CERN LHC Project Document No. CH-1211 Geneva 23 Switzerland LHC-VC8-TP-0001 CERN Div./Group or Supplier/Contractor Document No. AT-VAC the EDMS Document No. Large Hadron Collider 842128 project Date: 2007-05-10 Procedure COMMISSIONING OF THE LHCB BEAMPIPE EXPERIMENTAL SECTOR IP8.X Abstract This document describes the procedure to be followed for the first commissioning of the experimental sector of the LHCb beampipe VACSEC.IP8.X, as planned to be performed in May and June 2007. It takes into account the status of the installation at the moment of the commissioning. Prepared by : Délio Ramos AT/VAC Delio.Ramos@cern.ch Checked by : LHC Project Document No. LHC-VC8-TP-0001 Page 2 of 8 History of Changes Rev. No. Date Pages Description of Changes LHC Project Document No. LHC-VC8-TP-0001 Page 3 of 8 Table of Contents 1. INTRODUCTION .......................................................................................4 2. LIST OF DOCUMENTS ...............................................................................4 3. 3.1 3.2 PROCEDURE.............................................................................................5 PREPARATION PHASE ............................................................................... 5 NEG ACTIVATION PHASE .......................................................................... 6 4. REFERENCES............................................................................................8 LHC Project Document No. LHC-VC8-TP-0001 Page 4 of 8 1. INTRODUCTION The commissioning of the LHCb beampipe VACSEC.IP8.X is planned for May and June 2007. This corresponds to the pump-down, leak detection, instrumentation testing, surface conditioning and pure neon injection, leaving the beam vacuum chamber between VVGSF.33.1L8.X and VVGST.198.1R8.X with NEG activated surfaces, therefore only requiring the neon pump-down to be ready for beam. Although the LHCb beampipe is composed of all vacuum equipment in-between Q1 magnets, the installation of sectors VACSEC.A1L8.X and VACSEC.A1R8.X is not complete. However, the most important sector traversing the LHCb detector (VACSEC.IP8.X) is ready for commissioning, which must be done as soon as possible in order to avoid conflict resources with the remaining experimental beampipes, as well as with the detectors installation. As the VAX assemblies are not installed, an RGA and a penning gauge will be temporarily mounted, to allow the pressure reading at the downstream end of the beampipe. These will be replaced by blank flanges and mounted on the VAX assembly after this commissioning. The remaining sectors will be commissioned later with mobile pumping groups. The purpose of the pure neon injection is to allow the venting of the beampipe to atmospheric pressure while preventing the saturation of the NEG coating. However, the leaks on the VELO RF-boxes of the order of 2.6x10-5 mbar, measured with 1.5 mbar differential pressure of helium, will allow diffusion of air into the beampipe when the VELO detector volume will be open to air for the detectors installation. This may imply another bakeout after detector installation [1] . Scaffolding and handling are provided by LHCb. 2. LIST OF DOCUMENTS The following list of documents form an integral part of this procedure: Description Location 2.A Planning for the LHCb beampipe commissioning - Sector IP8.X EDMS Id: 837026 2.B Instrumentation layout of the LHCb beam vacuum system – temporary configuration for the first commissioning of the VACSEC.IP8.X EDMS Id: 842124 2.C Instrumentation layout of the LHCb beam vacuum system EDMS Id: 842125 2.D Layout of the bakeout heaters and control channel programs for the first commissioning of LHCb beampipe VACSEC.IP8.X EDMS Id: 842122 2.E Services in the LHCb cavern for the LHCb beampipe commissioning EDMS Id: 842120 2.F LSS Vacuum layouts LHC Functional Database 2.G Procedure for the air pumpdown of the LHC experimental beam vacuum chambers EDMS Id: 842115 2.F LHCb beampipe drawings CDD drawing numbers at: http://cern.ch/delio.ramos/LHCb.htm LHC Project Document No. LHC-VC8-TP-0001 Page 5 of 8 3. PROCEDURE 3.1 PREPARATION PHASE Status before start: Beampipe vented with N2. Sector valves VVGSF.33.1L8.X and VVGST.198.1R8.X closed. The 3 volumes separated by the sector valves were vented independently, eventually they are not at the same pressure. Hence, before operating the sector valves, the pressures must be equilibrated. 1 Step description Ref. doc. Equipment required Open the volume on the downstream side of VVGST.198.1R8.X to air and install temporarily the penning VGPB.219.1R8.X and RGA VGAB.219.1R8.X on the bellows module VMABJ. The RGA is assembled on a CF63 elbow. 2.B -CF63 elbow -VGPB -VGAB -CF63 blank flange with VAT CF16 or HOKE valve Install a CF63 blank flange with VAT CF16 or HOKE valve on the downstream side of MBXWS magnet (VVFMB.214.1R8.X). 2 Connect the gauges and ion pump cables. 2.B 3 Using the VELO vacuum system, pump 50 mbar and then inject N2 to equilibrate the pressure in the VACSEC.IP8.X to atmosphere. 2.B -NEG sample -Tube with CF40 flange Mount the NEG sample on the VC8G beampipe. -VGAB Mount RGA (VGAB) on the VELO. -Transition for VELO RGA Open VVFMB.214.1R8.X to expose the volume to atmosphere. Open the sector valve VVGST.198.1R8.X. Close VVFMB.214.1R8.X. Open VVFMB.72.1L8.X to expose the volume to atmosphere. Open the sector valve VVGSF.33.1L8.X. Close VVFMB.72.1L8.X 4 Pump-down the beampipe with both sector valves open. While pumping, regulate the restriction valve MV305 on the detector vacuum pumping line. Test instrumentation. 2.B 5 Leak detection of previously installed equipment, with the leak detector connected to the VELO. -Leak detector 6 Close VVGST.198.1R8.X. -Leak detector Vent the MBXWS volume trough VVFMB.214.1R8.X and inject He inside to leak check the sector valve seat. Close VVFMB.214.1R8.X. 7 Vent the VACSEC.IP8.X with Ne using the injection table and line. While injecting, regulate the restriction valve MV304 on the 2.B LHC Project Document No. LHC-VC8-TP-0001 Page 6 of 8 detector vacuum venting line. 8 Open VVFMB.214.1R8.X to expose the volume to atmosphere. 2.B Open VVGST.198.1R8.X. 9 Preparation phase finished. Status: VVFMB.72.1L8.X closed VVGSF.33.1L8.X closed VVGST.198.1R8.X open VVFMB.214.1R8.X closed 3.2 NEG ACTIVATION PHASE Step description Ref. doc. Equipment 1 Cabling of bakeout racks for the gas injection table and line. 2.D Bakeout racks E and B (24 channels each) 2 Programming and testing of bakeout racks for the gas injection table and line. 2.D 3 Commissioning/NEG activation of the injection table and injection line. Doc? 4 Assembly of bakeout equipment onto the beampipe and VELO. 2.D All bakeout equipment provided by AT-VAC except the VELO vacuum vessel walls which have a permanent heating and a dedicated controller integrated in the VELO mobile control rack. However, the VELO flanges were not accounted by NIKHEF, they will be heated using AT-VAC’s collars and power control channels. RICH1 side panels are open and mirrors removed to provide access to the beampipe. Removable jackets. TT, OT and IT, are open. “Free” access to the beampipe from the RICH1 exit window up to RICH2. Platform to reach the beampipe level needed in the OT/IT region. Removable jackets. RICH2 cannot be opened. A removable jacket is inserted from the OT/IT side. A temperature sensor on the detector wall, to be installed by RICH2, will provide an interlock with the power controler. Power is cut-off if the RICH2 temperature reaches 70ºC [2] . RICH2 provides the cable and connector up to the power controler. To prevent the detector overheating, compressed air is injected between the beampipe and the RICH2 tube to extract the dissipated power by convection. Compressed air line provided by LHCb, injector and flow meter provided Bakeout jackets, heating tapes, insulating blankets, heating collars. LHC Project Document No. LHC-VC8-TP-0001 Page 7 of 8 by AT-VAC. M1, SPD/PS, ECAL and HCAL open. Scaffolding to reach the beampipe level. Removable jackets. MF does not open. Permanent heating system with band heaters and Microtherm insulation. 1 thermocouple + 1 redundancy per heating circuit. Connectors at the beampipe level on both upstream and downstream sides. Temporary cables needed to reach the controlers in the cavern floor and the RB86 tunel. All flanges in the beam volume are actively heated. 5 Cabling of bakeout racks for the beampipe and VELO. 2.D Bakeout racks A, B and D (24 channels each) Bakeout Rack C (8 channels) 6 Programming and testing of bakeout racks for the beampipe and VELO. 2.D Maximum temperatures: • VELO vessel and aluminium window – 150ºC max (Helicoflex seal manufacturer specifies maximum 120ºC) • Beryllium – 220ºC (max 250ºC) • Aluminium flanges – 220ºC (max 230ºC) • Aluminium bellows – 200ºC max • Bimetallic transition flange stainless steel/aluminium – 220ºC (230ºC max) • Stainless steel, tubes, bellows, flanges – 220ºC (max. 300ºC) • The remaining copper chambers, valves, instrumentation, modules, pumps, etc. Following “standard LSS” parameters. 7 Install dial gages on the beampipe flanges and supports to measure the displacements due to pressure and temperature. 8 Pump-down the beampipe through the VELO vacuum system. 2.G 9 Close VVGSF.33.1L8.X 2.B 10 Bakeout and NEG activation 2.D Doc? 11 Ne injection Doc? 12 Close VVGST.198.1R8.X 2.B 13 Activation phase finished. Status: 2.B VVFMB.72.1L8.X closed VVGSF.33.1L8.X closed VVGST.198.8.X closed VVFMB.214.1R8.X closed LHC Project Document No. LHC-VC8-TP-0001 Page 8 of 8 VACSEC.IP8.X at atmospheric pressure of Ne, balancing to atmosphere VELO detector volume at atmospheric pressure of Ne, all valves closed. Volume upstream of VVSGF.33.1L8.X under vacuum. Volume downstream of VVGST.198.1R8.X at atmospheric pressure of Ne Ne injection line and injection table at 1000 mbar of Ne, ready to inject, if necessary to equilibrate pressure difference between the beampipe and atmosphere. 14 Demount temporary bakeout equipment 4. REFERENCES [1] Minutes of meeting on “LHCb Rescue commissioning procedure accounting for the leaks in the VELO rf-boxes”, 14-Mar-2007. [2] D. Ramos, H. Kos, “Test to determine the temperature of the RICH2 detector tube during bakeout of the LHCb beampipe”, May 2007, EDMS Id: 841120