Office of Physical Plant Operations Division Engineering Services The Pennsylvania State University Physical Plant Building University Park, PA 16802-1118 SEQUENCE OF OPERATION HEAT EXCHANGER w/ TWO VALVES, ⅓ - ⅔ Standard control of a heat exchanger served by two steam valves in a “1/3 - 2/3” configuration. 1. Upon a call to run, the “1/3 - 2/3” steam valves will be modulated by a PID control loop to maintain the required hot water temperature setpoint. The valves will be controlled in the following manner: a. The 1/3 valve will be modulated first. b. If the output of the PID control loop exceeds 25% (adjustable) for more than 2 minutes (adjustable), the 2/3 valve will become the first valve modulated making the 1/3 valve control range switch to the 66% to 100% output range of the PID control loop. c. If the output of the PID control loop exceeds 60% (adjustable) for more than 2 minutes (adjustable), the 1/3 valve will become the first valve modulated (the 1/3 valve will be 100% open at this time) making the 2/3 valve control range switch to the 33% to 100% output range of the PID control loop (the 2/3 valve will be modulating at this time). d. The reverse sequence shall occur at the 40% (adjustable) and the 25% (adjustable) points as steam demand decreases. e. The sequence shall also reset anytime the output of the PID control loop equals zero. See Sample program below. Page 1 of 1