Station: NTPC- Simhadri BHEL Ref No.PS-DC-186-500-156 NTPC Ref No. SIM/0/TS/4/156 Sheet 1 of 7 Plant area: OFF SITE PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA) SLNO LIST OF CONTENTS 1.0 PLANT DETAILS 2.0 OBJECTIVE 3.0 PROPOSAL 4.0 SERVICES REQUIRED 5.0 SAFETY PERECAUTIONS 6.0 EMERGENCY PROCEDURE 7.0 STATE OF THE PLANT 8.0 METHOD 9.0 COMPLETION CRITERIA 10.0 APPENDICES a) DRAWINGS Station: NTPC- Simhadri BHEL Ref No.PS-DC-186-500-156 NTPC Ref No. SIM/0/TS/4/156 Sheet 2 of 7 Plant area: OFF SITE PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA) SL.NO STATUS 1.0 PLANT DETAILS: Compressed Air System for the plant consists of 1) service Air System and 2) Instrument Air System. The pipe lines are mainly of galvanized and of ERW type. Service air and Instrument air lines emanating from compressor House connects all the points in the Power Plant where the requirement of this two type of air is envisaged. The normal working pressure of these system is 7.5 KSC. The various locations to which Service Air and Instrument air Connected are given below. SERVICE AIR SYSTEM: (OFF SITE AREA) - CPU Regeneration Bldg CW Pump House Chlorination Plant Water Treatment plant Fire Water P.H Canteen Permanent Store. Auxiliary Boiler F.O.P.H Coal Settling Pond CMB (Central monitoring Basin) Signatures NTPC BHEL Station: NTPC- Simhadri BHEL Ref No.PS-DC-186-500-156 NTPC Ref No. SIM/0/TS/4/156 Sheet 3 of 7 Plant area: OFF SITE PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA) SL.NO STATUS - Sewage Treatment plant. - Ash Water & slurry PH - Workshop Bldg - Gate House - Administrative Bldg - Service Bldg. - Spare points BOILER AREA - Feeders Mills FTP (Furnace Temperature Probe) Atomising air APH (Primary & Secondary APH – Air Motor, Fire Sensing Device, APHSB) Accoustic Pyrometer HEA Ignitors Spare points TG AREA - Bus Duct Pressurisation Spare Points INSTRUMENT AIR SYSTEM: OFF SITE AREA - CPU Regeneration Bldg CW Pump House DM Plant Air Receiver ( 2Cu.m) Chlorination plant Water Treatment plant Auxiliary Blr. Signatures NTPC BHEL Station: NTPC- Simhadri BHEL Ref No.PS-DC-186-500-156 NTPC Ref No. SIM/0/TS/4/156 Sheet 4 of 7 Plant area: OFF SITE PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA) SL.NO STATUS - Hydrogen Generation plant. - F.O.P.H - Air Receiver (Unit I/Unit II) (10 Cu.m) - Spare points BOILER AREA - FSSS System SADC System Milling system All pneumalic control valves / Drain valves. All control instruments Control Dampers Spare points TURBINE AREA 2.0 All control valves Generator purging Spare points OBJECTIVE: The objective of the testing schedule is to ensure cleanliness of the entire SA and IA system and make it available progressively for unit commissioning. 3.0 PROPOSAL: The objective is achieved by the following proposals. 3.1 Pressure Test of the air system at 7.5 KSC 3.2 Cleaning the piping system by blowing compressed air (5 minutes duration for main headers & 3 minutes for each tap-offs) maintaining at least 5 KSC at outlet point of compressor House / Air receivers. Blowing repeated till clear air observed at the blowing end. Signatures NTPC BHEL Station: NTPC- Simhadri BHEL Ref No.PS-DC-186-500-156 NTPC Ref No. SIM/0/TS/4/156 Sheet 5 of 7 Plant area: OFF SITE PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA) SL.NO STATUS 3.3 Alternatively, cleaning the piping system (only the main header) by card board bursting (Two times) method and the individual tap-off by contions blowing by air (3 minutes duration for each circuit) (Card board bursting at 3-4 KSC) 4.0 SERVICES REQUIRED: 4.1 Availability compressors 4.2 Availability of ECW 4.3 Availability of Electric supply for compressors. 4.4 Availability of work force for attending leakage / air blowing. 4.5 Availability of required communication, lighting and approaches at location where air blowing planned. 5.0 SAFETY PRECAUTIONS: 5.1 Ensure platforms / approaches wherever required for air blowing. 5.2 The agencies working in the blowing are to be informed about air blowing 5.3 Clear communication to be made available among the test team in controlling the activities of air blowing / Card board bursting. 5.4 First aid kits to be made available near the test area 5.5 Safety appliances such as helmet, gloves, ear mufflers are to be made available to the test team / work force. Signatures NTPC BHEL Station: NTPC- Simhadri BHEL Ref No.PS-DC-186-500-156 NTPC Ref No. SIM/0/TS/4/156 Sheet 6 of 7 Plant area: OFF SITE PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA) SL.NO STATUS 6.0 EMERGENCY PRECAUTIONS: 6.1 The test team should be generally aware of the entire lay-out / part lay-out where blowing done, in order to react to any emergency notified to them. 6.2 The test team should be aware of steps to be taken in case of any injury to personnel / damage to any section of air line or any machinery connected to the air system as a result of the proposed activity. 7.0 STATE OF THE PLANT: 7.1 Piping scheme of both SA and IA are erected and all the supports are provided as per recommended drawing. 7.2 Drain lines with valves / auto drain traps, wherever envisaged in IA scheme are provided. 7.3 Suitable openings are left open in the main air headers for air blowing requirements. 7.4 Identifications are made at strategic locations to indicate the layout of SA and IA lines. 8.0 METHOD: 8.1 Pressure Test 8.2 By running the service air compressor, slowly fill up the SA/IA system and raise the air pressure to 7.5 KSC. 8.3 Identify and attend to all leaking locations and repeat the test. Signatures NTPC BHEL Station: NTPC- Simhadri BHEL Ref No.PS-DC-186-500-156 NTPC Ref No. SIM/0/TS/4/156 Sheet 7 of 7 Plant area: OFF SITE PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA) SL.NO STATUS 8.4 The pressure test repeated till all leakages are attended. 8.5 Cleaning of Pipe Lines 8.6 After ensuring that all the tap-offs from the main header are closed and suitable opening kept open in the main header charge the SA/IA main headers slowly and air blow for about 5 minutes. 8.7 After ensuring closing of openings provided as above in the main header, commence air blowing of individual tap-off for about 3 minutes. 8.8 Air blowing given is Sec. 8.6 & 8.7 to be repeated, if required, till clean air visually observed at the outlet of blowing point. 8.9 After completing air blowing, both SA/IA system normalized / released for connecting to the end usage point. 9.0 COMPLETION CRITERIA 9.1 Cleanliness of SA/IA piping is achieved by carrying out the proposals given in section 3.0. 10.0 APPENDICES: a) Drawing referred i) PE-DG-186-555-0005 ii) PE-DG-186-555-0006 iii) PC-DG-186-555-0004 iv) PC-DG-186-555-0006 Signatures NTPC BHEL PROCEDURE FOR COMMISSIONING OF COMPRESSED AIR SYSTEM (SA/IA)