Regulations. These are the New Schemes measures as well as elements of expenditure under the Network Upgrade, Connections to the Public Mains and Takeover measures. However, a longstanding objective of the Rural Water Programme is to provide “a sufficient quantity of piped water in as many houses as feasible” 72 that is “of a suitable quality for drinking water” (Department of Finance 1989, p. 2.). The 2000-’06 National Development Plan (NDP) allocated €373.3m to the Rural Water Measure in the Border Midlands West (BMW) region. It stated that “better quality water is required, not alone for public health and quality of life reasons, but also to strengthen the infrastructure base of the areas concerned”. The NDP allocation for the Southern and Eastern (S&E) Region was €160m. This funding is for “upgrading quality-deficient group water schemes and installing new group schemes”. Terms of Reference No. 2 Examine the current validity of those objectives and their compatibility with the overall strategy of the Department of the Environment, Heritage and Local Government. Current validity of objectives The best starting place for considering the current validity of the Rural Water Programme objectives is the most recent EPA Drinking Water Quality Report published in January 2007. The report states that quality of group water schemes has historically been inferior to that of the public water supplies. It also states that the quality of water supplied by private group water schemes was of an inferior status in 2005 (2007,p.42.). The section concludes that “if the situation is allowed to continue as is at present, it is unlikely that compliance with the drinking water Regulations is going to be achieved in the group water scheme[sic] for many years” (ibid, p.43). As can be seen from Table 4.02 on p.77. , implementation of the water quality upgrade programme was only partially complete by June 2006 so further funding will be required post 2006 to complete the programme. The Minister for the Environment, Heritage and Local Government confirmed this when allocating €142 million under the 2007 Rural Water Programme. The Minister said that “the main emphasis in 2007 would be on measures to eliminate water quality deficiencies in group water schemes with private sources. Many of these schemes have been identified by the Environmental Protection Agency as failing to meet mandatory drinking water standards” (Departmental Press Release, 1st March 2007). Compatibility with Departmental Strategy 73 The current Strategy Statement of the Department of the Environment, Heritage and Local Government makes several references to the issue of drinking water quality. It states that “Significant progress has been made in meeting EU and National requirements in relation to water quality and urban wastewater discharges and in strengthening our economic infrastructure to facilitate industrial and residential development. There will be a continuing need over the period 2005 – 2007 to maintain the momentum that has been built up….Licensing will be introduced for the group water scheme sector to address ongoing quality problems in the sector.” (p.28) One of the Key Performance Indicators stated in the Strategy Statement is “The delivery of high quality water supply and wastewater services to the public and industry in accordance with objectives underpinning the Water Services Investment Programme, including meeting the needs of social economic development, compliance with EU and National requirements in relation to urban wastewater discharges, drinking water quality and sludge management (p.30. KPI)” The Strategy Statements also states “In relation to rural water supplies, which rely heavily on voluntary group schemes, the Department has promoted a partnership approach involving the local authorities, the National Federation of Group Water Schemes and the National Rural Water Monitoring Committee in order to secure necessary improvements in standards” (p.41.) It is clear, therefore, that the current water quality objectives of the Rural Water Programme are compatible with the current overall strategy of the Department of the Environment, Heritage and Local Government. 74 Terms of Reference No. 3, 4 & 5 Define the outputs associated with the programme activity and identify the level and trend of those outputs Examine the extent that the programme’s objectives have been achieved, and comment on the effectiveness with which they have been achieved. Identify the level and trend of costs associated with the Action Plan for Rural Drinking Water Quality 2003-’06 and thus comment on the efficiency with which it has achieved its objectives. Introduction These above three terms of reference will be addressed together by examining the implementation, cost efficiency and effectiveness of each of the capital spending measures in Table 4.01 below. Firstly though, an overview will be taken of progress to date based mainly on data collected from each local authority participating in the Rural Water Programme. Much of this data is drawn from a Questionnaire completed by all Councils responsible for the implementation of the Rural Water Programme (see Appendix 4). This will be followed by a detailed examination of each water quality upgrade solution, including an analysis of a number of case studies. Finally, a comparison will be made of the respective efficiency and effectiveness of the different water quality upgrade solutions. The new group water schemes and pipe network upgrade measures will also be considered as well as the annual operational subsidy for domestic water consumers on group schemes. Overview of programme inputs As can be seen from Table 4.01 below, there has been a considerable degree of capital expenditure under the Rural Water Programme between 2003 and 2006. The DBO and DBO advance works measures have been the greatest recipients of funding by far. It is also particularly noticeable that the second greatest capital expenditure area is not a water quality upgrade solution at all but pipe network upgrades. This expenditure area will be examined in detail later on in this chapter. It should be pointed out, however, that the network upgrades 75 measure also funds the disinfection/sterilisation, non-DBO water quality upgrade solutions and the new Group Schemes measures as well. Table 4.01 Annual Expenditure on Capital measures under the Rural Water Programme Expenditure on Capital Measures (€ million) Design Build Operate (DBO) DBO Advance Work LA Takeover 2003 2004 2005 8.723 21.194 33.812 31.568 95.297 - 16.874 18.464 35.338 - 2006 Total 9.467 8.91 10.884 16.924 46.185 Upgrade of GWS networks 30.352 20.323 25.738 28.996 105.409 Connect to the Public Main - 5.367 6.751 3.895 16.013 55.794 94.059 99.847 298.242 Total 48.542 Source: Department of the Environment, Heritage and Local Government Overview of programme outputs When the trend of annual expenditure is compared against programme outputs at June 2006 in Table 4.02 below, it is noticeable that the DBO expenditure reflects a considerable degree of activity under this measure in terms of schemes completed and underway. It is also the most common water quality upgrade solution for 35% of the Group Schemes. It is also noticeable that there has been a lower level of implementation for the two upgrade solutions involving connection to the public mains with only 5% of schemes complete in both cases. This implementation issue will be discussed in detail later on in the chapter. Implementation under the disinfection/sterilisation solution is very high at 75%. However, this is because the treatment facilities were often in place prior to the 2003-’06 period and only received minor upgrades. There are specific issues relating to the effectiveness of this water quality upgrade solution, which will be discussed later on in the chapter. Finally, it is very noticeable that there is a mismatch between the expenditure inputs and capital outputs in terms of the data available. This is because, as already mentioned, the nonDBO, disinfection/sterilisation solutions and new Group Schemes are funded from the network upgrade measure. Also, Councils are not required to provide overall statistics to the 76 Department on new Group Schemes and completed pipe network upgrades. This is because the Rural Water Programme is a devolved local authority function. The output data in table 4.02 below was compiled to update the European Commission on progress in meeting the terms of the Drinking Water Directive. Local authorities were asked to provide output data for new schemes and pipe network upgrades during the 2003-’06 period in their questionnaire returns and this will be discussed later on in this chapter. The need for a greater match between programme inputs and outputs will be considered in the chapter on performance indicators. Table 4.02 Implementation Status of Group Water Schemes by upgrade solution category Treatment Solutions DBO Non-DBO Connect to Public Main Council Takeover Disinfection/Sterilisation Public Source Total No. of Schemes % implementation % Solution In Work in Upgrades Total % Upgrades breakdown Planning Progress Complete Schemes complete 35% 3% 16% 9% 17% 20% 100% 19 7 85 35 19 21 209 9 27 27 11 15 30 5 6 3 92 109 258 21 118 65 122 145 186 26% 298 41% 245 34% 729 12% 24% 5% 5% 75% 75% Ref. Figures derived from June 2006 Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive Overview of Programme Implementation Local authorities were asked in the Questionnaire to provide estimates of the number of Group Schemes currently participating and not participating in the Rural Water Programme (see table 4.03 below). Councils estimated that 620 Group Schemes (77,669 houses) were participating while 59 Schemes (4,666 houses) were not. It should be noted that this totals 679 Group Schemes in all. This differs slightly with the 729 Schemes total in Table 4.02 above but can be explained by changes such as Group Scheme mergers etc. in the intervening period. 36 of the non-participating schemes were receiving their annual domestic operating subsidy while 23 schemes were not. In many cases, these 23 Group Schemes did not even 77 claim their subsidy. These figures below would suggest that the level of engagement with the Rural Water Programme is quite good with slightly less than 10% non-participation. It must be remembered, however, that these 10% represent the hard core of non-participants, who want nothing to do with the water quality upgrade programme. There are in addition a number of Group Schemes, who are co-operating with the Programme, but have not moved forward with the implementation of their water quality upgrade solution. It is more difficult to estimate how many Schemes fall into this category but the relatively large number of Group Schemes still categorised as in planning in Table 4.02, particularly for the ‘Connection to the Public Mains’ and ‘Takeover’ categories do provide a good indicator. Table 4.03 Local Authority Estimate of Group Water Schemes’ participation in Rural Water Programme Schemes Participating Schemes Not Participating No. of No. of Schemes Receiving Schemes Schemes Subsidy Schemes Not Receiving Subsidy 620 59 36 23 No. of Houses No. of Houses Houses Receiving Subsidy Houses Not Receiving Subsidy 77,669 4,666 3,735 931 Source: Qs. 9-10. of Local Authority Questionnaire Returns 2007 Obstacles to implementation This invariably leads to the question of what is holding up implementation. Local authorities offered a number of explanations in their responses to Q5 on the Questionnaire. Non-domestic consumers on Group Schemes unwilling to be connected to the public mains or be taken over as they would have to pay local authority water charges Poor enforcement powers available to local authorities Difficulties in acquiring lands and way leaves particularly where land owner is opposing water quality upgrade solution Reluctance of Group to accept most suitable treatment solution Difficulty of getting 100% of members to sign application required for Council takeover Insufficient public water services available to connect to Economic viability of smaller Group Water Schemes if treatment added to operational costs 78 Fear of chlorination in the water by Group members Groups reluctant to sign 20 year DBO Operational &Maintenance contracts Lack of ongoing commitment of Group Schemes to maintenance Group Schemes do not perceive that there is a water quality problem Concerns re. future volunteerism on Group Schemes Lack of State grants for universal metering of all Group Schemes, apart from DBOs. Very independent Group Water Scheme Committees Need to raise 15% capital contribution for Connection to the Public Mains (CTPM) Councils were also asked in Q6 of the questionnaire to outline additional measures, if any, which could improve implementation of the water quality upgrades under the Rural Water Programme. Councils proposed a number of additional measures outlined below. Greater enforcement powers to be made available to local authorities in Water Services Bill Streamline land acquisition mechanisms to expedite scheme takeovers Additional network upgrading funding Extension of regional water supplies suggested by Clare County Council None -has to be by consensus as you can’t push Group Schemes – Cork South CC Link subsidy to water quality compliance Increase grant aid to encourage take up of grants Source Protection Schemes are required to secure the State’s investment An accreditation or award scheme for GWS may encourage awareness of quality issues It would appear that the two main issues holding up implementation of the Rural Water Programme are the lack of appreciation that there is a water quality problem on some schemes and an unwillingness by non-domestic water consumers to be connected to the public mains or taken over, where this is the preferable upgrade solution. The latter issue will be discussed in detail later on in this chapter in the public source solution section. Councils were empowered to take prosecutions against non-compliant Group Schemes under the 2000 Drinking Water Regulations, however the 2007 EPA Drinking Water Report found no evidence of any such prosecutions taken in 2005. One member of a Group Scheme can currently veto a Scheme’s takeover by its local authority as this requires 100% membership agreement. The delays in the enactment of the Water Services Bill meant that the power to allow Councils to take over Group Schemes with the two thirds agreement of its members had been delayed. 79 It should be noted, however, that there are existing provisions under Sections 6 and 8 of the Local Government (Sanitary Services) Act 1962 and Section 79 of the Public Health (Ireland) Act 1878, which empower local authorities to take remedial action in relation to poor quality water supplies (Department of Finance 1989, p.54.). These legal provisions are in force until commencement of relevant sections of the Water Services Act supercedes them. On 13th March 2007, the Minister for the Environment, Heritage and Local Government approved revised Drinking Water Regulations (S.I. No. 106 of 2007), which gives Councils additional powers to carry out remedial water quality upgrade works on Group Schemes, without members’ consent if necessary (Section 12[2]). Effectiveness of Rural Water Programme Local authorities were asked in Q12 of their questionnaire returns to provide details of any completed Group schemes that are still non-compliant with the Drinking Water Directive after upgrading (see Table 4.04 below). Seven Councils reported that 16 Group Schemes overall were non-compliant after upgrading. 16 schemes non-compliant out of 245 complete (as per Table 4.01) i.e. less than 7% does not appear to be too high. However, the evidence of case studies later on in this chapter would suggest that Councils under reported the rate of noncompliance post upgrading in their Questionnaire returns. As already explained in Chapter 3 (Review Methodology), these case studies include a sample of upgraded Group Schemes for all solutions with EPA and local authority water quality test results being used to verify compliance. Table 4.04 – Non-Compliant Schemes after upgrading No. of No. of County Council Schemes Houses Reasons for water quality test failure/Risk Factors 80 Cork North Cork South Galway Kilkenny Offaly Sligo Wexford 1 1 11 No figures provided No figures provided 32 Unknown 62 Inadequate pipe network maintenance 1,641 Inadequate plant monitoring and pipe network maintenance No figures Inadequate O&M of plant chlorinator. Problem with nitrates provided and septic tanks contaminating borehole sources No figures provided Nitrates 2 1 a major risk factor Inadequate scouring of pipelines 3 Includes pub connection. Lack of O&M of Group Scheme 16 1,750 Total Source: Q12 - Compliance status after completion of water quality upgrade The Councils do not specify the upgrading solutions used in the cases of the non-compliant schemes above. However, inadequate treatment maintenance, pipe network maintenance and source protection appear to be common themes. All of these issues will be considered further in the course of this study. Non-compliance, due to inadequate treatment maintenance by Group Schemes, would indicate the use of the Disinfection/Sterilisation and Non-DBO solutions as these are the only solutions, where Group scheme volunteers retain responsibility for the operation of the water treatment infrastructure. There will be a particular focus on the effectiveness of these water upgrade solutions later on in this chapter. All Councils confirmed in Q11 of their questionnaire returns that they carry out water quality testing on Group Water Schemes in compliance with their statutory requirements under the Drinking Water Regulations. One Council did admit to reducing testing to twice per year due to lack of resources. The 2007 EPA Drinking Water Report stated that the level of water quality monitoring was inadequate in several Councils. The Minister for the Environment, Heritage and Local Government has given the EPA greater powers, under the 2007 Drinking Water Regulations, to take enforcement action against Councils, which do not comply with their statutory water quality monitoring duties. The effectiveness of all water quality upgrading solutions will be assessed later on in this chapter using 2005 EPA water quality data and local authority information for a selection of Group Schemes upgraded since 2003. Efficiency of the Rural Water Programme All Councils were asked to confirm in the Questionnaire whether they had adopted the most economically advantageous available water quality upgrade solution for Group schemes in 81 their administrative area (Q.1). They were also asked to confirm that they had considered and costed all alternative options and most specifically standalone DBO plants versus connecting Group Schemes to the public mains (Q.2). Table 4.05 - Councils’ responses to cost efficiency issues in Questionnaire Carlow Cavan Clare Cork North Cork South Cork West Donegal Galway Kerry Kildare Kilkenny Laois Leitrim Limerick Longford Louth Mayo Meath Monaghan Nth Tipp Offaly Roscommon Sligo South Tipp Waterford Westmeath Wexford Wicklow Q1 Q2 Q3 Q4 Cheapest option selected Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Costed all options Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No Yes Yes No Yes Yes Yes No Yes No Yes Yes No Yes No No Yes Yes Competitive DBO SubTenders bundling used considered Yes Yes Yes No Yes No Yes N/A Yes N/A Yes N/A Yes N/A Yes Yes Yes N/A Yes Yes Yes N/A Yes Yes Yes Yes Yes No Yes N/A Yes N/A Yes Yes Yes No Yes Yes Yes N/A Yes N/A Yes Yes Yes No Yes N/A Yes N/A Yes N/A Yes Yes Yes Yes Sources: Responses to Local Authority Questionnaire- December 2006 Councils were requested to confirm that competitive tendering had been used to procure contractors to carry out the water quality upgrade works required (Q3). If a DBO treatment plant was the chosen water quality upgrade solution, Councils were asked whether the sub- 82 bundling of DBO contracts, so that one treatment plant could serve two or more Group Water Schemes, was considered (Q4). Councils responses to these four questions are set out in Table 4.05 above. All Councils, with the exception of Meath, responded that they had implemented the most cost efficient solution for their Group Schemes (Q1). Meath County Council stated that one of their Group Schemes refused to be connected to the public water supply and insisted on using their own private source. Most Councils confirmed that they had carried out a comparison of the relative cost of building a DBO treatment plant to connecting their Group Schemes to the public mains (Q2). Councils were asked to provide documentary supporting this but few Councils provided this information within the timeframe of this Review. It will be recommended in the DBO section that this information be provided as part of the final accounts for the DBO treatment plant projects, in the interests of transparency. In cases where no cost comparison was carried out, Councils explained that this was because; Group Schemes were too far from the public mains for connection to be technically or economically feasible There was insufficient water supply capacity at the nearest public water treatment plant Group Schemes were unwilling to be connected to the public mains Building additional treatment capacity at the nearest public treatment plant does not appear to have been considered as an option. All Group Schemes confirmed that competitive tendering was used to procure contractors to carry out the water quality upgrade works (Q3). Councils were also asked about measures taken to ensure that treatment plant design capacities were economical with limited allowance for unaccounted for water (Q14-16). In nearly all cases, Councils responded that they had designed treatment plants in compliance with the Department’s guidelines that “water treatment plant capacity should be capped at current demand levels, plus an allowance in respect of projected growth demand over a 20 years horizon, plus an allowance of 25% for unaccounted for water (Departmental Circular L11/2004). 83 There was a mixed response to the question of whether the sub-bundling of two or more Group Schemes for connection to the same treatment plant was considered (Q4). It was considered on the newer DBO bundles e.g. Galway and Mayo DBO Bundles No. 2 as well as the inter-county South Leinster DBO. The reasons why sub-bundling was not adopted in some counties were; Some Group Schemes had already merged prior to DBO contracts being developed and were served by one DBO treatment plant e.g. Erne Valley DBO in South West Cavan DBO. Not economically feasible due to geographical distance between Group Schemes No water source with adequate capacity to serve larger sub-bundled DBO treament plant Criteria for upgrade solution selection There appears to be a slight element of ambiguity in relation to the basis for determining which water quality upgrade solution should be adopted. The Rural Water Strategic Plan Guidance document advises Councils to carry out an analysis of various solutions in order to identify the ‘most economically advantageous’ approach. Departmental Circular (L4/98), which established most of the structures of the existing Rural Water Programme, emphasises the importance of a partnership approach between local authorities and the Group Schemes’ sector in the determination and implementation of rural water policy. It is not 100% clear, who ultimately decides what the upgrade solution route should be, the local authority or the Group Water Scheme. The National Federation of Group Water Schemes (NFGWS) were asked for their understanding of this. They responded that in cases where the cost difference between different solution options is ‘marginal’, it should be a matter for the Group Water Schemes themselves to decide. The Federation also commented that agreeing treatment solutions by consensus rather than imposing solutions on Group Schemes is the preferable route. This interpretation concurs with the understanding of Departmental technical staff on the issue. This appears to be a pragmatic and sensible approach to take when dealing with the privately owned and voluntarily run Group Schemes sector, where the cost difference is marginal. However, it is clear that in certain cases, Group Schemes are unwilling to be connected to the 84 public mains because of non-domestic water charges and are seeking instead to have an often more expensive DBO treatment plant built. There are indications that some local authorities may have agreed to this in a small number of cases. Other Councils are not permitting this on cost grounds with the result that some Group Schemes are resisting connection to the public main or local authority takeover. It is impossible to form a definitive view without documentary verification from Councils that an analysis of the various cost options was carried out in each case. In many cases, however, Group Schemes were too geographically distant from public mains for connection to be a practical option or the raw water chemistry was not of sufficiently high standard for disinfection/sterilisation to be an option. Therefore, there was no option but to build a DBO water treatment plant either as a standalone or serving several adjacent Group Schemes, where technically possible. It is important, however, that the Department reminds Councils that while a partnership approach with the Group Schemes’ sector is vital for programme implementation, the ‘most economically advantageous’ treatment approach must ultimately be adopted in the interests of the taxpayer. Conclusions Many of these issues will be considered in far more detail in the following section of the chapter, which considers the implementation, efficiency and effectiveness of each of the water quality upgrade solutions separately. Some comparisons between water quality upgrade solutions are also done at the end of the chapter. Expenditure on non-water quality related upgrade measures such as pipe network upgrades, new schemes and the annual operational domestic subsidy will also be reviewed separately. 85 Design Build Operate (DBO) Water Quality Upgrade Solution Introduction This is the water quality upgrade that has been identified for 258 of the 729 schemes (35%). It also constitutes the single largest investment of all the other water treatment upgrade solutions put together with an investment of €130 million over the 2003-’06 period, with €95m on DBO works and €35m on Advance DBO works. This constitutes 44% of all capital expenditure on the Group Schemes sector during 2003-’06 and 68% of all capital expenditure on water quality upgrade solutions only i.e. excluding new Group Schemes and pipe network upgrade expenditure. The Design Build Operate (DBO) Bundle approach is quite complex so it is appropriate to explain its operation in some detail before the specific issues of efficiency and effectiveness are addressed. Development of DBOs Under traditional procurement, the design, build and operation of a water treatment plant is a separate three stage process. A project consultant is engaged who plans and designs the treatment plant. The plant specification is then put out to tender and a contractor is engaged to build the plant. Once the treatment plant has been completed and commissioned, the contractor transfers responsibility for the treatment plant to an operator, traditionally local authority technical staff. This traditional three stage approach was regarded as having several shortcomings. Firstly, in designing the treatment plant, the project consultant has little incentive to produce the most cost efficient construction design. By combining the design and build of the plant into one contract, contractors are incentivised to produce the most cost efficient plant design if they are to win the contract. There were a small number of pilot Design Build (DB) projects constructed prior to the 2003-’06 period under review. However, problems were encountered with their operation and maintenance after they were commissioned (NRWMC 2005, p.4.). Basically, while contractors were building plants that met the necessary specifications they were not efficient and effective from an operation and maintenance perspective. The concept of DBO was then developed firstly on the public schemes side and then in the Group Schemes’ sector. Successful contractors would not just design and operate the 86 treatment plants but would also operate and maintain the plants over a 20 year time period. 20 years is regarded as the most appropriate O&M period as it coincides with the expected life cycle of the treatment plant and it allows the DBO operator to recover their costs, which are usually significantly frontloaded at the start of the project. This was regarded as the most cost efficient and effective approach as the contractor in bidding knew that they would have to design and construct a plant that could be run in a cost efficient manner over its design life cycle. It also had the benefit of providing transparency in relation to the full life cost of operating the treatment plant allowing tenders to be assessed on a net present value basis (NPV) using a 5% discount rate in accordance with Department of Finance guidelines (2005). DBOs contracts also transfer a considerable amount of financial risk to the contractor. Under traditional procurement, unforeseen costs such drilling through rock etc. was generally borne by the client through price variation clauses in the contract. Under DBO contracts, there is very little scope for the contractor to claim for extra costs so invariably a greater degree of risk is carried. It must be emphasised that the use of DBOs should not be interpreted as a policy preference in favour of the public private partnership (PPP) approach. The Department does not regard Group Scheme DBO plants as being PPP projects and as such the public sector benchmark was not applied. DBOs are regarded as the most appropriate procurement approach for Group Schemes given that the newly constructed water treatment plants are transferred to private Group Scheme rather than local authority ownership post construction. Council personnel have no role in the operation of these plants so it is necessary to have a professional operator in place as Group Scheme volunteers would not be qualified to carry out this role. Also, although the State provides most of the capital funding for the design and build of these plants, the operation and maintenance costs have to be paid by the Group Scheme members apart from the annual subsidy payment for the domestic operation and maintenance cost element. 87 Cost Breakdown of a DBO for a water treatment plant The various capital and operational and maintenance cost elements of DBO treatment plants are set out below. Much of this detail has been extracted from the Department’s “Guidance Document for the Procurement of Small Water Services, Part C” (2002, p.70-72): Capital Costs The capital costs are broken down into (i) civil engineering and building – the building housing the treatment plant along with rising mains and reservoirs. (ii) Mechanical and Electrical – the actual infrastructure used to treat the water Operation and Maintenance Costs 1. Fixed Time based charges for the operation of the works(€/month). This includes the cost of appropriate labour, routine prevention maintenance, sampling and testing, insurance, updating management and quality plans, reporting procedures, supervision, management etc. 2. Fixed time based charges for the maintenance of the works (€/month). This includes scheduled maintenance and refurbishment of plant and buildings including replacement of parts having an expected useful life of not more than five years. 3. A volumetric charge payable to the contractor based on the production of the treated water incl. chemicals and energy costs directly related to the volume of water treated (€ / m3 ) Capital Replacement Fund The Group Scheme trustees, who are formally referred to as the employer in the DBO contract with the DBO operator, must pay funds into a bank account for the replacement of items of plant with a design life of more than 5 years. These could include “items such as bearings, drive belts on pumps and electrical motors as well as control and automation equipment” (ibid, p.8.). These costs are an integral part of the O&M portion of the contract. There should be a standard monthly charge to accumulate the required funds in a bank 88 account at the end of each of the five year periods comprising the total 20 year O&M period. There are separate charges for each of the five year periods with charges for individual years for the last 5 years to facilitate flexibility during handover. Discounting and Net Present value The fixed time and volumetric charges are discounted over the contract lifetime using a 5% discount rate as per the Department of Finance. While the volumetric charge will vary over the lifetime of the contract, the estimated current consumption is used for the purposes of tender evaluation. It is expected that future increases in consumption demand, due to new developments, will be offset by water conservation measures and reduced consumption by non-domestic users. There will also be an index linked fluctuation clause to allow for inflation. The estimated breakdown between fixed and volumetric costs, over the lifetime of the DBO project, is set out in Table 4.1.1 below. Table 4.1.1 -Indicative breakdown of O&M costs for water treatment Category Elements % of Total Costs Fixed – time based (incl. Labour, transport, head-office overheads, CRF) management Variable – Volumetric Cost per m3 of water includes chemicals, 60%-85% 15%-40% pumping and other electrical costs Source: Procurement Guidance Document 2002 p.8. DBO Grant structure The Department grant aids the capital cost of DBO treatment plants up to a maximum of €6,476 per house in the Group Scheme being served by the plant. This includes 100% of the cost of mechanical and electrical contract i.e. the treatment infrastructure itself. The Department funds 85% of the civil works contract with a 15% contribution from the Group Scheme members. The civil works contract would generally include elements such as the building containing the treatment infrastructure, reservoirs, rising mains and the access road to the plant. Any interconnector pipes to connect more than one scheme to the same treatment plant is funded at 100%. In addition, any pipe network upgrades to reduce Unaccounted for 89 Water (UFW) and avoid pipe recontamination is funded by a second 85% capital grant also up to a maximum of €6,476 per house. This second grant can be claimed from the network upgrade capital measure. Finally, Group Schemes can recoup an annual subsidy from the Department for the domestic household element of their operation and maintenance costs up to a maximum of €196.81 per house per year. This DBO subsidy limit is almost twice that of the normal subsidy limit of €101.58 in recognition of the additional costs for domestic households involved in funding the professional operation and maintenance of DBO treatment plants. The overall grant cap of €6,476 per house and 15% contribution from Group Schemes for civil works is an important cost control safeguard as it removes the incentive for Group Schemes to ‘gold plate’ their treatment plants with unnecessary expenditure as they will have to contribute towards the costs. The capital grant limits also reduces the incentive for DBO operators and Group Schemes to over engineer the treatment plants at the State’s expense so that subsequent operation and maintenance costs can be minimised. Similarly, the 85% grant limit on pipe network upgrades reduces the incentive for Group Schemes to have unnecessary pipe network replacement. Evolution of DBO bundles Although the above grant limits are relatively generous by comparison to the new Scottish grant system discussed in the Literature Review [€1,178 per house], they do create cost pressures in viably financing water treatment plants serving relatively small populations. As can be seen from the Fitzpatrick Report, bigger projects tend to generate economies of scale thus reducing costs (2005,p.44.). It would have proved prohibitively expensive to individually procure a DBO plant for each Group Scheme within existing grant limits and indeed it would have been impossible in many cases. The Department was aware that the small size of the Irish market meant that there were a limited number of construction firms available to carry out this kind of work. It was also known that advances had been made in small treatment plant technologies in other countries, which were not available in the Irish marketplace. Therefore, it was decided to procure a number of DBO treatment plants as a single package known as a DBO bundle. In this way, international consortia would be attracted to bid for these projects on the basis that they would gain a large volume of work if successful. A larger number of 90 bundled schemes should create economies of scale and reduce unit cost. For this reason, the DBO bundle is considered to be a cost effective solution. In the Department’s procurement guidance, it is advised, to achieve critical mass, that there should be a sufficient number of schemes in a DBO bundle so that the services of two or more operations staff are required on a full-time basis. This removes an element of redundancy, which could unnecessarily inflate the service providers’ costs. On the other hand, because of the time constraints in terms of getting plants into operation due to water quality problems, an upper limit of 20 bundled schemes was suggested. This could be increased where the nature of the scheme would allow the contractor to complete the work within a reasonable period (2002, pp.8-9.). Because of the complex nature of these contracts, local authorities would act as employers during the design and construction phase of the project and then withdraw following scheme completion. The participating Group Schemes will then take over as DBO employers and deal directly with the DBO service provider during the operation and maintenance (O&M) phase of the DBO contract (ibid, pp.9-10.). Technical advisors known as Client Representatives were to be engaged (by competitive procurement) to prepare the DBO bundle tender documents and assess the tender bids. They would also oversee the Design/Build of the project on behalf of both the Council and Group Schemes in the DBO bundle. The Client Representative for a DBO bundle would also ensure that planning, land ownership and access arrangements are legally in place before a particular scheme is allowed to enter the DBO bundle. To date, four firms of consulting engineers have been engaged as client representatives and four DBO consortia have been awarded all DBO bundle contracts either underway or complete to date (see Table 4.1.2 below). It should be noted, from above, that DBO Client Representatives and DBO contractors are procured separately so the Client Rep./Contractor combination differs in many DBO bundles. 91 Table 4.1.2 – List of DBO Client Representatives and DBO contractors DBO Client Representatives DBO Contract Consortia Jennings&O’Donovan & Partners (JOD) EarthTech Ireland Ltd. (ETIL) Ryan Hanley (RH) Electrical and Pump Services ( EPS ) T J O’Connor & Associates (TJOC) Treatment Systems Services Ltd. ( TSSL ) P J Tobin Veolia DBO Solution Implementation and overall expenditure As previously stated, implementation under the DBO treatment solution was very advanced in June 2006 with 12% of schemes complete and 81% underway. By April 2007, 11 DBO Bundles in seven counties were completed or nearing completion with treatment plants in place for 101 Group Water Schemes (see Table 4.1.3 below). Work is currently underway on the South Leinster DBO Bundle covering six counties. Mayo No. 2 and Galway No. 2 DBO Bundles have recently gone to tender. Table 4.1.3 - Completed DBO Group Water Scheme Bundles – April 2007 (see also Appendix 7) County Bundle Name Provisional Average DB Clients No. of No. of Total Design Cost per Contractor Rep GWS Houses Build Cost (€) House (€) Cavan Cavan Cavan Clare Monaghan Sligo Sligo Mayo Galway Galway Limerick Cavan West Cavan East Cavan South West Clare Bundle Monaghan Bundle Sligo North West Sligo South East Mayo No. 1 Glynsk/Creggs Galway Bundle 1 Limerick Bundle EPS Veolia EPS EPS Veolia TSSL TSSL Earthtech Veolia TSSL EPS 1,405 3,393 1,815 2,840 3,991 668 1,291 4,125 320 2,953 2,513 €7,101,151 €7,284,812 €4,023,583 €6,417,217 €7,846,228 €1,825,729 €2,616,622 €8,255,073 €977,130 €7,844,505 €4,794,256 101 25,314 €58,986,307 JOD TJOC Tobin JOD TJOC TJOC JOD RH TJOC RH TJOC Totals 9 10 5 4 14 6 5 14 1 15 18 Source: DBO Clients Representatives and Local Authorities 92 €5,054 €2,147 €2,217 €2,260 €1,966 €2,733 €2,027 €2,001 €3,054 €2,656 €1,908 Efficiency of DBO Solution As such a significant level of investment is being made under the DBO upgrade solution, all 11 completed DBO bundles were evaluated. Data was collected from both the local authorities and client representatives overseeing the projects on behalf of the Councils and Group Scheme members. However, it must be stressed that the financial data provided in Table 4.1.3 above is provisional and may be considerably understated. This is because final accounts have not been prepared on any of the completed DBO yet as they were mainly only completed from mid 2006 onwards. There could be additional costs such as advance DBO works, which will need to be incorporated into the final figures. Also, some DBO scheme data is likely to be more comprehensive than the data for other DBO schemes so definitive cost comparisons cannot be made until all figures are finalised. For example, the data provided on the number of houses in the Monaghan DBO is incomplete. Financial data for follow on pipe network upgrades are also not available yet. These figures are necessary to calculate the full cost of bringing the above Group Water Schemes into compliance with the Drinking Water Regulations. The additional figures are also necessary to draw an accurate comparison with the cost of alternative water quality upgrade solutions e.g. Council Takeovers etc. Therefore, all the data in Table 4.1.3 above may be subject to revision after the respective local authorities prepare final accounts. Unit Cost Analysis It would be unwieldy for presentational purposes to provide provisional design build cost data for all 101 completed Group Water Scheme DBO projects in the body of the text. Therefore, the provisional data is summarised on a DBO Bundle basis in Table 4.1.3. Provisional design build (DB) cost data for each completed Group Water Scheme is provided in Appendix 7. An average DB cost per house has been calculated for each bundle by dividing the Total DB cost of all Schemes in the Bundle by the total number of houses in the Bundle. These average DB costs per house are presented in the last column of Table 4.1.3 above. As can be seen, they vary widely from €1,908 per house in Limerick up to €5,054 per house in Cavan West. It would be unwise to draw any conclusions as to why there is such a marked difference in the average DB cost per house for these two bundles in the absence of definitive and complete final accounts figures for both DBO bundles. In the final analysis, it may just prove to be an 93 illustration of the hazards of using the unit cost approach is trying to compare the relative costs of two very different water treatment projects. Other measures of efficiency In an area as complex as the construction of DBO Treatment Plants, there are several areas where efficiency has to be considered. Because of the bespoke nature of treatment plants serving widely varying population patterns, it is difficult to compare capital costs on a unit cost basis. Other efficiency issues must also be considered. Were alternative more cost efficient options to DBO treatment plants explored Was there competitive procurement Was the option of connecting more than one plant to the treatment plant considered Was the most economic plant capacity used Consideration of alternative water quality upgrade options Given the expense of building a water treatment plant, DBO client representatives and local authorities were asked whether this was the only upgrade option considered. Specifically, was the option of connecting these Group Schemes to the public mains (CTPM) considered and costed. In most cases, Client Reps said that the CTPM option was considered. The reasons given for turning down the option were that schemes were too far from the public mains so it was too expensive the pipe network at the extremities of the existing public networks were too small to be connected into Group Schemes there was insufficient existing capacity on public treatment plants It noticeable that consideration was not given to costing the option of increasing treatment plant capacity on existing public plants, where connection was a viable technical and financial option. It is not clear whether such capital funding could come from the Rural Water Programme or the main Public Schemes Investment Programme. This could indicate a need for greater harmonisation between the two investment programmes. Councils were asked to provide documentation verifying that CTPM was considered and costed as the most economically advantageous option as specified in the Rural Water Strategic Plan Guidance 94 documentation. Very few Councils provided this verification within the timeframe of this Review. There is evidence in at least 4 cases that Group Schemes refused the more economic CTPM option and insisted on a treatment plant instead. That said, in most cases it appears that the construction of a water treatment plant was the only viable technical and economic upgrading option. Competitive procurement The DBO clients have confirmed that there was competitive procurement involving several bidders for each of the completed DBO Bundle contracts. This process was carried out in accordance with the stringent procurement arrangements already outlined in this Chapter. Rationalisation of Treatment Plants It has already been established that in most cases, alternative options to constructing a standalone DBO treatment plant were considered prior to the decision to adopt that water quality upgrade solution. The next question is whether, the option of connecting more than one Group Scheme to the same treatment plant was considered. This would involve additional costs in relation to the length of pipework connection but could it, in some cases, be more economic than building a standalone treatment plant for each Group Scheme. The evidence is that this has happened in a few cases but generally not. It has happened in a few cases e.g. in all three of the Cavan bundles, where the grant limit of €6,476 per house in some of the smaller schemes and the potential size of Group members’ 15% contribution meant that a standalone treatment plant was unviable. In some of these cases, neighbouring Group Schemes merged to form a new Group Scheme operating off one treatment plant. An example of this was Garty Lough and Bruskey/Killydoon in the South West Cavan DBO, which merged to form the Erne Valley Group Scheme. That said in most of the DBO bundles, if a stand alone DBO treatment plant could be built within existing grant limits with a relatively affordable group contribution, that is what happened. It should borne in mind though that while there may have been other cases where treatment plants could have been shared to the benefit of the exchequer, the distance between Group Schemes would have made it economically unviable in many other cases. The absence of economic assessments makes this impossible to tell. 95 The concept of rationalisation of plants is now very much on the agenda with two new DBO bundles currently in planning i.e. Galway and Mayo Bundles No. 2. The small size of the Group Schemes i.e. number of houses in these bundles makes a standalone DBO plant for each Group Scheme prohibitively expensive for the Group Scheme members. Before further discussion, it is important to first make a distinction between the concept of a bundle and a sub-bundle. The Group Schemes in a DBO bundle have no physical or legal relationship to one another. Their only linkage is that their treatment works is being procured as part of an overall package of treatment plants to be built by the same contractor and overseen by the same client representative. A sub-bundle, on the other hand, is a number of group schemes e.g. 2 or 3 within an overall bundle, which will be physically connected to the same treatment plant and will be legally required to join together in a new entity for the purposes of dealing with the DBO operator over the life of the treatment plant. This rationalisation of treatment plants involves additional interconnecting pipework, which the Department 100% funds although the overall scheme cost divided by the number of houses in the new merged scheme still cannot cost more than €6,476 per house. An illustration of a DBO sub-bundle with 3 Group Schemes, interconnected into one DBO treatment plant, is provided below. Source: Ryan Hanley Consulting Engineers- Galway DBO Bundle No. 2 – Source Rationalisation Report 96 Ryan Hanley consultants carried out two extensive rationalisation studies of both of the new bundles and compared the cost of standalone plants and sub-bundling of plants. In the case of Mayo Bundle No. 2, Ryan Hanley proposed the provision of 12 water treatment plants to serve the water needs of 25 Group Schemes with 7 of the proposed plants being shared. This was estimated to be a saving of 22% or €4.3 million to the exchequer, including the cost of 100% funding inter-connector pipes, over the option of building standalone treatment plants for each Group Scheme in the bundle (Executive Summary, August 2005). Ryan Hanley proposed an even more sophisticated rationalisation solution in the case of Galway DBO Bundle No. 2 . Group Schemes in Galway are particularly dependent on groundwater, which means that there are a large number of relatively small schemes with less than 50 domestic connections per scheme. Ryan Hanley proposed that 35 out of the 58 Group Schemes in the DBO bundle should be rationalised into sub-bundles served by 11 DBO treatment plants with a saving of €7.5 million to the exchequer. However, even with the rationalisation down to 11 DBO treatment plants, the cost per house of the treatment plants in some of the sub-bundles would well exceed the €6,476 per house grant limit because of the small size of the schemes. This would mean that several of the smaller schemes in the 11 subbundles would not be able to afford to participate as the contribution per house could be up to €7,000 per house in some cases. Ryan Hanley proposed as a one off solution that all 35 Group Schemes being rationalised be treated as a single entity (sub-bundle), instead of the normal 11 entities (sub-bundles) for each of the 11 treatment plants. This formula would allow the DBO Bundle to proceed as the cost per house of the 11 treatment plants divided by the total number of houses in the 35 Group Schemes would be within the €6,476 per house grant limit. In this scenario, the larger Group Schemes’ contribution would effectively subsidise the smaller schemes. All 35 Group Schemes would have to agree to merge into one legal entity to allow this to occur (p.4., February 2006). The Department considered this proposal and approved it on a once off basis as Galway DBO Bundle No. 2 could proceed without having to breach grant limits. It could be argued that an opportunity to make additional cost savings was lost by not carrying out an extensive rationalisation study on all the completed DBO bundles at their planning 97 stage. It must be recognised though that the use of DBO bundling in the Group Scheme sector was a completely new development and as such there was a steep learning curve involved for the Department and local authorities. On balance then, it is fairer to acknowledge the innovation and ingenuity involved in developing rationalisation models than in speculating on lost opportunities with 20/20 hindsight. One issue that these developments do highlight is the impact of the €6,476 grant ceilings and the 15% Group Scheme contribution on seeking value for money solutions. Rationalisation was driven by the cost implications for Group Scheme members of building stand alone treatment plants. Plant Capacity and UFW Departmental policy is that plant capacity for DBO treatment plants should be theoretical design demand for the no. of houses + future development needs to 2020+25% allowance for Unaccounted for Water (Circular L11/2004). In designing plant capacity, an allowance was made for the water needs of each connection and the total of these was the plant water treatment capacity required in order to meet water needs. As the plant has a 20 year design life, an additional capacity was built in to allow for future development demand based on population predictions. In addition to that, a 25% allowance is made for unaccounted for water, known as UFW, which is water that will leave the treatment plant but will not reach the consumers’ homes due to leakages in the pipe network. 25% UFW may seem like a generous allowance but UFW is a major problem in public as well as Group Scheme pipe networks. The Dublin Water study in the late 1990s calculated that 40% of treated water in some areas of Dublin was lost due to leakages in the pipe (Circular L7/96). Subsequently, an extensive National Water Conservation programme was launched to address this issue on public water schemes. As can be seen from Table 4.1.4 below, UFW is a substantial issue for Group Water Schemes. The majority of Group Schemes in four completed DBO bundles shown below were estimated to have UFW levels in excess of 25%. This creates a problem of security of water supply for Group Schemes with treatment plant capacities based on a 25% UFW allowance. Client Reps have reported in some cases that water treatment plants are only able to supply sufficient water because of the additional future development capacity built in, which is not sustainable. 98 Table 4.1.4 Estimated Unaccounted for Water (UFW) in DBO Bundles East Cavan DBO Estimated Estimated UFW in UFW in 2002 (%) Limerick DBO 2004 (%) Billis Lavey 54% Baggottstown 24% Bunnoe 44% Ballinvreena 43% Dhuish 35% Ballybricken 25% Drumkeery 41% Ballyduff 28% Kill 53% Ballyorgan 23% Mountain Lodge 19% Bulgaden 29% Caherline/Newtown 35% 6% Cappagh 49% _ Carnane 35% Coshma/Killeen 59% Croagh/Farradonnelly 37% 2004 UFW Glenroe 72% Ardrahan 29% Glenstal 53% Ballyglass/Fiddane 50% Granagh 27% Brierfield 69% Griston 26% Caherlistrane 66% Kileedy 32% _ Kilfinny 40% Lough Gur 38% Crosserlough Clifferna Dernakesh Glaslough Tyholland Galway DBO Cleggan/Claddaghduff _ 34% Cloonatleva 56% Cloonluane 32% Inis Meain 40% West Cavan DBO Kiltevna 45% Glangevlin 13% Doobally 32% Toberowen Lissybroder _ Est. UFW Lettergesh 67% Ballymagovern 58% Lowville 51% Corlough 44% Milltown 60% Sralaghan 37% New Inn 38% Kildallan 41% Rinn Killeeneen 63% Milltown 73% Gowlan 44% Source: DBO Client Representatives-January 2007 99 There are two options to address this UFW issue; 1) Build treatment plants to allow for existing UFW levels 2) Implement active leakage control and water conservation measures, including pipe network upgrades The first option will involve the additional expense of building extra treatment plant capacity and the additional operating costs of treating more water, much of which will be lost in the pipe network as UFW. There is an additional environmental cost of abstracting more water than is needed from surface or groundwater sources, which could also affect security of supply, particularly during dry periods. The alternative option is to repair and in some cases replace inadequate pipe networks. The question is which is the most economic solution. As already discussed in the Literature Review, Ryan Hanley consultants carried out a Leakage Control Study of the 21 Group Water Schemes proposed for the Mayo DBO Bundle No. 2 (currently in planning) in March 2005. The study found that it was cheaper to build additional treatment capacity in only two of those schemes. A previous Leakage Control Study carried out by Ryan Hanley for Galway Bundle No. 2 in August 2004 also concluded that in most cases leakage control measures were more cost effective than building additional treatment capacity (p.1.). These leakage control studies reinforced the Department’s policy view that treatment plants should only be built with a maximum UFW allowance of 25%. It was accepted, however, that in many cases that pipe upgrade works could not wait until after completion of DBO contracts as there was a high risk that insufficient water supply would reach households. Therefore, the Department authorised certain critical network upgrade works be carried out as DBO Advance Works prior to the DBO contracts to bring UFW down to relatively acceptable levels. The issue of pipe network upgrades will be addressed later on in this chapter in the context of all the other water quality upgrade solutions and the additional costs involved in network upgrades to bring all Group schemes into compliance with the Drinking Water Regulations. 100 Other efficiency innovations during the DBO bundle period Change of planning arrangements Procurement is a vital component of the DBO process. It takes place in two stages with initial preliminary contract bids and subsequent shortlisting of preferred bidders. The 1997 Strategic Review of the Construction Industry (The Barry report) recommended that two stage selective tendering be used for all DBO projects for two reasons: requisite experience and cost of tendering (Procurement Guidance Document 2002, p.32.). It would be prohibitive on cost grounds to ask all bidding contractors to complete full tender documentation, when only a small number of bidders have a realistic chance of winning the contract. Therefore, a number of initial bidders are shortlisted and invited to submit full tender documents. One significant cost issue remained which was the issue of pre-tender planning. Under partnership arrangements between local authorities and group schemes, planning approval was sought by the local authority in respect of any Specified Development as set out in Article 80, Part 8 of the Planning and Development Regulations 2001. Part 8 Planning was usually sought at pre-tender stage. “Pre-tender planning has, however, tended to restrict the ability of tenderers to put forward DBO proposals that fully comply with performance specifications, while at the same time reflecting best value for money principles. This is, in large part, due to the requirement to comply with planning approvals already secured and overly prescriptive contract documents, particularly for civil works. As a consequence, it is possible for the most economically advantageous tender to be deemed non-compliant where it includes a structure or works not specifically identified in the Part 8 Planning process. This has obvious affordability implications for group water schemes participating in bundled DBO projects where they are required to meet at least 15% of civil works contract costs from their own resources.” (Circular L4/04 – 16th February 2004) The Department of the Environment, Heritage and Local Government, therefore, decided that the statutory planning process for DBO works would no longer be completed prior to the issue of contract documents. 101 “Instead, each tenderer will now be required to provide, as part of the Contractor’s Proposal: (a) the appropriate planning documentation the Contracting Authority would need to initiate the Part 8 planning procedure, (b) sufficient documentation to demonstrate that the proposed designs can satisfy any applicable planning constraints, and, if so required subsequent to the submission of a tender, to provide such documentation within a specified time. Tenderers shall be deemed to have satisfied themselves, through consultation with the Planning Authority or otherwise, that the proposed development will be such that the Contracting Authority will decide to carry it out.” (ibid) Pre-tender planning was particularly an issue for Group Water Schemes located in remote areas often in designated special areas of conservation. Overly prescriptive planning requirements could significantly increase project costs. Under the new arrangements, the preferred bidders for a DBO contract engage with planners at an open day to discuss their development proposals. This allows potential contractors to develop more innovative and cost effective treatment plant designs to meet planning requirements rather than having their design scope limited by planner imposed specifications. This Departmental initiative has been deemed quite successful in improving value for money, while at the same time ensuring that the protection of the natural environment is in no way compromised. Criticism of DBO contracts DBO projects have been regarded as being quite successful to date in terms of cost effectiveness. One criticism that has been made though is that while DBOs are generally quite cost effective at the Design Build phase, there is little incentive for the operator to innovate with new technologies during the operational and maintenance phase to reduce costs. Even if they do, the operator will pocket any savings as their existing revenue stream is guaranteed. This assumes, however, that local authorities would innovate with new cost saving approaches if they were running such plants, which might not necessarily be the case. Provisions have been made in all DBO contracts for the dismissal of the DBO operator during 102 the 20 year O&M phase for non-performance. An independent arbitration process would determine the buyout terms. The dismissal clause does provide a safeguard to ensure that Group Schemes are not trapped in unsatisfactory DBO contracts. Water Pricing Framework and the application of the Polluter Pays Principle In March 2000, the Irish Government accepted the proposals of the Minister for the Environment and Local Government for a water pricing framework (WPF) including the following elements: collection of capital contributions by local authorities from non-domestic users in a structured and uniform manner and in accordance with the polluter pays principle; operational costs in respect of the provision of water and waste water services to nondomestic users to be recovered in full based on usage, with an attendant adjustment to the commercial rate; The objective of the framework was to develop a more sustainable approach to water services management by fully internalising the costs of water usage and waste water generation in respect of the non-domestic sector, while making more explicit and transparent to domestic users the costs of the services which they use. This was in keeping with the application of the polluter pays principle which has been defined by the OECD as “the principle to be used for allocating the costs of pollution prevention and control measures to encourage rational use of scarce environmental resources...”. It was also in line with EU requirements (the Maastricht Treaty states “that environmental damage should as a priority be rectified at source and that the polluter should pay” (Article 130r)) [Departmental Circular L16 of 2002]. In practice, this meant that non-domestic water users would be charged the marginal capital cost of building additional water treatment infrastructure capacity to meet non-domestic water demand. They would also be charged for the operational and maintenance cost of being supplied with treated water by Councils, when connected to the public mains. The implementation of the WPF has been rolled out to local authorities since 2000 based on a series of Departmental circulars consolidated into Circular L16/2002. As can be seen in Appendix 6, there are also significant levels of non-domestic water demand in the Group Schemes’ sector. Given the need for priority implementation of the Action Plan for Rural Drinking Water Quality, a more streamlined approach has been adopted with the 15% Group 103 Water Scheme contribution being treated as the marginal capital contribution, for the purposes of the Water Pricing Framework. Effectiveness of DBO Solution As these DBO plants were only coming into operation for the first time in 2006, there is limited water quality test data available to assess the effectiveness of this water quality upgrade solution. DBO Client Representatives have reported in most cases that the Group Schemes are now fully compliant with the Drinking Water Directive based on the latest test data. Cases where exceedances are still occurring are related to recontamination problems in the pipe network rather than the treatment solution themselves. While DBO plants are fully operated by trained professionals, the DBO operators’ responsibility ends once the treated drinking water leaves the plant and enters the Group Schemes’ pipe network. Effectiveness Risk Factors DBO Client Representatives do recognise that there is a risk of recontamination of treated water in the pipe network. The two risk factors are contaminants entering sub-standard pipes and poor maintenance of pipe networks by Group Scheme members. These risk factors can be reduced by replacing or repairing faulty pipe work and by periodically scouring/flushing out pipes. In most cases, pipe network upgrades are being carried out in tandem with the construction of the DBO treatment works so this will considerably reduce the re-infection risk. This should ensure that water quality in the completed DBO Bundles is satisfactory. The situation in relation to the maintenance of pipe networks is less clear. Some Group Schemes have engaged caretakers on a professional basis to maintain their pipe networks. This will considerably reduce re-infection risk. The Water Services National Training Group and the National Federation of Group Water Schemes organise training for Group Scheme members in pipe network maintenance. In some cases, Group Scheme volunteers have been very diligent at maintaining their pipe networks so the risk of re-infection is low. However, the standard of maintenance in other Group Schemes is less clear and the risk of re-infection in the pipes is a potential problem. Given the millions of euros of taxpayers’ funds being invested in building treatment plants and upgrading pipe networks, it is unacceptable that 104 water could become re-contaminated again before it reaches household taps due to poor pipe network maintenance. Possible future options for pipe network maintenance It seems clear that in a scenario of decreasing volunteerism, it is not sustainable to continue to expect pipe networks to be maintained on a non-professional basis. An alternative option would have been to include pipe network maintenance as part of DBO operator duties. Department of the Environment, Heritage and Local Government officials were asked why this was not originally considered as an option. Two main reasons for this were outlined; 1. The consortia bidding for the DBO contracts were mainly involved in constructing and operating water treatment plants and did not involve themselves in pipe network maintenance. Pipe network upgrades were carried out separately under non-DBO contracts. 2. The extension of DBO contracts to the operation and maintenance of the pipe networks would essentially have completely contracted out their operation to commercial concerns and this was a step that Group Water Schemes were reluctant to accept as community organisations. This level of privatisation has not taken place in the public schemes’ sector either although public DBO treatment plants are also in operation. An alternative option would be to have local authority staff carry out operation and maintenance work on pipe networks. This would have the merit of having statutorily accountable organisations responsible for a public health function, however it would also involve an additional cost to the exchequer as current subsidy levels are based on Group Scheme volunteerism. Whatever option is adopted, it is clear that additional investment will have to be made in pipe network maintenance in the future and it is likely that some if not all of this burden may fall on the exchequer because of the requirements of the Drinking Water Directive. 105 DBO Solution - Existing Value for Money Conclusions It is clear that value for money was a strong factor in developing DBO projects. Evidence of this is shown by initiatives such as: Bundling of DBO projects to attract innovative and competitive bids from the national and international water infrastructure construction market Merging/Sub-bundling of schemes to reduce the number of treatment plants required Change from Pre-tender to post-tender planning to encourage more cost effective designs Transference of construction risk to DBO contractor by limiting capital cost increases Economic plant design capacities with water conservation measures to reduce leakage and over abstraction of water for treatment purposes DBO Solution - Need for Value for Money Improvements There are certain areas where value for money issues need to be addressed; 1. While the local authority questionnaire returns suggest that in most cases, the DBO option was the most cost effective solution adopted, there is a need for greater transparency in relation to this. It is recommended that for all future DBO project proposals, a report should be prepared costing all alternative options to the DBO route and comparing those costs to the DBO cost. 2. County Councils have stated that in most cases all alternative options to DBOs were costed but verification of this was not provided, in most cases, within the time limits of this Review. This verification should be included in the Final Accounts of all DBO Bundles completed to date as well as confirmation of the final cost of the civil works contract and the payment by each Group Scheme of their 15% capital contribution. 3. In cases where Group Schemes cannot be connected to existing public supplies due to insufficient existing plant capacity, the cost of increasing existing water treatment plant capacity must be included as an option. 106 4. The Department and local authorities should continue to assess opportunities for achieving greater value for money by rationalising the number of water treatment plants in DBO Bundles so that two or more Group Schemes can be served by the same treatment plants. 107 Non-DBO Water Quality Upgrade Solution Introduction This is the water quality upgrade that has been identified for 21 of the 729 schemes (3%). Non-DBO is a somewhat incongruous name but encompasses all water quality upgrade solutions involving the installation of a stand alone treatment facility, not procured by way of a DBO contract. In some cases, it simply involved upgrades to existing treatment infrastructure. Responsibility for both the operation and maintenance of the treatment infrastructure and the pipe network remains with Group Scheme volunteers. The Department provides 85% grant aid up to a maximum of €6,476 per house with a 15% Group Scheme contribution. Any necessary pipe network upgrades must also be funded from the same €6,476 grant limit. Solution Implementation and overall expenditure As can be see from table 4.2.1 below, implementation under this treatment solution is moderate at 24% as of June 2006. There is no overall expenditure figure available for this treatment solution during the 2003-’06 period as works are funded out of the Upgrade measure, which also includes pipe upgrade works and Disinfection/Sterilisation schemes. From the data collected in the case studies below, it would appear, however, that capital expenditure per house under this solution is minimal by comparison to the cost of the other solution types Table 4.2.1 – Implementation of the Non-DBO solution Non-DBO Scheme No. of Group % implementation Status Schemes In Planning 7 33% Work in Progress 9 43% Complete 5 24% Total 21 Source: Report to the European Commission – June 2006 p.34. 108 Efficiency of non-DBO treatment solution It was decided to examine the five schemes that were complete. These schemes were identified from the list of completed schemes submitted by local authorities as part of the June 2006 Report to the European Commission. Monaghan County Council advised the Department that the treatment infrastructure for one of these non-DBO schemes (Magheracloone GWS) was installed long before the 2003-’06 period under review so there was no capital expenditure to report. Financial data in relation to the other four completed non-DBO scheme are listed in Table 4.2.2 below. Table 4.2.2 - Financial Data re. Non-DBO Schemes Pipe Total Capital Scheme No. of Completion Capital DB Upgrade Capital Cost per County Name Houses P/E Date House (€) Kerry Cappanlea 7 120 Jul-01 €37,000 €30,500 €67,500 €9,643 Wexford Adamstown 3 12 Jan-06 €5,303 €0.00 €5,303 €1,768 €1,886,519 €8,132 €399,231 €7,393 Claren/ Galway Knocklehard Cork South Kilcredan Cost Cost €1,378,030 Not 232 720 operational 54 - Cost €508,489 Nov-04 €44,473.91 €354,757 Source: Local Authority data requests-January 2007 As can be seen from Table 4.2.2 above, the overall Scheme capital cost and cost per house vary widely. Kerry and Cork South County Councils confirmed that the €6,476 per house grant limits were not exceeded in the cases of Cappanlea and Kilcredan as the Group Schemes paid the capital costs in excess of the grant limit. The Department is seeking certain clarifications from Galway County Council in relation to the funding of Claren/Knocklehard. It is noticeable in most cases that the cost of the pipe network upgrade was equivalent to or far exceeded the cost of the water quality upgrade solution. The small number of houses explains the high capital cost per house, in the case of Cappanlea. However, there is an adventure 109 centre attached to the Group Scheme. Therefore, even though the Group Scheme has less than 15 houses, it must comply with the Drinking Water Regulations, as there is a premises with a commercial function attached to it. In 3 out of 4 cases the non-domestic water demand was very low but it was 75% for Cappanlea. This is due to the water demand of the adventure centre. In 2 out of 4 cases, the public mains were too distant for connection. In the case of Cappanlea, Kerry County Council stated that there was insufficient capacity on the existing public mains. In the case of Claren/Knocklehard, Galway County Council stated that connection to the public main was initially proposed as a water quality solution in correspondence with the Group Water Scheme. However, the Group Scheme rejected this option and a standalone treatment facility was constructed instead. This is a matter for concern as it appears that the Group Scheme exercised a veto in this case and a more expensive solution was constructed instead. It is important that Group Schemes are consulted in relation to water quality upgrade solutions, particularly as they have to contribute towards the cost. However, a private Group Scheme cannot dictate that tax payers pay more than is necessary to resolve their water quality problems. Effectiveness of Non-DBO Treatment Solution 2005 EPA test data was checked to verify if the non-DBO Schemes were compliant with the Drinking Water Directive after completion. Councils were also asked to confirm that the Schemes were compliant based on 2006 water quality test results available to them. The results are set out in Table 4.2.3 below and are extremely mixed. 4 out of 5 of the completed non-DBO Schemes are still showing exceedances of Drinking Water Regulation parameters. In the case of two of these upgraded Group Schemes - Cappanlea and Claren/Knocklehard, there are exceedances of the E Coli microbiological parameters. Those two Group Scheme are clearly not in compliance with the Drinking Water Regulations. This is, particularly, a cause for concern with regard to Cappanlea in Kerry. This Group Scheme has a population equivalent (p/e) of 120 due to the Adventure Centre attached to it. 2 of the remaining 3 Group Schemes show exceedances of the less serious indicator parameters. Monaghan County Council said that the coliform exceedance in Magheracloone was a one off incident coinciding with maintenance works to part of the pipe network. Galway County Council have explained that there have been delays in commissioning the Claren/Knocklehard treatment plant so the treatment solution is not actually operational yet. This explains the 110 continuing exceedances of the E.Coli paramater even though the Group Scheme has officially been upgraded. Given the small number of schemes completed using this solution to date, it is difficult to form a conclusive view in relation the effectiveness of the solution. It certainly needs to be investigated further to clarify whether the solution is the problem or whether it is due to inadequate maintenance by Group Scheme volunteers. If it is the latter, local authorities should insist that members of the relevant Group Water Schemes participate in training courses organised by the Water Services National Training Group (WSNTG). Table 4.2.3 - 2005 and 2006 Exceedances of Drinking Water Quality Parameters No. of County Kerry Scheme Name Cappanlea Completion 2006 Houses P/E Date 7 120 2005 EPA Exceedances Exceedances E Coli , E coli, pH, Coliforms, manganese, Jul-01 Iron, pH Total iron Total Coliforms and Coliforms and Wexford Adamstown 3 12 Jan-06 pH pH 1 Coliform exceedance & Monaghan Magheracloone Colour E.coli, Not Galway Claren/Knocklehard Cork South Kilcredan Coliform & 232 720 Operational E. coli 54 Nov-04 None Manganese None Source: 2007 EPA Drinking Water Quality Report and Local Authority data Conclusion It is clear that the non-DBO solution is a residual treatment category for a small number of Group Schemes, whose treatment solution is not DBO or Disinfection/Sterilisation based. It is financially quite efficient but its effectiveness is questionable. Further analysis is necessary to 111 clarify whether the treatment solution itself or the operation and maintenance of the solution is ineffective. If the latter is found to be the problem, local authorities should insist that members of the relevant Group Water Schemes participate in training courses organised by the Water Services National Training Group (WSNTG). 112 Public Water Supply Solutions Introduction As stated in this Review’s introductory chapter, water quality upgrade solutions fall into two distinct categories. The first category involves the installation of water treatment infrastructure to serve the Group schemes and comprises the DBO, Non-DBO and Disinfection/Sterilisation solutions. The second category involves connecting Group Schemes to the nearest public water supply, where this is possible, and discontinuing the use of their sub-standard private water source. One of these solutions is called “Connection to the Public Main” (CTPM), where the Group Scheme receives it water supply from the public mains but remains responsible for the maintenance of its pipe network with a €50.89 annual operating subsidy per domestic household. The CTPM solution has been identified for 118 schemes (16%) of all schemes. The second solution is called “Takeover”, where a Group Scheme is connected to the public mains and is completely taken over by the Council. In this case, the Group Scheme effectively ceases to exist and its former members become public water consumers. The local authority is responsible for both water treatment and maintenance of the pipe network so no further operational subsidy payment is required. The Takeover solution has been identified for 65 schemes (9%) of all schemes. Implementation of Public Water Supply Solutions The first striking characteristic of these public water supply solutions is the low level of implementation of these solutions to date by comparison to the water treatment solutions. According to the June 2006 Report to the European Commission, there were only 3 takeovers and 6 CTPMs completed out of 65 schemes designated for takeover and 118 designed for CTPM (see table 4.3.1 below). It will be shown later on in this chapter that there were additional CTPM and Takeover works carried out but these were generally low priority works unrelated to compliance with the Drinking Water Regulations. Overall expenditure for CTPM and Takeover schemes, during the 2003-’06 period, were €16m and €46m respectively. It should be noted that CTPM works were funded as part of the network upgrade measure up to 2003 so the €16m figure only covers the 2004-’06 period, when CTPM works had their own separate capital measure. 113 Table 4.3.1 – Implementation of the CTPM and Takeover Solutions Scheme Status No. of CTPM No. of Takeover Schemes Schemes In Planning 85 35 Work in Progress 27 27 Complete 6 3 Total 118 65 Source: Report to the European Commission – June 2006 p.35-36. Councils were asked to provide reasons why implementation to date was so low particularly given the progress to date on the DBO treatment solutions. Councils offered a number of reasons in their Questionnaire responses (Q.7.); Delay in reaching agreement with Group Schemes on implementation of solution Delays in getting 100% agreement by Group members Lack of interest in some Schemes to takeover or CTPM Concerns and suspicions re. chlorination of public water supplies Unwillingness of non-domestic consumers on Group Schemes to pay commercial water charges if connected to public mains Problems with access to lands to allow connection to public mains Lack of statutory powers to allow Council to impose solutions on non-co-operative Group Schemes Insufficient water capacity on public schemes GWS don’t see benefit of paying 15% contribution towards civil works for CTPM, when their O&M cost will increase and their subsidy payment will half, as subsidy payment subsidises the non-domestic members of the GWS. It would appear from the information supplied by Councils and anecdotal evidence that the core reason why these projects are not progressing is that non-domestic users on Group 114 Schemes would be charged by the Council for water use, when they are connected to the public mains. Most of these non-domestic users would be relatively heavy water users, and regard it in their commercial interest to remain on private water supplies, even if those water supplies are seriously deficient. As most Group Schemes currently require 100% agreement of their membership to be taken over or to be connected to the public main, a minority of members can hold up progress. While this is a logical position to hold from a purely commercial perspective, it is simply not acceptable or sustainable from a public health perspective. Quite apart from that, the Irish taxpayer will be required to pay significant fines to the European Commission if sub-standard private water supplies like these are not upgraded to comply with the Drinking Water Directive. As already stated, at the start of this chapter, Councils were empowered to take prosecutions against non-compliant Group Schemes under the Drinking Water Regulations 2000. The Minister for the Environment, Heritage and Local Government gave local authorities additional powers to carry out remedial works, without Group Schemes’ consent where necessary, and charge the cost to Group Schemes under the 2007 Drinking Water Regulations (S.I. No. 106 of 2007). The Department believes that with the new Regulations, Councils will have the necessary powers to proceed with the implementation of these two water quality upgrade solutions. Of course, having legal powers and enforcing them are two different things so it waits to be seen whether local authorities will exercise these powers, the reaction of volunteer Group Scheme trustees and the outcome. The National Rural Water Monitoring Committee (NRWMC) previously appointed a national co-ordinator to oversee DBO project implementation. In light of the successful ongoing implementation of that solution, the NRWMC has decided to extend the remit of a newly appointed national coordinator to also oversee the implementation of the CTPM and Takeover solutions by Councils. Efficiency and Effectiveness of Public Water Supply Solutions Given the limited implementation to date of these two upgrade solutions, it was only possible to examine a relatively small number of schemes to assess effectiveness and efficiency. 115 Connection to the Public Mains (CTPM) Upgrade solution As has already been stated above, this solution has been identified for 118 schemes (16% of overall schemes) previously being served by sub-standard private water sources. The Group Scheme is connected to the nearest available public water supply so no longer has any responsibility for treating the water. The Group Scheme does remain responsible for the maintenance of its pipe network with a €50.89 subsidy per house. The capital cost of connecting to the public mains is 85% funded by the State with a 15% Group Scheme contribution. Councils have reported that some Group Schemes object to paying this 15% contribution on the basis that they are being connected to the public mains, while other public water users do not have to pay such a contribution. Also, Group Schemes that are completely taken over by Councils do not have to pay any capital contribution. The overall Departmental grant for connecting a Scheme to the public mains cannot exceed €6,476 per house. This grant limit also includes any necessary pipe network upgrades. Five completed CTPM schemes were selected to assess their efficiency and effectiveness and the results of these case studies are outlined below. Efficiency of CTPM solution The first point to note is that additional pipe network upgrades were carried out in all cases below. Also, the cost of the pipe network upgrade exceeded the cost of connecting the Group Scheme to the public mains in all five cases. It should be noted that there was a complete network replacement in the case of Carrowmeena. These pipe network upgrades were necessary to address UFW and to reduce the risk of re-infection in the pipes. County Councils have confirmed that competitive procurement was used for works on all 5 Group Schemes. As can be seen below, the total cost per house of this solution varies widely from scheme depending on their unique situation and in two cases the capital cost exceeded the €6,476 per house. However, Leitrim County Council confirmed that the €6,476 grant limit was not exceeded for Corraleehan due to the Group Scheme contribution. Clare County Council explained that it is intended that Ballagh/Cahersherkin will be completely taken over by the Council so the €6,476 per house grant limit doesn’t apply in this case. 116 Table 4.3.2 – Financial data on CTPM Schemes County Completion No. of Council Scheme Name Date Pipeline Network Total Distance Connection Cost Upgrade Upgrade Cost per Cost (€) Cost (€) Houses (km) per Km Cost Total House(€) Ballagh/ Clare Cahersherkin Mar-07 170 4.495 Donegal Carrowmeena Aug-03 47 1.3 411,214 91,483 0 985,850 1,397,064 8,218 0 215,975 215,975 4,595 Cloonmore Galway No. 1/Killilane Apr-05 73 0.63 25,200 40,000 59,850 85,050 1,165 Mayo Bekan May-05 146 2 100,000 50,000 548,653 648,653 4,443 Leitrim Corraleehan Jun-02 268 0 1,234,405 1,888,164 7,045 - 653,759 Source: Data requested from Local Authorities – January 2007 Effectiveness of CTPM Solution The latest available 2005 EPA test results and data from local authorities was examined to test the compliance of these Group Schemes with the Drinking Water Regulations after connection to the public water supply. There were no exceedances reported by Clare County Council for Ballagh/Cahersherkin after connection to the public main. Cloonmore No.1 /Killilane exceeded the manganese parameter but this is only an indicator parameter. On the other hand, Corraleehan had exceedances of the microbiological E. coli parameter in 2005, even though it was connected to the public mains in 2002. Leitrim County Council reported that they followed up this incident and the problem was resolved with all tests subsequently being passed. No assessment can be made of the effectiveness of the CTPM solution for Bekan or Carrowmeena Group Schemes as they do not appear to have been tested at all since they were connected to the public main. Donegal and Mayo County Councils are legally required under the Drinking Water Regulations to test all private water supplies serving >15 houses and/or with a commercial/public use connection but this does not appear to have occurred in 2005. 117 Table 4.3.3 – 2005 and 2006 Exceedances of Drinking Water Quality County Council Completion Scheme Name Date 2005 EPA Exceedances 2006 Exceedances Ballagh/ Clare Cahersherkin Mar-07 Colour and Odour only Donegal Carrowmeena Aug-03 No testing done No Cloonmore No. Galway 1/Killilane Apr-05 No exceedances Manganese only Mayo Bekan May-05 No testing done No Bacterial contamination E.Coli and coliform Leitrim Corraleehan Jun-02 bacteria incidents followed up and resolved Source: 2007 EPA Drinking Water Quality Report and Local Authority data It would appear from this relatively small sample and the latest 2006 exceedances data that the connection to the public mains is a relatively effective water quality upgrade solution. A larger sample is needed to definitely confirm this but successive EPA drinking water quality reports have categorised public source water quality as satisfactory. The main risk factor is re-infection in the pipe network due to poor network maintenance by the Group Schemes although the above five Councils have not cited this as a risk factor for the above schemes. 118 Takeover Upgrade Solution As already stated, this water quality upgrade solution involves the complete takeover of Group Schemes by their local authority. The Group Schemes are connected into the public mains and the Council becomes totally responsible for the maintenance of the pipe network, which transfers to Council ownership. This solution receives 100% capital funding with no Group contribution and no grant ceiling. The Department has made a conscious decision not to require a Group Scheme contribution for complete takeover of schemes by local authorities. Takeover is regarded as the best guarantee of addressing water quality issues as the former Group Scheme members will receive their water from the public supply and will have their pipe networks professionally maintained by local authority staff. Efficiency of Takeover Solution Table 4.3.4 – Financial data on Takeover Schemes Pipeline No. of Scheme Name Cost Network Total Total Distance Connection per Km Upgrade Upgrade Cost (€) Complete Houses (km) (€) Cost (€) Cost (€) Cost per House (€) Craans/Newstown Nov-06 56 5.3 455,000 85,849 0 455,000 8,125 Cloonminda Apr-04 54 0.246 10,000 40,650 227,032 237,032 4,389 Kilkerly Mar-04 46 0.71 67,166 94,600 0 67,166 1,460 Source: Data requested from Local Authorities – January 2007 Councils provided financial data for the above three schemes. Data was also requested from Roscommon County Council for Carane Whitehall and from Mayo County Council for the Clare Island takeover. Mayo County Council explained that there was no expenditure involved in taking over the Clare Island scheme and Roscommon did not provide the requested data. As can be seen, the takeover costs vary widely and in the case of Cloonminda the pipe network upgrade cost far exceeded the connection to the public mains cost. The Craans/Newstown takeover in Co. Carlow was particularly expensive at €8,125 per house. It should be noted though that there is no grant ceiling for takeovers and they are 100% grant aided by the Department. Generally, connections to the public main (CTPM) and takeover are 119 cheaper than standalone DBO treatment plants. But there are situations where there is no adequate water source for a standalone plant so connection to a distant public mains may be the only technical but expensive option. Effectiveness of Takeover Solution The effectiveness of the takeover solution was assessed based on the latest available EPA data for 2005 and test result data provided by Councils for 2006. No tests were carried out on some of these schemes post take over as they no longer exist as Group Schemes and are now part of the public mains. This is legally in order as only certain sections of the public mains supply are sample tested, whereas all Drinking Water Regulated Group Schemes must be tested. Table 4.3.5 – 2005 and 2006 Exceedances of Drinking Water Quality County 2006 2005 Council Scheme Name Carlow Craans/Newstown Nov-06 None Nitrate Galway Cloonminda Apr-04 None None Mayo Clare Island Roscommon Carane Whitehall Louth Kilkerly Complete Exceedances Exceedances No data None None No data No Data No Tests Mar-04 None No Tests Source: 2007 EPA Drinking Water Quality Report and Local Authority data As the above 5 Group Schemes are now fully connected into the public mains and their pipe networks are being maintained by local authority technical staff, it is safe to conclude that this water quality upgrade solution is effective, in spite of the lack of test result data, based on EPA reports in relation to the satisfactory standard of public drinking water quality. 120 Takeover and CTPM works unrelated to the European Court of Justice (ECJ) case In view of the apparent lack of implementation of the CTPM and Takeover water quality upgrade solutions in the June 2006 report to the European Commission, Councils were asked in the November 2006 Questionnaire (Q8) to list all the Group Water Schemes taken over and CTPM during the 2003-'06 period. The response received was that 142 Schemes were taken over and 94 schemes were CTPMs. These figures differ considerably with the June 2006 Report to the European Commission of 3 Takeovers and 6 CTPMs. In both cases, the number of completed CTPMs and Takeovers exceeded the total schemes designated for these solutions in the June 2006 Report (see Table 4.3.6 below). Needless to say, this difference cannot be merely explained away by speculating that there was a substantial increase in solution implementation in the second half of 2006. Table 4.3.6 – Comparison of June 2006 and Jan 2007 CTPM/Takeover completions Solution Category Total Schemes June 2006 Jan 2007 Designated per Report Questionnaire Solution Completions Completions Takeovers 65 3 142 CTPM 118 6 94 Scheme Totals 183 9 236 Source: Q8 Local Authority Questionnaire Returns (Jan 2007) & June 2006 Report to the European Commission p.35-36. In trying to reconcile this considerable difference, a number of explanations were found; 1. Public Source – A number of schemes were misclassified under this heading in the June 2006 Report to the European Commission when in fact they were completed CTPM schemes now connected to the public mains. In other words, the number of private source schemes connected to the public mains during the 2003-’06 period was undercounted in the June 2006 Report to the European Commission. 121 2. Takeovers - Of the 142 schemes taken over by Councils, 92 were already on the public mains and 50 were on a private source. The Department’s current policy is that sub-standard private source schemes should be taken over as a matter of priority. Group Schemes, already connected to the public mains, should not be taken over unless strictly necessary. Table 4.3.7 - Breakdown of Completed Takeovers into Public/Private Source Schemes Completed Takeovers Public Source Private Source Total Total 92 50 % 65% 35% 142 100% Source: Q8 Local Authority Questionnaire Returns (Jan 2007) The data supplied in local authorities returns in Table 4.3.7 above would suggest that 65% of all Group Schemes taken over by local authorities during the 2003-’06 period were already on the public mains and only 35% were on a private source, when taken over. 3. Schemes not on June 2006 list of Schemes to European Commission - There are more schemes in total taken over and CTPM during 2003-06 period than are actually designated for these treatment solutions in the overall lists sent to the European Commission in June 2006 (see Table 4.3.6 above). This is explained by the fact that quite a number of Schemes CTPM and taken over during 2003-06 do not appear on the list of schemes sent to the European Commission. In other words, quite a large number of the schemes taken over or CTPM during 2003-’06 were not required to comply with the Drinking Water Directive at all due to their small size and were not relevant to the European Court of Justice (ECJ) case against Ireland. So while implementation under the priority Schemes has been very slow, capital funds appear to have been drawn down by some Councils to takeover or connect non-priority Group Schemes to the public mains. 122 Council Explanations Several Councils were contacted and asked to explain why there was so much CTPM and Takeover activity underway on small non-priority Group Scheme, particularly given the low level of implementation on priority schemes. Councils offered several explanations In some cases, there were serious quality problems with smaller Group Schemes. These Schemes were connected to the public mains or take over on public health grounds, even though they were too small to require compliance under the Drinking Water Regulations. Some smaller Group Schemes requested to be connected to the public mains or be taken over as they did not have the resources to maintain the Scheme themselves. Departmental view Departmental officials point out that they have always emphasised to Councils the need to advance priority CTPM and Takeover projects over the 2003-’06 period. They do concede that it is possible that some Councils were committed to carrying out lower priority projects at the start of the 2003-’06 period. Councils were invited by the Department to submit bids for their 2007 block grants on 7th December 2006. They were specifically instructed to prioritise projects, which needed upgrading to comply with the Drinking Water Directive, ahead of any other projects because of the implications of the ECJ ruling. The Department still received ‘elaborate proposals’ for takeovers of low priority Group Schemes in the 2007 local authority bids. These proposals were rejected by the Department and did not receive funding under the 2007 block grant allocations. It is clear that that the Department has given unambiguous instructions to local authorities to only advance CTPMs and Takeovers for priority Group Schemes. Expenditure on water quality upgrades, unrelated to the ECJ case, was necessary so it should not, in any way, be regarded as wasted. However, it is important that funding targeted at high priority schemes should be spent on those high priority schemes. New performance indicators will be recommended in Chapter 6 to try and ensure this. Comparison of Local Authority water charges to DBO O&M costs It is clear from the Questionnaire returns from local authorities and anecdotal evidence that the key issue holding up the implementation of the CTPM and the Takeover solutions is the reluctance of some non-domestic water consumers on Group Schemes to be connected to the 123 public water supply due to local authority water charges. There is also a clear preference on the part of such consumers for the DBO treatment plant option, as they perceive this to be the cheaper option in terms of ongoing operation and maintenance (O&M) costs for them. The ongoing O&M costs for Group Schemes of the respective water upgrade solutions is not directly an issue for the Department beyond the payment of the annual domestic household subsidy. It is, however, impacting on the implementation of the Rural Water Programme and increasing the risk of European Court of Justice (ECJ) fines for non-compliance with the Drinking Water Regulations. Therefore, it is important that this Review briefly examines the issue of comparative O&M costs for DBO and Public Source Group Schemes. Local Authority Water Charging System Local authorities are required to charge all non-domestic consumers for their water usage, under the terms of the Government’s Water Pricing Framework (Circular L16/2002). This also applies to any non-domestic consumers on Group Water Schemes connected into the public water supply. In addition, non-domestic water consumers on any private source Group Water Schemes, which are subsequently taken over by their local authority and absorbed into the public water supply system, are also required to pay water charges to the local authority. As domestic water consumers on the public mains are not directly required to pay water charges (the costs of which are funded through central taxation), the Department recommends that domestic water consumers on publicly sourced Group Schemes should be given a free water allowance of 50,000 gallons per house per year (227 cubic meters) by their local authority. Connections, with both domestic and non-domestic water needs e.g. farms, should also be given an annual 50,000 gallons allowance for domestic purposes (Subsidy Memorandum 2002, p.6.). Councils should charge for any water usage above and beyond the permitted allowance. Water charging levels differ from Council to Council both in terms of fixed connection charges and volumetric water usage charges. Councils also apply different domestic water allowances to Group Scheme consumers. All Councils providing water to Group Schemes, with the exception of Kilkenny and Kerry County Councils, use exactly the same charging rates for Group Scheme non-domestic consumers as for non-domestic water consumers, who are fully on the public mains. These charges are set out in Table 4.3.8 below. Some Councils reported that they do not currently have any active Group Schemes connected to the public mains so they are marked non-applicable (N/A). 124 Table 4.3.8 – Table of annual local authority water charges for public Group Schemes (2006) Annual Same as Vol. charge Fixed Initial Free Dom. Urban per M3 of Charge per Connection Water m3 charges water (€) connection Fee per hse Allowance Yes €0.86 €290 €750 - €2500 €190 Carlow N/A N/A N/A N/A N/A Cavan Yes €0.76 €211 €1,050 227 Clare €0.84 €220 €670 155 Cork North Yes €0.84 - No Limit Cork South Yes €0.84 €230 €650 155 Cork West Yes Yes €1.40 €236- €436 Varies 228 Donegal Yes €0.73 €0 Varies 227 Galway No €0.52 €50 228 Kerry Yes €1.28 €578 €431 €242 Kildare No €0.69 €38 €1,000 182 Kilkenny Yes €1.09 €50 €0 227 Laois Yes €0.74 €60 €650 227 Leitrim Yes €0.86 €0 €600 227 Limerick Yes €1.09 €100 €600 No Limit Longford N/A N/A N/A N/A N/A Louth Yes €0.00 €0 €1,500 227 Mayo N/A €0.00 €0.00 €0.00 N/A Meath €0.80 €0 €0 None Monaghan Yes Yes N/A N/A N/A N/A Nth Tipp Yes €1.01 €0 €500 227 Offaly €0.92 €0 €880 227 Roscommon Yes Yes €1.25 Varies €0 227 Sligo €0.83 €0 €0 No Limit South Tipp Yes N/A N/A N/A N/A Waterford Yes €0.95 €0 €0 227 Westmeath Yes N/A N/A N/A N/A N/A Wexford Yes €1.13 €40 €0 170 Wicklow Source: Q20-21. Local Authority Questionnaire Returns – January 2007 County Council DBO Operation & Maintenance (O&M) Costs Several DBO treatment plant bundles are now starting to come into operation. Early, and it must be stressed provisional, O&M charging data has been supplied by DBO client representatives for the purposes of this Review. The DBO operators’ estimated fixed cost per house and volumetric cost per cubic meter of water charges for the Galway No. 1, Clare and East Sligo DBO Bundles are set out in the Tables 4.3.9 below. The local authorities’ corresponding fixed and volumetric water charges for non-domestic consumers on publicly sourced Group Schemes in the same counties are summarised in Table 4.3.10 below. 125 Tables 4.3.9 – Provisional DBO operator annual water charging rates Fixed Variable Galway DBO 1 Scheme Costs per cost per Names House m3 Ardrahan €112 €0.15 Ballyglass/Fiddane €113 €0.20 Brierfield €115 €0.20 Caherlistrane €107 €0.10 Cleggan/Claddaghduff €107 €0.30 Cloonatleva €113 €0.18 Cloonluane €109 €0.20 Inis Meain €109 €0.33 Kiltevna €107 €0.19 Toberowen Lissybroder €107 €0.19 Lettergesh €108 €0.28 Lowville €120 €0.29 Milltown €108 €0.25 New Inn €110 €0.12 Rinn Killeeneen €113 €0.55 Fixed O&M Volumetric Clare DBO Group Costs per hse Cost per Scheme Names per year M3 Lissycasey €92 €0.13 Killone €92 €0.18 Toonagh/Dysart €92 €0.18 Kilmaley/Inagh €92 €0.10 Fixed O&M East Sligo DBO Costs per Volumetric Scheme Names house Cost per M3 Geevagh/Highwood €215 €0.33 Keash €215 €0.22 Culfadda €215 €0.17 Corrick €215 €0.33 Castlebaldwin €215 €0.23 Source: DBO Client Representatives – January 2007 126 Table 4.3.10 – County Council Water Charging Rates 2006 County Council Annual Fixed Cost per m3 of Cost water Galway Nil €0.73 Clare €211 €0.76 Sligo Varies €1.25 Source: Q20-21. Local Authority Questionnaire Returns – January 2007 It would appear from this rough comparison that the DBO Bundles provisional O&M cost volumetric rates are significantly lower than those charged by the three corresponding local authorities. It would appear from the perspective of a non-domestic water consumer that they receive better value for money in terms of operating costs by being connected to a DBO treatment plant than being connected to the public mains or taken over. It must be stressed again that the DBO O&M costs figures are provisional and may turn out to be significantly understated but it is clear that anecdotal knowledge of this apparent cost differential is encouraging non-domestic consumers on Group Schemes to delay or obstruct connection to the public mains. It should be borne in mind that local authority charges also include network maintenance charges, which are not part of the DBO operators’ responsibility. It should be noted though that local authorities only maintain the public part of the pipe networks and not the privately owned Group Scheme portion. The Department’s domestic subsidy partially contributes towards the network maintenance costs for domestic Group Scheme householders, while nondomestic Group Scheme consumers must directly contribute towards their network maintenance as well as pay local authority water charges. It is not clear, however, whether network maintenance costs fully explain the difference in charges. The apparently significant operational cost differential between Group Scheme DBO and local authority run water treatment plants lies outside the terms of reference of this particular Review but it is a matter that should be examined more closely by the Department and local authorities on value for money grounds. 127 Conclusions It would appear based on the case studies examined that both the CTPM and Takeover public source upgrade solutions are effective and relatively cost efficient. As with other water quality upgrade solutions, there are significant costs involved in upgrading the pipe networks in addition to the water quality upgrade costs. There is an effectiveness risk factor for CTPM Schemes as the Group Schemes remain responsible for the maintenance of the pipe networks. This is not an issue for takeover schemes as they are fully absorbed into the public water system and are maintained by local authority technical personnel. Implementation is the real problem for public source solutions due to local authority water charges for non-domestic Group Scheme consumers. However, the Department has taken steps to ensure that Councils must only advance high priority projects, requiring compliance with the Drinking Water Regulations first. County Councils have now also been given greater legal enforcement powers to deal with non-co-operative Group Schemes. 128 Disinfection/Sterilisation Water Quality Upgrade Solution Introduction This is the water quality upgrade that has been identified for 122 of the 729 schemes (17%). Although, there are a large number of schemes using this solution, it is mainly clustered into a small number of counties, which receive their water from mainly groundwater sources. The natural chemistry of this raw water is generally quite good so basic chlorination is availed of. The National Rural Water Monitoring Committee (NRWMC) expressed reservations in relation to this minimal treatment solution in their 2005 Review of their Action Plan. In this review, “the NRWMC questions the sustainability of this approach and recommends that each Council review the quality of the raw water (based on source monitoring) and look again at the appropriateness of this solution” (2005, p.8.). There were also concerns in relation to the possible creation of potentially carcinogenic Trihalomethanes (THMs) if untrained Group Scheme volunteers mixed incorrect amounts of chlorine into water generating THMs. Solution Implementation and overall expenditure As can be see from Table 4.4.1 below, implementation under this treatment solution is very high at 75% as of June 2006. However, much of this work was carried out prior to the 2003’06 period under review so this level of output is not really comparable to implementation under the other upgrade solutions. There is no overall expenditure figure available for this treatment solution during the 2003-’06 as works are funded out of the Upgrade measure, which also includes pipe upgrade works and non-DBO schemes. From the data collected in the case studies below, it would appear, however, that capital expenditure per house under this solution is minimal by comparison to the cost of the other solution types. It is grant aided up to a maximum of €6,476 per house with a 15 % Group Scheme contribution. Any necessary pipe network upgrades must also be funded out of the grant maximum. Table 4.4.1 – Implementation of Disinfection/Sterilisation Solution – June 2006 Report, p.39. Scheme Status No. of Group Schemes % implementation In Planning 19 16% Work in Progress 11 9% Complete 92 75% Total 122 129 Case Studies As already stated, the Disinfection/ Sterilisation solution is mainly clustered into a relatively small number of local authority areas. Four County Councils were contacted by phone and email in relation to this treatment solution. Each Council was questioned as to the effectiveness and efficiency of this treatment solution. North Tipperary County Council and Offaly County Council installed their disinfection/sterilisation equipment prior to the 2003-’06 period under review so they were not asked to provide historical cost data as it would not be comparable to more recently upgraded schemes. The Councils did say that capital expenditure on these schemes were minimal with the installation of chlorinators costing less than €10,000 each. Louth and Kilkenny County Councils did have schemes completed more recently so were asked to provide cost data to assess the efficiency of this treatment solution. North Tipperary County Council North Tipperary County Council has the greatest number of such schemes but all of these schemes were upgraded prior to the 2003-’06 period under review. The Council believe that this is a sustainable treatment solution and monitor such Schemes closely to ensure that they are properly maintained. They have not encountered any problems with THMs but concede that monitoring of Group Schemes is vital. Effectiveness The 2005 EPA results for North Tipperary County Council were checked to verify if there were any exceedances of the Drinking Water Regulations water quality parameters. All of the 39 Group Schemes already upgraded using Disinfection/Sterilisation were tested and 7 exceedances were identified. 5 of these are indicator parameters but 1 exceedance related to the presence of the E.coli microbiological parameter in Fantane Group Scheme. The Council explained that there were specific problems in relation to that Scheme, which they are currently seeking to resolve and that that Group Scheme would not be representative of schemes in North Tipperary. There was also a nitrates exceedance in Ballycasey. The EPA Report for 2005 stated that the overall rate of compliance with the Drinking Water Directive in North Tipperary for both public and private group schemes was good and well above the national average (EPA 2007,p.87.). The EPA commented that North Tipperary County Council carried out no monitoring of private water supplies that supply water as part of a 130 public or commercial activity. Two Schemes were tested for THMs but there were no THM parameter exceedances. Given that only two schemes in thirty nine in North Tipperary are not compliant with the microbiological and chemical parameters of the Drinking Water Regulations, there is no evidence that the Disinfection/Sterilisation water quality treatment solution is not effective. Table 4.4.2 – North Tipperary Disinfection/Sterilisation Schemes Exceedances 2005 Water Supply Zone Date Parameter Result Units Ballycasey 1-Mar-05 Nitrate 69.3 mg/l Barnane 22-Mar-05 Colour 58 Hazen Barnane 22-Mar-05 Turbidity (at tap) 17.2 NTUs Cullenagh 28-Nov-05 Coliform Bacteria 7 No/100ml Fantane 16-Aug-05 Coliform Bacteria 19 No/100ml Fantane 16-Aug-05 E. coli 3 No/100ml Graigue Pouldine 23-Mar-05 Colour 25 Hazen Luska 22-Nov-05 Ammonium 0.43 mg/l Plunkett St,Tullaheady 28-Sep-05 Coliform Bacteria 2 No/100ml Source: 2005 EPA Drinking Water Report CD (2007) Offaly County Council Fifteen out of nineteen Group Schemes in Offaly were originally due to be upgraded with the construction of DBO treatment plants. However, this proposal did not proceed on grounds of economic viability. Therefore, it was decided to maintain the Groups’ existing disinfection/sterilisation equipment as the main water treatment system for these fifteen schemes. Effectiveness All of the 15 Group Schemes upgraded using Disinfection/Sterilisation were tested and exceedances were identified in 8 schemes, in the 2005 EPA results. 7 of these exceedances were of indicator parameters but 1 exceedance related to the presence of the E.coli microbiological parameter in Killeigh/Cloneygowan Group Scheme 131 Table 4.4.3 – Offaly Disinfection/Sterilisation Schemes Exceedances 2005 Water Supply Zone Date Parameter Result Units Aghancon G.W.S. 17-Jan-05 Coliform Bacteria 53 No/100ml Bloomhill G.W.S. 18-Oct-05 Coliform Bacteria 200 No/100ml Boher G.W.S. 19-Sep-05 Coliform Bacteria 16 No/100ml Clareen G.W.S. 22-Mar-05 Colony County at 22C 119 No/ml Clondelara G.W.S. 21-Feb-05 Iron 262 ug/l Durrow G.W.S. 3-Oct-05 Coliform Bacteria 89 No/100ml Durrow G.W.S. 22-Aug-05 Coliform Bacteria 70 No/100ml Killeigh/Cloneygowan G.W.S. 10-Jan-05 Coliform Bacteria 25 No/100ml Killeigh/Cloneygowan G.W.S. 5-Sep-05 53 No/100ml Killeigh/Cloneygowan G.W.S. 13-Jun-05 Colour 29.3 Hazen Killeigh/Cloneygowan G.W.S. 10-Jan-05 E. coli 2 No/100ml Mountlucas G.W.S. 13-Jun-05 Coliform Bacteria 16 No/100ml Mountlucas G.W.S. 5-Sep-05 16 No/100ml Coliform Bacteria Coliform Bacteria Source: 2005 EPA Drinking Water Report CD (2007) Offaly County Council explained that this E.coli exceedance was an isolated incident and was not representative of Group Schemes in Offaly. The EPA Report agreed with this stating that “the microbiological quality of the private group schemes was also good”. The EPA commented that Offaly County Council carried out no monitoring of private water supplies that supply water as part of a public or commercial activity. The EPA also commented that “compliance with the indicator parametric values in private Group Schemes was higher than that in the public water supplies through compliance with the coliform bacteria parametric value was less than satisfactory (88%) and in need of improvement (EPA 2007, p.88.) Nine Schemes in Offaly were tested for THMs are there were no exceedances of that parameter. In general though, the Disinfection/Sterilisation water quality treatment solution appears to be relatively effective in Offaly. 132 Kilkenny County Council Fifteen of the twenty five Group Schemes in Kilkenny requiring a water quality upgrade were treated using the disinfection/sterilisation solution. Only eight of these fifteen schemes were upgraded during the 2003-’06 period under review. The efficiency and effectiveness of these eight schemes are considered below. Efficiency As can be seen from the table below, the disinfection/sterilisation water treatment solution is very cheap with the treatment cost per house ranging from €40 to €595 per house. Additional network upgrade works were carried out, however, for 4 of the 8 schemes. This increased the overall cost of compliance per house to between €1,333 and €4,147 for these four schemes. It should be noted, however, that some of this network upgrade work included extensions of the network, which would not have been strictly necessary to upgrade the water quality of existing houses. The Council said that they have no ongoing current cost commitments in relation to these Group Scheme apart from the normal subsidy payment. Table 4.4.4 – Kilkenny Disinfection/Sterilisation costs Network Treatment Treatment Upgrade/ Total No. of Completion Solution Scheme Name Ballymack Cost (€) Houses Date Solution Total Cost Extension Upgrade Cost per per house Cost (€) House (€) (€) Cost (€) 68 2005 15,000 165,000 180,000 221 2,647 123 Dec-03 12,000 498,000 510,000 98 4,146 Dunmore 30 Dec-05 5,561 0 5,561 185 185 Kilree Stoneyford 32 Apr-05 16,100 0 16,100 503 503 Maddoxtown 30 Jun-05 1,200 0 1,200 40 40 Newtown Kells 42 Dec-04 25,000 125,000 150,000 595 3,571 Seskin 90 Dec-05 30,000 90,000 120,000 333 1,333 Windgap 55 Sep-04 9,160 0 9,160 167 167 Caherlesk/Coolaghmore Source: Kilkenny County Council 2007 133 Effectiveness As can be seen in Table 4.4.5 below, exceedances of the Drinking Water Regulations were recorded in 7 of the 8 Group Schemes upgraded during the 2003-’06 period. However, 3 of these schemes only exceeded the less serious indicator parameters. Of the remaining 4, Kilree Stoneyford GWS had e.coli contamination and Dunmore, Maddoxtown and Windgap all had nitrate exceedances. Kilkenny County Council have advised the Department that there were further exceedances of the nitrates parameter for Maddoxown and Dunmore in 2006 and that investment in a further nitrates treatment solution will be required in both cases. Kilree Stoneyford GWS also subsequently had both an e coli and nitrate exceedance in 2006 and Kilkenny County Council have noted that this scheme is vulnerable to pollution if chlorine dosing is not implemented properly. Table 4.4.5 – Kilkenny Disinfection/Sterilisation Schemes Exceedances 2005 Water Supply Zone Date Parameter Result Units Ballymack GWS 20-Dec-05 Coliform Bacteria 4.1 No/100ml Caherlesk-Coolaghmore GWS 14-Apr-05 Manganese 225 ug/l Dunmore GWS 21-Dec-05 Nitrate 52.36 mg/l Kilree Stoneyford GWS 12-Apr-05 Clostridium perfringens 10 No/100ml Kilree Stoneyford GWS 12-Apr-05 Coliform Bacteria 60.1 No/100ml Kilree Stoneyford GWS 12-Apr-05 E. coli 2 No/100ml Maddoxtown GWS 23-Sep-05 Clostridium perfringens 31 No/100ml Maddoxtown GWS 12-Apr-05 Coliform Bacteria 3.1 No/100ml Maddoxtown GWS 12-Apr-05 Nitrate 52.09 mg/l Maddoxtown GWS 20-Dec-05 Nitrate 56.17 mg/l Newtown Ovenstown GWS 27-Jun-05 Coliform Bacteria 27.5 No/100ml Newtown Ovenstown GWS 27-Jun-05 Coliform Bacteria 27.5 No/100ml Newtown Thomastown GWS 3-Feb-05 Coliform Bacteria 6 No/100ml Newtown Thomastown GWS 5-Apr-05 Coliform Bacteria 1 No/100ml Windgap GWS 14-Apr-05 Coliform Bacteria 8.6 No/100ml Windgap GWS 4-Apr-05 Nitrate 55.5 mg/l Windgap GWS 14-Apr-05 pH 6.29 Source: 2005 EPA Drinking Water Report CD (2007) 134 Given that four of the eight schemes (50%) upgraded using the Disinfection Sterilisation treatment solution during the 2003-’06 period are still quite clearly non-compliant with the Drinking Water Regulation’s microbiological and chemical parameters, one has to question the effectiveness of this treatment solution in Kilkenny. The Council did, however, also provide water quality test data in relation to the 7 disinfection/sterilisation schemes upgraded prior to 2003 and there were serious exceedances in only 2 of those cases (Bawnmore GWS – e.coli and nitrates and Listerlin GWS – e.coli). The EPA regards Kilkenny’s private Group Schemes’ overall compliance with the Drinking Water Regulations as being satisfactory in 2005. It noted that 7 of the 35 schemes monitored were contaminated with E.coli. This was, however, “a significant reduction in the number of schemes that were contaminated compared to 2004 when 28 of the 33 private group water schemes monitored were contaminated” (EPA 2007, p.77.). The EPA did, however, express concern that 7 schemes exceeded the Nitrate chemical parameter (an increase from 4 schemes in 2004). They stated that “this trend is worrying and must be addressed by the sanitary authority”(ibid). Kilkenny County Council have advised the Department that nitrates are their biggest problem at the moment and this will need to be addressed. One scheme was tested for THMs in Kilkenny in 2005 and was found to be compliant. Although, Kilkenny’s compliance with the Drinking Water regulations is improving, the test results of the schemes upgraded using Disinfection/Sterilisation during 2003-’06 means that a conclusion cannot be reached as to the effectiveness of this water treatment solution. . 135 Louth County Council Eight of the nine Group Schemes in Louth requiring a water quality upgrade were treated using the disinfection/sterilisation solution. Louth County Council provided expenditure data and 2006 water quality test results in relation to those eight schemes. The efficiency and effectiveness of these eight schemes are considered below. Efficiency As can be seen from the table below, the disinfection/sterilisation water treatment solution is relatively cost efficient with the treatment cost ranging from €13 to €2,026 per house. The two largest schemes Ballymakenny and Tullyallen had the cheapest treatment cost per house because of economies of scale. Additional upgrade works were carried out, however, for 5 of the 8 schemes. This increased the overall cost of compliance per house to between €861 and €6,073 for these four schemes. It should be noted, however, that three of these additional upgrades (Ballymakenny, Mountain Park and Sheepgrange) included source upgrades. The Council said that they have no ongoing current cost commitments in relation to these Group Scheme apart from the normal subsidy payment. Table 4.4.6 – Louth Disinfection/Sterilisation Scheme Costs Network/ Treatment Source* No. of Completion Solution Cost (€) Scheme Name Houses Date Total Treatment Total Cost Upgrade Upgrade Solution Cost per house Cost (€) Cost (€) per House (€) (€) 20 Mar-06 40,518 0 40,518 €2,026 2,026 547 Dec-02 7,092 *463,866 470,958 €13 861 Waterunder 56 Feb-04 23,929 52,427 76,356 €427 1,364 Grangebellew 23 Sep-05 18,713 0 18,713 €814 814 Mountain Park 32 Feb-04 17,400 *176,939 194,339 €544 6,073 Sheepgrange 40 Jun-06 37,630 *187,499 225,129 €941 5,628 Tinure 23 Nov-04 18,831 0 18,831 €819 819 189 Jun-01 6,921 116,767 123,688 €37 654 Ardaghy Ballymakenny Drybridge/ Tullyallen Source: Louth County Council 2007 136 Effectiveness Table 4.4.7 – Louth Disinfection/Sterilisation Exceedances 2005 Water Supply Zone Date Parameter Result Units Ardaghy 20-Jun-05 Coliform Bacteria 48 No/100ml Ardaghy 12-Dec-05 Coliform Bacteria 200 No/100ml Ardaghy 12-Dec-05 pH 6.2 Ballymakenny 29-Aug-05 Coliform Bacteria 1 No/100ml Ballymakenny 12-Dec-05 Coliform Bacteria 13 No/100ml Ballymakenny 12-Dec-05 Colony County at 22C 170 No/ml Ballymakenny 29-Aug-05 E. coli 1 No/100ml Drybridge/Waterunder 22-Aug-05 Coliform Bacteria 3 No/100ml Drybridge/Waterunder 12-Dec-05 Coliform Bacteria 2 No/100ml Drybridge/Waterunder 22-Aug-05 E. coli 3 No/100ml Grangebellew 25-Apr-05 Coliform Bacteria 3 No/100ml Grangebellew 12-Sep-05 Coliform Bacteria 6 No/100ml Grangebellew 12-Sep-05 Coliform Bacteria 10 No/100ml Grangebellew 3-Oct-05 Coliform Bacteria 2 No/100ml Mountain Park 12-Dec-05 Coliform Bacteria 2 No/100ml Mountain Park 12-Dec-05 E. coli 1 No/100ml Sheepgrange 4-Apr-05 Coliform Bacteria 50 No/100ml Sheepgrange 8-Dec-05 Coliform Bacteria 3 No/100ml Tullyallen 26-Sep-05 Coliform Bacteria 1 No/100ml Tullyallen 5-Dec-05 Enterococci 1 No/100ml Source: 2005 EPA Drinking Water Report CD (2007) As can be seen from Table 4.4.7 above, exceedances were recorded in 7 out of the 8 upgraded schemes during 2005 (Tinure had no exceedances). 4 of those 7 schemes exceeded microbiological parameters (e. coli and enterococci ) with the remaining 3 schemes exceeding indicator parameters. In 7 out of the 8 schemes, Louth County Council identified inadequate scouring of the pipe network as the major recontamination risk. This would seem to suggest that the problem lies in the maintenance of the pipe network by the Group Scheme rather than the effectiveness of the treatment solution itself 137 The EPA commented that Louth County Council carried out no monitoring of private water supplies that supply water as part of a public or commercial activity in 2005. It also expressed concern with the “drop in the level of compliance with the coliform bacteria parametric value from 61% in 2004 to 50% in 2005 and coliform bacteria exceedances were recorded in 8 of the 9 private group schemes monitored” (2007, p.83.) Four Schemes were tested for THMs in 2005 and no exceedances were found. Table 4.4.8 - Louth County Council Update on 2006 Water Quality Test Results Scheme Name Microbiological Indicator Exceedances Recontamination Risk Issues Total & Faecal Coliforms, pH, Absence of scour valves and Ammonia dead ends in pipe network Exceedances Ardaghy None Ballymakenny Enterococci Total & Faecal Coliforms, Iron Inadequate scouring of network Drybridge / None None Inadequate scouring of network Grangebellew None Total Coliforms Inadequate scouring of network Mountain Park None Total & Faecal Coliforms, Inadequate scouring of network Waterunder Clostridia Perfrigens Sheepgrange None Total Coliforms Inadequate scouring of network Tinure None Total Coliforms Inadequate scouring of network Tullyallen None Total Coliforms None Source: Louth County Council 2007 In the 2006 water quality test results provided by Louth County Council in Table 4.4.8 above, 7 of the 8 schemes had exceedances. It is notable that Tinure had an indicator exceedance in 2006 even though it was fully compliant in 2005. Drybridge/Waterunder had no exceedances in the 4 samples taken during 2006 even though it had an E.coli exceedance in 2005. Ballymakenny had the only microbiological exceedance (Enterococci) in 2006 with the other 6 schemes reporting indicator exceedances. The evidence of the 2005 and 2006 water quality test results for the completed Disinfection/Sterilisation schemes in Louth would suggest that this solution has not been successful in sustainably ensuring compliance with the Drinking Water Regulations. However, the fault appears to lie more in the maintenance of the pipe 138 network by Group Scheme volunteers rather than the robustness of the solution itself. Louth County Council have advised the Department that they are currently meeting with Group Water Scheme representatives in relation to the implications of the 2007 Drinking Water Regulations and the need for proper operation and maintenance of Group Schemes. Conclusions Disinfection/Sterilisation appears to be a very cost efficient water treatment solution, where the chemistry of the water permits it. However, the evidence of the Kilkenny and Louth water quality test results on upgraded schemes casts a question mark over its sustainable effectiveness. This is a matter for concern given that it is the water quality upgrade solution selected for 122 Group Schemes (17% of the total). On the other hand, the positive test results for the North Tipperary and Offaly schemes appear to indicate its effectiveness. The explanation seems to be that the problem lies in the operation of the water treatment solution by individual Group Schemes themselves rather than necessarily in the solution itself. The Disinfection/ Sterilisation solution (and the non-DBO solution on a far smaller scale) are the only water quality upgrade solutions, where responsibility for water treatment remains with Group Scheme volunteers rather than professional technicians. The Department has tried to encourage such Group Schemes to engage professional O&M contractors for this role by offering a higher rate of domestic subsidy (€196.81 per house) for this purpose rather than the basic €101.58 per house subsidy. However, the local authority questionnaire returns (Q26) suggest that this higher rate of subsidy is not being claimed by Group Schemes. See domestic subsidy section of this chapter. The Disinfection/Sterilisation solution is in practice the pre-existing treatment solution for many Group Schemes, which has been kept in place. It is attractive to Group Schemes as it is cheap to operate and has minimal local authority involvement so the issue of local authority or DBO plant water charges is non-existent. However, the status quo is unsustainable if many of these Group Schemes continue to fail to comply with the Drinking Water Regulations. At a minimum, local authorities must require Group Scheme members in non-compliant schemes to participate in training programmes being run by the Water Services National Training Group (WSNTG) or otherwise face prosecution for non-compliance with the Regulations. In some cases, disinfection/sterilisation is only an interim solution as it only deals with 139 microbiological contamination. Therefore, it will eventually be superceded on some Group Schemes by a more robust solution such as a DBO treatment plant. The data examined shows no problems with THM exceedances but the statutory monitoring requirements for this particular parameter, under the Drinking Water Regulations, are not as onerous as for other parameters. Therefore, while there were no exceedances of THMs identified for the above 4 counties, the proportion of schemes tested for THMs was quite small. It might be prudent for local authorities to increase the level of testing for THMs for Disinfection/ Sterilisation schemes, given the possible carcinogenic risk factors. Finally, the issue of source protection was raised in the context of Kilkenny, where there is a problem of nitrate contamination of groundwater sources. North Tipperary also mentioned the need for aquifer protection measures to protect their Group Schemes’ groundwater sources. As stated in the introduction, the use of the minimal disinfection/sterilisation treatment is limited to Group Schemes where the raw water quality is quite high. If the quality of the source water declines due to pollution of the source, the solution becomes ineffective and more robust DBO treatment plants may need to be built in outlying locations, if connection to the public mains is not technically feasible. The Department issued guidance to local authorities on 31st July 2003 in relation to groundwater protection plans and the need to link them to County Development Plans. It also suggests the creation of ‘Source Protection Areas’ around groundwater drinking water sources (Circular SP 5/03). However, only a limited number of local authorities have adopted groundwater protection plans. There is already a surface water source pilot protection project underway in Monaghan. The Department should perhaps consider similar ‘low tech’ pilot approaches to source protection of groundwater, where the water is only receiving minimal disinfection /sterilisation treatment. 140 Comparison of relative cost efficiency of Water Quality Upgrade Solutions The relative efficiency of different water quality upgrade solutions is difficult to measure as they are very varied in nature and as such reliable and meaningful comparisons are harder to make. However, as grants are made on a cost per house basis, the relative cost of a number of schemes from each upgrade solution are compared in Table 4.5.1 below. The DBO schemes are part of the West Cavan and Mayo No. 1 DBO bundles. The upgraded Group Schemes have been listed in ascending cost per house order with pipe network costs excluded. In many respects, the exercise below bears out the conclusions of the previous two recent reviews of the Water Sector discussed in the Literature Review i.e. 2002 Expenditure Review and 2006 Fitzpatrick Associates NDP Review. It is actually very difficult to make meaningful cost comparisons as individual water projects are by their nature unique. A “distinct feature of the sector, which has very direct relevance to any evaluation that addresses value-for-money issues, is that water infrastructure and plant is designed on a quite bespoke basis for particular locations. In practice this makes benchmarking and cost comparisons across projects and locations even within Ireland, never mind internationally, difficult.” (Fitzpatrick Associates 2005, p.6.) As can be seen from the table below, there are wide variations in the cost per house of Schemes upgraded under the same solution never mind different solutions. That said, certain patterns can be discerned. Generally, the disinfection/sterilisation solution is by far the cheapest solution in cost per house terms and the DBO treatment plant solution is the most expensive. Some of the DBO plants appear to have lower cost per houses, which could be as a result of the economies of scale of the size of the schemes or the size of the overall DBO Bundle. It must be remembered, though, that the DBO figures are provisional due to the current lack of final accounts as these Schemes are only just completed. Therefore, it is likely that the cost per house for DBO Schemes are actually understated as there are outstanding Design Build costs yet to be included. Additional pipe network upgrade costs have been excluded from the figures below for all solutions, as their inclusion would seriously distort the exercise due to the widely differing densities of the areas served by individual Schemes. 141 Relative cost efficiency of Water Quality Upgrade Solutions (Table 4.5.1) No. of Cost per Scheme Name Solution Type Houses Cost (€) House Ballymakenny Disinfection 547 7,092 €13 Tullyallen Disinfection 189 6,921 €37 Maddoxtown Disinfection 30 €1,200 €40 Caherlesk/Coolaghmore Disinfection 123 €12,000 €98 Windgap Disinfection 55 €9,160 €167 Cloonminda Takeover 54 €10,000 €185 Dunmore Disinfection 30 €5,561 €185 Ballymack Disinfection 68 €15,000 €221 Seskin Disinfection 90 €30,000 €333 Cloonmore No. 1/Killilane CTPM 73 €25,200 €345 Bohola DBO 574 €243,201 €424 Drybridge/ Waterunder Disinfection 56 23,929 €427 Kilree Stoneyford Disinfection 32 €16,100 €503 Mountain Park Disinfection 32 17,400 €544 Newtown Kells Disinfection 42 €25,000 €595 Bekan CTPM 146 €100,000 €685 Grangebellew Disinfection 23 18,713 €814 Tinure Disinfection 23 18,831 €819 Sheepgrange Disinfection 40 37,630 €941 Kilkerly Takeover 46 €67,166 €1,460 Glencorrib DBO 337 €516,317 €1,532 Kilmovee DBO 523 €803,221 €1,536 Fahy Drumindoo DBO 652 €1,110,293 €1,703 Adamstown Non-DBO 3 €5,303 €1,768 Belderrig DBO 55 €105,132 €1,911 Ballyglass/Carnacon DBO 366 €731,109 €1,998 Ardaghy Disinfection 20 40,518 €2,026 Lough Mask Creevagh DBO 325 €675,623 €2,079 Kilmeena DBO 320 €668,784 €2,090 Claren/Knocklehard Non-DBO 232 €508,489 €2,192 Ballycroy DBO 325 €750,404 €2,309 Ballagh/ Cahersherkin CTPM 170 €411,214 €2,419 Corraleehan CTPM 268 €653,759 €2,439 Killeen DBO 208 €552,261 €2,655 Milltown DBO 312 €989,837 €3,173 Glenhest DBO 146 €481,465 €3,298 Kildallan DBO 230 €776,705 €3,377 Brackloon/Spaddagh DBO 150 €628,843 €4,192 Laghta DBO 98 €513,039 €5,235 Cappanlea Non-DBO 7 €37,000 €5,286 Ballymagovern/Corran DBO 115 €609,185 €5,297 Glangevlin DBO 145 €837,130 €5,773 Source: Local Authority and DBO Client Representative data – January 2007 142 Network Upgrades and Leakage Control Introduction It has been very noticeable from the examination of the various case studies that the cost of network upgrades in many cases was equivalent to or exceeded the actual water quality upgrade solution. In fact, expenditure under the network upgrade measure of €105 million during the 2003-’06 Action Plan period was second only to capital expenditure on DBO projects. It is important, therefore, to consider the value for money of this area of expenditure. Expenditure trends and implementation As can be seen from the table below, while 64% of the pipe network upgrades were carried out on privately sourced Group Schemes, 36% of upgrades were for publicly sourced schemes. It is also noticeable that 23% of the network upgrades were unrelated to water quality upgrade works. No. of Group Schemes receiving network upgrades 2003-‘06 Group Scheme pipe network upgrades Private Water Supply Public Water Supply Total Unrelated to water quality upgrades 2003 2004 2005 2006 Total % 73 44 117 25 76 46 122 29 57 39 96 24 72 28 100 23 278 157 435 101 64% 36% 100% 23% Source: Local Authority Questionnaires (Q25) – January 2007 Network upgrade data from the previous case studies of the different treatment solutions are compiled in the table below in ascending cost per house order. The table shows that there is no relationship between treatment solutions and the cost per house of network upgrades. The use of cost per house to compare distribution networks unit cost is virtually meaningless as the housing density pattern is unique from Group Scheme to Group Scheme. What this table does show, however, is that network upgrades are quite costly so ensuring value for money is vital. 143 Group Water Scheme Name Solution Type Tullyallen Disinfection Cloonmore No. 1/Killilane CTPM Network Upgrade/ Extension Cost (€) No. of Houses Network Upgrade Cost per house (€) 189 €116,767 €618 73 €59,850 €820 Ballymakenny Disinfection 547 €463,866 €848 Drybridge/ Waterunder Disinfection 56 €52,427 €936 Seskin Disinfection 90 90,000 €1,000 Erne Valley DBO 1,011 €1,520,000 €1,503 Lavagh/Ballyheelan Ballymack DBO Disinfection 369 €650,000 €1,762 68 165,000 €2,426 Newtown Kells Disinfection 42 125,000 €2,976 Bekan CTPM 146 €548,653 €3,758 Crossdoney GWS DBO 255 €1,010,000 €3,961 Caherlesk/Coolaghmore Disinfection 123 498,000 €4,049 Cloonminda Takeover 54 €227,032 €4,204 Cappanlea Non-DBO 7 €30,500 €4,357 Carrowmeena CTPM 47 €215,975 €4,595 Corraleehan CTPM 268 €1,234,405 €4,606 Sheepgrange Disinfection 40 €187,499 €4,687 Mountain Park Disinfection 32 €176,939 €5,529 Ballagh/ Cahersherkin CTPM 170 €985,850 €5,799 Claren/Knocklehard Non-DBO 232 €1,378,030 €5,940 Kilcredan Non-DBO 54 €354,758 €6,570 Objectives of network upgrades It is important to first remember that this was the original Group Schemes capital funding measure, prior to the focus on water quality. Funds were used to build new Group Water Scheme pipe networks to abstract raw water and transfer it to households. This funding measure was also used to upgrade the pipe networks of existing Group Schemes. Since 2006, new Schemes and scheme extensions have been funded under a separate capital measure. The need to comply with the Drinking Water Regulations has given the network upgrade measure an even greater significance. Although, network upgrades have nothing to do with water 144 treatment, they do play an important role in water quality upgrade solutions namely leakage reduction and avoiding water recontamination. Raw water re-contamination Under all treatment solutions, the treated water is distributed from the Group Scheme or County Council treatment facility to households via the Group Scheme pipe network. If, however, there are any leaks or breaks in the pipe network, this can cause infiltration of the water in the pipe network with external contaminants. Therefore, expenditure on treating the water would be wasted as the water is re-infected in a sub-standard pipe network. In such cases, it is necessary to repair or replace the sub-standard sections of pipe in order to remove the risk of re-infection. Unaccounted for Water (UFW)/Leakage As was already discussed in the DBO section, water leakage or Unaccounted for Water (UFW) is a major issue in the Group Scheme sector. Studies, such as the Mayo No. 2 Leakage Control Strategy, have shown that bursts and leakage represent the single largest component of Unaccounted for Water (March 2005, p.5). DBO treatment plants are built with an allowance for 25% UFW. That means that 25% of the water coming out of the treatment facility is lost through leaks and wastage in the pipe network. However, as has been seen, the majority of Group Schemes have UFW well in excess of 25% and would not be able to supply adequate levels of treated water to Group Scheme without eating into their additional development design capacity for 2020. This is unsustainable for Group Schemes from a development and economic perspective. If the Group Schemes are already using up their water allowance for additional development to meet existing water demand , then that development will not be able to take place as there will be inadequate water supply due to excessive leakage. More importantly, from the perspective of existing Group Scheme members, this level of water wastage is financially untenable. The DBO plant operator charges for all the water that is treated and piped out to Group Scheme networks. If 50% of that treated water is lost in the pipe network, that is Group Schemes’ problem not the DBO operators as their responsibility ends once the water enters the Group Schemes’ pipe network. In many cases, the DBO plant 145 operation and maintenance (O&M) charge bills are only now issuing to Group Schemes for the first time. Several of the DBO Client Representatives have predicted that many Group Schemes with high UFW/leakage levels will get a shock when they receive their first bills from their DBO operator. Similarly, if a Group Scheme is receiving water from a public water supply, the Council charge them for all water supplied to the Group Scheme, although allow for 25% UFW. Any UFW in excess of 25% has to be paid for by the Group Scheme. A 25% UFW allowance may appear quite high but “it is unrealistic to expect any buried system to be leak free due to the many factors affecting the system” (Mayo Bundle 2 Leakage Control Strategy – March 2005, p.8.). Implications for the State It could be argued that high UFW and the consequent level of DBO O&M charges or Council water charges are a matter for Group Schemes rather than the State. However, all Group Schemes domestic consumers receive an annual subsidy from the State towards the O&M cost of being supplied with treated water. If the DBO O&M costs or County Council water charges become too high due to excessive leakage in Group Scheme networks, Group Scheme members will inevitably look to the State and taxpayer to provide higher subsidies. UFW is also a major issue on public schemes but is not a major political issue as domestic consumers are not paying directly for water services, which are funded through central taxation. As it happens, “a €118m [public] project to repair and replace over €280km (174 miles) of leaky water pipes in the Dublin region , saving 20 million litres of water per day, is to get under way this summer” (Irish Times, 26th March 2007). In some cases, the level of UFW could be so high that a treatment plant could not be brought into operation as it would not be able to treat sufficient water to supply the Group Scheme, even using up its additional development capacity. In such cases, untreated water would have to continue to be abstracted from sub-standard existing sources. So there would be a major problem of security of supply and the environmental cost of over-abstraction of water. Therefore, the State would have built an expensive treatment plant, which could not be used. The Department has addressed this issue by approving Advance DBO works, where critical mains are replaced in cases where the level of leakages and bursts are too high to allow a treatment plant to become operational. This is now a separate capital measure to network 146 upgrades. The Department has allocated €35 million towards Advance DBO works over 2005-’06. As already discussed in the DBO section, the Leakage Control Studies carried out for Mayo and Galway by Ryan Hanley consultants provided clear evidence that leakage control is more economical than adding plant design capacity (Mayo DBO Bundle No. 2 – Leakage Control Strategy-March 2005). There are also clear environmental benefits from reducing UFW through leakage control. “Excessive abstraction of water may impact on the natural environment if it exceeds limits necessary for compensatory flows to sustain the environment affected by the source e.g. fish, flora, fauna. Excessive abstraction is also wasteful of scarce resources such as energy and materials” used in abstracting and treating wasted water (ibid, p.11). There are also clear potential savings for Group Scheme households from leakage control. In the table below, Ryan Hanley calculate major savings in annual O&M costs for households by reducing UFW to 20% for each of the Group Schemes below. Mayo Bundle No. 1 – Potential Leakage Control Savings Scheme Name Potential 20% No. of houses Potential Annual UFW Target O&M Savings per Saving (€) House (€) Ballycroy €17,575 300 €59 Ballyglass/Carnacon €27,905 366 €76 Killeen €9,344 201 €46 Laughta €4,221 77 €55 Glencorrib €45,553 394 €14 Bohola €8,176 574 €14 Lough Mask/Creevagh €8,176 303 €27 Source: Ryan Hanley Consultants – March 2007 Location of Leakage and Metering The location of leakage in a pipe network is a very important issue from the perspective of paying for the leaking water and paying for its repair. If the leak is on the consumer’s 147 premises they pay for the leakage costs but if it is in the Group distribution system or cannot be located, all Scheme members pay for it (Ardrahan Leakage Control Study 2006, p.9.). Leakage Control studies carried out, as part of the Galway DBO Bundle No. 1, showed that in some cases leakages are occurring excessively on either the consumer or the distribution side. The studies were able to measure the source of water leakage on these schemes by methodically isolating sections of the pipe networks using district meters and sluice valves and measuring the water loss (Ardrahan Leakage Control Study 2006, p.10.). The Department’s Inspectorate’s view based on experience to date of a broader range of schemes, is that water leakage/UFW is occurring predominantly on the consumer’s side of the meter. Scheme Name Distribution leakage Consumer leakage Ardrahan 63% 37% Rinn Killeeneen 13% 86% Source: Galway DBO Bundle No. 1 – Leakage Control Studies 2006 There is, therefore, a strong financial incentive for Group Scheme members to have individual metering of their connections particularly if they are required to contribute towards the payment of large UFW bills to the DBO operator as part of their O&M charge. “The installation of consumer meters should lead to a significant reduction in waste, as many consumers will be unaware of what is a normal consumption for their premises should be. The fact remains that without metering there is no incentive to conserve water and minimise waste” (Mayo DBO Bundle No. 2 – Leakage Control Strategy-March 2005,p.13.). The current position is that the Department 85% grant aids meters for domestic connections on bundled DBO projects up to a maximum grant of €300 per domestic connection. Metering on DBOs is recommended but not compulsory. These grants can be claimed under the network upgrade measure. “In accordance with the Polluter Pays Principle, capital grants may not be paid in respect of the provision of meters on non-domestic connections” (Circular L11/2004). There is no grant aid available for metering under any of the other treatment solutions. Metering is only funded on DBO bundles due to the high O&M costs to consumers from high unidentified UFW levels. 148 Leakage repair cost – Efficiency and Effectiveness issues The location of leakage is also vitally important from the perspective of repairing it in the most cost effective manner. As already stated, it is clear from the examination of case studies for each water quality upgrade solution that the cost of pipe networks network upgrades in many cases was equivalent to or exceeded the actual water quality upgrade solution. While the necessity of addressing leakages through network upgrades has already been considered at length, it is important to ensure that network upgrade funds are being invested in the most effective and cost efficient manner. In several cases, the whole pipe network was completely replaced as part of the network upgrade works. In many cases, this may have been necessary if the existing pipe work was originally badly laid or the pipe work had so badly deteriorated that re-contamination of water or constant bursts were likely to occur. There is anecdotal evidence, however, that some network upgrades were carried out without an evidenced based investigation of where the main leakage problems in the network were located. A methodical leakage control study as outlined above for Galway DBO Bundle No. 1 would ensure that only those parts of the network, where leakages are definitely occurring, would need to be replaced. There is also the issue of ensuring that the new pipe network is adequate for meeting future hydraulic demand needs to avoid expensive pipe replacement works at a later date. Because of their experience in leakage control studies, Ryan Hanley were asked to comment on the best way to ensure value for money in pipe network investment (Ryan Hanley Submission, 14th March 2007 – Appendix 8). Ryan Hanley agreed with the current Department policy of approving advance funding for the replacement of critical mains, with clearly identified frequent bursts, prior to the start of DBO works. These Advance DBO works should ideally include the installation of metering and water conservation infrastructure. In the case of further network upgrades on DBOs or for the other water quality upgrade solutions, a leakage control study should be carried along the lines outlined above to ensure that the source of the leakage is scientifically verified. “This study will serve two purposes namely the identification of remaining network sections with excessive leakage together with the names and location of consumers which are excessively wasting water the on site hands on training of GWS personnel in the active leakage management” 149 Ryan Hanley also advised that “The design and construction of such rehabilitation works should be undertaken only on the basis of full knowledge of the condition and performance of the existing network and with a view to the future requirements for upgrading necessary to distribute the 2025 daily demand + 25%. It is recommended that such rehabilitation works should be sized using a hydraulic model distributing above future design daily demands”. The Department’s view is that is longstanding practice that local authorities should ensure that network upgrades should only take place based on evidence based studies of leakage problems and that such works should be properly hydraulically assessed. The Department pointed to Circular L7/96 and the accompanying manual “Water Distribution Network Management and Leakage Control” which provides guidance on “how to estimate UFW and how to reduce leakage in a distribution network. If a comprehensive water audit has not been carried out already, a preliminary audit should be carried out if it is suspected that the proportion of UFW may be significant.” (Guidance Document for the preparation of a Rural Water Strategic Plan, June 1999, p.2.5). The Department do concede, however, that as the Rural Water Programme is a devolved local authority function, it is possible that in some cases network upgrades may have occurred in the absence of such studies, as it is not the Department’s role to verify this. Conclusions It seems clear from the above that the current levels of UFW, on Group Schemes, are unsustainable from both an economic and environmental perspective. It has been proved that investment in network upgrades makes good economic sense to reduce UFW and also to remove the risk of recontamination of water in the network. “Future levels of unaccounted for water in existing distribution networks are dependent on both operational practises and investment in rehabilitation of the network. In the event that no action is taken, there would be a progressive increase in unaccounted for water over time” (Mayo Bundle No. 2 Leakage Control Study-March 2005, p.6.) 150 It is also important however, that such upgrades are carried out in the most effective and cost efficient manner. Network upgrade costs exceeded the actual treatment solution costs in many of the water quality projects already examined in this chapter. The National Federation of Group Water Schemes (NFGWS) has also predicted that the replacement of sub-standard network will be the next big infrastructural challenge facing the rural water sector (Appendix 3). It is, therefore, recommended that revised guidance be issued to Councils in relation to approving network upgrades. Such upgrades should only take place based on the results of a methodical leakage control study. In addition, where substantial network upgrades are being proposed, a hydraulic study should be carried out to ensure that the proposed upgrade will meet the future requirements for 2025 demand+25% UFW. Finally, it is vital that universal metering of all Group Water Schemes being upgraded under the Rural Water Programme be considered as there is no incentive to conserve water or minimise waste without it. The National Federation of Group Water Schemes (NFGWS) has expressed support for such an initiative (Appendix 3). Quite apart from being a charging tool, meters are more importantly a vital management tool for operating water distribution systems and identifying the precise location of water leakages. Without such management information, it is comparable to “attempting to run a national electricity grid without electricity meters” (NDP Evaluation of Water Services 2005, p. 153.) 151 Rural Water Subsidy Introduction The annual Rural Water Subsidy is the only contribution that the State makes towards the domestic operational and maintenance (O&M) costs of running Group Water Schemes. It is important to emphasise that this grant subsidises the water costs of domestic households only and that there is no subsidy for non-domestic water consumers such as farms and other commercial operations. Originally, the subsidy mainly covered the O&M costs of maintaining pipe networks but in recent years, most of the O&M costs have related to water treatment costs. Annual expenditure under the domestic subsidy scheme (€8 million in 2006) is relatively low by comparison to the capital works programme. However, the subsidy is an ongoing cost to the taxpayer that will continue after capital works have been completed so it is important that this area of expenditure is examined. Also, there are increasing demands from the Group Schemes’ sector for subsidy rates to be increased due to increased O&M costs on Group Schemes since the subsidy was last increased in 2000 (Rural Water News, Spring 2006). Evolution of the Group Water Scheme Subsidy In 1997, the Government abolished public water charges for domestic users and instead funded the current cost of supplying treated water through the Local Government Fund (LGF). In the interests of equity, the Government also introduced a subsidy payment to Group Scheme households to cover the operating cost of providing for their domestic water needs. This subsidy is also funded through the Local Government Fund. The original 1997 subsidy rates were £75 (€95.23) for each house supplied from a private source, and £35 (€44.44) for each house supplied from a local authority source. The Minister increased the subsidy rates to their current level on 28th March 2000. Current Subsidy levels The subsidy is paid directly by local authorities to Group Schemes on the basis of expenditure on the domestic element of the Schemes’ operational costs. The current subsidy levels are 100% of the qualifying expenditure as approved by the local authority, subject to a limit of: €50.79 for each house in a Group Scheme supplied from a local authority source. In this case, householders receive up to 50,000 gallons of treated water from the Council 152 for free so there are no treatment O&M costs. The €50.79 per house subsidy rate is for the O&M of the pipe network only. € 101.58 for each house in a Group Scheme supplied from a private source, where the Scheme members are responsible for the O&M of both the water treatment facilities and the pipe network. €196.81 for each house in a Group Scheme where water disinfection and/or treatment is provided under a Design, Build, Operate (DBO) contract or where the water disinfection/treatment plant is operated and maintained by a contractor by way of a bona fide Operational and Maintenance Contract. This higher rate is paid in recognition of the additional costs involved in paying for a professional water treatment service and also to incentivise Group Schemes to avail of such professional services to guarantee drinking water supplies of adequate quality. This grant also subsidises the O&M of the pipe network. Subsidy Expenditure trends As can be seen from the table below, annual current expenditure under the domestic subsidy scheme is quite small relative to the capital expenditure measures for water treatment and network upgrades. However, it must be remembered that this is an ongoing annual cost to the taxpayer unlike capital investment in treatment plants with a 20 year design life. It is noticeable, therefore, that there has been a 50% increase in annual expenditure under the domestic subsidy scheme between 2003 and 2006. Expenditure on Domestic Subsidy 2003-‘06 Expenditure (€ million) 2003 2004 2005 2006 Domestic Household Subsidy 5.305 5.276 7.141 7.957 Source: Department of the Environment, Heritage and Local Government It is likely that this increase in overall subsidy expenditure is due to the increasing number of Group Water Schemes in receipt of the higher €196.81 per house subsidy rate, where water treatment is provided under a Design, Build, Operate (DBO) contract. Councils also permit Group Schemes to make back subsidy claims for several years, in recognition of their limited 153 voluntary administrative resources. This back claim facility can cause annual expenditure figures to fluctuate from year to year. The number of Group Water Schemes claiming the annual subsidy, under the different categories, is set out in the table below Number of Group Water Scheme claims per subsidy category No. of Group Water Schemes claiming Subsidy 2003 2004 2005 2006 Public GWS Subsidy (€50.79 per house max.) Private DBO Subsidy (€196.81 per house max.) Private Non-DBO subsidy (€101.58 per house max.) Total 128 23 520 671 130 24 518 672 111 27 467 605 82 33 316 431 Source: Q. 26. Compiled from Local Authority Questionnaire Returns 2007 Administration of the Subsidy Scheme Councils pay the domestic subsidy to individual Group Schemes on foot of claims with supporting documentation, verifying their O&M expenditure. Councils receive an annual subsidy allocation from the Department, which is recouped throughout the year. The Department has issued an Explanatory Memorandum to Councils, which provides guidance on the operation of subsidy scheme. The Memorandum states that “Where water supplied by a Group Scheme for non-domestic purposes is metered, expenditure should be apportioned by reference to metered usage. In cases where usage is not metered , operational expenditure may be apportioned on the basis of a standard allowance of 50,000 gallons per house per year. Group are also permitted, as an interim measure to apportion usage on the basis of the ratio of the number of domestic to non-domestic connections. For the purposes of apportioning costs and the more effective application of the polluter pays principle, local authorities may require that supplies of water for non-domestic purposes be metered” (Department for the Environment, Heritage and Local Government 2002, p.6.) Rural Water Liaison Officers were asked how they, in practice, distinguish the domestic from the non-domestic element of O&M expenditure in order to recoup the appropriate subsidy to the Group Scheme. Council responded that they generally apportion the O&M costs based on the proportion of non-domestic connections on the Group Scheme. This apportionment approach is quite rough and does not relate to actual water usage. It is possible, therefore, that 154 some non-domestic Group Scheme members may be relatively heavy water users and may use up a disproportionate amount of treated water. This could result in domestic users and potentially the State subsiding non-domestic water users. This problem could be overcome with the use of metered data on actual water usage for calculating subsidy payments but this is not currently possible in many cases due to a lack of metering on many Group Schemes. Case for subsidy increase As already stated, there have been growing calls from the Group Schemes’ sector for increases in the State subsidy in recent years. At its 2006 Annual Delegate Conference, “the Board of the National Federation of Group Water Schemes (NFGWS) has been mandated to secure a subsidy review that reflects the massively increased costs on group water schemes since 2000, the last occasion on which subsidies were reviewed” (Rural Water News, Spring 2006, p.1.). It is certainly true that subsidy levels have fallen in real terms since 2000, as there have been no increases to allow for inflation. There is also evidence from the early O&M data available for the recently completed DBO treatment plants that the O&M charges per house frequently exceed the €196.81 per house maximum subsidy level. More definitive operational and maintenance data is required to confirm this. This annual domestic subsidy is supposed to cover both water treatment and pipe network management costs. If all the subsidy is spent on water treatment, there are no funds remaining for management of the pipe network. This study has already identified that poor maintenance of pipe networks by Group Scheme volunteers creates a risk of re-infection of water in the pipe network. The NFGWS is seeking to “secure an increase in subsidy support that takes into account two factors: 1. the cost associated with water treatment and 2. management costs” (NFGWS Strategic Plan 2006-’08, p.9.). The NFGWS is also calling for paid managers and staff to operate Group Schemes on a part-time or full time basis (Rural Water News-Autumn 2006, p.1.). The NFGWS certainly have a case for requesting a subsidy review but there are a number of issues that the Department must consider in carrying out such a Review. Cost Issues for Department This Review has already identified certain issues impacting on the O&M costs of Group Schemes. 155 There is evidence of significant non-domestic water usage by Group Water Schemes based on the number of connections and water usage data (see Appendix 6). However, metered water usage is often not used in calculating Group Scheme subsidies. It is possible that there could be cross-subsidisation of non-domestic water usage through the domestic subsidy. There are already high levels of leakage/UFW on Group Schemes, which are pushing up O&M costs for domestic and non-domestic users. The Department could not possibly justify subsiding UFW in excess of the 25% guidelines through increased domestic subsidies. Policy objectives Two of the eligibility conditions for the Group Scheme subsidy are that it is providing a supply of water for domestic purposes that in the opinion of the local authority, is satisfactory, and that water conservation measures are being actively implemented. It is not clear how strictly these conditions are currently being enforced. It appears that many Councils have not been overly rigorous in enforcing these conditions because of the need to win Group Scheme’s co-operation in upgrading their water supplies. This is regarded as a pragmatic approach as some Group Schemes have simply withdrawn from claiming subsidy as they have no interest in upgrading their water supplies. Some Councils, on the other hand, do not pay subsidies to Group Schemes that are not co-operating with the Rural Water Programme. Another of the eligibility conditions for receiving subsidy is that Group Schemes must adopt the Charter of Rights and Responsibilities for Consumers on Group Water Schemes compiled by the National Rural Water Monitoring Committee (NRWMC) in 2002. “The European Commission is concerned that individual group scheme consumers should have access to a transparent and practical means of having genuine complaints listened to and acted upon by those responsible for their water supply. The Charter of Rights is seen as a guarantee of consumer rights in this regard” (NRWMC 2004, p.9). Anecdotal evidence would suggest that the Charter of Rights is not always being actively implemented across the Group Scheme sector. Some Councils have expressed the view that domestic consumers are subsidising the cost of water usage by non-domestic consumers on Group Schemes. As the domestic subsidy 156 is being paid to the Group Scheme rather than individual householders, local authorities must ensure that there is transparency in how Group Schemes operate and that the domestic consumers benefit solely and fully from the domestic subsidy. The major policy focus, at the moment, is on ‘end of pipe’ solutions to tackling drinking water quality. In other words, treating the water after it has become contaminated. There is a growing consensus on the need to “move beyond the present focus on end-of-pipe solutions to providing sustainable quality water supplies through an increasing emphasis on source protection and water conservation” (NFGWS 2006, p.1.). In other words, focusing on prevention rather than cure. Several Councils already offer guidance to Group Schemes on best practice in relation to source protection and the ongoing National Pilot Source Protection Study in Churchill/Oram, Co. Monaghan is likely to propose some practical source protection measures. Some Councils have suggested, in their questionnaire responses, that subsidy payments should only be paid to Group Schemes, which have active source protection measures in place. The NRWMC’s Charter of Rights contains a section on source protection and states that “It is the responsibility of suppliers of drinking water to protect drinking water sources and to take necessary preventative and /or remedial action as appropriate. The public generally, and in particular consumers of a local supply, should be aware of the risks of contamination and should act to protect drinking water sources.” (NRWMC 2004, Appendix 1, p.25.) Conclusion The subsidy is a relatively small component of the Department’s budget for the Rural Water Programme. However, it is an ongoing current cost commitment so it is important to implement safeguards to ensure that the funding is used solely for the purposes intended i.e. domestic water users only. Preliminary DBO O&M treatment cost data and the need for a more professionalised approach to pipe network maintenance suggest that the Group Scheme sector have a case for seeking a review of current subsidy rates. However, any decision to increase rates must be based on a rigorous study of metered water usage data to ensure that the Department does not in any way subsidise non-domestic water consumption or UFW leakage levels in excess of the 25% limit. It is accepted that this may pose difficulties as many Group Schemes are not metered and the Department only grant aids individual domestic 157 connections on DBO schemes. County Councils must also ensure that the achievement of policy objectives such water conservation, water quality and transparency for Group Water Scheme members, as already required under the existing subsidy scheme, are being implemented by Group Schemes. There is also a need to link the payment of subsidies to the active implementation of source protection measures by Group Schemes to protect their drinking water sources from contamination. 158 New Group Schemes Given the level of capital expenditure that has been invested in ‘end of pipe’ treatment solutions for substandard Group Schemes over the 2003-’06 period, it is vital to ensure that this problem does not recur. The principle of prevention rather than cure has to come to the fore. The first question that needs to be asked is whether any more new Group Schemes should be funded. In fact, given that the State will be legally accountable for any Group Schemes falling within the criteria of the Drinking Water Regulations, it has to be questioned whether any new Group Schemes should be permitted under the new statutory licensing system. The first thing to do is to consider what has been happening under the New Schemes measures during the 2003-’06 period. Up to 2006, new schemes were not in fact a distinct spending measure so Councils simply funded new schemes from the Upgrade measure. In 2006, the Department allocated €9 million funding for new Schemes as a separate measure from an overall budget of €113 million i.e. 8% of overall funding. There is, however, no separate expenditure outturn figure available for 2006 as it is still recorded as part of the overall 2006 Upgrade expenditure figure of €29 million. Implementation of New Schemes Councils were asked to provide details on new Schemes built in the table below. It should be borne in mind that many of these schemes are quite small and will not be required to meet the criteria of the Drinking Water Directive. No. of new Group Water Schemes constructed 2003-‘06 New Group Water Schemes 2003 2004 2005 2006 Total % Private Water Supply 71 44 30 27 172 28% Public Water Supply 131 118 101 88 438 72% Total 202 162 131 115 610 100% constructed Source: Q.23 on Local Authority Questionnaire Returns 2007 The Questionnaire data indicates that 72% of the 610 new schemes constructed during the 2003-’06 period, were built with a connection to the public water supply. The number of new Group Schemes built with private water sources declined each year. This is a very 159 encouraging sign as the EPA has identified Group Schemes with private sources as being the main risk factor for water quality problems. No. of existing Group Water Schemes extended 2003-‘06 Group Water Schemes 2003 2004 2005 2006 Total % Private Water Supply 15 19 13 21 68 63% Public Water Supply 10 15 7 8 40 37% Total 25 34 20 29 108 100% extended Source: Q.24 on Local Authority Questionnaire Returns 2007 Only 108 Group Schemes were extended in size over the 2000-’06 period but worryingly 63% of these were served by a private water source. If any new or extended scheme grows to beyond 15 houses or connects in to a premises with a public or commercial function e.g. dairy farm, then the water quality must comply with the parameters of the Drinking Water Regulations and water treatment upgrades may be required. Alternative approaches to privately sourced Group Schemes That said, one has to also consider the alternative to privately sourced Group Schemes. As already stated, the preference would be to have all communities absorbed or connected into the public mains. However, that is not economically viable for many existing small and geographically remote communities. The only alternative for many of these schemes is to either abstract water from a surface supply or more usually to drill a well. Wells do not come within the remit of the Drinking Water Directive so there is little liability for the State for their water quality. However, excessive wells do have environmental impacts and increase the risk of contamination. Therefore, the Department’s long standing principle has been to only to make well grants where there is no local Group Scheme for a house to connect to. It would seem, therefore, that while it is preferable to limit new Group Schemes with private sources to a minimum, they cannot be totally abolished as it is preferable to have a group of houses abstracting from the same water source than a number of sources. That said, precautions will need to be taken to ensure that the optimum private water source in the area is selected to reduce the risk of source contamination. The Group will also have to put active source protection measures in place, including the possible designation of source protection zones 160 (Daly and Deakin 1995). Councils should carry out audits of New Schemes to ensure that active source protection is ongoing, as a requirement for continuing capital and subsidy funding. Conclusions If new Group Schemes are to continue to be approved, it is necessary to put additional conditionality in place to ensure that the water quality issues do not recur in the future. It is also essential that the future need for uneconomic water treatment infrastructure is reduced. Finally, Group Schemes should not be used as a vehicle to support unsustainable rural housing patterns as small new schemes could eventually grow to become larger schemes, which will need to be fully compliant under the Drinking Water Directive with the need for additional costly treatment infrastructure. Therefore, the following measures are recommended: 1) New Group Schemes should only be licensed in areas where it is verified that they are compliant with local authorities’ County Development and Local Area Plans for housing development. 2) All new Group Schemes approved must be connected to the public mains or an existing DBO treatment plant, where it is technically and economically viable to do so under existing grant limits. 3) New Group Schemes with private sources should only be licensed where there is no other viable drinking water solution for existing houses. 4) New Group Schemes with private sources should not be licensed unless a comprehensive risk assessment of alternative water sources, and the optimum water source has been selected. 161 5) Active local source protection measures must be put in place for new Schemes, which can be verified by Councils on an audit basis as a condition for continued subsidy or capital funding. A review of the New Schemes grant measure is vital to ensure that the water quality problems of the past do not recur. The focus has to move from expensive ‘end of pipe’ solutions to source protection. While the State currently has a legal obligation and financial imperative to provide expensive treatment solutions for existing geographically remote communities, the taxpayer cannot be reasonably expected to fund future remedial treatment infrastructure on new Group Schemes with water quality problems in new housing settlements. If such measures are not implemented, it is likely that the problems of the past could recur with substantial financial consequences for the taxpayer. 162 Chapter 5 Future Funding Needs/Alternative Approaches 163 Terms of Reference No. 6 Evaluate the degree to which the objectives warrant the allocation of public funding on a current and ongoing basis and examine the scope for alternative policy or organisational approaches to achieving these objectives on a more efficient and/or effective basis. Future Funding Commitments It is clear from the June 2006 Report to the European Commission that there is still considerable work to be done, which will require capital funding. Although, the bigger schemes have been identified, there is still uncertainty with regard to the number of smaller Group schemes serving a commercial or public function. Councils were asked to identify such schemes as part of the data collection for the June 2006 Report to the European Commission. Some schemes were identified but it is believed that a significant number of others exist. One of the difficulties is that commercial or public function is not specifically defined under the Drinking Water Directive or Regulations. The EPA did, however, issue a guidance circular (DW 01/06) in relation to this on 11th May 2006 and included dairy farming and food production as commercial functions. Given that Group Schemes are located in rural agricultural areas, it is fair to assume that there are a considerable number of small Group Schemes with connections to a dairy farm. It is imperative, therefore, that local authorities identify such Group Schemes in their area so that upgrading solutions can be identified and put in place. As previously stated, there is also a significant amount of capital work ongoing in relation to building new Schemes and extending existing Schemes. Any of these Schemes eventually falling within the criteria of the Drinking Water Regulations will also need to be upgraded if their water quality is not compliant with the Regulations. As stated earlier, it is important to minimize the number of new schemes with private sources and investment in source protection will be necessary to avoid considerably more investment in end of pipe solutions in the future. 164 The existing level of subsidy payments to the Group Schemes sector will have to remain in place for the foreseeable future unless there is a Government policy change in relation to water charging for domestic consumers on the public mains. Subsidy levels have not been increased since 2000 so have in fact fallen in real terms. The NFGWS have made proposals for subsidy increases on the basis that declining volunteerism will involve paying caretakers for the operation and maintenance of Group Scheme pipe networks. However, subsidy increases cannot be considered unless there is rigorous analysis to ensure that existing subsidy payments are not subsidising non-domestic consumers. The levels of UFW on many Group Schemes is also extremely high so it should be assessed whether it would be more sustainable to make greater investment in leakage control measures and metering than increasing the subsidy. That said, it is clear from talking to Federation and Council officials that the general decline in volunteerism in Ireland is reflected in the Group Scheme sector. Many Group Schemes are now run by a small number of long serving members, many of whom are relatively elderly. It is likely that many Group Schemes in the future will not be able to operate without professional managers. Alternatively, many of these schemes will have to be taken over by local Councils. A wholesale ‘nationalisation’ of the Group Water Scheme sector would inevitably result in significant cost increases to the taxpayer as many Group Water Schemes are currently operated on a voluntary basis and would be replaced by professional local authority technical staff in the event of takeover. Whatever the outcome, it seems clear that the State is going to have to make an increased investment in the operating costs of Group Schemes in the years to come. Alternative policy approaches Given the increased cost of the Rural Water Programme and the legal pressures to comply with the Drinking Water Regulations, it is important that the Department considers alternative policy approaches to try and implement the programme objectives in a more effective and cost efficient manner. Some of these options are considered below. 165 Administrative arrangements The last review of the Group Water Schemes Programme in 1989 looked at the administrative arrangements for the Group Schemes’ sector and considered a number of alternative organisational approaches ranging from central administration to full devolution of the programme to local authorities (Department of Finance, 1989). The 1989 Report concluded that the Programme should continue to be centrally administered by the Department. The Programme was subsequently devolved to local authorities in 1997 with the Department only making annual block grants and recouping claims from local authorities. Councils are now solely responsible for the selection and technical assessment of schemes for grant purposes. The Department funds a Rural Water Liaison Officer post in each Council to administer this role. Given the significant increase in capital funding for the Rural Water Programme over the 2003-’06 period and the implementation problems that have been encountered, it is an appropriate time to review the current administrative arrangements for the Programme. The options essentially are that the programme should continue to be run by local authorities or alternatively be transferred back to Departmental control. Given the current urgency to upgrade Group Schemes, it is questionable whether there would be any added value in recentralising the administration of the programme. In fact, any radical administrative changes during this critical period would be likely to disrupt rather than improve programme implementation. As can be seen from the table below, there is a relatively small number of staff in the Water Services Infrastructure Section currently working on the Rural Water Programme. One Assistant Principal with five support staff and a single Engineering Inspector are assigned to this area. They have responsibility for administering the block grants to local authorities for upgrading the 729 Group Schemes as well the devolved Well grants and the Small Public Schemes measures, which are not being reviewed as part of this report. Breakdown of staff in Department’s Water Services Infrastructure Section 2007 Public Schemes Devolved Rural Programme Water Programme Administrative Staff 25 6 Technical staff 10 1 No. of Schemes 889 public schemes 729 Group Schemes 166 There are significantly more administrative and technical staff involved in running the nondevolved Public Schemes Programme, where individual Water and Sewerage Scheme proposals are appraised, approved and over seen by Departmental staff. In the event of recentralisation of the administration of the Rural Water Programme back to the Department, it is clear that substantial new administrative and technical staffing resources would be required within the Department. Vital local knowledge would also be lost as Departmental staff could not possibly match local authorities’ knowledge of situations on the ground. The diversity and community nature of the Group Schemes Programme means that it is best administered on a local authority basis by a cohort of dedicated Rural Water Liaison officers and should remain so. The implementation problems to date cannot be ignored though and greater monitoring of local authority activity is required. Councils currently provide six monthly reports to the Department under the NDP but much of this data is of an expenditure nature. Councils should be required to provide the Department with management data on physical progress to date preferably on a six monthly or at least on an annual basis. Examples of such data are detailed in Chapter 6 on Performance Indicators. The Department should be monitoring this data to ensure that priorities are being addressed and that Departmental resources are being allocated in an efficient and effective manner. It is noticeable that progress on the DBO element of the Rural Water Action Plan has been quite strong even though this is the most complex element of the Programme. The Department appointed a National Co-ordinator on a temporary contract to oversee this element of the Programme and to liaise with local authorities and the DBO project managers (DBO client representatives). It should be noted that a new National Co-ordinator was appointed in August 2006 but the post’s terms of reference have been extended to overseeing the implementation of all treatment solutions and particularly the Takeover and Connection to the Public Mains solutions. On balance then, it is recommended that the current organisational and administrative arrangements for the Rural Water Programme remain in place. Cost of Compliance The significant capital investment of recent years in the Rural Water Programme have been almost solely dedicated to upgrading the sub-standard quality of drinking water in Group 167 Water Schemes through the installation of treatment infrastructure or connection to the public mains. As has been seen from the case study section of this report, the cost per house of the DBO solution, in particular, is quite expensive due to the dispersed nature of the rural population in Group Water Scheme communities. The European Court of Justice (ECJ) will fine the State if these schemes are not upgraded but should this cost fall on the taxpayer? There are two alternatives to pass on the cost to either Group Schemes or local authorities. Under the first option, the State could implement legal measures to pass on the cost of upgrading schemes to the Group Schemes themselves. This could be justified on the basis that the Group Water Schemes are essentially private enterprises set up, owned and run by Group Scheme members. One could question why a taxpayer living in inner city Dublin should be required to fund the upgrade of privately owned infrastructure in rural Ireland. On the other hand, the historical reason why Group Schemes exist in the first place is that the State did not make provision for the public supply of running water to many dispersed rural communities in the 1960s, due to opposition from large farming interests because of the impact on local authority rates. These communities had to make their own arrangements with limited State grants and the modern Group Scheme movement evolved there from (Mary Daly, The Buffer State, 1997, p.483-488.). What the Dublin taxpayer can take for granted required a huge voluntary commitment by small local communities. Putting aside the equity argument, there is also a question of practicality. Unpaid trustees generally run group Schemes on a voluntary basis. The State could legally require Group Schemes to upgrade their Schemes from their own resources but nothing would happen in most cases as many Group Scheme members simply could not afford to 100% fund upgrade works (See NFGWS submission – Appendix 3) . The ECJ would impose its fines and the State would have to upgrade the schemes without delay as it pays punitive daily fines as well as a lump sum fine for not upgrading the schemes from the start. The alternative option is to pass on the cost of compliance to County Councils as the responsible sanitary authorities for the area. The reality here is that County Councils are almost completely dependent on central government for capital funding purposes so schemes would not be upgraded with similar consequences to the option already outlined above. 168 Programme Implementation So it would seem that the State has little option but to continue to fund the cost of compliance from central taxation. The problem at the moment, however, is not the availability of funding. It is programme implementation. As already outlined in the previous chapter, implementation of public water supply solutions has been relatively slow. Councils have listed problems with Group Scheme co-operation and a lack of statutory power to intervene in non co-operating Group Schemes. It has to be accepted that a small minority of the Group Schemes’ sector do not regard water quality as being a problem for them and have no interest in co-operating with the Rural Water Programme particularly if it involves increased costs for it members. On the other hand, the Drinking Water Directive was approved by the Irish Government in the EU Council of Ministers and is now enshrined in Irish law as the Drinking Water Regulations. Private entities cannot choose to ignore a significant piece of public health legislation and State agencies have to implement it. Sanitary Authorities i.e. County Councils are legally required to take prosecutions against Group Water Schemes, that fail to put a plan in place to upgrade their drinking water supplies. While Councils do have powers to take legal action against Schemes, there has been a question mark over their powers to take follow up action. Most Councils have argued that they are waiting for the Water Services Bill to be enacted. The Department brought forward several sections of the Bill and enacted them as the Drinking Water Regulations 2007. While the new licensing system will be enacted with the Water Services Act 2007, the new Regulations now give Councils extensive statutory powers to carry out remedial works on Group Schemes themselves, where necessary. European Court of Justice case These new powers for Councils are obviously not a panacea but there needs to be clear action to try and deal with implementation issues otherwise the possibility of ECJ fines will become a serious possibility (see Rural Water News–Summer 2006). As previously explained, such fines would be likely to include a lump sum comprising the amount of money saved by a State for not investing in the necessary water treatment infrastructure plus a substantial daily fine i.e. >€1 million until such time as the Schemes are compliant with the Directive. These fines would have to be paid out of central government resources in the first instance as neither 169 County Councils nor Group Schemes would have the resources to do so, as already explained above. However, given that the implementation of the Rural Water Programme is devolved to individual local authorities, it does not seem equitable to expect national taxpayers to have to carry the burden of fines imposed due to a local infringement. This would be particularly the case if fines were imposed due to the inertia of a small number of Councils in enforcing their powers under the Drinking Water Regulations against non-cooperative Group Schemes in their administrative area. It could be more equitable to sanction such Councils individually by reducing their annual Local Government Fund allocation until such time as the fines are paid off. The Department has already warned of the possibility of such sanctions against local authorities in public fora (Athlone Seminar-June 2006). Source Protection One of the notable feature of the Rural Water Programme is that most of the capital investment relates to ‘end of pipe’ solutions. In other words, the water is treated after it becomes contaminated. All five treatment solutions are ‘end of pipe’ solutions. This raises the question as to why this water has become polluted in the first place. The generally accepted response to this is poor farming practices, run offs from septic tanks and inadequate protection of water sources (EPA 2006, p.21.). The National Federation of Group Water Schemes (NFGWS) itself concedes that ‘end of pipe’ solutions are not sustainable and that there needs to be a greater emphasis placed on source protection (NFGWS 2006, p.5). Article 7.3 of the EU’s Water Framework Directive states that “Member State shall ensure the necessary protection for the bodies of water identified with the aim of avoiding deterioration in their quality in order to reduce the level of purification treatment required in the production of drinking water. Member states may establish safeguard zones for those bodies of water”. This would appear to indicate that in the future ‘end of pipe’ treatment of polluted water may no longer be regarded as sufficient and that member states will be legally required to ensure that their water sources do not become contaminated in the first place. Therefore, the issue of source protection of drinking water supplies is likely to come to the fore in the future. The Department is currently working on a Master Plan to meet the requirements of the Water 170 Framework Directive and specifically to produce River Basin Management Plans (RBMP) by 2009. Local Authority Source Protection Initiatives Councils were asked in the Questionnaire (Q13) to detail any initiatives that they have taken to encourage Group Schemes to adopt source protection measures. Most Councils responded that they have given Group Water Schemes information in relation to source protection best practice. This issue is also discussed with Group Schemes when they are preparing Action Plans to address water quality deficiencies on their Schemes. Cork (North Area) and Longford County Councils require Group Schemes to have source protection plans in place as a requirement for their annual domestic subsidy payment. In Cork County Council (South and West Areas), areas around sources are fenced off, where possible, to exclude cattle. Surrounding landowners are advised in relation to nutrient management near water sources and lectures are given to applicants on water quality, under the Department of Agriculture’s Rural Environmental Protection Scheme (REPS). Some Councils advise Group Schemes to re-locate their water abstraction to more suitable entry areas and to keep buffer zones around water sources clear of contamination. A small number of Councils have taken no initiatives with Group Schemes in relation to source protection. National Action Programme under the Nitrates Regulations 2005 The National Action Programme was jointly drawn up by the Department of the Environment, Heritage and Local Government and the Department of Agriculture and Food to give effect to the terms of the EU’s 1991 Nitrates Directive. It was launched in July 2005 and was subsequently given legal effect under the Nitrates Regulations of 12th December 2005. The Regulations places limits on the land spreading of fertilisers and livestock manure and creates buffer zones from surface and ground water supplies. It is hoped that the implementation of these measures by farmers will protect surface and groundwater supplies from microbiological contamination from animal waste and from chemical contamination by excessive nitrates from fertilisers. The problem of nitrates in source water supplies has already been identified as a problem for the effectiveness of the disinfection /sterilisation solution in Kilkenny. “High levels of nitrate in drinking water may induce ‘blue baby’ syndrome [methaemaglobinemia]” (EPA 2007, p.30.). 171 Departmental Initiatives - Groundwater Protection As previously discussed in the context of the disinfection/sterilisation solution, the Department’s Spatial Policy section issued guidance to local authorities in July 2003, in relation to the role of the planning system in protecting groundwater quality (Circular SP 5/03). “This circular letter covers three main issues in relation to the role of the planning system in ensuring that development proceeds in a manner that offers the best possible environmental protection, including protection of groundwater quality. The three issues are: (a) The need for more information within development plans on the location and potential vulnerability of groundwater resources and for clear policies on how development in different areas will be approached based on the available information. (b) The need within the development control system to ensure that effective regimes for the proper assessment of site conditions as well as the design, installation and maintenance of on-site wastewater treatment and disposal facilities are put in place. (c) The need for planning authorities to put in place appropriate monitoring and enforcement mechanisms that ensure that those who carry out approved development meet their obligations to adhere to the terms of planning permissions.” In practice, this Circular advises Councils to identify key groundwater resources and develop groundwater protection plans, which should be linked with the implementation of their County Development Plans. This could involve identifying source protection areas around key aquifers i.e. groundwater sources used for drinking water purposes and determining “the appropriateness of various categories of development to areas that have different levels of vulnerability in terms of groundwater contamination” (SP5/03, p.3.). Planning Authorities should also seek to verify that single house effluent treatment systems e.g. septic tanks are properly installed and maintained as a condition of planning permission and measures should also be put in place to verify that these conditions are observed on an ongoing basis. Circular SP5/03 is specifically referred to in the Guidelines for Planning Authorities on Sustainable Rural Housing issued to planning authorities i.e. County Councils in April 2005 (Department of the Environment, Heritage and Local Government 2005, p.36.) This circular makes some 172 very practical and sound proposals in relation to source protection but it is advisory only and has no legal effect. Several County Councils have not opted to adopt groundwater protection plans. Anecdotal evidence would suggest that local concerns in relation to the impacts of such environmental protection measures on planning permissions for rural housing has influenced this. The Department may need to review its position in relation to this issue given the cost implications of being legally required to install water treatment solutions on small Group Schemes, with commercial connections e.g. dairy farms, where the drinking water quality has declined due to local source contamination. Departmental Initiatives - Surface Water Protection There are currently no Departmental guidelines in relation to source protection measures for surface water supplies i.e. rivers and lakes. The National Rural Water Monitoring Committee (NRWMC) has commissioned the Centre for Freshwater Studies in the Dundalk Institute of Technology (DKIT) to carry out a National Pilot Source Protection Study on the Churchill Oram Group Water Scheme in Co. Monaghan. “After a full year of detailed monitoring, the project has identified the nature of all the pollutants in Milltown Lake, source for the Churchill & Oram Group Water Scheme. Low tech remedial solutions are shortly to be introduced on sections of the lake catchment and intensive work is starting on farmyard and septic tank surveys” (Rural Water News-Autumn 2006, p.7.) These remedial measures will include readily available materials and technologies e.g. buffer strips, fencing, cattle drinkers, tailored REPS and recommendations for improvements in farmyard practices” (National Source Protection Pilot Project, Interim Report December 2006). DKIT is also currently researching “the extent to which wetlands and biomass cultivation might help in preventing run-off from agriculture and septic tanks into our waterways” (Ibid- Winter 2006, p.12.). The septic tank survey is considered particularly significant given concerns expressed by organisations such as An Taisce and the Geological Survey of Ireland (GSI), in relation to the possible impact of runoffs from poorly maintained septic tanks on rural water sources nationally (Daly, Donal, 2000, p.8.). It is estimated that there are approximately 300,000 septic tanks in the country and it is suspected that a significant number of these tanks may be inadequately maintained. Analysis of the 2006 Census returns will provide more definitive data on the number of septic tanks in the coming months. The results of the National Pilot 173 Source Protection Study’s extensive septic tank survey may provide some firm data in relation to the potential scale and impacts of this problem. The new Water Services Act makes provision for local authorities to legally require the owners of septic tanks to properly maintain their effluent treatment systems. It is hoped that the outcomes of the National Pilot Study will produce a source protection template for surface drinking water supplies in Ireland. It should be stressed, however, that the quality of raw surface water is generally inferior to groundwater so successful source protection measures are likely to reduce the level of water purification treatment rather than remove the need for treatment entirely. Teagasc, the State’s farm advisory body, is also currently looking at the practical application of measures under the Department of Agriculture and Food’s Rural Environment Protection Scheme (REPS) to encourage intensive farmers to implement source protection measures (Rural Water News-Autumn 2006, p.7.). As already stated in the subsidy section, active and verifiable source protection should be linked to subsidy payments in the future. 174 Chapter 6 Proposed Performance Indicators 175 Terms of Reference No. 7 Specify potential future performance indicators that might be used to better monitor the performance of future Action Plans for Rural Drinking Water Quality. Introduction The starting point in developing new performance indicators is to first examine the existing monitoring system and review how the inputs, outputs and outcomes are monitored. Grant Allocation/drawdown process The inputs i.e. spending measures are set out in the table below. The Department makes an annual block grant to each Council, participating in the Rural Water Programme, broken down into the capital investment measures below. Councils select and prioritise the individual Group Water Scheme works, to be funded from the various measures. Councils draw down these capital grants from the Department during the course of the year, as expenditure is incurred, so the Department is able to monitor expenditure under the various capital measures, throughout the year. Table 6.01 Annual Expenditure on Capital measures under the Rural Water Programme Expenditure on Capital Measures (€ million) Design Build Operate (DBO) DBO Advance Work LA Takeover 2003 2004 2005 8.723 21.194 33.812 31.568 95.297 - 16.874 18.464 35.338 - 2006 Total 9.467 8.91 10.884 16.924 46.185 Upgrade of GWS networks 30.352 20.323 25.738 28.996 105.409 Connect to the Public Main - 5.367 6.751 3.895 16.013 55.794 94.059 99.847 298.242 Total 48.542 Source: Department of the Environment, Heritage and Local Government Expenditure reporting requirements As part of National Development Plan (NDP) reporting requirements, Councils are required to prepare six monthly expenditure returns for the Border Midlands West (BMW) Regional 176 Assembly and Southern and Eastern (S&E) Regional Assembly. Some of this capital expenditure is eligible to be recouped from the European Regional Development Fund (ERDF). These returns are submitted in the first instance to the Department for onward transmission to the BMW and S&E Regional Assemblies. The Department have developed an excel based Management Information System (MIS) to record and process this six monthly expenditure. It is broken down on a County Council basis with details on each Group Water Scheme in receipt of capital funding. For each Group Scheme, the following indicator data is recorded: Population Equivalent (P/E) of Scheme No. of house/farm/commercial water connections Average Water Supply demand per day in m3 (cubic meters) %Domestic/Non-Domestic Water demand Expenditure reporting is broken down into the following categories. Regional Assembly Reports Expenditure Categories Water Treatment/Disinfection New Schemes/Scheme Upgrades Takeover Therefore, expenditure for each Group Scheme is recorded under one or more categories. For example, a Group scheme, which receives a DBO treatment plant and a pipe network upgrade would have expenditure recorded under both the water treatment/disinfection and New Schemes/Scheme upgrade categories. It is also recorded whether the scheme is complete or still work in progress. It is clear to see that the annual capital allocation measures and the NDP reporting expenditure categories do not match. There are only three expenditure categories for Group Schemes under the NDP reporting system. Expenditure on DBOs and Disinfection/Sterilisation are 177 recorded under the ‘Water Treatment/Disinfection’ heading. Expenditure on new Group Schemes, pipe network upgrades and connections to the public mains are recorded under ‘New Schemes/Scheme Upgrades’. The 2000-’06 NDP reporting system was developed in 2000 based on the capital allocation measures for the Group Schemes Programme existing at that time. Annual allocations were broken down into more specific spending measures over subsequent years to target expenditure on priority areas. As a result, the NDP reporting categories have become quite dated and while meeting NDP/Regional Assemblies reporting requirements provide little in the way of substantial management information for current needs. Programme Output reporting requirements The Department occasionally requests Councils to provide output data in relation to each of the water quality upgrade solutions. This is generally required to update the European Commission on progress with Group Schemes required to comply with the Drinking Water Regulations. The last such report was the June 2006 Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive. Progress under the five water quality upgrade solutions, are outlined below. Councils were requested to provide a further update on progress in March 2007. Table 6.02 - Implementation Status of Group Water Schemes by upgrade solution category Treatment Solutions DBO Non-DBO Connect to Public Main Council Takeover Disinfection/Sterilisation Public Source Total No. of Schemes % implementation % Solution In Work in Upgrades Total % Upgrades breakdown Planning Progress Complete Schemes complete 35% 3% 16% 9% 17% 20% 100% 19 7 85 35 19 21 209 9 27 27 11 15 30 5 6 3 92 109 258 21 118 65 122 145 186 26% 298 41% 245 34% 729 12% 24% 5% 5% 75% 75% Ref. Figures derived from June 2006 Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive The first thing that is apparent is that there is a mismatch between the financial inputs and physical outputs for the Programme. The non-DBO and Disinfection/Sterilisation treatment 178 solution outputs do not appear in the list of annual allocation capital measures (inputs). This is because they are financed out of the upgrade measure. This anomaly has been corrected in the 2007 allocations with a separate capital spending measure for Disinfection/Sterilisation schemes. The non-DBO treatment solution generally involves an upgrade of existing water treatment infrastructure on a small number of Group Schemes so it is probably appropriate for it to be funded as part of the Upgrade expenditure measure rather than have its own dedicated measure. Non-Drinking Water Regulations related outputs The other issue that needs to be considered is that this output progress report only looks at Group Schemes, which require a water quality upgrade solution, in order to comply with the Drinking Water Regulations i.e. Schemes>15 houses and Schemes with a connection to a commercial premises or a premises with a public function. As has been seen from this VFM Review, there are several areas of capital expenditure, which have no relationship to the Drinking Water Regulations compliance. These measures are; Non-Drinking Water Regulations related outputs Funding Measure New Group Water Schemes New Schemes Extensions to existing Group Schemes New Schemes Schemes taken over by Council Takeover Schemes connected to the public mains Connection to the Public Mains Pipe Network Upgrades Upgrade of Group Water Schemes The ‘Takeover’ and ‘Connection to the Public Mains’ measures are particularly problematic as expenditure related and unrelated to achieving Drinking Water Regulations compliance i.e. outcomes are mixed in together. Therefore, while there is currently a significant level of expenditure and outputs under these spending measures, very little of this activity related to achieving priority outcomes during the 2003-’06 period under review. Pipe network upgrades is another expenditure area, which is related to different outcomes, and indeed is linked to all treatment solutions as well. The Department instructs all local authorities to prioritise Drinking Water Regulations Schemes for upgrades when submitting their funding bids for 179 block grants. However, this is ultimately a matter for local authorities to implement as they approve and advance the individual schemes rather than the Department. Proposed new Measures structure Therefore, expenditure and outputs related to different outcomes should be separated out to give a true picture of implementation and achievement of priorities. The starting point to improving performance monitoring is to change the way that capital funds are allocated in the first place to try and match inputs to outputs to outcomes. This is, of course, only possible Inputs - Outputs - Outcomes- Spending Completed Objectives Measures Works achieved where your outcomes i.e. objectives are known. In the case of most of the Rural Water Programme, this is clear cut i.e. compliance with the Drinking Water Regulations. In the case of other works, the outputs are clearly definable but the objectives or certainly the prioritisation of objectives is less clear. To date, the policy has been to set out programme priorities and to ask Councils to only advance work for priority schemes. However, if there are delays in progressing priority works, there is very little control to stop Councils from instead spending funds on low priority works e.g. non-urgent Group Scheme takeovers and connections to the public mains. The proposed solution is to split the annual capital allocations into two main categories – Works related and Works unrelated to compliance with the Drinking Water Regulations. These two main allocation categories can then be split into sub-categories based on programme priorities and objectives. The two proposed Measures structures are outlined in turn below. Drinking Water Regulations Measures Structure This only includes capital allocations for Group Schemes, which require a water quality upgrade solution, in order to comply with the Drinking Water Regulations i.e. Schemes>15 houses and Schemes with a connection to a commercial premises or a premises with a public 180 function. In this case, the inputs will be the capital allocations made under the various treatment solution measures. The outputs will be the completed treatment solutions and the outcomes will be results of the water quality tests carried out by the local authorities, to confirm compliance with the Drinking Water Regulations. The following is the proposed system for monitoring these inputs, outputs and outcomes. Proposed Allocations/Input Measurement Capital allocations should match each of the five water quality upgrade solutions. The Takeover measure should, however, be broken down into public source and private source schemes. Analysis of Questionnaire returns from local authorities indicates that 65% of takeover expenditure related to lower priority Group Schemes with public sources. The European Commission is most concerned with the upgrade of private source schemes as these present the greater risk to public health. Therefore, it is prudent to allocate takeover funds for private and public source schemes separately to ensure that expenditure under these two priorities can be tracked separately. Allocations – (Drinking Water Regulations Compliance) Treatment Solutions Allocation sub-categories Allocation amount (€) DBO Non-DBO Disinfection/Sterilisation Connection to the Public Mains Takeover (Private Source) Takeover (Public Source) Pipe Network Upgrade Proposed Output Measurement Councils should be asked at least once a year, but preferably every 6 months, to provide output details of Group Scheme works in planning, work in progress or complete for each of these measures as per the summary June 2006 Report to the European Commission. Schemes would only be categorised as work in progress if the contractor has commenced work and complete if the new water quality upgrade solution is fully operational. The only change from the existing June 2006 Report output table would be to break the Takeover scheme outputs 181 into the number of public source and private source schemes taken over, as the latter are the priority Schemes. Proposed Outputs Table No. of Group Schemes (by In Work in upgrade solution) Planning Progress Completed Total Design Build Operate (DBO) Treatment Plant Non-DBO Treatment Plant Connection to the Public Mains Local Authority Takeover (Private) Local Authority Takeover (Public) Disinfection/Sterilisation Pipe Network Upgrades (included in schemes above) The only problem here is how to incorporate expenditure on pipe upgrades into the above outputs model. It is possible that pipe upgrades could be carried out on any of the above schemes in addition to the water quality upgrade solutions. The solution is to include an additional row in the outputs table for the number of Group Schemes receiving a pipe network upgrades in addition to their water quality upgrade. It is vital that basic pipe network upgrade output data is recorded, as expenditure under this measure is second only to the DBO measure. When reporting to the European Commission, the Department has also reported outputs in terms of households as well as Group Schemes. This is important to ensure that a distorted picture of implementation is not presented due to the varying sizes of Group Water Schemes. For example, in the table below, there are three Group Water Schemes of varying sizes. If one was to measure completions purely on a Group Scheme basis, you would say that one out of 182 the three Group Schemes is complete so you have 33% completion. Alternatively, you could count completions in terms of Group Scheme Name No. of Households Status Group Scheme A 900 Complete Group Scheme B 85 WIP Group Scheme C 15 Planning the number of households that have benefited from Scheme completions overall. This would mean that 900 out of 1,000 houses have been upgraded i.e. 90% completion. It would be generally be agreed that household completions give a more genuine measurement of implementation. However, annual capital allocations (inputs) are made on Group Scheme basis and the water quality i.e. outcomes is tested on a Group Scheme basis. Therefore, output data should be provided by Councils on a per Group Scheme and a per household basis using the proposed Outputs table format above. Proposed Outcome Measurement The objective/outcome of water quality upgrade works is to bring Group Schemes into compliance with the Drinking Water Regulations. The measurement of this outcome is quite clear cut as the quality of water coming out of household taps must meet the necessary standards. As previously stated, local authorities are legally required to test the water quality in Group Schemes and forward the results to the Environmental Protection Agency (EPA) for publication in an Annual Report so the data is publicly available. The only problem is that there is a significant time delay between testing and the publication of the results by the EPA. For example, the most up to date EPA Drinking Water Report, based on 2005 water test results, was published in January 2007. The Department needs far more recent test result data than that to assess effectiveness of outcomes. Therefore, for each completed Scheme above in the outputs table, Councils should be required to report any exceedances of the Drinking Water Regulations’ parameters on at least an annual basis. This places no additional administrative burden on local authorities as they are current statutorily required to provide annual drinking water quality test results on all Group 183 Schemes to the EPA by February of the following year. In other words, the test results for the 2005 EPA Drinking Water Quality Report published in January 2007, should have been sent to the EPA by February 2006. Therefore, the test data results are already available in Councils and can be used to complete the Exceedances table below. If no exceedances are reported for a completed Group Scheme, the Council are, by default, confirming that that Group Scheme is now fully compliant with the Drinking Water Directive. Upgraded Group Schemes - Exceedances Report Name of Date Upgrade Microbiological Chemical Indicator Remedial Group Completed Solution Parameters Parameters Parameters Action exceeded exceeded exceeded Taken Scheme As has been seen from the analysis of various case studies under the different solutions, there are still exceedances in the case of some Group Schemes even after they have been upgraded. This calls into question the effectiveness of the treatment solution. In some cases, it needs to be established whether the treatment solution is ineffective or whether the problem in fact lies in the operation and maintenance of the Group Scheme by its volunteer members. It is not possible to detect such problems unless there is timely test data available to Group Schemes, local authorities and the Department. While it is the legal responsibility of the local authority to resolve the water quality problem in conjunction with the Group Scheme, the Department needs to be aware of such problems; to identify if there is a problem with the effectiveness or sustainability of any of the completed treatment solutions to ensure that there is no public health hazard to water consumers to ensure that the necessary remedial action is taken prior to the publication of the test results in the EPA Drinking Water Reports to avoid ECJ imposed fines for continuing to breach the terms of the Drinking Water Directive 184 The last point is the most significant from a value for money perspective. An ineffective treatment solution not only means that the taxpayer’s money was wasted on that capital investment, the taxpayer could also end up bearing the brunt of substantial EU fines, far in excess of the treatment solution cost. The latest EPA Drinking Water Report was quite critical of some Council’s water quality monitoring regimes. It found that no testing at all was done on 9% of Group Schemes. As has been seen from this study, some Group Schemes are not tested at all after they have been connected to the public mains, even though they are still Group Schemes with independent pipe networks. The Minister for the Environment, Heritage and Local Government has recently introduced new regulations giving additional powers to the EPA to prosecute Councils not fulfilling their statutory duty to test all Group Water Schemes. Annual Output Statement From 2007, Government Departments are required to produce annual output statements, which set out annual output targets. These output statements are appended to the annual Departmental Estimates, when submitted to the Oireachtas for approval. The Group Water Schemes’ sector’s target is set out in the table below. Performance Indicators Output Target for 2007 Percentage of Group Water Scheme 85% of Group Water Scheme households households in compliance with national in compliance compared to 75% at the drinking water standards at year end end of 2006 As can be seen from the table, the performance target is actually an outcome target rather than an output target. The Department will need to ensure that the information in the Exceedances Report is taken into account as basing compliance on the number of upgraded Group Schemes would be inaccurate unless it is verified that all of these Group Schemes are in fact compliant after upgrading. Identification of Group Schemes with a commercial function As has been stated several times throughout this Report, the Drinking Water Regulations do not just apply to Group Schemes with greater than 15 houses. It also applies to Group 185 Schemes of any size with a connection to a premises providing a public or a commercial function. For example, the non-DBO Cappanalea Group Scheme was required to comply with the Regulations as it is connected to an adventure centre, although it only has 6 houses connected to the Scheme. The EPA noted in its 2005 Drinking Water Report (January 2007) that many County Councils had, in fact, not provided water test results for many such schemes. It is important that Councils ensure that Group Schemes serving a public and commercial function, as per the EPA (DW 01/06 of 11th May 2006) circular are identified and upgraded, if necessary. Other Allocations Measures Introduction This includes all capital measures, where compliance with the Drinking Water Regulations, is not an objective (outcome). In other words, the Irish Government is not legally compelled by the EU Drinking Water Directive to invest in the Other Allocations Measures so this is discretionary capital expenditure. The first point to note, though, is that expenditure under these measures may, in some cases, also have water quality objectives. For example, there could be a small Group Scheme <15 houses with a polluted private water source. While this Scheme is not required to comply with the Drinking Water Regulations, the Council may quite justifiably decide to connect it to the public mains on public health grounds. It is important to make this distinction from the outset as the allocations’ split is based on Drinking Water Regulations upgrades and non-Drinking Water Regulations upgrades not water quality and non-water quality upgrades. Proposed Inputs Measurement Capital allocations would be made based on the measures set out in the Other Allocations structure table below. It should be noted that New Schemes, Scheme Extensions and Takeovers are broken down into private and public source schemes. This reflects the reality that private source schemes generally have worse water quality problems. Therefore, as already discussed in the New Schemes section, it is important to monitor the development of new Schemes and Schemes Extensions with private sources as they may need expensive water 186 treatment solutions in the future if they expand and need to comply with the Drinking Water Regulations i.e. > 15 houses or connect to a premises with a commercial or public function. Allocations – Other (Non-Drinking Water Regulations Compliance) Measures Allocation amount (€) Allocation sub-categories New Schemes (Public source) New Schemes (Private source) Scheme Extensions (Public source) Scheme Extensions (Private source) Scheme Takeovers (Private Source) Scheme Takeovers (Public Source) Connection to the Public Main Pipe Network Upgrade Proposed Outputs Measurement Outputs should be measured by asking each local authority to complete an outputs table for all the allocation sub categories as below. Outputs Table Allocation sub-categories In Work in Schemes Planning Progress Completed New Schemes (Public source) New Schemes (Private source) Scheme Extensions (Public source) Scheme Extensions (Private source) Scheme Takeovers (Private Source) Scheme Takeovers (Public Source) Connection to the Public Main Pipe Network Upgrade 187 Councils will also have to complete an additional table (below) listing any Group Schemes, which have fallen under the remit of the Drinking Water Regulations since the last Report. These Group Schemes may require future treatment upgrade funding so this needs to be flagged in advance. An exceedances report needs to be prepared for each of these Group Schemes, which are non-compliant. Name of New No. of houses Indicate whether Public/Commercial Group in Group Public or Private Connection Scheme Scheme Source (Yes/No) Outcomes Measurement Measuring outcomes are problematic for the Other Allocations measures as in many cases the objectives/outcomes of the capital investment are unclear. The last Review of the then Group Water Schemes Programme in 1989 stated the two main objectives as being Water Quality and Water Quantity i.e. “providing a sufficient quantity of piped water in as many houses as is feasible” (p.2). The Review subsequently stated that “at present virtually all houses have a piped water supply” whether from a Group Scheme or a single house source e.g. a well (1989, p.25). The water quality objective has subsequently come to the fore and has been already been discussed at length. The expected outcomes/objectives from Other Measures with no connection to water quality is less clear. Those measures are New Schemes, Extensions to existing Schemes and Pipe network upgrades unrelated to water quality issues. Investment under these capital measures is currently demand led by Group Schemes and County Councils. Group Schemes request funding from County Councils who submit funding bids to the Department in support of their block grant allocation. If the block grant allocation is large enough, then the Council approves whatever works it wishes. The only Departmental constraint is that there is a 15% capital 188 contribution from the Group Scheme and that the total capital works does not exceed €6,476 per house. As already stated in previous chapters, there is a need for greater guidance to County Councils in relation to the approval of New Schemes particularly as these Group Schemes could require expensive publicly funded water treatment solutions in the future, if their growth is not regulated by the State. There also needs to be greater guidance in relation to the approval of pipe network upgrades in the Other Measures category. Both sets of guidance must clearly set out the objectives/outcomes required for public investment under these Measures to ensure Value for Money for taxpayers. Pipe Network Upgrades – Outcomes Measurement As stated several times during this study, pipe network upgrades have been a very significant element of expenditure under the Rural Water Programme over the 2003-’06 period. This expenditure is largely explained by the need to reduce the levels of UFW in pipe networks. Therefore, it logically follows that the Department and local authorities should set specific UFW reduction targets as the outcome for pipe network upgrade investment. Conclusions On balance then, what are the advantages and disadvantages of putting in place a dual allocations system with separate allocations for Group Schemes required and not required to comply with the Drinking Water Regulations. The advantages are that : 1. There is a clear distinction made between discretionary and non-discretionary capital expenditure. In other words, it is clear which capital expenditure the Irish Government is legally compelled to make under the EU Drinking Water Directive and which expenditure is at the discretion of the State. This is particularly important to know if the Minister needed to target funding for diversion to higher priority areas in the future. 2. The Department will be clearly able to track capital investment (inputs) to comply with the Drinking Water Regulations to outputs (Scheme completions) to outcomes (compliance with drinking water quality parameters). At present, this is not possible with takeovers, connection to the public mains and pipe network upgrades for Group 189 Schemes, with no compliance requirements, mixed into the same capital measures (inputs) and outputs (completed schemes) data. Under a separate allocations and outputs reporting system, the Department will have clear headline data for tracking the achievement of different outcomes. 3. Councils will be prevented from diverting capital funds targeted at high priority Drinking Water Regulations Group Schemes to non-Drinking Water Regulations Schemes. The disadvantages are that: 1. An already complicated system of capital measures becomes even more complicated with even more splits into sub-categories. The counter argument to that is that the expenditure will be better targeted with a more coherent match between inputs, outputs and outcomes. 2. It could cause local authorities to underspend their allocations under certain measures e.g. in cases where there were delays in progressing high priority Drinking Water Regulations Group Schemes. However, in such cases, the Council can simply advise the Department of an expected underspend and request that the funds be diverted elsewhere. In other words, under the new system the Department will have to approve the diversion of capital funds to lower priority areas. Under the current allocation system, the Department is not aware if such diversions of targeted funding is taking place e.g. from high priority to low priority Scheme Takeovers. It could be argued that the Rural Water Programme is a devolved local authority programme and such changes to the capital allocations system would be quasi- recentralisation of the Programme. It must be remembered, however, that the Programme was devolved to local authorities in 1997, when Councils could only approve individual public schemes costing less than £250,000. The situation has changed radically since then particularly following the European Court of Justice ruling against Ireland. Expenditure under the Group Scheme elements of the Rural Water Programme has increased by 105% between 2003 and 2006 from 190 €48.542 million to €99.847 million per annum. This funding has come substantially from central Government. Implementation of the Action Plan for Rural Water Quality has only been very modest for some measures i.e. takeovers and connections to the public mains. Therefore, it is essential that the Department has an allocation system in place to ensure that funds are targeted in priority areas and a coherent reporting system to monitor progress in achieving required outputs and outcomes. 191 Chapter 7 Conclusions and Recommendations 192 Introduction As has been seen from this Review, the implementation of the Rural Water Programme is an extremely complex and diverse undertaking. Unlike the Public Water Services Investment Programme, its implementation is dependent on the co-operation of the privately owned and voluntarily run Group Schemes’ sector. Also because it is a devolved local authority programme, the Department is dependent on the initiative of individual local authorities in delivering its objectives. It is also unique in that there is very little discretion available to the Department in funding this capital programme as Ireland is facing the imminent prospect of having to pay millions of euros in fines to the European Commission if it fails to bring Group Water Schemes into compliance with the European Union’s Drinking Water Directive. Finally, there is no neat ‘one size fits all’ solution as the Rural Water Programme involves providing costly water treatment, using five different upgrade solutions, to dispersed communities in remote areas. Therefore, the issue of delivering value for money is a challenging but vital necessity. Limitations of Study Before discussing the Conclusions and Recommendations of this Review, it is important to first qualify them by setting out the limitations of this study. Implementation analysis The last substantive information collected to date on implementation to date under the Rural Water Programme was for the June 2006 Report to the European Commission (see table below). Therefore, the implementation data used in this 2003-’06 Review does not reflect scheme implementation during the second half of 2006. The only exception was the DBO bundles programme, where more up to date implementation information was made available by DBO Client Representatives. 193 Implementation Status of Group Water Schemes by upgrade solution category – June 2006 Treatment Solutions % Solution In Work in Upgrades Total % Upgrades breakdown Planning Progress Complete Schemes complete DBO Non-DBO Connect to Public Main Council Takeover Disinfection/Sterilisation Public Source 35% 3% 16% 9% 17% 20% 100% Total No. of Schemes % implementation 19 7 85 35 19 21 209 9 27 27 11 15 30 5 6 3 92 109 258 21 118 65 122 145 186 26% 298 41% 245 34% 729 12% 24% 5% 5% 75% 75% Ref. Figures derived from June 2006 Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive A revised implementation report was sent to the European Commission in May 2007, which provided details on schemes’ implementation as of 30th April 2007 (see table below). This information was only made available after the completion of this 2003-’06 review but it shows an improved situation in relation to implementation of the two water quality upgrade solutions involving connection to the public mains. The difference in the total number of schemes designated under each of the treatment solution types is explained by the fact that the planned solution for some schemes has changed since June 2006. Also as explained in this Review, the June 2006 Report had understated the number of completed Schemes connected to the public mains by categorising them as public source so this has been corrected. Implementation Status of Group Water Schemes by upgrade solution category – 30th April 2007 Treatment Solutions DBO Non-DBO Connect to the Public Main LA Takeover Disinfection/Sterilisation Public Source Total No. of Schemes % status In In Advanced Work in Planning Planning Progress Upgrades Total % Upgrades Complete Schemes Complete 3 5 31 25 20 2 88 1 6 19 5 2 34 8 13 27 4 2 102 21 46 34 139 91 227 35 96 105 168 97 45% 60% 48% 32% 83% 94% 86 12% 121 16% 88 12% 433 60% 728 59% Ref. Figures derived from background data collected for May 2007 Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive 194 Effectiveness analysis The most up to date EPA water quality test results available were for 2005. Therefore, this Review was dependant on local authorities for confirmation of whether or not Group Schemes, upgraded after 2005, were compliant. However, given that the EPA’s published data is based on local authority test results, there is no reason to assume that the local authority data is not accurate. Efficiency analysis Data on the capital cost of completed DBO Schemes is incomplete as these Schemes are only recently finished and no final accounts are available for any of the DBO schemes. Provisional DBO Client Representative data was used in this Review. It is likely, therefore, that the DBO capital costs may be understated. DBO pipe network upgrade data is not available yet. This means that unit cost i.e. cost per house comparisons between DBO projects and with other treatment solutions is very provisional. In any case, previous studies have shown that unit cost comparisons of the water sector only provide limited indicators of relative value for money, due to the unique nature of individual water projects, particularly when serving dispersed rural communities. Fitzpatrick Associates have also predicted that it will not be possible to conclusively assess the value for money of DBO projects for many years (2005, p.96). Councils stated in most cases that all alternative water quality upgrade options were costed to ensure that the ‘most economically advantageous” option was chosen. However, documentary verification of this was not provided in most cases. It will be recommended that this verification be included in the DBO final accounts in the interests of transparency. It was only possible to carry out a limited assessment of the relative operational and maintenance (O&M) costs of the DBO and the two public source solutions involving connection to the public mains. This was because DBO O&M data is very provisional and also because the basis for calculating local authority water charges differs from Council to Council. It was not possible to carry out an O&M comparison with the Disinfection/Sterilisation and Non-DBO solutions as they are voluntarily maintained so there is no comparative cost data available. Potential Areas for further Study The comparison of provisional DBO treatment plant O&M costs and local authority O&M charges (see p.123.) would appear to suggest that the volumetric i.e. variable costs of DBO 195 plants are considerably lower. This could be explained by the inclusion of network maintenance overheads in the local authority water charges unlike the DBO contractors’ charges. This apparent cost differential needs to be explored further based on more definitive DBO O&M data and more information on the basis used for calculating individual local authority water charges for non-domestic consumers. As already stated (see p.69.), the Department may wish to look at standardising the basis for calculating local authority water charges in a further study. Conclusions of the Rural Water Programme Review Validity of Programme Objectives The primary objective of the Rural Water Programme during the period of the Action Plan for Rural Drinking Water Quality 2003-2006 was to bring the quality of rural water supplies, and specifically privately sourced Group Schemes, into compliance with the Drinking Water Regulations 2000. This is clearly stated in the Department of the Environment, Heritage and Local Government’s Statement of Strategy. The June 2006 Report to the European Commission and the 2007 EPA Drinking Water Quality Report clearly indicates that, in spite of significant implementation activity, this objective has not yet been fully achieved. Therefore, the primary objectives of the Rural Water Programme continue to be relevant post 2006. Implementation of Water Quality Upgrade Solutions As has been seen, the best progress to date on water quality upgrade implementation has been with DBO and Disinfection/Sterilisation Schemes. Much of the work on Disinfection /Sterilisation Schemes was, however, carried out prior to the 2003-’06 period under review so minimal upgrades were needed. Progress on completing DBO treatment plant bundles has also been substantial in spite of the complicated nature of such contracts. Implementation of the two public water connection solutions has been relatively slow and, according to local authority questionnaire returns, the unwillingness of some non-domestic Group Scheme consumers to pay for local authority water appears to lie at the heart of this delay in many cases. 196 Effectiveness of Water Quality Upgrade Solutions The Environmental Protection Agency (EPA) regard the quality of public water supplies as generally satisfactory unlike many Group Schemes’ private water supplies (2007). Therefore, the Takeover solution would appear to be the most effective as Group Schemes are fully absorbed into the public water system and their pipe networks are maintained by professional local authority personnel. Similarly, the Connection to Public Mains (CTPM) solution is effective but there is an effectiveness risk factor involved as Group Schemes maintain responsibility for pipe network maintenance. The DBO treatment plant solution also appears to be effective but has the same pipe network maintenance risk factor. Disinfection/Sterilisation and Non-DBO schemes also have this risk factor as well as a more serious risk of non-compliance if Group Schemes do not properly operate and maintain their treatment infrastructure and protect their water source. EPA test result data for several Group Schemes upgraded using the Disinfection/Sterilisation and Non-DBO solutions still show exceedances of microbiological and chemical parameters in some counties. It is probable, in many cases, that this may be due to inadequate operation and maintenance of treatment facilities and pipe networks by Group Scheme volunteers. Therefore, there is a question mark over the effectiveness of those latter two solutions without active Group Scheme maintenance. The EPA also raised concerns, in its 2007 Drinking Water Quality Report, in relation to the level of water quality monitoring and testing carried out by local authorities on Group Schemes in 2005. Water quality monitoring is key to identifying Group Scheme in need of possible upgrades and also to assess the effectiveness of these water quality upgrades. The Minister for the Environment, Heritage and Local Government has given the EPA additional powers to take enforcement action against local authorities, who do not fulfil their statutory monitoring requirements, under the new 2007 Drinking Water Regulations. Efficiency of Water Quality Upgrade Solutions The relative efficiency of each of these individual solutions is more difficult to measure as they are very varied in nature and as such reliable and meaningful comparisons are harder to make. However, as grants are made on a cost per house basis, the relative cost of a number of schemes from each upgrade solution, were compared (see p.142). There were wide variations 197 in the cost per house of Schemes upgraded under the same solution never mind different solutions. In many respects, the exercise bore out the conclusions of the previous two recent reviews of the Water Sector discussed in the Literature Review i.e. 2002 Departmental Expenditure Review and the 2006 Fitzpatrick Associates NDP Review. It is actually very difficult to make meaningful cost comparisons, as individual water projects are by their nature unique. That said, certain patterns can be discerned. Generally, the Disinfection/Sterilisation solution is way and by far the cheapest solution in cost per house terms and the DBO treatment plant solution is the most expensive. Some of the DBO plants appear to have lower cost per houses than others, which could be as a result of the economies of scale of the size of the schemes or the size of the overall DBO Bundle. The practice of procuring DBO treatment plants in bundles to create critical mass rather than individually appears to have been successful in attracting more competitively priced bids. That said, it must be remembered that the DBO figures are provisional due to the current lack of final accounts as these Schemes are only just completed. Therefore, it is likely that the cost per house for DBO Schemes are actually understated as there are outstanding Design Build costs yet to be included. Provisional Operational and Maintenance (O&M) data for DBO treatment plants would suggest that the variable O&M costs of DBO plants are lower than the local authority variable charges for non-domestic Group Scheme consumers connected to the public mains. More definitive data and further study is necessary to confirm this. However, there is anecdotal evidence to suggest that an awareness of the relatively higher cost of local authority water charges is motivating non-domestic Group Scheme members to favour the DBO treatment solution over connection to the public mains or Council takeover. By contrast, many domestic Group Scheme consumers would probably be better off being connected to the public mains, where this is a viable option, as they would receive up to 50,000 gallons of water per house free each year and would not have to pay DBO O&M costs. Discussion of Water Quality Upgrade Conclusions As can be seen from the above analysis, Disinfection/Sterilisation is generally the cheapest water quality upgrade solution with DBO treatment plants the most expensive. However, 198 Disinfection/Sterilisation is limited as an option to a relatively small number of County Councils areas where the water chemistry, mainly groundwater, is naturally of a high standard. Even with that, there are issues with the sustainability of this minimal treatment solution due to inadequate source protection and poor management of treatment infrastructure and pipe networks by some Group Schemes. Local authorities should insist that members of such Group Schemes participate in training programmes provided by the Water Services National Training Group (WSNTG) or otherwise face prosecution under the Drinking Water Regulations. It should be noted that the Disinfection/Sterilisation treatment solution appears to be working quite well in some areas due to the diligence of Group Schemes in maintaining their water treatment infrastructure. In some other cases, it is only an interim treatment solution and it is intended that it will be superceded by a more robust treatment solution in the future. A more consistently effective and relatively cost efficient solution is connection to the public mains or complete takeover of Group Schemes, which are within a reasonable distance of existing public mains. However, as already discussed, some Group Schemes have delayed solution implementation or opted for standalone DBO treatment plants rather than connection to the public mains due to local authority charges for non-domestic water charges. Local authorities must continue to stand firm on this issue particularly where connection to the public mains is the far cheaper option on value for money grounds. Also, it is important to ensure that the interests of domestic consumers on Group Schemes are protected as, in many cases, they are financially better off being connected to the public mains, where this is possible. Finally, while DBO treatment plants are relatively expensive on a cost per house basis, they are often the only viable treatment solution for Group Schemes, which are remote from the public mains, and where the raw water quality is inadequate for minimal disinfection/sterilisation treatment. It is clear that achieving value for money was a strong factor in developing DBO projects. Evidence of this is shown by initiatives such as: Bundling of DBO projects to attract innovative and competitive bids from the national and international water infrastructure construction market 199 Merging/Sub-bundling of schemes to reduce the number of treatment plants required Change from Pre-tender to post-tender planning to encourage more cost effective designs Transference of construction risk to DBO contractor by limiting capital cost increases Economic plant design capacities with water conservation measures to reduce leakage and over abstraction of water for treatment purposes It is essential that the Department and Councils continue to try and deliver these projects on as economical a basis as possible through measures such as DBO procurement bundling and sub-bundling, to avail of treatment technologies at the most competitive market prices, and also through economical plant designs with minimal UFW allowances. Non-Water Quality Upgrade Measures Network Upgrades Expenditure on pipe network upgrades of €105 million was the second highest spending capital measure during 2003-’06 after DBO projects. It has been shown from various leakage studies that leakage control measures, including universal metering and the replacement of critical network mains, to reduce unaccounted for water (UFW) is more efficient than building additional plant treatment capacity. Network upgrade expenditure is also needed to sustain treatment solution effectiveness by avoiding the recontamination of treated water in sub-standard Group Scheme pipe networks. The National Federation of Group Water Schemes (NFGWS) predicts that “replacement of sub-standard networks will be the next major infrastructural challenge facing the rural water sector” (Appendix 3). It should be noted, however, that in many of the cases examined in this study, the network upgrade cost exceeded the actual treatment solution cost, with complete network replacement in some cases. It is important, therefore, that expenditure on network upgrades and critical mains replacements is carefully targeted based on sound engineering assessments of the location of leaks and the future hydraulic needs of the pipe network. 200 Annual Domestic Subsidy This is a relatively small element of the Rural Water Programme but an ongoing current expenditure commitment. There has been a 50% increase in annual expenditure from €5.3 million to €7.9 million between 2003-2006. This rate of annual expenditure is likely to increase in the short term as many Group Schemes begin to claim the higher €196.81 per house rate for the operation and maintenance of their new DBO treatment plants. The National Federation of Group Water Schemes have made proposals for increases in the domestic water subsidy rates to reflect the current operational and maintenance (O&M) costs for Group Schemes. However, any decision to increase domestic subsidy rates must be based on a rigorous study of metered water usage data to ensure that there is no cross subsidisation of non-domestic water consumers or subsidisation of UFW leakage levels in excess of the 25% limit. Also, Councils must continue to ensure that Group Schemes observe the conditions of the Subsidy scheme. The Department may also need to consider making active source protection measures by Group Schemes a condition for payment of the subsidy. The State’s annual domestic subsidy payment, to households connected to Group Schemes, is likely to remain in place for the foreseeable future, on the grounds that it provides some level of equity with domestic water consumers on the public water system. New Schemes and Scheme extensions This is a very significant measure as new Group Schemes could potentially add to the number of sub-standard schemes requiring water quality upgrades in the future, if not controlled. Analysis of New Schemes measure indicates that 72% of the 610 new schemes constructed during the 2003-’06 period, were built with a connection to the public water supply. The number of new Group Schemes built with private water sources declined each year. This is a very encouraging sign as the EPA has identified Group Schemes with private sources as being the main risk factor for water quality problems. If any new or extended scheme grows to beyond 15 houses or connects in to a premises with a public or commercial function e.g. dairy farm, then the water quality must comply with the parameters of the Drinking Water Regulations and water treatment upgrades may be required. 201 Potential Future Funding Commitments It is clear from the June 2006 Report to the European Commission that there is still considerable work to be done, which will require capital funding. Although, the bigger schemes have been identified, the number of smaller Group schemes serving a commercial or public function has yet to be finalised. Councils were asked to identify such schemes as part of the data collection for the June 2006 Report to the European Commission. Some schemes were identified but it is believed that a significant number of others exist. One of the difficulties is that commercial or public function is not specifically defined under the Drinking Water Directive or Regulations. The EPA did, however, issue a guidance circular (DW 01/06) in relation to this on 11th May 2006 and included dairy farming and food production as commercial functions. Given that Group Schemes are located in rural agricultural areas, it is fair to assume that there are a considerable number of small Group Schemes with connections to a dairy farm. It is imperative, therefore, that local authorities identify such Group Schemes in their area so that upgrading solutions can be determined and put in place. The EPA have been granted additional enforcement powers under the 2007 Drinking Water Regulations to ensure that local authorities identify and adequately monitor the water quality of Group Water Schemes required to comply with the Regulations. For all upgrade solutions, except local authority takeover, Group Schemes continue to be responsible for the maintenance of their pipe networks. Local authorities and DBO Client Representatives have both identified poor network maintenance and re-contamination of treated water in Group Scheme networks as possible risk factors. This is exacerbated by the fact that volunteerism in the Group Scheme sector is gradually declining and the National Federation of Group Water Schemes has identified the future need for professional managers for some Group Schemes. The alternative is that more and more Group Schemes will have to be taken into public charge at even greater cost to the taxpayer. As already stated, the NFGWS also predicts that future investment will be required to replace sub-standard pipe networks. It is likely, therefore, that even after the present programme of water quality upgrades is complete, there are likely to be continuing financial demands from the Group Water Schemes sector. 202 Alternative Organisational Approaches The options essentially are that the programme should continue to be run by local authorities or alternatively be transferred back to Departmental control. Given the current urgency to upgrade Group Schemes, it is questionable whether there would be any added value in recentralising the administration of the programme. In fact, any radical administrative changes during this critical period would be likely to disrupt rather than improve programme implementation. It was concluded that the diversity and community nature of the Group Schemes Programme means that it is best administered on a local authority basis by a cohort of dedicated Rural Water Liaison officers and should remain so. There is, however, an inconsistency in implementation under the various water quality upgrade solutions and lack of routine data reporting to the Department on programme outputs. Revised data reporting requirements for Councils are proposed in Chapter 6 on Physical Indicators. Possible implications of ECJ fines Given the potential threat of European Court of Justice (ECJ) fines if Ireland does not comply with the Drinking Water Directive in relation to Group Schemes, it is essential that the water quality upgrade programme is completed without delay. Local authorities have been given a broad range of powers under the Drinking Water Regulations 2007 to take action against nonco-operating Group Schemes and to carry out remedial works themselves if necessary. Given that the implementation of the Rural Water Programme is devolved to individual local authorities, it does not seem equitable to expect national taxpayers to have to carry the whole burden in the event of ECJ fines being imposed due to a local infringement. This would be particularly the case if fines were imposed due to the inertia of a small number of Councils in enforcing their powers under the Drinking Water Regulations against non-cooperative Group Schemes in their administrative area. It could be more equitable to develop a mechanism whereby such Councils carry the cost of potential fines through their annual Local Government Fund allocation. The Department has already warned of the possibility of such sanctions against local authorities in public fora (Athlone Seminar for Rural Water Liaison Officers-June 2006). 203 Alternative Policy Approaches - Source Protection Article 7.3 of the EU’s Water Framework Directive states that “Member State shall ensure the necessary protection for the bodies of water identified with the aim of avoiding deterioration in their quality in order to reduce the level of purification treatment required in the production of drinking water”. This would appear to indicate that in the future ‘end of pipe’ treatment of polluted water may no longer be regarded as sufficient and that member states will be legally required to ensure that their water sources do not become contaminated in the first place. Therefore, the issue of source protection of drinking water supplies is likely to come to the fore in the future. The National Federation of Group Water Schemes also agrees that ‘end of pipe’ solutions are not sustainable into the future. The Department is currently working on a Master Plan to meet the requirements of the Water Framework Directive and specifically to produce River Basin Management Plans (RBMP) by 2009. It is also currently engaged with the Department of Agriculture and Food in the implementation of a National Nutrient Management Plan, in order to comply with the 1991 Nitrates Directive, to reduce the impacts of the land spreading of fertilisers and other nutrients on water sources. The Department has issued guidance to local authorities on groundwater protection (SP05/03) and is currently funding a National Pilot Source Protection Study of Churchill Oram Group Water Scheme in County Monaghan. This will also include an extensive survey of the condition of septic tanks and their potential impacts on water quality. The Water Services Act 2007 gives additional enforcement powers to local authorities to require householders to properly maintain septic tanks. Active local source protection measures by Group Schemes may also need to be added as a condition for receipt of the annual domestic subsidy payment. Performance Indicators The Review of the Rural Water Programme has found that there is a mismatch between inputs and outputs measurement categories for reporting purposes (see Chapter 6). Inputs and outputs reporting relating to differing objectives are also mixed in together. There is also a need for more output data in relation to capital spending measures, unrelated to compliance with the Drinking Water Regulations. There is also a need for earlier water quality exceedances information from local authorities in relation to Group Schemes, which are 204 required to comply with the Drinking Water Regulations. Data needs to be periodically collected on new Group Schemes requiring compliance with the Drinking Water Regulations, due to an expansion in the Schemes’ size or connection to premises, with a public or commercial function. Finally given the level of expenditure on pipe network upgrades, the Department and local authorities should set specific UFW reduction targets as the outcome for such investment. Recommendations of the Rural Water Programme Review General Recommendations 1. The Programme of water quality upgrades required to comply with the Drinking Water Regulations must be completed without delay to protect the public health of Group Water Scheme householders. 2. It is important that the Department reminds Councils that while a partnership approach with the Group Schemes’ sector is vital for programme implementation, the ‘most economically advantageous’ effective treatment approach must ultimately continue to be adopted in the interests of the taxpayer. Local Authority Final Accounts for all water quality upgrade projects should verify that all alternative water treatment options were considered and costed. Final Account verification should also be provided that Group Scheme capital contributions have been fully paid and that the Department’s €6,476 per house grant limit has not been exceeded. DBO treatment solution (p.86.) 3. While the local authority questionnaire returns suggests that in most cases, the DBO option was the most cost efficient solution adopted for that situation, there is a need for greater transparency in relation to this. It is recommended that for all future DBO project proposals, a report should be prepared costing all alternative options to the DBO route and comparing those costs to the DBO cost. 4. County Councils have stated that in most cases all alternative options to DBO were costed but verification of this was not provided, in most cases, within the time limits 205 of this Review. This verification should be included in the local authority Final Accounts of all DBO Bundles completed to date as well as confirmation of the final cost of the civil works contract and the payment by each Group Scheme of their 15% capital contribution. This is important for transparency and will also be of assistance to the Office of the Comptroller and Auditor General in any future audit of DBO Bundle expenditure. 5. In future cases where Group Schemes cannot be connected to existing public supplies due to insufficient existing plant capacity, the cost of increasing existing public water treatment plant capacity must be considered as an option by local authorities. 6. Local authorities should continue to assess opportunities for achieving greater value for money, when planning future DBO Bundles, by rationalising the number of water treatment plants in DBO Bundles so that two or more Group Schemes can be served by the same treatment plants. Non-DBO solution (p.108) 7. The effectiveness of this solution is questionable possibly due to inadequate operation and maintenance of the treatment solution by some Group Scheme volunteers. Local authorities should insist that members of these Group Schemes participate in training programmes provided by the Water Services National Training Group (WSNTG) in such cases or otherwise face prosecution under the Drinking Water Regulations. In cases where inadequate maintenance is not the problem, Councils should review the effectiveness of this solution for such Group Schemes. Public Source Solutions (p.113.) 8. Implementation is the main problem for public source solutions mainly due to resistance to local authority water charges for non-domestic Group Scheme consumers. Local authorities must, where necessary, utilise the new powers available to them under the 2007 Drinking Water Regulations to take enforcement action against non-co-operating Group Schemes, including the direct implementation of remedial works. 206 Disinfection/Sterilisation Solution (p.129.) 9. The effectiveness issues in relation to the Disinfection/Sterilisation solution are a matter for concern given that it is the water quality upgrade solution selected for 122 Group Schemes (17% of the total). Local authorities should insist that members of non-compliant Group Schemes, using this treatment solution, participate in training programmes provided by the Water Services National Training Group (WSNTG) or otherwise face prosecution under the Drinking Water Regulations. In cases where disinfection/sterilisation is only an interim treatment solution, local authorities should put permanent solutions in place as soon as possible. 10. While there were no exceedances of Trihalomethanes (THMs) identified for any of the four Counties studied, the proportion of schemes tested for THMs in each County was quite small. It might be prudent if local authorities increased the level of testing for THMs for Disinfection/ Sterilisation schemes, given the possible carcinogenic risk factors. 11. Where vulnerable water sources are identified as a risk factor for the sustainability Disinfection/Sterilisation treatment solution, local authorities should require the relevant Group Schemes to implement more robust local source protection measures. Network Upgrades (p.143.) 12. Given that network upgrade costs frequently exceed water treatment costs and that the NFGWS have predicted that demand for network upgrades will increase, it would be timely to issue updated guidance to Councils in relation to approving pipe network upgrades. Such upgrades should only take place based on the results of a methodical leakage control study to ensure that upgrade funds are targeted at replacing critical mains. In addition, where substantial network upgrades are being proposed, a hydraulic study should be carried out to ensure that the proposed upgrades will meet the future requirements for 2025 demand+25% UFW. 207 13. It is vital that the Department considers funding universal metering of all Group Water Schemes being upgraded under the Rural Water Programme, as there is no incentive to conserve water or minimise waste without it. Such grant aid is currently only available to DBO Schemes under the network upgrades measure and consideration should be given to extending this to all upgraded Group Schemes. Quite apart from being a charging tool, meters are more importantly a vital management tool for operating water distribution systems and identifying the precise location of water leakages. It will also create greater transparency in relation to the sources of water usage and leakage in Group Schemes, particularly between domestic and non-domestic users. In this way, it reduces the risk of cross-subsidisation of the non-domestic users by domestic users and the subsidisation of excessive UFW, through the domestic household subsidy. Additional metering could be funded through savings created by a more targeted approach to network upgrades, based on leakage control studies. The National Federation of Group Water Schemes (NFGWS) have expressed support for the concept of universal metering of Group Scheme connections (See Appendix 3). Domestic Household Subsidy (p.152.) 14. Any decision to increase domestic household subsidy rates must be based on a rigorous study of metered water usage data to ensure that there is no crosssubsidisation of the non-domestic sector by the domestic sector, at the tax payers’ expense. Also, an increased domestic subsidy cannot be used to subsidise UFW leakage levels on Group Schemes in excess of the 25% limit. 15. Local authorities must ensure that the achievement of policy objectives such as water conservation, water quality and transparency for Group Water Scheme members, as already required under the existing subsidy scheme, are being implemented by Group Schemes. 16. There is also a need to link the payment of subsidies to the active implementation of source protection measures by Group Schemes to protect their drinking water sources from contamination. 208 New Group Schemes (p.159.) 17. All new Group Schemes approved must be connected to the public mains or an existing DBO treatment plant, where it is technically and economically viable to do so under existing grant limits. 18. New Group Schemes with private sources should only be licensed where there is no other viable drinking water solution for existing houses. 19. New Group Schemes with private sources should not be licensed unless a comprehensive risk assessment of alternative water sources has been carried out, and the optimum water source has been selected. 20. Active local source protection measures should be put in place for new Schemes, which can be verified by Councils on an audit basis, as a condition for continued subsidy or capital funding. 21. New Group Schemes should only be licensed in areas where it is verified that they are compliant with local authorities’ County Development and Local Area Plans for housing development. Potential future funding issues/ECJ fines (p.163.) 22. Local authorities should ensure that all small Group Schemes in their area, connected to commercial or public premises, are identified so that water quality upgrading solutions, if necessary, can be put in place for these Schemes, to comply with the Drinking Water Regulations. The Minister for the Environment, Heritage and Local Government has given the Environmental Protection Agency (EPA) additional enforcement powers under the 2007 Drinking Water Regulations to ensure that local authorities fulfill their statutory monitoring obligations in this regard. 23. Local authorities and DBO Client Representatives have both identified poor network maintenance and re-contamination of treated water in Group Scheme networks as risk factors. Local authorities should require members of non-compliant Group Schemes to 209 participate in training programmes provided by the Water Services National Training Group (WSNTG) or otherwise face prosecution under the Drinking Water Regulations. In the longer term, the Department, in conjunction with local authorities and the NFGWS, may need to consider alternative professional based approaches to Group Scheme maintenance due to declining volunteerism in the Group Schemes sector. 24. Given that the implementation of the Rural Water Programme is devolved to individual local authorities, it does not seem equitable to expect national taxpayers to have to carry the whole burden in the event of ECJ fines being imposed due to a local infringement. This would be particularly the case if fines were imposed due to the inertia of a small number of Councils in enforcing their powers under the Drinking Water Regulations against non-cooperative Group Schemes in their administrative area. It could be more equitable to develop a mechanism whereby such Councils carry the cost of potential fines through their annual Local Government Fund allocation. Alternative Policy Approaches – Source Protection (p.170.) 25. Given the implications of the Water Framework Directive and the costs of compliance with the Drinking Water Directive, the Department may need to consider introducing more robust measures in the future in order to protect drinking water sources from contamination. Local authorities should first implement the existing powers available to them. Active source protection by all Group Schemes should be added as a condition for receipt of the annual domestic subsidy payment. Performance Indicators (p.175.) 26. The Performance Indicators proposed in Chapter 6 should be used to better monitor the performance of the Rural Water Programme. Given the level of expenditure on pipe network upgrades under the Rural Water Programme, the Department and local authorities should set specific UFW reduction targets as the outcome for such investment. 210 Conclusions For the future then, there will have to be a number of priorities. Public health has to be the first and foremost objective. Therefore, implementation of all remaining water quality upgrades must proceed without further delay in order to comply with the Drinking Water Regulations. Secondly, the water quality upgrade solution selected for each Group Water Scheme must be both effective in ensuring compliance with the Drinking Water Regulations and also must be the most cost efficient workable solution, from the perspective of the taxpayer. Therefore, Group Schemes should be connected to the public mains, where this is the more economically viable option. Also where a DBO treatment plant is the only viable option, the number of treatment plants in a DBO bundle should be rationalised to serve two or more Schemes, where this is technically possible and economically viable, in order to keep the number of treatment plant constructed to a minimum. The levels of capital grant aid being paid to the Group Schemes’ sector is relatively generous by European standards (see Scottish example in the Literature Review) so it is only fair that the Irish taxpayer receives value for money from this investment. Ongoing investment in leakage control, targeted network upgrades and metering is also vital to reducing UFW and operating Group Schemes in a more cost efficient manner. There also needs to be a greater emphasis on source protection measures rather than just ‘end of pipe’ treatment solutions. Much has been achieved from the Department’s relationship of co-operation and consultation with the Group Schemes’ sector through the National Rural Water Monitoring Committee (NRWMC). The National Federation of Group Water Schemes (NFGWS) was founded in 1997 to try and achieve parity of treatment for rural communities from the State (Rural Water News-Spring 2007). The domestic household operational subsidy was introduced as a way of creating greater equity for domestic householders connected to Group Schemes, by comparison to their counterparts on the public water supply. The Department and local authorities must continue to work with the Group Schemes’ sector in the same spirit of cooperation dealing with the interests of both domestic and non-domestic Group Scheme consumers in an even handed manner. Local authorities must ensure that the interests of domestic consumers are protected in decisions in relation to Group Scheme solutions and also that non-domestic consumers are treated in an equitable manner to their counterparts on the public mains. 211 The Department and local authorities have demonstrated a large degree of innovation in trying to achieve value for money in the delivery of water quality upgrading solutions to the Group Schemes’ sector. This is particularly noticeable in the case of DBOs. 10% of the Irish population are served by Group Water Schemes and, unlike the public water sector, its domestic consumers have to directly contribute towards the operational costs of providing treated water to that sector. Many of these voluntarily run Group Water Schemes have shown great innovation in reducing their operational and maintenance (O&M) costs through water conservation and leakage control measures. There is recognition in many Group Scheme households that water is a valuable environmental resource, which should not be wasted and such initiatives provide an example to producers and consumers of drinking water in the public water sector. 212 Appendices 213 Appendix 1 Breakdown of relevant Group Water Schemes by County Source: Report to the European Commission on Measures to bring Group Water Schemes into compliance with the Drinking Water Directive – June 2006 p. 8. Note: Explanation of terms in above table Schemes – No. of Group Water Schemes Domestic – No. of domestic connections i.e. households Annex 14 Schemes – Group Schemes serving > 50 persons cited in 2002 ECJ ruling Non-Annex 14 Schemes - Schemes serving > 50 persons not cited in 2002 ECJ ruling but subsequently identified by local authorities as requiring compliance 214 Appendix 2 Membership of National Rural Water Monitoring Committee Chairman: Dr. Tom Collins, NUI Maynooth Secretary: Mr. Carthage Cusack, Department of the Environment, Heritage and Local Government Member Organisations County and City Managers’ Association Irish Countrywomen’s Association Irish Creamery Milk Suppliers Association Irish Farmers’ Association National Federation of Group Water Schemes General Council of County Councils Local Authority Members Association Department of Community, Rural and Gaeltacht Affairs Department of the Environment, Heritage and Local Governme 215 Appendix 3 National Federation of Group Water Schemes (NFGWS) response to questions re. Rural Water Programme Value for Money (VFM) issues 1. What, in your view, would be the outcome if the State simply required the GWS by law to meet the criteria of the Drinking Water Directive, without providing capital funding, and passed on any fines for non-compliance to individual GWS? When originally established, group water schemes were driven primarily by the requirements of farming. Drinking water quality was not an issue, particularly as many households retained individual wells for their potable supply. The transition of schemes to providing drinking water as their primary focus only commenced following the establishment of the National Federation of Group Water Schemes and the introduction of State investment under the Rural Water Programme in 1998. Without capital grant aid, the sector simply could not meet the obligations of the Drinking Water Directive. With few exceptions, schemes that are noncompliant at present would remain so, as they would not be able to raise the resources to remedy the situation, while at the same time meeting the costs of other capital works and general maintenance and administration. This would inevitably result in committees of management simply ‘walking away’ (rather than being held legally accountable) and schemes collapsing. In such a scenario, local authorities would have no option but to move in to upgrade and administer them. This would require substantially greater State resources than the current investment programme which benefits from the voluntary input of local GWS activists and a 15% local contribution towards capital works (apart from the cost of water treatment). 2. What, in your view, would be the outcome if the State withdrew current funding i.e. the subsidy for GWS? Apart altogether from the iniquitous situation that would arise vis-à-vis the water entitlements of consumers on public schemes (that are wholly subsidised) the NFGWS feels very strongly that the part-funding, through subsidy, of the management and operation of a group scheme is an absolute prerequisite to the modernisation and continued sustainability of the GWS sector, not least in ensuring compliance with the Drinking Water Directive. While the NFGWS (through our Management Training Course and quarterly magazine) is actively encouraging schemes to move towards pricing structures that will lead to increased self-sufficiency in the long-term, there is still some distance to go before this is achieved. In the short to medium term, therefore, the operational subsidy will remain essential, while a subsidy in respect of the fixed element of water treatment will be required for the O&M contract period. 3. Is the current subsidy level adequate? What safeguards are in place to ensure transparency so that domestic consumers are not subsidising non-domestic water usage in Group Schemes? It is totally inadequate at present. The last review of subsidy levels was in March 2000. Subsidy levels, at present, do not reflect the growing financial demands on schemes in the new and ever-changing legislative and regulatory environment that exists for water supply services. As with other organisations, we are finding that the purely voluntary effort of a few 216 dedicated individuals (and they are getting fewer!) is not equal to the demands of a modern water service. As a result (and to ensure schemes maintain quality in all aspects of their business) the NFGWS is promoting the employment of paid management/maintenance personnel on group schemes and a move towards greater professionalism in all areas of the administration. Apart from the rising costs of administration, some schemes face very high DBO fixed costs (for treated water), yet these costs have to be met for the next 20 years. Even with appropriate charges on metered usage, this creates a huge and ongoing financial burden on schemes and leaves them with very few resources to invest in wider scheme management/administration. As for safeguarding domestic consumers, universal metering is being introduced both as a water management tool and as the basis for an equitable charging system that fully reflects the principle of ‘polluter pays’. Charging on metered usage protects domestic consumers from cross-subsidising the business or farming sectors. 4. Is the annual Dept grant to the NFGWS necessary for funding its operations? Yes, it is! The partnership arrangement introduced under the Rural Water Programme established the active participation of three stakeholders; the Department, local authorities and the NFGWS. It was agreed that the latter two (local authorities and the NFGWS) would require State funding to perform their respective roles. While the federation is very grateful and fully acknowledges the assistance we receive from the State, we sincerely believe that VFM is being achieved. Further, we firmly believe that the range of activities undertaken by the federation in advancing the Rural Water Programme would not be possible without continued funding. In brief, this funding has supported the reinvigoration of the entire rural water sector through the direct guidance, encouragement and training programme of the NFGWS. We would argue that the supports currently available should be increased and index-linked to inflation to reflect the ever-expanding workload of the Federation in preparing schemes to meet the new environment for drinking water services. For details of the wide range of those services and the active delivery by Federation staff, we would refer you to our Annual Reports, Strategic Plan and quarterly magazine, all of which are available on our website at www.nfgws.ie. 5. What level of contributions are householders typically making from their own resources towards O&M costs? Because subsidy hasn’t been reviewed since 2000 and, therefore, doesn’t reflect the full costs of providing a drinking water service, schemes are forced to charge households for a proportion of O&M costs. It is difficult to provide a ‘typical’ contribution as costs vary, depending on several factors (raw water quality, size of scheme etc.). To meet their costs, schemes will charge up to €100 as an annual membership contribution. After this, metered usage can be as high as €4.50 per 1,000 gallons used over the ‘free’ allocation. 6. What level of contributions are householders typically making from their own resources towards capital costs? Again, this varies, but depending on the extent of capital works involved and the levels of grant-aid available, householders on group water schemes are paying up to €1,200 as a direct 217 contribution to infrastructural upgrades. The average contribution would probably be in the region of €600 a household. In some instances, where population density is low and where the local contribution would otherwise be in excess of €1,200, CLÁR funding has been a welcome addition. 7. Are all GWS receiving equal benefit under the different treatment solutions? All schemes that comply with EU and National Procurement rules in pursuing an agreed and approved upgrading strategy would appear to be receiving equal benefit. Where schemes decide to pursue a go-it-alone upgrade and/or fail to follow the conditions required for funding, the costs are borne entirely out of their own resources. 8. Are GWS households being dealt with equitably compared to urban dwellers? No. Householders on public schemes have an unlimited supply of free treated water. They are not required to make any direct contribution to capital works or the maintenance of their water supply network. However, subsidy and State capital grants do redress the imbalance to some extent. 9. What is the NFGWS view on the application of non-domestic user charging for water across the different treatment solutions? The NFGWS fully supports the principle of non-domestic charging, providing it is fair and equitable and relates to cost and metered usage. We believe that this principle should apply, irrespective of the different treatment solutions. 10. What is the NFGWS view on UFW levels in GWS and the cost implications? Would universal metering of all GWS not provide better management information to address UFW problems and also to ensure that Group Schemes are not subsidising individual members overusing/wasting water? The Federation is fully committed to dealing effectively with the unacceptably high UFW levels identified on many group water schemes. We have resolutely pursued the adoption of universal metering as a demand management tool, particularly in the context of DBO bundle projects. To this end, all schemes involved in such projects (representing the vast bulk of the sector) will be fully metered by 2009. We acknowledge the importance of the additional financial supports towards achieving this objective. Furthermore, we believe that all schemes have to move to universal metering and would welcome Department support in this regard, as per our recent submission. We would add that there is a growing recognition amongst schemes that universal metering is key to ending wastage and also to fairness in charging. The NFGWS firmly believes that universal metering of schemes is the only way to avoid any perception that one member is subsidising another. The charges put forward by committees are generally agreed at an AGM of the members. As such, they must be fair and equitable, and must be seen to be so. People should pay for what they waste/use and this is the advice the Federation gives to schemes on an ongoing basis. We would be happy to forward particular and incontrovertible evidence of the success of the Federation and of individual 218 schemes in significantly reducing UFW levels in recent years, both as a result of universal metering and the introduction of effective leak detection strategies. 11. What is the likelihood substandard distribution systems? of recontamination of treated water in With regular maintenance and monitoring of chlorine residual the risk is low, but it cannot be ignored. The focus of the Federation is on encouraging proper record-keeping on schemes and we also plan to begin (later this year) delivering the NFGWS Quality Assurance Scheme on GWS that have upgraded. Even with these efforts, however, there is little doubt that replacement of substandard network will be the next major infrastructural challenge facing the rural water sector. The concerns of the sector in relation to this issue are reflected in motions adopted at our recent Annual Delegate Conference. 12. What is the NFGWS view on source protection measures and the effects of one off housing, farming practices and septic tanks on water quality and subsequent treatment costs? The group scheme sector is pro-actively pursuing source protection as one of our key objectives. We recognise that this is an issue that will grow in importance in the years ahead and we are mindful of the fact that end-of-pipe solutions can never of themselves provide a sustainable answer to water pollution. The NFGWS was instrumental in the establishment of a National Source Protection Pilot Project, based in a group scheme source catchment, that would be capable of roll-out across the GWS sector. This pilot is adopting a communitybased, low-technology approach to the issue and aims to harness local awareness of and support for source protection initiatives. The project is currently examining the impact of point and diffuse sources of pollution from farming and from septic tanks and early evidence would suggest that the impacts may be site specific and that they may be remediated through simple measures such as denying cattle direct access to a lake catchment, proper construction and regular desludging of wastewater treatment systems and common sense. Where one-off housing is regulated and particular attention is paid to the proper installation of wastewater systems and their desludging, we feel that they are not incompatible with source protection. We would also be keenly aware of the need to sustain the population base of rural communities and recognise that one-off housing is a factor in achieving that sustainability. The Federation will, however, wait for the final report of the Source Protection Project before making a definitive evaluation of these issues. 13. What is the NFGWS view on continued funding for new GWS in view of the cost implications of the Drinking Water Directives particularly for small schemes with commercial connections? Except in exceptional circumstances, new schemes should be funded only where they are connecting to an existing treated supply, be that public or private. The Federation view is that (depending on the scale of treatment required) very small schemes are simply not viable in the context of maintaining compliance with the Drinking Water Directive and meeting the wider regulatory and legislative demands on water suppliers. Where public or private suppliers have 219 proven capacity in their existing supplies, they should be obliged to facilitate the extension of that supply to an unserviced area. 14. What legal provision is there requiring connect in new GWS to their DBO plants in the future? existing DBO Groups to We are not aware of any legal responsibility in this regard. However, it is generally the practice of group schemes to welcome new members, subject only to the source, treatment system and infrastructure being capable of servicing an expanded network. The NFGWS drew up a Charter of Right and Responsibilities that has been adopted by schemes. This emphasises that as a condition for claiming subsidy and where they have sufficient capacity, group schemes must not deny a householder water. Perhaps existing capital grant aid might also be looked at in regard to this issue, to deal with the small handful of schemes that will not facilitate an extension to unserviced communities. 220 Appendix 4 20 November, 2006 Circular L9/2006. To each County Manager Value for Money Review of the Action Plan for Rural Drinking Water Quality 2003-2006 A Chara, I wish to advise you that this Department has recently commenced a Value for Money Review of the Rural Water Programme. This Review forms part of the 2006-2008 programme of Value for Money Reviews approved by the Government in June 2006. The Review will focus on the implementation of water quality upgrading solutions for Group Water Schemes, falling within the remit of the Drinking Water Regulations, 2000, during the period of the Action Plan for Rural Drinking Water Quality 20032006. The Small Public Water and Sewerage Scheme and Well Grant elements of the Rural Water Programme will not be reviewed as part of this study. The terms of reference for the Review (see Appendix 1) are in line with Department of Finance guidelines. As the administration of the Rural Water Programme is largely devolved to local authorities, the efficiency and effectiveness of the local government system in meeting the objectives of the Action Plan for Rural Drinking Water Quality 2003-2006 will be a central element of the Review. Accordingly, as a first step in this Review, each local authority is asked to complete the attached questionnaire. Local authorities are also welcome to make additional submissions, relevant to the terms of reference of the Review. Individual local authorities will be contacted in the coming months in relation to specific Group Water Schemes in their administrative area. Information already provided in previous local authority returns, including the June 2006 Report to the European Commission, will also be used as part of the Review. The attached questionnaire has also been e-mailed to all Rural Water Liaison Officers. Local authorities are asked to return the completed questionnaire (both by e-mail and signed hard copy) and any other submissions by 15th December 2006. Submissions should be forwarded to Frank Gallagher, Water Services Section, Block 1, Irish Life Centre, Lower Abbey Street, Dublin 1 (frankJ.Gallagher@environ.ie). Frank Gallagher Assistant Principal Officer Water Services Section Tel. No. 01-8882771 Cc: Rural Water Liaison Officers 221 Local Authority Questionnaire re. Rural Water Programme This Review is focusing on the period of the Action Plan for Rural Drinking Water Quality 2003-2006 and the implementation of water quality upgrading solutions for Group Water Schemes falling within the remit of the Drinking Water Regulations, 2000. All references to Group Water Schemes in questions below (except Q.23, Q.24, Q25 & Q.26) only refer to those schemes, which require water quality upgrading to comply with the Drinking Water Regulations, 2000 i.e. schemes serving greater than 50 people. The references to water quality upgrading solutions below refer to the five solutions identified in the June 2006 Report to the European Commission i.e. Design Build Operate (DBO), Non-DBO, Connection to the public main, Takeover by local authority and Sterilisation/Disinfection. Please provide a response to each of the questions below (using as much space as you need) and e-mail the completed questionnaire to frankJ.gallagher@environ.ie by 15th December 2006. Value for Money Question 1 Did your local authority select the most economically advantageous water quality upgrade solution for all Group Water Schemes in your administrative area (as specified in the Rural Water Strategic Plan Guidance Documentation)? Yes No If No, please state reason?………………………………………………………… Question 2 Did your local authority carry out a comparison of the relative cost of building/upgrading a water treatment facility for each Group Water Scheme (or sub-bundle of schemes) or alternatively connecting the scheme(s) to an existing public water supply? Yes No If No, please state reason? If there was insufficient available public water capacity, was the option of increasing public water capacity considered and costed? …………………………………………………………………….………….……… If Yes, please state where this information is documented?…………………………... Question 3 Is competitive tendering being used in the procurement of all contractors for the implementation of all water quality upgrading solutions (including necessary network upgrades) for all Group Water Schemes in your local authority’s administrative area? Yes No 222 If No, please state reason?………………………………………………………… Question 4 In all cases where it was decided to procure water treatment plants using DBO bundles, was a technical/economic assessment of the possibility of connecting a number of Group Water Schemes to the same treatment plant as a DBO sub-bundle considered? Yes No If No, please state reason?………………………………………………………… If Yes, please state where this assessment is documented?…………………………... Implementation of the Action Plan for Rural Drinking Water Quality 2003-‘06 Question 5 What in your local authority’s view are the main obstacles to the full implementation of the current Action Plan for Rural Drinking Water Quality? ………………………………………………………………………………………… ………………………………………………………………………………………… Question 6 What additional measures if any, in your local authority’s view, are needed to fully and successfully implement the current Action Plan for Rural Drinking Water Quality? ……………………………………………………………………………………… ……………………………………………………………………………………… Question 7 It appears from the June 2006 Report to the European Commission, which was compiled based on local authority information, that the two water quality upgrading solutions involving connection to the public water supply i.e. “Takeover by local authority” (3 schemes completed nationally) and “Connection to the Public Main” (6 schemes completed nationally) have not been implemented at the same rate as other upgrading solutions e.g. DBO. Please provide reasons, if any, why there have been delays in implementing the “Connection to the Public Main” upgrade solution in your county? ……………………………………………………………………………………… Please provide reasons, if any, why there have been delays in implementing the “Takeover by local authority” upgrade solution in your county? 223 …………………………………………………………………………………………. Question 8 Please confirm the number of schemes completed for the above two upgrade solutions in your County during the period of the Action Plan 2003-’06 (provide name of Group scheme and month and year of completion in each case). In the case of takeovers, please indicate whether the scheme taken over was on a public or private water supply at the time. If no details are provided, a nil completion will be recorded for your County for the “Takeover by local authority” and “Connection to the Public Main” upgrade solutions. ………………………………………………………………………………………………..… ……………………………………………………………………………….. Question 9 Please provide details in the box below of how many Group Schemes (approx) in your administrative area are participating and not participating in the Action Plan for Rural Drinking Water Quality in implementing a water quality upgrade solution for their scheme? Participating Not Participating No. of Group Water Schemes Total No. of Households (approx) Please state reasons given by Group Schemes for non-participation ………………………………………………………………………………………… Question 10 Please provide details in the box below of how many Group Schemes, who are not participating in the Action Plan for Rural Drinking Water Quality, are in receipt of an operational costs subsidy from the Rural Water Programme. Non-participating Schemes No. of Group Water Schemes No. of Households (approx) Receiving Subsidy Not receiving subsidy Monitoring of the Action Plan for Rural Drinking Water Quality Question 11 In schemes where water quality upgrading solutions have now been completed, what monitoring measures have your local authority implemented to verify that the water coming out household taps in those Group Schemes now fully comply with the Drinking Water Directive on a sustained basis? ………………………………………………………………………………………… ………………………………………………………………………………………… 224 Question 12 Do all Group Water Schemes in your County, where water quality upgrading solutions have been completed, as per the June 2006 Report to the European Commission, now fully comply with the Drinking Water Directive? Yes No If No, please state reasons and provide details of numbers of compliant and non-compliant completed Schemes below? Please also state any risk factors, which could cause currently compliant upgraded schemes to become non-compliant again. …………………………………….………………………………………………….. ………………………………………………………………………………………… Compliant Non-Compliant No. of upgraded Group Water Schemes Total No. of Households (approx) Question 13 What initiatives have your local authority taken to encourage Group Water Schemes to implement improved source protection measures? ………………………………………………………………………………………….. Water Demand and Unaccounted for Water (UFW) Question 14 How does your local authority calculate the maximum allowable plant capacity, when authorising the design and construction (or upgrade) of a water treatment facility for a group water scheme(s)? Please specify the maximum domestic water allowance per house when calculating plant design capacity. …………………………………………………………………..……………………… ………………………………………………………………………………………….. Question 15 What is the maximum level of unaccounted for water, which your local authority permits when authorising the design and construction (or upgrade) of a water treatment facility for a group water scheme(s)? …………………………………………………………………..……………………… ………………………………………………………………………………………….. Question 16 What measures have your local authority taken to encourage group water schemes to reduce their level of UFW? …………………………………………………………………..……………………… 225 ………………………………………………………………………………………….. Water Charging for Group Schemes connected to the Public Water Supply Question 17 Are domestic Group water users charged for their water supply? Yes No Question 18 Are non-domestic Group water users charged for their water supply? Yes No Question 19 How is water usage by domestic and non-domestic Group Scheme consumers measured? ………………………………………………………………………………….. ………………………………………………………………………………….. Question 20 Are Group Water Scheme non-domestic users charged for water on the same basis as nonGroup Water Scheme non-domestic customers e.g. commercial customers in urban centres? Yes No If No, please state reasons. ………………………………………………………………………………………… ………………………………………………………………………………………… Question 21 Please provide details of your authority’s current charging levels for Group Scheme domestic and non-domestic users in the box below. If different Group Water Schemes are charged at different rates, please explain in the space below. Mark N/A, where not applicable. Domestic User Non-Domestic User Connection Fee per house (€) Fixed Charge per house (€) Variable/Volumetric Charge(€ & qty) Free Water Allowance (quantity) Other Charge (please specify) ………………………………………………………………………………………. Question 22 Does your local authority’s water charging system recover your full costs in providing water to Group Scheme customers? Yes No 226 If No, please state reasons. ………………………………………………………………………………………… New Schemes, Network Upgrades and Subsidy Payments for all Group Schemes Please provide details in relation to all Group Water Schemes for the last four questions (Q23 – Q26) not just Group Water Schemes serving greater than 50 persons. Question 23 Please provide details of all newly established Group Water Schemes that have received approval for funding i.e. current (subsidy) and/or capital funding (network or water quality upgrade) for the first time from your local authority during the period of the Action Plan for Rural Drinking Water Quality 2003-2006? Where a new Group Scheme received funding over more than one year, only include/count the Group Scheme and its houses in the first year of funding approval. Year of first funding approval No. of new Group Schemes with a private source Total no. of houses in new Group Schemes with a private source No. of new Group Schemes with a public source Total no. of houses in new Group Schemes with a public source 2003 2004 2005 2006 Question 24 Please provide details of all existing Group Water Schemes that have received funding for an extension by your local authority during the period of the Action Plan for Rural Drinking Water Quality 2003-2006? Where a Group Scheme received extension funding over more than one year, only include/count the Group Scheme extension and its additional houses in the first year of funding approval. First year of extension funding approval No. of extended Group Schemes with a private source Total no. of new houses in extended Group Schemes with a private source No. of extended Group Schemes with a public source 2003 2004 2005 2006 227 Total no. of new houses in extended Group Schemes with a public source Question 25 Please provide details of all existing Group Water Schemes i.e. (not new Group Schemes), which have received a pipe network upgrade during the period of the Action Plan for Rural Drinking Water Quality 2003-‘06? Where a Group Scheme received network upgrade funding over more than one year, only include/count the Group Scheme and its houses in the first year of funding approval. First year of pipe upgrade approval No. of existing private Group Schemes which received pipe network upgrades Total no. of Houses in upgraded private Schemes No. of existing public Group Schemes which received pipe network upgrades Total no. of Houses in upgraded public Schemes No. of Scheme network upgrades (in Columns 2&4 of this table) unrelated to water quality upgrade solutions 2003 2004 2005 2006 Question 26 Please provide details of the number of Group Water Schemes and houses in receipt of the different levels of subsidy during the 2003-’06 period in the table below? Subsidy for houses supplied by local authority source (€50.79 max) No. of No. of Total Schemes Houses Subsidy Paid (€) Subsidy for houses supplied from private source (€101.58 max) No. of No. of Total Schemes Houses Subsidy Paid (€) Subsidy for houses with a DBO/O&M treatment contract (€196.81 max) No. of No. of Total Schemes Houses Subsidy Paid (€) 2003 2004 2005 2006 Thank you for completing the above questionnaire. The questionnaire respondent is asked to provide their name and details in the space provided below. Name: ……………………………………………………………………………… Official Title:………………………………………………………………………. 228 Date: ……………………………………………………………………………….. E-mail address:…………………………………………………………………….. Contact telephone No……………………………………………………………… The Department may need to contact you again in relation to expenditure on specific Group Water Schemes in your administrative area. If there are any further issues that you wish to raise in relation to the implementation of the Action Plan for Rural Drinking Water Quality 2003-2006, please provide details on subsequent pages. Local authorities are asked to return the completed typed questionnaire and any other submissions by 15th December 2006. Completed questionnaires and submissions should be emailed to Mr. Frank Gallagher (frankJ.Gallagher@environ.ie), Water Services Section, Block 1, Irish Life Centre, Lower Abbey Street, Dublin 1 (tel. No. 01-8882771). 229 Appendix 5 Drinking Water Regulations 2000 – Water Quality Parameters 230 Appendix 6 Table 4.1.5 - % Non-Domestic Water Demand (approximate) for DBO Bundles %Non %Non Domestic East Cavan DBO Limerick DBO Consumption Domestic Consumption Billis Lavey 57% Baggottstown 59% Bunnoe 52% Ballinvreena 70% Dhuish 57% Ballybricken 50% Drumkeery 60% Ballyduff 71% Kill 52% Ballyorgan 61% Mountain Lodge 72% Bulgaden 67% Crosserlough 40% Caherline/Newtown 52% Clifferna 54% Cappagh 53% Dernakesh 39% Carnane 36% Glaslough Tyholland 45% Coshma/Killeen 46% Croagh/Farradonnelly 46% Glenroe 30% South West Cavan Erne Valley 82% Glenstal 56% Lavagh/Ballyheelan 38% Granagh 68% Crossdoney GWS 71% Griston 75% Kiltale 58% Kileedy 76% Kilfinny 60% Lough Gur 63% Galway DBO 1 Ardrahan 52% Ballyglass/Fiddane 60% Brierfield 49% Sligo East DBO Caherlistrane 51% Geevagh/Highwood 60% Cleggan/Claddaghduff 29% Keash 56% Cloonatleva 55% Culfadda 45% Cloonluane 6% Corrick 25% Inis Meain 49% Castlebaldwin 46% Kiltevna 45% Toberowen Lissybroder 45% Lettergesh 13% Lowville 50% Milltown 56% 231 New Inn 55% %Non Mayo DBO No. 1 Domestic Consumption Monaghan DBO Ballycroy 45% Aughnashavley 22% Ballyglass/Carnacon 65% Barraghy Belderrig 43% Churchill/Oram 51% Bohola 36% Corduff 24% Brackloon/Spaddagh 55% Donaghmoyne Drummin 32% Doohamlet 34% Glencorrib 35% Drumgoole 69% Glenhest 43% Inniskeen Killeen 40% Killanny Kilmeena 21% Newbliss Kilmovee 35% Smithborough Laghta 26% Stranooden Lough Mask Creevagh 47% Truagh Fahy Drumindoo 32% Tydavnet No Data No Data No Data 5% No Data 14% 7% 15% No Data Source: Figures derived from DBO Client Representative data – January 2007 232 Appendix 7 Provisional Design Build (DB) Costs for completed DBO Bundles – April 2007 West Cavan DBO Scheme Names Glangevlin Doobally Ballymagovern/Corran Corlough Sralaghan Kildallan Milltown Gowlan Bawnboy Public WS No. of Houses Totals East Cavan DBO Scheme Names Billis Lavey Bunnoe Dhuish Drumkeery Kill Mountain Lodge Crosserlough Clifferna Dernakesh Glaslough Tyholland Total SW Cavan DBO Scheme Names Erne Valley Lavagh/Ballyheelan Crossdoney GWS Kiltale Totals Capital Capital Cost Total Capital Cost per per Population DB Cost House population 145 435 €837,130 €5,773 €1,924 52 156 €817,846 €15,728 €5,243 115 345 €609,185 €5,297 €1,766 297 891 €1,241,558 €3,706 €1,235 38 114 230 690 €776,705 €3,377 €1,126 312 936 €989,837 €3,173 €1,058 150 450 €1,114,576 €7,431 €2,477 66 198 €714,315 €10,823 €3,608 1,405 Population Houses 1,290 480 615 1,269 285 1,122 1,638 1,329 561 1,590 10,179 No. of Houses 4,215 €7,101,151 Cost per Cost per Total DB Cost House person 430 €1,052,992 €2,449 €816 160 €782,600 €4,891 €1,630 205 €1,365,723 €6,662 €2,221 423 €918,441 €2,171 €724 95 €880,049 €9,264 €3,088 374 €786,450 €2,103 €701 546 €400,536 €734 €245 443 €293,158 €662 €221 187 €335,461 €1,794 €598 530 €469,403 €886 €295 3,393 €7,284,812 Capital Total Capital Cost per Capital Cost Population DB Cost House per person 1,011 3,235 €1,801,609 €1,782 €557 369 1,181 €751,258 €2,036 €636 255 816 €896,562 €3,516 €1,099 180 576 €574,154 €3,190 €997 1,815 5,808 233 €4,023,583 Clare DBO Scheme Names Lissycasey Killone Toonagh/Dysart Kilmaley/Inagh No. of Houses Totals Monaghan DBO Scheme Names Aughnashavley Barraghy Churchill/Oram Corduff Donaghmoyne Doohamlet Drumgoole Inniskeen Killanny Newbliss Smithborough Stranooden Truagh Tydavnet Total Capital Capital Cost DB Cost per House 772 €1,930,655 €2,501 185 €1,058,030 €5,719 328 €1,732,267 €5,281 1,555 €1,696,265 €1,091 2,840 €6,417,217 Population served Houses 1300 No Data No Data 900 1100 No Data 700 900 650 No Data 1400 434 No Data 300 No Data 2600 No Data 1384 2040 Cost per DB Cost House 414 €628,172 €1,517 €83,200 286 €556,693 €1,946 314 €736,224 €2,345 800 €835,489 €1,044 220 €670,296 €3,047 257 €722,211 €2,810 €581,497 620 €739,447 €1,193 €548,573 €43,136 €51,033 395 €872,833 €2,210 685 €777,423 €1,135 3,991 Total €7,846,228 NW Sligo DBO Scheme No. of Names Houses Ballintrillick Beltra Benbulben Castletown Drum East Keelogyboy Total DB DB Cost per Cost House 98 €294,628 €3,006 80 €360,351 €4,504 66 €273,346 €4,142 58 €264,402 €4,559 260 €360,041 €1,385 106 €272,961 €2,575 Totals 668 €1,825,729 234 East Sligo DBO Scheme No. of Names Houses Geevagh/Highwood Keash Culfadda Corrick Castlebaldwin Totals Mayo Bundle No. 1 Ballycroy Ballyglass/Carnacon Belderrig Bohola Brackloon/Spaddagh Drummin Glencorrib Glenhest Killeen Kilmeena Kilmovee Laghta Lough Mask Creevagh Fahy Drumindoo Total DB Capital Cost Capital Cost per House 501 €849,192 €1,695 140 €467,787 €3,341 194 €205,634 €1,060 126 €383,735 €3,046 330 €710,274 €2,152 1,291 Population 828 1,221 150 2,145 457 148 1,025 250 646 1,242 2,230 301 1,049 2,125 Total Galway DBO No. 1 Schemes Ardrahan Ballyglass/Fiddane Brierfield Caherlistrane Cleggan/Claddaghduff Cloonatleva Cloonluane Inis Meain Kiltevna Toberowen Lissybroder Lettergesh Lowville Milltown New Inn Rinn Killeeneen Totals €2,616,622 Houses DB Cost 325 366 55 574 150 46 337 146 208 320 523 98 325 652 €750,404 €731,109 €105,132 €243,201 €628,843 €475,381 €516,317 €481,465 €552,261 €668,784 €803,221 €513,039 €675,623 €1,110,293 4,125 €8,255,073 Cost per House €2,309 €1,998 €1,911 €424 €4,192 €10,334 €1,532 €3,298 €2,655 €2,090 €1,536 €5,235 €2,079 €1,703 Cost per person €906 €599 €701 €113 €1,376 €3,212 €504 €1,926 €855 €538 €360 €1,704 €644 €522 Population DB Cost DB Cost per No of Houses Served Total D&B Cost per House person 157 447 €398,011 €2,535 €890 98 313 €369,131 €3,767 €1,179 64 223 €370,675 €5,792 €1,662 867 3200 €1,016,863 €1,173 €318 240 €1,447,225 €6,030 76 280 €396,758 €5,220 €1,417 150 495 €366,968 €2,446 €741 117 200 €343,726 €2,938 €1,719 83 250 €128,771 €1,551 €515 192 100 51 350 317 91 2,953 578 313 145 1541 1049 269 5,120 235 €297,879 €371,838 €334,424 €1,133,774 €500,639 €367,823 €7,844,505 €1,551 €3,718 €6,557 €3,239 €1,579 €4,042 €515 €1,188 €2,306 €736 €477 €1,367 Glinsk Creggs DBO (Galway) Glinsk Creggs GWS Population DB Cost DB Cost per No of Houses Served Total D&B Cost per House person 320 1,000 €977,130 €3,054 €977 Limerick DBO Scheme Names Houses Baggottstown Ballinvreena Ballybricken Ballyduff Ballyorgan Bulgaden Caherline/Newtown Cappagh Carnane Coshma/Killeen Croagh/Farradonnelly Glenroe Glenstal Granagh Griston Kileedy Kilfinny Lough Gur Total Total DB Costs Cost per house 45 €135,540 €3,012 67 €178,301 €2,661 187 €352,088 €1,883 26 €153,863 €5,918 35 €184,378 €5,268 103 €310,591 €3,015 212 €120,974 €571 175 €350,351 €2,002 329 €238,755 €726 95 €217,098 €2,285 36 €198,017 €5,500 32 €170,594 €5,331 90 €171,484 €1,905 140 €333,852 €2,385 32 €173,729 €5,429 199 €721,471 €3,625 209 €180,105 €862 501 €603,065 €1,204 2,513 4,794,256 Source: DBO Client Representatives 236 Appendix 8 Ryan Hanley Submission re. Leakage Control – 14th March 2007 Dear Frank, I refer to our phone discussion of last week during which we discussed the evolution, during Bundles no 1 in Mayo and Galway, of our approach to the necessary control of Unaccounted for Water and the interrelationship in achievement of this goal between critical mains identification based primarily on burst frequency and their early replacement during the procurement of the DBO plant in conjunction with the provision of water conservation infrastructure i.e. district meters, PRVs, valves and consumer meters. The realization of such critical mains replacement and water conservation infrastructure as a precursor to their subsequent use in the conduct of Leakage Control surveys has proved vital to the arming of GWS committees with the tools to permit them control their water usage. Active leakage control involving implementation of the findings of the Leakage Control Survey has allowed GWS to control their O&M costs from the start of the O&M period and in some cases, where existing daily demand outstripped 2025 Design daily demand + 25% UFW, permits the DBO Contractor to commission the DBO Plant and to supply treated water without the use of process bypasses carrying untreated or partially treated fractions to supply to take over the O & M of the plants which he otherwise could not. I prepared a Table setting out the history of UFW management since the original Preliminary Report Water Audit which is attached for a selection of schemes in Mayo and Galway Bundles Nos 1. This table in conjunction with the Bundle Leakage Control Strategies sent to you previously and the selection of attached site specific Leakage Control Survey Reports (for Ardrahan and Rinn Killineenen GWS in Galway) sets out the methodology of this approach and the level of detail emanating from these surveys to permit GWS to address the problem. The attached Table of Leakage Survey findings and the appended comments will also give you a flavour for the range between the wonderful success of committees who have been and continue to be active in the implementation of the Leakage Survey findings compared with the failure of some GWS to manage UFW where apathy and inactivity prevails. The effect of such inactivity on the timely completion of the DB phase of the DBO contract can also be seen. In addition the Table seeks to show that there is a large cost in all instances, associated with the application of tendered O&M variable charges by the DBO operator. The range of cost that will be incurred by individual GWS if their inactivity continues to result in a failure to manage UFW is also set out. Such high costs I predict will yet spurn the inactive into active demand management. You also expressed concern regarding costs incurred on network improvement works associated with these GWS and the optimum timing of such upgrade works. In evolving our approach to the second bundles in Mayo in Galway, which attempts to learn from our experiences in the first bundles, the following is the sequence of works which we believe will best facilitate the goal of necessary UFW control to permit construction of treatment processes sized at 2025 demand + 25% while also accommodating the ongoing phasing of network upgrade works to accommodate within existing networks the growth in daily water demands to 2025. 237 1) 2) 3) 4) 5) identification of critical mains replacement based on high burst frequency or grossly inadequate hydraulic capacity which limit quality of supply Inclusion of such critical mains for each bundle scheme into an early Advance Works Scheme(s) with necessary metering and water conservation infrastructure, to be procured and executed during the procurement, design and Part 8 planning phases of the main DBO Contract. In the case of the second Mayo and Galway bundles, the scoping, procurement and execution of separate advance works contracts for the necessary pipework interconnection of amalgamating schemes where the Bundle Rationalisation Report shows that a shared DBO treatment plant offers better value to the exchequer than discrete scheme plants Following the phased realistion of works on schemes provided with critical mains replacement and water conservation infrastructure, as in 2) above, undertake Leakage Control Surveys on each scheme to determine the factor of overall daily demand attributable to leakage in the GWS distribution network compared to the quantity wasted daily by consumers on their side of each boundary box. This survey will serve two purposes namely the identification of remaining network sections with excessive leakage together with the names and location of consumers which are excessively wasting water the on site hands on training of GWS personnel in the active leakage management The ongoing achievement of the leakage targets by GWS, as evident in some of the Bundle 1 Leakage surveys, in addition to helping management of daily demand below the design demand, will free up hydraulic capacity in the existing distribution pipework previously suffering a reduction in service level consequent from excessive headlosses incurred by the conveyance of leaking and wasted water. It is recommended where and when the leakage surveys identifies further critical mains necessary for GWS to control water usage or improve levels of service without the use of excessive pressurization of mains, a further network rehabilitation contract including these critical mains should be scoped. The design and construction of such rehabilitation works should be undertaken only on the basis of full knowledge of the condition and performance of the existing network and with a view to the future requirements for upgrading necessary to distribute the 2025 daily demand + 25%. It is recommended that such rehabilitation works should be sized using a hydraulic model distributing above future design daily demands Using this approach would ensure that decisions regarding the sequencing of works would be made based on sound engineering reasons and designed to achieve the goal of UFW Control thereby permitting the DBO process to progress without impediment while at the same time claiming back available hydraulic capacities in existing distribution networks. Having reduced UFW towards target levels, decisions regarding the replacement of critical mains for leakage or hydraulic reasons could be sensibly progressed based on the use of hydraulic models which would properly size the pipes for the particular level of UFW and the condition of mains pertinent to each network. It should not be forgotten that existing networks were often designed and installed 20-30 years ago to accommodate daily demands that have already been grossly exceeded notwithstanding their inability to distribute the larger future 2025 daily demand + 25% I hope you will find the foregoing useful to you in the finalization of your report. Please do not hesitate to contact me if you need anything further. MICHAEL JOYCE Director 238 Appendix 9 Membership of Departmental Rural Water Review Steering Committee Mr. Terry Allen – Principal Officer (Chairperson) Mr. Carthage Cusack – Assistant Principal Mr. John Fitzgerald – Engineering Inspector Mr. Frank Gallagher – Assistant Principal (Lead Reviewer) 239 Bibliography Coombs and Jenkins, “Public Sector Financial Management”, Thomson Learning, 2002 Daly, Donal and Deakin, Jenny, “Protection of Public Groundwater Sources”, Geological Survey of Ireland, 1996 Daly, Donal, “Practical Approaches to preventing pollution of wells”, Geological Survey of Ireland, 2000 Daly, Mary E , “The Buffer State: The Historical Roots of the Department of the Environment”, Institute of Public Administration, 1997 Department of the Taoiseach, “Regulatory Impact Assessment Guidelines”, 2005 Department of Finance, “Department of the Environment: Review of the Group Water Schemes Programme” May 1989 Department of Finance, “National Development Plan 2000-2006”, 2000 Department of Finance, “Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector”, February 2005 Department of the Environment, Heritage and Local Government, “Explanatory Memorandum - Subsidy towards the operational costs of a group water scheme” 2002 (Revised) Department of the Environment, Heritage and Local Government, “Guidance Document for the Procurement of Small Water Services, Part C”, 2004 (Revised) Department of the Environment and Local Government, “An Expenditure Review of Exchequer Financed Water and Sewerage Schemes” December 2002 Department of the Environment, Heritage and Local Government, “Statement of Strategy – 2005-2007”, 2005 Department of the Environment, Heritage and Local Government, “Sustainable Rural Housing – Guidelines for Planning Authorities”, April 2005 Department of the Environment, Heritage and Local Government & Department of Agriculture and Food, “National Action Programme under the Nitrates Directive”, 28th July 2005 Department of the Environment, Heritage and Local Government, “Report to EU Commission on measures to bring Group Schemes into compliance with the Drinking Water Directive”, June 2006 240 Department of the Environment, Heritage and Local Government, “Roche Announces Record Rural Water Spending Programme”, 1st March 2007. Environmental Protection Agency, “Water Quality in Ireland – Key Indicators of the Aquatic Environment, 2006 Environmental Protection Agency, “The Quality of Drinking Water in Ireland – A Report for the Year 2005”, 2007 European Commission, “Reasoned Opinion – Infringement No. 1997/4409”, C(2007) 1111, 21st March 2007 Fitzpatrick Associates Economic Consultants, “Evaluation of Water Services Investment in the National Development Plan (NDP) and Community Support Framework (CSF) for Ireland, 2000 to 2006”, 2005 Hulsmann, Adriana, “Small Systems Large Problems – A European inventory of small water systems and associated problems” (June 2005) – http://www.weknow-waternetwork.com Linnane, Suzanne, “National Source Protection Pilot Project, Interim Report” Dundalk Institute of Technology & NRWMC, March 2007. Mulreany, Michael ed., “Economic and Financial Evaluation-Measurement, Meaning and Management ”, Institute of Public Administration 2002 National Federation of Group Water Schemes, “NFGWS Strategic Plan 2006-2008”, 2006 National Federation of Group Water Schemes, “Rural Water News” –Spring, Summer, Autumn, Winter 2006 & Spring 2007 editions National Federation of Group Water Schemes, “Rural Water Programme Submission”, April 2007. National Rural Water Monitoring Committee, “Guidance Document for the preparation of a Rural Water Strategic Plan”, June 1999 National Rural Water Monitoring Committee, “Rural Water Strategic Plan - Guidance Document for Stage 2”, May 2002 National Rural Water Monitoring Committee, “Action Plan for Rural Drinking Water Quality 2003-2006”, 2003 National Rural Water Monitoring Committee, “Towards Quality Water – A Review of the work of the NRWMC and implementation of the Action Plan 2003-2006”, 2005. 241 Ryan Hanley Engineering Consultants, “Galway DBO Bundle 2 – Leakage Control Strategy”, August 2004 Ryan Hanley Consulting Engineers, “Mayo DBO Bundle 2 – Leakage Control Strategy”, March 2005 Ryan Hanley Consulting Engineers, “Mayo DBO Bundle No. 2 – Source Rationalisation Report”, August 2005 Ryan Hanley Consulting Engineers, “Galway DBO Bundle No. 2 – Source Rationalisation Report”, February 2006. Ryan Hanley Consulting Engineers, “Ardrahan Leakage Control Study”, 2006 Ryan Hanley Consulting Engineers “Submission re. Leakage Control and Network Upgrades”, 14th March 2007. Scottish Executive, “Private Water Supplies -Technical Manual”http://www.privatewatersupplies.gov.uk/ , 2006 Departmental Circulars L1/97 – Devolution of responsibility to local authorities for group water and sewerage schemes and small public water and sewerage schemes L7/97 - Water Distribution Network Management and Leakage Control L4/98 – Rural Water Programme L16/2002 – Water Pricing Framework SP5/03 – Groundwater Protection and the Planning System L4/04 – Part 8 Planning for Group Water Scheme DBO contracts L11/04 – Grants for the Installation of Water Treatment and Disinfection Equipment in Privately Sourced Group Water Schemes L09/06 – Value for Money Review of Action Plan for Rural Water Quality 2003-‘06 WSP 5/07 – European Communities (Drinking Water) Regulations 2007 (S.I. No. 106 of 2007) 242 EPA Circulars DW 01/06 [11th May 2006] – Re. European Communities (Drinking Water) Regulations, 2000: A Handbook on Implementation for Sanitary Authorities: Additional Guidance on Monitoring of Small Supplies North Tipperary County Council Guidance Notes on the Application of the Water Services Charging Methodology Template – March 2006 (www.wsntg.ie ) Relevant Websites Department of the Environment, Heritage and Local Government and links to Local Authority Websites - www.environ.ie Environmental Protection Agency – www.epa.ie European Commission – www.europa.eu European Court of Justice (ECJ) fines (http://europa.eu/rapid/pressReleasesAction.do?reference=MEMO/05/482&format=HTML&a ged=0&language=EN&guiLanguage=fr) Irish Legislation (primary and secondary) – www.irishstatutebook.ie Irish Draft Legislation – www.oireachtas.ie National Federation of Group Water Schemes – www.nfgws.ie Scottish Executive-http://www.scotland.gov.uk/Topics/Environment/Water/pws/pws1 Scottish Executive - http://www.privatewatersupplies.gov.uk/ Water Services National Training Group - www.wsntg.ie Web-based European Knowledge Network on Water –http://www.weknowwaternetwork.com 243