Calendar Year 2004 Ohio Department of Transportation District 10 Contracted Construction Projects District 10 Regional Projects District guard rail rebuilding Rebuilding of guard rail as needed throughout the district Cost: $493,410 Contractor: PDK Construction Awarded: August 2003 Scheduled completion: June 2005 District 10 polyester pavement markings Includes replacements on various routes/sections throughout the district. To be awarded: May 2004 District 10 raised pavement markers (RPM) Includes replacements on various routes/sections throughout the district. To be awarded: April 2004 District 10 fast dry pavement markings Includes the application of fast dry pavement markings on various routes/sections throughout the district. To be awarded: June 2004 District 10 herbicidal spraying Herbicidal spraying on various routes/sections in the district. Cost: $76,343 Contractor: D-C Cunningham Group Awarded: January 2004 Scheduled completion: July 2004 District 10 mowing Mowing on various routes/sections in the district. Cost: $119,178 Contractor: Tom Mayle and Sons Awarded: January 2004 Scheduled completion: October 2005 District 10 sign replacement (Gal, Hoc, Meg, Moe, Nob, Was) Replacement of signs on various routes/sections in the counties listed above. Cost: $350,396 Contractor: PDK Construction Awarded: August 2003 Scheduled completion: June 2004 Athens County Athens to Darwin major new construction - Phase 1 Relocating US 33 route and building a Super II limited access highway between TR 68 just north of Shade and the four-lane section at Darwin; includes Meigs County Cost: $33.25 million Contractor: Smith & Johnson Awarded: June 2001 Scheduled completion: September 2004 Athens to Darwin major new construction - Phase 2 Relocation of US 33 continues from Shade to Athens; includes Meigs County Cost: $39.75 million Contractor: Smith & Johnson Awarded: October 2001 Scheduled completion: September 2004 U.S. 50 – Four-lane resurfacing project Work includes approximately 10 miles and begins at the Meigs County line. Cost: $1.4 million Contractor: Shelly & Sands Awarded: November 2003 Scheduled completion: July 2004 State Route 124/681 – Culvert replacement, includes Meigs County Work begins just west of TR161 Cost: $997,454 Contractor: Smith and Johnson Construction Awarded: October 2003 Scheduled completion: June 2004 State Route 144 – Two-lane resurfacing Work includes approximately 10 miles starting at State Route 144 Cost: $758,909 Contractor: Shelly Company Awarded: July 2003 Scheduled completion: July 2004 State Route 682 – Culvert replacement Work includes the replacement of twin box culverts located .11 miles south of the W. Chauncey corporation limit. Cost: $96,101 Contractor: Parker Corporation Awarded: September 2003 Scheduled completion: June 2004 State Route 329 – Preventive maintenance, includes Morgan, Washington Counties Preventive maintenance using a polymer seal coat application; begins just north of Amesville. Cost: $357,773 Contractor: Lytle Construction, Inc. Awarded: March 2004 Scheduled completion: July 2004 Gallia County State Route 7 – Two-lane resurfacing Work to begin .26 miles south of northeast corporation line of Gallipolis. Cost: $1.1 million Contractor: Shelly Company Awarded: September 2003 Scheduled completion: June 2004 State Routes 7, 141, 160 – Culvert repair Work includes three locations on routes listed above. To be awarded: Late March 2004 State Route 218 – Bridge repair Work located .04 miles north of CR112 (Lewis Road), and sections of State Routes 554 and 775. Cost: $369,274 Contractor: Ratzlaff Construction Awarded: September 2003 Scheduled completion: July 2004 State Route 325 – Culvert replacement Work located north of Vinton. To be awarded: April 2004 Hocking County U.S. 33 – Four-lane resurfacing Work includes 4.21 miles from the Fairfield County line east Cost: $958,834 Contractor: Shelly Company Awarded: October 2003 Scheduled completion: August 2004 State Route 78 – Culvert construction, includes Washington County Culvert construction on various sections in Hocking and Washington County. Cost: $201,217 Contractor: Parker Corporation Awarded: October 2003 Scheduled completion: October 2004 Hocking Hills State Park – Bridge enhancement Add stone facade to wingwalls and head wall of State Route 374 bridge within Hocking Hills State Park. Cost: $308,099 Contractor: R.C. Construction Awarded: December 2003 Scheduled completion: June 2004 County projects Hocking County Road 118 – Bridge replacement Replacement of two-span bridge over the Hocking River. Cost: $1.1 million Contractor: Maiden and Jenkins Construction Awarded: December 2003 Scheduled completion: Determined by the county (LPA process) Meigs County U.S. 33 – Athens to Darwin major new construction - Phases 1 and 2 Refer to Athens County U.S. 33 – Pomeroy-Mason Bridge replacement Replacement of the Pomeroy-Mason Bridge with a cable-stayed structure. Cost: $45.8 million Contractor: Joint venture - C.J. Mahan Construction and National Engineering Awarded: February 2003 Scheduled completion: September 2006 State Route 124/681 – Culvert replacement Refer to Athens County State Route 338 – Two-lane resurfacing Work includes asphalt overlay, striping and berm conditioning of 7.2 miles beginning at State Route 124 To be awarded: Late March 2004 State Route 681 – Bridge repair Bridge rehabilitation located just east of TR239 (Henderson Road) To be awarded: May 2004 Meigs wetland (Rocksprings Road) Create 3.5 acres of wetland and protect an additional 50 acres of woodland and wetland as mitigation for Ravenswood Connector and Athens to Darwin projects. Cost: $995,995 Contractor: Lubarg, Inc. Awarded: April 2003 Scheduled completion: June 2004 Monroe County State Route 379 – Preventive maintenance, includes Morgan and Noble Counties Preventive maintenance using a polymer seal coat on various sections in listed counties. Cost: $332,761 Contractor: Shelly & Sands Awarded: January 2004 Scheduled completion: July 2004 Morgan County State Route 37 – Major reconstruction Two-lane reconstruction to improve geometrics located .2 miles west of State Route 78. Includes the rebuilding of two intersections, repaving and minor signal work Cost: $4.55 million Contractor: Alan Stone Company Awarded: February 2003 Scheduled completion: July 2004 State Route 60 – Two-lane resurfacing Work includes 10 miles beginning at the Washington County line Cost: $1.27 million Contractor: Shelly & Sands Awarded: February 2004 Scheduled completion: June 2004 State Routes 78 and 83 – Preventive maintenance Refer to Monroe County, State Route 379 State Routes 329 and 555 – Preventive maintenance Refer to Athens County, State Route 329 State Route 376 – Slide repair Project located .5 miles north of CR 6 (Bebout Road) To be awarded: April 2004 Noble County I-77 – Bridge repair Work located .5 miles north of the State Route 821 underpass; includes deck overlay of various Noble Co. locations. Cost: $425,399 Contractor: 5-D Construction Awarded: January 2004 Scheduled completion: August 2004 State Route 83 – Preventive maintenance Refer to Monroe County, State Route 379 State Route 83 – Bridge replacement Bridge replacement over Rannells Creek tributary located .7 miles north of CR20 (Chapel Road). To be awarded: April 2004 State Routes 260 and 340 – Two-lane resurfacing Work includes approximately 8 miles of State Routes 260 and 340. Cost: $979,280 Contractor: Shelly & Sands Awarded: January 2004 Scheduled completion: July 2004 State Route 564 – Preventive maintenance Approximately 9 miles of preventive maintenance using a polymer double seal coat beginning .05 miles west of TR490 and ending .22 miles west of State Route 145. Cost: $136,162 Contractor: Lytle Construction, Inc. Awarded: February 2004 Scheduled completion: June 2004 Vinton County Zaleski State Forest – Culvert replacement, resurfacing Work includes placing limestone on eight different roads totaling 17.66 miles, replacing 56 culverts and placing asphalt on one parking lot within Zaleski State Forest. Cost: $352,994 Contractor: Parker Corporation Awarded: January 2004 Scheduled completion: August 2004 Lake Hope State Park – New guard rail, pavement repair and berm reconstruction Work begins at State Park entrance. Cost: $38,321 Contractor: Parker Corporation Awarded: March 2004 Scheduled completion: May 2004 U.S. 50 – Culvert replacement Work located .5 miles west of CR7 Cost: 788,387 Contractor: DGM Awarded: March 2004 Scheduled completion: October 2004 State Route 160 – Bridge replacement Bridge replacement located .2 miles east of the east corporation limit of Hamden. To be awarded: May 2004 State Route 278 – Bridge repair Work located at the south corporation limit of Zaleski. To be awarded: April 2004 Washington County State Route 7 – Emergency slip repair Repair of 1.5-mile section beginning just south of Marietta Cost: To be determined Contractor: Beaver Excavating Company Awarded: January 2004 Project is approximately 75% completed. Total completion cannot be estimated at this time. State Route 7 – Preventive maintenance Four-lane resurfacing using mill and fill process beginning near TR720 and ending at the Virginia Street exit. To be awarded: April 2004 State Route 26 – Preventive maintenance Refer to Athens County, State Route 329 State Route 26 – Bridge replacement Bridge replacement over Duck Creek tributary beginning .08 miles west of intersection of CR16. To be awarded: April 2004 State Route 339 – Two-lane resurfacing Project includes approximately 14 miles beginning at the intersection of State Route 618 Cost: $2.99 million Contractor: Shelly & Sands Awarded: December 2003 Scheduled completion: July 2004 State Route 339 – Bridge repair Rehabilitation of deck on steel beam bridge over south fork of Wolf Creek To be awarded: April 2004 District Office renovations Renovations to headquarters include window replacement To be awarded: April 2004 County projects County Road 9 – Minor rehabilitation Base pavement reconstruction and guard rail project Schedule will be determined by Washington County Engineer. City projects Marietta bikeway Construction of 10-ft wide shared use path in the city of Marietta. To be awarded: April 2004 Marietta brick paving Work starts at Sixth and Cutler Streets To be awarded: April 2004 U.S. 50 (Belpre) – Signals Work includes to installation of traffic signals at the intersection of Braun Road To be awarded: April 2004 Civitan Park enhancement (Belpre) Installation of lighting fixtures, benches, trash receptacles, paving of parking area; also expansion of walkway facilities To be awarded: May 2004