Chapter 6 Avoiding Hazard The plan should be read as a whole. The general planning policies in Chapter 2 will be applied to all planning applications, in addition to those in other relevant sections. Avoiding Hazard Avoiding Hazard Our Strategic Approach 6.1 There are two types of hazard which are relevant to land use planning. These are: Natural hazards which may threaten existing or proposed development e.g. flooding Man-made hazards e.g. mining, leading to land stability problems, previous development which has resulted in contamination, or new developments which cause pollution or noise nuisance etc. 6.2 The planning system must consider how these hazards may affect the current and future uses of land. Often detailed advice and guidance must be sought from other statutory bodies such as the Environment Agency or the Health and Safety Executive. The role of the planning system is to take these natural and man-made hazards fully into account in considering the location and design of new development, so that the need for any future mitigatory measures can be avoided and any risks to existing development, the community or the environment can be minimised. 6.3 In some cases the nature of risk from a hazard is unknown or poorly understood. In such cases the precautionary principle, one of the key principles of sustainable development, will be applied. This works on the basis that where there are significant risks of damage to the environment, the local planning authority should seek to limit risks, even where scientific knowledge is not conclusive, if the balance of costs and benefits justifies it. Brecon Beacons National Park Authority109 Authority Approved Interim Unitary Development Plan, Working Copy, March 2007 Avoiding Hazard Avoiding Hazard Our Detailed Policies Unstable Land 6.4 There is no register of unstable land in the Park and the NPA has does not have the statutory responsibility to produce such a register. However there are areas where land stability is likely to be an issue. The responsibility lies with the developer to ensure and effectively prove that the proposed development will not be affected by instability or trigger ground movements off-site. Where unstable land is suspected, the NPA will require applications to be accompanied by a stability report prepared by a geo-technical specialist, describing and analysing the issues relevant to ground instability and indicating how they would be overcome. Such a report would be required to demonstrate: whether the land is capable of supporting the loads imposed over the expected lifetime of the development; and whether the development would threaten the continuing stability of the site and its surrounds through the processes of excavation, changing drainage or groundwater regimes, changes in land use etc. Policy H1: Development on Unstable Land Proposals for development on potentially unstable land will only be permitted where it can be demonstrated that the site is stable or could be made stable and that development is unlikely to trigger any form of instability within or beyond the boundaries of the site. The applicant will be required to provide a stability report, undertaken by a suitably qualified person and agreed with the NPA, on how the factors relevant to ground instability would be overcome. Development on Land Liable to Flooding 6.5 It is important to ensure that new development is safe and not exposed unnecessarily to flooding. Development may also impair the effectiveness of the floodplain in conveying and storing water, causing an increased risk of flooding elsewhere. Flood plains should therefore be allowed to continue to function for their natural purposes and be protected from inappropriate development. The Welsh Assembly Government advice note TAN15 ‘Development and Flood Risk’ provides advice as to the areas and zones where development could be considered and where it should be resisted. TAN15 is supported by development advice maps showing the flood risk zones as follows: - Zone C2 – areas of the floodplain without significant flood defence infrastructure; - Zone C1 – areas of the floodplain that are developed and served by significant infrastructure including flood defences; - Zone B – areas known to have flooded in the past evidenced by sedimentary deposits; - Zone A considered to be at little or no risk of fluvial or tidal/coastal flooding. 6.6 Further detailed guidance on considering risks from flooding can be found in TAN15. The terms used in Policy H2 below find detailed expression in TAN15. The Environment Agency will be a key consultee in the NPA’s application of this policy. 110Brecon Beacons National Park Authority Authority Approved Interim Unitary Development Plan, Working Copy, March 2007 Avoiding Hazard Policy H2: Development and the Risk of Flooding Development, including the raising of land, will not be permitted where that development would: ia) be on land at high risk of flooding i) result in an unacceptable risk of flooding either on or off site; ii) adversely affect flood management or maintenance schemes; iii) impede flood flows or result in changes in flow regime; or iv) result in a net loss of flood-plain storage. Where, exceptionally, development is allowed on land at high risk of flooding, such exceptional circumstances will be justified where it can be demonstrated that: It needs to be located in a high risk area, or be part of a local strategy sustaining the settlement; or It is necessary to contribute to key employment objectives; The proposal is on previously developed land; and The potential consequences of flooding have been considered and found to be acceptable. and, Highly vulnerable development will not be permitted on land at high risk of flooding where that land is without significant flood risk infrastructure. Reducing the Risk of Flooding 6.7 Attempts should be made in all development proposals to reduce to a minimum the rate of run-off caused by new development. The NPA will encourage the development and use of sustainable drainage systems and of rainwater recycling in general. Sustainable drainage systems use techniques to control surface water run-off as close to its origin as possible, before it enters a watercourse. Such systems include filter strips and swales, filter drains and permeable and porous pavements, infiltration devices and basins and ponds. Policy H3: Reducing the Risk of Flooding Development will only be permitted where:(i) it can be demonstrated that there is no increased risk of flooding locally or elsewhere due to additional surface run-off or changes in flow regime; or (ii) where adequate mitigation works which are necessary to achieve such aims can be provided. Notifiable Installations 6.8 Under health and safety legislation, certain sites and pipelines are designated as "notifiable installations" by virtue of the quantities and type of hazardous substances stored or used. Consultation with the Health and Safety Executive, and other relevant organisations such as the Environment Agency, is required if further installations are proposed. The Executive has defined consultation zones around such installations, mostly gas pipelines, and requires to be consulted if development is proposed within them. It may be necessary to refuse permission for residential and some other types of development within these zones. Brecon Beacons National Park Authority111 Authority Approved Interim Unitary Development Plan, Working Copy, March 2007 Avoiding Hazard Policy H4: Notifiable Installations Development proposals for notifiable installations or proposals affecting notifiable sites will not be permitted unless the NPA is satisfied that there is no risk to public health and safety, following consultation with the Health and Safety Executive and other relevant bodies. 112Brecon Beacons National Park Authority Authority Approved Interim Unitary Development Plan, Working Copy, March 2007