weighted comparison matrix

advertisement

CSCC40

Analysis and Design of Information Systems

weighted comparison matrix

When comparing options, you can use a weighted comparison matrix .

This purpose of developing this matrix is to have a record of the decisions leading to a choice of the best option. This matrix must be "signed off" by the users/clients and the project team.

Note that the criteria will never include a "must have" features, because any option that does not have a

"must have" feature will not even be considered. For example, a library system must have the ability to calculate and track due dates, and if it does not permit this, the option is rejected. However you can include in the criteria the effectiveness or specific features of the due date functionality. For example, a criterion might be "provides automatic notification to lender of upcoming due date".

This matrix is accompanied by a list of the "must have" features that all options have.

For the example library system, an incomplete matrix is given below...

Option A = develop entire new system to meet all or most of the functionality

Option B = buy and install LibraryPlus system (software package sold to similar libraries)

Option C = enhance current system (modifications in stages/phases)

The weight column indicates the relative importance of the criteria. For example, the cost (criterion A) is more than twice as important as the support of RFID technology (criterion D).

The rating column indicates how well the option complies with the criterion. See the explanations below.

The calc . column is the weight times the rating.

The total indicates how well the option complies with the criteria. In this example, option B is the best and option C is the worst.

Note that the criteria, weights and ratings are determined by discussion with users. Typically criteria are added or removed and weights and ratings are changed when new information comes to light or decision are made. This matrix evolves. evaluation criteria weight

Option A rating calc.

Option B rating calc.

Option C rating calc.

A cost to install <$80,000

B delivery date Jan 2006

C interface to affiliated libraries

D supports RFID technology

E conversion interruption < 16 hrs etc.

8

5

6

3

5

6

5

10

8

6

48

25

60

24

30

187

10

10

5

3

8

80

50

30

9

40

209

8

8

3

8

6

64

40

18

24

30

176

1 / 2

CSCC40

Analysis and Design of Information Systems

The above matrix is usually followed by explanations of the ratings.

A. cost to install < $80,000

weighted comparison matrix

Option A full features $85,000, may be able to work without some for a year or two

Option B $50,000 which includes some customization

Option C $ 60,000 buys critical enhancements, could rise to $75,000 for full features

B. delivery date Jan 2006

Option A optimistic estimate is January 2006, but pessimistic is March 2006

Option B can be installed by November 2005

Option C can be altered in stages, with first increased functionality by October, but last functionality not until March 2006

C. interface to affiliated libraries

Option A full interface, easy to use

Option B need an intermediate stage, response time will be slow

Option C need to alter current database architecture to accommodate the functionality

D. supports RFID technology

Option A can be accomplished with purchased tag read/write software

Option B no available, vendor not interested in making changes

Option C same situation as option A

E. conversion interruption < 16 hrs

Option A full conversion will take about 24 hours, but can convert in stages of 4-6 hours each

Option B guaranteed by vendor, other customers agree that it can be done

Option C functionality will be implemented in stages of 4-6 hours each

2 / 2

Download