INDIVIDUAL PROJECT IMPLEMENTATION REPORT CONSOLIDATION OF ECOSYSTEM MANAGEMENT AND BIODIVERSITY CONSERVATION OF THE BAY ISLANDS (a) Project General Information Project Name: Consolidation of Ecosystem Management and Biodiversity Conservation of the Bay Islands Project’s GEF ID Number: 1515 Country: Honduras GEF Focal Area and Operational Program: Biodiversity, (OP 2) Coastal, marine, and freshwater ecosystems. Implementing/Executing Agency: Inter-American Development Bank (IADB) Executing Agency: Project Approval Date and Date of Project Effectiveness (Implementation Start Date: The project approval date is August 25th, 2003; IADB approval date June 21st, 2004 resulting in the signature of the Non-reimbursable Operation Financed with GEF Resources Agreement No. GRT/FM8753-HO between the Republic of Honduras and IADB on June 24th, 2004. Total Eligibility date October 12, 2004. Total Project Cost. US$16,620.000.00 GEF Grant Amount: US$ 2.820 million through IADB GEF Project Preparation Grant Amount (if any): US$320,000.00 Other Executing Agency/Agencies: Ministry of Tourism of Honduras Project Partners: Bay Islands Environmental Management Program (Programa de Manejo Ambiental de las Islas de la Bahia - PMAIB), the four (4) Bay Islands Municipalities of Roatán, Jose Santos Guardiola, Utila and Guanaja; NGOs Bay Island Conservation Association (BICA), Roatan Marine Park, Fundación Guanaja, Community organizations (Patronatos, Juntas de Agua, others) and the Honduran National Tourism Chamber (CANATURH) throught its regional office in Roatan; the Mesoamerican Barrier Reef System (MBRS); Honduras Sustainable Coastal Tourism Project. (b) Objective The development objective is to consolidate the environmental management program created during the first stage, setting in place a self sustaining institutional framework that supports ecosystem management and biodiversity conservation as well as environmentally sustainable tourism in the Bay Islands of Honduras. The global objective is to strengthen the conservation of globally significant coastal and marine habitats and species under national jurisdiction, including linkages with ongoing regional programs such as the Mesoamerican Barrier Reef System (MBRS). (c) (i) Rating Project Performance and Risk Progress towards achieving project objective. Marginally Satisfactory The project has been subject to series of external factors that have affected its execution. During the past year, there has been a complete change of personnel within the PMAIB Project Coordinating Unit (UCP), which has required recruitment of new personnel and caused interruptions leading to several delays in project execution. This rotation of personnel was due to a series of causes (mainly personal) that started in 2005 and that have been complicated by the national elections and the change of government at the end of January 2006. This change of administration caused a change in personnel in all the Ministries, including the Ministry of Tourism and other governmental institutions that have to work and support the program. Three of the four municipalities have elected new mayors as well as a new Departmental Governor. These changes in key actors have required that the Project Coordinating Unit dedicate a considerable amount of effort in initiating new UCP members such as the Protected Areas Specialist and overseeing the recruitment of the Technical Manager and Communications Specialist, among others. In addition, several workshops and meetings with the new authorities had to be carried out to re-introduce the PMAIB’s goals, the functions of the Executive Commission for Sustainable Tourism (CETS) as the regional institutional arrangement for ecosystem management, and the different initiatives underway requiring a consultation and validation process. Nonetheless, as confirmed in a Bank mission conducted in June 2006 and with continued consultations, the new authorities have endorsed both the overall Program and the GEF project objectives. There is no sign that the projects original objectives are unachievable, though the time frame originally used has obviously not been met. Finally, cooperation with MBRS on key activities such as protected area management and monitoring increased in 2006, consistent with the global objective of the project. (ii) Implementation progress. Marginally Unsatisfactory The physical execution of the Project in general is low due mainly to the fact that two activities financed with GEF resources are being implemented through services contracts that have experienced delays in their procurement processes and start-up. The two consultancies are technical assistance to the system of protected areas, the sustainable tourism and environment initiative with the private sector. In terms of disbursements, the project document expected disbursements for the GEF funds for year two equal to 1,015,000.00 (40%). As of October 20th. Total disbursement for the GEF component was US$ 700,294.89 (28%) consisting mainly on expenses related to the Commissions work meetings and participatory workshops, the technical assistance to protected Areas and public outreach. Component 1: Strengthening of the Executive Commission for Sustainable Tourism and its Technical Unit Activities in this component have been oriented first at reactivating the Executive Commission for Sustainable Tourism (CETS) following the change in administration, through local meetings so that the new members comprised of the recently named municipal and other local political authorities could be introduced to the Commission’s original mission, structure and work plan. Since the change of government in late January, 2006 there have been 3 meetings of the CETS that have dealt primarily with: the revision of the national decree for the legal establishment of the Commission; the regulations contained in the General Norms for the Development of the Bay Islands that were approved and published on January 13th, 2005 and the methodology for the zoning proposals for Bay Island; and a proposal with two scenarios on the environmental fee and the priority activities for funding. Work is about to be initiated on the different implementation norms and guidelines specified in the original General Development Norms Decree, where consensus within the CETS will be critical. The most sensitive issue under consideration by the CETS is the establishment of the financial mechanism that will assure the sustainability of the program and its recurrent activities over the longterm. Towards this end, the new government has generated 2 new scenarios with the approved amounts established for cruise ship arrivals and international tourists arriving by plane (stay-over tourists). The negotiated fee for cruise ship passengers is US$ 0.50 (expected to generate an estimated US$ 220,000 in revenues in 2007 based on a conservative scenario). A US$ 10.00 fee was approved for international stayover tourists and US$5.00 for Central American tourists. The government is currently reviewing the implementation procedures in order to put the mechanism into effect. This mechanism was originally contemplated to be operational in June 2006, but is now reprogrammed to January 2007. Component 2: Investments for the Regional System of Marine and Coastal Protected Areas The procurement process for the legal delimitation and physical demarcation of boundaries of the 12 proposed areas that shall conform the Bay Islands Marine National Park is in its final stretch having concluded the technical evaluation of the offers on October 5th, 2006. This is a requirement for the promulgation of the Law for the System of Protected Areas of the Bay Islands. Another set of activities that will contribute towards the consolidation of the system of protected areas are linked to a contract with the IBERINZA/ESA Consultores and AZTI Consortia for technical assistance in protected areas. The technical assistance contract started on July 28th, 2005 for a period of 30 months until August 21st, 2008. The main focus of the Consortia’s work in 2006 has been the revision and approval by the new authorities of the legal decree proposal for the Congress’s approval, that will ratify the establishment of the regional protected areas system under the principle of an ecosystem approach that would consolidate the Bay Islands Marine National Park, with a series of different buffer and nucleus zones. In terms of institutional strengthening, the Consortia has been advising the local protected areas comanagers capacity in the revision and technical adjustment of the existing management plans and budget, as well as the establishment of the Local Protected Area Committees for the socialization and implementation process. Additionally the local co-managers are preparing the technical specification for the acquisition of equipment and materials to improve patrolling and monitoring activities. The PCU is also completing, in cooperation with the co-managers, recruitment of the technical staff for each protected area. The identification and legal agreements with the owners of the properties for the construction of the protected areas visitor’s center on the islands of Guanaja and Utila have also been made. Offers for the architectural design of the visitor centers were received on August 24th, 2006 and are currently under negotiations before awarding the consultancy for the designs. Component 3: Public Outreach, Participation and Local Destination Management During this year there has been a significant outreach to coordinate activities with the GEF financed MBRS Project Coordination Unit, particularly in designing the different resource monitoring processes in which MBRS monitoring protocols would be applied and a workshop in November, 2006 to formulate jointly a protocol for watershed monitoring. In terms of public participation, there were a series of activities the past months aimed at designing the audio y visual components for the socialization process. There have also been 2 workshops on the island of Roatan with a total of 16 participants from the local communities for the thespian arts. These have included acting instructions, plastic arts expression, script and direction and production. As part of this outreach, the Compañia de Teatro Bahia, which uses theater to raise public awareness of the importance of managing the archipelago’s coastal and marine ecosystems, was consolidated. Through the project public outreach activities, the island has also formed an Association for Recycling with an established methodology and structure to work in this area. Pilot activities have been undertaken demonstrating the benefits of local participation in recycling programs, including for example the construction of water tanks have been built from plastic bottles. VERIFIABLE INDICATORS The level of activities and financial execution of CETS is superior to the 90% of planned. CETS has a 5 years strategic action plan and annual budget in coordination with the municipalities to enforce new activities or maintain infrastructure. MEANS OF PERCENTAGE MEASUREMENT OF EXECUTION Minutes of 20% meetings 5% Strategic plandocument Legal Decree The new representatives of CETS are preparing their work plan. 50% Environmental fee established and mechanisms to collect revenues and administrative system defined. Approved by CETS. In stage of approval by Congress POA -CETS In operation the technical unit, with costs covered by the environmental fee COMMENTS 0% The environmental fee in stage of approval by Congress. Management plan for 12 protected areas established, watershed management plans on terrestrial areas and no take zone on fishing areas established and maintain with the financial resources of the environmental fee A minimum of 20 community organizations and NGOs strengthened and participating in ecotourism activities. A minimum of 80 tourism operators have adopted best environmental practices To December 2007, from a total 70 dove operators, 70% have adopted best environmental Management plan 10% Existing management plans have been reviewed with comanagers. Number of organizations 15% Number of tour operators 5% Community organizations have received assistance resulting in their legal establishment. 30 tour operators received training in best practices. Number of dive operators 5% EGMASA will be in charge of carrying VERIFIABLE INDICATORS MEANS OF PERCENTAGE MEASUREMENT OF EXECUTION practices according to guidelines generated by the project (iii) COMMENTS these activities but had just been hired. Risk. Modest 1. Delays in the legal declaration of the protected areas systems as well as the regulations due to political conflicts of interests. Risk: Modest. Consensus building is taking place through the members of the CETS. In addition, participatory workshops and local consultation process will take place for approval. 2. The capacity of all four municipalities and CETS to reach agreements on a coordinated environmental strategy. Risk: Modest. To strengthen the work of the Commission, the PCU has provided technical assistance in activating work meetings again, preparation of a common work plan and progress in establishing mechanisms to ensure environmental fee implementation. 3. The establishment of the financial mechanism that will ensure the sustainability of the environmental management program. Risk: Modest. Consensus has been built in CETS. Higher levels of the Ministries of Tourism and Finance are actively engaged in the process of implementation of the mechanism. 4. Uncertainty in projecting growth and development trends Risk: Substantial. Development decisions affecting growth rates (mainly in Roatan) are outpacing the capacity to manage growth, particularly at the municipal levels. The IDB loan is helping to strengthen the municipal administrations in all functions (financial, land use planning, environmental, among others) but this is a gradual process that will yield results in the medium-term. (d) Contributions of the project towards focal area strategic priorities and where applicable targets: Conservation of Biodiversity and marine ecosystems and its sustainable use An active decision making process is taking place within the Commission for the establishment of a sustainable agreement for environmental management. Innovative community based projects are being launched to strengthen them in environmental management activities; broad participation of children, youngster and the formal public education sector is involved in performing/theater activities as well as the creation of small-scale enterprises. For public outreach and socialization of the environmental management plan, materials for the multi media shock campaign have been produced through videos and radio. In support of community organization, a series of trainings on recycling techniques have taken place as well as a practical methodology implemented. With the help of IBERINSA/ESA /AZTI and all stakeholders preparing the work plan for supporting full participation in the protection and restoration of coastal and marine ecosystems; promoting the implementation of an environmental oversight mechanism; biodiversity related research and monitoring program, the full implementation of effective management actions and management plan. Empowerment of all stakeholders, including vulnerable groups that depend on biodiversity The program through its components is undertaking great efforts to identify, organize and strengthen stakeholders which will be part of management programs and/or activities directed to build linkages and successful experience exchanges related to facilitating sustainable fishing, tourism and protected areas management, as well as for promoting conservation and marine resources sustainable use. (e) Co –Financing Does not apply. (f) Leveraged financing: Does not apply